You are on page 1of 173

LM Jade Installation instruction

Table of Contents „reduced headroom“


09
M-09.500.122-E

Status: 03/07 Page 1 of 3

Installation instruction
Machineroomless lift Jade
„reduced headroom“
LM Jade Installation instruction

Table of Contents „reduced headroom“


09
M-09.500.122-E

Status: 03/07 Page 2 of 3

Table of contents

1. General arrangement drawing / 3-D Overview Z-09.500.120


2. General part M-09.500.001-E
3. Guide rails & rail brackets M-06.584.000-E
4. Machine support M-01.501.231-E
5. Overspeed governor attachment M-01.501.212-E
6. Tensioning weight M-04.554.610-E
7. Counterweight M-04.140.000-E
8. Car frame M-04.130.100-E
9. bufferupstand M-06.455.410-E
10. Installation of drive unit M-01.501.230-E
11. Brake resistor attachment M-08.500.030-E
12. Ropes & rope suspensions M-05.500.001-E
13. Counterweight protection & rope stretch compensation M-06.231.000-E
14. Suspension for travelling cables M-08.470.002-E
15. Limit switches & accessories M-08.438.210-E
16. Filler element for reduced pit M-06.309.022-E
17. foldable ceiling M-03.420.100-E
18. Cable plan M-08.470.001-E
19. Instruction for commissioning, testing and maintenance
“reduced headroom I-09.500.122-E
20. Spare parts list E-09.500.120-E
LM Jade

Table of Contents „reduced headroom“


Installation instruction
09
M-09.500.122-E

Status: 03/07 Page 3 of 3

Introduction

You have decided to buy a machineroomless lift of LM LIFTMATERIAL.


We wish to congratulate you on this decision since you will get a high-quality
lift which can be used for various purposes in a very flexible way .

All components, whether mechanical or electrical, are supplied pre-mounted


resp. pre-wired and pluggable whenever possible.

Please observe the following installation instructions and read them carefully
before starting the installation. In these instructions we describe the basic
functions of the lift.

More details for installation and adjustment of the lift please take from the
separate instructions attached to the individual components, like:

 Landing and car doors


 Car
 Control (electrical diagrams and controller manual)
 Frequency inverter
 Weighing device
 Drive and brake unit
 Overspeed governor and tensioning weight
 Buffer
 safety gear
LM Jade Installation instruction

Table of Contents „reduced headroom“


09
M-09.500.122-E

Status: 03/07 Page 1 of 3

Installation instruction
Machineroomless lift Jade
„reduced headroom“
LM Jade Installation instruction

Table of Contents „reduced headroom“


09
M-09.500.122-E

Status: 03/07 Page 2 of 3

Table of contents

1. General arrangement drawing / 3-D Overview Z-09.500.120


2. General part M-09.500.001-E
3. Guide rails & rail brackets M-06.584.000-E
4. Machine support M-01.501.231-E
5. Overspeed governor attachment M-01.501.212-E
6. Tensioning weight M-04.554.610-E
7. Counterweight M-04.140.000-E
8. Car frame M-04.130.100-E
9. bufferupstand M-06.455.410-E
10. Installation of drive unit M-01.501.230-E
11. Brake resistor attachment M-08.500.030-E
12. Ropes & rope suspensions M-05.500.001-E
13. Counterweight protection & rope stretch compensation M-06.231.000-E
14. Suspension for travelling cables M-08.470.002-E
15. Limit switches & accessories M-08.438.210-E
16. Filler element for reduced pit M-06.309.022-E
17. foldable ceiling M-03.420.100-E
18. Cable plan M-08.470.001-E
19. Instruction for commissioning, testing and maintenance
“reduced headroom I-09.500.122-E
20. Spare parts list E-09.500.120-E
LM Jade

Table of Contents „reduced headroom“


Installation instruction
09
M-09.500.122-E

Status: 03/07 Page 3 of 3

Introduction

You have decided to buy a machineroomless lift of LM LIFTMATERIAL.


We wish to congratulate you on this decision since you will get a high-quality
lift which can be used for various purposes in a very flexible way .

All components, whether mechanical or electrical, are supplied pre-mounted


resp. pre-wired and pluggable whenever possible.

Please observe the following installation instructions and read them carefully
before starting the installation. In these instructions we describe the basic
functions of the lift.

More details for installation and adjustment of the lift please take from the
separate instructions attached to the individual components, like:

 Landing and car doors


 Car
 Control (electrical diagrams and controller manual)
 Frequency inverter
 Weighing device
 Drive and brake unit
 Overspeed governor and tensioning weight
 Buffer
 safety gear
LM Elevator

Installation General Part


Installation instruction
09
M-09.500.001-E

Status: 07/03 Page 1 of 7

Installation instruction
General part
LM Elevator

Installation General Part


Installation instruction
09
M-09.500.001-E

Status: 07/03 Page 2 of 7

I. Introduction

This installation instruction applies to the installation of the compo-


nents of an LM lift. It is meant für fitters who are trained for working
on lift equipment and who are familiar with the safety regulations
applicable to this domain.

The installation instruction includes important advice for the proper


and safe erection. Sticking to it will minimize the cost for repair and
down-time, creating the conditions for an enduring and fault-free
operation of the whole lift equipment.

II. Safety instructions

Area of applicability
These safety instructions apply to passenger and goods lifts, plan-
ned, assembled and supplied by LM LIFTMATERIAL GmbH in ac-
cordance with the lift directive 95/96/EC, installation carried out by
the installer.

