Professional Documents
Culture Documents
net/publication/301443034
CITATIONS READS
9 848
2 authors, including:
Chun-Lien Su
National Kaohsiung University of Science and Technology (NKUST)
164 PUBLICATIONS 2,555 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Chun-Lien Su on 22 September 2021.
Abstract--One of the most basic tasks for ship power system the generator fittings [2]. The methods emphasize the
design is electrical load analysis, which is used to determine investment cost of generators and do not consider their
the required installed capacity of on-board power generators.
energy efficiency due to level of loading, thereby in some
Traditionally, the analysis is carried out based on
cases resulting in the generators operated at conditions with
considerations of investment cost and supply adequacy, while
using a design of generators with the same rating. It does not low load factor. There have been several observations
consider the energy efficiency, thereby in some cases resulting experienced by shipyards concerning ship electrical load
in the generators operated at a lower efficiency under heavy analysis, some of which are shown in Table I.
loading conditions and high energy consumption. To enhance
power generation efficiency and reduce energy cost, a new TABLE I
load analysis method for marine vessels is proposed in this ACTUAL EXAMPLES OF GENERATOR INSTALLED CAPACITY DETERMINED BY
paper. The relationship of operation efficiency and load factor SHIP ELECTRICAL LOAD ANALYSIS
Generator Ratings
�
of generators is mathematically modeled and considered in the Total Power Supply
Rated (kW)/Load Factor of
analysis. The problem is formulated as a non-differential Type of Rated
Power Generators under
combinational optimization problem, where the total Exa m
ple Ship Voltage
(kW) Different Operating
No. (V) Conditions (%)
generation cost during a whole voyage is minimized subject to INumber
system operation and technical constraints, in order to derive CI:9000/77.23
C5: 1200/S4.32
the optimal generators rated power and unit commitment container
I 6600 3000/4 C4:9000/S5.65
using genetic algorithms. The results confirmed the validity of vessel
C7:9000/7S.S2
the proposed method through load analysis of a practical ship CS:3000/51.94
power system, as well as energy-saving benefits using the CI:12S0/47.60
C2:2560/SI.SO
proper generator rated power and unit commitment operation container
II 440 12S0/3 C5:3S40/79.90
vessel
and an accurate load model for power pumps. C7:2560/79.20
CS:12S0/36.00
CI:S00/S0.40
Index Terms--Industrial power system, Marine vessel, Load III bulk carrier 440 SOO/3 C6:2400/70.60
analysis, Power Generation, Energy efficiency. CS:SOO/5S.10
CI:440/S9.00
C3:SS0/5S.S0
I. INTRODUCTION IV bulk carrier 440 440/3
C6:1320/74.S0
CS:440/45.60
One of the most basic tasks for ship power system design CI:420/S2.40
is to determine the required installed capacity of on-board V
coast guard
440 420/3
C9:S40171.20
vessel C3:S40/S5.S0
power generators. To conduct the analysis, different CS:420167.00
methods, including load factor method, day and night load coast guard
C1:120160.09
VI 440 120/2 CIO: 120/76.97
method, probabilistic analysis method, and weighting load vessel
CS:120/32.72
method [1], are proposed. Among these methods, the load Note: Cl: Normal at sea; C2: Normal at sea With reefer; C3: Departure; C4: Departure with refer only;
C5: Departure with reefer & BIT; C6: Cargo handling; C7: Cargo handling with reefer; C8: Port
factor method or demand factor method is widely used in Service; C9: Nonnal at sea with gun fire pump; ClO: War condition
Authorized licensed use limited to: National Kaohsiung Univ. of Science & Technology. Downloaded on September 22,2021 at 07:19:37 UTC from IEEE Xplore. Restrictions apply.
2015-PSEC-0035 Page 2 of 11
Authorized licensed use limited to: National Kaohsiung Univ. of Science & Technology. Downloaded on September 22,2021 at 07:19:37 UTC from IEEE Xplore. Restrictions apply.
