Professional Documents
Culture Documents
BIRMINGHAM JEFFERSON
COUNTY TRANSIT AUTHORITY,
et al.,
Defendants.
ORDER
• The court denies the BJCTA’s Rule 50(b) motion (doc. 239), which
means the jury’s verdict against the BJCTA on Count III stands;
• The court grants Relators’ Rule 50(b) motion (doc. 240), which means
the base damage amount for Count III is $1,438,467.74, resulting in
a treble damage award of $4,315,403.22; and,
• The court grants in part and denies in part Relators’ motion for
civil penalties (doc. 253) and penalizes the BJCTA $14,000 for each of
its 22 violations of the False Claims Act, resulting in a penalty award
of $308,000.
BACKGROUND
This case is about the BCJTA’s failure to comply with the Brooks Act
when using federal grants to pay for Strada’s work on Birmingham’s Bus Rapid
Transit (BRT) Project. Relators presented these claims to the jury:
1
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 2 of 44
The jury found that Relators proved the BJCTA falsely implied
compliance with the Brooks Act when asking for federal grant money to pay
for Strada’s work and awarded the Government compensatory damages.
The jury rejected all of Relators’ other claims. The jury found that
Murdock did not know that the BJCTA was falsely implying compliance with
the Brooks Act when the BJCTA submitted its reimbursement requests, and
that neither Strada nor Watters made false records or statements material to
the BJCTA’s reimbursement requests. So the jury also found that Murdock,
Strada, and Watters were not conspiring with the BJCTA to submit false
claims. Finally, the jury found that Culpepper failed to prove that she acted to
stop the BJCTA from violating the Brooks Act.
Culpepper doesn’t challenge the jury’s finding against her, so the court
won’t discuss it further. Both sides, however, challenge some part of the jury’s
verdict against the BJCTA on Count III. So the court recounts the facts
produced at trial that support the jury’s finding that the BJCTA violated the
False Claims Act while Murdock, Strada, and Watters did not.
1. Strada secures the BRT Project: Birmingham was awarded the World
Games in January 2015. The City wanted to build a rapid bus system in time
for the Games. Two companies pitched ideas to make it happen.
2
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 3 of 44
The City chose Strada, although the parties disagree as to why. Murdock
testified that the City chose Strada because WRA’s plan to extend the system
into wealthy suburbs like Mountain Brook would have prevented the City from
using certain federal funds that target impoverished neighborhoods like
Woodlawn and West End. But Relators say the City chose Strada because the
mayor was friends with Strada’s owner, Edmond Watters.
Three days after Strada sent the revised proposal, the City Council
resolved to make an agreement that would pay Strada $1.5 million per year to
manage the BRT program. (Id. at 35). Watters and the mayor signed the
agreement in early 2016. (Id. at 50).
2. The federal grants: In June 2015—one month after the City Council
passed the Strada resolution—Strada worked with the City and the BJCTA to
secure a $20 million federal TIGER grant to help fund the City’s work on the
BRT project. As for funding the BJCTA’s work, the BJCTA asked the FTA to
allow it to use the balance of existing Grants AL-03-0058 and AL-03-0077 on
the BRT Project. (See Tr. Ex. 1, 2).
3
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 4 of 44
40 U.S.C. § 1103(c) (Step 1); § 1103(d) (Step 2); § 1104(b) (Step 3).
In line with Step 1, the BJCTA issued a Request for Qualification from
A&E firms on June 3, 2015. (Tr. Ex. 95, “RFQ 15-17”). RFQ 15-17 said that the
BJCTA would “make a single award.” (Id., ¶ 1.26).
(Tr. Ex. 24, p. 3). As you can see, the committee ranked WRA (the firm the City
rejected) first, and it ranked Strada (who the City had already resolved to hire
as the BRT project manager) third.
4
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 5 of 44
Instead, on October 1, 2015, the BJCTA and Strada signed a contract for
Strada to provide the services described in RFQ 15-17. (Tr. Ex. 113). Barbara
Murdock signed and dated the contract for the BJCTA under the title, “Interim
Executive Director.” (Id., p. 9). But Murdock couldn’t explain how she could
have signed the Strada contract as interim director on “10-1-15,” because she
didn’t become Interim Executive Director until October 9th. She speculated
that the contract was backdated, but wasn’t sure what happened—other than
to say that, at the time, she “was directed by the Board and by attorneys as to
what to do.” (Trans. 140-142).
Similarly, Murdock testified that it was not her “regular habit” to sign
agreements with vendors like Strada before the Board gave her approval.
(Trans. 176). Yet, the Board didn’t pass the resolution that allowed Murdock
“to contract with the STRADA, Wendel, and WR&A to perform tasks” under
RFQ 15-17 until October 28, 2015—i.e. 27 days after Murdock signed the
contract with Strada. (Tr. Ex. 93).
Instead, Strada performed all 33 task orders between October 2015 and
April 2018. The BJCTA reimbursed Strada for the work it did under Task
Orders 7, 7a, 7b, 12, and 24 from the two grants that the FTA converted at the
BJCTA’s request in July 2015 and a grant that the FTA awarded the BJCTA
in February 2015 (Grant 95-X007).