Text symbols
Hazard
This symbol attracts attention to a high risk of injury for persons. It is
always to be observed.
Caution
This symbol attracts attention to information, non-observance of
which may lead to personal injuries or/and to considerable material
damages.
Check
This symbol refers to visual checks resp. checks of condition, re-
spective measurement checks or adjustments.
Note
This symbol attracts attention to important information.
LM Elevator

Installation General Part


Installation instruction
09
M-09.500.001-E

Status: 07/03 Page 3 of 7

Standards
The lifts are designed according to the state of the art and comply
with the requirements of lift directive 95/96/EG.

LM LIFTMATERIAL observes the following basic standards, as far


as applicable to the respective equipment:
95/16/EG Lift directive
- EN 81-1/2
89/336/EWG Directive regarding the elektro-magnetic
compatibility
- EN 12015 - EN 50081
- EN 12016 - EN 50082
98/37/EG Machinery directive
93/68/EWG Low voltage directive
Further national standards are probably to be observed by the in-
staller.

In case of type-examined lifts, for instance the LM Emerald


(machineroomless lift), the deviations described in the installation
instructions need special attention.

Since not all the components used are manufactured by LM LIFT-


MATERIAL, individual standards can be taken from the manufac-
turers declarations, which are made up according to the configura-
tion of the lift.

Demands on the installer


The installer ensures that only appropriately trained persons - theo-
retically and practically - having sufficient experience in the field of
lift installation, commissioning and maintenance are employed.
Furtheron the installer ensures that in particular the professional skill
of the employees is regularly checked and updated. Upon demand,
LM LIFTMATERIAL is prepared to render necessary assistance and
advice to the installer.

Commissioning
The lift shall be put into operation only after verification that
- the individual components are mounted according to the
installation instructions
- they comply with the basics of the safety and health require-
ments of the specified directives and standards,
- the declaration of conformity is made out by the installer, con-
firmed by a CE-sign fitted in the car,
- the operating instruction has been handed over and its under-
standability is confirmed in writing,
- the documentation acc. to EN 81/1998 has been handed over.
LM Elevator

Installation General Part


Installation instruction
09
M-09.500.001-E

Status: 07/03 Page 4 of 7

Intended use
In order to restrict hazards upon installation and for the future users,
all components are to be installed according to the intended use in
compliance with the requirements of the installation instructions.
Modifications, extensions or alterations not in compliance with the
intended use or carried out without the approval of the manufac-
turer, are not permitted.
Examinations in connection with installation work that are
prescribed by the manufacturer are to be carried out definitely.

III. Safety precautions

General
In addition to this installation instruction - for all installation work -
national and local regulations on work safety and accident prevention
measures are to be observed.
Special attention is drawn to the following accident prevention rules
resp. instructions of the Health and Safety Executives:
- General directives (VBG 1),
- Electrical installations (VBG 4),
- Operation of hoisting equipment (VBG 9a),
- Welding, cutting (VBG 15)
- Instructions on safety measures upon installation and repair of lift
equipment (ZH 1/312),
- Safety rules for hoistable transportation means for persons
(ZH 1/461)

Basically, the installer/fitter takes appropriate measures enabling safe


working and safe staying (of visitors also !) within the installation a-
rea.
Here, the following measures must be emphasized:

Supervision
As a matter of principle, one person has to supervise the work. Work-
ing alone is only allowed if in case of danger help can be called for at
any time.

Instruction
Fitters are to be instruced about the safety rules in regular intervals.

Protective kit
Any person staying within the installation area shall wear the per-
sonal protective kit (e.g. safety helmet and safety boots).
LM Elevator

Installation General Part


Installation instruction
09
M-09.500.001-E

Status: 07/03 Page 5 of 7

Protection
Appropriate safety measures must be taken at shaft entrances, floor
openings, hydraulic systems, work beneath the car etc..
Work at the underside of the car shall be carried out only in the
lowest possible area of the shaft.
Open shaft entrances must be provided with barriers and warning
labels.

Safe work with electrical utilities


Safe work with electrical utilities (e.g. connecting) shall be carried out
only in accordance with VDE 0100. In case of electrical welding the
welding-current return cable must be connected directly to the work-
piece that is to be welded. It is not allowed to use the installation sur-
rounds for the return of the welding current (refer to VBG 15).

Installation without scaffold


For that, suspended platforms, conveyor cages, suspended stools
etc.are used. Design and equipment of these installation appliances
are subject to particular safety requirements (refer to ZH 1/461 and
ZH 1/312).
These safety requirements are to be strictly observed.

Installation with scaffold


All erection platforms must be fixed to the wall with sufficiently di-
mensioned anchors.
Before stepping on, the fitter has to make sure about the unobjec-
tionable condition of the platform (load capacity, non-slipping etc.).

Hoist
Crane crabs, pulley tackles, winches etc. shall be charged with the
specified admissible load only. The load data specified for the LM
components are to be observed.
Preferably, steel wire ropes shall be used.

Work in the shaft


This is allowed only after completion of all work that is to be carried
out before (e.g. brick work).
It is prohibited to work at the same time on platforms being arranged
one above the other.
When leaving the installation place, all door openings to the shaft
must be barred.
LM Elevator

Installation General Part


Installation instruction
09
M-09.500.001-E

Status: 07/03 Page 6 of 7

In case of special hazards


Hazards by gases, steam, smoke and dust
If welding, flame cutting or grinding is unavoidable, special attention
is to be drawn to the following:
- work surrounds to be cleaned from dust and combustible materials
- endangered working area to be covered with metal plate or similar
means
- fire extinguishing equipment to be kept ready
- provision of sufficient ventilation (caution in case of small rooms!)
- fire-endangered area and its surround shall be checked repeatedly
after completion of work.

Oil, grease and other chemical substances


Here, the product-related safety regulations are to be observed. Be
careful when dealing with hot consumables!

