Professional Documents
Culture Documents
H4091 MM07.5 Ege
H4091 MM07.5 Ege
4. Control Panel
5. Spare parts
6. Instruction maual
CONTENTS
1 Design/Construction 2
2 Operating Cycle 5
3 Installation 7
4 Caution on Hydraulic Test 9
5 Adjustment 10
6 Troubles and Shooting 12
7 Repair and Lapping 13
8 Reassembly 14
DOC. NO. JK-WIP-E-04
INSTRUCTION MANUAL REV. NO. 1
FOR
DATE 2001. 10. 26
SAFETY RELIEF VALVE
PAGE 2 of 14
1. DESIGN / CONSTRUCTION
Full Bore Type is provided that Seat Opening Diameter (SOD) is not less than 1.15 times the throat
Opening Diameter(TOD), and that the steam passage area of the seat when opened is not less than
1.05 times of the throat opening area, and that the area of the valve inlet and the connection nozzle
are not less than 1.7 times of the throat opening area.
Those valves have a unique Nozzle Seat which provides maximum capacity obtainable. The
discharge through this nozzle enters a body chamber which is carefully proportioned in the internal
contours and in the ratio of inlet to outlet area to minimize flow restriction and body pressure.
Especially for the positive proper adjustment of operating characteristic on fluid, One Ring is
adopted to obtain substantial adjustment to its pop action.
For easy access to resume normal seating face. if need due to failure of its trueness, the most
important characteristic of Flat Seat Nozzle Valve is the ease with which seating surface can be
reconditioned the slight deviation from the specific angles can lead leakage and faulty operation.
All important part are thermally balanced and precisely machined, thus assuring accurate alignment
regardless of temperature variation.
Trim parts in a safety relief valve include disc and nozzle seat only.
(1) Disc
A disc acts as the top guide and is guided by a cylindrical valve guide, standard
construction of safety relief valves includes metal-to-metal seats in a view of tightness
which provide commercial tightness acceptable for most applications or special bubble
tightness under certain conditions.
For reinforcement of seating faces both on disc and nozzle seat to insure their trueness from
violent and rapid shout down force during operating,
DOC. NO. JK-WIP-E-04
INSTRUCTION MANUAL REV. NO. 1
FOR
DATE 2001. 10. 26
SAFETY RELIEF VALVE
PAGE 3 of 14
Also, with a view to avoid any malfunction, leaks, or other problems which may be caused
by stress from the outlet piping or by thermal strains, the seat surface is designed to occupy
a position at the center of the body cylinder and separated as far as possible from the
contact position with body.
Since the fluid channel from the throat to the valve seat is the most important part
determining the performance of the valve, a logical Shape is provided so that there will be
no interruption in the fluid expansion.
DOC. NO. JK-WIP-E-04
INSTRUCTION MANUAL REV. NO. 1
FOR
DATE 2001. 10. 26
SAFETY RELIEF VALVE
PAGE 4 of 14
The area expansion due to a small amount of fluid leakage just before the blow-off produces
pressure enough to lift the disc. this force causes a quick popping action of the valve. The
ring adjusts the simmer of the fluid.
1.3 Body
The body maintains tightness with its precise finishing and its stout construction ensures
safety against thermal stress due to the rapid variation in the temperature of the fluid to be
blown off as well as securing it against the reaction strength resulting from a large amount
of fluid blown off.
1.4 Bonnet
Standard construction of bonnet includes closed one to protect the internal spring and support
the adjusting screw.
On model SSRF open and yoke bonnet can be provided to ensure safety against thermal
stress due to rapid variation in the temperature of the discharging flow during blowing off
Standard caps for pressure relief valve are screwed or Bolted Top and Open Lever Top to
provide periodical test, for usage of which hermetic sealing is not required (with most uses
for steam and air) Adopted Test Gag on two kinds o top cap, when required, is handy for use
in hydraulic test.
On standard open lever, Fork lever are adopted to larger size valve.
DOC. NO. JK-WIP-E-04
INSTRUCTION MANUAL REV. NO. 1
FOR
DATE 2001. 10. 26
SAFETY RELIEF VALVE
PAGE 5 of 14
When the safety valve is blowing off fluid, back pressure is applied to the back of disc and
the guide. The back pressure interferes with the valve when it is being lifted but assists it
when the valve is being closed.
To apply the back pressure most effectively, on additional cock which can be handled from
the outside, can be provided. Safety valve can be suitable provided with the adjust needle on
construction of open bonnet to prevent any trouble in the operation of it even if the throttle is
closed too much.
2. OPERATING CYCLE
All of safety-relief valves are of the direct spring loaded construction. The operating mechanism
of each type is as follows:
Should the pressure upstream of the valve rise abnormally and reach near to the set pressure, it
cause the balanced spring to push upward and the valve disc be slightly lifted up to make an
initial opening. Steam or gas gushing out of this initial opening will be guided by the properly
adjusted lower ring to exert dynamic pressures on the valve disc and the valve disc will be lifted
quickly, the valve will start to discharge.
In case of the Full Bore Type Valve. operating characteristic of which is controlled by the ring,
fluid discharged by the initial blowing-out will be deflected in a downward direction through
upper ring and this deflection as well as pressure generated between two ring are exerted on the
face of the valve disc to lift it to a higher position.
