NAMAKHVANI HPP CUT-OFF WALL PROJECT, GEORGIA

General Method of Statement for Secant Pile Wall

ENKA INS. VE SAN. AS BRANCH IN GEORGIA

NAMAKHVANI HPP CUT-OFF WALL


PROJECT

NAMAKHVANI, GEORGIA

GENERAL METHOD OF STATEMENT


FOR
SECANT PILE WALL

MAY 2021

BG.1604.B01 BAUER Georgia Foundation Specialists LLC Page 1 of 12


27 Mitskevich Str., floor 7, 0194 Tbilisi, Georgia | Tax ID: 204572006
Tel / Fax: +995 322 251466 | Mobile: +995 591 19 66 00
E-Mail: bauer@bauer.ge | Web: www.bauer.ge
NAMAKHVANI HPP CUT-OFF WALL PROJECT, GEORGIA
General Method of Statement for Secant Pile Wall

TABLE OF CONTENTS:

1. Construction Procedure for Secant Pile Wall ............................................................3


1.1 Guide Wall..................................................................................................................3
1.2 Drilling .......................................................................................................................4
1.2.1 Work Sequence ..........................................................................................................4
1.2.2 Drilling Primary Piles ................................................................................................5
1.2.3 Drilling Secondary Piles.............................................................................................5
1.2.4 Control of Accuracy ...................................................................................................5
1.2.5 Drilling Equipment....................................................................................................5
1.2.6 Kelly Bar and Rotary Drive ........................................................................................6
1.2.7 Tools / Casings..........................................................................................................6
1.2.8 Drilling Tools .............................................................................................................7
1.3 Concreting ..................................................................................................................7
1.3.1 Plastic Concrete Mix Design .....................................................................................7
1.3.2 Installation of Concrete .............................................................................................8
2. Quality Control ..........................................................................................................8
2.1 Concrete Control ........................................................................................................8
2.2 Accuracy Control........................................................................................................9
2.3 Check of Excavated Soil ............................................................................................9
2.4 Determination of the Final Depth .............................................................................9
2.5 Concrete Testing ........................................................................................................9
2.6 Pile Records ...............................................................................................................9
3. Appendices ............................................................................................................... 10
3.1 Appendix A: Pile record .......................................................................................... 10
3.2 Appendix B: General Layout & Elevation Drawing ............................................... 11

BG.1604.B01 Page 2 of 12
NAMAKHVANI HPP CUT-OFF WALL PROJECT, GEORGIA
General Method of Statement for Secant Pile Wall

1. Construction Procedure for Secant Pile Wall


1.1 Guide Wall
Prior to starting the construction of the pile wall a reinforced concrete guide wall has to be
installed on the wall axis.
Steps of installation:
- Excavate ditch
- Set out axis and corner points (by surveyor)
- Place blinding concrete on level ground as support for formwork if necessary
- Erect prefabricated formwork with stiffeners
- Countercheck location of formwork by surveying
- Place concrete
- Remove formwork
- Secure position by internal bracing
These steps are performed consecutively on the wall axis.

Plan View

Isometric View
Figure 1

BG.1604.B01 Page 3 of 12
NAMAKHVANI HPP CUT-OFF WALL PROJECT, GEORGIA
General Method of Statement for Secant Pile Wall

1.2 Drilling
1.2.1 Work Sequence
The basic layout of the wall is a series of unreinforced concrete primary piles and secondary
piles.
The primary piles will be constructed first with required center to center spacing.
The secondary piles will be drilled within two constructed primary piles, thus overcutting
adjacent constructed primary piles.
The sequence of piling operations will be arranged in a way to avoid disturbance of adjacent
freshly poured piles.

- Installation of temporary casing with oscillator (If required) and with required casing
diameter.
- Drilling down to final depth according to approved pile design with drilling rig attached
telescopic Kelly-bar and attached tools of corresponding diameter.
- The borehole is supported through partly full depth by the temporary casing.
- Drilling down to final depth by BAUER BG drilling rig with telescopic Kelly-bar and attached
tools such as augers of the corresponding diameter.
- Cleaning of pile toe with bucket.
- Pouring of plastic concrete by tremie tube method in temporary cased borehole by service
crane/BG and truck mixer.
- Withdrawal of temporary casing by Bauer BG drilling rig.
- Shifting of equipment to the next location.

BG.1604.B01 Page 4 of 12
NAMAKHVANI HPP CUT-OFF WALL PROJECT, GEORGIA
General Method of Statement for Secant Pile Wall

Refer to Appendix 2 for General Layout and Elevation (Drawing Nr: 1609T01-01) drawing for
sequence and depths of the piles.

1.2.2 Drilling Primary Piles


The primary piles will be drilled with a hydraulic rotary drilling rig of BG. The pile hole will be
stabilized and guided by temporary casing.

1.2.3 Drilling Secondary Piles


The secondary piles will be drilled with a hydraulic rotary drilling rig of BG. The piles will be
stabilized and guided with a steel casing. The casing will be installed with the rotary drive of
the BG rig in advance of the excavation of soil inside the casing, performed by means of auger,
bucket and core-barrel.
The casing string is formed of sections, which are connected with flush screwed joints. The
casing shoe is equipped with a ring of teeth which will enable cutting into adjacent concrete
of primary piles.

