You are on page 1of 6

DRAINING - FILLING - BLEEDING : COOLING SYSTEM

INJECTION EW10J4 OR INJECTION EW12J4 OR EW10A INJECTION OR INJECTION EW7A OR


INJECTION EW7J4

1. Special tools

Figure : B1GK06LC

[ 1] filling cylinder (-).0173-2.


Figure : B1GK0BHD

[2] Pliers (-).0165.

2. Draining
CAUTION : The draining operation is carried out when cold.

Place the vehicle on a lift.


Raise the vehicle.
Remove the shield under the power train.
Lower the vehicle.
N.B. : Place a tray under the radiator to drain the circuit cleanly.

Remove the cap from the expansion tank.

Figure : B1GKB3ZD

Cooling radiator (With drain screw) : Unscrew the radiator drain plug (3).
Figure : B1GKB1WD

Cooling radiator (Without drain screw) : Disconnect the radiator bottom hose (4) (Use tool [2]) .

Figure : B1GKB1TD

Open the bleed screw (1) of the heat exchanger pipe .


Figure : B1GKB1UD

Open the bleed screw (2) of the coolant outlet unit .


Raise the vehicle.

Figure : B1GKB1XD

Drain the engine by removing the plug (5) : On bulkhead side (At the rear of the engine) .
The plug is located under the pipe running from the water outlet housing to the coolant pump .
If necessary : If necessary use an extender, a universal joint and a 8,0 mm square adaptor.

3. Filling and bleeding the system


Before any re-filling operation, flush the cooling circuit with clean water.
Close the bleed screws (1 - 2).
Refit the drain plug(s) (5) and one (of the) new seal(s).
Tighten the cap (5) to 3.0 ± 0.3 da.Nm.
CAUTION : Ensure that the lower pipe on the radiator is in place.

Check the cooling system for leaks.

Figure : B1GK0BBD

Fit the filling cylinder [1] to the filler opening.


Open the bleed screws .
Fill the circuit slowly with coolant.
Close the bleed screws when the liquid flows without bubbles.
The filling cylinder must be filled to the 1,0 litre mark to bleed the heater matrix correctly.
Start the engine.
Maintain a speed between 1500 and 2000 rpm until the end of the second cooling cycle (the cooling
fan(s) cutting in then stopping) while keeping the filling cylinder full to the 1 litre mark.
Remove the filling cylinder [1].
Immediately tighten the plug on the expansion chamber .
Stop the engine.
Engine cold : If necessary fill up to the level of the maximum mark.
Refit the shield under the power train.