Professional Documents
Culture Documents
Engineering Management
Ibrahim Mahamid
To cite this article: Ibrahim Mahamid (2015) Factors affecting cost estimate accuracy: Evidence
from Palestinian construction projects, International Journal of Management Science and
Engineering Management, 10:2, 117-125, DOI: 10.1080/17509653.2014.925843
Factors affecting cost estimate accuracy: Evidence from Palestinian construction projects
Ibrahim Mahamid*
Civil Engineering Department, Engineering Faculty, P.O. Box 2440, Hail University, Hail, Saudi Arabia
(Received 29 May 2013; final version received 6 January 2014)
Estimating the cost of construction projects with high accuracy at the early phase of project development is crucial for
project planning and financing. Construction clients require early and accurate cost advice prior to site acquisition and
commitment to build in order to enable them to take the correct decision concerning whether to construct the project or not.
However, many factors might affect the accuracy of a cost estimate. This study aims at identifying the factors affecting the
accuracy of cost estimating construction projects in the West Bank in Palestine. A survey of 60 contractors and 45
consultants from the West Bank in Palestine was performed. Forty-one factors are identified in the study. The study
investigates the impact of those factors measured by level of importance and ranked according to an importance index from
both the contractors’ and the consultants’ points of view. The degree of agreement between the participating parties on the
importance ranking of the factors affecting cost estimating accuracy in construction projects is presented. The findings
reveal that the top five affecting factors according to the surveyed contractors are: fluctuation in currency exchange rate;
Downloaded by [University of Waterloo] at 09:07 25 October 2015
contract management; number of competitors; financial status of owners; and fluctuation of prices of materials. While the
top five factors according to the surveyed consultants are: the political situation; fluctuation of prices of materials; economic
instability; poor planning; and previous experience of the contractor.
Keywords: cost estimating; construction; importance index; accuracy; Palestine
1. Introduction and analysing all the costs which will enter into a
The construction industry is considered the backbone of particular job and arriving at a total. In nearly all contract
any economy in the world as it takes a relatively high types, the preparation of a realistic cost estimate is a
percentage of the national labor workforce and its necessary part of any construction operation (Holm,
contribution to gross domestic product (GDP) is also Schaufelberger, Griffin, & Cole, 2005).
high. Additionally, it plays a strategic role in both In Palestine, Mahamid and Bruland (2012) conducted
developed and developing countries and this industry is a study to investigate the statistical relationship between
one of the largest in the world due to its responsibility for the actual and the estimated cost of road construction
creating the infrastructure for cities, towns, and countries. projects using data from Palestinian projects awarded over
However, it is becoming more complex because of the the years 2004 to 2008. The study was based on a sample
many involved uncertainties during the life of a project of 169 road construction projects. The findings reveal that
due to the sophistication of the construction process itself, 100% of projects suffer from cost divergence; it is found
the large number of parties involved in the construction that 76% of projects have cost under estimation and 24%
process, and its sensitivity to external changes. have cost over estimation. The discrepancy between
The construction industry is a major element of the estimated and actual cost has an average of 14.56%,
Palestinian economy. Construction activities account for ranging from 2 39.3 to 98%. Mahamid (2014) conducted a
about 13.9% of all employed personel in Palestine and for study which revealed that the average cost overrun in
11.2% of value added to GDP in 2011. Furthermore, in the building projects constructed in the West Bank in Palestine
first quarter of 2012 it contributed 10.3% of GDP (PCBS, is between 10 and 30% of the original estimated cost of a
2012). Any improvement in the construction industry will project. The above examples demonstrate that the problem
probably lead a clear improvement in the Palestinian of cost deviation in construction projects in Palestine is
economy. An improvement in the construction industry alarming. Thus, the identification of factors affecting the
can be achieved by improving the construction project accuracy of cost estimates is highly important for
management functions. One of the most important alleviating this problem in the future. This study presents
construction management functions is the estimating the findings of a survey aimed at identifying the most
process (Abdal-Hadi, 2010). The success or failure of a important factors affecting cost estimating accuracy in
project is dependent on the accuracy of estimates. construction projects in the West Bank from both the
Accurate estimates optimize good contracting (Ahuja, contractors’ and consultants’ points of view. It is hoped
Dozzi, & Abou Rizk, 1994). It is the process of calculating that the findings will assist construction cost estimators in
Palestine and other developing countries in improving
their predictive ability of cost estimates by exploring
*Email: imahamid@ymail.com or i.mahamid@uoh.ed.sa factors affecting estimate accuracy.