According to Murdock, the FTA knew that Strada was doing all of the
BRT-related work from 2015 to April 2018—including the grant-funded work
in Task Orders 7, 7a, 7b, 12, and 24—because the City, the BJCTA, and Strada
would go to the FTA’s regional office in Atlanta, and the FTA “would give us
direction as to what would come next.” (Tr. Trans. 322). For example, Murdock
5
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 6 of 44
testified that the FTA asked the BJCTA and Strada to perform the “NEPA”
and “Historic Property and Cultural Resources” work that ended up in Task
Order 12. (See Tr. Trans. 323-25; Tr. Ex. 1, p. 8 (Grant AL-03-0058)). After
these meetings, Strada would draft the task orders and set a price; the BJCTA
would review and propose edits; and then the BJCTA would assign the task to
Strada—without negotiating the project with WRA or Wendel.
5. FTA intervention: Relators filed their qui tam complaint under seal
on April 9, 2018. (Doc. 1). Soon after, the FTA asked the City to explain how it
chose Strada to serve as the Program Manager for the BRT Project. On May
24th, the City sent Strada a check for its unpaid work and told Strada to stop
all BRT-related work until further notice. (Tr. Ex. 45).
The next month (June 2018), the FTA suspended the City’s use of the
ECHO system that disbursed the City’s $20 million TIGER grant. (Tr. Ex. 61,
p. 6). The City responded to the FTA’s questions in October. Because the City
had no documents that showed “a competitive procurement for Professional
Services,” the FTA demanded the City return all of the grant funds ($261,854),
plus interest. (Id.). The FTA told the City that it would not reopen the City’s
access to the TIGER grant funds until the City had paid back the entire
amount. The City complied.
In November, the FTA similarly asked the BJCTA to explain its process
for awarding all A&E work to Strada. (Tr. Ex. 24, p. 2). Unlike the City, the
BCJTA had papers. It sent the FTA a copy of RFQ 15-17; the independent
committee members’ evaluation forms and notes; and, the October 2015
Resolution that gave Murdock the authority to sign on-call contracts with
WRA, Wendel, and Strada. (Tr. Ex. 24). At first, an FTA Program Manager
said that, based on these documents, the FTA was “satisfied that the
procurement of design services for grants AL-03-0058 (New Starts Grant) and
AL-95-X007 (CMAQ Flex Grant) were procured through open competition.”
(Tr. Ex. 28, p.1). But the FTA later clarified that “‘satisfied’ is probably not the
correct term at this time. We still need to have a few more people to look at the
documentation that was submitted.” (Id.). Ultimately, the FTA took no
position; the BCJTA kept the disputed money; and Relators tried the case to
the jury on behalf of the Government.
6
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 7 of 44
Because the United States will keep most of any award, the court asked
the Government to weigh in on falsity and the proper amount of damages. (Doc.
249). The Government agrees with Relators that Relators proved falsity and
that the proper damage amount is 100% of the grant monies that the FTA gave
the BJCTA. (Doc. 261).
STANDARDS OF REVIEW
2. Motion for Penalties: The court must impose a penalty for each
violation of the False Claims Act. See 31 U.S.C. § 3729(a). The court can set
the per-act penalty between $13,508 and $27,018. See 28 C.F.R. § 85.5(a); table
1, column 7 (penalty amount for acts that occurred after November 2, 2015 and
assessed after January 30, 2023). The False Claims Act does not list factors for
the court to consider; those generally come from caselaw. The court will discuss
the factors it considered in the Discussion section.
7
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 8 of 44
DISCUSSION
As explained, the BJCTA could not use grant funds to pay for Strada’s
A&E work unless the BJCTA complied with the Brooks Act when it chose
Strada to do the work. It didn’t. So the jury found that the BJCTA submitted
a “false or fraudulent claim” under 31 U.S.C. § 3729(a)(1)(A) each time the
BJCTA drew down grant funds to reimburse Strada’s A&E work because the
BJCTA was falsely implying that it had complied with the Brooks Act.
Escobar, 579 U.S. at 190 (emphasis added). This court used the two-condition
test above to instruct the jury on the falsity element. (See Doc. 230, p. 9).
The BJCTA argues that Relators provided no evidence to prove the first
condition: “the claim does not merely request payment, but also makes specific
representations about the goods or services provided.” Escobar, 579 U.S. at
190. The BJCTA says that, when Stephanie Walker sought grant money from
the ECHO payment system, “[t]he only information [she] inputs into ECHO is
the ‘award number’ (i.e. the grant number) and the amount of payment being
8
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 9 of 44
requested.” (Doc. 239, p. 13). The BJCTA argues that it can’t be held liable
under Escobar because neither the grant number nor the amount of money
requested “makes specific representations about the goods and services
[Strada] provided.” Escobar, 579 U.S. at 190.
This is half true. It’s true that Walker did not type a detailed description
of the tasks that Strada completed into the ECHO system. But it’s untrue to
say that Walker didn’t convey that information when she filled in the grant
number and amount requested. Those numbers were codes, filled with greater
meaning than mere digits on a screen.
9
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 10 of 44
Provider Identification (NPI) numbers. Arbour would then submit the NPI
numbers plus “payment codes corresponding to different services that its staff
provided to Yarushka, such as ‘Individual Therapy’ and ‘Family Therapy’” to
get reimbursed. Escobar, 579 U.S. at 184. By typing these two codes, Arbour
was telling the State that a “Social Worker, Clinical” provided a patient with
“Individual Therapy.” The State would then reimburse Arbour’s services with
Medicaid funds.
Yarushka’s parents sued Universal Health under the False Claims Act.
