LEAK TEST EXECUTION PLAN OF BRONANG JACKET LEGS & BT's FILLING AIR COMPRESSED

A. LEAK TEST JACKET LEGS


No. Description Execution Date Injection Time Holding Time Depressurized Time Remarks

1 Jacket Leg A3 TBA 12.00 - 12.30 PM 12.30 - 13.30 PM 13.40 PM Depressurized from 1.7 barg to 1.2
barg
2 Jacket Leg B1 16 August '22 12.00 - 12.30 PM 12.30 - 13.30 PM 13.40 PM Depressurized from 1.7 barg to 1.2
barg
3 Jacket Leg B2 16 August '22 12.00 - 12.30 PM 12.30 - 13.30 PM 13.40 PM Depressurized from 1.7 barg to 1.2
barg
B. BT's LEAKT TEST & RE-FILLING AIR COMPRESSED
4 BT-1-A1 9-Aug-22 08.00 - 08.30 PM 08.30 - 09.30 09.35 AM Completely done, refilling prior sail
away
5 BT-1-B1 9-Aug-22 09.40 - 10.10 PM 10.10 - 11.10 11.15 AM Completely done, refilling prior sail
away
6 BT-1-C1 9-Aug-22 08.00 - 08.30 PM 08.30 - 09.30 09.35 AM Completely done, refilling prior sail
away
7 BT-2-A1 11-Aug-22 17.00 - 17.30 PM 17.30 - 18.30 18.35 PM Completely done, refilling prior sail
away
8 BT-2-B1 11-Aug-22 18.40 - 19.10 PM 19.10 - 20.10 20.15 PM Completely done, refilling prior sail
away
9 BT-2-C1 11-Aug-22 17.00 - 17.30 PM 17.30 - 18.30 18.35 PM Completely done, refilling prior sail
away

Preparation Test Equipment :


a All Blinds set has been passing test prior connection to injection point
b All Flange set to be connected to injection point at least one day before execution date
c Air Compressor, Air Manifold and Hoses are move to the barge one day prior execution date
d Personnal Man Basket (if access scaffold did not available)
e Safety Body Harness
f Handy Talkie Radio
g Hand Tools (Adjustable Wrench, Combination Wrench, Pipe Wrench, etc)

Documentation
- PTW, JRA
- Procedure & Methode Statement
- Timer for Holding Time
- Exclusion Zone Calcullation
- Leak Test Map Layout

ED To be followed of Construction Readiness


Activity Time Required
Tools and Equipment Preparation 2 hr.
Move Manifolds and Air Compressor to Barge 30 min.
Prepare Man Basket 30 min.
Preparations before man basket embarking 30 min.
Install Injection Point A3 30 min.
Install Injection Point B1 30 min.
Install Injection Point B2 30 min.
Fill Leg B2 30 min.
Holding Time B2 1 hr.
Fill Leg B1 30 min.
Holding Time B1 1 hr.
Fill Leg A3 30 min.
Holding Time A3 1 hr.
Finish test tasks 30 min.
Housekeeping 2 hr.
7:00 AM 7:15 AM 7:30 AM 7:45 AM
Remarks
Prepare hand tools, flange sets, boxes, etc. and move to jetty

Wear body harnesses, tying hose to man basket etc.

Disconnect hoses, disembark from man basket, etc.


Cleanup barge etc.
8:00 AM 8:15 AM 8:30 AM 8:45 AM 9:00 AM 9:15 AM 9:30 AM 9:45 AM 10:00 AM 10:15 AM
10:30 AM 10:45 AM 11:00 AM 11:15 AM 11:30 AM 11:45 AM 12:00 PM 12:15 PM 12:30 PM 12:45 PM
1:00 PM 1:15 PM 1:30 PM 1:45 PM 2:00 PM 2:15 PM 2:30 PM 2:45 PM 3:00 PM 3:15 PM
3:30 PM 3:45 PM 4:00 PM 4:15 PM 4:30 PM 4:45 PM 5:00 PM 5:15 PM 5:30 PM 5:45 PM
6:00 PM
LEAK TEST EXECUTION PLAN OF FOREL JACKET LEGS & BT's FILLING AIR COMPRESSED
A. LEAK TEST JACKET LEGS
No. Description Execution Date Injection Time Holding Time Depressurized Time Remarks

1 Jacket Leg A3 TBA 08.00 - 08.30 AM 08.30 - 09.30 AM 09.30 - 09.45 AM Preparation will do one day prior
execution date
2 Jacket Leg B1 TBA 08.50 - 09.20 AM 09.20 - 10.20 AM 10.20 - 10.35 AM Preparation will do one day prior
execution date
3 Jacket Leg B2 TBA 09.40 - 10.10 AM 10.10 - 11.10 AM 11.10 - 11.25 AM Preparation will do one day prior
execution date
B. BT's FILLING AIR COMPRESSED
4 BT-1-A1 TBA 14.00 - 14.30 PM NOT REQUIRED NOT REQUIRED Preparation will do one day prior
execution date
5 BT-1-B1 TBA 14.40 - 15.10 PM NOT REQUIRED NOT REQUIRED Preparation will do one day prior
execution date
6 BT-1-C1 TBA 15.10 - 15.40 PM NOT REQUIRED NOT REQUIRED Preparation will do one day prior
execution date
7 BT-2-A1 TBA 15.50 - 16.20 PM NOT REQUIRED NOT REQUIRED Preparation will do one day prior
execution date
8 BT-2-B1 TBA 16.30 - 17.00 PM NOT REQUIRED NOT REQUIRED Preparation will do one day prior
execution date
9 BT-2-C1 TBA 17.10 - 17.40 PM NOT REQUIRED NOT REQUIRED Preparation will do one day prior
execution date

Preparation Test Equipment :


a All Flange set has been passing test prior connection to injection point
b All Flange set to be connected to injection point one day before execution date
c Air Compressor, Air Manifold and Hoses are move to barge one day prior execution date
d Personnal Man Basket
e Safety Body Harness
f Handy Talkie Radio
g Hand Tools (Adjustable Wrench, Open Wrench, Pipe Wrench, etc)

Documentation
- PTW, JRA
- Procedure & Methode Statement
- Timer for Holding Time