You are on page 1of 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/265989616

Dilatometer tests in deep boreholes in investigation for Brenner


base tunnel

Article · May 2007


DOI: 10.1201/NOE0415408073.ch47

CITATION READS

1 917

4 authors, including:

Marek Zalesky Ulrich Burger


SG Geotechnika a.s. Brenner Base Tunnel
5 PUBLICATIONS   5 CITATIONS    23 PUBLICATIONS   33 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Brenner Base tunnel View project

All content following this page was uploaded by Ulrich Burger on 26 March 2015.

The user has requested enhancement of the downloaded file.


Underground Space – the 4th Dimension of Metropolises – Barták, Hrdina, Romancov & Zlámal (eds)
© 2007 Taylor & Francis Group, London, ISBN 978-0-415-40807-3

Dilatometer tests in deep boreholes in investigation for Brenner base tunnel

M. Zalesky & Ch. Bühler


Solexperts AG, Mönchaltorf, Switzerland

U. Burger
BBT SE, Innsbruck/Bolzano, Austria/Italy

M. John
John Tunnel Consultant, Innsbruck, Austria

ABSTRACT: Results from more than one-year of in-situ deep borehole dilatometer testing and data evaluation
for the Brenner base tunnel geotechnical investigation project are presented. The principle of dilatometer mea-
surements is explained. Dilatometer measurements describe deformation properties of rock massif. Deformation
modulus and modulus of elasticity are determined in relationship to applied pressure. Equipment for testing in
deep boreholes with diameters ranging from 96 to 158 mm is described. Information needed prior to measure-
ments, testing procedures as well as evaluation of recorded data are discussed. Examples of in-situ dilatometer
measurements are presented. Range of use of gained results is discussed and conclusions are drawn.

1 INTRODUCTION 1977). Determination of the mechanical properties of


the rock mass is based on real-time measurement of
The Brenner base tunnel will be a significant part of the applied pressure and the resulting deformation –
European railway axis Berlin – Napoli – Palermo. The the change of the borehole diameter.
55.6 km long tunnel route will be built from Aus- The dilatometer probe consists of a metal core,
trian Innsbruck to Italian Franzensfeste (Fortezza). which holds three potentiometeric displacement trans-
Numerous deep boreholes up to 1351 m depth were ducers placed in the centre of the core, Figure 1.
simultaneously drilled during the second phase of The axes of the transducers are oriented 120◦ to each
geological exploration in 2004–2005. Depth of the other and vertical distance between the transducers is
boreholes required drilling in several sections with 75 mm. The borehole wall is loaded by means of a re-
decreasing diameter. Other reason for various borehole inforced packer sleeve fixed to the core of the probe
diameters was that six different drilling companies par- at its both ends. The packer can be expanded by
ticipated in the project. To comply with the proposed compressed nitrogen or air via a high-pressure hose
procedure of “drilling – logging – measuring”, Sol- connected to either nitrogen bottles or a compressor.
experts AG was obliged to perform tests in boreholes The dilatation of the borehole wall is directly measured
with diameters ranging from 96 mm to 158 mm. by the transducers, which contact the borehole wall
Several types of borehole measurements were per- through steel pins with spherical heads. The applied
formed: geophysical logging, packer tests, stress meas- pressure is measured at the surface using a pressure
urements using hydraulic fracturing and dilatometer sensor. The electronic signals of the displacement
measurements. In this paper we focus on in-situ deter- transducers are transmitted to the dilatometer logger
mination of deformation properties of rock massif through a coaxial cable within the high pressure-hose.
using Solexperts dilatometer. The probe can be additionally equipped with a compass
for oriented strain measurement or with two pressure
sensors: one measuring the formation pressure under-
2 SOLEXPERTS DILATOMETER SYSTEM neath the probe and the other measuring the pressure
inside the packer. To simplify installation and mini-
The dilatometer probe developed by SolexpertsAG has mize risk of damage when retrieving the probe from
been successfully used for more than 30 years (Thut the borehole a steel cone is attached to the lower end