As the Low-Lift Type Valve is not provided with an upper ring, the fluid is deflected through a
chamber formed by the lower face of the valve disc and the lower ring. The valve disc is lifted by
static and dynamic pressure.
2.1 Close
when inner pressure is lower than set pressure, the valve disc keeps the condition of full close
due to differential power between the fluid pressure and the condition of full close due to
differential power between the fluid pressure and the counter-pressure by the adjusted spring
DOC. NO. JK-WIP-E-04
INSTRUCTION MANUAL REV. NO. 1
FOR
DATE 2001. 10. 26
SAFETY RELIEF VALVE
PAGE 6 of 14
(Commence-to-blowout)
In case that the inner fluid pressure reaches near the set pressure, the power retaining valve
closed by the spring will be gradually overcome by the inner pressure allowing a little fluid
leakage into accumulating chamber which is formed between the lower and upper rings.
The pressure condensed in the accumulating chamber makers greater force to lift the disc
upward against spring force. This pressure leads popping action to lift up the disc quickly in
this case, the full open can be easily attained at the given overpressure above the set pressure.
2.4 Re-seating
Re-seating will be duly obtained at the adjusted ring mechanism after enhancement of
blow-off.
DOC. NO. JK-WIP-E-04
INSTRUCTION MANUAL REV. NO. 1
FOR
DATE 2001. 10. 26
SAFETY RELIEF VALVE
PAGE 10 of 14
5. ADJUSTMENT
consideration of service pressure characteristic
(differential between operating and set pressure)
In order to avoid unsatisfactory operation of safety relief valves in normal processing service. the
operating pressure of the system should not exceed 90% of the set pressure. in the pump and
compressor delivery line, however, the difference between the set pressure and the operating
pressure should be made large on account of the pulsation attributable to the pump delivery
pressure is a better method.
Before re-adjustment, remove a Pb seal to cap and set screws which is sealed to prevent arbitrary
adjustment by an incompetent and visual check of any external changes of set pressure or
blowdown pressure.
Take off cap, loosen lock nut and turn down the adjusting screw to the right(clockwise
viewing from above) to raise set pressure and turn up the left (anti-clockwise viewing from
above) to lower the set pressure.
At the readjustment, be sure to lower the pressure of the system at below 90% of the set
pressure.
After completion of re-adjustment, screw up the adjusting screw with lock nut.
6.1 Leakage
The most frequent causes of leakage are from damages on the valve seat and adhering of
foreign materials on it. In these cases, pull the lever to blow off the dirt sticking from the
seat. If the leakage does not stop, the seat must have been damaged.
To avoid seating surfaces damaged by foreign materials. care should be taken thoroughly
from storage to installation which is the best practice after completely flushing out.
Refer to, when it is need, the repair and lapping procedures in para 7 for reconditioning
If the safety valve does not operate at specified pressure, a major cause is accumulation of
dirt or scale between the disc and the guide or the change of the spring load due to bent of
stem. in the case, cleaning or
Dismounting for servicing is required.
Unstable operation often results from wrong adjustment. the followings are the state of
unstable operation and its remedy.
(1) Simmer
When a simmer is present raise the lower ring(push the notches to the right while viewing
in front of notch) by one noter at a time. ( Never set the lower ring in contact with the
valve disc)
this is the case of the slightly weakening dynamic power to lower accumulation not
enough to lift up the disc.
(2) Chattering
This is a rapid reciprocating variations in valve lift during which the disc repeatedly
contacts the seat. It is because popping power is weak. In this case, bring up the lower ring
(closer to the bottom face of the disc but never contact each other)
(3) Hunting
This is the states where the disc repeats violent vertical motion during operation as if it
beat the seat violently. This is often caused when there is much flow restriction in the
piping connected with inlet and discharge side of the safety valve or when blowdown is
excessively too short, in this case, open the gland cock or needle valve or bring down the
upper ring to increase blowdown.
If hunting is not ceased despite the above adjustment, rechecking of the piping is
necessary.
DOC. NO. JK-WIP-E-04
INSTRUCTION MANUAL REV. NO. 1
FOR
DATE 2001. 10. 26
SAFETY RELIEF VALVE
PAGE 13 of 14
In practice, the main necessary repair work will be lapping on the sealing surfaces of disc and
nozzle seat. Its procedure is as follows:
7.3 Washing
Carefully wash the valve seat and valve disc with cleaning oil or liquid after lapping to make
them completely free from lapping compound.
(Commence-to-blowout)
In case that the inner fluid pressure reaches near the set pressure, the power retaining valve
closed by the spring will be gradually overcome by the inner pressure allowing a little fluid
leakage into accumulating chamber which is formed between the lower and upper rings.
The pressure condensed in the accumulating chamber makers greater force to lift the disc
upward against spring force. This pressure leads popping action to lift up the disc quickly in
this case, the full open can be easily attained at the given overpressure above the set pressure.
2.4 Re-seating
Re-seating will be duly obtained at the adjusted ring mechanism after enhancement of
blow-off.
DOC. NO. JK-WIP-E-04
INSTRUCTION MANUAL REV. NO. 1
FOR
DATE 2001. 10. 26
SAFETY RELIEF VALVE
PAGE 7 of 14
3. INSTALLATION
Safety-relief valve are often off hand at the job site several months before they are actually
installed. Unless they are properly stored and protected their performance may be affected
deadly. Roughness in handling may damage valve appearance sharp, worst to crack, or cause
misalignment of the valve part. Furthermore carrying by pulling up the lever may cause
change of the spring set pressure and alignment of the stem.
