Professional Documents
Culture Documents
MNG 201 - Lect. (3), 2023 - 2024
MNG 201 - Lect. (3), 2023 - 2024
Lecture (3)
Construction Project Planning
(Construction Project Networks)
1
Bar Chart , AOA, AON and PERT
First Term (2023- 2024)
Dr. Asmaa Soliman
Asmaa.soliman@hti.edu.eg
Higher Technological Institute (HTI), 10th of Ramadan City.
Project Management, Dr. Asmaa Ahmed Soliman
2
Time Management Definition
Time management is the discipline of planning and scheduling
one’s activities so that they fit in with other commitments,
resources, and goals.
It involves the identification of the necessary tasks (work, personal,
family) and the allocation of time to each task.
Planning Process
5 Planning phase is a phase of the life cycle that involves creating plans for
management, monitor, and execution.
In this phase, the project has to be developed in detail to meet its objectives.
The project manager’s team will define the work that needs to be done in
order to start construction by identifying the resources and strategies to obtain
supplies.
The project manager will prepare the budget of the project by considering
the estimated costs. This includes the costs of equipment, material and
manpower.
Nowadays, numerous software options are available that can help in scheduling
project to complete a project within its time frame. It can also help in
monitoring the cost of the project. All the things planned in this stage have to be
documented in detail so that they can be reviewed repeatedly throughout its
execution.
Activities Duration
6
Activity Duration is the time consumed to complete an activity from
start to finish.
𝑸𝒖𝒂𝒏𝒕𝒊𝒕𝒚
Duration =
Ex: 𝑷𝒓𝒐𝒅𝒖𝒄𝒕𝒐𝒏 𝑹𝒂𝒕𝒆(𝒑𝒓𝒐𝒅𝒖𝒄𝒕𝒊𝒗𝒊𝒕𝒚)
Excavation Quantity = 2000 m3 Duration = 2000/200
= 10 working days
Excavator rate = 200 m3\day
Note: The project manager should always remember that the project
schedule could be a legal and binding document, as part of the contract.
In such a case, it may be used in court later to prove or disprove a delay
claim.
Higher Technological Institute (HTI), 10th of Ramadan City.
Project Management, Dr. Asmaa Ahmed Soliman
Predecessor
Activity (A)
1 3
Finish to start Successor Start to
Activity (B)
(FS). Finish (SF).
SS= zero
Activity (A) Activity (A)
Overlap Overlap
FF=zero
2 4
Activity (B) Activity (B)
Finish to Finish Start to start
(FF). (SS).
Activity (A)
Activity (A) FF=x
10th
Higher Technological Institute (HTI), of Ramadan City.
Project Management, Dr. Asmaa Ahmed Soliman
Project Networks
8 Network Diagram is a graph or chart which clearly indicates the flow
of elements in the project. It consists of the elements that are shown
from left to right with their dependencies
There are three ways that are commonly used to draw a network
diagram, to visual presentation of the sequence
of construction events for a project:
1.Activity On Arrow (AOA);activities are represented by Arrows
Between nodes.
¡ Activity name ϳ
2.Activity On Node (AON);activities are represented by the nodes.
= -
Es succossor activity
Es Ff Ef
+ = =
Activity Ft -
11 Solution
2) Arrow Directions
M T
C j
A
One B S One
Start End
M T
S T
M T
C j
A
B S
M T
R
C Z
A j
B S
M T
C j
A
R
B S
Terminology
17
19
Solution
Ex. (1)
Solution
22 Ex. (2)
Duration = No. of units Required /
No. of units required per day
R T
E F
D Z
Q B
N
S
P
Activity Successor
Ex. (3) It’s required to :
A F G -
F -
10
B 30
70
C G
40 D 60
S
A 20
R
80 Q
6
10
0 90
B
C P
30
50
O 70
N
40
25