They alleged “that Universal Health (acting through Arbour) submitted
reimbursement claims that made representations about the specific services
provided by specific types of professionals, but that failed to disclose serious
violations of regulations pertaining to staff qualifications and licensing
requirements for these services,” id. at 184-85, and “[t]he Massachusetts
Medicaid program, unaware of these deficiencies, paid the claims.” Id.
After the district court dismissed the claim, and the circuit court
reinstated it, the Supreme Court granted cert to resolve a split “over the
validity and scope of the implied false certification theory.” Id. at 186.
2. The holding: The Court started with its holding: “When, as here, a
defendant makes representations in submitting a claim but omits its violations
of statutory, regulatory, or contractual requirements, those omissions can be a
basis for liability if they render the defendant’s representations misleading
with respect to the goods or services provided.” Id. at 187. The Court then
explained how it got there.
Because Congress did not define “false” or “fraudulent” in the FCA, the
Court looked to the common-law meaning of fraud, and from there, the common
law rule of half-truths:
10
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 11 of 44
Id. at 188-89. As you can see, the payment codes told the state Medicaid office
that Arbour provided Yarushka with specific counseling services. That was
true information, hence the phrase “half-truth.” The untrue half—i.e., the half
that made Arbour’s request actionable—was the follow-up statement that
Arbour didn’t make: Our staff wasn’t qualified to treat Yarushka. The Court
said Relators’ claim was viable because it pleaded both the truth (the codes)
and the lie (the failure to disclose noncompliance): “By using payment and
other codes that conveyed this information without disclosing Arbour’s many
violations of basic staff and licensing requirements for mental health facilities,
Universal Health’s claims constituted misrepresentations.” Id.
The court recounts the entire holding to make this point: the Court ended
its analysis by finding that Relators could prove the true half of Arbour’s
payment request—i.e., the counseling services Arbour employees provided—by
presenting evidence that Arbour used “payment and other codes that conveyed
11
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 12 of 44
this information.” Id. Only then, right after saying that “payment and other
codes” can prove the goods and services provided, did the Court articulate the
two-condition test for future cases that the BJCTA hangs its hat on here:
Now having the full context of this statement, we know that Escobar does
not require Relators to show the defendant typed out a detailed description of
the goods or services provided to prove their case. Codes that correspond to
general categories “such as ‘Individual Therapy’ and ‘Family Therapy.’” id. at
184, can be enough, as long as the codes provide enough information about the
services provided to make the unspoken noncompliance with statutes or
regulations “a misleading half-truth.” Id. at 190.
That means all Relators had to show here was that Walker’s use of the
grant number and amount requested conveyed enough information to notify
the FTA about the type of services Strada provided, thus making the BJCTA’s
failure to admit noncompliance with the Brooks Act a misleading half-truth.
A reasonable juror could have found that Walker told the FTA about the
services Strada provided each time she typed the grant numbers and amount
requested into the ECHO system. It’s not a close question. The FTA not only
knew what services each grant was compensating, the FTA helped Strada and
the BJCTA write the task orders—and even dictated some of the tasks. The
court uses Grant AL-03-0058 and Task Order 12 as examples.1
1 The BJCTA requested funds from Grants AL-03-0058, AL-03-0077 and AL-95-X007 to
reimburse Strada’s work on Task Orders 7, 7a, 7b, 12 and 24.
12
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 13 of 44
1. The facts: The BRT project was a collaborative effort between the
City, the BJCTA, the FTA, and others. Once a quarter (at least), Murdock and
representatives from the City, Strada, and others would drive to Atlanta to
meet with the FTA “and go over what the time line was for whatever task order
we were about to undertake.” (Trans. 322). According to Murdock, “Strada
would lead the presentations to the Federal Transit Administration, and they
would have a professional notetaker there taking notes as to what were the
next steps in this project and how the money would be spent.” (Id.).
Among other things, the FTA told the BRT team that someone had to
produce an environmental “NEPA” study and “Historic Property and Cultural
Resources Inventory.” (Trans. 323-24). The BJCTA agreed to manage and fund
those tasks. (See id.; Tr. Ex. 19).
In February 2016, Murdock asked the FTA to repurpose two grants for
use on the BRT Project. Relevant here, Murdock asked the FTA to allow the
BJCTA to use Grant AL-03-0058 to fund the NEPA process under Task Order
12. Here’s a portion of that letter to the FTA:
(Tr. Ex. 13). As you can see, Murdock told the FTA that Grant AL-03-0058
would be used “to cover expenses associated with the technical assessments
and analysis of the environmental document”—i.e., the “NEPA process” in
13
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 14 of 44
The FTA promptly responded that “there are no impediments with the
use of the 5309 funds for the preliminary engineering and NEPA work. The
proposed activities noted in your letter for use of the remaining funding in AL-
03-0058-02 are eligible.”2 (Tr. Ex. 14).
Strada and the BJCTA worked with the FTA on the NEPA process and
Historic Property and Cultural Resources Inventory (i.e., Task Order 12) for
the next few months. Here’s how Murdock described the process:
A: But I can add that the FTA, at every step, was aware of the
task orders that we were executing with Strada because we
had to go over them quarterly in Atlanta during the
meetings with the FTA.
(Trans. 330-31).