IV. Warranty/Liability

LM LIFTMATERIAL accepts only the warranty for lifts which have


been installed in accordance with our installation instructions and are
used according to the intended purpose. The installation has been
design in conformity with the information available to us about:
- kind of usage,
- ambient temperature,
- other special requirements.

Use of the lift or of individual components for purposes which is not to


the intended use is not allowed.
The installer shall be liable for any damages resulting therefrom.

V. Definitions

Installer
The individual or juridical person who is responsible for the design,
the manufacture and the installation of the lift.

Manufacturer
The individual or juridical person who is responsible for the design
and the manufacture of the lift components.

User/Owner
The individual or juridical person who disposes of the lift and takes
responsibility for the planned usage and for the operation.
LM Elevator

Installation General Part


Installation instruction
09
M-09.500.001-E

Status: 07/03 Page 7 of 7

Installation
A complete passenger and/or goods lift which has been handed over
to the user/owner.

Safety components
Components defined in lift directive 95/16/EG Annex IV.

Commissioning
Moment, when the authorized representative of the installer initially
hands over the lift to the user/owner.
LM Jade

Guide rails & rail brackets


Installation instruction
06
M-06.584.000-E

Status: 11/06 Page 1 of 16

Installation instruction
Guide rails & rail brackets
LM Jade

Guide rails & rail brackets


Installation instruction
06
M-06.584.000-E

Status: 11/06 Page 2 of 16

Table of contents Page

1. Preparation for installation ……………………………………………………. 002


1.1 Overall view on delivered parts …….………………………………… 003
1.2 Introduction …………………………………………………………. 004
1.3 Preparatory work .......…………………………………………………. 004
1.4 Installation sequence .....…………………………………………….. 004
2. Shaft plumbing .............…………………………………………………………. 005
2.1 Shaft measuring ………………………………………………... 005
2.2 Plumb lines setting ………………………………………………... 005
2.3 Establishing the usable shaft depth resp. width……………………... 006
2.4 Shaft gauge ........... ………………………………………………… 007
2.5 List of shaft dimensions ………………………………………………… 008
3. Rail brackets …………………………………..……….……………. 009
3.1 Fixing to Halfen channels …………………………………………….. 009
3.2 Fixing with plugs ...... ……………………………………………….. 011
3.3 Setting of car guide rails ............ ……………………………. 013
3.4 Setting of counterweight guide rails .............…………………… 014
3.5 Guide rail joints …………………………………………………………. 015
3.6 Check of Guide rail joints ………………………………………. 016
3.7 Fixing of the oiltray .............………………………………………. 016

1. Preparation for installation

1.1 Overall view on delivered parts

The guide rails are delivered in finished lengths of 5000mm, together with
the fixing parts and accessories.

The end pieces of the rails are cut to length and can be mounted either on
top or bottom of the rail track (observe the general arrangement plan)
LM Jade

Guide rails & rail brackets


Installation instruction
06
M-06.584.000-E

Status: 11/06 Page 3 of 16

Shaft wall

Shaft wall

Rail bracket (fixing


with dowel)

Fishplate
! Note ! Car guide rail

The fishplate in the zone of


the drive supporting beam is
omitted as the rail connec-
tion is performed by means Fishplate
of the drive supporting beam. Counterweight
Shaft wall guide rail
Details please find in chapter
“Drive supporting beam”. Guide rail
Counterweight

Rail bracket
Shaft wall (fixing to Halfen
channels)

Guide rail
Car

Fig. 001
Rail base plate

Rope length compensation

Oiltray
LM Jade

Guide rails & rail brackets


Installation instruction
06
M-06.584.000-E

Status: 11/06 Page 4 of 16

1.2 Introduction

The correct setting of the guide rails is the most important part of installation. The
accuracy of this work decides on the later travelling properties of the lift and the
fault-free functioning of the shaft information switches and the landing doors as
well.

1.3 Preparatory work

The praparations for the installation represent an important element of the whole
installation. Insofar, special attention is to be paid to the preparatory works.

Installation technicians / installing companies shall consider the following:

- Attentive reading of this installation instruction before the begin of the installa-
tion, especially the remarks on work safety,
- Knowledge of kind and extent of provisions by the customer (e.g. provision of
appropriate hoisting means, availability of erection scaffolds),
- Inspection of the building site before before the begin of the installation (e.g. in-
spection of access ways and building accesses, storage facilities, safety of
erection scaffolds, availability of protections in the shaft),
- Check of already performed work (e.g. installation of Halfen channels correct
and in true position, check of the shaft dimensions),
- Reporting of possible defects or damages to the site management,
- Indication of the probable end of installation.

1.4 Installation sequence


after erection of the plumbing scaffold installation is carried out in following steps:
• Shaft measuring,
• Rail bracket mounting,
• Rail position establishment,
• Guide rail setting,
• Guide rail alignment,
• Oiltray fixing.
LM Jade

Guide rails & rail brackets


Installation instruction
06
M-06.584.000-E

Status: 11/06 Page 5 of 16

2.1 Shaft measuring

Prior to guide rail installation the shaft has to be measures exactly in order to be
able to compensate lateron for building inaccuracies and to apply the reference
lines of the general arrangement drawing to the shaft.

Fopllowing reference lines are to be used:


- Centre lines of the guide rails,
- Centre lines of car and counterweight.

2.2 Plumb lines setting

• Fixing plumb lines in the shaft headroom


• Making notes of distance of plumb lines between each other
Securing of plumb lines in the shaft pit resp. „calming down“ in a bucket etc.

Check the equidistance of the plum blines and their verticality.


Plumb lines that are inaccurately set and secured require an additional amount of
work.

2.3 Establishing the usable shaft depth resp. width

Partly, planned shaft dimensions and actual ones can deviate considerably. In any
case, the admissible building tolerances have to be respected.

Shift the rail bracket level, if necessary.

(see following figures 002 & 003)


LM Jade

Guide rails & rail brackets


Installation instruction
06
M-06.584.000-E

Status: 11/06 Page 6 of 16

• Use the list following herebelow


• Enter the plumb line distance and set-
point value for shaft depth and width
• Establish distances A – F for each floor
• Enter the lowest measured value of
columns A – F underneath
• Add the measurements as indicated in
the table
• Enter the actual values for shaft depth
and width and compare with the re-
Plumb line
spective setpoint values.
distance
min. 50mm

Installation support

Begin and end of the rail gauge is


marks in the ground plan with an X
and dimensioned with 50mm each
from the blade end of the car guide
Fig. 002 rail.

In a shaft that shows to be slightly under-


dimensioned upon measuring a lift can
be installed nevertheless if:
- the shaft is planned large enough,
- the walls are parallel and the corners
rectangular.

Whether the walls are parallel and the


corners rectangular can be verified
easily by measuring the diagonales.
If the diagonals are showing differ-
ences higher than the usual ones
(2 – 3 cm) further measurements might
be required.

Fig. 003
LM Jade

Guide rails & rail brackets


Installation instruction
06
M-06.584.000-E

Status: 11/06 Page 7 of 16

2.4 Rail gauge

Plumb lines

Rail gauge

Plumb lines

Abb. 004
LM Jade

Guide rails & rail brackets


Installation instruction
06
M-06.584.000-E

Status: 11/06 Page 8 of 16

2.5 Rail gauge list

Shaft width Shaft depth


Floor A B C D E F

12

11

10
9

7 Distance
between
6 plumb lines

5
4

3
2

Min. A - F + + + _________

Min. (IST +

Setpoint +25/-15 mm* +25/-15 mm*


LM Jade

Guide rails & rail brackets


Installation instruction
06
M-06.584.000-E

Status: 11/06 Page 9 of 16

3. Guide rails
Description for
3.1 Fixing to Halfen channels guide rail fixation
(right hand posi-
tion)

Halfen channel
T-Head bolt
M16

Inserted washer
Inside-∅ 17mm

Lock washer
Hexagon nut M16 FIG. 005

Rough
adjustment
Plumb lines

Distance rail bracket to top of


rail blade
T89  62mm
Compensation T125  82mm
(shaft tolerance)
FIG. 006

Fine adjustment
LM Jade

Guide rails & rail brackets


Installation instruction
06
M-06.584.000-E

Status: 11/06 Page 10 of 16

3.2 Fixing with dowel

The fixation by plugs needs special care.


Please take the individual steps of installation from the next
pictures incl. descriptions

Overview on the parts needed incl. the different plugs

Fischer dowel Type:


Fischer FHB-A dyn
12x100

UPAT dowel Type:


UPAT EXA 8/15

Inserted washer
Inside-∅ 15mm

Accessories for plug Fig. 008

Description for Lock washer


guide rail fixation Accessories for plug
(right hand posi-
tion)
Observe the enclosed description
on the packing of the plugs!
Torques upon anchoring

Fischer FHB-A dyn 12x100  40Nm


(min. wall thickness = 200mm / effective anchoring depth = 100mm)
UPAT EXA 8/15  14Nm
(Min. wall thickness = 100mm / effective anchoring depth = 47mm)
LM Jade

Guide rails & rail brackets


Installation instruction
06
M-06.584.000-E

Status: 11/06 Page 11 of 16

Marking out of the bore holes by means of the rail gauge

distance „B0“ (view Fig. 010)

DBG car frame


(distance between car guide rails)

Flush with blade top of


guide rail
Shaft
wall
L2
L1

Plumb lines

B0

Distance rail
Marking out of bracket to top of
bore holes rail blade
Fig. 009 T89  62mm
T125  82mm

Establishment of the further bore hole

Bore hole for


oblong hole L1 & L2
B0
Fig. 010

B1
B2
• To determine the oblong hole L1 (Fig. 009), the rail gauge with
bore hole B1 (Fig.010) has to be held to the marked bore hole
described “B0” under Fig. 009 .
• To determine the oblong hole L2 (Fig. 009), the rail gauge with
bore hole B1 (Fig.010) has to be held to the marked bore hole
described “B0” under Fig. 009 .

LM Jade

Guide rails & rail brackets


Installation instruction
06
M-06.584.000-E

Status: 11/06 Page 12 of 16

Guide rail alignment and preparation for final assembly

UPAT plug Type:


UPAT EXA 8/15

Aligning
Plumb lines
UPAT plug Type:
UPAT EXA 8/15

Distance rail
bracket to top of
rail blade
T89  62mm
T125  82mm
Fig. 011

! When setting is completed (see next item) alignment is no longer possible !

Final assembly guide rail to Shaft wall

Inserted washer Fischer plug Type:


Internal-∅ 15mm Fischer FHB-A dyn
12x100

Fig. 012

Before boring it is to be observed that the washers are inserted


! Drill only with the help of the washers !
Fig. 013
LM Jade

Guide rails & rail brackets


Installation instruction
06
M-06.584.000-E

Status: 11/06 Page 13 of 16

3.3 Setting of the car guide rails

Tightening torques for the locking


screws

Type L 14  M12  56Nm


Type L 18  M16  141Nm

Fine
adjustment

Tightening torques for the hexagon Fine ad-


screws justment

M12  80Nm

Fig. 014
LM Jade

Guide rails & rail brackets


Installation instruction
06
M-06.584.000-E

Status: 11/06 Page 14 of 16

3.4 Setting of counterweight guide rails

Tightening torques of the locking


screws
Type L 11,5  M10  33Nm

Fig. 015

Fine adjustment of the counterweight guide rail by means of spacers

Fig. 016

Fig. 017
LM Jade

Guide rails & rail brackets


Installation instruction
06
M-06.584.000-E

Status: 11/06 Page 15 of 16

3.5 Guide rail joints

Torques

M10  50Nm
M12  80Nm
M16  200Nm

Fig. 018
LM Jade

Guide rails & rail brackets


Installation instruction
06
M-06.584.000-E

Status: 11/06 Page 16 of 16

3.6 Check of guide rail joints

Check all rail joints for unevennesses, as


otherwise a bad travelling behaviour of the
car is to be expected.
Moreover, the guide shoe lining will be sub-
ject to an increased wear and tear.

Fig. 019

3.7 Fixing of the oiltray

In order to avoid the pollution of the shaft pit


by moving oil from the guide rails, oiltrays
are to be placed under the lower ends of the
guide rails.
These can be sticked to (see fig. 020) resp.
put under the lower end of the guide rail.

Fig. 020
LM Jade

Machine support
Installation instruction
01
M-01.501.231-E

Status: 05/07 Page 1 of 7

Installation instruction
Machine support
LM Jade

Machine support
Installation instruction
01
M-01.501.231-E

Status: 05/07 Page 2 of 7

I. General description

The machine support is designed to carry the drive unit Type


SM200.

The machine support is always fixed between the car guide rails at
the upper guide rail joint.

The machine support is designed to be used also as a support for


the overspeed governor and an abutment for the ropes (see
figure 1).

In this chapter only the installation of the support is described.

Information for drive fixation, as well as rope installation and rope


suspensions and the overspeed governor support please take from
the respective instructions as listed in the table of contents.

Fig. 001
LM Jade

Machine support
Installation instruction
01
M-01.501.231-E

Status: 05/07 Page 3 of 7

Machine support mounting in the shaft headroom

End section of
car guide rail

End section of
car guide rail

Overspeed
governor
support

Rope abutment

Fig. 002

Car guide rail Car guide rail

Tightening torques for screws

M12 (8.8)  80 Nm
M16 (8.8)  200 Nm
LM Jade

Machine support
Installation instruction
01
M-01.501.231-E

Status: 05/07 Page 4 of 7

Equalization of distance between guide rails

Stable device M16

Shim Fig. 003

The spacer shall compensate for differences in the gauge between the car guide rails.
It prevents the guide rails from being deflected off the plumb position during erection of
the machine support. The shims are attached to the package and are available with
0,5mm and 1,5mm thickness.

The stable device on the left-hand and right-hand side of the guide rail are additional pro-
tections against horizontal slipping, they prevent also the machine support from being
twisted toward the guide rail. It is very important that the top rail section is demounted to
enable repair work (e.g. change of traction pulley).
LM Jade

Machine support
Installation instruction
01
M-01.501.231-E

Status: 05/07 Page 5 of 7

Support for overspeed governor „Standard“

Fixation if DBG car frame


1200mm

Fixation if DBG car frame


750mm / 870mm / 1000mm
Support for
overspeed
governor
„Standard“

Fig. 004

The support for the overspeed governor is part of the machine support.
Possible changes in position and installation shall be taken from the general arrangement
drawing, as well as the left-hand or right-hand position.
LM Jade

Machine support
Installation instruction
01
M-01.501.231-E

Status: 05/07 Page 6 of 7

Support for overspeed governor


for elevators with reduced head room
overspeed governor with test groove

Fixation if DBG car frame


1200mm

Fixation if DBG car frame


750mm / 870mm / 1000mm Support for
overspeed
governor

Fig. 005

The support for the overspeed governor is part of the machine support.
Possible changes in position and installation shall be taken from the general arrangement
drawing, as well as the left-hand or right-hand position.
LM Jade

Machine support
Installation instruction
01
M-01.501.231-E

Status: 05/07 Page 7 of 7

Support for overspeed governor „v = 1,6m/s“

Fixation if DBG car frame


1200mm Support for
overspeed
Fixation if DBG car frame governor
750mm / 870mm / 1000mm

Fig. 006

The support for the overspeed governor is part of the machine support.
Possible changes in position and installation shall be taken from the general arrangement
drawing, as well as the left-hand or right-hand position.
LM Jade

Overspeed governor support


Installation instruction
01
M-01.501.212-E

Status: 05/07 Seite 1 von 4

Installation instruction
Overspeed governor support
LM Jade

Overspeed governor support


Installation instruction
01
M-01.501.212-E

Status: 05/07 Seite 2 von 4

I. General description

The variations in mounting position (lefthand/righthand) to


be taken from the enclosed general arrangement drawing
(see pictures 002 & 003).

The position of the overspeed governor is defined by the support


fitted to the machine supporting beam.

Hexagon
screw
M12x35

Fig. 001

Hexagon
screw
M12x35
Fig. 002
LM Jade

Overspeed governor support


Installation instruction
01
M-01.501.212-E

Status: 05/07 Seite 3 von 4

Installation of overspeed governor, lefthand

Support for overspeed


governor „Standard“

Fig. 003

Support for overspeed governor


for elevators with reduced head room
Fig. 004
overspeed governor with test groove
LM Jade

Overspeed governor support


Installation instruction
01
M-01.501.212-E

Status: 05/07 Seite 4 von 4

Installation of overspeed governor, righthand

Support for overspeed


governor „Standard“

Fig. 005

Support for overspeed governor


for elevators with reduced head room
Fig. 006
overspeed governor with test groove
LM Elervators / Components

Tensioning weight (floor mounting)


Installation instruction
04
M-04.554.610-E

Status: 03/06 Page 1 of 4

Installation instruction
Tensioning weight (floor mounting)
LM Elervators / Components

Tensioning weight (floor mounting)


Installation instruction
04
M-04.554.610-E

Status: 03/06 Page 2 of 4

I. General description

The tensioning weight is mounted to the bottom of the pit


by means of expansion anchors.

Take the position of the tensioning weight from the general


arrangement drawing.

The switch should be mounted in such a way that it is easily acces-


sible after the erection of the lift (to facilitate maintenance work).

Fig. 001
LM Elervators / Components

Tensioning weight (floor mounting)


Installation instruction
04
M-04.554.610-E

Status: 03/06 Page 3 of 4

Detail: Mounting of protective


cover

(screws, nuts & washers are


included in the protective cover
package)

Fig. 002

Detail: Mounting of switch

(screws, washers and


trip cam are included in
the switch package)

Fig. 003
LM Elervators / Components

Tensioning weight (floor mounting)


Installation instruction
04
M-04.554.610-E

Status: 03/06 Page 4 of 4

Floor mounting

Fig. 004

hexagon screws
M12x35 with washers
and hexagon nuts

floor-mount angle

hexagon screws
M8x45 with washers +
expansion anchors
(brass)
LM Jade

Counterweight
Installation instruction
04
M-04.140.000-E

Status: 11/06 Page 1 of 8

Installation instruction
Counterweight
LM Jade

Counterweight
Installation instruction
04
M-04.140.000-E

Status: 11/06 Page 2 of 8

I. General description

The version of the counterweight depends on the gauge of guide


rails, and also from the rated load of the lift.

Tightening torque for the screws

M 8 (8.8)  25 Nm
M10 (8.8)  50 Nm
M12 (8.8)  80 Nm
M16 (8.8)  170 Nm
LM Jade

Counterweight
Installation instruction
04
M-04.140.000-E

Status: 11/06 Page 3 of 8

See item:
„Rope pulley installation“

See item:
„Protection against unseating
of ropes“
See item:
„Counterweight – Top element“

See item:
„Protection against
bouncing of counterweight
blocks“

Counterweight filler

Counterweight

(Shown for rail


distance 635 mm)

See item:
„Steel inserts as additional
weights in the lower
beam“
Fig. 001
LM Jade

Counterweight
Installation instruction
04
M-04.140.000-E

Status: 11/06 Page 4 of 8

Steel inserts as additional weights in the lower beam

! It is to be checked before erection (see parts list) whether steel inserts


for the lower beam are attached to the package!

! In individual cases only, when filling height is not sufficient !

Additional steel inserts

Fig. 002

Impact buffer
(Number and size
variable acc. to the
rated load)
Spacers

Guide shoe
with lining
Side-parts fixed:

without safety gear with hexagon screws M12


with safety gear with hexagon screws M16
LM Jade

Counterweight
Installation instruction
04
M-04.140.000-E

Status: 11/06 Page 5 of 8

Counterweight – Top element

Bend-up the
ends slightly, if
necessary
Protective plate

Bend-up the
ends slightly, if
necessary Guide rail oiler
Hexagon
(Screws for fixing
screw
are included in the
M10x20
package)

Axle

Axle guard

Protective
plate
Hexagon
screw
M10x20

Fig. 003
Spacer
Guide shoe
with lining

Screwed joint for guide shoe assembly

ATTENTION:
Only counterweight with DBG 385mm

Fig. 004
LM Jade

Counterweight
Installation instruction
04
M-04.140.000-E

Status: 11/06 Page 6 of 8

Rope pulley installation

Hexagon
screw Return pulley
M10x20 Hexagon No. of grooves
screw (=width of pulley)
Axle
M10x20 may vary
Spacer ring

Fig. 005
Spacer ring

Hexagon
screw
Hexagon M10x20
screw
M10x20
LM Jade

Counterweight
Installation instruction
04
M-04.140.000-E

Status: 11/06 Page 7 of 8

Protection against unseating of ropes

Fig. 006
Protection against
Hexagon
unseating of ropes
screw
M8x25

Protection plate
Bend-up the ends slightly, if
necessary

Protection against unseating of ropes


(only counterweight with DBG 385mm)

Hexagon screw
M12x35
incl. washer

Protection
against unseat-
ing of ropes

Fig. 007
LM Jade

Counterweight
Installation instruction
04
M-04.140.000-E

Status: 11/06 Page 8 of 8

Protection against bouncing of the counterweight filler

Hexagon screw
M12x35

Protection against
bouncing of
counterweight fillers

Fig. 008
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 1 of 19

Installation instruction
Car frame
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 2 of 19

I. General description

Please observe the following details when installing the car frame.

Tightening torques for screws

M 8 (8.8)  25 Nm
M10 (8.8)  50 Nm
M12 (8.8)  80 Nm

Table of contents

1. Overview of cantilevered frame for roping 2:1 ..............…………………. 003


2. Fundamental sequence of assembly ……………………………………. 004
3. Assembly of lower cross connection …………………………………………….. 005
4. Assembly of cross connection on top …………………...………………. 006
5. Screwed joint & Auxilary guide of cross connection on top ………………. 007
6. Guide shoe assembly, bottom ....………………………………………….. 008
7. Return pulley assembly (roping 2:1) ………...…………………………. 009
8. Installation of overload measuring device …………………………………… 010
9. Crosstie assembly ………………………………………………………. 011
10. Tripping linkage ………….……………………………………………………. 012
11. Governor application point ….…………………………………………………… 013
12. Governor application point (v=1,6m/s) ….………………………………… 014
13. Fixation of limit switch ……………………………………………………… 015
14. Shaft information by magnets .……………………………………………. 016
15. car holder ………..…………………………………………………….... 017
16. Car floor fixation …..………………………………..………………………….. 018
17. added car floor fixation ……………………………...………………………. 019
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 3 of 19

