Professional Documents
Culture Documents
qsnqnd ssaJdx3
~
Z8AB48 )iJBif\J
Aa1ooo 1\uuar
SUB/\3 B!U!6J!J\
11 UO!l~nJlSUOJ
Published by Express Publishing
Made in EU
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or
transmitted in any form, or by any means, electronic, photocopying, or otherwise, without the prior
written permission of the publishers.
ISBN 978-1-4715-1535-4
...
Table of Contents
f:)
1
..
Answer Key ... . . . ..... . .. . . ......... . . . . ... . . ... . . .. ............... ... . ... . 4
Audioscripts ...... . . ... .......... . .......... . ....... ... . . . . . . .. . . .... ... . . . . 12
~
2
Answer Key ...... . . . . . . . . .. . . . .. . . ..... . . . ... .. . ......... . ... ... . ..... . . ... 14
Audioscripts . .. . . ... ........ .... ....... ....... . .. .. . . .... .... . .. .... . .. ... . 22
83
Answer Key . . . ................ ...... . . ............... .... .. . .. ...... ....... 25
Audioscripts .............. . .. . . ......... ................... . .. . . . . . ... . . . .. 34
Book Answer Key
Unit 1 2 F 2 T 3 F
1 Suggested Answers
3 E 2 A 3 C 4 B 5 D
1 Highways, freeways, boulevards, cui-de-sacs, alleys,
and toll roads are examples of roads and streets.
4 1 corner 3 storm drain 5 roadway
2 A toll road is not free to use.
2 shoulder 4 gutter
2 T 2 T 3 F
5 Suggested Answer
3 1 c 3 F 5 B The roads are in bad condition after a storm. There
2 E 4 D 6 A are tree branches all over the road. Leaves filled
storm drains and gutters, which caused flooding. A
4 1 freeways 3 Dead ends median was damaged and a streetlight fell.
2 Alleys 4 roads
6 A 2 c
5 Suggested Answer
7 1 going to clear 4 That way
A boulevard, a street, an avenue, and a road lead to
2 need to do 5 Sounds good
the office from the freeway.
3 No problem 6 get clogged
6 D 2 A
8 Suggested Answer
7 1 freeway 4 Avenue A: Your team is going to clear the roadway on Main
2 get off on 5 turn left onto Street.
3 highway 6 dead end B: Okay. What do we need to do?
A: First, move any big objects off the roadway.
8 Suggested Answer B: No problem. Anything else?
A: Clear the gutters of leaves. That way, water can
A: Can you drop these designs off at the client's
flow into the storm drains.
office?
B: Okay. I'll go get things started.
B: Yes, but I need directions.
A: Wait. Don't forget to check the pavement, too. If
A: Sure. You take the freeway north. Then you get
you don't, we might miss damage to the roads.
off on exit ten onto highway four.
B: Of course.
B: All right. Is it off the highway?
A: No, not quite. Next, you turn left onto Madison
9 Suggested Answer
Street.
B: Got it, left onto Madison. Then? Hanson Roadworks
A: You turn right onto James Boulevard. it's a dead Work Order
end. The client is at the end of James. Task 1: Remove large objects like branches from the
B: Okay, I'll head out now. road.
Task 2: Clear the storm drains of leaves. This will let
9 Suggested Answer water flow into the sewer.
Task 3: Clear the gutters of leaves. Otherwise the
Directions to Jackson Construction
drains will get leaves in them again.
1 Take the freeway south
2 Get on highway nine Unit 3
3 Turn right on Green Street
4 Turn left onto Washington Street Suggested Answers
1 Drivers can use the breakdown lane if their cars
Unit 2 break down.
2 Cars use an exit to leave a highway.
1 Suggested Answers
1 Lanes, curbs, medians, corners, shoulders, and 2 Widen: on ramps, off ramps
drains are some parts of a road. Repave: all lanes, express lane, fast lane
2 Drains are used to drain water from a road. Replace: dividers, guardrails
Create: breakdown lane
4 Answer Key
Book 1 Answer Key
3 1 D 3 E 5 F 5 Suggested Answer
2 A 4 c 6 B The two main types of intersections are ones that
require drivers to stop and ones that allow drivers to
4 1 exit 3 on ramp turn or cross without stopping.
2 breakdown lane 4 divider
6 F 2 T 3 T
5 Suggested Answer
Their journey times will be increased while the work 7 1 intersection of 4 roundabout
is going on, but once completed traffic will move 2 calls for 5 jughandle
more quickly and safely. 3 slow down 6 take another look
6 1 D 2 c 8 Suggested Answer
A: I have an idea for the intersection of 9th Street
7 1 highway project 4 close and Route 10.
2 What is it 5 dividers and guardrails B: What is it?
3 able to meet 6 some lanes A: The plan calls for a T -junction.
B: Yes, that's correct.
8 Suggested Answer A: I think that will slow down traffic too much.
A: Let's talk about the highway project. B: lt will. But there's no room for a traffic circle there.
B: Okay. What would you like to know? A: I know. But I think we could fit a jughandle.
A: Will you be able to meet the deadline? B: That's a good idea. Let's look at the plans again.
B: I think so. We're close.
A: I saw the new pavement and guardrails. What else 9 Suggested Answer
needs to be done? To: tjackson@cityplanner.org
B: A few things. We still have to install the divider. From: broberts@cityplanner.org
A: I see. That was supposed to be done already. Subject: Intersection Change
What happened?
B: Our supplier had a problem. lt took a long time for Dear Mrs. Jackson,
the materials to arrive. The Route 9 plan calls for a four-way intersection. I
think this will slow down traffic. A roundabout will not
9 Suggested Answer fit. Instead, I suggest we use a jughandle. Let me
know what you think.
HIGHWAY 109 CONSTRUCTION SCHEDULE
Sincerely,
Installation/Task Deadline
Bryan Roberts
Build express lane October 10
Install divider November 1
Pave all lanes November 30 Unit 5
Pave on ramps December 14 1 Suggested Answers
1 Asphalt, bitumen, and gravel are some materials
Unit4 used to build the surface of a road.
1 Suggested Answers 2 Rubber and fly ash are recycled to be used in
road construction.
1 T-junctions, 4-ways, roundabouts, jughandles, and
box junctions are some common types of
2 1 T 2 F 3 F
intersections.
2 Roundabouts and jughandles are two examples
of intersections that do not require a full stop.
3 1 c 2 D 3 E 4 A 5 B
Answer Key 5
Book 1 Answer Key
6 B 2 B 5 Suggested Answer
Some words used to describe increasing a total are
7 1 got an email 4 any ideas and, plus, and add. Some words to describe a total
2 was it about 5 we could amount are equals, comes to, and is.
