Mobilise full team at start of
a Full & adeqaute site reconnaissance, ground survey & mapping. Inadequate Cannot proceed with design. 2 5 10 Consultant After Kick-Off Date. End of 7 Month. Open
project.
*
Mobilise full team at start of
b Adequate geotechnical investigation incuding hydro-geological study. Inadequate Cannot proceed with design. 2 5 10 Consultant After Kick-Off Date. End of 7 Month. Open
project.
*
Fully address land acquisition, re-location of existing services/facilities, Mobilise full team at start of
c Inadequate Cannot proceed with design. 3 5 15 Consultant After Kick-Off Date. End of 7 Month. Open
social safeguard and environmental concerns properly. project.
c
Incorporation of local design and measurement standards whenever
preferable or applicable.
Non-Incorporation. Sub-standard roads. 2 4 8 * Incorporate applicable local
standards in the design.
Consultant
One Month after Kick-
Off Date.
End of 7 Month. Open
*
Flooding incidents will Try to use the software to run a 3 Months after Kick-
b Need for a Flood assessment with SP-SWM or Mike Flood?? Not Carried Out. 3 5 15 Consultant End of 7 Month. Open
increase. flood simulation model. Off Date.
Working with relevant government agencies and university research Exposed areas not properly
c centres to formulate a strategy for suitable greening effort e.g.
identification of right plant species, setting up of nurseries etc.
Not Reaching Out to
Experts.
vegetated resulting in high
maintenance costs.
2 3 6 * Start to consult the other external
experts.
Consultant
3 Months after Kick-
Off Date.
End of 7 Month. Open
d Others?
This item is essential and is a potential for delay and variation claim Duration of Design
Insufficient information for Carry out sufficient investigation &
*
during construction stage if it is not captured properly in the Time Delay & Variation Claim Period & ensure full
a re-location of existing 5 5 mapping exercise & captured in Consultant End of 7 Month. Open
investigation, drawings, bills of quantities and tender documentation during construction stage. info is captured in the
services. tender documents.
stage. tender documents.
As an alternative, the Malaysian MyCESMM2 for the preparation of the Bills of Quantities not
*
Alternative Not Submit a copy of MyCESMM2 to 4 to 5 Months after
a Bills of Quantities can be considered for tender as we believe this an comprehensive, resulting in 3 3 9 Consultant End of 7 Month. Open
Considered. MOP's consideration first. Kick-Off Date.
enhancement to the local method of preparing bills of quantities. subsequent claims.
13 06.03.2023 Other Concerns and Useful Tips from MOP? Negative Positive