q 2014 International Society of Management Science and Engineering Management
118 I. Mahamid
success factors influencing project performance in Nigeria. fluctuation in prices of raw materials; unstable cost of
Based on the result, objective management, management manufactured materials; high cost of machinery; lowest
of design, technical factors, top management support and bidding procurement procedures; poor project (site)
risk management were selected as the most critical success management/poor cost control; delays between design
factors in project performance. Al-Zarooni and Abdou and procurement phases; incorrect/inappropriate methods
(2000) conducted a survey to investigate variations in of cost estimation; additional work; improper planning; and
UAE public projects’ estimates. They found variations unsupportive government policies. Mahamid (2014)
(positive or negative) between feasibility and contract conducted a study to identify the risk factors affecting
cost, ranging between 2 28.5 and þ 36%. They stated that cost overrun in building construction projects in the West
these variations could be explained by the fact that Bank in Palestine from the contractors’ point of view. To do
feasibility estimates in government agencies are usually so, 31 contractors working in building construction
budgeted using a Single Unit Estimating (cost per square completed a structured questionnaire survey. The results
foot) basis, regardless of the nature of projects and their indicated that the top five affecting factors are: fluctuation
associated risks or the construction complexity of each in currency exchange rates; project financing; contract
building type. Enshassi, Mohamed, and Madi (2005) management; level of competition; and cost of materials.
identified the essential factors and their relative import- Abdul Rahman, Memon, and Abd. Karim (2013) conducted
ance that affect the accuracy of the cost estimation a study in Malaysia aimed at identifying the causes of
of building contracts in the Gaza Strip. The results of significant cost overruns in construction projects. They
analysing 51 factors considered in a questionnaire survey found that the top three most significant factors of cost
concluded that the main factors are: location of the project; overrun are: fluctuation in the prices of materials; cash flow
segmentation of the Gaza Strip and limitation of and financial difficulties faced by contractors; and poor site
movement between areas; the political situation; and the management and supervision. These factors belong to two
financial status of the owner. Koleola and Henry (2008) categories, i.e. contractor’s site management and financial
identified six important factors affecting the accuracy of a management.
pre-tender cost estimate in Nigerian construction projects. In order to have a general view about the main factors
These six factors are: the expertise of the consultants; the affecting cost estimating accuracy in construction projects,
quality of information and flow requirements; the project the findings of the investigated previous studies are
team’s experience of the construction type; the tender summarized in Table 1.
period and market condition; the extent of completion of
the pre-contract design; and the complexity of design and
construction.
Al-Juwairah (1997) conducted a study to identify the 4. Research methodology
most severe factors affecting construction costs in Saudi Forty-one factors that might affect cost estimating
Arabia. Forty-two factors were considered in the study. accuracy in construction projects were identified through
He concluded that the most severe factors affecting a literature review and discussion with local experts in the
construction costs from the contractors’ perspective are: the construction industry. The factors were tabulated in a
cost of materials; incorrect planning; contract management; questionnaire form. The questionnaire was developed in
wrong estimation methods; and previous experience of the order to evaluate the importance of the identified factors.
