Professional Documents
Culture Documents
CONDOMINIUM DEVELOPMENT AT
WELIGAMA
METHOD STATEMENT
FOR
SWIMMING POOL WALL
CONSTRUCTION
Method Statement for Swimming Pool
Wall Construction
1 Purpose ................................................................................................................................................ 2
2 Specification References ...................................................................................................................... 2
3 PPE Materials ...................................................................................................................................... 2
4 Materials ............................................................................................................................................... 2
5 Plant and Equipment........................................................................................................................... 3
6 Resources and Manpower ................................................................................................................... 4
7 Methodology ......................................................................................................................................... 4
8. Inspection & approval ………………………………………………………………………..………7
1. Purpose
➢ The main purpose of this method statement is to explain the procedure of swimming
pool construction.
2. Specification References
3. PPE Materials
4. Materials
• P cone
• Chains
• Turn Buckles
• Mould oil
• Scaffoldings
• Cross bracing
• Join pin
• GI clamps
• Power Saw
• Tower crane
• Transit mixers
• Concrete pump
• Mechanical/Electrical vibrators
• Masonry trowel
• Electric Drill
• Hammer
• Nail Puller
• Total station
• Level instrument
• Measuring Tape
• Set Square
• Plum bobs
• Marking boat
• Water level
• Spirit level
➢ Site manager
➢ Site Engineer
➢ Assistant Engineer
➢ Supervisor
➢ Survey Helpers
➢ Un Skill Labour
➢ Carpenter
➢ Mason
➢ Health and Safety Officer
7. Methodology
• Initially all the panels prepared at formwork fabrication yard and then directly install
and combine at the construction site.
• Wall formwork prepare by panels as shown in Figure 1 & 2
• Mould oil will be applied on the 15mm plywood board to improve the removal of
formwork.
• Before erection area shall be cleaned to remove all debris, dust, rust, etc.
• A cleaning pocket shall be arranged at the bottom of wall for work to facilitate final
cleaning.
• Erect the formwork by providing sufficient props and struts including necessary bracing as
per above figures. Seal gaps in formwork by using tapes & 2 to 3mm sponge strip to avoid
leakage of grout.
• In wall form work, Threaded tie rod with cone arrangement shall be used. Furthermore, the
tie rod shall be equipped with a water stopper (casting nut & washers).
• Grade 30 ready mix concrete shall be used for swimming pool walls.
• Pouring of concrete shall be done using pump car or tower crane.
• Concrete pouring shall be done in four stages. Pouring sequence & construction joint of
wall as shown in figure 3.
• Vertical wall shall be cast up to required level without any further horizontal construction
joint.
• Vertical MS water bar shall be placed in construction joint.
• Approved bonding agent shall be applied at the construction joint before concrete the new
part.
• All concrete work shall be done as per approved method statement of concrete.
• Support removal will be carried out in such a way that no any damage occurred to a
concrete structure.
• Removal of form work shall be done after 7 days
• All the removed supporting materials will be stacked properly and all the debris should be
cleaned after removal of supports.
• Once the panels removed all the “P Cone” holes will be patched by approved non-
shrink grout as per the specification
➢ 7.6 Curing