3 recycled materials 6 fly ash
6 A 2 B
8 Suggested Answer
A: I got an email from our client. 7 1 take a look 4 came to
B: What was it about? 2 What's up 5 remember to add
A: She wants to use some recycled materials in the 3 goes for 6 plus
road project.
B: Do you have any ideas? 8 Suggested Answer
A: We could mix rubber into the asphalt. A: Will you take a look at this order?
B: Yes, that would make the traffic noise quieter. Or, B: Of course. What's up?
we could mix some fly ash into the concrete areas. A: it's this bill. it's way too high.
A: Good idea. I'll let the client know these options. B: We ordered ten tons of gravel. lt goes for ten
dollars per ton. Ten times ten is one hundred.
9 Suggested Answer A: But the total came to one hundred twenty.
Dear Mr. Anderson, B: Did you remember to add shipping costs?
A: Oh, no. I forgot.
I got your email about using recycled materials in the
B: That's it, then. The total was one hundred for the
road. I think we have two good options.
gravel, plus twenty for shipping.
First, we could mix rubber from old tires into the
asphalt. This would reduce the noise level of the 9 Suggested Answer
traffic on the road. To: carl.g@jacksonconstruction.com
Secondly, we could mix fly ash into the concrete. From: kate.r@jacksonconstruction.com
This would make the road stronger. Subject: Order Receipt
6 Answer Key
Book 1 Answer Key
5 Suggested Answer 3 1 c 3 B 5 E
The meter and yard are almost equal. Likewise, the 2 D 4 A 6 F
metric ton and the short ton are almost the same.
4 1 A wheelbarrow B measure wheel
6 B 2 D 2 A sledgehammer B jackhammer
Answer Key 7
Book 1 Answer Key
8 Suggested Answer
3 1 Drop off 3 Pick up 5 removed
A: So you'll start work next week. Do you have any 2 sweep 4 measured
questions?
B: Just one. Do I need to bring any equipment to the 4 c 2 A 3 E 4 D 5 B
job site?
A: Just a few things. You'll have to bring a hard hat. 5 Suggested Answer
B: That's no problem.
No. The gravel must be picked up.
A: Good. You'll also need some safety glasses or
goggles.
6 ./ 2 ./ 5 ./
B: That's fine. Will the company provide me with steel-
toe boots, kneepads, a face shield, and stuff like
7 1 work on 3 mark off 5 unloaded
that?
2 remove 4 start on 6 ready to
A: Bring your own boots, but we'll make sure you
have all the other stuff that you'll need.
8 Suggested Answer
9 Suggested Answer B: What should the crew work on today?
A: First, start clearing the area.
Dear Luke,
B: All right, I'll have some of the guys remove the
Welcome to Ace Construction! On your first day, you debris.
will need to bring several items with you, including: A: Then, we need to mark off the boundaries of the
1 A hard hat to protect your head from falling new lanes.
objects. B: I can start on that right away.
2 Safety glasses or goggles to protect your A: Next, make sure that all the gravel is spread
eyes from dust and flying objects. correctly.
3 Steel-toe boots to protect your feet if B: Okay. Got it.
something falls on them. A: Great. After that, we're ready to lay the road.
The company will provide:
9 Suggested Answer
1 Kneepads for when you are doing work on the
floor. Tasks to Complete
2 A face shield to block flying objects. The following tasks need to be completed on this
3 Earplugs ...to protect the ears when working construction project:
with loud tools.
• pick up gravel from the suppliers
Please direct all questions to your manager. • unload the gravel at the construction site
• mark off boundaries for the road
Unit 10 • move dirt from the area and make the surface level
• spread gravel
1 Suggested Answers
1 Workers must clear a site to prepare it for road
construction.
2 Paint is used to mark off an area.
8 Answer Key
Book 1 Answer Key
Unit 13 Unit 14
1 Suggested Answers 1 Suggested Answers
1 Sand, silt, and clay are some components of soil. 1 Mountainous landscapes with mountains and
2 A penetration test is one test that measures the rolling hills are landscapes that are difficult to build
strength of soil. roads on.
2 A body of water such as a river or a lake requires
2 F 2 F 3 F a bridge or a major rerouting of a road.
3 1 8 3 c 5 F 2 D 2 D 3 8
2 A 4 E 6 D
3 c 2 A 3 E 4 D 5 8
4 1 sub grade 4 Clay
2 C8R test 5 penetration test 4 1 flat 3 bend
3 soil 2 body of water 4 mountainous
10 Answer Key
Book 1 Answer Key
Unit 15
1 Suggested Answers
1 Rises, drops, and dips are some landscape features
around hills.
2 A dogleg is an example of a sharp turn.
2 1 F 2 T 3 F
3 1 8 2 A 3 D 4 c 5 E
...
4 1 slight 3 drop 5 rise
2 curve 4 dip
5 Suggested Answer
The road will not be able to have many flat
straightaways. lt will have to curve around a sharp
drop and some land may need to be leveled out.
6 A 2 A
8 Suggested Answer
A: How is the Route 10 expansion coming?
8: Well, it was going great until two days ago.
A: Really? What happened?
8: We got as far as three kilometers from the end of
the route. Then we ran into trouble.
A: What kind of trouble? A problem with the
landscape?
8: Yeah. We reached a large body of water. it's too
big to go around.
A: So we have to build a bridge?
8: I think so.
9 Suggested Answer
Josh Harrison
Highway 35 Expansion Progress
Point reached: The road is up to two kilometers from
the end of the expansion.
Problem: There is a problem with the landscape. We
have reached a sharp rise that we cannot go over.
Solution: We will have to curve the road around the hill.
Answer Key 11
Audioscripts
Worker 1: No, thanks. I was hoping you'd track down a Owner: That's great.
jackhammer. Manager: Yes, but there's a problem. We might not have
Worker 2: Oh, I think there's one in the truck. enough asphalt.
Worker 1: Great! Can you make sure? Owner: Find out and let me know. That way I can order
Worker 2: Yeah, I'll run down there now. some more.
Manager: Okay. What's the best way to contact you?
Unit9 Owner: I'll be around the site for a while. So you could
contact me on the two-way radio or just send me an
Manager (F): So Jacob, you'll start work on Monday. Do email.
you have any questions? Manager: All right, I'll do that.
Employee (M): Just one. Do I need to bring any equipment
to the job site?
Unit 13
Manager: Just a few things. You'll have to bring steel -toe
boots, for one. Manager (M): Claire, have you completed the CBR test
Employee: That's no problem. on that silt area?