The BJCTA summarized this back-and-forth with the FTA in its monthly
activity summaries. (Tr. Ex. 41). Here’s an example from December 2016 that
reflects the relationship between Strada and the FTA:
2The term “5309 Funds” refers to 49 U.S.C. § 5309, which gives the FTA authority to issue
grants for fixed guideway projects. Grant AL-03-0058 was a “New Starts” 5309 project.
14
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 15 of 44
(Id., p.50).
Strada would submit invoices to Murdock for its work. (See, e.g., id., p.
49 (Strada’s December 2016 invoice for Task Order 12)). Once the BJCTA paid
Strada, Walker would calculate 80% of the amount paid (i.e., the federal share
of the project) and identify the appropriate grant. (Trans. 580). Walker would
then log into the ECHO system and type the grant number and amount
requested to draw down the appropriated funds. (Trans. 582-84). Walker then
received a receipt like this:
Looking at Relators’ evidence as a whole, the jury could have found that
the FTA knew what services were being reimbursed when Walker submitted a
payment request through the ECHO system. Relator’s best evidence on this
point is Walker’s testimony that the FTA knew which services were being
reimbursed when she typed the grant number into ECHO:
A: No.
A: No.
16
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 17 of 44
(Trans. 610) (highlight added). By Walker’s own admission, when she typed in
the grant number, she was “explaining to the FTA” that the BJCTA was
seeking funds to pay for the “particular scopes or activities” in the grant
application. She couldn’t seek reimbursement for any other goods or services.
That testimony alone is enough to allow the jury to find that the BJCTA
made representations about the goods and services provided. But as the court
has detailed, the jury heard much more. Relators provided documents that
showed the FTA approved the use of the grants for the specific purposes being
compensated. Murdock testified that “the FTA, at every step, was aware of the
task orders that we were executing with Strada.” (Trans. 330-31). And
Murdock testified that the FTA ordered some tasks, knowing how they would
be funded. Combined, this evidence would allow a reasonable juror to find that
the FTA knew what goods and services Strada provided because the FTA was
intimately involved in—and sometimes directed—the process.
In Escobar, the Supreme Court found that a simple payment code for
“Individual Therapy,” 579 U.S. at 184, was enough evidence of the counseling
services Arbour provided to make a viable claim. The combination of Walker’s
testimony, Murdock’s testimony, the letters between the BJCTA and the FTA,
and the BJCTA’s monthly activity summaries easily clears that low bar.
17
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 18 of 44
31 U.S.C. § 3729(b)(1).
The BJCTA argues that Relators failed to provide evidence that the
BJCTA knowingly failed to disclose its violations of the Brooks Act because (a)
the BJCTA didn’t violate the Brooks Act, and (b) if it did, the BJCTA didn’t
know it was violating the Brooks Act.
Relators argue that they proved that the BJCTA violated the Brooks Act
and that either (a) the BJCTA knew it had violated the Brooks Act or, if it
didn’t know, (b) it acted in reckless disregard of its violation.
The court divides its discussion into two parts. First, the court decides
whether Relators provided enough evidence to support a finding that the
BJCTA violated the Brooks Act. Second, the court decides whether Relators
provided enough evidence to support a finding that the BJCTA either knew it
violated the Brooks Act or recklessly disregarded the violation.
The court interpreted the Brooks Act in its summary judgment opinion
and adopts that analysis here. (See Doc. 206, pp. 20-27). As it did then, the
court starts with the full text of Title 40, Sections 1103 and 1104:
18
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 19 of 44
19
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 20 of 44
With these provisions, Congress created a three-step process that the BJCTA
had to use when contracting for A&E services:
40 U.S.C. § 1103(c) (Step 1); § 1103(d) (Step 2); § 1104(b) (Step 3). Section
1103(b) required this process “[f]or each proposed project.”
For Step One, Relators provided evidence the BJCTA released RFQ 15-
17 to solicit A&E firms (Tr. Ex. 95), and five firms submitted responses.
20
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 21 of 44
2 Wendel 349
(Tr. Ex. 24, p. 3). Relators provided evidence that the BJCTA Board passed a
resolution that allowed Murdock to sign a contract with the three top ranked
firms: WRA, Wendel, and Strada. (Tr. Exs. 93, 113, 115, 117). In its resolution,
the Board said that it was authorizing those three firms “based on the FTA
Circular 4220.1F guidance and the evaluation committee’s ranking of the top
three firms.” (Tr. Ex. 93, p. 1).
So far, so good.
The court finds that this evidence was sufficient to allow a reasonable
juror to find that the BJCTA violated the Brooks Act. Relators presented
enough evidence to allow a reasonable juror to find that the BJCTA selected
21
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 22 of 44
WRA as the “most highly qualified firm selected under section 1103,” and that
the BJCTA did not negotiate Task Orders 7, 7a, 7b, 12, or 24 with WRA before
awarding them to Strada. Those two facts combined result in a Brooks Act
violation.
22
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 23 of 44
While the parties don’t discuss it, the Federal Acquisition Regulations
(“FAR”) would have allowed the BJCTA’s “selection authority” to overrule the
independent committee’s rankings before signing contracts. Here’s what FAR
required the independent committee to do:
3For example, the BJCTA quote about “broad discretion” comes from Section 22:5 of
Government Contract Awards, titled “selection criteria.” That section discusses the selection
criteria listed in Federal Acquisition Regulation 36.602-1. Government Contract Awards
discusses “negotiation and award” process, which Relators based their case on (i.e., Step 3),
five sections later. See 2 Government Contract Awards: Negotiation and Sealed Bidding
§22:10.