Page 3 of 11 2015-PSEC-0035
load demand under different operating conditions. For a where N is the number of operating conditions throughout
system planning point of view, the optimal combination of the voyage; lJu is the operating efficiency (%) of generator j
generator capacity and which generator should be put in under operating condition i; FRu is the fuel rate (g/kWh) of
operation and disconnected from the system are the key generator j under operating condition i; Tij is the operating
points of overall problem analysis. This type of problem can time (hours) of generator j under operating condition i; FC
be modeled as a combination problem. According to the is the unit cost of fuel oil for power generation ($/ton); Pu is
permutation and combination theory of probability statistics the active power output (kW) of generator j under operating
[9], if the number G of required on-board power generators condition i, where its magnitude can be determined
is given, the total number of repeated combinations selected according to the installed capacity of on-board generators,
from the M generator capacity options can be calculated as expressed as follows:
follows:
-
(M -1) !G!
1
1 G
MmF= I I--xPijxTijxFRijx10 xFC (5) (a) Power equilibration limit:
i=1 )=1 lJij
-4
Authorized licensed use limited to: National Kaohsiung Univ. of Science & Technology. Downloaded on September 22,2021 at 07:19:37 UTC from IEEE Xplore. Restrictions apply.
2015-PSEC-0035 Page 4 of 11
pump loads can be divided into deck machines and E/R pump; Q%P and H%P are the flow rate (m3/h) and lift
pumps. Deck machines include steering gear, windlass,
required for ballast pump (m), respectively, as obtained
warping winch, cargo crane, boat crane, and ladder; the E/R
from the following equations:
pumps are pumps, including sea water pump, fresh water
pump, gear pump, fuel oil pump, lubrication oil pump,
ballast pump, sewage water pump, air compressor, (17)
ventilation pump, bow thruster, and air-conditioning
equipment, for maintaining the population and power (18)
H BP = Hdis - H sue
systems operation security. These pumps can be divided into p
centrifugal pump, rotary pump, piston pump, and ejection
pump, according to the standard operating procedure [10].
Authorized licensed use limited to: National Kaohsiung Univ. of Science & Technology. Downloaded on September 22,2021 at 07:19:37 UTC from IEEE Xplore. Restrictions apply.
Page 5 of 11 2015-PSEC-0035
where VWBi is the total capacity of ballast tank (m3); T is the (g/cm\ and its value is 1.0; l7 �P is the efficiency of motor
time required for water ballast (hour); Hdis is the outlet head
P
for ballast pump (m); H,Mc is the inlet head for ballast pump for jacket water pump; l7 � IS the efficiency of jacket
(m). water pump.
The estimate in power demand for the power loads of the
In terms of the M/E jacket cooling fresh water pump, the ballast pump and jacket water pump can be determined by
heat generated by the combustion of the main engine must
(16) and (21), respectively. The result are then used to
be removed from the cylinder liner, thus, a closed cooling determine the total load of the system under specific
fresh water circulating system is required, including cooler, operating conditions according to equipment put in
centrifugal pump, expansion tank, and fresh water
operation, thus, ensuring an accurate estimate in load
generator for cooling in order to reach thermal equilibrium. demand data for electrical load analysis for determining the
To calculate the power demand of the jacket water pump, proper generator sizing and unit commitment.
the actual flow demand of the pump must be calculated.
First, the following heat transfer equation is used for the C. Solution Method
jacket water inlet and outlet temperatures, as well as the The optimization problem shown in (5) and (10)-(14) is a
rated flow of jacket cooling water, when the main engine is mixed integer non-linear programming problem, which can
under full load to determine the total heat generated by the be solved through mixed integer programming [12,13],
jacket cooling water and the main engine is under full load. dynamic programming [14,15], or artificial intelligence
algorithms [16-18]. The focus of this paper is not the
- QjW
h w - X
C
X
(jW
to lit jW) X 103
- tin (19) optimization of the problem-solving technology; therefore,
j rated
only a basic genetic algorithm (GA) [19] is used and
where hjw is the total heating value of jacket water (kcal/h); implemented to determine the optimal solution being close
Qj��ed is the rated flow of jacket water (m3!hr); C is the to the global optimum. The main computational procedure
of GA used in this work is described as follows:
specific heat of jacket cooling water (cal/gOC), which is 1. 0;
tb;� is the jacket water outlet temperature (C); tin is the Step 1- Coding: The generator set capacity configuration
and unit commitment scheduling problem is represented by
jacket water inlet temperature (C).
