PROPOSED SOUTH BEACH WELIGAMA

CONDOMINIUM DEVELOPMENT AT
WELIGAMA

METHOD STATEMENT
FOR
SWIMMING POOL WALL
CONSTRUCTION
Method Statement for Swimming Pool
Wall Construction

TABLE OF CONTENTS PAGE NO

1 Purpose ................................................................................................................................................ 2
2 Specification References ...................................................................................................................... 2
3 PPE Materials ...................................................................................................................................... 2
4 Materials ............................................................................................................................................... 2
5 Plant and Equipment........................................................................................................................... 3
6 Resources and Manpower ................................................................................................................... 4
7 Methodology ......................................................................................................................................... 4
8. Inspection & approval ………………………………………………………………………..………7

Buildmart Lanka (Pvt) Ltd Page 1


Method Statement for Swimming Pool
Wall Construction

1. Purpose

➢ The main purpose of this method statement is to explain the procedure of swimming
pool construction.

2. Specification References

➢ Structural Consultant’s guidelines and notes.


➢ BS standards and CIDA guidelines and specifications.
➢ Relevant / applicable construction drawings.

3. PPE Materials

➢ Following PPE (Personal Protective Equipment) should be provided in


order to all work.
• Safety Helmets
• Safety Boots
• Hand Gloves
• Safety Masks

4. Materials

• 15mm coated Plywood


• Grade 30 ready mix concrete
• Wire nails
• Concrete Nails
• 2”x 2” Timber
• 2”x 4” Timber
• 4”x 4” Timber
• “T” Jack
• “U” Jack
• Acro jack
• GI Pipes
• Form Tie
• Thread bar

Buildmart Lanka (Pvt) Ltd Page 2


Method Statement for Swimming Pool
Wall Construction

• P cone
• Chains
• Turn Buckles
• Mould oil
• Scaffoldings
• Cross bracing
• Join pin
• GI clamps

5. Plant and Equipment

• Power Saw
• Tower crane
• Transit mixers
• Concrete pump
• Mechanical/Electrical vibrators
• Masonry trowel
• Electric Drill
• Hammer
• Nail Puller
• Total station
• Level instrument
• Measuring Tape
• Set Square
• Plum bobs
• Marking boat
• Water level
• Spirit level

Buildmart Lanka (Pvt) Ltd Page 3


Method Statement for Swimming Pool
Wall Construction

6. Resources and Manpower

➢ Site manager
➢ Site Engineer
➢ Assistant Engineer
➢ Supervisor
➢ Survey Helpers
➢ Un Skill Labour
➢ Carpenter
➢ Mason
➢ Health and Safety Officer

7. Methodology

➢ 7.1 Setting Out

• The detailed drawings will be used for setting out work.


• Line Setting out for form work.
• MEP clearance shall be taken before erection of form work.
• Erection of formwork shall be done in several stages accordingly.
• The Levels and line will be checked by supervisors before Erection of Formwork.
• On field inspections and approvals sign off by team confirming consulting Engineer
and Contractor representative

➢ 7.2 Preparation for Formwork

• Initially all the panels prepared at formwork fabrication yard and then directly install
and combine at the construction site.
• Wall formwork prepare by panels as shown in Figure 1 & 2
• Mould oil will be applied on the 15mm plywood board to improve the removal of
formwork.

Buildmart Lanka (Pvt) Ltd Page 4


Method Statement for Swimming Pool
Wall Construction

SECTION OF WALL FORMWORK


Figure 1

ELEVATION OF WALL FORMWORK


Figure 2

➢ 7.3 Erection of Formwork

• Before erection area shall be cleaned to remove all debris, dust, rust, etc.
• A cleaning pocket shall be arranged at the bottom of wall for work to facilitate final
cleaning.

Buildmart Lanka (Pvt) Ltd Page 5


Method Statement for Swimming Pool
Wall Construction

• Erect the formwork by providing sufficient props and struts including necessary bracing as
per above figures. Seal gaps in formwork by using tapes & 2 to 3mm sponge strip to avoid
leakage of grout.

• In wall form work, Threaded tie rod with cone arrangement shall be used. Furthermore, the
tie rod shall be equipped with a water stopper (casting nut & washers).

• Alignment & verticality of formwork shall be checked. Each structural element’s


Allowable dimensional Tolerance must be following the structural specification.

➢ 7.4 Pouring Concrete

• Grade 30 ready mix concrete shall be used for swimming pool walls.
• Pouring of concrete shall be done using pump car or tower crane.
• Concrete pouring shall be done in four stages. Pouring sequence & construction joint of
wall as shown in figure 3.
• Vertical wall shall be cast up to required level without any further horizontal construction
joint.
• Vertical MS water bar shall be placed in construction joint.
• Approved bonding agent shall be applied at the construction joint before concrete the new
part.
• All concrete work shall be done as per approved method statement of concrete.

POURING SEQUENCE & PROPOSED CONSTRUCTION JOINT


Figure 3

Buildmart Lanka (Pvt) Ltd Page 6


Method Statement for Swimming Pool
Wall Construction

➢ 7.5 Removal of Formwork

• Support removal will be carried out in such a way that no any damage occurred to a
concrete structure.
• Removal of form work shall be done after 7 days

• All the removed supporting materials will be stacked properly and all the debris should be
cleaned after removal of supports.

• Once the panels removed all the “P Cone” holes will be patched by approved non-
shrink grout as per the specification

➢ 7.6 Curing

• Curing should be done for 7 days.


• After 24hours of laying of concrete, the surface shall be cured by spray water.

8.Inspections and Approvals


➢ On field site inspections and approvals sign off by team confirming
consulting Engineer and Contractor representative.

9.Health and Safety


➢ In accordance with the BML Health and safety guidelines.

Buildmart Lanka (Pvt) Ltd Page 7