Q1. (a) Find the value of median from the following data.  
Daily Wages   No. of Workers 

50-60  25 

60-70  30 

70-80  15 

80-90  18 

90-100  12 

Answer :  

 
 
(b) Calculate the standard deviation and variance of the marks of 36 students of Delhi University. 
Marks   No. of Students 

0-10  1 
10-20  13 

20-30  15 

30-40  2 

40-50  5 

Answer : 

 
 
Q2. Construct a pareto diagram for all types of errors discovered during surgical setup. 
Error Type   Frequency  

Excess Count   34 

Wrong Supplier  57 

Wrong Size  10 

Too Few Count  17 

Wrong Sterile Instruments Set  20 

Missing Item  8 

Damaged Item  6 

Other   2 

Answer : 
 

 
 
Q3. Mean values and ranges of data from 20 samples (sample size = 4) are shown in the 
table below: 

 
Plot x̅and R chart. What conclusions can you draw about statistical control? 
Answer :  
 

 
 
Conclusion from above control charts : 
1. In  the  X   chart,  3  points  lie  beyond  the  upper  control  limit  (UCL).  Hence  we  conclude  that  the  process 
average is out of control due to the presence of some assignable causes. 
2. In  the  R-chart,  all  points  lie  within  the  control  limits,  hence  it  is  concluded  that  process  variability  is  in 
control.  
 
Q6. A vendor ships components in lots of size 10,000. A single sampling plan with n = 89, 
c = 2 is being used for receiving inspection. Plot an OC Curve for this plan. 
Answer :  

 
 
Q7.  A  single  sampling  plan  is  given  as  -  Lot  size  N= 5000, n = 50 and c = 1. Plot an OC Curve and AOQ Curve 
for this plan. Also find AOQL. 
Answer :  
AOQL for the given sampling plan is approximately 0.0165. 
 
 

 
 