You are on page 1of 7

Risk-based PLM

Tooling and
Machinery Design and
Manufacturing
A white paper by

Richard Harpster

and

Dr. Suresh C. Rama


Risk-Based PLM For Tooling and Machinery Design and Manufacturing

Key Words: FMEA, Machinery FMEA, MFMEA, Process FMEA, PFMEA, Design Validation Plan, Design Verification
Plan, Usage Risk Assessment, URA™, Application FMEA, Process Validation Plan, failure mode and effects analysis,
failure mode, Requirements Risk Assessment, RRA®, Class, Risk-Based PLM, RBPLM®.

SUMMARY & CONCLUSIONS audit to it. The core requirements of the ISO 9001:2015
standard with respect to risk-based thinking required for
The Machine Tool Industry has struggled for years trying companies seeking compliance to ISO 9001:2015 1 are:
to implement Risk-Based PLM tools. The requirement
for their proper implementation has received additional 1. Determine the processes needed for the QMS system;
emphasis with the introduction of ISO 9001:2015 and its 2. Define the inputs and outputs of the QMS processes;
requirement for the implementation of risk-based thinking 3. Determine the sequence and interaction of the QMS
when managing the business. processes;
4. Define the risks created by the QMS processes;
The purpose of this paper is to describe an ISO 9001:2015 5. Prioritize actions to reduce or eliminate the sources
compliant Risk-Based PLM System currently being based on the levels of risks that they are causing.
implemented at Valiant TMS, a global Machine Tool 6. Use risk-based Plan-Do-Check-Act (PDCA) process
Builder. The system is applicable to any company in the to evaluate process changes to reduce or eliminate the
Machine Tool Industry. The paper will cover applying sources of risk.
Risk-Based PLM tools from the definition of Customer
Requirements through to the installation and maintenance 3 SOURCES OF RISK
of the machine tool. Special attention will be paid on how
to properly implement the Machinery FMEA (MFMEA) There are five major sources of risk that all Machine Tool
and the common mistakes made when doing so. The Builders face. The first is exposure to harm due to
obstacles experienced by Valiant TMS while incorrect or incomplete customer requirements. Talk to
implementing Risk-Based PLM will also be discussed. any Machine Tool Builder for almost any industry and
you will hear the problems that incomplete, incorrect or
1 WHAT IS RISK? changing Customer Requirements cause them in terms of
increased costs and delivery times. There are many
Risk has two components. The first component is the reasons for why it is so difficult to properly define
consequences of an event when it occurs. The Customer Requirements including the many different
consequences can take on many forms including financial customer requirement types and the quantity of
loss or in the worst-case bodily injury. The second requirements per type.
component of risk is the probability of the event
occurring. Consequently, one can reduce the risk of a The problem of reducing risk due to Customer
particular event by taking steps to mitigate the Requirements gets even more difficult when a company is
consequences when the event occurs or to reduce the attempting to design and manufacture a single piece of
probability of the event. machinery for multiple customers. Since different
customers can have different requirements, it is not
uncommon that a company cannot come up with a set of
2 ISO 9001:2015 AND “RISK-BASED THINKING” Customer Requirements that represent the needs and
wants of all customers. The Machine Tool Builder finds
The main difference between ISO 9001:2015 and ISO itself facing the risk of losing some of its customers due
9001:2008 is the use of risk-based thinking was implicit to the selection of Customer Requirements it decides to
in the ISO 9001:2008 standard while there are attempt to fulfill.
documented requirements for its use in the ISO
9001:2015 standard. The ISO 9001:2015 standard The second source of risk exposure that the Machine Tool
requires the company to implement risk-based thinking to Builder faces is incorrect Machine Tool Design
determine the potential causes of process and QMS Requirements. Machine Tool Builders cannot design to
failures and to implement actions to eliminate or reduce the language contained in customer requirements.
the probability of the causes to an acceptable level. Consequently, the Customer Requirements must be
translated to design requirements in the language of the
By design, the ISO 9001:2015 standard is non- Machine Tool Builder. Unfortunately, it is almost
prescriptive and offers only general guidelines on how to impossible to define a set of design requirements that
implement risk-based thinking. This has created a lot of when Machine Tool is built to them will result in Machine
confusion within Machine Tool Builders who want to be Tool that meets all the customer requirements. This is
compliant with the standard and the auditors attempting to due to the fact that the multiple Customer Requirements
defined can be competing, conflicting or beyond the
limits of technology.