two bits, thus, the possible capacity and in operation (bit
When the heat balance of the cooling system determines value of 1), but not the in operation (bit value of 0) of
generator sets, should be modularized in each population of
the gross heating value, the actual flow demand of jacket
the analysis time period (whole voyage). For example, if the
water pump can be derived from the rated data of the jacket
total number of generators to be installed on the ship is 3,
water cooler, expressed as follows:
and there must be at least one generator running during any
time interval. Moreover, there will be 7 combinations of
jp h w
Q =
j unit commitment of generators under operating conditions,
p 3 (cl cl) (20)
10 C which are encoded by 3 bits. Tf the total number of on-board
X X tout - tin
generators is G, and the unit commitment is dispatched
where Q �P is the required flow rate of jacket water pump according to different operating conditions during the
voyage, the number of operating conditions in the analysis
(m3/h); t;;11 is the jacket water cooler outlet temperature time period is N. Thus, the gene structure for unit
commitment of generators under all operating conditions
(C); tf/z is the jacket water cooler inlet temperature (C).
during the voyage can be composed of GxN bytes. Tn
addition, the 4-bit gene structure of the rated power of diesel
The estimated value of the actual power demand of the generators is considered and used in this paper according to
jacket water pump can then be obtained from the following the generator technical data provided by manufacturers, as
equation: shown in Table TT. It is noteworthy that different gene
jp jp structures can be considered without altering the analysis
jp Qp xHp xgfiv method proposed in this paper.
P;n = ----:j'=-p--j"O":p'---"--
--- - (21) Step 2- Initialization: Different genes of the above generator
17m xl7p x367.13
rated power and unit commitment compose a chromosome,
and the populations of chromosomes compose the initial
where P; �P
is the input electrical power required for jacket population. The initial population can be designated
P according to experience or randomly generated. Tn this
water pump (kW); H �
is the head required for jacket paper, all initial populations are randomly generated.
water pump (m); gfiv is the specific gravity of fresh water
Authorized licensed use limited to: National Kaohsiung Univ. of Science & Technology. Downloaded on September 22,2021 at 07:19:37 UTC from IEEE Xplore. Restrictions apply.
2015-PSEC-0035 Page 6 of 11
Step 3- Evaluation: The better chromosome is determined be found from [20]. Note that the required power in Table
by evaluating the chromosome fitness function value. In the III includes line loss. Continuous duty (Cont.) refers to the
analysis, the power demands of ballast pump and jacket equipment works continuously in an operation status for 24
water pump are evaluated by (16) and (21), respectively. hours, including cooling sea and fresh water pumps, fuel oil
The rated power and unit commitment scheduling data of pump, etc. Intermittent duty (Int.) means the equipment
the generators represented by each chromosome are then works periodically or short-term in an operation status, e.g.
calculated by (6) in order to obtain the active power output air compressor, fuel oil transfer pump, warping winch, etc.
of each generator under different operating conditions. The Four design models for the electrical load analysis are
load factor of each generator is determined by (8). With the considered and shown as follows:
parameters for relationship to the efficiency, fuel oil
consumption rate, and load factor of each generator are
• Model-A: The electrical load analysis using traditional
calculated by (7) and (9). The objective function is
method (base case);
calculated by (6) from the unit cost data of fuel oil to form
the fitness function value that is defined as the aggregation • Model-B: The electrical load analysis using an accurate
of the objective function of (5) and the penalty factors for load model for power pumps;
violating the constraints of (10)-(14). • Model-C: The electrical load analysis considering power
Step 4- Crossover: Information exchange between two generation efficiency ;
chromosomes. The chromosome with smaller fitness value
• Model-D: The electrical load analysis using the proposed
must have higher probability to reproduce new offspring, method which simultaneously considers power generation
which is duplicated with the next generation chromosome. efficiency and an accurate load model for power pumps.
