WASA MITRA ENGINEERING


Tanjung Awar-Awar 2 X 350 CFPP Project Tuban

ACTUAL CALCULATION / COMPARATION MDS PLTU REMBANG

CONTRACT ACTUAL
No. DESCRIPTION QUANTITY (TONS) TOTAL TOTAL REMARK
MDS/TONS MDS/TONS
MDS MDS
INSTALL STEEL STRUCTURE FOR
1 6,200.00 Tons 6 Mds 37,200 7 Mds 43,400
BOILER

2 STEAM DRUM LIFTING 358.30 Tons 6 Mds 2,150 3 Mds 1,075

3 INSTALL OF STAIR & GRATING 1,221.33 Tons 6 Mds 7,328 30 Mds 36,640

4 INSTALL OF DUCTING 1,417.23 Tons 8 Mds 11,338 9 Mds 12,755

5 INSTALL OF BUCKSTAY 579.68 Tons 8 Mds 4,637 9 Mds 5,217

6 INSTALL OF PRESSURE PART 6,845.09 Tons 13 Mds 88,986 25 Mds 171,127

7 INSTALL WIND BOX 646.53 Tons 10 Mds 6,465 20 Mds 12,931

8 INSTALL OF PENTHOUSE 146.74 Tons 10 Mds 1,467 20 Mds 2,935

9 INSTALL OF COAL PIPE 463.20 Tons 12 Mds 5,558 18 Mds 8,338

10 INSTALL OF AUX. EQUIPMENT 1,034.87 Tons 4 Mds 4,139 4 Mds 4,139

11 INSTALL OF COAL MILL 1,411.08 Tons 4 Mds 5,644 6 Mds 8,466

12 INSTALL OF ESP 2,854.49 Tons 10 Mds 28,545 9 Mds 25,690

13 INSTALL OF AIR PREHEATER 1,782.52 Tons 4 Mds 7,130 4 Mds 7,130

14 BOTOM ASH SILO/SSC 258.00 Tons 8 Mds 2,064 12 Mds 3,096

15 SUPPORTING ( 30 Persons ) 20 MM - Mds 16,800 - Mds 16,800

ASSIST COMMISSIONING ( 20
16 6 MM - Mds 3,360 - Mds 3,360
Persons )

15 MM - Mds 3,360 - Mds 3,360


17 WARRANTY PERIDE ( 8 Persons )

TOTAL 25,260.06 Tons 236,173 366,460


AVERAGE 9 Mds/Tons AVERAGE 14.5 Mds/ TON