283
possible to perform measurements up to 1400 m in
depth. One or more 200 m sections of the hose/cable
can be replaced, if needed.
The inflation pressure is manually regulated and
automatically measured at the control panel with
a pressure sensor. Additionally it can be observed
together with the pressure in the system and the
rest pressure in the nitrogen bottle (or compres-
sor) with mechanical pressure gauge in the control
panel. For special long-term dilatometer experiments
a fully automated monitoring system (the Solexperts
GeoMonitor II) can be used. In this case however, the
dilatometer system is pressurized with silicon oil.
The pressure sensor and the signal cable from
the probe are connected to special dilatometer data
acquisition system, which is controlled by a com-
puter via the software program DilatoII developed by
Solexperts. This program provides data acquisition,
testing control, graphical and numerical real-time data
presentations, as well as test analysis and reporting.
Figure 1. Scheme of the Solexperts dilatometer.

Table 1. Diameters of Solexperts dilatometer. 3 DILATOMETER TESTS

Diameter 3.1 Planning and preliminary information


Unexpanded probe Borehole – minimum To comply with a “drilling – logging – measuring”
mm mm Sign procedure requires a significant planning, decision
making and preparation is necessary prior to execution
92 96 HQ of each series of tests.
95 101 In-situ testing i.e. dilatometer measurements or
118 122 PQ hydraulic tests using a double packer system can be
142 146 done during the drilling phase or after the entire length
148 152
of the borehole has been drilled. Performing measure-
ments according to the state of drilling progress may
be difficult to manage especially when several bore-
of the probe and an open type bailer, called sedimenta- holes are being drilled simultaneously, as it was for the
tion tube, to its upper end in order to prevent blocking Brenner exploration project.
the probe by loose material falling down the drill hole. In most cases however, measurement campaigns are
The maximum measurement range of the displace- carried out after the drilling has been successfully fin-
ment transducers is 25 mm, also due to their high ished. The geologist in charge usually overviews the
accuracy of 0.001 mm. The packer is designed for this entire borehole and specifies the borehole sections of
range of strain too. To perform tests in boreholes with interest. Results of tests might be affected by “borehole
diameters ranging from 96 mm to 158 mm there had to history effect” (especially affecting the hydraulic tests
be either a single probe for each diameter or one type results). Another problem to be considered for testing
of probe, where the packer element and transducer after drilling is the stability of the borehole. Especially,
extension pins could be easily changed. Solexperts investigation of faults and shear zones is of interest for
has developed a dilatometer probe body (core), which the design of planned excavation. In cases of poor bore-
can be equipped by packer elements of different diam- hole stability only the “measurement-while-drilling”
eters. A set of corresponding sedimentation tubes and approach can be applied.
calibration tubes have also been provided, Table 1. The The approach chosen for the geotechnical and
probe is installed with so called hydro-frac tubing of hydrogeological investigation for the Brenner base
1 using a drilling rig. tunnel was a compromise of the presented possibili-
The high-pressure hose containing signal cable is ties: a series of test measurements was done after a first
wound on a winch on the surface. The hose/cable was section of the borehole with one diameter was drilled.
manufactured in sections of 200 m with the appropriate Borehole logging and geophysical measurements
connectors. Connecting multiple sections, made it were carried out at the beginning of a testing campaign.