Manager: Good. You'll also need some leather gloves. Technician (F): Yes, we just got the results back.
Employee: That's fine. Will the company provide me with Manager: Good. How did it go?
a hard hat, goggles, a face shield, and stuff like that? Technician: I have good news. The silt soil is actually
Manager: Bring a hard hat, but we'll give you the other stronger than we originally thought.
things. Manager: That's great to hear. So we can use it as sub
grade after all?
Unit 10 Technician: Yes. lt shouldn't be a problem.
Manager: Excellent. Do you have any more tests to do?
Foreman (F): Mr. Clark, what should the crew work on Technician: Just a couple more on the clay. I'll give you
today? a call when I have those results.
Supervisor (M): Well, first, I need you to gather a group
and start clearing the area.
Unit 14
Foreman: All right, I'll have some of the guys remove the
debris. Owner (M): What do you think of the plan for Highway 28?
Supervisor: Good. Then, we need to mark off the Manager (F): it's not the greatest. The area has rolling hills.
boundaries of the new lane. To keep the road level, we'll need to build around them.
Foreman: Of course. I can start on that right away. Owner: So there will be plenty of bends and sharp turns.
Supervisor: Great. Next, make sure that all the gravel is Manager: That's right.
unloaded correctly. Owner: Would it be better to build near Eagle Lake?
Foreman: Okay. Got it. Manager: Much better, actually. Aside from the lake, the
Supervisor: Great. After that, we're ready to spread it. area is flat.
Owner: Will we have to build a bridge over the lake?
Unit 11 Manager: That won't be necessary. We can build the
highway next to the lake.
Manager (F): Gary, let's go over the tasks for the week.
j Employee (M): Okay, Ma'am. What are we going to do?
Unit 15
Manager: We'll mainly be leveling ground for a new lane
on a road. Owner (F): Josh, how is the Highway 35 expansion coming?
~ Employee: So we'll need the grader and bulldozer, then. Manager (M): Well, it was going great until yesterday.
Manager: Yes. We'll probably want the backhoe, too. Owner: Really? What happened?
Employee: No problem. lt has a loader on its front end Manager: We got as far as two kilometers from the end
too, right? of the expansion. Then we ran into trouble.
Manager: Yes. That'!! save us having to bring another Owner: What kind of trouble? A problem with the
vehicle. landscape?
Employee: Good idea. I'll go get the equipment ready. Manager: Yeah. We reached a sharp rise. We planned on
going over it. But it's too steep.
Unit 12 Owner: So we'll curve the road around it?
Manager: Yeah, that's what I thought, too.
Owner (F): How is everything coming along, Daniel?
Manager (M): Pretty well. We're about to start paving the
road .
Answer Key 13
Book 2 Answer Key
Unit 1 Unit 2
1 Suggested Answer 1 Suggested Answer
1 Chain surveying is one method of surveying land. 1 Gyroscopic theodolites, optical and digital levels,
2 Station pegs, ranging rods, and measurement tape optical plumbs, total stations, and optical
are some of the equipment used when surveying micrometers are examples of surveying equipment.
land. 2 A digital level is more accurate.
2 T 2 F 3 F 2 B 2 c 3 D
3 1 c 3 A 5 B 3 1 A 3 D 5 B 7 G
2 E 4 D 6 F 2 E 4 c 6 F 8 H
Unit 3 Unit4
1 Suggested Answer 1 Suggested Answer
1 A map is used to identify and mark different land 1 Repeated alignment is one method of setting out
features. a line.
2 A centerline, a horizontal scale, and a detail 2 Steel pins and nylon line are some equipment
drawing are some features of a map or plan for used when setting out a line.
road construction.
2 1 Use repeated alignment.
2 1 c 2 c 3 D 2 Use curve ranging.
3 Double check calculations . ...
3 1 c 3 D 5 H 7 G 4 Calculate the angle and use right-angles or
2 E 4 A 6 F 8 B radiused corners.
7 1 emphasis on 4 difference in 6 F 2 T 3 F
2 a little distorted 5 along
3 horizontal scale 6 for a reason 7 1 setting out 4 So it's just
2 steel pins 5 Not exactly
8 Suggested Answer 3 one or two 6 repeated alignment
A: Joe, do you have a second?
B: Sure. What's up? 8 Suggested Answer
A: it's this plan. The hill here seems really emphasized. A: What are we working on today?
B: What do you mean? B: Today we're setting out a line.
A: lt seems that the vertical scale is distorted. A: Okay, I'd like to start right away. Where are the
B: The vertical scale has a 1:250 ratio compared to supplies?
the horizontal scale. lt has a 1:750 ratio. We want B: They're in the truck. We have steel pins and tape
to make sure we stress the elevation. measures.
A: Why's that? Is there that much difference in A: Wait, are we setting out one or two lines today?
elevation from the bottom of the hill and the top? B: We will start with one. Line two will take off from
., B: The hill is steeper than it is wide since. There are line one, later.
important details for the road along the slope. A: Sounds good. So it's just a simple straight line?
A: Okay. lt looked a little odd at first. B: No. The road path is flat, but it's around that big hill.
A: I see. So we'll use curve ranging?
9 Suggested Answer B: Yes. Make sure the other workers understand, too.
Downtown Project
Plan/Map notes 9 Suggested Answer
Harrison Road Construction
Horizontal scale: 1:500
Vertical scale: 1:100 Date: June 10
Project: Brown Avenue extension
Reason for difference: The road has several elevation
changes. To make sure we note important elevation Goal for the day: Set out line over hill.
details, the vertical scale has been exaggerated.
Steps/Notes: Gather nylon line and steel pins. Set out
line. Be sure to use repeated alignment. Point 2
cannot be seen from point 1 due to the hill.
Answer Key 15
Book 2 Answer Key
Unit 5 Unit 6
1 Suggested Answer 1 Suggested Answer
1 Excavating and compacting land both require 1 Swamps and marshes are difficult to build roads on.
heavy machinery. 2 Fascine construction uses sticks.
2 Trees need to be cleared during preparation of a
site for road construction. 2 F 2 T 3 T
2 D 2 A 3 A 3 D 2 A 3 E 4 B 5 c
16 Answer Key
Book 2 Answer Key
Unit 7 UnitS
1 Suggested Answer 1 Suggested Answer
1 Storm water can build up in an area after heavy 1 Pipes can be connected by bolting or with joints.
rain. 2 Rubber tube is flexible.
