Design Sequence Pit 7 (Optimize Seam M, Week III Feb – Week II Mar 2023)

Sequence_Pit 7

IPD P7

OPD
P7

Seam Overburden Tonnase SR ASH CVG TS

M1 41,328.26 14,561.92 2.84 3.74 6,039.12 0.38


M 24,838.88 638.16 38.92 9.70 5,571.00 1.21
M2 1,576.23 3,835.55 0.41 7.62 5,872.12 4.25
N 146,324.86 13,245.92 11.05 5.61 5,927.78 2.34
Total/Average 214,068.23 32,281.55 6.63 5.09 5,964.34 1.66

Follow up Request by IBP update 20 February 2023 (demand for coal Seam M , N)
- Seam M ( 8,000 ton)
- Seam N ( 9,500 ton)