Question 1
Incorrect
In an IT project, you are the project manager. You will need to manage the whole effor, start to nish. You’ll need to work with the
client to establish goals, choose the team, estimate time and cost, manage and track all of your decisions, and make sure you
keep everybody in the loop on what’s going on. This description implies a situation from a … organizational structure.
Select one:
a. weak matrix
b. project
c. strong matrix
d. balanced matrix
e. functional
Question 2
Correct
Select one:
a. determining
b. estimating
c. planning
d. controlling
e. changing
https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 1/10
7/4/2021 UTS 2020-Genap: Attempt review
Question 3
Correct
Projek membangun sebuah kafe, total anggaran yang diberikan oleh client sebesar 100 juta. direncanakan waktu pengerjaan
project selama 2 bulan dan setiap bulan mengeluarkan biaya yang sama. Pada akhir bulan ke-1 client datang untuk memeriksa
kemajuan projeknya dan ternyata pekerjaan baru selesai 40 %. Berapa BAC (Budget At Completion) projek tersebut?
Select one:
a. 100 juta
b. 50 Juta
c. 50%
d. minus 50 Juta
Question 4
Incorrect
Select one:
a. Mencari Sponsor
b. Estimasi biaya
c. Penentuan Anggaran
d. Pengendalian perubahan
Question 5
Correct
Select one:
a. Memperkirakan biaya
b. Mengontrol biaya
c. Menentukan anggaran
https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 2/10
7/4/2021 UTS 2020-Genap: Attempt review
Question 6
Correct
Select one:
a. False
b. True
Question 7
Correct
Select one:
a. Many organizations have a required minimum acceptable rate of ROI for projects.
b. Internal rate of return can be calculated by nding the discount rate that makes the NPV equal to zero.
c. ROI is calculated by substracting the project costs from the bene ts and then dividing by the costs.
Question 8
Correct
Tiga metode utama untuk menentukan nilai proyek yang diproyeksikan dari proyek, kecuali:
Select one:
a. Payback analysis
b. Return on investment
https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 3/10
7/4/2021 UTS 2020-Genap: Attempt review
Question 9
Correct
Select one:
b. Payback analysis
Question 10
Correct
Apakah mungkin untuk membuat perubahan pada scope baseline di seluruh proyek?
Select one:
b. Ya, setiap kali tim merasa bahwa sebagian dari persyaratan tersebut tidak layak untuk diterapkan
d. Ya, itu hanya dapat diubah melalui prosedur pengendalian perubahan formal dan digunakan sebagai dasar
perbandingan
Question 11
Correct
Select one:
a. Integrasi
b. Waktu
c. Biaya
d. Cakupan
https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 4/10
7/4/2021 UTS 2020-Genap: Attempt review
Question 12
Correct
Jenis hubungan ketergantungan mana yang cocok dengan pernyataan berikut "The predecessor must start before the successor
can nish"?
Select one:
a. Start-to-Finish
b. Start-to-Start
c. Finish-to-Finish
d. Finish-to-Start
Question 13
Correct
As a project manager, you create a WBS by breaking down a project work into smaller tasks hierarchically and create a tree-like
structure of project works. Your approach is the ...
Select one:
a. top-down approach
b. bottom-up approach
d. benchmarking approach
e. analogy approach
Question 14
Correct
Select one:
https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 5/10
7/4/2021 UTS 2020-Genap: Attempt review
Question 15
Correct
Select one:
c. Membuat jadwal proyek yang realistis dan menjadi dasar pengawasan berjalannya proyek
Question 16
Correct
Buffer adalah waktu tambahan untuk menyelesaikan sebuah tugas, buffer dapat ditambahkan setelah jatuh tempo proyek
Select one:
a. Salah
b. Benar
https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 6/10
7/4/2021 UTS 2020-Genap: Attempt review
Question 17
Correct
Gantt Chart
#Bagan yang menggambarkan pekerjaan Proyek.
Baik
#Semakin tinggi NPV maka semakin.
#Memberi pertimbangan, rekomendasi kebijakan dan prosedur, serta memberi wewenang manajer Fungsi PMO
proyek tertentu.
#Model yang digunakan untuk memilih proyek dengan membandingkan seberapa besar proyek Bene t Measurement Model
menguntungkan perusahaan.
Critical Path
#Lintasan kritis proyek di sebut.
Controlling Schedule
#Mengendalikan dan mengelola perubahan jadwal proyek.
Proses Penutupan
#Memberikan laporan hasil yang diperoleh dari aktivitas proyek yang sudah dilaksanakan.
deliverable
#A product produced as part of a project.
pro t margin
#The ratio of revenues to pro ts.
#Teknik untuk mengukur performansi proyek yang mengintegrasikan lingkup, waktu dan biaya Earn Value Management
proyek.
https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 7/10
7/4/2021 UTS 2020-Genap: Attempt review
Question 18
Partially correct
Time Planning
ES EF LS LF FS TS
A 0 4 0 4 0 0
B 4 7 10 13 0 0
C 4 9 4 9 0 0
D 4 10 14 18 10 8
E 9 17 9 17 0 0
F 9 11 19 21 10 10
G 17 26 17 26 0 0
H 26 33 26 33 0 0
https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 8/10
7/4/2021 UTS 2020-Genap: Attempt review
Question 19
Incorrect
_____ adalah kumpulan dari …, …, dan operasi yang diatur untuk mencapai tujuan strategis organisasi. Berikut ini yang paling
tepat untuk mengisi titik-titik di atas secara berurutan adalah … .
Select one:
Question 20
Correct
Manajer proyek bertanggung jawab terhadap banyak hal sebagai berikut, kecuali:
Select one:
Question 21
Correct
Select one:
https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 9/10
7/4/2021 UTS 2020-Genap: Attempt review
Question 22
Incorrect
Select one:
a. Kerangka politik
b. Kerangka S.D.A.
c. Kerangka struktur
d. Kerangka simbolik