36 part 1 UTS 2223-Genap: Attempt review

MANAJEMEN PROYEK TIK IT-44-GAB [CDF]


Dashboard / My courses / CII3G3-IT-44-GAB / Ujian CLO2 Manpro 2023 / part 1 UTS 2223-Genap

Started on Thursday, 13 April 2023, 3:24 PM

State Finished

Completed on Thursday, 13 April 2023, 4:35 PM

Time taken 1 hour 10 mins

Question 1

Incorrect

Marked out of 2.00

Project work is most successful in an organizational culture where ___ are strong/ high.

Select one:

a. all three are correct

b. group emphasis

c. all three are incorrect

d. member identity 

e. risk tolerance

Question 2

Correct

Marked out of 2.00

The three types of dependencies in activity sequences are ___

Select one:

a. Mandatory, discretionary, and inherited dependencies

b. Internal, external, and discretionary dependencies

c. Mandatory, optional, and external dependencies

d. Mandatory, discretionary, and external dependencies 

e. Optional, internal, and external dependencies

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=6733055&cmid=3132560#question-6880707-18 1/9
13/04/23, 16.36 part 1 UTS 2223-Genap: Attempt review

Question 3

Correct

Marked out of 2.00

SALAH SATU PENGARUH ORGANISASI BAGI PROYEK,  DITINJAU DENGAN 4 KERANGKA YAITU

Select one:

a. KERANGKA PROJEK

b. KERANGKA BISNIS

c. KERANGKA BIAYA

d. KERANGKA STRUKTUR 

Question 4

Incorrect

Marked out of 2.00

A project management plan for small projects with high complexity should contain following artefacts, except ....

Select one:

a. network diagram

b. WBS

c. HR plan

d. schedule plan

e. risk plan 

Question 5

Incorrect

Marked out of 2.00

A project is planned for 10 months duration and is budgeted for $20,000 with fix expenses each month. After two
months, 25% of the work has been completed and $10,000 has been spent. Calculate the PV, EV, SPI, and CPI of the
project!

Select one:

a. PV = $4,000; EV = $5,000; SPI = 125%; CPI = 50%

b. all three are correct

c. PV = $2,000; EV = $4,000; SPI = 80%; CPI = 50% 

d. all three are incorrect

e. PV = $4,000; EV = $10,000; SPI = 80%; CPI = 125%

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=6733055&cmid=3132560#question-6880707-18 2/9
13/04/23, 16.36 part 1 UTS 2223-Genap: Attempt review

Question 6

Incorrect

Marked out of 2.00

Dari berikut ini, apa bagian dari the scope management processes?

Select one:

a. Semuanya benar

b. Scope Verification 

c. Create WBS

d. Scope Control

Question 7

Correct

Marked out of 2.00

Salah satu tantangan manajemen proyek adalah:

Select one:

a. Kompleksitas proyek 

b. Waktu proyek yang lama

c. Biaya proyek yang rendah

d. Biaya proyek yang tinggi

Question 8

Incorrect

Marked out of 2.00

Payback occurs when the net cumulative discounted ... equals to the ...

Select one:

a. benefits, costs

b. plan, actual

c. values, returns 

d. positive, negative

e. spendings, budgets

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=6733055&cmid=3132560#question-6880707-18 3/9
13/04/23, 16.36 part 1 UTS 2223-Genap: Attempt review

Question 9

Correct

Marked out of 2.00

Dalam Proses manajemen ruang lingkup proyek, pernyataan ruang lingkup dibuat?

Select one:

a. Create WBS

b. Define Scope 

c. Collect Requirements

d. Control Scope

Question 10

Correct

Marked out of 20.00

Pilihlah jawaban yang tepat untuk soal berikut

Gantt Chart
#Bagan yang menggambarkan pekerjaan Proyek.

Sequencing Activities
#Mengidentifikasi dan mendokumentasikan hubungan antara kegiatan proyek

Baik
#Semakin tinggi NPV maka semakin.

#Pengaruh organisasi bagi proyek ditinjau dengan empat kerangka, salah satu contohnya simbolik
yaitu proses launching proyek di momen atau agenda tertentu, merupakan kerangka: 

#Dokumen formal yang mengakui keberadaan proyek dan menyediakan arah tujuan dan Project Charter
pengelolaan proyek. 

Deliverable
#Produk yang dihasilkan.

Profit
#Pendapatan dikurangi pengeluaran

Cost Management Plan
#Dokumen berisi rencana pengelolaan keuangan proyek.

SMART
#Characteristics of milestones

cost
#Sasaran proyek terdiri dari tiga goals yaitu scope, time dan ____ .

