CAPEX Planning. Business Process With SAP - PS

The document outlines the CAPEX business process timeline and responsibilities. It involves identifying budgeted CAPEX projects, planning the projects, submitting the proposed project list and budget, obtaining approvals, creating the project coding and uploading to SAP, attaching supporting documents, initiating routing for approval, approving projects over 5M PHP, releasing funds, and executing the approved projects. The process spans from the first quarter for identification and planning through to project execution after fund release in the following year. Key steps include project definition, planning, budget submission, approvals from EXCO and functional heads, and setting up the project in SAP for routing, approval and fund release.

Uploaded by

Marijune Letargo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
1K views3 pages

CAPEX Planning. Business Process With SAP - PS

The document outlines the CAPEX business process timeline and responsibilities. It involves identifying budgeted CAPEX projects, planning the projects, submitting the proposed project list and budget, obtaining approvals, creating the project coding and uploading to SAP, attaching supporting documents, initiating routing for approval, approving projects over 5M PHP, releasing funds, and executing the approved projects. The process spans from the first quarter for identification and planning through to project execution after fund release in the following year. Key steps include project definition, planning, budget submission, approvals from EXCO and functional heads, and setting up the project in SAP for routing, approval and fund release.

Uploaded by

Marijune Letargo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
  • CAPEX Business Process Overview - Page 1
  • CAPEX Business Process - Continuation 1
  • CAPEX Business Process - Continuation 2

CAPEX Business Process

Responsible
Time Process Flow T-Code Documents / Remarks
Person

Normal BUDGETED
Project Definition
1st - Identify and propose
Project Manager /
2nd Quarter CAPEX list (for PDP)
Proponent
Jan -June

Project Planning - Request for Sourcing (RFS) or Tender Document.


- Conduct PMA (Phase I & II) meeting.
1st - Technical, Commercial and
Project Manager / Financial data gathering
2nd Quarter
Proponent Data Gathering
Jan -June

- Conduct PMA Phase I & II meeting


- Investment Cost Estimation (ICE) based on actual
Project Executive Summary (PES), budgetary or firm offer/s from supplier / contractor
1st - Investment Cost Estimation (ICE) - CVT document must be attached if required
Project Manager /
2nd Quarter and PMA Lite (Phase I & II) - PMA lite not needed for Replacament CAPEX
Proponent
Jan -June

CAPEX Manager Submit Proposed Project and Budget List


Mid-August to
Plant Manager / (3yr plan) PDP to MTP
late Sept
Business Unit Head

Endorse Budget CAPEX List to EXCO and waits


Aug 18* for their Approval
Region
- Sept

No Postpone
Approve
Sept Region / EXCO / Defer

Yes Project Def and WBS level 1 created for Projects


with Cash out / Spending on the first year
CAPEX Admin and Create Project coding Mask / WBS Code and Upload - Project Release is blocked
4th Quarter CJ20N / LSMW - Mass upload & Overall Budget is Uploaded
HEAB Projects in SAP PS.

Prerequisite for Routing and Approval


PES, ICE, RFS, Reallocation Form
CAPEX Manager / Attach supporting documents in Project Definition Level
4th Quarter Project Manager and Creation of Activities (PR) CJ20N

4th Quarter No
Complete

Yes
- CAPEX Admin to route only those with
complete supporting documents attached in
4th Quarter CAPEX Admin Initiates Routing Process ZPS_0007 Project Def level

Cost > Php 5.0 Mio - Budget Controller inputs breakdown of budget in
CJ30 as necessary based on the proposed and based
on what was approved in the PES / ICE

Budget Controller,
4th Quarter Functional Head, Approve in CJ20N
CEO* SAP-PS

Fund Release
Note that Fund Release will not be possible if Project
has not secured or completed Project Approval up to
Approve Fund Release FH / CEO
Jan of Budget in SAP-PS
CFA for all budgeted CAPEX CJ32
year

Project Execution - Project Release enables AUC to be generated


CAPEX Manager /
Enforce Project and Network Release CJ20N
after fund release Maintenance
WBS-all
Manager /

Jan of Budget Procurement,


year Purchasing Process

Boxes in blue require SAP PS


CAPEX Business Process
ngayon lng meron long lead time kasi hindi nakaplan last year

Responsible
Time Process Flow T-Code Documents / Remarks
Person

Normal Long lead time BUDGETED


Project Definition
1st - 1st - Project Manager / Identify and propose
2nd Quarter 2nd Quarter Proponent CAPEX list (for PDP)

Project Planning - Request for Sourcing (RFS) or Tender Document.


- Conduct PMA (Phase I & II) meeting.
Technical, Commercial and
1st - 1st - Project Manager / Financial data gathering
2nd Quarter 2nd Quarter Proponent Data Gathering

- Conduct PMA Phase I & II meeting


- Investment Cost Estimation (ICE) based on actual
Project Executive Summary (PES), budgetary or firm offer/s from supplier / contractor
1st - 1st - Project Manager / Investment Cost Estimation (ICE) - CVT document must be attached if required
2nd Quarter 2nd Quarter Proponent and PMA Lite (Phase I & II) - PMA lite not needed for Replacament CAPEX

Equivalent to Midterm Plan (MTP)

CAPEX Manager Submit Proposed Project and Budget List


Mid-August to
July Plant Manager / (3yr plan) based on PDP
late Sept
Business Unit Head

Project Def and WBS level 1 created for Projects


with Cash out / Spending on the first year
3rd Quarter CAPEX Admin and Create Project coding Mask / WBS Code and Upload - Project Release is blocked
4th Quarter CJ20N - Mass upload & Overall Budget is Uploaded
(July) HSEA Projects in SAP PS.