Step 5- Mutation: The chromosomes are randomly corrected
at a lower probability in order to ensure the possible The electrical load analysis result using Model-A is shown
solutions in any region of the solving space are searched, in Table TIT. The load factor in Table TIT is defined as the
and to avoid ignoring a possible solution during the total required power divided by the total power supply. In
reproduction and crossover processes. the analysis, the maximum operating time of each generator
should not exceed the total period of time during analysis of
In order to obtain better analysis results, tests were
336 hours, and the maximum and minimum power limits of
conducted repeatedly. The GA parameters used in this paper
generator are 90% and 20% of its rated power, respectively.
include a chromosome number of 200, elite policy rate of
The system spinning reserve ratio limit is assumed to be
0.2, crossover rate of 0.7, mutation rate of 0.02, and
10%. The curves for relation of generator load factor to its
maximum generation number of 300.
efficiency and fuel oil consumption rate are as shown in Fig.
T ABLE II 1. With the ryjax of 0.91 as observed in Fig. 1, the Cl and
GENE STRUCTURE OF RATED POWER OF DIESEL GENERATORS
Rated Power Rated Power C2 in (7) are determined as -21.8 and -0.067, respectively.
String String
(kW) (kW)
0000 336 1 000 772
For the parameters in (9), the aO, aI, a2, a3, a4, and a5 are
000 1 400 1001 800 determined as 484.3, -18.55, 7.61xl0·1, -1.47xlO·2,
00 1 0 500 1010 900
1.29xlO·4, and -4.184xl0·7, respectively. The unit cost of
00 1 1 560 10 1 1 1200
0 1 00 612 1 1 00 1 440 fuel oil used in the analysis is 659 USD per ton. It is noted
0101 640 1 101 1 600 that since only the shaft generator is operated under the
0110 688 1 1 10 2000 condition of sea going, this condition is not considered in
01 1 1 720 1111 2280
the load analysis.
Authorized licensed use limited to: National Kaohsiung Univ. of Science & Technology. Downloaded on September 22,2021 at 07:19:37 UTC from IEEE Xplore. Restrictions apply.
Page 7 of 11 2015-PSEC-0035
TABLE III
ELEClRICAL LOAD ANALYSIS RESULT USING MODEL-A
Load Analysis at Each Operating Nonnal at Sea Departure Cargo Handling In Port Emer ency
Condition Cont lnt Cont lnt Cont lnt Cont. lnt Cont lnt.
Required Power (kW) 545 1 29 1030 96 725 1 80 330 205 143 3
Diversity Factor I 2 I 2 I 2 I 2 I 2
Necessary Power (kW) 545 65 1030 48 725 90 330 103 143 I
Grand Total (kW) 610 1 078 815 433 144
Shaft Generator (kW) 720 - - - -
The ship is equipped with two ballast pumps, which suck respectively. The jacket water pump required flow is about
seawater into the ballast tank or discharge the seawater 81.53m3• The jacket water pump required head is then
from the tank during cargo handling operations. The obtained as about 30m by (20), and motor and pump
original design value of one pump motor input power is efficiencies are 0.9 and 0.75, which are substituted in (21)
240.9kW. The total capacity of the ballast tank is in order to obtain the jacket water pump motor required
106,891m3, and the time required by the owner for ballast power of about 9.87kW.
