PROJECT
WORK ITEM Laying of GI pipes 1"
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site m 1 0.20 0.20 DL 10 1
Loding & unloading m 1 0.20 0.20 Forman 1 1
0.00 Plumber 1 1
0.00 Assitant plumbers 2 1
0.00 Construction Eng. 1 0.1
0.00 Surveyor 1 0.5
0.00
0.00
PROJECT Gerbsegen
WORK ITEM fixing DN90mm fitting appurtnance
TOTAL QUANTITY OF WORK ITEM 1pcs
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site Pcs 1 5.00 5.00 DL 4 1
Loding unloading cost Pcs 1 5.00 5.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
0.00
0.00
PROJECT
WORK ITEM fixing 3" fitting appurtnance
TOTAL QUANTITY OF WORK ITEM 1pcs
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site Pcs 1 5.00 5.00 DL 4 1
Loding unloading cost Pcs 1 5.00 5.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
0.00
0.00
PROJECT
WORK ITEM fixing DN50mm fitting appurtnance
TOTAL QUANTITY OF WORK ITEM 1pcs
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site Pcs 1 0.50 0.50 DL 2 1
Loding unloading cost Pcs 1 0.50 0.50 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
0.00
0.00
PROJECT
WORK ITEM fixing < DN50mm fitting appurtnance
TOTAL QUANTITY OF WORK ITEM 1pcs
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site Pcs 1 5.00 5.00 DL 4 1
Loding unloading cost Pcs 1 5.00 5.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
0.00
0.00
PROJECT
WORK ITEM fixing Gate valve 3"
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Gate valve 3" Pcs 1 5.00 5.00 DL 4 1
0.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
PROJECT
WORK ITEM fixing Water meter 3"
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Water meter 3" Pcs 1 5.00 5.00 DL 4 1
0.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
Total (1.01) 5.00 Total (1.02)
PROJECT
WORK ITEM fixing Gate valve 1"
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site Pcs 1 0.50 0.50 DL 4 1
Loding unloading cost Pcs 1 0.50 0.50 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
PROJECT
WORK ITEM Laying of uPVC pipes DN 80 0.333
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site m 1 0.50 0.50 DL 10 1
Loding unloading cost m 1 0.50 0.50 Forman 1 1
0.00 Plumber 1 1
0.00 Assitant plumbers 2 1
0.00 Construction Eng. 1 0.1
0.00 Surveyor 1 0.5
0.00
0.00
PROJECT
WORK ITEM Laying of uPVC pipes DN 100 1
TOTAL QUANTITY OF WORK ITEM 1
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site m 1 0.50 0.50 DL 10 1
Loding unloading cost m 1 0.50 0.50 Forman 1 1
0.00 Plumber 1 1
0.00 Assitant plumbers 2 1
0.00 Construction Eng. 1 0.1
0.00 Surveyor 1 0.5
0.00
0.00
Total Cost
PROJECT
WORK ITEM Laying of uPVC pipes DN 150
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site m 1 1.00 1.00 DL 10 1
Loding & unloading m 1 1.00 1.00 Forman 1 1
0.00 Plumber 1 1
0.00 Assitant plumbers 2 1
0.00 Construction Eng. 1 0.1
0.00 Surveyor 1 0.5
0.00
0.00
PROJECT
WORK ITEM Laying of uPVC pipes DN 200 1.66666666666667 3.333
TOTAL QUANTITY OF WORK ITEM 1
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site m 1 1.00 1.00 DL 10 1
Loding & unloading m 1 1.00 1.00 Forman 1 1
0.00 Plumber 1 1
0.00 Assitant plumbers 2 1
0.00 Construction Eng. 1 0.1
0.00 Surveyor 1 0.5
0.00 Site Manager 1 0.05
0.00 Team leader 1 0.05
PROJECT
WORK ITEM Laying of uPVC pipes DN 250 4.167
TOTAL QUANTITY OF WORK ITEM 1
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site m 1 1.00 1.00 DL 10 1
Loding & unloading m 1 1.00 1.00 Forman 1 1
0.00 Plumber 1 1
0.00 Assitant plumbers 2 1
0.00 Construction Eng. 1 0.1
0.00 Surveyor 1 0.5
0.00
0.00
Total (1.01) 2.00 Total (1.02)
PROJECT
WORK ITEM Laying of uPVC pipes DN 300 2.5 5
TOTAL QUANTITY OF WORK ITEM 1
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site m 2 1.50 3.00 DL 10 1
Loding & unloading m 2 1.50 3.00 Forman 1 1
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.1
Surveyor 1 0.5
PROJECT 0
WORK ITEM Laying of uPVC pipes DN 350
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site m 2 1.50 3.00 DL 10 1
Loding & unloading from AA m 2 1.50 3.00 Forman 1 1
0.00 Plumber 1 1
0.00 Assitant plumbers 2 1
0.00 Construction Eng. 1 0.1
0.00 Surveyor 1 0.5
0.00
0.00
PROJECT
WORK ITEM fixing DN50mm Gate valve
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site Pcs 1 5.00 5.00 DL 4 1
Loding unloading cost Pcs 1 5.00 5.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
PROJECT
WORK ITEM fixing DN80mm Gate valve
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site Pcs 1 5.00 5.00 DL 4 1