284
The logs were used to decide about the subsequent test- first, the probe was inflated to a base pressure, which
ing strategy and number of tests. For the dilatometer was about 0.5 MPa higher than the hydrostatic pres-
tests the most important information was: sure at the test position in order to establish a good
contact between the packer and the borehole wall. The
– nominal borehole diameter,
first cycle consisted of initial loading and subsequent
– test depths,
unloading to the base pressure. The following cycles
– type of rock / inspection of borehole cores,
consisted of reloading up to the maximum pressure of
– dipping of shistosity,
the previous load cycle, initial loading to a higher level
– calliper log for actual borehole diameter or
and then unloading to the base pressure level.
– borehole scan for geologic structure and
The maximum level of loading pressure has to be
– ground water table / hydrostatic pressure at each test
chosen with respect to the rock type, its assumed
depth.
compressibility and the aim of the test. In case of meas-
The calliper log and/or the borehole scan provided urements for a future base tunnel, the applied pressure
information about the true borehole diameter as well as should reach the same order as the horizontal pres-
the possible existence of caverns, discontinuities, large sure at rest in the mountain massif. One of the aims
cracks and fractures of the massif. Uneven borehole of a good dilatometer test is to describe the ratio of
walls result in higher risk of packer damage and, in the plastic and elastic deformations together with general
extreme case, the possible blockage of the borehole by behaviour of the rock, which can be also mostly elas-
an irretrievable probe. Additionally, to high artesian tic or plastic. The range of applied pressures should be
water pressure (determined by the hydrogeological chosen so, that the maximum of elastic deformation
tests) can cause difficulties during the tests. phase of the rock is used, but causing massive plas-
tification or fracture of the rock is to be avoided if
possible.
3.2 Test procedure After the test is finished, the probe is unloaded under
the level of acting hydrostatic pressure and raised to
The dilatometer probe must be calibrated prior to test-
the next higher measurement zone.
ing. The calibration is done by inflating the probe
inside a steel tube of known diameter. The DilatoII
software then records the data from each displacement 3.3 Evaluation of dilatometer test
transducer and calculates offsets so that a “zero read-
ing” corresponds to the known inner diameter of the The moduli are calculated based on Lamé’s equation
tube. The actual borehole diameter can then be pre- for a tube with infinite wall thickness (1):
cisely determined. It is needed for control of the probe
expansion state during the test and for test analysis.
The test sequence usually begins at the lowest
test position in the borehole. During installation into
deep boreholes the probe must be partially inflated where p = pressure difference; d = borehole diam-
in order to counterbalance the acting hydrostatic pres- eter; d = change of borehole diameter; ν = Poisson’s
sure. After lowering the probe to the depth given by the ratio. In case where no results of laboratory tests are
geologist, the dilatometer measurement can start. The available for the tested rock formation, we assume the
actual borehole diameter can be determined with the Poisson’s ratio of 0.33 with respect to rock quality.
dilatometer probe in cases where the calliper log shows The deformation modulus (V) is calculated based
significant variations in borehole diameter along the on data of initial loading from each load cycle. The
borehole section selected to be the test position, or modulus is computed using a linear regression along
the borehole cores showed discontinuities, but espe- the corresponding section of the curve. The deform-
cially if no core could be retrieved. The actual diameter ation modulus from reloading phase of each cycle is
can be determined by inflating the probe just enough calculated in a similar manner.
to overcome the hydrostatic pressure and the stiffness The modulus of elasticity (E1 ) is calculated from
of the packer. Then the packer is in contact with the the slope of a secant connecting the first and the last
borehole wall. Under low inflation pressure there is point of the unloading phase, which corresponds to the
no danger for the probe even if a cavern or fracture initial loading range for each cycle. However in cases
exists at this borehole section. The risk of damaging of very step slopes which correspond to very small
the equipment can be minimized by selecting a test elastic deformation of the borehole wall and thus to
position with an appropriate diameter after measuring very high moduli, it appears to be more appropriate to
the borehole diameter at several locations along the calculate E2 (Fig. 2) from the entire unloading curve
test zone using the described procedure. for each load cycle.
The dilatometer tests for Brenner base tunnel The averaged displacement measurements of the all
project were performed with four loading cycles. At three transducers are mainly used for the calculation

285
Figure 4. Schema for computation of E and  for Schnei-
Figure 2. Dilatometer test in borehole Va-B-03/04s, der’s criterion. Graph: Test in borehole Pf-B-03/05, depth
986.5 m depth, chlorite schists. Graphical representation 39 m, quartzphyllite. Average from deformation measure-
from the DilatoII software program: average from deform- ments of all three extensometers.
ation measurements of all three extensometers.