It is the best practice to directly mount the safety and safety-relief valve in vertical position
on a nozzle of pressure vessel or a short connection which smooth flow of fluid.
Where rounded or beveled approaches can not be provided ahead of the safety-relief valve, it
is recommended that one size larger riser or fitting be used. The pressure drop in the valve
inlet piping should not exceed 3% of the set pressure.
Valves are sometimes badly damaged just as they go into service because of failure to clean
the connections.
It is essential that the boiler, pressure vessel, valve inlet, and all connections should be
cleaned thoroughly before the valve is mounted.
When arranging the discharge piping, pay due attention to the following points talking into
consideration that discharge piping should be simple and direct :
(1) Minimize the length and the number of bends of discharge piping so as to reduce the back
pressure of the valve to a minimum. Especially, when a silencer is used, note that the
discharge pipe tends to be long and
DOC. NO. JK-WIP-E-04
INSTRUCTION MANUAL REV. NO. 1
FOR
DATE 2001. 10. 26
SAFETY RELIEF VALVE
PAGE 8 of 14
Gives a large pressure drop due to discharge exceed 10% of the set pressure.
(2) Discharge piping should be so designed that the weight of the piping will at no time be taken
up by the valve body.
A sufficient flexibility to the discharge piping is also essential to avoid strain on the valve
caused by thermal pipe expansion.
※ Where either of the above conditions are unacceptable, the use of balanced bellows valves is
recommended.
Conventional valve with vented bonnet is not suitable for continuous back pressure.
Therefore never try to arrange discharge pipe from two or more valves into a common
header.
When hydraulic pressure test on the pressure vessel is conducted without removing the safety
valve installed on it. increase inner pressure of the vessel to 80 to 90% of the set pressure of the
valve, then mount the test gag to hold the end of the stem lightly in order to protect the valve
from damage caused by undue load.
Removal of the gag shall also be conducted at 80 to 90% of the set pressure.
When several valves are installed on a vessel or pipe line and one of the valves is being on
adjustment. The same caution should be taken at the mounting of the test gag or gags on the other
valve or valves to prevent it or them from blowing off.
4.1 Cautions
The test gag can not be mounted on the ordinary type caps. Therefore, the caps should be
replaced with those made for the purpose.
In case of pressure test for pressure vessels without using test gag, test them without the
safety valves for safety of it.
Removed valve should be covered at the flange parts against intrusion of dusts, etc.
Replace with a plug and gasket in case of closed top (or take off when open top) after the test,
otherwise the valve will not operate thereby creating a dangerous situation.
DOC. NO. JK-WIP-E-04
INSTRUCTION MANUAL REV. NO. 1
FOR
DATE 2001. 10. 26
SAFETY RELIEF VALVE
PAGE 10 of 14
5. ADJUSTMENT
consideration of service pressure characteristic
(differential between operating and set pressure)
In order to avoid unsatisfactory operation of safety relief valves in normal processing service. the
operating pressure of the system should not exceed 90% of the set pressure. in the pump and
compressor delivery line, however, the difference between the set pressure and the operating
pressure should be made large on account of the pulsation attributable to the pump delivery
pressure is a better method.
Before re-adjustment, remove a Pb seal to cap and set screws which is sealed to prevent arbitrary
adjustment by an incompetent and visual check of any external changes of set pressure or
blowdown pressure.
Take off cap, loosen lock nut and turn down the adjusting screw to the right(clockwise
viewing from above) to raise set pressure and turn up the left (anti-clockwise viewing from
above) to lower the set pressure.
At the readjustment, be sure to lower the pressure of the system at below 90% of the set
pressure.
After completion of re-adjustment, screw up the adjusting screw with lock nut.
6.1 Leakage
The most frequent causes of leakage are from damages on the valve seat and adhering of
foreign materials on it. In these cases, pull the lever to blow off the dirt sticking from the
seat. If the leakage does not stop, the seat must have been damaged.
To avoid seating surfaces damaged by foreign materials. care should be taken thoroughly
from storage to installation which is the best practice after completely flushing out.
Refer to, when it is need, the repair and lapping procedures in para 7 for reconditioning
If the safety valve does not operate at specified pressure, a major cause is accumulation of
dirt or scale between the disc and the guide or the change of the spring load due to bent of
stem. in the case, cleaning or
Dismounting for servicing is required.
Unstable operation often results from wrong adjustment. the followings are the state of
unstable operation and its remedy.
(1) Simmer
When a simmer is present raise the lower ring(push the notches to the right while viewing
in front of notch) by one noter at a time. ( Never set the lower ring in contact with the
valve disc)
this is the case of the slightly weakening dynamic power to lower accumulation not
enough to lift up the disc.
(2) Chattering
This is a rapid reciprocating variations in valve lift during which the disc repeatedly
contacts the seat. It is because popping power is weak. In this case, bring up the lower ring
(closer to the bottom face of the disc but never contact each other)
(3) Hunting
This is the states where the disc repeats violent vertical motion during operation as if it
beat the seat violently. This is often caused when there is much flow restriction in the
piping connected with inlet and discharge side of the safety valve or when blowdown is
excessively too short, in this case, open the gland cock or needle valve or bring down the
upper ring to increase blowdown.