Loding unloading cost Pcs 1 5.00 5.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
PROJECT
WORK ITEM fixing DN100mm Gate valve
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site Pcs 1 5.00 5.00 DL 4 1
Loding unloading cost Pcs 1 5.00 5.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
PROJECT
WORK ITEM fixing DN 150mm Gate valve
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site Pcs 1 5.00 5.00 DL 4 1
Loding unloading cost Pcs 1 5.00 5.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
PROJECT
WORK ITEM fixing DN 250mm Gate valve
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site Pcs 1 10.00 10.00 DL 4 1
Loding unloading cost Pcs 1 10.00 10.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
Total (1.01) 20.00 Total (1.02)
PROJECT
WORK ITEM fixing DN 300mm Gate valve
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site Pcs 1 10.00 10.00 DL 4 1
Loding unloading cost Pcs 1 10.00 10.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
PROJECT
WORK ITEM fixing DN 350mm Gate valve
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site Pcs 1 10.00 10.00 DL 4 1
Loding unloading cost Pcs 1 10.00 10.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
PROJECT
WORK ITEM fixing DN 400mm Gate valve
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site Pcs 1 15.00 15.00 DL 4 1
Loding unloading cost Pcs 1 15.00 15.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
PROJECT
WORK ITEM Laying of DCI pipes DN 250
TOTAL QUANTITY OF WORK ITEM MEASURED IN meters
PROJECT
WORK ITEM Laying of GI pipes 1"
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site m 1 0.20 0.20 DL 10 1
Loding & unloading m 1 0.20 0.20 Forman 1 1
0.00 Plumber 1 1
0.00 Assitant plumbers 2 1
0.00 Construction Eng. 1 0.1
0.00 Surveyor 1 0.5
0.00
0.00
Total (1.01) 0.40 Total (1.02)
PROJECT Gerbsegen
WORK ITEM fixing DN90mm fitting appurtnance
TOTAL QUANTITY OF WORK ITEM 1pcs
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site Pcs 1 5.00 5.00 DL 4 1
Loding unloading cost Pcs 1 5.00 5.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
0.00
0.00
PROJECT
WORK ITEM fixing 3" fitting appurtnance
TOTAL QUANTITY OF WORK ITEM 1pcs
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site Pcs 1 5.00 5.00 DL 4 1
Loding unloading cost Pcs 1 5.00 5.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
0.00
0.00
PROJECT
WORK ITEM fixing DN50mm fitting appurtnance
TOTAL QUANTITY OF WORK ITEM 1pcs
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site Pcs 1 0.50 0.50 DL 2 1
Loding unloading cost Pcs 1 0.50 0.50 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
0.00
0.00
PROJECT
WORK ITEM fixing < DN50mm fitting appurtnance
TOTAL QUANTITY OF WORK ITEM 1pcs
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Transport from store to the site Pcs 1 5.00 5.00 DL 4 1
Loding unloading cost Pcs 1 5.00 5.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
0.00
0.00
PROJECT
WORK ITEM fixing Gate valve 3"
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Gate valve 3" Pcs 1 5.00 5.00 DL 4 1
0.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
PROJECT
WORK ITEM fixing Water meter 3"
TOTAL QUANTITY OF WORK ITEM 1m
MATERIAL COST (1.01) LABOUR COST (1.02)
Type of Material Unit Qty U.Price* T.Cost Trade No UF
Water meter 3" Pcs 1 5.00 5.00 DL 4 1
0.00 Forman 1 0.15
Plumber 1 1
Assitant plumbers 2 1
Construction Eng. 1 0.15
Surveyor 1 0.25
9.09
3.18
12.28
7.34
2.57
9.91 59.46 for 6m length
209.20
73.22
282.42
176.00
61.60
237.60
54.07
18.92
72.99
49.84
17.44
67.28
455.00
159.25
614.25
505.00
176.75
681.75
282.25
98.79
381.04
HOURLY OUT PUT 48.75
EQUIPEMENT OUT PUT ______ 390
8.50
2.98
11.48
9.77
3.42
13.19
14.96
5.24
20.20
18.49
6.47
24.96
21.87
7.65
29.52
31.89
11.16
43.05
42.95
15.03
57.98
42.04
14.72
56.76
285.95
100.08
386.04
372.33
130.32
502.65
412.59
144.41
557.00
532.92
186.52
719.44
HOURLY OUT PUT 0.44
EQUIPEMENT OUT PUT _______________
617.62
216.17
833.79
686.15
240.15
926.30
730.56
255.69
986.25
730.56
255.69
986.25
1,035.83
362.54
1,398.38
150.00
34.67
12.13
46.80
52.00
18.20
70.20
HOURLY OUT PU 62.50
EQUIPEMENT OUT PUT _______________
7.34
2.57
9.91 59.46 for 6m length
HOURLY OUT PU 1.25
EQUIPEMENT OUT PUT _______________
277.10
96.98
374.08
176.00
61.60
237.60
49.84
17.44
67.28
455.00
159.25
614.25
505.00
176.75
681.75
282.25
98.79
381.04
Labour Cost
S/N Description Daily Rate (birr)