Another approach, Schneider’s criterion (1967),


also uses the Lamé’s equation, but allows interpre-
tation and comparison of series of dilatometer tests
from a wide range of rocks. Development of the
deformation properties can be evaluated with respect
to acting pressure. Measurements with four loading
cycles are required for the Schneider’s criterion, which
describes the relationship of a factor of permanent
deformation Cp (2) to a ratio of elasticity modulus E
to deformation modulus  (3):

Figure 3. Dilatometer test in borehole Va-B-03/04s, depth


986.5 m. Comparison of pressure/deformation graphs for
three extensometers.
where dp = permanent deformation after a complete
of the moduli. Based on comparison of all three pres- loading cycle; and pmax = maximum loading pres-
sure / deformation graphs, conclusions on elastic or sure applied with this cycle. The factor of permanent
plastic behaviour of the rock massif can be drawn and deformation is calculated for each loading cycle.
estimates of anisotropy can be made. Figures 2 and 3 The modulus of elasticity E is defined as a slope
show a dilatometer test in chlorite schists at 986.5 m of a straight line, which connects points d25 av and
depth. The borehole Va-B-03/04s is inclined 30◦ from d75 av . These points represent average deformation
vertical. from unloading (d25 U , d75 U ) and reloading (d25 L ,
The method of analysis described above allows d75 L ) phase of the corresponding load cycle (see
assessing one dilatometer test at a time. The stiffness Fig. 4).Values of d25 and d75 are determined at pressure
of the examined rock can be classified according to levels of 25% and 75% from the maximum pressure
the values of deformation and elasticity modulus from applied in the loading cycle. The E moduli are calcu-
the last loading cycle. For this purpose we use the lated for the first to the third load cycle.The calculation
classification based on E-modulus values, which was of E-modulus from the last (fourth) cycle is based on
proposed by AFTES (1993). data from the unloading phase only. These calculations

286
Figure 5. Schneider’s criterion, after Schneider (1967).
Graph: dilatometer tests in shales, borehole Va-B-03/04s. Figure 6. Modified Schneider’s criterion. Distribution of 70
test results. The position of the points corresponds with aver-
age of E/V and Cp for each presented rock class. The size of
points relatively depicts the number of tests.
can be done by interpolation between the data points
recorded during the measurement (see Figure 2) or
estimated in the chart. The analysis data presented in in Schneider’s graph. To get a better overview of the
this article were interpolated. The deformation mod- distribution of test results, the average is calculated
ulus  is determined as the slope of a secant, which for each rock class. Seventy dilatometer tests exe-
connects the first and last point of an initial loading cuted during the exploration campaign for Brenner
phase of a load cycle, Figure 4. base tunnel project are shown in Figure 6.
The resulting data is plotted in a semi-logarithmic The proposed analysis and graphic presentation
graph, which is also used for rock classification, after gives an overview of the deformation properties along
Schneider (1967), Figure 5.All four data sets presented the whole project. Based on the modified Schnei-
in this example indicate compact rocks with mainly der’s criterion, it is obvious, that that about 95% of
elastic deformation behaviour. the tests indicate a compact rock, of mainly elastic
Data analysis for Schneider’s criterion is not inte- behaviour in the range of applied pressures. Only four
grated into the analysis part of DilatoII program. tests (roughly 5%) represent rock with partly plastic
Therefore the analysis was made with a spreadsheet deformation behaviour. In the next step, these tests
program, which is rather time consuming. Further, should be reviewed in detail and further investigation
presentation of a large number of tests in a dia- might be considered if these results appear to be critical
gram according to Schneider can become confusing. for the project.
For these reasons we propose a modified version of This approach might be helpful for decision mak-
Schneider’s criterion based on the values from the last ing in the early stages of geological and geotechnical
(fourth) loading cycle only. The results of a complete survey. The knowledge gained from the modified
dilatometer test are reduced to only one point in the Schneider’s criterion may be used:
Schneider’s graph, instead of a polygon line in the – as another point of view for preliminary character-
original Schneider’s criterion. This method allows a istics the rock mass,
quick comparison of rock properties in a large set of – to find areas, where further investigation may be
dilatometer tests. This procedure does not depict the required,
development of the moduli and the amount of plastic – to obtain an overview of the deformation properties
deformation with respect to pressure changes during of the rock mass and
the test but makes evaluation of the distribution of – to estimate suitable tunnelling techniques and the
measured moduli much easier. type of primary tunnelling supports.
We use the data of V (deformation modulus cal-
culated as regression) and E (elasticity modulus)
computed by the DilatoII program in the modified
Schneider’s analysis. The E2 modulus calculated from 4 APPLICATION OF RESULTS
the entire unloading phase of the fourth loading cycle
was chosen, because it is closer to the original Schnei- For the determination of the stiffness parameters of
der’s criterion than the E1 value determined from the the rock mass at the Brenner base tunnel various for-
upper part of the corresponding unloading phase only, mulas given in the literature such as Hoek et al 2002
Figure 2. This simplifies determination of coefficient have been used. Results obtained revealed a consider-
E/V (instead of original E/), whereas the coefficient able scatter. The results of the dilatometer tests have
Cp remains unchanged. All results are then displayed been used to verify calculated results. Due to the fact