The third source of risk exposure that the Machine Tool


Builder faces is that the Machine Tool is not designed to
meet all the design requirements. The problem can be
that like the customer requirements, the multiple design
requirements that must be met to meet them can be
conflicting, competing and beyond the limits of
technology.

The fourth source of risk exposure that the Machine Tool


Builder faces is that the Machine Tool is not built to the
design specifications. There can be many reasons for this
including out of specification materials and components
received from outside suppliers. Another source of the
exposure to the risk is the assemblers making errors while
building the Machine Tool.

The fifth source of risk exposure that the Machine Tool


Builder faces is improper installation, maintenance and
usage of the Machine Tool. Of all the sources of risk
exposure, this can be the most difficult source to limit.

4 THE VALIANT TMS RISK-BASED PLM SYSTEM

The Valiant TMS Risk-Based PLM System is a risk-based


product life cycle management system designed for
Machine Tool Builders. The major objective of the
Valiant TMS Risk-Based PLM System is to reduce the
Machine Tool Builder’s risk exposure due to the five Figure 1: The Valiant TMS Risk-Based PLM System
sources previously defined.

The Valiant TMS Risk-Based PLM System (Figure 1) is One important role of the RRA® is to assess the feasibility
comprised of 6 core processes. They are: of the Customer Requirements and Machine Tool Design
Requirements. It is very important for the Machine Tool
1. Define Customer Requirements; Builder to know if there are any Customer or Machine
2. Define Design Requirements; Tool Design Requirements that the Machine Tool Builder
3. Design Machine Tool; lacks the current capability of meeting them. The
4. Design Usage Instructions; possible exposure to risk is very high under these
5. Design Manufacturing Process; conditions if the Machine Tool Builder accepts the job
6. Build Tool Using Manufacturing Process. and fails to develop the required capabilities. The
potential types of harm include large financial losses,
There are four core risk management tools in the Valiant damage to reputation and damage to the
TMS Risk-Based PLM System. They are the Customer/Machine Tool Builder relationship.
Requirements Risk Assessment® (RRA®), Machinery
FMEA, Usage Risk Assessment™ (URA™) (aka The RRA® is also used to assist in the performance of
Application FMEA or Customer Process FMEA) and additional activities including Machine Tool Design
Process FMEA on building of Machine Tool. Validation, Customer Requirement change control,
Design Requirement change control and Rapid Integrated
Performed prior to the release of design requirements to Problem Solving (RIPS®).
the Machine Tool designer, the Requirements Risk
Assessment® (RRA®) is designed to reduce risk exposure Performed prior to the release of the design specifications
due to improperly or incompletely defined Customer to Machine Tool manufacturing, the Machinery FMEA is
Requirements captured through the Voice of the designed to reduce risk exposure due to improperly
Customer (VOC) as well as improperly or incompletely defined Machine Tool Design Specifications. The
defined Machine Tool Design Requirements. Machinery FMEA is also used to assist in the
performance of additional activities including Machine
Tool Design Verification, Machine Tool design
specification change control and RIPS®). The Machinery
FMEA also drives the performance of the Usage Risk One of the most common mistakes made when
Assessment™ (URA™) and Process FMEA on the completing the “Requirements” column of the MFMEA is
manufacturing process used to manufacture the Machine to use the column as a Bill of Materials and list all sub-
Tool. assemblies and components along with their function
(Figure 3).
Performed prior to the release of the installation, usage
and maintenance instructions to the customer the URA™ A second mistake made when performing a MFMEA is
is designed to reduce risk exposure due to improperly filling out the Failure Cause column of the before the
installed, used and maintained Machine Tools. The Machine Tool design has been documented. The
URA™ is sometime referred to as a Process FMEA on MFMEA is a risk assessment of the Machine Tool Design
the use of the Machine Tool by the customer. before its release. Consequently, you must have a
Information provided by the URA™ is used to assist in Machine Tool design to assess before you can perform an
Machine Tool installation, usage and maintenance MFMEA. It is not uncommon to have customers require
instruction creation, instruction change control and the completion of the initial MFMEAs and Usage Risk
RIPS®. Assessments (aka Application FMEA or Customer
Process FMEA) before the Customer Requirements for
Performed prior to the release of the manufacturing the Machine Tool have been finalized. A proper MFMEA
process for manufacture of the Machine Tool, the Process cannot be performed under these conditions.
FMEA is designed to reduce risk exposure due to
improperly manufactured and assembled Machine Tool.
The Process FMEA is also used to assist in Machine Tool
manufacturing and assembly instruction creation,
instruction change control and RIPS®.