contractor. Iyer and Jha (2005) presented the findings of a Contractor and consultant information (i.e. names, grade,
questionnaire survey conducted on the factors affecting the and address) was collected from the Palestinian Contrac-
cost performance of Indian construction projects. Fifty-five tors Union (PCU). Data were gathered through a survey,
International Journal of Management Science and Engineering Management 119
Table 1. Main factors affecting cost estimating accuracy as presented in the investigated studies.
analysed by using an importance index, taking in the views In Equation (1), the multiplication by 100 is to obtain
of both contractors and consultants. Agreement on the the importance index as a percentage, and the division by
ranking of the importance of the factors affecting cost five is because the impact level of the identified factors
estimating accuracy between contractors and consultants was categorized on a five-point scale. Accordingly, if all
Downloaded by [University of Waterloo] at 09:07 25 October 2015
factors; construction items, construction parties; environ- Group importance indexð%Þ ¼ X i =n; ð2Þ
i¼1
mental; and financing factors. For each factor, a question
was asked: ‘What is the impact level of this factor on cost where Xi is the importance index of factor i under the
estimating accuracy in construction projects?’ The impact group and n is the number of factors under the group.
level was categorized on a five-point scale as follows: very
high, high, moderate, low, and very low (on a five to one
point scale).
6.2 Spearman’s rank correlation
The correlation is used to measure the degree of
correspondence between two lists of ranks of the sample
6. Data analysis
observation. This test is used to find and compare how well
The information collected from the questionnaire was the contractors and consultants agree on the importance of
analysed statistically using Excel statistical tools. the factors affecting cost estimating accuracy in construc-
The statistical methods used for calculating and presenting tion projects. A perfect positive correlation (rs ¼ þ 1)
the survey results are discussed below. means that the two samples rank each object identically,
while a perfect negative correlation (rs ¼ 2 1) means that
the ranks of the two samples have an exactly inverse
6.1 Ranking relationship. Values of rs between 2 1 and þ 1 denote less
than perfect correlation. The following formula is used for
The suggested factors are ranked by the measurement of
the importance index from both the contractors’ and the
consultants’ points of view. The following formula is used Table 2. Importance index range and the corresponding impact
to calculate the importance index: level.
X
Importance index ð%Þ ¼ aðn=NÞ £ 100=5; ð1Þ Range (%) Impact level
0 – 20 very low
where a is a constant expressing the weighting given to 20 – 40 low
each response (ranging from one for very low up to five for 40 – 60 moderate
60 – 80 high
very high), n is the frequency of the responses, and N is the
80 – 100 very high
total number of responses.
120 I. Mahamid
the calculation of the Spearman rank correlation: Table 3. Summary of sample size calculation trials.
X d2 Population I (contractors) Population II (consultants)
rs ¼ 1 – 6 £ ; ð3Þ
ðn 3 2 nÞ n0 173 92
n1 162 88
where rs is the Spearman rank correlation coefficient n2 84 45
(the agreement between contractors and consultants), d is n3 56 30
the difference between ranks on one variable and ranks on n4 42 22
n5 33 17
the other variable, and n is the number of factors. n6 27 14
n7 23 12
n8 20 11
indicated 173 registered contractors (grades 1, 2, and 3) The table shows that the ranking of factors from both
and 92 consultants (grade 1) with valid membership. The the contractors’ and the consultants’ points of view are
following formula was used to determine the sample size quite similar. But there is significant difference between
of participants (Emory, 1980): their ranking of ‘wrong estimation method’, which scores
ts2 ts2
rank 7 from the contractors’ point of view and rank 2 from
n¼ = 1þ =N ; ð4Þ the consultants’ point of view.
d d
Table 5. Ranking of factors related to construction items. Table 7. Ranking of environmental factors.
that the top three affecting factors under this group are: Social and cultural impacts 44,35 14 48,08 14
previous experience of the contractor; poor planning; and
the relationship between managers and labor.