287
that dilatometer tests represent the deformability of ACKNOWLEDGEMENTS
sections of rock mass of less than 1 m, whereas during
excavation stress redistributions affect sections of up The authors would like to thank BBT SE for the
to 10 m results of dilatometer tests have been regarded permission to publish results from the 2004/2005
as an upper limit taking into consideration the scale exploration campaign.
effect.

REFERENCES
5 CONCLUSIONS
AFTES, Groupe de travaille No. 1, Géologie – Géotechnique.
Texte des recommandations pour une description des mas-
Results of dilatometer in-situ measurements describe sifs rocheux utile à l’étude de la stabilité des ouvrages
deformation properties of rock mass. A large num- souterrains. Tunnels et ouvrages souterrains, supplément
ber of tests were performed during the second phase au No117, Mai 1993, pages 12–21, Annexe 1.
of geological exploration for the Brenner base tunnel Hoek, B., Carranza-Torres, C., Corkum, B. 2002. Hoek-
in 2004–2005. The borehole diameters were ranging Brown Failure Criterion – Edition 2002. Vancouver.
from 96 to 158 mm and the boreholes were reach- Schneider, B. 1967. Moyens nouveaux de reconnaissance des
ing to depths of more than 1300 m. The results from massifs rocheux. In Nouredine Dinia et al, Méthodologie
the provided dilatometer tests were used to verify des essais au dilatomètre: application à quatre grands
calculated stiffness parameters of the rock mass at barrages Marocains; Proc. intern. Symp. Essais en place
volume 2, Paris 1983.
the Brenner base tunnel. Based on our experience Solexperts 2005. Brenner Basistunnel Erkundungsbohrun-
with test analysis and interpretation, a modification gen 2004 B0008-Wipptal BohrungVa-B-03/04s Dilatome-
of Schneider’s analysis of dilatometer tests has been terversuche. Final report. Mönchaltorf: Solexperts.
created in order to allow quick overview and compari- Solexperts 2005. Brenner Basistunnel Erkundungsbohrun-
son of numerous dilatometer tests. The most important gen 2004 B0008-Wipptal Bohrung Pf-B-03/05 Dilatome-
modifications are: moduli calculated only from the terversuche. Final report. Mönchaltorf: Solexperts.
last loading cycle are directly used. Each dilatome- Thut, A. 1977. Deformationsmoduln der Mergelschiefer der
ter test is then represented by only a single point in the Flyscherie und des verlehmten Gehängeschuttes Vergle-
Schneider’s graphical classification. Even large series iche zwischen Dilatometer- Lastplatten- und Druckver-
suchen. Mitteilungen der Schweizerischen Gesellschaft
of tests covering the whole explored area of inter- für Boden- und Felsmechanik No. 96, Frühjahrstagung,
est can be assessed. Evaluation of the distribution of Luzern, 13. Mai 1977.
points in the resulting graph allows characterization of Zalesky, M., unpubl. 2006. Comparison of all results of
the major type of rock mass deformability. The rock dilatometer test form Brenner base tunnel (2nd phase of
classes where few tests occur can indicate areas to be exploration) and modification of the Schneider’s criterion.
reviewed or further investigated.

288

View publication stats

You might also like