operation is 20 hours. The required flow rate of a ballast According to the comparison between the original design
pump is 2673m3, as calculated by (17). In addition, values of the ballast pump and jacket water pump motors
according to the design data, the total depth of the ship is and the values obtained from the load model proposed in
24m. The draft of the empty ship after handling is 11m, and this paper, the original design value of the ballast pump
the draft of the full loaded ship is 16m. As the ship is empty motor power is 240.90kW, the calculated value obtained
before loading operations, the ballast water must be pumped with the proposed load model is 150.28kW, and the power
out of the ship, and the maximum required head is 16m. demand is reduced by 37.62%. In terms of the jacket water
The ship is in full load condition before discharging pump, the original design value of motor power and the
operation, seawater must be pumped into the ballast tank, calculated value with the proposed load model are 19.6kW
and the maximum required head is also 16m. Therefore, the and 9.87kW, respectively. The required power is reduced by
maximum required head of ballast pump is 16m. The about 49.64%. The result of required power for the ballast
required flow rate of the ballast pump and maximum pump and jacket water pump motors with the proposed load
required head are substituted in (16) in order to obtain the model is used in the electrical load analysis. The results are
ballast pump required power of about 150.28kW. In the shown in Table IV. It can be seen from Table IV that an
analysis, the ballast pump efficiency and motor efficiency accurate estimate in require power for ballast pump and
are 0.93 and 0.85, respectively. The ship is equipped with jacket water pump power motors has reduced the total
two jacket water pumps which are mostly used during the require powers for the conditions of normal at sea,
operation of the main engine, thus, it is used only in the departure, and cargo handling. The total require powers are
conditions of normal at sea and departure. The original reduced from 610kW, 1078kW, and 815kW to 600kW,
design value of the pump motor power is 19.6kW. The 1068kW, and 724kW, respectively. If the existing design for
theoretical value of the required power of the jacket water three generators with rated power of 720kW is used, the
pump can be calculated by (21) to review the existing load factors in these three operating conditions are reduced
design result. First, the jacket water inlet, outlet temperature, from 84.72%, 74.86%, and 56.60% to 83.33%, 74.17%, and
° 50.28%, respectively. The result shows that an accurate load
and flow of the main engine under 100% load, are 81 C,
° 3 model for the power pumps can have a significant impact
73 C and 160m , respectively, and are substituted into (19)
to obtain the maximum heating value of the main engine on the total power consumption of the ship. It has relative
jacket water, which is 1,280,000kcallh. According to the relationships to ship investment cost, fuel oil cost, fittings
cooling system heat balance theory and the specifications cost, and maintenance cost. If each pump has at least 25
for main engine jacket water cooler, the maximum cooling years of service life, the non-required energy consumption
° ° of the pumps during the service life can be reduced. The
temperatures of inlet and outlet are 80.8 C and 65.1 C,
result also indicates that with the proposed load model, the
Authorized licensed use limited to: National Kaohsiung Univ. of Science & Technology. Downloaded on September 22,2021 at 07:19:37 UTC from IEEE Xplore. Restrictions apply.
2015-PSEC-0035 Page 8 of 11
total required power of the ship under different operating ship owners in performing ship energy efficiency
conditions can be accurately estimated and actual power management plan.
consumption of the ship can be reflected, which can assist
TABLE IV
ELEClRICAL LOAD ANALYSIS RESULT USING MODEL- B
Load Analysis at Each Operating Normal at Sea Departure Cargo Handling In Port Emer ency
Condition Cont lnt Cont lnt Cont lnt Cont. lnt. Cont. lnt.
Required Power (kW) 535 1 29 1 020 96 634 180 330 205 1 43 3
Diversity Factor I 2 I 2 I 2 I 2 1 2
Necessary Power (kW) 535 65 1 020 48 634 90 330 1 03 1 43 1
Grand Total (kW) 600 1068 724 433 144
Shaft Generator (kW) 720 - - - -
TABLE V
CANDIDATE LIST OF COMBINATION OF RATED POWER AND UNIT COMMITMENT OF GENERATORS
As can be seen from Table III that the required power generators for the engineers, which can be used to match
varies with the operating conditions, thus, it is impossible to individual owner's special needs.
implement high power generation efficiency under different Based on the optimal solution of 336/500/612kW in Table
operating conditions if generator with the same rated power V, the electrical load analysis result using Model-C is
is used. With the proposed method, the optimal combination shown in Table VI. With the computational procedure
of rated power and unit commitment of generators can be mentioned above, the electrical load analysis with
derived by the genetic algorithm. The analysis results of the considering power generation efficiency and an accurate
first 10 optimal combinations are shown in Table V. In the load model for power pumps can be performed and the
analysis, the number of generators to be installed is 3. It can optimal solution is 336/5001nOkW, as shown in Table VIT.