The consultants indicate that the top three affecting factors 7.2.5 Financing factors
are: poor planning; previous experience of the contractor; Table 8 illustrates the importance index and ranking of
and lack of coordination between designers and contractors. financing factors. Three factors are identified under this
group. The contractors’ input indicates that the most
affecting factor under this group is fluctuation in the
7.2.4 Environmental factors currency exchange rate, followed by the financial status of
Table 7 illustrates the importance index and ranking of the owner, and the financial status of the contractor,
environmental factors. Fourteen factors are identified respectively. The consultants indicate that the top
under this group. The contractors’ input indicates that the affecting factor is the financial status of the contractor,
top three affecting factors under this group are: number of followed by the financial status of the owner, and
competitors; awarding the contract to the lowest bidder; fluctuation in the currency exchange rate, respectively.
and the political situation. The consultants indicate that the
top three affecting factors are: the political situation;
economic instability; and manipulation of suppliers.
7.2.6 Overall ranking
The table shows that the ranking of factors from both
the contractors’ and the consultants’ points of view are The importance index and ranking of all 41 factors
quite similar. But there is significant difference between investigated that might affect the accuracy of construction
their ranking of the following factors: cost estimating in the West Bank from both the
contractors’ and the consultants’ points of view are listed
. manipulation of suppliers, scoring rank 7 from in Table 9.
contractors and 3 from consultants; The results show that there are eight factors with
. project location, scoring rank 12 from contractors importance index above 80% from the contractors’ point
and 7 from consultants. of view, namely:
Table 11. Top ten factors and their related groups from the Table 12. Main groups ranking from both the contractors’ and
consultants’ point of view. the consultants’ points of view.
atically and efficiently managing contract creation, manipulation of suppliers; the financial status of the
execution, and analysis for the purpose of maximiz- owner; awarding the contract to the lowest bidder; and
ing financial and operational performance and contract management.
minimizing risk. As most of the involved parties in Contractors and consultants specify the same ranking
construction projects in the West Bank are of low of sources affecting cost estimating accuracy in
experience as discussed above, this leads to general construction projects. They specify financing factors as
weakness in contract management, which leads to the top ranked group, followed by factors related to
disputes on site between construction parties, which construction parties, environmental factors, factors
affect the cost performance. This result is supported related to construction items, and cost estimating factors,
by Mahamid (2014) and Al-Juwairah (1997) respectively.
The value of the Spearman’s rank correlation
5. Fluctuation of material prices coefficient of 0.83 shows that there is good agreement
Much of the literature investigated shows that between contractors and consultants on the importance of
fluctuation of the price of materials is one of the the factors affecting cost estimating accuracy in construc-
main factors affecting construction cost overrun. This tion projects in the West Bank in Palestine. Statistical
has many causes, e.g. inflation, supply and demand, analyses of the data show the following: (1) the minimum
monopoly, and the political situation. The construc- importance index has the values 36.29 and 32.69% from
tion sector in Palestine depends on importing the contractors and consultants, respectively; (2) group
construction materials from abroad, but because of
Downloaded by [University of Waterloo] at 09:07 25 October 2015
Mahamid, I. (2014). Contractors’ perception of risk factors Ogwueleka, A. (2011). The critical success factors influencing
affecting cost overrun in building projects in Palestine. project performance in Nigeria. International Journal of
The IES Journal Part A: Civil & Structural Engineering, Management Science and Engineering Management, 6,
7(1). doi: 10.1080/19373260.2013.854180. 343– 349.
PCBS (The Palestinian Central Bureau of Statistics). (2012).
Mahamid, I., & Bruland, A. (2012). Cost deviation in road Tables retrieved from http://www.pcbs.gov.ps/Portals/_
construction projects: The case of Palestine. Australasian Rainbow/Documents/Employed%20Person%20by%
Journal of Construction Economics and Building, 12, 58 –71. 20sector.htm
Downloaded by [University of Waterloo] at 09:07 25 October 2015