Magnets for the


shaft information
system
Car holder

Auxiliary guiding
appliance

Limit switch

Cantilevered car
frame for roping
2:1

Cross
connection

Crosstie
Return
pulley

Fig. 001

Extension of the
cantilever arm
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 4 of 19

Fundamental sequence of assembly

Put the uprights in place and


1 secure toward the guide rails

5
2 Bring in the cross connection

Put the upper connection in


place and fix it according to
3 the total car height
Guide rails
as per the table.
1
Mount the bottom guide
4 shoes

1
5 Mount the top guide shoes

Install the cross connection


6 with return pulley resp. with
rope suspensions

4
Fig. 002

2
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 5 of 19

Assembly of lower cross connection

Complete view

Fig. 003

View inside left-hand

View from be-


low, left-hand

Fig. 004

Bore holes resp. threads are needed


(see the following chapter) for
mounting of the guide shoes

Cross connection in the marked area


not yet to be screwed together!

Fig. 005
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 6 of 19

Cross connection on top

Fixing the cross connection on top

Cabin flloor
1 + cabon floor covering
+ cabin height (see generald drawing of elevator)
2 + cabin roof
3

9
Fig. 006

Please consider cabin height when mounting cross


connection on top
(see general drawing of elevator)
example:
Fixation holes assign to figure 007 below cross conection
on top = 2440mm with
Cabin height with suspended cabin height 2300mm
ceiling / rough cabin height holes

2000mm  1&4
2050mm  2&5
2100mm 2200mm  3&6
2150mm  4&7
2200mm 2300mm  5&8
2250mm  6&9

Fig. 007
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 7 of 19

Screwed joint & Auxilary guide of cross connection on top

Auxiliary guide
(hole spacing 150mm)

1x per backside of each


upright

Wall Side

Cabin side

Screwed joint
(hole spacing 150mm)

Cabin side

Fig. 008

Wall Side

1x per frontside of
each upright
Fig. 009
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 8 of 19

Guide shoe assembly, bottom

Fig. 010

Screwed together with


cross connection

Fixation with hexa-


gon screws, from the Guide shoe with
outside lining

Spacer,
thicknesses
0.5mm and 1.5mm

Guide shoe holder to be shifted


first with the snapper into the up-
right

Fig. 011
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 9 of 19

Return pulley assembly (roping 2:1)

Rope pulley support,


rear view

Fig. 012

Fig. 013
Spacer ring

Pulley of synthetic
material

Protection against unseating


of ropes

Verbus-Tensilock
M8x16

Screwed joint
(hole spacing 100mm)

Rope pulley support,


front view
(cross connection Fig. 014
transparent) Hexagon
screw M10x20

Axle guard
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 10 of 19

Installation of
overload measuring device

Fig. 015

Overload measuring device


„Strain Link 942“
(Cross connection transparent)

Overload measuring
device
mounted underneath
the rope suspension
support resp. the rope
pulley support.

Screws, nuts and wash-


ers are included in the
package of the measur-
ing device.

Fixation 4x by hexagon
screws M6x30
+ 8x hexagon nut
(counternut see
Fig. 018)

Optionally mounted at
the lefthand or righthand
side of the support

Fig. 016
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 11 of 19

Crosstie assembly

Fig. 017

Screwed joint
(hole spacing 100mm)

Mounted from the inside


(cross connection transparent)

Fig. 018
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 12 of 19

Tripping linkage

Fig. 019

Safety gear
Safety gear shifter
SL-protection (optic could be chan- Tripping lever
ged)

Stop for tripping lever


at the sheet metal

Hexagon screw
M8x16

Fig. 020
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 13 of 19

Governor application point

Governor rope

Rope clamp Governor application,


complete
Rope socket
complete incl.
Verbus-
wedge, pin and
Tensilock
cotter pin
M8 x16
Hexagon nut M10
with lock washer
Distance
plate
Hexagon screw
M10 x 30 with lock
washer Switch

Rope socket
connection

Tension
spring

Fig. 021

Strap for tensioning


of the spring Hexagon screw
M8 x 16

Hexagon screw
M8 x 40

Fig. 022
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 14 of 19

Governor application point (v=1,6m/s)

Governor rope Hexagon screw


M8 x 16
Governor
Rope clamp application,
complete
Rope socket
complete incl. Verbus-
wedge, pin and Tensilock
cotter pin M8 x16

Hexagon nut M10


with lock washer Distance
plate
Sechskant-
schraube
M10 x 30 inkl. Switch
Sperrkantscheibe

Rope socket
connection

Tension
spring

Fig. 023

Lasche zum Spannen


der Feder

Hexagon screw
M8 x 40

Fig. 024
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 15 of 19

Fixation of limit switch

Shift the limit


switch fixation
up to the end Mounting and demounting
stop of the limit switch fixation
only with the empty car set
Limit switch
onto the buffer
fixation

Before mounting the


switch to the limit switch
fixation turn the roller of
the switch by 90°(see pic-
ture) toward the shaft wall.

The installation position


(lefthand / righthand
upright) to be taken from
the general arrangement
Limit switch drawing.
(roller switch)

Fig. 025
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 16 of 19

Shaft information by magnets

Sensor 1 is standard execution


Sensor 2
Sensor 2 exists only for
- Safety circuit
- Preopening doors or rele-
velling
Sensor 1
- Relevelling B-door side

Connection

Connection

Screws are packed-up with the


guide rail oiler

Mounting angle for


the shaft information
system by magnets Guide rail oiler

Fig. 026

The sensor for the shaft information by magnets is mounted on the angle.
Please observe the enclosed operating instruction for commissioning.