Prerequisite for Routing and Approval


PES, ICE, RFS, Reallocation Form
CAPEX Manager / Attach supporting documents in Project Definition Level
4th Quarter 3rd Quarter Project Manager and Creation of Activities (PR) CJ20N

4th Quarter 3rd Quarter No


Complete

Yes
- CAPEX Admin to route only those with
complete supporting documents attached in
4th Quarter 3rd Quarter CAPEX Admin Initiates Routing Process ZPS_0007 Project Def level

Cost > Php 5.0 Mio - Budget Controller inputs breakdown of budget in
CJ30 as necessary based on the proposed and based
on what was approved in the PES / ICE
Budget Controller,
4th Quarter 3rd Quarter Functional Head, Approve in CJ20N
CEO* SAP-PS

- T&E to list all projects that have completed approval


process and endorse to Budget Controller cc
Functional Heads, CAPEX Manager / Dept Mgrs
- Approved list will be based only on those projects
Endorse Pre approved Budget CAPEX List to that have completed approval in PS up to FH or CEO
EXCO and waits for their Approval level
- Any project that is not included in this list will be
Aug Aug
considered as UNBUDGETED or any project from the
list that incurs changes in cost will go through Re-
allocation process

No Postpone
Approve
18-Aug 18-Aug EXCO / Defer

Yes
Fund Release
Note that Fund Release will not be possible if Project
has not secured or completed Project Approval up to
Approve Fund Release
FH / CEO
Jan of Budget in SAP-PS
3rd Quarter CFA for all budgeted CAPEX CJ32
year

Project Execution - Project Release enables AUC to be generated


CAPEX Manager /
Enforce Project and Network Release CJ20N
after fund release 4th Quarter Maintenance
WBS-all
Manager /

Jan of Budget
4th Quarter Procurement,
year Purchasing Process

Boxes in blue require SAP PS


CAPEX Business Process

Responsible
Time Per MBantiyan Process Flow T-Code Documents / Remarks
Person

BUDGETED
Project Definition
1st - 1st - Project Manager / Identify and propose
2nd Quarter 2nd Quarter Proponent CAPEX list (for PDP)

Project Planning - Request for Sourcing (RFS) or Tender Document.


- Conduct PMA (Phase I & II) meeting.
Technical, Commercial and
1st - 1st - Project Manager / Financial data gathering
2nd Quarter 2nd Quarter Proponent Data Gathering

- Conduct PMA Phase I & II meeting


- Investment Cost Estimation (ICE) based on actual
Project Executive Summary (PES), budgetary or firm offer/s from supplier / contractor
1st - 1st - Project Manager / Investment Cost Estimation (ICE) - CVT document must be attached if required
2nd Quarter 2nd Quarter Proponent and PMA Lite (Phase I & II) - PMA lite not needed for Replacament CAPEX

CAPEX Manager Submit Proposed Project and Budget List


2nd Quarter Mid-August to
Plant Manager / (2yr plan) based on PDP
(June) late Sept
Business Unit Head

Long lead
time?

Project Def and WBS level 1 created


- Project Release is blocked
CAPEX Admin and Create Project coding Mask / WBS Code and Upload - Mass upload & Overall Budget is Uploaded
3rd Quarter 4th Quarter CJ20N
HSEA Projects in SAP PS.

Prerequisite for Routing and Approval


PES, ICE, RFS, Reallocation Form
CAPEX Manager / Attach supporting documents in Project Definition Level
3rd Quarter 4th Quarter Project Manager and Creation of Activities (PR) CJ20N

3rd Quarter 4th Quarter No


Complete

Yes
- CAPEX Admin to route only those with
complete supporting documents attached in
3rd Quarter 4th Quarter CAPEX Admin Initiates Routing Process ZPS_0007 Project Def level

Cost > Php 5.0 Mio - Budget Controller inputs breakdown of budget in
CJ30 as necessary based on the proposed and based
on what was approved in the PES / ICE
Budget Controller,
3rd Quarter 4th Quarter Functional Head, Approve in CJ20N
CEO* SAP-PS

See Approval Limits for Investments


Pre ordering from Next Year's budget
Secure Pre Approval Proposed CAPEX Project
3rd Quarter 3rd Quarter FH and Budget List ( 2yr plan)

Approve No Postpone
3rd Quarter 3rd Quarter BoD
/ Defer

Yes
- T&E to list all projects that have completed approval
process and endorse to Budget Controller cc
Functional Heads, CAPEX Manager / Dept Mgrs
- Approved list will be based only on those projects
Endorses Pre approved Budget CAPEX List to that have completed approval in PS up to FH or CEO
EXCO and waits for their Approval level
- Any project that is not included in this list will be
Aug Aug
considered as UNBUDGETED or any project from the
list that incurs changes in cost will go through Re-
allocation process

No Postpone
Approve
18-Aug 18-Aug EXCO / Defer

Yes
Fund Release
Note that Fund Release will not be possible if Project
has not secured or completed Project Approval up to
Approve Fund Release FH / CEO
After 18 in SAP-PS
After 18 Aug CFA for all budgeted CAPEX CJ32
Aug

Project Execution - Project Release enables AUC to be generated


CAPEX Manager /
Enforce Project and Network Release CJ20N
4th Quarter 4th Quarter Maintenance
WBS-all
Manager /

4th Quarter Procurement,


Purchasing Process

Boxes in blue require SAP PS