5 MACHINERY FMEAS AND COMMON MISTAKES

Unfortunately, the majority of MFMEAs are done


incorrectly. The are many reasons for this. Following are Figure 4: Common MFMEA Mistakes – Enter Conditions of
six different mistakes commonly found in a typical Machinery/Tooling in Cause Column
MFMEA.
A third mistake made when performing a MFMEA is to
list objectionable tooling conditions in the ‘Failure
Cause” column. (Figure 4) Objectionable conditions of
the Machine Tool are “Failure Modes” of the Machine
Tool design and not “Failure Causes”.

Figure 2: MFMEA – Requirement, Failure Mode, Failure


Effects and Severity (SEV) Rating Columns

The most important column of the MFMEA is the


“Requirements” column used to capture the Machine Tool
Design Requirements (Figure 2). The number one Figure 5: Common MFMEA Mistakes – Mitigation Controls In
mistake when performing MFMEAs is improperly or Design Controls Column
inadequately completing this column.
A fourth mistake made when performing a MFMEA is to
list Preventative Maintenance items in the Design
Controls column. (Figure 5) MFMEA Design Controls
are always methods for assessing the adequacy of the
Machine Tool design.

Figure 3: Common MFMEA Mistakes – Construct BOM In


Requirements Column
condition identified in the Failure Cause column. A
rating corresponding to the probability is placed in the
Occurrence Rating (Occ) column. The OCC rating is then
used to calculate the RPN which is SEV x OCC x DET.
A sixth mistake is to use the RPN value to determine
which sources of risk to address. A better method is to
use the Risk Matrix (Figure 9).

Figure 6: MFMEA – Mitigation Controls

The Machine Tool designer would like to be able to create


Machine Tools that do not physically change over time.
Unfortunately, this not possible and the performance of
the Machine Tool can change when these physical
changes happen. The Mitigation Controls are controls
either performed by the Machine Tool or the Machine
Tool user to prevent the presence of physical changes that
can result in reduced machine tool performance (Figure
6). This column is very valuable in defining the required
preventative maintenance that must be done by the user.

Figure 9: MFMEA – Use Risk Matrix to Determine Class


Column Entries
The Risk Matrix can take on different forms. All Risk
Matrices have zones base on Severity of Harm. The
example Risk Matrix provide has a Safety/Legal Zone
(S/L) and Return/No Buy Zone where the S/L Zone
represents a much higher level of harm. The SEV and
OCC ratings are used to look up the Class Symbol in the
Risk Matrix. If there is no Class Symbol for the SEV and
Figure 7: Common MFMEA Mistakes – No Mitigation Controls OCC combination, the risk is considered acceptable and
Column no improvements to the Machine Tool design are
required. Items in the highest harm zone furthest to the
A fifth mistake made when performing the MFMEA is to right should be worked on first.
exclude the Mitigation Controls column from the
MFMEA form (Figure 7).

Figure 8: MFMEA – Use DVP Derived from MFMEA To Figure 10: MFMEA – Class Column Populated
Determine OCC and Calculate RPN
It is very important to understand that it is the Class
The next step in performing the MFMEA process is to column and not the RPN that is used to determine what
perform the Design Controls identified in the MFMEA must be worked on in the MFMEA. In the above
(Figure 8). The results of the performance of the Design example, the row with the RPN of 168 would not be
Control(s) are used to determine the probability of worked on while the row with the RPN of 96 would
exposure to harm due to the design requirement not being (Figure 10). One should never use RPN thresholds.
met because of the Machine Tool design specification
6 OBSTACLES TO RISK-BASED PLM IMPLEMENTATION 8 OBSTACLE #2: CUSTOMER LACK OF KNOWLEDGE
OF RISK-BASED PLM TOOLS

