MANAJEMEN PROYEK TIK IF-42-01 [SOL]


Dashboard / My courses / CII3G3-IF-42-01 / UTS / UTS 2020-Genap

Started on Wednesday, 7 April 2021, 1:30 PM

State Finished

Completed on Wednesday, 7 April 2021, 3:00 PM

Time taken 1 hour 29 mins

Question 1

Incorrect

Marked out of 2.00

In an IT project, you are the project manager. You will need to manage the whole effor, start to nish. You’ll need to work with the
client to establish goals, choose the team, estimate time and cost, manage and track all of your decisions, and make sure you
keep everybody in the loop on what’s going on. This description implies a situation from a … organizational structure.

Select one:

a. weak matrix

b. project

c. strong matrix 

d. balanced matrix

e. functional

Question 2

Correct

Marked out of 2.00

Following are main processes of project cost management, except ... .

Select one:

a. determining

b. estimating

c. planning

d. controlling

e. changing 

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 1/10
7/4/2021 UTS 2020-Genap: Attempt review

Question 3

Correct

Marked out of 2.00

Projek membangun sebuah kafe, total anggaran yang diberikan oleh client sebesar 100 juta. direncanakan waktu pengerjaan
project selama 2 bulan dan setiap bulan mengeluarkan biaya yang sama. Pada akhir bulan ke-1 client datang untuk memeriksa
kemajuan projeknya dan ternyata pekerjaan baru selesai 40 %. Berapa BAC (Budget At Completion) projek tersebut?

Select one:

a. 100 juta 

b. 50 Juta

c. 50%

d. minus 50 Juta

Question 4

Incorrect

Marked out of 2.00

Yang tidak termasuk dalam akti tas Pengendalian Biaya Proyek

Select one:

a. Mencari Sponsor

b. Estimasi biaya

c. Penentuan Anggaran

d. Pengendalian perubahan 

Question 5

Correct

Marked out of 2.00

Yang bukan termasuk dalam manajemen biaya adalah

Select one:

a. Memperkirakan biaya

b. Mengontrol biaya

c. Menentukan anggaran

d. Mengestimasi Sumber Daya 

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 2/10
7/4/2021 UTS 2020-Genap: Attempt review

Question 6

Correct

Marked out of 2.00

Pembuatan Project charter masuk kedalam tahap perencanaan(planning)

Select one:

a. False 

b. True

Question 7

Correct

Marked out of 2.00

Following statements are TRUE regarding ROI, except ...

Select one:

a. Many organizations have a required minimum acceptable rate of ROI for projects.

b. Internal rate of return can be calculated by nding the discount rate that makes the NPV equal to zero.

c. ROI is calculated by substracting the project costs from the bene ts and then dividing by the costs.

d. ROI is usually presented as a percentage.

e. The lower the ROI, the better. 

Question 8

Correct

Marked out of 2.00

Tiga metode utama untuk menentukan nilai proyek yang diproyeksikan dari proyek, kecuali:

Select one:

a. Payback analysis

b. Return on investment

c. Work Breakdown Structure 

d. Net present value

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 3/10
7/4/2021 UTS 2020-Genap: Attempt review

Question 9

Correct

Marked out of 2.00

The method(s) that can be use in nancial analysis of projects... .

Select one:

a. All three are correct 

b. Payback analysis

c. Net Present Value (NPV)

d. Return on Investment (ROI)

e. All three are incorrect

Question 10

Correct

Marked out of 2.00

Apakah mungkin untuk membuat perubahan pada scope baseline di seluruh proyek?

Select one:

a. Tidak, tidak mungkin mengubahnya

b. Ya, setiap kali tim merasa bahwa sebagian dari persyaratan tersebut tidak layak untuk diterapkan

c. Tidak ada yang benar

d. Ya, itu hanya dapat diubah melalui prosedur pengendalian perubahan formal dan digunakan sebagai dasar 
perbandingan

Question 11

Correct

Marked out of 2.00

_______ knowledge area yang memiliki aktivitas disetiap process group

Select one:

a. Integrasi 

b. Waktu

c. Biaya

d. Cakupan

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 4/10
7/4/2021 UTS 2020-Genap: Attempt review

Question 12

Correct

Marked out of 2.00

Jenis hubungan ketergantungan mana yang cocok dengan pernyataan berikut "The predecessor must start before the successor
can nish"?

Select one:

a. Start-to-Finish 

b. Start-to-Start

c. Finish-to-Finish

d. Finish-to-Start

Question 13

Correct

Marked out of 2.00

As a project manager, you create a WBS by breaking down a project work into smaller tasks hierarchically and create a tree-like
structure of project works. Your approach is the ...

Select one:

a. top-down approach 

b. bottom-up approach

c. mind mapping approach

d. benchmarking approach

e. analogy approach

Question 14

Correct

Marked out of 2.00

The three types of dependencies in activity sequences are ___

Select one:

a. Mandatory, discretionary, and external dependencies 

b. Mandatory, optional, and external dependencies

c. Internal, external, and discretionary dependencies

d. Mandatory, discretionary, and inherited dependencies

e. Optional, internal, and external dependencies

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 5/10
7/4/2021 UTS 2020-Genap: Attempt review

Question 15

Correct

Marked out of 2.00

Tujuan utama pembuatan jadwal proyek adalah:

Select one:

a. Membuat jadwal proyek agar berjalan sukses

b. Membuat jadwal proyek yang terinci

c. Membuat jadwal proyek yang realistis dan menjadi dasar pengawasan berjalannya proyek 

d. Membuat jadwal proyek agar cepat selesai

Question 16

Correct

Marked out of 2.00

Buffer adalah waktu tambahan untuk menyelesaikan sebuah tugas, buffer dapat ditambahkan setelah jatuh tempo proyek

Select one:

a. Salah 

b. Benar

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 6/10
7/4/2021 UTS 2020-Genap: Attempt review

Question 17

Correct

Marked out of 20.00

Pilihlah jawaban yang tepat untuk soal berikut

Gantt Chart
#Bagan yang menggambarkan pekerjaan Proyek.

Baik
#Semakin tinggi NPV maka semakin.

#Memberi pertimbangan, rekomendasi kebijakan dan prosedur, serta memberi wewenang manajer Fungsi PMO
proyek tertentu. 

#Model yang digunakan untuk memilih proyek dengan membandingkan seberapa besar proyek Bene t Measurement Model
menguntungkan perusahaan. 

Critical Path
#Lintasan kritis proyek di sebut.

Controlling Schedule
#Mengendalikan dan mengelola perubahan jadwal proyek.

Proses Penutupan
#Memberikan laporan hasil yang diperoleh dari aktivitas proyek yang sudah dilaksanakan.

deliverable
#A product produced as part of a project.

pro t margin
#The ratio of revenues to pro ts.

#Teknik untuk mengukur performansi proyek yang mengintegrasikan lingkup, waktu dan biaya Earn Value Management
proyek. 

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 7/10
7/4/2021 UTS 2020-Genap: Attempt review

Question 18

Partially correct

Marked out of 40.00

Cari ES,EF LS,LF, FS, TS untuk kasus berikut

Time Planning
ES EF LS LF FS TS

A 0  4  0  4  0  0 

B 4  7  10  13  0  0 

C 4  9  4  9  0  0 

D 4  10  14  18  10  8 

E 9  17  9  17  0  0 

F 9  11  19  21  10  10 

G 17  26  17  26  0  0 

H 26  33  26  33  0  0 

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 8/10
7/4/2021 UTS 2020-Genap: Attempt review

Question 19

Incorrect

Marked out of 2.00

_____ adalah kumpulan dari …, …, dan operasi yang diatur untuk mencapai tujuan strategis organisasi. Berikut ini yang paling
tepat untuk mengisi titik-titik di atas secara berurutan adalah … .

Select one:

a. Portfolio, program, proyek

b. Program, proyek, portfolio

c. Program, portfolio, proyek

d. Proyek, portfolio, program 

Question 20

Correct

Marked out of 2.00

Manajer proyek bertanggung jawab terhadap banyak hal sebagai berikut, kecuali:

Select one:

a. Mengestimasi waktu dan jadwal pelaksanaan proyek

b. Menyiapkan sumber daya proyek yang dibutuhkan

c. Mengidenti kasi rencana kontingensi

d. Menentukan ruang lingkup proyek

e. Mendelegasikan proses pengontrolan proyek kepada klien. 

Question 21

Correct

Marked out of 2.00

Siklus hidup proyek adalah:

Select one:

a. Daftar pekerjaan dalam membuat proyek

b. Kegiatan yang dilakukan untuk mencapai tujuan proyek

c. Pengulangan di dalam pekerjaan proyek

d. Tahapan yang berhubungan dari awal sampai akhir proyek 

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=2059608&cmid=1125497#question-2099421-18 9/10
7/4/2021 UTS 2020-Genap: Attempt review

Question 22

Incorrect

Marked out of 2.00

Pengaruh organisasi bagi proyek, dapat ditinjau dengan kerangka, kecuali :

Select one:

a. Kerangka politik 

b. Kerangka S.D.A.

c. Kerangka struktur

d. Kerangka simbolik