23
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 24 of 44
(a) Review the current data files on eligible firms and responses to
a public notice concerning the particular project (see 36.603).
(c) Hold discussions with at least three of the most highly qualified
firms regarding concepts and the relative utility of alternative
methods of furnishing the required services.
48 C.F.R. 36.602-3. The Federal Regs then allowed the BJCTA to rearrange
the independent committee’s ranking order, if it followed this process:
(a) The final selection decision shall be made by the agency head
or a designated selection authority.
(c) The selection authority shall not add firms to the selection
report. If the firms recommended in the report are not deemed to
be qualified or the report is considered inadequate for any reason,
24
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 25 of 44
the selection authority shall record the reasons and return the
report through channels to the evaluation board for appropriate
revision.
(Tr. Ex. 93, p. 3). But they did not recommend that the Board re-rank the firms
and provided no written explanation of the reason for preferring Strada as
required by the FAR. As a result, when the Board passed the resolution that
authorized Murdock to sign contracts with the top three firms, it used the
independent committee’s ranking—because that’s the only ranking it had:
B. Knowing violation
1. Actual Knowledge: The Master Agreement between the FTA and the
BJCTA required the BJCTA to follow the Brooks Act and FTA Circular 4220.1.
(Tr. Ex. 11, § 16(a)(3)). And the Board’s Resolution that gave Murdock the
authority to sign contracts with Strada, Wendel, and WRA said that the
Board’s decision was “based on the FTA Circular 4220.1F and the evaluation
committee’s ranking to top-three firms[.]” (Tr. Ex. 93, p.1). So the BJCTA knew
it had to comply with the Brooks Act.
26
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 27 of 44
The question is whether the BJCTA knew it was violating the Brooks
Act when it awarded Strada Task Orders 7, 7a, 7b, 12, and 24 without
negotiating with any other firms. The timeline of events suggests it did.
The Board voted to allow Murdock to sign contracts with Strada, Wendel,
and WRA on October 28, 2015. (Tr. Ex. 93). In its resolution, the Board said
that it based its decision on FTA Circular 4220.1F, which says that
negotiations start “only with the most qualified” firm:
FTA Circular 4220.1F, Ch. VI, ¶ 3(f)(3). Yet Murdock signed the contract with
#3-ranked Strada on October 1st—27 days before the Board gave her authority
to contract with anyone, six months before she signed a contract with #2-
ranked Wendel, and eight months before she signed a contract with #1-ranked
WRA. (Tr. Exs. 113, 115, 117).
27
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 28 of 44
A: I don’t recall who directed me. I’m just saying that I didn’t
get the official – there was a special called meeting in
October that put me in the position, and I reported to the
board and board chairman.
(Trans. 141-42). A reasonable juror hearing this testimony could have found
that the BJCTA Board or its attorneys told Murdock to sign a contract with
Strada before giving her the authority to do so and before she talked to WRA
or Wendel about its ability to do BRT-related work. Based on that finding, the
same juror could have agreed with Relators’ theory that the BJCTA decided
months earlier to assign all tasks to Strada as the City’s pick for BRT Project
Manager, and it posted RFQ 15-17 and assembled an independent committee
to rank the firms’ responses as a ruse to fake compliance with the Brooks Act.
The court finds that Relators presented enough evidence to support its
theory that the BJCTA knew it was violating the Brooks Act, and thus
presented enough evidence to support the jury’s finding of scienter.
2. Reckless disregard: Assuming instead that the BJCTA did not know
it was violating the Brooks Act, the court finds that Relators presented enough
evidence to support a finding that the BJCTA recklessly disregarded its
noncompliance with the Brooks Act when the BJCTA certified to the FTA that
it had complied with the requirements of the Master Agreement.
28
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 29 of 44
Yates v. Pinellas Hematology & Oncology, 21 F.4th 1288, 1303 (11th Cir. 2021).
If gross negligence is enough, then a corporate admission that the BJCTA
handled its known legal duty with gross incompetence is enough to support a
finding of reckless disregard.
—
In sum, Relators provided enough evidence to allow a reasonable juror
to find that the BJCTA had actual knowledge of its noncompliance with the
Brooks Act, or alternatively, that the BJCTA was reckless in not knowing. So
the court denies the BJCTA’s motion for judgment on the scienter element.
3. Materiality
The question is whether the Government “in fact paid for claims that it
would not have paid had [the requestor] been truthful.” Yates, 21 F.4th at 1305.
One way to gauge whether the Government would have paid if it knew of the
violation beforehand is to gauge its response after discovering a violation. As
the Supreme Court put it, “if the Government regularly pays a particular type
of claim in full despite actual knowledge that certain requirements were
violated, and has signaled no change in position, that is strong evidence that
the requirements are not material.” Escobar, 579 U.S. at 195. On the flip side,
evidence that the Government regularly demands repayment when it discovers
a violation would be strong evidence of materiality.
Below, the court recounts Relators’ evidence that the FTA demands
repayment of grant funds when it discovers similar statutory or regulatory
violations.
29
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 30 of 44
Karen Jacobs served as the BJCTA’s financial director from 2015 to 2018.
Jacobs agreed that “if you don’t follow proper procurement rules and didn’t do
what you were supposed to do when it came to procuring federal grants, that
the funds would have to be paid back to the FTA[.]” (Trans. 541).