If hunting is not ceased despite the above adjustment, rechecking of the piping is
necessary.
DOC. NO. JK-WIP-E-04
INSTRUCTION MANUAL REV. NO. 1
FOR
DATE 2001. 10. 26
SAFETY RELIEF VALVE
PAGE 13 of 14
In practice, the main necessary repair work will be lapping on the sealing surfaces of disc and
nozzle seat. Its procedure is as follows:
7.3 Washing
Carefully wash the valve seat and valve disc with cleaning oil or liquid after lapping to make
them completely free from lapping compound.
8. REASSEMBLY
Reassembly will be made following the reverse order of disassembly.
(1) Care should be taken not to damage or soil the lapped surfaces of valve disc and valve seat.
(2) Properly center the tip end of the valve spindle on the valve disc.
(3) Evenly and alternately lock up nuts to tighten the bonnet or yoke bolts.
DOC. NO. SPP-DM-001
REV.NO. -
Circulation flow measurement DATE -
PAGE 1 OF 8
1. Description
A water tube exhaust gas boiler requires a continuous forced circulation of water through the boiler as dry running
would seriously increase the danger of a fatal soot fire. The forced circulation is provided by two circulating pumps.
One of the pumps must be kept in continuous operation ( also in port ) and the other pump in automatic standard -
by operation mode.
The circulation flow measurement control system will ensure a continuous water circulation.
The system consist in general or an orifice, differential pressure indicator switch, see Figure 1.
Figure 1
The office will protect the pump by reducing the discharge flow variations resulting from different working
conditions. The pressure drop in the boiler and circulation return pipe as well as the required static lift
(due to differences in specific volumes between water and steam / water mixture in the return pipe)
strongly depend on the boiler load and are smallest when no steam in generated.
DOC. NO. SPP-DM-001
REV.NO. -
Circulation flow measurement DATE -
PAGE 2 OF 8
This might give rise to large flow variations which would not be desirable for a reliable pump operation.
However, variations are reduced when the pressure drop across the orifice becomes considerable compared
to the total back pressure ( at design load ).
The differential pressure indicator switch has two switches which should be user for:
- Alarm in case of low circulating water flow.
- Start of the stand-by pump in case of too low circulating water flow.
In additional to this, the stand-by pump should also be started in case of overload on the motor of the operational
pump.
DOC. NO. SPP-DM-001
REV.NO. -
Circulation flow measurement DATE -
PAGE 3 OF 8
2. Recommendations
The typical system is shown in Figure 1. The actual system may be slightly different but the following descriptions
and recommendations would generally still be valid.
All the components of the circulating system have to be carefully designed and installed to ensure a reliable,
continuous circulation in the exhaust gas economizer under all working conditions.
The following working conditions must be taken into account when designing the circulating system:
3. Installation
The installation details are described in this section and in Figure 2. The important points mentioned below
should be observed.
Figure 2
3.1 Orifice
The orifice must be installed in a straight pipe with a length of at least 25 and 10 times the nominal pipe size before
and after the orifice, respectively. The orifice must be properly centered by means of flange connection bolts.
The impulse legs must be of sufficient length to avoid overheating of the pressure switch. The impulse legs must
be provided with isolating valves close to the circulating water pipe. Additional valves at the pressure switch as
well as drain cocks are recommended for easy blow-out of the impulse legs. The recommended minimum pipe
size is 8 mm (OD).
The pressure switch should always be located below the lower impulse leg connection. The high pressure impulse
leg (before the orifice) must be connected to “+” and the low pressure impulse leg connected to “-“.
The impulse legs must be designed in such a way that there is no strain on the pressure switch.
DOC. NO. SPP-DM-001
REV.NO. -
Circulation flow measurement DATE -
PAGE 7 OF 8
4. Operation
4.1 Operation
It is essential that the circulating water pumps are running continuously (also in port) without any problems.
The system behavior under all working conditions should be observed during the first period of operation,
especially at full load, no load (main engine stopped) and large load variations.
In case of low flow alarm at full load, the mixing valve should be re-adjusted (if required, to a higher total flow
rate) in accordance with the above instructions.
Check that the circulating water flow does not exceed the permissible range of the circulating pumps at any
load conditions. In case of automatic stand-by pump start, the cause should be investigated immediately so that
the necessary action can be taken to eliminate the operational problems.
The impulse legs for the differential pressure indicator switch should be regularly blown through to remove
deposits, if any. The switch should not be reconnected before the temperature is sufficiently low.
Enter corresponding water flow (㎥/h) at design flow, low flow alarm ( 80% of design flow ) and stand-by pump
start ( 60% of design flow ). Use throttle orifice performance curve ( provided in the documentation ) to find
pressure drop across orifice at the specified 3 conditions.
DOC. NO. SPP-DM-001
REV.NO. -
Circulation flow measurement DATE -
PAGE 8 OF 8
1. INTRODUCTION
It is advisable that this instruction book should be read and understood throughout
prior to using or operating the “ EGE ” (Exhaust Gas Economizer) for Installation,
This instruction of EGE, somewhat differs from the others depending on the
arrangements of ships related to the each vessel, however, the general guidance
will be given to this instruction book for all SPP Machine Tech EGEs.
