Professional Documents
Culture Documents
net/publication/318753880
CITATIONS READS
8 5,563
4 authors:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Mehran Samavati on 23 August 2017.
Abstract
Keywords: Open pit mine, production planning, large scale Scheduling, in-
pit crushing and conveying system
2
1. Introduction
The open pit mine production scheduling problem (OPMPSP) in the tradi-
tional T&S system consists of scheduling the extraction of a mineral de-
posit that is broken into a number of smaller segments, or blocks, across a
horizon of several periods in order to maximize the total discounted profit
known as net present value (NPV) from the mining project subject to a va-
riety of operational constraints. A similar optimization problem exists in
the IPCC system. Even though the objective in both systems seeks to max-
imize NPV, introducing conveyors (in IPCC) into an open pit operation in-
troduces a number of additional sequencing and pit expansion constraints
that are not required in traditional T&S systems. These constraints mainly
relate to the geometric need for a fixed pit access location to accommodate
the conveyor which thus restricts possible production sequencing in the
deposit. This means that generating a schedule for extracting blocks is de-
termined based on the location of conveyors, while finding the best loca-
tion for conveyors is itself an optimization problem and can change the
schedule. These additional constraints add further complexity to an already
complex large scale OPMPSP.
3
2. IPCC system
IPCC systems come from a few decades ago, first appearing in Germany in
1956. They were first applied to transport material out of a limestone
quarry which was not possible by a truck and shovel operation due to the
floor conditions (Koehler, 2003). In the current economic and political
climate, high diesel prices, shortages of tyres for large off-highway trucks
and labour, and high carbon emissions have reduced the attractiveness of a
truck and shovel operation. While these factors are a limitation to the use
of a truck and shovel system, they can also be seen as an opportunity to
exploit an IPCC system for its reduced operating costs, severely reduced
labour requirements, minimal reliance on large tyres for off-highway
trucks, and decreased carbon emissions (McCarthy, 2011).
In spite of these benefits, companies are still unwilling to use IPCC. One
of the reasons is the fact that there are some factors that must be consid-
ered to justify the replacement of trucks with IPCC configuration. These
factors, however, are totally related to the initial investment of the project,
4
Typically IPCC operating costs are lower than normal truck and shovel
operations; however, some factors, such as fuel prices, size of the mine,
materials mined, and the manpower required need to be analyzed and de-
termined for the full life of the orebody to optimize the profit. Due to the
lack of a methodology to obtain the best sequence of the extraction opera-
tions and an optimal schedule, these factors are analyzed based on strategic
plan that only comes from the judgement of experienced personnel in stra-
tegic decision making.
when using IPCC systems. In fact, there are a variety of aspects that must
be optimized in order to develop such a plan. In this section, we introduce
these aspects to OR community.
Figure 1 shows the deepest level of a pit from a top view. Each square in-
dicates a block, and the grey shaded blocks represent those containing
valuable material, known as ore blocks.
The best location for these conveyors is itself a decision variable and must
be determined at the same time with scheduling the extraction. The third
conveyor, bench conveyor, is mobile and can move to different rows.
The preceding example describes one of the aspects in IPCC systems that
should be optimized. There are, however, other aspects that can be consid-
ered in order to develop a strategic plan for the entire project:
From a practical point of view, the first two aspects may be the most im-
portant ones to be considered. All these operational aspects also exist in
the traditional T&S extraction system; from an OR point of view, integrat-
ing waste dump scheduling has been the most difficult aspect in the tradi-
tional system and, in fact, there are still no efficient algorithms to address
this problem. The same may hold for the IPCC system, as incorporating
waste dump requires considering the storing of extracted material along-
side extraction scheduling.
4. Conclusion
References