1.2.4 Control of Accuracy


Construction of the secant pile with sufficient verticality is of great importance for cut-off wall.
System details and methods to ensure the correct positions of piles are as follows:
- Accurate guide wall
- Type of drilling equipment
- Tools
- Rope Inclinometer
- Verticality measurement before concreting. The target vertical
accuracy will be 1/100.
A reinforced guide wall will be constructed prior to start of piling. It
will be accurately set out by a surveyor and rechecked as built. This
guide wall will act as main guidance for accurate position of piles.

1.2.5 Drilling Equipment


The BG drilling rig is considered sufficient to excavate even the deep
piles. The base carrier, a Sennebogen or O&K is specially built for the
drill rig for high performance along with high quality.
Beside the capability to excavate the deep piles the machine offers
various tools for the quality control data for the operator such as
depth.
Equipment noise emission is in range of 100-120 dB(A).

BG.1604.B01 Page 5 of 12
NAMAKHVANI HPP CUT-OFF WALL PROJECT, GEORGIA
General Method of Statement for Secant Pile Wall

1.2.6 Kelly Bar and Rotary Drive


The design requirements with
respect to the required pile
depths can be achieved using
a Bauer telescopic Kelly bar.
The standard Kelly bar can be
extended depending on the
type of bar used. Special
technical features provide the
bar with sufficient stiffness to
transmit the torque of the rig
to the drilling tool.
The BG is mounted with a
Rotary drive KDK. All further
tools as Kelly drive adapter
and casings fit to the selected
piling diameter.
When installing the casing the verticality is checked with a precise spirit-level. Required
corrections can be easily made by moving the top end of the casing with the turntable.

1.2.7 Tools / Casings


The temporary casing string for pile construction consists of individual casing pieces connected
together in sufficient quantity to reach the required depth. The connection is made with high
quality screws.
The extreme stiffness of the casing together with the stiff joint connection ensures a vertical
hole.

BG.1604.B01 Page 6 of 12
NAMAKHVANI HPP CUT-OFF WALL PROJECT, GEORGIA
General Method of Statement for Secant Pile Wall

1.2.8 Drilling Tools

The drilling tools are attached to the bottom of the Kelly bar. They are loosening the soil and
taking out the spoil from the borehole.

1.3 Concreting
1.3.1 Plastic Concrete Mix Design
The concrete and its components will comply with the relevant Standards and will be chosen
by MC.
- Prior to starting works a trial mix will be prepared to check suitable mix proportions,
workability and strength, including type and quantity of additives.
- Workability of fresh concrete will be checked at the borehole prior concreting. The
slump and slump flow value shall be 210-230 and 480-580 mm, respectively.

BG.1604.B01 Page 7 of 12
NAMAKHVANI HPP CUT-OFF WALL PROJECT, GEORGIA
General Method of Statement for Secant Pile Wall

1.3.2 Installation of Concrete


Ready mix concrete will be supplied to site with truck mixers. Concrete will be placed with a
tremie pipe to avoid segregation and ensure continuous, dense concrete quality.
Concrete is filled into the tremie pipe through a hopper.
During concreting the tremie pipes will be kept continuously immersed in the fresh concrete
by a minimum requirement. While the concrete is rising from bottom to top, sections of the
tremie pipe string will be taken out to fulfill the requirement of a minimum 3 m embedment
of the bottom of the string into fresh concrete. The sequence of tremie tube sections will be
recorded during installation in order to avoid the unintentional removal of a section too long
for minimum immersion as expressed above.
Concreting will end when clean concrete will reach the surface or when the concrete level is
approximately 3 m above theoretical cut-off level in order to ensure consistent quality of
concrete along the entire pile bore.
Concreting of one pile will be
performed in one continuous
Hopper
operation.
One tremie pipe string consists
of:
- 1 hopper with lifting rope
Lifting Cap Support Fork
- Tremie pipes with male and
female connections
Tremie Pipe
- 1 lifting cap
- 1 tremie support fork
O-Ring
O-rings in conjunction with
grease will ensure adequate Seil Rope
water tightness at the joints of
the tremie pipe sections. The
Pipe Coupling
tremie pipe string will be with Steel Cable
Pipe Connection
with Threads
Starter Pipe
positioned by a service crane or (Standard) (Option)

drilling rig.

2. Quality Control
2.1 Concrete Control
It has to be ensured that the delivered concrete is in compliance with the technical
specifications and the practical requirements for the pouring process/piling works.
Before the actual concreting of a pile starts, slump and slump flow tests will be made for each
mixer concrete trucks by the Main-Contractor on site to confirm the workability of the
concrete. The supplier of the concrete makes test cubes of a certain percentage of batches
from concrete taken from the trucks on site and tests them as per requirements and
specifications.