Page 1
2. EGE(ECONOMIZER)
SPP Machine Tech EGE, comprises sections of Heating Coils with their
characteristic function, a steam generator. The elements in each section are formed
from steel tubes with steel fins welded in position on each side.
The EGE is a waste heat recovery unit, generating steam from exhaust gas of
diesel engine or others. The EGE is always operated in conjunction with a steam
of tubes, the tubes being connected to each other by return-bends and to the
headers by stubs. Pressure part connections are separated from gas stream by
the tube and supports, access being provided by gas tight panels which are welded
on.
Access doors are provided in the end casing by bolting for inspection of return-
Page 2
3. WATER/STEAM FLOW
EGE is water tube, forced circulation type and works in combination with water tube
boiler at all times in order to separate the steam from the circulation water.
For EGE, the water saturated is drawn by a circulation pump from the generating
vessel, boiler and passing through the generator coils, is returned to the generating
single or double flow and the internal pressure losses are relatively low.
The feed water is direct into Aux. Boiler at a temperature as specified on the
drawing or the enclosed performance date sheet. To avoid low metal temperature of
heating tubes and possibility of corrosion, the Circ. water temperature should not be
below 115 degree C.
Page 3
SECTION B. INSTALLATION
1. POSITIONING
must be made in the joints between the feet of the unit and the supporting
slot-holes.
1.2 The units for very large one are built in two or more parts if necessary or
joints are bolted. After bolting, the joint must be seal welded on the outside,
also seal welded the heads of the bolts and the nuts.
1.3 On the gas side, the EGE is naturally arranged in the engine exhaust trunk
type, chamber type, with entry and exit connections to promote a good flow
distribution over all heating surface and to inspect the heating surface. The
1.4 After perfect installation of EGE body, the bracing should be arranged in each
four direction of rectangle body in case the unit is over than 5 ton/hr – steam
evaporation capacity. The connections are to be made by slot holes and the
1500mm.
1.5 Facilities for water washing of heating surface and casings should be provided
Page 4
above of the unit, and the collecting hopper, with large bore drain port, must
be positioned below of the unit to prevent any water entry into the main engine.
For routine on-load cleaning, conventional soot blowers are recommended and
for off-load cleaning, the water washing through the access door of outlet trunk
recommended.
Ample access above and below the unit should be arranged for inspection and
water washing.
1.6 The tube removal space to be arranged for inspection and maintenance.
External pipework should be clear and permit ready access to all inspection
1.7 The piping arrangement should incorporate stop valves and the necessary
complement of additional mountings and fittings as required by the overall
Discharge pipework between the EGE and the boiler should be of ample size
and fitted with straight through valves for minimum pressure losses.
1.8 All valves must be either fully open or closed and it is important to ensure that
position.
Page 5
2. LIFTING AND HANDLING
2.1 Lifting Generally the lifting lug is fitted at the top of the unit according to the
with wire rope and lifting beam when lifting the unit.
The wire rope to be decided and designed in accordance with the EGE weight.
When lifting, the total weight to be distributed to each rope uniformly and the
length to be equalized.
If the unit is less than 10 Tons, its advisable to use the bracing lug instead of
lifting lug. In this case the lifting method is identical with the above condition.
The wire rope should be arranged in parallel direction against the unit side
2.2 Handling
The EGE unit should always stand-up vertically because the heating coils are
supported by pipe sleeve of end supports for thermal expansion.
If the unit is less than 5 ton, it may be laid down on the ground with several
props.
When standing up on the ground, the proper prop also to be used and the
If wooden props are supplied, the additional supports will be not necessary.
Page 6
3. PREPARATION FOR CLEANING
Man-hole for inspection should be arranged at chamber (smoke box) of the above
and below of the unit, a large bore drain port also to be arranged at the bottom of
The water washing for heating coils should be carried out through the man-hole of
outlet chamber side, therefore a suitable man-hole or access door required at the
Drainage for return-bends washing is provided by suitable drain holes at the bottom
side of EGE casing in order to inspect the cleaning situation when washing.
The mixed water with soot are dropped toward the inlet chamber and drained
Page 7
4. SYSTEM PROVISION
If the damper system fitted to control the steam output, it is arranged over the unit.
The operation mechanism is linkage and may be hand operated or fitted with
Where divided headers are arranged for steam output control, it must be served by
A further system for output control can, where convenient, be arranged by a direct
Page 8
SECTION C. OPERATION
1. GENERAL
Operation of the EGE will be dependent upon the individual ship’s system but it is
possible to give some general guidance.
Under the operation, the circulation pump should always be kept running before
main engine started and after shut down of main engine the circulation pump to be
kept running for 12 hours or more. Valves except drain valve are to be opened.
2. START UP
2.1 Softened and deaerated feedwater is obviously preferable for reducing
2.2 Before start up, it is important to ensure that all valves, with the
generator section and the steam generating vessel are fully opened to permit
2.3 Open the air vent valves of each header and close the drain valves and open
2.4 It is also important to start the circulation pumps immediately prior to starting
2.5 Open the circulation pump discharge valve gradually after confirm the above.
2.6 It is preferable for the circulation water to have a hot or pressurized steam
separating vessel(Aux. Boiler). In this way the tube warming must be kept and
minimized, or alternatively, if the tubes are already hot, the element cooling
2.7 The circulation water flow should be gradually increased at the pump
2.8 Close the air vent valves for generator section after ensuring thatwater or
Page 9
steam is issuing from air vent valves.