2 Workers gain access to a sewer system through
manholes. 2 B 2 D 3 A
2 B 2 B 3 c 3 1 F 3 G 5 E 7 H
2 D 4 B 6 c 8 A
3 1 E 3 c 5 A
2 F 4 D 6 B 4 1 A metal pipe B gasket
2 A pipe B Welding
4 1 A manhole B gradient
2 A sewer line B storm water 5 Suggested Answer
3 A self -cleansing velocity B Subsoil drainage The metal culvert can be connecting to other pipes
through bolting or welding.
5 Suggested Answer
The storm water isn't draining properly because the 6 F 2 T 3 T
soil is saturated and the sewer lines are blocked.
7 1 due for 4 hold off on
6 T 2 F 3 F 2 Hold on 5 install
3 at the earliest 6 trench
7 1 looking at 4 obstructions
2 messed up 5 self-cleansing velocity 8 Suggested Answer
3 standing water 6 drainage areas A: Hey, Joe, I want to check something with you.
B: What's up?
8 Suggested Answer A: Those corrugated pipes came in, right?
A: I'm glad you could come in. B: No, they're not due for a few days.
B: My pleasure. What are we looking at? A: Hold on, I thought they'd be coming sooner.
A: The storm messed up our drainage. B: No, not until tomorrow at the earliest. Did you
B: Yes, I saw the standing water. What's wrong with already start digging the trenches?
the sewer system? A: Yeah, but we need the pipes now. Should we hold
A: There must be some obstructions. off on other parts of the street then?
B: I can clear those. But shouldn't they reach self- B: Yes. Don't dig any more trenches for now.
cleansing velocity? A: Okay. I can do that. But what should we do until
A: The ditches overflowed. Too much trash got into the joints arrive?
the sewer. B: Hmm. We still need to connect a few other pipes.
B: I see. Well, where should I start? A: Got it. We'll weld those pipes today.
A: Unfortunately, many manholes are underwater B: And when that's done, the corrugated pipes
"' B: That's no problem. Just find one that's clear. We should be here.
have equipment that can take care of the rest.
9 Suggested Answer
9 Suggested Answer Murphy Street Pipe Construction
Damage Report Status Report:
Damaged sections of road: Main Street
Completed tasks: The damaged pipe under Murphy
Cause of damage: A storm caused drainage areas to street has been replaced.
overflow. Mud and trash from the ditches clogged the
Available materials: We have two joints and another
sewer lines. There is standing water in many streets.
polyethylene pipe available.
Solution: A contractor will clear the sewer line from
Materials to be delivered: We're still waiting for bolting
an available manhole.
and caulking materials to connect the pipes.
Answer Key 17
Book 2 Answer Key
Unit9 Unit 10
1 Suggested Answer 1 Suggested Answer
1 Cross drains, fin drains, edge drains, slope drains, 1 The sub-grade layer is the lowest layer of flexible
and pipe underdrains are some types of drains. pavement.
2 A cross drain runs below a road. 2 The wearing course is the top layer of flexible
pavement.
2 T 2 F 3 F
2 F 2 F 3 T
3 1 B 3 A 5 F
2 E 4 D 6 c 3 1 E 3 c 5 D
2 F 4 B 6 A
4 1 A discharge B soakaway
2 A French drain B trench 4 1 A base course B surface course
3 A pipe underdrain B land drain 2 A binder course B sub-grade course
18 Answer Key
Book 2 Answer Key
5 Suggested Answer 3 1 E 3 F 5 B
The woman asks about the number of vehicles that 2 A 4 c 6 D
will drive on the road, what the average traffic load
is, and how much the traffic will increase. 4 1 Abrasion 3 split friction
2 polished stone value 4 aggregate
6 F 2 F 3 T
5 Suggested Answer
7 1 just checking 4 have that to me The road surface performed poorly on the PSV test,
2 traffic growth 5 design thickness which means that it will lose skid-resistance due to
3 move forward 6 Right again abrasion.
8 Suggested Answer 6 1 c 2 c
A: Do you have time to go over the Main Street
project? 7 1 for a moment 4 not that bad
B: Of course. 2 small problem 5 the bad news
A: I'm just checking that I have things right. We have 3 Oh, no 6 polished stone value
to decide the design life first, correct?
8: Yes. 8 Suggested Answer
A: And you want a report on the traffic load? A: Can we talk for a moment?
8: Yes. We can't move forward without that. 8: Of course. Is something wrong?
A: When would you like that? A: There is a small problem. I got the inspection
.# B: I'd like it by Thursday. report on Highway 10.
A: Okay. And the next stage is planning the design 8: Oh, no! I thought we did a great job.
thickness, right? A: it's not that bad. The good news is that the PSV
8: lt is. We have to know that before we can start test came out well. They're also happy with the
construction. appearance of the road.
A: What do you need to know to do that? B: Good. But what's the bad news?
8: We need to know what type of vehicles will be A: The bad news is the result from the friction test.
using the road. 8: What's wrong?
A: The investigator is worried about split friction. One
9 Suggested Answer side of the highway has a little more skid-resistance
From: Mike Watson than the other.
To: All Engineers B: That's not good. How can we fix it?
Subject: Elm Street Project A: We'll just have to watch the condition of the road.
If it gets bad we'll have to repair it.
B: Okay. Keep me updated on any changes.
Answer Key 19
Book 2 Answer Key
9 Suggested Answer A: That's not good. Take your crew out there as soon
Highway Nine Inspection Report as you finish on Main Street.
B: it will be a while before we're done with Main
Test: Friction Test Street. The shoving is pretty bad.
Results: The highway has good skid-resistance. A: Is it dangerous?
Test: PSV Test B: No, not yet.
Results: The highway has a poor PSV value. The A: I'm glad to hear that. Okay, I'll send another crew
aggregate could become smooth due to abrasion. to Middle Street.
2 A 2 B 3 B 1 Suggested Answer
1 Transverse joints and longitudinal joints are some
3 1 F 3 D 5 H 7 G joints used in pavement construction.
2 c 4 B 6 A 8 E 2 CRCP is reinforced with steel.
4 1 slippage 4 irregularities 2 T 2 F 3 T
2 transverse cracking 5 Alligator cracking
3 reflective cracking 3 1 D 3 F 5 E
2 A 4 B 6 c
5 Suggested Answer
Weather can damage pavement through block 4 1 joint 3 slab
cracking and transverse cracking. This happens 2 sealant 4 rigid pavement
because the pavement expands and shrinks with hot
or cold weather. 5 Suggested Answer
Sealant is applied to joint grooves.
6 T 2 F 3 T
6 A 2 c
7 1 not looking good 4 block cracking
2 weather caused 5 bleeding 7 1 going smoothly 4 more expensive
3 defects 6 as soon as 2 I'm afraid not 5 cut costs
3 jointed reinforced 6 few ideas
8 Suggested AMwer
A: What's wrong? You look worried. 8 Suggested Answer
B: I drove down Middle Street earlier today. it's not A: Did you visit the Main Street project this morning?
looking good. B: Yes. All of the concrete is poured.
A: What's the problem? A: That's great. Is the sealant placed?
B: The winter weather has caused a lot of damage. B: No, but the joint grooves are almost ready.
A: I'm not surprised. The temperature has changed A: I'm glad to hear it.
a lot. What kinds of defects did you see? B: Everything's going smoothly. We might finish the
B: There was a lot of transverse cracking. I also saw entire project soon.
the start of some bleeding. A: How about the Tenth Street project? Is it going well?
20 Answer Key
Book 2 Answer Key
B: I'm afraid not. The engineers are still designing the A: Good to know. Okay, up next is tamping. Has the
joints. it's getting expensive. crew started that yet?
A: What if we used jointed reinforced concrete? B: Yes, we just finished.
Would that be cheaper than URC? A: Sounds good. Be sure to let me know when you
B: No. The price of steel is rising. So using reinforced strike the formwork. I want to examine the final
concrete would be more expensive. product.
B: Of course.
I 9 Suggested Answer
} Jackson Construction 9 Suggested Answer
Concrete Installation - Final Checklist
Main Street Project
Type of concrete being used: JRC Did the crew ... Yes I No
Project status: The slabs are poured. The joint grooves 1 - Perform a slump test? Yes
have been placed. The sealant will be applied soon. 2 - Install expansion joints? Yes
3- Tamp the concrete? Yes
Green Street Project
4 - Strike the formwork? No
Type of concrete being used: URC
Project status: Engineers are designing the joints.
Unit 15
1 Suggested Answer
1 A slump test and a cube-crushing test are two
tests applied to building materials.
2 A warping joint is located on the surface of a
roadway.
2 D 2 D 3 D
3 1 G 3 E 5 c 7 A
2 D 4 F 6 B
5 Suggested Answer
The last action the crew should take is striking the
formwork.
6 T 2 F 3 F
8 Suggested Answer
A: Do you have a minute to go over a checklist?
B: Of course. What is it for?
A: Just making sure the concrete is laid correctly.
B: What can I tell you?
A: First, did you performed the cube-crushing test?
B: Yes. we took care of that.
A: Good. I'll check that off. Did you place warping
joints?
B: Yes.
Answer Key 21
Audioscripts
Answer Key 23
Audioscripts
Engineer: I'm just checking that I have things right. We Worker: lt will be a while before we're done with Jackson
have to determine the design life first, correct? Street. The rutting is pretty bad.
Contractor: That's correct. Supervisor: Is it dangerous?
Engineer: And you want a report of the traffic growth Worker: No, not yet.
and load? Supervisor: I'm glad to hear that. Okay, I'll send another
Contractor: Yes. We can't move forward without that. crew to Washington Street in the meantime.
Engineer: When would you like that? Worker: Good. it needs it.
Contractor: Please have that to me by Friday.
Engineer: Okay. And the next stage is planning the Unit 14
design thickness, right?
Contractor: Right again. We have to know that before Manager (F): Mr. Hartman, did you visit the Wellington
we can start construction. Street project this morning?
Engineer: What do you need to know to do that? Owner (M): I stopped by earlier. All of the concrete is
Contractor: Well, first we'li need to determine what type poured.
of vehicles will be using the road. Manager: That's excellent. Is the sealant placed yet?
Engineer: I'll include that with the report on traffic load, Owner: No, but the joint grooves are almost ready. They
then. were washing them this morning.
Contractor: Sounds good, thanks. Manager: I'm glad to hear it.
Owner: Everything's going smoothly. We might finish the
entire project by fall.
Unit 12
Manager: How about the Green Street project? Is it going
Owner (F): Bill, can we talk for a moment in my office? well?
Manager (M): Yeah, of course. Is something wrong? Owner: I'm afraid not. The engineers are still redesigning
Owner: Well, there is a small problem. I got the inspection the joints. it's starting to get pretty expensive.
report on Highway 95 back from the Department of Manager: What if we used jointed reinforced concrete?
Transportation. Would that be cheaper than URC?
Manager: Oh, no! I thought we did a great job. Owner: Not at all! The price of steel is rising. So using
Owner: it's not that bad. The good news is that the reinforced concrete would be more expensive.
friction test came out well. They're also very happy Manager: I see. Is there any way to cut costs?
with the appearance of the road. Owner: I have a few ideas. But we'll talk about that later.
Manager: Good. I'm glad. But what's the bad news?
Owner: The bad news is the polished stone value. Unit 15
Manager: What's wrong?
Owner: The investigator is worried about abrasion Manager (F): Hi, Ted. Do you have a minute to go over
wearing down the asphalt and making it dangerous. this checklist with me?
Manager: That's not good. How can we fix it? Worker (M): Sure, Ms. Jones. What is it for?
Owner: We'll just have to watch the condition of the road. Manager: Just making sure the concrete is laid correctly.
If it gets bad we'll have to repair it. Worker: Sure. What can I tell you?
Manager: Okay. Keep me updated on any changes. Manager: First, you performed the slump test?
Worker: Yes. I took care of that before we laid the
concrete.
Unit 13
Manager: Good. I'll check that off. Did you place expansion
Supervisor (M): What's the problem, Shelly? You look joints?
worried. .. Worker: Yes. I saw Mr. Shaw's instructions.
Worker (F): I drove down Washington Street earlier today. Manager: Good to know. Okay, up next is tamping. Has
it's not looking good. the crew started that yet?
Supervisor: What's wrong? I haven't seen it since last fall. Worker: No, not yet. We were about to start.
Worker: The winter weather caused a lot of damage. Manager: Sounds good. Be sure to let me know when
Supervisor: I'm not surprised. The temperature kept you strike the formwork. I want to examine the final
dropping and then rising again. What kinds of defects product.
did you see? Worker: Of course. I'll check in with you later.
Worker: There was a lot of block cracking. it's not too
bad yet, but I also saw the start of some bleeding.
Supervisor: That's not good. Take your crew out there
as soon as you finish on Jackson Street.
24 Answer Key
Book 3 Answer Key
26 Answer Key
Book 3 Answer Key
old beam bridge that couldn't accommodate the A: Since it will be the hardest, I'd start with the deck.
traffic flow. B: Okay. Should we just fix the cracks?