There are four major obstacles facing the Machine Tool The most common problems that occur as a result of lack
Builder when attempting to implement Risk-Based PLM of Customer knowledge of Risk-Based PLM Tools are
properly. They are: improper timing for their creation and improper methods
used for selection of the high-risk items identified by the
1. Previous poor experiences with Risk-Based PLM Risk-Based PLM tools to work on.
tools;
2. Customer lack of knowledge about Risk-Based PLM When it comes to improper timing a common problem is
tools; the Customer deliverable timing charts requiring the
3. Supplier lack of knowledge about Risk-Based PLM MFMEA and PFMEA to be completed too early. The
tools; purpose of the MFMEA is to assess the adequacy of the
4. Lack of time and resources to complete. Machine Tool in meeting the Machine Tool Design
Requirements. Due to the highly compressed delivery
time structure of Machine Tool industry, some
7 OBSTACLE #1: PREVIOUS POOR EXPERIENCES WITH Customers’ deliverable timing charts call for completion
RISK-BASED PLM TOOLS of the first version of the MFMEA before the Design
Requirements for the Machine Tool are approved by the
Most people within the Machine Tool industry have not customer.
had a good experience with Risk-Based PLM tools. The
most common Risk-Based PLM tools used by the industry The purpose of the Process FMEA (aka Usage Risk
are the MFMEA and Process FMEA on the use of the Assessment or Application FMEA) on the use of the
Machine Tool by the customer (URA™). Machine Tool is to assess the adequacy of install, usage
and maintenance instructions for the Machine Tool. Like
The MFMEA is typically done too early to be performed the MFMEA, Customer deliverable timing charts can
correctly or too late to be of value. The MFMEA is rarely cause problems when they require the completion of the
used to drive a Design Verification Plan to assess the Process FMEA on the use of the Machine Tool before
adequacy of the Machine Tool design. Finally, most Machine Tool design has been finalized.
MFMEAs when complete look more like Process FMEAs
on the use of the Machine Tool. Selection of what to work on can also be a problem when
the Customer does not understand Risk-Based PLM tools.
Most machine tools have considerable complexity. The Many Customers use RPN thresholds to determine what
typical MFMEA lacks sufficient detail to properly address to work on in the MFMEA and Process FMEA on use of
the complexity of the Machine Tool that the MFMEA is Machine Tool by the Customer instead of the Class
being performed on. Column. If RPN thresholds are used instead of the Class
Column, there is high likelihood of the Customer wanting
When the MFMEA is done incorrectly and at the wrong the Machine Tool builder to work on the incorrect issues.
time, the value of the MFMEA process is severely
degraded. The vast majority of MFMEAs created by the
Machine Tool Builder have historically been performed to 9 OBSTACLE #3: SUPPLIER LACK OF KNOWLEDGE OF
meet a paper deliverable requirement rather than to RISK-BASED PLM TOOLS
improve the quality of the Machine Tool design.
If the Machine Tool Builder must integrate Machine
The Machine Tool Builder typically does a much better Tools designed by suppliers into their Machine Tool
job of performing the Process FMEA on the use of the deliverable, the Machine Tool Builder can find itself
Machine Tool by the customer than they do performing unable to use the Risk-Based PLM tools properly because
the MFMEA on the design of the Machine Tool. the suppliers have not properly used the applicable Risk-
Although there can be several reasons for this, the most Based PLM tools and consequently have not provided the
common is that it is much easier to define the mistakes appropriate documentation. The solution to this problem
users can make in the use of the Machine Tool to cause it is not always easy.
to function incorrectly than attempting to define all the
design mistakes that may have been made to cause the The best case is the supplier takes it upon itself to learn
failure. Like the MFMEAs, the Process FMEA how to use the tools correctly. The next best solution is
performed on the use of the Machine Tool by the that the supplier is willing to answer questions show you
customer typically lacks sufficient detail to cover the can obtain the information normally found in properly
complexity of the Machine Tool. constructed Risk-Based PLM documents created by the
supplier. The worst case is the supplier refuses to learn or reprinting/republishing this material for advertising or
work with the Machine Tool Builder. In this case, the promotional purposes, creating new collective works, for
Machine Tool Builder may have to find a new supplier resale or redistribution to servers or lists, or reuse of any
unless the supplier has been selected by the customer. copyrighted component of this work in other works.”

