HARADH AND HAWIYAH FIELD GAS COMPRESSION PROJECT

HYDROTEST CHECKLIST
0130-02-091-PD-00013-tmp18
Preparation HYDROTEST activities PERMIT Nº:
Test packet Nr:…………………………………………………………………………………………………………….. Date: Time start/end:
WORK PERMITS OK NO NA
Work Permit Available in the test area
Work permit to be signed after this verification
SAFETY POINTS OK NO NA
Size (thickness') and location of all test blinds and including those required at instrument connections e.g. orifice flanges.
Location and range of pressure gauges to be used. Minimum (2) Calibrate gauges enquired,
All blinds in the test pack used must withstand the maximum test pressure.
All test equipment and tool used must withstand the maximum test pressure, and certificates available.
Joints in the system which would be subjected to failure or flexible tubing shall be restrained during the test to prevent personnel injury.
Exclusion zone: the area is barricated as per the Work Permit and signalizated
The system was vented
Mandatory PPEs and face shield or safety googles
Do not allow person who doesn’t have any relation along with the hydrostatic test, to enter the evaluation area. Area to be barricated
All hoses ought to be tied down.
This hydrostatic-pressurizing pump is completed with safety relief device.
Drain valve within the lowest point in order to completely empty the vessel and conduit.
Check the vent out line before assessment and make sure it is not blocked.
TEST SET-UP OK NO NA
First pressure gauge is always visible for pump operator.
Force measurement tools are calibrated and their particular statuses of calibration continues to valid.
Pressure gauges utilised in the test have enough capacity.
Pressure gauges will have to be installed at a suitable location in order that it can be easily read
Each of the temporary tools (such as valve, fitting, hoses, flanges, blind registration, etc) should be
rated more in comparison to the maximum hydrostatic burden.
Isolate other equipments in addition to pipe lines that not include inside hydrostatic test.
Safe practices relief valve is calibrated with PSV Tag number:……………
Many test equipments and tools should be inspected for wear and damage.
Vents are offered and installed this high points to help you vent air. Check the vent out line before assessment and make sure it is not blocked.
With manual pump confirming drawing OK NO NA

With motor-driven pump confirming drawing OK NO NA

RECOMMENDATIONS
Remove all air from the vessel and water line by normal water through vent brand.
Pressurization is usually conducted gradually/slowly.
Start off de-pressurization by beginning gradually the in-take valve. Do the idea slowly.
Tend not to open the drain valve if ever the vent valve if still closed. This is certainly to avoid vacuum condition inside vessel.
Manifold properly supported in a table or stable surface
Bolt tighting must be done without pressure in the line
Drain of the water must be conducted using hoses
Make it possible for no remaining pressure trapped inside the pipe line and also vessel.
CHECKED BY:

Subcontractor Supervisor: ____________________________________ Date:

Contractor Supervisor: _____________________________________ Date: