Chiller Commissioning Checks

1.Have all the technicians and operators read and understood all manuals?

Yes No N/A

2.Have all the technicians and operators read and understood all manuals for third party components?

Yes No N/A

3.Has the unit installation and vibration damper adjustment been checked?

Yes No N/A

4. Has functional testing of safety equipment been carried out?

N/A
Yes No

5.Are the opening pressures on all safety valves, correct?

N/A
Yes No

6.Has vacuum test been carriecl out?

N/A

Yes No

7.Have oil levels been checked?


N/A

Yes No

8.Has the heating element in the oil been on for 6-8 hours before start-up?

Yes No N/A

9.Has a sample of the primary refrigerant been taken and checked to ensure it is free horn water, air, etc?

Yes No N/A

10. Is the motor


rotation direction correct?

N/A

Yes No

11. Is the coupling


alignecl?
N/A

Yes No

12. Is the compressor cooling connected correctly?

Yes No N/A

13. Are there any


leaks in the plant?

N/A

Yes No

14. Are valves in the correct position for operation?

Yes No N/A

1.Is the capacity regulation system working correctly?

Yes No N/A

2.Has the refrigerant charge (at full load) been checkecl?

Yes No N/A

3.Has the unit been checked for vibrations?

Yes No N/A

4.Has the unit been checked for vibrations using variable speecl?

Yes No N/A

5. Has a lubricating oil sample been collected after about 1 hour of operation and saved?

Yes No N/A

1.Operation time (hours)

Enter Text

2.Suction pressure (•C/R)

Enter Text

3.Suction temperature (°/

Enter Text

4.Superheating, suction gas (K)

Enter Text

5. Discharge pressure (•C/R)

Enter Text

6. Discharge temperature (•C)

Enter Text

7.Oil pressure, compressor (bar)

Enter Text

8.Oil pressure, filter(bar)

Enter Text

9.Oil temperature (°

Enter Text

10. Oil temperature, separator (°C)

Enter Text

11. Oil collection from shaft seal (ml)

Enter Text

12. Oil level (0, 1/4, 1/2,3/4, Full)

Enter Text

13. Charged oil (Litre)

Enter Text

14. Motor 1/1 load (amp.)

Enter Text

15. Capacity load (%)

Enter Text

16. Noise level

Enter Text

17. Pass,FaiI Radio

Enter Text

18. Vibrations (0-100% capacity)

Enter Text

19. Pass,FaiI Radio

Enter Text

20. Brine temperature, outlet - Evaporator(•C)

Enter Text

21. Brine temperature, outlet - Condenser(•C)

Enter Text

22. Refrigerant charge (Kg)

Enter Text

Is this sample what you are looking for?


Sign up to use & customise this template, or create your own custom checklist:

Checklist by GoAudits com — Please note that this checklist is intended as an example. We do not guarantee compliance with the Ian’s applicable to your territory or industry. You should seek professional
advice to determine how this checklist should be adaptecl to your workplace orjurisdiction.

You might also like