Higher Technological Institute (HTI), Mechanical Engineering

10th of Ramadan City Department

Project Management
MNG 201
Lecture Eight
Second Term (2021- 2022)
82 Dr. Mahmoud Malek
Dr. Asmaa Soliman

Higher Technological Institute (HTI), 10th of Ramadan City.


Project Management, Dr. Mahmoud Malek, Dr. Asmaa Ahmed Soliman
Precedence diagramming method /Activity-On-Node (AON)
83
 All Activities from One start and to One end
A A
Activities ( A, B, C ) One
B Start B Start
are Start
C C

X
X
Activities ( X, Z, Q ) Z END One End
Z
are End
Q
Q

 Arrow Crossing are Allowed


Higher Technological Institute (HTI), 10th of Ramadan City.
Project Management, Dr. Mahmoud Malek, Dr. Asmaa Ahmed Soliman
Solved Examples on Activity On Arrow (A.O.N)
84

Ex (2):
 A project of installing new Cabinets, Based
on the data given below:
1. Draw an arrow diagram
2. Determine The Total Time of The
Project
3. Determine The Critical Paths(s)
4. Determine the ES, EF and Free Float for
all activities
5. Draw Bar Chart for Critical Path Only.

Higher Technological Institute (HTI), 10th of Ramadan City.


Project Management, Dr. Mahmoud Malek, Dr. Asmaa Ahmed Soliman
Solution
85

Duration = No. of units Required /


No. of units required per day

D5
F R T
E
10 10 10
30
F 20

Start Q B D Z End
10 10 5 5

L3
N P S
30 20 10 Higher Technological Institute (HTI), 10th of Ramadan City.
Project Management, Dr. Mahmoud Malek, Dr. Asmaa Ahmed Soliman
86