BG.1604.B01 Page 8 of 12
NAMAKHVANI HPP CUT-OFF WALL PROJECT, GEORGIA
General Method of Statement for Secant Pile Wall

2.2 Accuracy Control


- Survey and checking of guide wall location
- Control verticality of pile bore during drilling
- Control of concrete level during and after concreting

2.3 Check of Excavated Soil


The excavated spoil will be continuously observed to confirm the soil report. In case of any
variation, the construction method and the used drilling tools may be adapted to the new soil
conditions, if required. Type of soil will be recorded in a log.

2.4 Determination of the Final Depth


Upon reaching the designed depth and cleaning the pile base, the final depth will be con-
firmed additionally to the online check of the drill rig itself or by ballasted measurement tape.

2.5 Concrete Testing


It has to be ensured that the delivered concrete is in compliance with the technical
specifications and the practical requirements for the pouring process.
Before the actual concreting of a pile starts, slump and slump flow tests will be made by the
supplier to confirm the workability of the concrete. The supplier of the concrete makes test
cubes of a certain percentage of batches from concrete taken from the trucks on site and tests
them as required.

2.6 Pile Records


The following data will be assembled for each pile:
- Record of soil strata
- Drilling depth
- Concrete consumption
- Dates and times of all operations
A sample of Pile record Sheet is given in Appendix A.

BG.1604.B01 Page 9 of 12
NAMAKHVANI HPP CUT-OFF WALL PROJECT, GEORGIA
General Method of Statement for Secant Pile Wall

3. Appendices
3.1 Appendix A: Pile record

BG.1604.B01 Page 10 of 12
NAMAKHVANI HPP CUT-OFF WALL PROJECT, GEORGIA
General Method of Statement for Secant Pile Wall

3.2 Appendix B: General Layout & Elevation Drawing

BG.1604.B01 Page 11 of 12
NOTES

1) All dimensions are in meters (unless otherwise stated)

2) Working platform elevation = +235.00m

3) Lengths of SPW to be verified and confirmed at the site


with respect to level of basalt / andesite rock formation.

4) Overlap between adjacent piles = 500mm

M01
F01

M02
F02

M03
F03

M04
F04

M05
F05

M06
F06

M07
F07

M08
F08

M09
F09

M10
F10

M11
F11

M12
F12

M13
F13

M14
F14

M15
F15

M16
F16

M17
F17

M18
F18

M19
F19

M20
F20

M21
F21

M22
LEGEND

F22

M23
F23

M24
F24

M25
F25

M26
F26

M27
F27

M28
F28

M29
F29

M30
F30

M31
F31

M32
F32

M33
: Secant Pile Wall Ø 1500 mm - 63 pieces

F33

M34
F34

M35
F35

M36
F36

M37
F37
(Primary-Unreinforced)

M38
F38

M39
F39

M40
F40

M41
F41

M42
F42

M43
F43

M44
F44

M45
F45
: Secant Pile Wall Ø 1500 mm - 62 pieces

M46
F46

M47
F47

M48
F48

M49
F49
(Secondary-Unreinforced)

M50
F50

M51
F51

M52
F52

M53
F53

M54
F54

M55
F55

M56
F56

M57
F57

M58
F58

M59
125.50 m

F59

M60
F60

M61
F61

M62
F62

F63
Ø1.50 m

0.5m 0.5m 0.5m 0.5m

1.0m 1.0m 1.0m 1.0m

Final Top Elevation of Cofferdam


+254.00

REVISION DATE REVISION ITEM


00 24.05.2021 FOR TENDER

125.50 m
M01

M02

M03

M04

M05

M06

M07

M08

M09

M10

M11

M12

M13

M14

M15

M16

M17

M18

M19

M20

M21

M22

M23

M24

M25

M26

M27

M28

M29

M30

M31

M32

M33

M34

M35

M36

M37

M38

M39

M40

M41

M42

M43

M44

M45

M46

M47

M48

M49

M50

M51

M52

M53

M54

M55

M56

M57

M58

M59

M60

M61

M62
F01

F02

F03

F04

F05

F06

F07

F08

F09

F10

F11

F12

F13

F14

F15

F16

F17

F18

F19

F20

F21

F22

F23

F24

F25

F26

F27

F28

F29

F30

F31

F32

F33

F34

F35

F36

F37

F38

F39

F40

F41

F42

F43

F44

F45

F46

F47

F48

F49

F50

F51

F52

F53

F54

F55

F56

F57

F58

F59

F60

F61

F62

F63
Top Elevation of Wall
+235.00
1604
+232.79 PROJECT NAMAKHVANI HPP CASCADE CUT-OFF WALL PROJECT

+231.08

+229.38 CLIENT
+227.69

+225.31 CONTRACTOR
Estimated Rock Elevation
+223.67

+221.33 DRAWING GENERAL LAYOUT & ELEVATION

+219.59

SCALE : nts DESIGNED BY :


+217.55

SHEET SIZE : A3 DRAWN BY :

D ER
TYPE : TEN CHECKED BY :
FOR APPROVED BY :

REVISION NO. : 00
DATE : 24.05.2021

DRAWING NO. 1 6 0 4 T 0 1 - 0 1