MRP Vs CBP:-
Process It’s carried out using current and It’s carried out using Historical consumption
Flow future sales figures. data to calculate future requirements with
the help of the material forecast.
Open sales orders and
Deliveries.
Open Purchase Orders and
Purchase Requisitions.
Open Planned Orders and
Production Orders.
SastraGeek Solution
Reorder point planning: - Procurement is triggered when the sum of plant stock and firmed
receipts falls below the reorder point.
Manual Reorder Point Planning (VB)
In manual reorder point planning, you define both the reorder level and the safety stock level
manually in the appropriate material master.