2.9 Also check the steam evaporating at the air vent valve of steam generating
vessel and then close this valve when steam starts to evaporate.
2.10 When the pressure of Aux. Boiler reaches the specified value, operating
Page 10
3. SHUT DOWN
3.1 The circulation pump should be continuously operated for twelve (12) hours
at least or more after main engine shut down. During this operation of pump
- Check the inside, heating surface, through the manhole or inspection door
whether any sparks due to soot accumulations in the heating surface are
- The EGE must be free from abnormality in appearance and also its surface
3.2 Stop the circulation pump after inspection of above and then close the all
valves of circulation line and open the drain valves of each section.
3.3 Shut down would be in reverse procedure for start up, commencing with
4. CONTROL
4.1 If divided headers are included, sections may be isolated so that amount of
circumstances the boiler should have direct feedwater. In this case, the
valves serving those sections not in use must be closd and water in those
“ SEE DRY-RUNNING ”
4.2 The steam output should not be controlled by curtailment of circulation water
flow at any case. This promotes deposition of water treatment additives and
solid matter within the tubes. These depositions decrease the heat transfer
Page 11
efficiency consequently.
Furthermore, in the worst condition this deposition may clog the pipe inside
4.3 Under steaming condition, the unit should operate at all times with line valves
The circulation water should flow continuously at the maximum flow rate.
4.4 If the preheating section fitted, the inlet temperature at Economizer section
should be kept by specified value in this instruction or on specification sheet
and flow diagram in final drawing at any case during operation of main engine.
The exhaust gas contains the sulfur dioxide(SO2) forming from sulfur of fuel
oil.
temperature the condensation of sulfur dioxide will occur on the surface of the
heating tubes and then result in sulfur corrosion, called low temperature
4.5 No-water heating should not be performed generally except the emergency
condition or trouble of circulation pump. However, in case no-water
emergency measures :
- The inside of header and heating tubes should be free from pressure and
water. The drain and air vent valves should be opened and also the
- The exhaust gas temperature at the inlet of EGE must be maintained below
the maximum allowable temperature for example, 400 Deg. C. for carbon
- When this condition is done, the inside temperature of the unit will be
increased and the soot fire may by occurred more easily. Therefore, the
Page 12
washing before dry-running performed.
4.6 If damper system is included, the flow of gas will be controlled by dampers.
These have a self lubricating bearing inside of the unit but the lubrication is
required for outside bearing and linkages of it. The damper system should be
operated throughout the full arc of travel at least once a day in order to
Page 13
5. DRY-RUNNING
CATION: It is only allowable to perform dry running in case emergency measure, with
under paying attention to below points:
① Prior to dry running, inspect and clean heating surface by water if any soot is
CAUTION: If ignition (soot fire) has started, do not operate soot blowers not
⑦ Monitoring of the inlet and outlet gas temperatures in important to ensure that
temperature must be avoided prior to dry running and before water circulation.
Open the air vent and drain valves and open outlet valve slowly. The inlet valve must
be opened little by little with checking the water or steam output from air vent and
drain valves. It is preferable to ensure that the heating coils are cooled and reach the
normal operating temperature before full open of the inlet valve. After that, close the
air vent and drain valve, open the inlet/outlet valves fully to permit normal operation.
Page 14
SECTION D. MAINTENANCE
1. CLEANING “ IMPORTANCE ”
1.1 GENERAL
High velocity gas flow coupled with good combustion and maintained
operational temperatures ensure minimum deposit formation for heating
The circulation water with good treatment of boiler water will reduce the scale
Gas leakage check from the unit, manhole, inspection door and casings, and
loss, differential pressure of gas, between the inlet and outlet of the EGE body
should be carefully inspected and recorded in order to judge the situation of
respectively. Before the water washing, ensure that the drain hole is clear and
the drain pipe line is free from clogging. A soaking spray with a 10 percent
soda ash solution is advisable before washing, particularly where deposits are
highly corrosive.
Water washing will be done by hand hose or convenient device if fitted. The
washing should be carried out through the manhole of outlet chamber of EGE
unit, smoke box. In this case the water must not enter into the Turbo-
Generator and the heating surface should be washed perfectly in the whole
surface, especially corners until the washed water is clear at the drain ports of
the bottom of hopper. The soot blowers can not be perfect to remove soot,
Page 15
consequently water washing must be done with regular interval, once per two
months in case the heating surface has a normal condition. However, the
surface situation.
After water washing, open the inspection doors and access doors and then
inspect the inside of the unit throughout. It is advisable to perform the water
washing just after circulation pump shut down because the heating coils
remains hot and the corrosion will be thereby reduced. The exhaust gas
temperature, the casing surface temperature, the draft loss, gas color coming
from the funnel and the spark situation in exhaust gas etc. must be carefully
inspected to decide the frequency of water washing and soot blower operation
The frequency of soot blower operation should be also dependent upon the
soot deposit conditions in the heating surface. Therefore regular inspection of
the heating surface through manholes and inspection doors is required. Soot
blowing is not the complete answer but will remove dry loose deposits until
washing can be carried out.
surface.
If the unit is operated under adverse soot forming conditions and low speed
shutdown of the unit, before dry running, and after turbo blower washing.