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=6733055&cmid=3132560#question-6880707-18 4/9
13/04/23, 16.36 part 1 UTS 2223-Genap: Attempt review

Question 11

Correct

Marked out of 2.00

___is the amount of time an activity may be delayed from its early start without delaying the planned project finish
date.

Select one:

a. forward pass

b. total float 

c. duration

d. free slack

e. backward pass

Question 12

Incorrect

Marked out of 2.00

_____ adalah kumpulan dari …, …, dan operasi yang diatur untuk mencapai tujuan strategis organisasi. Berikut ini
yang paling tepat untuk mengisi titik-titik di atas secara berurutan adalah … .

Select one:

a. Program, portfolio, proyek

b. Proyek, portfolio, program

c. Program, proyek, portfolio 

d. Portfolio, program, proyek

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=6733055&cmid=3132560#question-6880707-18 5/9
13/04/23, 16.36 part 1 UTS 2223-Genap: Attempt review

Question 13

Partially correct

Marked out of 20.00

Cari ES,EF LS,LF, FS, TS untuk kasus berikut

Time Planning
ES EF LS LF FS TS

A 0  4  0  4  0  0 

B 4  7  4  7  0  0 

C 4  9  7  12  3  3 

D 4  10  9  15  5  5 

E 7  15  12  20  5  5 

F 7  9  15  17  6  6 

G 10  19  10  19  0  0 

H 15  22  15  22  0  0 

Question 14

Correct

Marked out of 2.00

Dokumen formal yang mengakui keberadaan proyek dan menyediakan arah tujuan dan pengelolaan proyek adalah:

Select one:

a. Project Management

b. Project Manager

c. Project Proposal

d. Project Charter 

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=6733055&cmid=3132560#question-6880707-18 6/9
13/04/23, 16.36 part 1 UTS 2223-Genap: Attempt review

Question 15

Correct

Marked out of 2.00

_____ is a cost estimate done very early in the project life cycle, provides estimate of cost for selection decisions, and
has a low accuracy.

Select one:

a. actual cost

b. rough of magnitude 

c. planned estimate

d. definitive

e. budgetary

Question 16

Correct

Marked out of 2.00

Following are main processes of project cost management, except ... .

Select one:

a. changing 

b. planning

c. controlling

d. estimating

e. determining

Question 17

Correct

Marked out of 2.00

Biaya atau manfaat yang sulit diukur dalam rupiah adalah:

Select one:

a. Intangible costs 

b. Direct costs

c. Tangible costs

d. Indirect costs

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=6733055&cmid=3132560#question-6880707-18 7/9
13/04/23, 16.36 part 1 UTS 2223-Genap: Attempt review

Question 18

Correct

Marked out of 2.00

Dengan diskon rate 10%, maka tahun depan nilai uang $6000 akan menjadi

Select one:

a. $5454 

b. $6600

c. $5400

d. $6666

Question 19

Incorrect

Marked out of 2.00

Dasar pembuatan Project Statement harus memenuhi

Select one:

a. System Requirement Specification (SRS)

b. Term of Reference (TOR) 

c. Risk register

d. Technical Review Document

e. Acceptance Criteria

Question 20

Correct

Marked out of 2.00

Manajer proyek bertanggung jawab terhadap banyak hal sebagai berikut, kecuali:

Select one:

a. Menyiapkan sumber daya proyek yang dibutuhkan

b. Mendelegasikan proses pengontrolan proyek kepada klien. 

c. Menentukan ruang lingkup proyek

d. Mengestimasi waktu dan jadwal pelaksanaan proyek

e. Mengidentifikasi rencana kontingensi

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=6733055&cmid=3132560#question-6880707-18 8/9
13/04/23, 16.36 part 1 UTS 2223-Genap: Attempt review

Question 21

Correct

Marked out of 2.00

Jika diketahui bahwa sebuah proyek terdiri atas tujuh aktivitas A, B, C, D, E, F, G dengan durasi masing-masing aktivitas
secara berurutan adalah 2, 3, 1, 4, 2, 3, 4 minggu. Tiga jalur dalam diagram jaringannya adalah A-B-C, A-D-E, dan F-G.
Maka critical path dari proyek tersebut adalah … dengan durasi … .

Select one:

a. A-D-E, 8 minggu 

b. F-G, 7 minggu

c. A-B-C, 6 minggu

d. A-B-C-D-E-F-G, 19 minggu

Question 22

Correct

Marked out of 2.00

terdapat beberapa hal pada Project Scope Management Processes. berikut yang bukan termasuk dari Project Scope
Management Processes adalah

Select one:

a. Validating scope

b. Planning scope

c. execute scope 

d. Defining scope

Previous Activity

Jump to...

Next Activity