be seen from Table V that the optimal solution is lt can be seen from Table VII that with the optimal solution,
336/500/612kW, and all three generators must be switched the maximum efficiency occurs during the condition of
in operation during the condition of departure (about 12 departure, which is about 87.54%, when the 500kW and
hours). If the result is not acceptable, as the owner has nOkW generators are switched in operation. From Tables
stand-by generator safety considerations, the generator VI and VIT, it is observed that the determination of sizing of
sIZIng combination can be 500/5001nOkW. This generators is closely related to the unit commitment and
combination only requires two generators in the condition required power under different operating conditions. For
of departure. However, the operation and maintenance costs example, in the condition of departure, the total required
resulted from the increased generator rated power may be powers for Model-C and Model-D are 1078kW and 1068kW,
increased. Differing from the traditional design method, the respectively. The number of generators in operation is 3 and
proposed method can provide different combinations of 2, respectively, which are 336kW/500kW/612kW and
Authorized licensed use limited to: National Kaohsiung Univ. of Science & Technology. Downloaded on September 22,2021 at 07:19:37 UTC from IEEE Xplore. Restrictions apply.
Page 9 of 11 2015-PSEC-0035
500kW1720kW and the load factors of generators are after performing an accurate estimate in power required for
74.44% and 87.54%, respectively. For the condition of ballast pump motor. Thus, the fuel cost per voyage is
cargo handling, the total powers for Model-C and Model-D 1,334.83 USD lower than Model-A. If there are 12 voyages
are 815kW and 724kW, respectively. There are two in a year, the annual power generation fuel cost can be
generators in operation, which are 336kW/612kW and reduced by 16,017.96 USD, for an energy-saving percentage
336kW/500kW, respectively. The load factors of generators of 3.42%. For Model-C, the rated powers of generators are
are 85.97% and 86.60%, respectively. Test results have changed from 72017201720kW of Model-A to
shown that for obtaining better analysis results, the load 336/500/612kW. The required generation fuel decreases as
model should be carefully studied and considered together the power generation efficiency increases. The fuel costs can
with unit commitment in the electrical load analysis. be reduced by 3,864.78 USD for one voyage, and the annual
Based on the unit cost of fuel oil and annual voyage data cost can be reduced by 46,377.36 USD, for an energy-saving
provided by the owner, the analysis results using Model-A, percentage of 9.90%. It is noteworthy that the generator
Model-B, Model-C, and Model-D, as shown in Tables ITI, rated powers of 336/500/720kW for Model-D are larger
IV, VI, and VII, are converted into monetary values for than those for Model-C; however, the unit commitment
comparisons. Using the annual generation fuel cost for significantly depends on the optimum operating efficiency
Model-A as a basis, the annual energy-saving benefit and of generators, while scheduling aims at minimization of fuel
percentage using Model-B, Model-C, and Model-D are costs. The analysis results showed that with Model-D, the
calculated. The results are shown in Table VITI. As can be fuel cost per voyage and annual fuel costs are 5,562.19 USD
seen from Table VITI, the fuel cost per voyage for Model-A and 66,746.28 USD lower than Model-A. The energy
is 3,9041.35 USD. The required power under the condition saving percentage is 14.25%, which is higher than Model-B
of cargo handling for Model-B is reduced by almost 100kW and Model-C.
TABLE VI
ELECTRICAL LOAD ANALYSIS RESULT USING MODEL- C
Load Analysis at Each Operating Normal at Sea Departure Cargo Handling In/Out Port Emer ency
Condition Cont. Int. Cont. Int. Cont. Int. Cont. Int. Cont. Int.
Required Power (kW) 545 1 29 1030 96 725 180 330 205 1 43 3
Diversity Factor 1 2 1 2 1 2 1 2 1 2
Necessary Power (kW) 545 65 1030 48 725 90 330 1 03 1 43 1
Grand Total (kW) 610 1078 815 433 144
Shaft Generator (kW) 720 - - - -
TABLE VII
ELECTRICAL LOAD ANALYSIS RESULT USING MODEL-D
Load Analysis at Each Operating Normal at Sea Departure Cargo Handling In/Out Port Emer ency
Condition Cont. Int. Cont. Int. Cont. Int. Cont. Int. Cont. Int.