A: Wow. We do need someone with that kind of A: No. You should re-lay the whole road.
experience. But our next project is actually a B: Really? Do you think that's necessary?
double-decked suspension bridge that needs to A: Absolutely. The cracks in the concrete are too
accommodate road traffic and a railroad. Are you severe.
prepared to take on a project like that? B: You're right. We'll start tomorrow.
B: I don't have a lot of experience with double-
decked bridges, but I'm eager to learn. 9 Suggested Answer
Jackson Construction
9 Suggested Answer Work Order
The job applicant has excellent experience with major Remington Bridge
bridge design projects, including a recent cable-stayed
Items that need repair: The deck of the bridge has
bridge construction. However, she has not worked on
many large cracks. The parapet is too low to meet
a double-decked bridge, and we really need someone
new safety standards.
with that experience. For that reason, I do not think
the applicant is a good candidate for the job. Steps for repair: To repair the deck, we must repave
the entire surface. To fix the parapet, we must
Unit 5 increase its height to four feet.
1 Suggested Answers Order of repairs: The deck work will take much
longer, so begin that task first. When the deck is
1 Piers, hammerhead piers, and bent caps are parts
repaved , start work on the parapet.
of a bridge that provide support.
2 A bridge must support a live load, which includes
traffic. Unit6
1 Suggested Answers
2 1 F 2 T 3 T
1 Post and wire fencing, post and rail fencing,
barbed wire, and snow fencing are some types of
3 1 c 3 D 5 F 7 E
fencing used along roads in rural areas.
2 A 4 B 6 G
2 Snow fencing might be used in areas with cold
winters.
4 1 A live load B dead load
2 A deck B pier
2 1 c 2 c 3 B
5 Suggested Answer
3 1 D 3 B 5 A
The bridge, deck, and parapet of the bridge all need 2 E 4 c 6 F
work to be done on them.
4 1 strained wire fence 4 chain-link fence
6 1 T 2 F 3 F 2 concrete wall 5 Snow fencing
3 livestock 6 ancillary work
7 1 need work 4 start with
2 What about 5 Should we just 5 Suggested Answer
3 start on first 6 Are you sure
The man suggests three types of fences: post and
rail fencing, post and wire fencing, and a strained wire
8 Suggested Answer
fence made of barbed wire.
A: I have your inspection report.
B: Great. Were there any problems? 6 1 F 2 T 3 T
A: Yes. The deck and parapet need work.
B: What's wrong with them? 7 1 finished digging 4 go with plan B
A: The deck is cracked and the parapet is too short. 2 You're kidding 5 go back
B: Okay. What about the deck. Do we need to 3 going to do 6 move on with more
repave it?
A: Yes. lt has severe cracks.
B: What should we work on first?
Answer Key 27
Book 3 Answer Key
3 1 H 3 B 5 D 7 E UnitS
2 c 4 A ,. 6 G 8 F
1 Suggested Answers
4 1 A vigilant B Power lines 1 When traffic merges two lanes of traffic form into
2 A personnel B hazards one.
2 A road closure might be necessary due to flooding
5 Suggested Answer or major road construction taking place.
The first step to take in the case of an emergency is
to evacuate all personnel. 2 Road closure: use signs directing drivers to detour
Reduced lanes: use merging taper to direct drivers
6 1 F 2 T 3 T to correct lane
Two-way traffic in one lane: post workers with stop/go
boards at each end of area
28 Answer Key
Book 3 Answer Key
Unit9 Sincerely,
Janet Carlson
1 Suggested Answers
1 Stop signs, yield signs, crossing signs, and warning Unit 10
signs are examples of road signs.
2 A warning sign alerts drivers to dangers. 1 Suggested Answers
1 Median barriers and guard rails are installed for
2 D 2 B 3 B safety reasons.
2 People wait for a bus at a bus stop.
3 1 H 3 D 5 G 7 c
2 A 4 E 6 B 8 F 2 A 2 c 3 c
Answer Key 29
Book 3 Answer Key
3 1 H 3 A 5 c 7 G Unit 11
2 F 4 B 6 D 8 E Suggested Answers
1 Viscometers and penetrometers are examples of
4 1 guard rail 3 trash can
concrete testing equipment.
2 mail boxes 4 median barrier
2 Paving materials are produced in a batch plant.
5 Suggested Answer
2 F 2 T 3 F
On the Block 11 project, bollards and street lights will
control traffic. On Highway 19, the median barrier and 3 1 D 3 F 5 E 7 c
guard rails will affect safety. 2 G 4 A 6 B
30 Answer Key
Book 3 Answer Key
Test #2: We will also need to test EVT since the 9 Suggested Answer
material likely has a lower viscosity than their usual Raymond Testing
material. Concrete Test Report
Tests Performed: We performed a slump test and a
Unit 12
compacting factor test.
1 Suggested Answers
Test Results: The concrete failed both tests. The
1 Slump tests, silt tests, and cube tests are important slump test collapsed after the cone was removed.
tests preformed on concrete. The compacting factor test showed a low workability.
2 A trap door is part of a hopper.
Recommended Tests: Because the concrete failed
2 1 F 2 F 3 T both tests, we are recommending a silt test.
3 1 F 3 B 5 G 7 A Unit 13
2 c 4 D 6 E
1 Suggested Answers
4 1 A slump test 1 Scouring, spalling, and both structural and
B Vebe test shrinkage cracks are problems that can affect a
2 A silt test bridge . .
B degree of compactibility test 2 No. A structural crack is more serious than a
3 A compacting factor test shrinkage crack.
B cube test
2 1 A 2 D 3 D
5 Suggested Answer
3 1 E 3 c 5 B
All tests should use a standard sampling plan.
2 F 4 D 6 A
6 1 F 2 T 3 F
4 1 A shrinkage crack B structural crack
2 A Sand blast B Steam clean
7 1 Did you say 4 test results said
2 too wet 5 Not if it failed
5 Suggested Answer
3 right 6 hold off
The deck has no major structural problems, but does
8 Suggested Answer have shrinkage cracks, and spalling of concrete near
the end of the bridge. it requires some repairs.
A: Hello, Concrete Testing Services. How can I help
you?
6 1 T 2 T 3 F
B: Good morning. You completed tests for my
company, Goodwin Construction.
A: Yes, we completed your tests just the other day.
7 1 spalled concrete 4 only need to
2 take care of 5 just come back
B: I've got a problem. We performed a slump test.
3 And after 6 really depends on
And it collapsed.