The draft loss and gas temperature should be measured regularly and
Page 16
compared with that of normal condition, it means that soot deposits were
In this case the soot blowers should be operated more frequently and water
that the heating surface was fouled and the heat transfer efficiency was
deteriorated. Also in this case the soot blowers have to be operated more
frequently and the sooner water washing performed, the better efficiency
promoted.
The standard data of water quality should be in accordance with the below
are provided, it is general that the soot blowers will be installed at the
same height( same level). Firstly operate No.1(one set), and next
No.2(the other set), and then operate No.1 soot blower again. In case 4
sets or more are provided, the soot blowers will be installed at different
“AUTOMATIC” mode.
Page 17
every 8 hours. This time interval is recommended value, so it is
“MANUAL” mode.
② Soot blowing is carried out by turning the “START-STOP” mode
Page 18
1.6 STANDARD DATA FOR WATER TREATMENT
of control for feedwater and boiler water in consultation with the compound
If the scale has been accumulated on the inside of tube, it must be removed
by chemical cleaning.
Page 19
2. EMERGENCY REPAIR
In the unlikely event of a tube failure, a temporary repair may be done by cutting
Insert the tube plug into the header stubs and weld to the headers stubs.
For a more permanent repair with minimum loss of heating surface, it is possible to
bypass the affected tube by welding straight piece across selected bends.
Where divided headers are fitted, that section containing the faulty tube may be
isolated by blanking plates between the joint flanges, or by other convenient means.
The effective heating surface is of course reduced considerably, and the output
2.1 Find the position of failed tube through manholes and inspection doors by
Take care of them with no damage because they are used again.
2.3 Cut off the affected tube from the inlet and outlet headers with care of the
cutting position.
longitudinal axis of the tube and the stub should have a circle instead of oval
2.6 After the plug is fixed in position, the hydrostatic test should be carried out to
ensure that no leakage occurs. The cutting points of coil side must be
plugged by means of convenient method and then close the doors finally.
3. PERMANENT REPAIR
It is dangerous to interfere with the pressure parts of the EGB while they are under
pressure. To carry out repairs, the EGB must be completely isolated on both the
flue gas side and the water side. Prior to draining the unit, it is necessary to
ascertain the correct position of the leak and mark the faulty element.
Page 20
For a permanent repair it will be necessary to withdraw the affected coil from the
EGB unit. Remove the appropriate casing from each and of the unit and any end
casing supports which will interfere with the withdrawal of the coil.
The superheater is sometimes split into sections with the supporting boxes
In this case one complete section must be removed from the EGB.
Cut off the header bends, remove all the bolts from the end box at each end
of the unit, remove the sealing plate from over the element and boxes at each
The steam generator is arranged for either single or double flow on the water
side and the elements are built into coils, one element wide. See the removal
of coils.
So all bends attaching the vertical column of tubes should be removed to the
4.1 Remove the end casing doors of the both sides (1). These doors to be re-
4.2 Cut off the connections (2), (3), (4) and (5).
4.3 Remove the bolts (6), (7) and (9) for the both sides and then remove the flat
4.5 Pull out the heating coil with failure by using a chain block. If the unit don’t
plate under the coil but over the support, on which the coil can slide.
Page 21
The plate should be well greased and should have a lip fitted over the bottom
end support at the end opposite to the withdrawal end. Lift the coil a little to
4.7 When the coils are withdrawn, use the shims where necessary to prevent the
Page 22
5. RENEWAL OF COILS (Refer to Figure 2 on page 26)
5.1 Spares
The spares supplied with the unit include sufficient bend spares to enable
The end of all tubes and bends should be prepared in readiness for welding
by using a grinder.
The tube or bend ends should be cut back to the weld, or the equivalent
distance from the element end supports, before dressing the ends.
5.3 Insert the coil into the EGB and weld to the header stubs.
In the Economizer section, weld on the return bends in the same pattern as
5.4 It is important to ensure correct fin alignment between the new element using
the welding clip provided in the tool box, tack weld the bends in position.
Remove the clips and finish welding the bends ensuring minimum internal
weld deposition.
Page 23
6. HYDROSTATIC TEST
Whenever repairs are made to any of the pressure parts of the EGB the unit must
The original test pressure for the EGB will be shown on the pressure part drawing.
Under the emergency repair this test will be done less than the safety valve setting
Fix the safety valve in position by using the pressure test tool.
Use fresh water and close all valves except feed valve, air vent valve and pressure
Supply water slowly and check the water leakage at the air vent valve and then
Increase the pressure gradually up to the test pressure and hold the test pressure
If the test is successful the water should be drained fully. After the test, remove
the pressure test tool of safety valve and put it back to the original position.
Page 24
7. FINAL PREPARATIONS
Clean out all debris from the flue gas side and ensure that there are no obstructions
Refit the end casing doors ensuring that a gas tight joint is made and also confirm
that all inspection doors and manholes are securely fitted into correct position.
8. DAMPER
Sometimes an integral bypass damper will be provided for steam output control if
required. These have self lubricating bearings but the outside ball bearings and
linkages should be lubricated by suitable grease for high temperature at least once
a month.
To ensure the freedom of movement, the damper must be operated throughout the
full arc of travel at least once a day to release the sliding bearing lubricant
accordingly.