Required Power (kW) 535 1 29 1 020 96 634 180 330 205 1 43 3
Diversity Factor 1 2 1 2 1 2 1 2 1 2
Necessary Power (kW) 535 65 1 020 48 634 90 330 1 03 143 1
Grand Total (kW) 600 1068 724 433 144
Shaft Generator (kW) 720 - - - -
Authorized licensed use limited to: National Kaohsiung Univ. of Science & Technology. Downloaded on September 22,2021 at 07:19:37 UTC from IEEE Xplore. Restrictions apply.
2015-PSEC-0035 Page 10 of 11
TABLE VIII
COMPARISONS OF ENERGy - SAVING BENEFITS USING DIFFERENT DESIGN MODELS
Desit,'Il Models Model-A Model-B Model-C Model-D
Rated Power of
72017201720 72017201720 3 3 6/500/6 1 2 3 3 6/5001720
No. I/No. 2iNo. 3 Gen. (kW)
Cargo Cargo Cargo Cargo
Operation Conditions Dept In Port Dept In Port Dept In Port Dept In Port
Hand. Hand. Hand. Hand.
Rlmning T imes (hours) 12 96 228 12 96 228 12 96 228 12 96 228
Total System Demand and
1 078 815 433 1068 724 433 1 078 815 433 1 068 724 433
Loss (kW)
1 0 1 0 0 1 0 1 1 0 0 1 0
Gen.
tic; 2 1 1 1 1 1 1 1 0 1 1 1 1
No.
3 1 0 0 1 0 0 1 1 0 1 0 0
1 0 407. 5 0 0 362 0 250. 1 4 288.86 0 0 290. 99 0
Rated Power Gen.
2 539 407. 5 433 534 362 433 372.24 0 433 437. 7 1 433 . 0 1 433
(kW) No.
3 539 0 0 534 0 0 455.62 526 . 1 4 0 630.3 0 0
1 0 56.6 0 0 50.28 0 74.45 85 . 97 0 0 86.6 0
Loading Gen.
2 74. 86 56.6 60. 14 74. 17 50.28 60. 1 4 74.45 0 86.6 87.54 86.6 86.6
(%) No.
3 74. 86 0 0 74. 17 0 0 74.45 85 . 97 0 87.54 0 0
1 0 90. 6 1 0 0 90.35 0 90.95 9 1 . 03 0 0 9 1 . 03 0
Efficiency Gen.
2 90.96 90. 6 1 90. 7 1 90.95 90.35 90.71 90.95 0 9 1 .03 9 1 .04 9 1 . 03 9 1 . 03
(%) No.
3 90.96 0 0 90.95 0 0 90.95 9 1 . 03 0 9 1 .04 0 0
1 0 287.72 0 0 296.94 0 26 1 . 42 255.47 0 0 255.45 0
FOCR Gen.
2 26 1 . 0 1 287.72 2 8 1 . 96 26 1 . 7 1 296.94 28 1 . 96 26 1 . 42 0 255.45 255.46 255.45 255.45
(gkWh) No.
3 26 1 . 0 1 0 0 26 1 . 7 1 0 0 26 1 . 42 255.47 0 255.46 0 0
1 0 12.42 0 0 1 1 .42 0 0 . 86 7.78 0 0 7 . 84 0
FOC Gen.
2 1 . 86 12.42 30.69 1 . 84 1 1 .42 30.69 128 0 27.70 1 . 47 1 1 .67 27.70
(Ton) No.
3 1 . 86 0 0 1 . 84 0 0 1 . 57 14. 1 8 0 2 . 12 0 0
1 0 8 1 86.28 0 0 7526. 87 0 568.57 5 1 28.6 0 0 5 1 65.75 0
Fuel Cost Gen. 1 8256.3
2 1223 . 14 8 1 86.28 20222 . 5 1 2 1 5 . 1 4 7526. 87 20222 . 5 846.08 0 1 8256.32 9 7 1 . 3 7687. 1 2
($) No.