That three BJCTA employees believed the FTA would require the
BJCTA to pay the grant funds back if the BJCTA violated the Brooks Act is
strong evidence of materiality. Martin’s statement that it was “common
practice” for the FTA to take its money back alone was enough to let the jury
decide. But there’s more.
2. The City’s Repayment: Soon after Relators filed their complaint, the
FTA investigated the City’s use of grant funds to pay Strada. When the City
failed to produce documents that showed compliance with FTA Circular
4220.1F, the FTA demanded the City return “[t]he total amount of Federal
dollars expended on the non-compliant Federal contract” ($261,854), plus
interest. (Tr. Ex. 61, p. 6). This is strong evidence that the FTA would not have
paid out grant funds to either the City or the BJCTA if the FTA had known
that neither entity complied with the Brooks Act and FTA regulations when
selecting Strada. See FTA Circular 4220.1F, Ch. VI, ¶ 3(f)(3) (instructions for
compliance with the Brooks Act).
30
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 31 of 44
3. The FTA did not demand its money back after the 2019
Triennial Review of the BJCTA’s procurement files; and,
4. The FTA still awards grants to the BJCTA, despite this lawsuit.
(Doc. 239, p. 17-20). The court agrees that Facts #2, #3, and #4 weigh against
materiality. But the jury heard evidence about all four facts and found that
Relators’ evidence had more weight.4 It is not the court’s role to second guess
the jury’s weighing of the evidence. The court’s role is to determine whether
Relators presented enough evidence to support the jury’s verdict. As explained,
they did. So the court denies the BCJTA’s request for judgment on the
materiality element.
4The parties hotly debated the relevance and impact of the FTA’s actions after Relators filed
their complaint under seal (Facts #2, #3, and #4). After consulting the parties (Trans. 921-
22), the court instructed the jury about the Government’s right to intervene in Relators’ case
and its choice not to. (Doc. 230, p. 5). So the jury was allowed to consider both sides’
arguments about how the FTA’s actions weighed for and against materiality.
31
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 32 of 44
The court asked the jury two questions about damages, and the jury gave
these answers:
Relators ask the court to set aside the second number because, they say, the
Federal Government received no benefit from Task Orders 7, 7a, 7b, 12 and 24
as a matter of law. (Doc. 240). The United States agrees. (Doc. 261, p. 5).
The court tackles the issue in four steps. First, the court explains how
Relators preserved the issue. Second, the court explains the unsettled nature
of the law on FCA damages. And with its final two steps, the court applies the
Eleventh Circuit’s published and unpublished tests for damages.
The BJCTA argues that Relators waived their right to argue that the
Government did not benefit from Strada’s work in a Rule 50(b) motion because
Relators did not first make this argument in a Rule 50(a) motion.
In short, before the court submitted the case to the jury, Relators asked
the court to declare, as a matter of law, that the Government did not benefit
from Strada’s work. Relators make the same argument based on the same
caselaw here. As a result, Relators preserved the issue. Fed. R. Civ. P. 50(a)(2);
see also Etienne v. Inter-County Sec. Corp., 173 F.3d 1372, 1374 (11th Cir. 1999)
(counsel’s statement during trial asking the court to enter judgment was
enough to preserve the issue for appeal, even though he “did not expressly
make a motion for judgment as a matter of law”).
The circuit court has applied two equations. In its published opinions,
the court has measured damages by finding “the difference between what the
government paid and what it would have paid had the defendant’s claim been
truthful and accurate.” Id.; see also United States v. Killough, 848 F.2d 1523,
1532 (11th Cir. 1988) (“Case law indicates the measure of damages is generally
determined to be the difference between what the government actually paid on
the fraudulent claim and what it would have paid had there been fair, open
and competitive bidding”).
33
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 34 of 44
United States v. Anghaie, 633 F. App’x 514, 518 (11th Cir. 2015) (highlight
added); (citing United States v. Sci. Applications Int’l Corp., 626 F.3d 1257
(D.C. Cir. 2010); United States ex rel. Longhi v. United States, 575 F.3d 458,
473 (5th Cir. 2009)).
34
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 35 of 44
the court finds that the BJCTA presented enough evidence to support the jury’s
finding of fact that Strada’s work was worth $1,078,467.74.
Now the court decides whether, as a matter of law, that amount can be
subtracted from the Government’s damages using either the base equation
announced in the published Killough and Yates opinions or the modified
equation announced in the unpublished Anghaie opinion.
Applying the published, base equation is easy. For the first number, the
parties agree with the jury’s finding that the Government paid $1,438,467.74
for Task Orders 7, 7a, 7b, 12 and 24. And the second number must be $0
because, when the jury found that Relators proved materiality, it necessarily
found that the Government would have paid nothing had it known that the
BJCTA violated the Brooks Act. See Yates, 21 F.4th at 1305 (materiality shown
if the Government “in fact paid for claims that it would not have paid had [the
requestor] been truthful.”). As a result, applying the test from the Circuit’s
published opinions to the jury’s fact findings means that the Government’s
damages are the full amount of the funds paid ($1,438,467.74) minus zero.
35
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 36 of 44
As you can see, Congress forbid the United States Government from receiving
a tangible benefit—i.e., “direct benefit or use”—from grant agreements. 31
U.S.C. § 6304(1). The United States Government can only receive direct,
tangible benefits from procurement contracts, 31 U.S.C. § 6303(1), which come
with their own set of rules and regulations absent here.