Page 25
Page 26
Page 27
SECTION E. SOOTFIRE “IMPORTANCE”
1. INTRODUCTION
Soot fires are a kind of second combustion in the heating surface of waste boilers
due to soot accumulation. On board fires, including fires in waste boilers of both
the seriousness of fires when they do occur and because they can occur and
because they can be avoided, these guidance is given in an attempt to prevent fire
Fires are caused by mal-operation of the engine, or engine operation under adverse
conditions, with subsequent failure to clean the heating surfaces of the waste boiler
elements.
Carbon deposits coming from exhaust gas cannot always be prevented but, they do
occur, it is essential that they be removed from the boiler elements before a fire
hazard is created.
With adequate crew training, the conditions tending to create a fire hazard can be
prevented.
This instruction should be first understood in detail and the action should be taken if
A ship’s procedure for dealing with fires is strongly recommended but a routine for
Page 28
2. AT EMERGENCY
If a fire has started :
If fitted, close the outlet damper of tube side and open the bypass damper
wide angle spray to slowly cool casings without producing thermal shock.
Ascertain and inspect the severity of fire. In general, if minor fire occurs, keep
circulation pumps running, if major fire occurs, stop circulation pumps and drain
Do not use any soot blower or spray boiler internals with water.
In close navigational waters, the ship should be moved to a safe area before the
engine is stopped. The exhaust gases of engine contain at least 17 percent oxygen
which will naturally feed the fire. Therefore, it is essential to eliminate this source of
Page 29
3. CAUSE OF FIRES
Under normal conditions a fire is most unlikely.
Incandescent particles carried over from the engine in the exhaust gases, made
oxygen rich by the scavenge air, will readily ignite the deposits particularly when
The incidence of fires is highest during maneuvering, leaving a port because the
The soot in exhaust gas will be increased when the ship is going to arrive at port, or
If dampers are fitted they should be set to allow the gases to pass through the
boiler bypass without passing over the heating surfaces on all occasions of above.
On engine shutdown, the circulation pump should be kept running, keeping the
elements cool, until most of the residual heat in the unit has been dissipated.
Mal-functioning of the engine will cause incomplete combustion of the fuel with
consequent dirty exhaust gases. This condition is affected by the fuel and its
treatment, the condition and setting of the engine, etc.
Slow running will cause engine inefficiency with increased carbon in the exhaust
gases and, with reduced gas velocity, the carbon is more readily deposited on the
element heating surfaces. The problem is aggravated if an incorrect type of fuel
When turbo blowers are washed in service there is a resultant increase in deposit in
Page 30
4. PROGRESS OF FIRES
Soot fire usually progresses in three distinct phases as follows :
Phase I is the early stage of the fire before overheating of the elements has
taken place. This can be accompanied by the emission of burning particles from
the funnel.
It is essential that the fire is dealt with quickly and efficiently at this stage before
If the engine is stopped and the air intake restricted, the fire will probably by
quickly extinguished.
oxidation.
At this stage, the boiler casing may start to glow, circulation pump be stopped
Page 31
5. PREVENTION OF FIRES
If carbon deposits are not present on the heating surface, the fires will not occur.
hazard. In the case of fires, however, the bridge crew may be the first to observe
The earliest indications in the engine room of the possible existence of a fire will be
given to fitting flue gas temperature sensors in the boiler body with alarms in the
A ship procedure should be established for dealing with soot fires and training
arranged to ensure that all aspects of the procedure can be carried out quickly and
effectively.
Consequently, early detection of a fire will reduce the damage of heating tubes from
soot fire. The best countermeasure to prevent soot fires is preventing the
accumulation of soot in heating surface and removing the carbon deposits on the
Page 32
6. CONCLUSION
Fires in waste heat boilers, EGE can occur if equipments are not maintained
correctly.
Never allowing deposits to build up to such an extent that they present a fire
hazard.
Observing the exhaust gas differential pressures (draft loss) across the boiler
Running the circulation pump continuously when gases are passing through the
Keeping the circulation pump running on shutdown until residual heat is lost from
the boilers.
Washing when the need and the opportunity arises.
Ensuring that soot blowers, water washing equipment, and circulating pumps are
always in service condition and operating according to the design conditions.
Ensuring that the main engine is operated under normal condition with good
function.
Checking the exhaust gas temperature and the draft loss are abnormal.
Page 33
SECTION F. INSPECTION
The inspection should be carried out regularly and whenever the opportunity arises,
especially the heating surface to be inspected whenever main engine is shut down.
When the main engine is shut down, the followings should be at least inspected.
- Circulation Pump
Boiler circulation pump to be run continuously for minimum 12 hours in order to
prevent soot fire hazard and cool the heating coils from the residual heat after
The heating surface to be inspected by using the hand lamp through the inspection
door or access holes.
All gas passage should be checked and confirmed thoroughly, whether any other
substance or carbon deposits is in the passage between the fins.
immediately.
If the surface condition is dusty and the deposits severely accumulated, the water
The unit inside temperature to be checked and compared with design value.
The abnormal high temperature may mean that the soot is burning.
In this case the inspection door or access hole should be kept closing until the
temperature is decreased, and any other air supply or soot blowing shall not be
And also the circulation pump to be operated for long time more than 12 hours until
Page 34
Other inspection, gas differential pressure, spark situation at funnel outlet, main
section inlet if fitted, super heated steam temperature and so on should be checked
This check point is different from ship’s system but the above item to be checked
and recorded regularly and always to be compared with each recording data,
respectively.
Page 35