3 1223 . 14 0 0 1215. 14 0 0 1035.6 934 1 . 3 9 0 1398.67 0 0
Fuel Cost ($/vovage) 3904 1 . 3 5 37706. 52 3 5 1 76 . 57 33479. 16
Annual Fuel Cost ($/year) 468496. 2 452478. 24 422 1 1 8 . 84 401749.92
Energy-Saving Benetit
N/A 1334.83 3864.78 5562. 1 9
($/vovage)
Annual Energy-Saving
N/A 1 60 1 7 . 96 46377.36 66746.28
Benetit ($/year)
Energy-Saving Percentage
N/A 3 . 42 9.90 14.25
(%)
V . C ONCLUSIONS REFERENCES
A new method for ship electrical load analysis considering [1] M. A. Walker and C. R. Riggs, "A realistic approach to electrical load
analysis for marine vessels," in Proc. OjJShore Technology Conference,
power generation efficiency has been proposed. An accurate 1 97 8 .
analytical load model was derived for evaluating required [2] L. L. .I. Mahon, Diesel Generator Handbook, Butterworth-Heinemann,
power for pumping systems on ships. A mathematical 1 9 92.
[3] S . V. Giannoutsos and S . N . Manias, "Development of an integrated
model was also derived for the generator efficiency and fuel energy efficiency control system for ship power balance and diesel
consumption rate as a function of the generator load factor. generator fuel consumption optimization," in Proc. 2013 IEEE lAS
Load analysis of a practical ship power system confirmed Annual Meeting.
[4] C. L. Su, W. L. Chung, and K. T. Yu, "An energy-savings evaluation
the power required for different types of pumps driven by method for variable frequency drive appl ications on ship central cooling
motors, which had been estimated theoretically. The test systems," IEEE Trans. on Industry Applications, vol. 50, no. 2 ,
results indicated that an estimate in power required for March/April 2 0 1 4 , p p . 1 2 8 6 - 1 2 9 4 .
[5] C. L. S u , Y H . Yeh, C . H . Liu, C. W. Lin, L. W. Wang, and C . C . Lee,
pump loads can have a significant impact on the load "Energy-efficient electronic Iight sources for marine vessels," in Proc.
analysis. The results also showed that for obtaining better 2012 IEEE lAS Annual Meeting.
analysis results, the load model should be carefully studied [6] C. L. Su, M. C. Lin, and C. H. Liao, "A method for evaluating energy
efficiency to justity power factor correction in ship power systems,"
and considered together with unit commitment in the load IEEE Trans. on Industry Applications, November/December 2 0 1 3 , vol .
analysis. Because of this, a load analysis with large energy 49, no. 6, pp. 2773-2782.
saving benefits originates from relatively more accurate load [7] Implementing a Ship Energy Efficiency Management Plan (SEEMP) :
Guidance for Shipowners and Operators, Lloyd' s Register, Technical
model and proper generator sizing and unit commitment, as Report, June 2 0 1 2 .
observed in the load analysis results. [8] Diesel Generator Efficiency Curve for Ship-N4 1 7, Nisisiba Electric Co.
Ltd. Technical Report, February 2 0 1 1 .
Authorized licensed use limited to: National Kaohsiung Univ. of Science & Technology. Downloaded on September 22,2021 at 07:19:37 UTC from IEEE Xplore. Restrictions apply.
Page 11 of 11 2015-PSEC-0035
BIOGRAPHIES
C hun-Lien Su ( S ' 97-M' 0 1 -SM' 1 3) received the Diploma of Electrical
Engineering from National Kaohsiung Institute of Technology, Taiwan, the
M . S . and Ph.D. degrees in Electrical Engineering from the National Sun Yat
Sen University, Taiwan in 1 9 92, 1 9 97, and 200 1 , respectively. Since 2002,
Dr. Su has been with the National Kaohsiung Marine University, Taiwan and
is now Professor of the Marine Engineering Department H is main areas of
interest are power system analysis and computing, power quality, and ship
power and electrical systems.
Authorized licensed use limited to: National Kaohsiung Univ. of Science & Technology. Downloaded on September 22,2021 at 07:19:37 UTC from IEEE Xplore. Restrictions apply.
View publication stats