The only benefit the United States could have received from its grant
agreements with the BJCTA was an intangible benefit—i.e. “to carry out a
public purpose of support or stimulation authorized by a law of the United
States.” 31 U.S.C. § 6304(1). Which, of course, makes sense because the
Federal Government does not own Birmingham’s Bus Rapid Transit system.
36
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 37 of 44
Relators and the United States point to the Brooks Act and its policy
statement: “The policy of the Federal Government is to publicly announce all
requirements for architectural and engineering services and to negotiate
contracts for architectural and engineering services on the basis of
demonstrated competence and qualification for the type of professional
services required and at fair and reasonable prices.” 40 U.S.C. § 1101. They
argue that the BJCTA’s payment of Strada deprived the Government of the
benefit it bargained for—i.e., a contract with the most highly qualified firm.
The court agrees with Relators and the United States that the BJCTA’s
violation of the Brooks Act vitiates any intangible benefit the Government
would have received from Strada’s work, for three reasons.
First, giving the BJCTA credit for Strada’s work flouts the jury’s finding
of materiality. The circuit court recently made this point in Yates:
37
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 38 of 44
Given what Escobar held, ruling that the United States did not
incur damages when it in fact paid for claims that it would not
have paid had they been truthful is difficult to square with a
finding that a false statement or representation is material.
Indeed, Pinellas’ argument ignores the implicit, necessary
conclusion of the jury’s materiality finding—that CLIA
certification is a considerable part of what the United States
expected and bargained for.
Yates, 21 F.4th at 1304-05. The same is true here. The BJCTA asks the court
to find that the Government benefitted from “approximately 75% of the total
amount of BJCTA’s reimbursement from the FTA,” (doc. 242, p. 21), even
though the jury found that the Government would have paid 0% of the total
amount if it knew about the noncompliance. Those facts cannot be squared.
Second, the Eleventh Circuit focused on the violated policy when judging
the Government’s intangible benefit in Anghaie. In that case, the defendant
was a professor who, along with his wife, fraudulently won four contracts for
research funded by grant programs. 633 Fed. Appx at 515. At sentencing for
their crimes, the court found that the Anghaies “provided valuable innovative
research” to the Government. Id. at 517. Seizing on that finding, the Anghaies
argued in their civil FCA case that they fulfilled Congress’ policy of awarding
these funds “to undertake and to obtain the benefits of research and
development in order to maintain and strengthen the competitive free
enterprise system and the national economy.” Id. at 518 (quoting 15 U.S.C. §
638(a)). Yet the Eleventh Circuit found that the Government received no
intangible benefit from the Anghaies’ work because the Anghaies deprived the
United States of another intangible benefit announced by Congress:
“award[ing] money to eligible deserving small businesses.” Id. at 518. So the
circuit court affirmed the district court’s award of full damages.
38
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 39 of 44
The same is true here. In the same chapter that contains Congress’ policy
statement about developing and revitalizing public transportation systems, 49
U.S.C. § 5301(a), Congress requires grant recipients to comply with the Brooks
Act. See 49 U.S.C. § 5309(c)(1)(E) (requiring grantees to comply with 39 U.S.C.
§ 5325, which in turn requires compliance with the Brooks Act when awarding
A&E contracts, see 49 U.S.C. § 5325(b)(1)). The BJCTA’s former executive
director, financial director, and procurement manager all testified that they
knew the FTA would demand its money back if the BJCTA violated the Brooks
Act. In other words, they expected no credit from the FTA for Strada’s work if
the BJCTA broke the rules. And based on the jury’s verdict on materiality, they
would have received no credit.
To sum up, the court finds as a matter of law that the United States
Government did not benefit from Strada’s work on Task Orders 7, 7a, 7b, 12,
and 24 because the BJCTA violated the Brooks Act. That finding, combined
with the jury’s finding that the FTA would not have given the BJCTA the grant
monies if it knew about the BJCTA’s noncompliance, means that the damage
suffered by the United States Government is the full amount of money paid,
regardless of which Eleventh Circuit equation is applied. The court will thus
grant Relators’ renewed motion for judgment as a matter of law. (Doc. 240).
39
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 40 of 44
Finally, the court must impose a civil penalty against the BJCTA, on top
of treble damages. 31 U.S.C. § 3729(a)(1). Adjusted for inflation, the current
penalty range is $13,508 to $27,018 per violation. 28 U.S.C. § 2461 (requiring
adjustment for inflation); 28 C.F.R. § 85.5(a); table 1 column 7 (adjusted rate
for False Claims Act violations imposed after January 30, 2023).
1. Number of Violations
• The BJCTA drawing down funds from the ECHO system; and,
Only one of these—i.e., the BJCTA drawing down funds from ECHO—involves
the BJCTA presenting a claim for payment or approval to the United States.
So this is the only event that qualifies as a punishable violation. See Killough,
848 F.3d at 1533 (“each separate fraudulent submission by a defendant
demanding payment from the government is a ‘claim.’”).
40
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 41 of 44
Congress did not list factors for courts to consider when determining the
penalty amount; Congress left it to the courts. This court accepted three rounds
of briefing on penalties, in which the parties named more than a dozen factors
for the court to consider. The court also held oral argument to allow the parties
to argue these factors. The court has considered the factors named by the
parties, and the parties’ written and oral arguments.5 Based on everything it
heard, the court imposes a penalty at the lower end of the statutory range:
$14,000 per violation. See 28 C.F.R. § 85.5(a) (setting a range of $13,508 to
$27,018 per violation). The court discusses the factors that weighed most
heavily in its decision to impose a lower-end penalty below.
