All examinations and stress relieving activities have to complete before testing.
The Workshop Forman shall ensure all bolts and its nut had tightened.
Barricade must be limited at the testing area with display signboard with “KEEP AWAY
HYDROTEST IN PROGRESS”.
The QC inspector shall send the notification to Client before official testing.
The pressure test follows project specification and approval drawings or 1.5 times of the
design pressure.
The QC inspector shall monitor the testing process and verify that there is no leakage or
visual distortion during or upon completion of test.
Upon completion of the test, test medium shall be drained and unbolt flange joint.
All internal pipe spools shall clean and flush with pressurized water, then drying out by
dried air
If leakage found on products or product welds, their location shall be marked and
forward the report to QC Engineer for investigation before re-testing.
If leakage found on flanged joints, threaded joints shall rectify before re-starting test.
1.12 DOCUMENTATIONS
b. Job number
f. Date of test
g. Tag name or piping spool number
h. Test medium
i. Test pressure
j. Test temperature
k. Test results