10 OBSTACLE #4: LACK OF TIME AND RESOURCES TO BIOGRAPHIES


COMPLETE
Richard Harpster is president of Harpco Systems Inc.
The Machine Tool industry has a highly compressed which he founded in 1987. Harpco Systems specializes in
delivery schedule. It is not uncommon to require the providing software, training and consulting for Risked
delivery of over 100 Machine Tool stations in less than a Based Product Lifecycle Management (RBPLM®). Over
year. Machine Tool Stations can be extremely complex the past 30 years Mr. Harpster has helped hundreds of
with hundreds or thousands of components. The question companies implement improved risk-based design and
becomes how does the Machine Tool Builder properly use manufacturing systems in a wide variety of industries. He
Risk-Based PLM tools given the volume of Machine is a recognized expert in the application of FMEAs and
Tools the Risk-Based PLM tools must be used on? invented several new concepts including the linking of
Design FMEAs to Process FMEAs in 1990 which became
The answer is you must leverage your knowledge. an automotive industry standard eighteen years later. His
Whenever a Machine Tool Builder places a component in latest inventions in the field of RBPLM® include
a Machine Tool it should trigger a best practice design Requirements Risk Assessment™ (RRA®), Multiple
response, manufacturing response and usage response. Integrated Cause Analysis (MICA™) and Rapid
The various Risk-Based PLM tools are used to measure Integrated Problem Solving (RIPS®). He has published
the adequacy of these responses and determine where several papers on the topic of RBPLM®.
changes are required to optimize the Machine Tool’s
risk/benefit ratio. Prior to starting Harpco Systems, Richard spent 14 years
at Ford Motor in a wide variety of positions including
A computer-based tool must be found or created by the Plant Manager. His education includes a B.S.E.E. from
Machine Tool Builder that enables the Machine Tool Penn State University, M.S.E.E from the University of
Builder to leverage these best practice responses. There Detroit and an M.B.A. from Eastern Michigan University.
are many Risk-Based PLM software tools on the market. He is a registered PE in the State of Michigan.
The Machine Tool Builder must perform the necessary
research and find the appropriate one that fits their E-mail: richard.harpster@harpcosystems.com
business.
Dr. Suresh C. Rama is currently Director of Global
11 CONCLUSION Engineering and Innovation at Valiant TMS – a global
Automation Company. Dr. Rama holds a Ph.D. M.E. from
The implementation of risk-based-thinking using Risk- Texas A&M University along with an M.B.A. from
Based PLM Tools in the Machine Tool design and build Michigan State University. Dr. Rama has extensive
process can lead to a significant improvement in Machine experience in implementation of lean quality systems
Tool quality, on time delivery and Machine Tool builder including Six Sigma. He has extensive experience in large
profitability. Although the rewards of the successful scale deployment of Design for Six Sigma including
implementation of risk-based thinking are considerable, understanding and responding to the Voice of the
obstacles to its successful implementation can be Customer. With experience in academia and industry, he
significant and come from many sources including the has unique perspectives on Innovation and Value
Machine Tool Builder’s customers, suppliers, past Engineering. He has mentored several Blackbelts in Rad
experiences with Risk-Based PLM tools and time and X Shainin and Lean Six Sigma techniques during his
resource limitations. Despite these barriers, successful tenure in FCA-Chrysler. In his involvement in the Design
companies understand that proper management of risk is a for Six Sigma deployment initiative, he promoted best
critical key to success. practice usage of FMEAs. Recently, in his role to improve
efficiency and effectiveness of automation systems and
REFERENCES tool designs at Valiant TMS, he has championed the
transformation of current practices into a risk-based
1. International Standard ISO 9001:2015: Quality methodology by promoting systems thinking and FMEAs.
Management System Requirements, 09-15-2015. He is using these ideas to manage several Business
Process Improvement initiatives, including
©2018 IEEE. Personal use of this material is permitted. implementation of a Company-wide PLM system.
Permission from IEEE must be obtained for all other uses,
in any current or future media, including E-mail: suresh.rama@valiantmachine.com

You might also like