You are on page 1of 6

PROJECT PROPOSAL

01. Proposed Components/process

Manufacture plastic based waste pyrolysis prototype machine to Produce Petroleum fluid by
using Waste Plastics, Polythene and Rubber to fulfill the essential requirement of petroleum
oil of SLAF Station Ekala.

02. Rational of Project

Plastic, polythene and Rubber waste is become a huge issue to the Sri Lanka Air force as
well as to complete environment system. Further, at present the cost of the petroleum
products is become an immerse issue to SLAF with prevailing economic situation of the
country. As a remedy to this matters we suggest to build a prototype machine to convert
plastic and rubber based waste to petroleum fluid.
03. Background of the Project

As an Airframe Advanced Trainees we hope to implement practice to recycle the plastic,


polythene and rubber waste (which considered as non-recyclable) and save money in
environmental friendly way. This will be the first attempt in Air force to produce
petroleum oil from waste and by this project we can seek the feasibility to utilize this in all
SLAF establishments to produce petroleum oil by using waste materials. In addition, by
this project, trainees can have number of opportunities to obtain a practical experience.
Moreover, trainees will be able to improve their skills in group activities and coordinating
with others to reach a common target

04. Project Plan

The project plan has been scheduled as follows,

 Initially, a project proposal was submitted for the approval of CO SLAF TTS Eka
subjected to WO I/C, Off I/C, CI Tech and OCT TTS.

 Then, trainees are to be planned the way of doing this. Afterwards the material
collection as per the schematic of the project after the quotation is taken.

 The completion of the group project will be successfully realized by overcoming


faults, shortcomings and barriers they met.

05. Project Implementation Plan

Implementation of this project was carried out as per the “Project plan” indicated in above
Paragraph number 04.
06.
Project Team

S/N SVC RANK NAME


NO
1 44709 LAC RATHNAYAKA KACJ
2 45183 LAC UDAYAKUMARA DMS
3 45189 LAC BOPITIYA AM
4 45204 LAC PRASANNA MGS
5 45214 LAC RANATHUNGA BGPPK
6 45220 LAC SAMANKUMARA WAKT
7 45719 LAC SUMANAPALA ST
8 45724 LAC PEIRIS TMSP
9 45737 LAC MAHANAMA KASS
10 45748 LAC BANDARA HMMW
11 45749 LAC RASANGA PG
12 45756 LAC MADUSHAN LPS
13 45760 LAC GUNARATHNA HPHPM
14 45762 LAC GUNATHILAKA KMAD
15 45773 LAC RANDIKA AT
16 45786 LAC MADUMAL SWS
17 45795 LAC WEERASINGHW DDV
18 45797 LAC GUNARATHNA DNAS
19 45810 LAC MADUSHANKA RMD
20 45819 LAC ADIKARI AACKS
21 45832 LAC ANURADHA AMK
22 45833 LAC INDIKA WPR
23 45837 LAC DE ZOYSA MYS
07. System procedure for approach

S/No Project tasks Week Week Week Week Week


01 02 03 04/05 06
01 Planned the project as per the √
instruction by CI tech

02 Collecting requirements from √


market

03 Draw a sketch diagram √

04 Arrange of the necessary systems √

05 Complete required documents √

08.
References

Internet based information


Experience of the trainees

09.
Capability

We strongly believe, this waste pyrolysis machine will be a fortune to save both money
and environment not only in TTS Eka but also indirectly whole establishment will be
benefitted.
10. Material requirement

REQUIRED
MATERIAL EA PRICE (RS) TOTAL PRICE
QTY
Empty Freon Gas Tanks EA 06 1000.00 6000.00
Copper tubes ½ inch 05m 1500.00 7500.00
Heat resistant Gasket EA 01 500.00 500.00
Radiator with fan EA 01 5000.00 5000.00
Water pump EA 01 1000.00 1000.00
Cement EA 1/2 1000.00 1000.00
Reactor EA 01 4000.00 4000.00
Brass valves EA 03 1400.00 4200.00
Welding Electrodes 01 Pack 1500.00 1500.00
L Iron Bar 01 Inch EA 02 1500.00 3000.00
Total 33700.00

11 Approximate budgeter

Approximate budgetary requirement is to be indicated as given bellow


S/N ITEM TOTAL COST (LKR)

01. Manpower -

02. Transport 5000.00

03. Material 33700.00

04. Professional services (Lathe Machine 5000.00


work)
05. Miscellaneous -

TOTAL 43700.00
12 REMARKS OF OFFICER IC

Date: Signature:

13 REMARKS OF CI

Date: Signature:

14 REMARKS OF OCT

Date: Signature:

15 APPROVAL OF CO

Granted / Not Granted

Date: Signature:
PROPOSED WASTE PLASTIC PYROLYSIS MACHINE

You might also like