A: I'm sorry, I didn't hear you. Did you say it was
8 Suggested Answer
slumped or collapsed?
B: it collapsed. The concrete was too wet. A: I just read your report. The first problem is the
A: That's definitely a problem. scouring near the foundation?
B: I agree. But, the other tests were normal, right? B: Yes. I suggest using sand bags to fill the scoured
A: Yes, that's true. But you shouldn't use the areas.
concrete if it failed the slump test. We'll send a A: Okay. That shouldn't be a problem.
representative out to your site immediately. B: There are also shrinkage cracks on the deck.
B: I was about to add more Portland cement to the A: Yes, we need to take care of that, too.
mix. B: First, you need to sand blast the cracks.
A: I wouldn't do that. Our representative should be A: Right. And after sand blasting, we fill it with new
able to tell what went wrong. That way you only concrete.
have to correct the mix once. B: Actually, I would suggest mortar. You only need
B: Okay, I'll wait. to use new concrete for large areas.
Answer Key 31
Book 3 Answer Key
A: Really? Concrete is much stronger. If we use A: So what do you think we should do first?
mortar, I'm afraid the cracks will just continue. B: Let's start with patching.
B: For small cracks, mortar is fine. But for structural A: Good idea. Patching should be enough there.
cracks, you need to lay new concrete. What else?
A: Sounds good to me. B: We'll need to do some repainting, too.
A: But what about bigger changes? We need to make
9 Suggested Answer structural changes on Onyx Avenue.
To: Carl Smith B: Yeah, we'll have to widen some parts of the street.
From: Brad Jenks A: In my opinion, we also need to resurface it.
Subject: Inspection Report B: Okay. That section is pretty torn up.
A: We could have one team work on patching.
Mr. Smith, Another big team can do resurfacing by the park.
I have completed the inspection report. The apron B: Sounds good.
and invert are in good condition. There is some
spalling on the deck. There is also some scouring 9 Suggested Answer
around the foundation as wel l. To repair the spalling,
Project Plan
I suggest sand blasting the area. Then, I would fill it
Road improvements on several streets have been
with mortar. Concrete doesn't have to be used unless
approved. Fifth Avenue is a high traffic area.
the area is large. To repair the scouring around the
Therefore, keeping it in good condition is essential.
foundation, I recommend that you fill the holes with
The intersection of Fifth and Carlton Avenues will
sandbags. Let me know if you have any questions.
need to be patched to correct any unevenness.
Brad Jenks
When that is completed, lanes on the street will be
repainted as well. Main Street needs more structural
Unit 14 maintenance, however. That street will be widened
1 Suggested Answers to allow for better traffic conditions in the area. 0 n
Fifth Avenue, near the park, the street will be
1 Repainting, sweeping, and patching are some
resurfaced. One team will focus on patching the
maintenance tasks that need to be carried out on
streets. The other will work on resurfacing the area
roads.
by the park. All repainting will be completed last.
2 The road can be widened.
Unit 15
2 T 2 F 3 T
3 1 H 3 E 5 G 7 A 1 Suggested Answers
2 B 4 D 6 c 8 F 1 A plow is used to remove snow from roads.
2 Rock salt is commonly used to salt roads.
4 1 A repaint B maintain
2 A structural B routine 2 F 2 T 3 F
5 Suggested Answer 3 1 F 3 E 5 G 7 B
The mayor approved both routine and structural road 2 c 4 H 6 A 8 D
maintenance. Workers will resurface and repaint roads.
They will also widen a street in the downtown area. 4 1 A Shot blasting B Bush hammering
2 A Plowing B retexturing
6 T 2 F 3 T 3 A snow removal B rotating disc
32 Answer Key
Book 3 Answer Key
8 Suggested Answer
A: Caston City Hall. How can I help you?
B: Hello, this is Mike Hayes with Hayes Contractors.
A: Hello, are you calling to discuss a highway
maintenance bid?
B: Yes.
A: Are you interested in all three projects?
B: We're interested in helping with retexturing and
snow removal.
A: How about pressure grouting?
B: We don't specialize in that. Although I'd be happy
to help you find someone.
A: Well, let's start by talking about retexturing.
B: Yes, it looks like that's the biggest project.
A: Which abrasion techniques do you typically use?
B: We have experience with shot blasting and bush
hammering.
A: Great. Which one is more expensive?
B: Shot blasting could run higher.
A: How is that determined?
B: lt depends on how much concrete has to be
removed. The deeper we go and the larger the
area, the higher the price.
9 Suggested Answer
Bid for Highway Maintenance Project
Company: Hayes Contracting
Physical Abrasion Methods: Hayes Construction offers
abrasion through the use of rotating discs, bush
hammering, and shot blasting. When appropriate, we
can also offer high pressure water retexturing.
Rotating discs and bush hammering are the most
affordable options. Shot blasting and high pressure
water retexturing are the more expensive options.
Snow Removal and De-icing: Hayes Contracting
offers plowing and salting services. Our trucks are
equipped to spread rock salt as we plow falling snow.
Answer Key 33
Audioscripts
Unit 1 Unit3
Contractor (M): Leonard Construction, Conrad speaking. Employee (M): Good morning, welcome to Jackson and
Planner (F): Hi, Conrad. it's Sarah Adams at the city Sons. How can I help you?
planner's office. I got your email. But I have a few Planner (F): Hello. I'm a city planner for the mayor's office,
questions. and we're looking at redoing some city sidewalks.
Contractor: Okay, what can I tell you? Employee: I'm glad you chose to come here! Are these
Planner: Well, you mentioned a barrier curb. What exactly urban or residential sidewalks?
is that? Planner: Some of both. I wanted to talk about prices.
Contractor: Oh, a barrier curb goes between lanes of Employee: Sure. Well, it depends on the material.
traffic. it's strong enough to stop cars from crossing assume you want concrete?
over it. Planner: Yes. Do you have different types of concrete
Planner: I see. That's what I thought. But how is that paving slabs?
different from a vertical curb? Employee: Of course. We work with both hydraulically
Contractor: A vertical curb isn't a strong as a barrier curb. pressed slabs and open-mold slabs.
Planner: I'm sorry, I didn't catch that. Did you say it isn't Planner: What's the difference in cost?
as long as a barrier curb? Employee: Hydraulically pressed slabs go for about six
Contractor: No, you misheard me. Vertical curbs aren't dollars per square foot.
as strong as barrier curbs. Planner: And how about open-mold slabs?
Planner: Got it. So they can't be used for the same jobs? Employee: Those will run you more like ten dollars per
Contractor: Definitely not. lt wouldn't be safe. square foot.