Again, the jury found that the BJCTA knowingly submitted false claims,
but acquitted executive director Murdock, Strada, and Strada’s owner Watters
of any wrongdoing. The best way to read this verdict consistent with the
evidence is that the BJCTA was stuck between a rock and a hard place. The
BJCTA had to honor two things: (1) the City of Birmingham’s choice of Strada
to be the program manager for the BRT project and (2) its obligation to comply
with the Brooks Act and FTA Circular 4220.1F when assigning A&E projects.
The BJCTA was placed in a bind when the independent committee ranked the
City’s disfavored firm (WRA) over the City’s chosen firm (Strada). Rather than
follow the law and regulations by first negotiating A&E projects with WRA,
the BJCTA Board decided to sign the top three firms so that Strada could get
all the work. The Board told its newly minted director (Murdock) what to do,
and she signed off on Strada’s truthful invoices to seek federal funds.6
5The court considered these factors: (1) Does the damage award make the government whole,
(2) did the defendant cooperate with any investigation, (3) was the defendant’s conduct
particularly egregious, (4) were the violations pervasive, (5) what was the defendant’s level
of scienter, (6) what is fair, (7) did the defendant accept responsibility, (8) how serious was
the defendant’s misconduct, (9) how much did the investigation cost, (10), harm to the public,
(11) the defendant’s ability to pay, (12) comparison of penalties to damages, (13) the need for
deterrence, (14) was the federal agency vindicated, and (15) the totality of circumstances.
(See Doc. 251, pp.7-8; Doc. 254, pp. 3-4; Doc. 256, p. 5; Doc. 258, p. 4-5; Doc. 261, p. 8-9).
6The jury found that Murdock didn’t know she was submitting false claims and that Strada
and Watters did not create any false records. (Doc. 231).
41
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 42 of 44
That the BJCTA Board or counsel told Murdock to sign a contract with
Strada four weeks before the Board resolved to sign contracts with the top
three firms suggests that the BJCTA knowingly—not negligently—chose to
follow the City’s directive over the law’s requirement. That’s egregious and
warrants a higher penalty.
But several factors temper the egregiousness. First, only three of the first
33 task orders required Brooks Act compliance, making it a small part of the
bigger picture. Second, no one at the BJCTA stood to financially gain from the
decision to let Strada do the A&E work. Third, there was no evidence that
Strada inflated its costs to pocket extra money on A&E projects.
In short, the egregiousness factor prevents the court from imposing the
minimum penalty. But this factor is tempered by the circumstances, and it is
outweighed by the remaining factors the court discusses below.
As discussed, the BJCTA must pay the full amount of grant funds that
it used to pay Strada as damages—about $1.44 million. This damage award
fully reimburses the Government’s tangible financial interest.
The BJCTA has to pay another $2.88 million because the FCA requires
the court to impose “three times the amount of damages which the Government
sustains[.]” 31 U.S.C. § 3729(a). The court finds that this extra $2.88 million
fully reimburses the Government’s intangible interest in promoting
compliance with laws and regulations that govern awards of government-
funded contracts.
In short, assuming the higher courts agree that the proper amount of the
Government’s damages is the full amount paid, this court finds that the
imposition of treble damages makes the government whole. So this factor
weighs heavily in favor of a lower-end penalty.7
7If
higher courts subtract the $1.078 million value of Strada’s work off of the base damage
amount, then this factor would instead weigh in favor of an increased penalty on remand.
42
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 43 of 44
C. Deterrence
Penalties aside, this case will cost the BJCTA a lot of money: over $4.3
million in damages, plus an untold amount of litigation expenses, costs, and
attorney’s fees for both sides. See 31 U.S.C. § 3730(d)(2) (requiring an FCA
defendant to pay to Relators “an amount for reasonable expenses which the
court finds to have been necessarily incurred, plus reasonable attorneys’ fees
and costs”). The court finds that these expenses alone provide a healthy
deterrent against future violations of the Brooks Act and FCA, so a lower-end
penalty is warranted.
D. Public Harm
To sum up, the court finds that the BJCTA must pay $14,000 for each of
its 22 violations. So the court will grant in part and deny in part Relators’
motion for penalties (doc. 253) and impose a penalty of $308,000.
8 The BJCTA has turned over all board members and the executive director since Relators
filed their complaint. Only Walker (the grants director) remains, and the evidence suggests
Walker was innocent of any wrongdoing.
43
Case 2:18-cv-00567-CLM Document 274 Filed 03/07/23 Page 44 of 44
CONCLUSION
For these reasons, the court rules on the post-trial motions as follows:
• The court denies the BJCTA’s Rule 50(b) motion (doc. 239), which
means the jury’s verdict against the BJCTA on Count III stands;
• The court grants Relators’ Rule 50(b) motion (doc. 240), which means
the base damage amount for Count III is $1,438,467.74 and results in
a treble damage award of $4,315,403.22; and,
• The court grants in part and denies in part Relators’ motion for
civil penalties (doc. 253) and penalizes the BJCTA $14,000 for each of
its 22 FCA violations, resulting in a penalty award of $308,000.
_________________________________
COREY L. MAZE
UNITED STATES DISTRICT JUDGE
44