A. To defines all the work, activities, and deliverables that the project team must provide
in order for the project to achieves the MOV.
B. To defines the first step to establishing what is and what is not part of the project work
to be completed by the project team.
C. To defines and documents how the project and product scope will be defined, verified,
and changed if necessary.
D. TO defines and managing actual changes to the project’s scope as and when they
occur to ensure that changes to the project’s scope will be beneficial.
3. You have plans to set up a team building activities, but you are facing some difficulties
due to the nature of the project organization. Which type of organization are you having?
A. Functional
B. Project
C. Matrix
D. Hybrid
4. All the following are steps in developing the project Measurable Organization Value (MOV)
EXCEPT:
5. What should be done by the project manager to ensure that all work in the project is
included?
A. Milestone
B. Deliverables
C. WBS
D. SDLC
9. The following approaches are used to increase the likelihood that IT projects will succeed
include:
10. An estimation technique that involves multiple experts who arrive at a consensus on a
particular subject or issue is called:
A. Guesstimating
B. Delphi Technique
C. Time Boxing
D. Top-Down Estimating
5 CS/DEC2022/ISP640
The measurable organizational value (MOV) provides a clear understanding of the project’s
purpose and is the foundation for writing the business case.
Figure 1
a) Based on Figure 1 above, describe why should a project align with an organization’s strategy,
vision, and mission? (3 marks)
Answer: The main purpose of business case is to obtain approval and funding for the planning
phase of the project.
6 CS/DEC2022/ISP640
(6 marks)
Answer
a) Program Evaluation Review Technique (PERT) uses the project network diagramming
technique to create a visual representation of the scheduled activities that expresses both
their logical sequence and interrelationships.
Consider the following data for a small software development project (all times are in
weeks).
Answer
i. Complete the expected time in table above (4 marks)
Task Task Predecessor Optimistic Most Pessimistic Expected
Description Task (s) Time Likely Time Time
Time
A Establish None 4 5 12 6
project
B Establish A 2 3 4 3
customer
requirements
C Produce B 6 8 22 10
software
specification
documents
D Write test C 4 6 8 6
plans
E Write code C 3 4 5 4
8 CS/DEC2022/ISP640
F Developer E 2 4 6 4
testing
G System D,F 2 3 4 3
testing
H Write manuals C 5 7 15 8
ii. Show the possible PERT activity paths and what the critical path in this project.
( 4 marks)
b) The Gantt chart will depicts the general sequence of activities or work tasks and also be useful
for tracking and monitoring the progress of a project. Create a basic Gantt chart based on the
information in table below:
( 7 marks)
9 CS/DEC2022/ISP640
Answer
10 CS/DEC2022/ISP640