Planner: Understood. Planner: Are there advantages with open-mold slabs?
Contractor: Was there anything else? Employee: Well, you can add different colors and textures.
Planner: Yes, one thing. You suggested cut stone curbs Planner: Hmm. Is one of them stronger than the other?
for the residential project. Employee: Yes, hydraulically pressed slabs are usually
Contractor: I did. lt would look great. stronger. Open-mold slabs can be more decorative.
Planner: Yes, but unfortunately, we don't have the budget Planner: Okay, we'll probably use hydraulically pressed
for that. slabs. But I need to check with my supervisor before
Contractor: Well, a standard curb and gutter would work we make an order.
as well.
Unit4
Unit 2
Interviewer (M): So, Ms. Andrews, it says on your
Manager (F): Jim, are you ready to try your first curb application that you used to work for GMA Engineering.
installation? Applicant (F): That's right. I headed several bridge design
Employee (M): Yes. I've been watching the other workers. projects there.
I'm ready to give it a shot. Interviewer: That's excellent. What types of projects did
Manager: Okay, tell me what you're going to do first. you handle?
Employee: Well, the curb bed is already laid. So all I need Applicant: Well, for my last project, I was the lead
to do is make sure the curb is positioned correctly engineer on the Unibar Bridge construction.
along the curb line. Interviewer: That's a suspension bridge, isn't it?
Manager: Aren't you forgetting something? Applicant: Yes, it replaced the old beam bridge across
Employee: Hmm. Let me see. Oh, do I need to put in a the bay. The county needed something that could
haunch? handle much higher traffic flow.
Manager: No, that comes later. I'll give you a hint. What Interviewer: Wow. We do need someone with that kind
holds the curb in the curb bed? of experience. That must have been a major project.
Employee: When the concrete dries, it will secure the Applicant: lt was. We made it a double-decked bridge
curb, right? with northbound traffic above and southbound traffic
Manager: No, that's only the case in wet beds. This is a below.
dry bed. Interviewer: Our upcoming project is actually a moveable
Employee: Oh, I see. So it needs bonding? bridge that needs to accommodate passing boats.
Manager: That's right. You'll need to use the epoxy resin Are you prepared to take on a project like that?
to bond the curb to the curb bed. Applicant: I don't have a lot of experience with moveable
Employee: Got it. I'll remember that next time. bridges, but I'm eager to learn.
Interviewer: Well, that's something we like to see, too.
34 Answer Key
Audioscripts
Employee 2: Okay. What's going on? Representative: Then we'll probably need to send a
Employee 1: First, we're shipping two stop signs. We're penetrometer. And since the tar is thicker than
also adding a yield sign to the order. normal, it probably has a higher EVT.
Employee 2: Got it. Are there any other signs on the Client: Right. So we need to know just how hot it should
order? be before we start laying it.
Employee 1: Yes, a few more. There's a warning sign Representative: Okay, so we'll set you up for a ring and
about icy conditions and two crossing signs. ball test as well.
Employee 2: What kind of crossing signs do we need? Client: Great. Do you need me to prepare a sample
Animal crossing signs? before the tester arrives?
Employee 1: No, both are children crossing signs. They're Representative: No, just leave it to us. Our tester will
going near a school. determine the most appropriate way to extract a
Employee 2: And that's it? sample from your batch.
Employee 1: Yeah, that will do it.
Unit 12
Unit 10
Employee (F): Hi, this is Rachel with U.S. Concrete Testing
Manager (F): Hello, Amanda Peterson, Breckin Construction. Services. How can I help you?
Contractor (M): Ms. Peterson, it's John Parker. This is Client (M): Good morning, my name is Oliver Smith, from
embarrassing, but I deleted your email with street Johanson's Construction and Building. You did some
furniture instructions. tests for my company.
Manager: Mr. Parker! Don't worry about the email. You Employee: Hi, Mr. Smith. Yes, we completed your tests
called at a perfect time. We just got our permit for just the other day.
the project. Client: Yes, we got your results. Thank you. But I've got
Contractor: Oh, that's great! a question.
Manager: Yes, we can begin work immediately. Employee: Of course. Let me look up your tests on the
Contractor: So, where should I start? computer. Okay, ready.
Manager: Well, I suggest you arrange the street and Client: Well, it's just that we performed a slump test. And
traffic lights first. Then work out the details for the it col lapsed.
benches and trash cans. Employee: I'm sorry, I didn't hear you. Did you say it was
Contractor: Okay. And then? slumped or collapsed?
Manager: Pick out the bollards next. They have to be Client: it collapsed. So we know that the concrete was
both functional and attractive. too wet.
Contractor: Do we have a vendor? Employee: Hmm. Okay, that's definitely a problem if the
Manager: We do. We used him on our last project. Look at consistency is wrong.
his catalog and see if there are any that complement Client: I agree. But, the other tests were normal, right?
the site. Employee: Yes, that's true.
Contractor: Will do. What about the highway project? Client: Well, whatever the test results said, I can't use
What should we do there? this concrete.
Manager: If I were you, I would ask the engineers about Employee: No, Sir. Not if it failed the slump test. We'll
the median barrier and guard rail lengths first. send a representative out to your site immediately.
Contractor: Got it. I'll call them right away. Client: I was about to add more Portland cement to the
mix. Should I hold off?
Unit 11 Employee: I would. Our representative will run all the tests
again. He should be able to tell what went wrong. That
Representative (M): Thanks for calling Levy Chem way you only have to correct the mix once.
Testing. How can I help you? Client: Okay, I'll wait then. Thanks.
Client (F): Hi, this is Linda Wilson with Wilson's Paving. I
need to have someone come out to examine a new
Unit 13
batch of tar.
Representative: I can schedule a visit to your batch plant Contractor (F): Good morning, David. How are you doing?
this afternoon. What types of tests do you need? Engineer (M): Hey Diane! I'm great. I'm guessing you're
Client: Well, I know we need to determine the viscosity. here to discuss the Larabee Street Bridge repairs?
This tar is thicker than our usual stuff, since we're Contractor: Yes, I just read your report. The first problem
using it for an especially hard surface. is the scouring near the foundation?
36 Answer Key
Audioscripts
Answer Key 37
Construction 11
The Teacher's Book contains a full answer key and audio scripts.
The audio CDs contain all recorded material in American English and British
English .
Books 1-3 of Career Paths: Construction 11- Roads & Highways are rated for
the Common European Framework of Reference for Languages at A 1, A2 and
.. B1 respectively.
Express Publishing
ISBN 978-1-4715-1535-4
111111111111111111111111
9 781471 515354