The angle is mounted at the guide shoe, above the screws of the guide rail oiler.

Optionally, the shaft information system by magnets


can be mounted also on the opposite side of the cantilevered frame.
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 17 of 19

car holder (roof)

Car roof holder

Fig. 027 Fixation material for cabin


roof is included in cabin ac-
cessories
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 18 of 19

Car floor fixation

Fig. 028

The car floor is fixed to the cantilevered frame by clamping plates (+ hexagon screws M10x30).
The quantity can be different, depending on the rated load.

Car floor section

Hexagon screw
M10x30 Clamping plate

Fig. 029
LM Jade

Car frame
Installation instruction
04
M-04.130.100-E

Status: 11/06 Page 19 of 19

Added Car floor fixation

car floor fixation plate

Fig. 031

Fig. 030

Hole Ø11mm has to be drilled on site

ca. 8,5mm

hole Ø11mm

Fig. 032
LM Elervators / Components

bufferupstand
Installation instruction
06
M-06.455.410-E

Status: 10/06 Page 1 of 4

Installation instruction
bufferupstand
LM Elervators / Components

bufferupstand
Installation instruction
06
M-06.455.410-E

Status: 10/06 Page 2 of 4

maximum adjustment
1006mm

minimum adjustment
556mm

reduced version
(by builder)
( 201mm)

The bufferupstand is intended to supporting


cellasto lift buffer (max. Ø165mm) or
hydraulic lift buffer (series „SEB“)

The bufferupstand is adjustable in a screen


of 15mm.

For a height smaller than 556mm, the


bufferupstand must be reduced (cut off) by
builder.
LM Elervators / Components

bufferupstand
Installation instruction
06
M-06.455.410-E

Status: 10/06 Page 3 of 4

reduction bufferupstand – upper part

All cants und edges must be


deburr after reducing

Otherwise risk of injury !


LM Elervators / Components

bufferupstand
Installation instruction
06
M-06.455.410-E

Status: 10/06 Page 4 of 4

reduction bufferupstand – lower part

circa
30 mm

required
height

All cants und edges must be


deburr after reducing

Otherwise risk of injury !


LM Jade

Installation of drive unit


Installation instruction
01
M-01.501.230-E

Status: 11/06 Page 1 of 10

Installation instruction
Installation of drive unit
LM Jade

Installation of drive unit


Installation instruction
01
M-01.501.230-E

Status: 11/06 Page 2 of 10

I. General description

The drive unit is mounted to the machine support on vibration isola-


tion elements.

For machine support assembly please observe the respective chap-


ter.

In this chapter, besides of the “machine mounting on the support“ or


“device to recognize the sense of rotation “, also an option allowing
an easier positioning of the drive in the shaft headroom is described.

Distinction:

Vertical positioning
is performed by a drive mounting platform that is fitted to the cantile-
vered car frame (condition: this frame is already installed).
Horizontal positioning
is performed by load hooks set within the drive area with a “sling
rope“ to take the drive unit onto the supporting beam

Fig. 001
LM Jade

Installation of drive unit


Installation instruction
01
M-01.501.230-E

Status: 11/06 Page 3 of 10

Machine mounting on the machine support

Drive installed on
premounted
base plate

Hexagon screw
M12x80
Hexagon screw
M12x80

Machine support Fig. 002

Weight of drive unit incl. support plate : ______ kg


LM Jade

Installation of drive unit


Installation instruction
01
M-01.501.230-E

Status: 11/06 Page 4 of 10

Vibration-decoupled support and screwed connection of drive unit to frame

Condition as delivered:

• Drive unit pre-


mounted on the
supporting plate

• Cellasto plates,
glued-on

• Hexagon socket
head screw incl.
washers

Fig. 003

Hexagon screw
M12x80

Vibration-
isolated screwed
connection by
means of Cel-
lasto buffers
Fig. 004

Washer
outside-∅
58mm

Locknut with
Pretensioning to plastic ring
_______mm
of buffer height Fig.005
LM Jade

Installation of drive unit


Installation instruction
01
M-01.501.230-E

Status: 11/06 Page 5 of 10

Device to identify the sense of rotation

Magnets to be
fixed to the trac-
tion pulley

Sensor to identify the


sense of rotation
Protection against unseating incl. hexagon nuts M4
of ropes premounted on the & washers
drive unit

Fig. 006

Locking screw Fixing angle for


Verbus-Tensilock the sensor
M8x16
LM Jade

Installation of drive unit


Installation instruction
01
M-01.501.230-E

Status: 11/06 Page 6 of 10

Preparation of the mounting support for the drive unit

Hexagon screw M12x35


incl. washer

Mounting support
Fig. 007

For car frame


DBG 1000mm

Hexagon screw M12x35


incl. washer
+ hexagon nut M12
incl. washer

Fig. 009

For car frame


For car frame DBG 750mm
DBG 1200mm
Fig. 008
LM Jade

Installation of drive unit


Installation instruction
01
M-01.501.230-E

Status: 11/06 Page 7 of 10

Assembly mouting support to cantilevered car frame


(Vertical positioning)

Fig. 010

The mounting support for the drive unit is


hooked to the connecting member on top of the
cantilevered car frame and fixed by means of
the screws (see Fig. 002)

The connecting member of the mounting


support fits closely to the inner side of the
uprights.

In the same way the mounting support


supported by the connecting member of the Fig. 011
mounting support against the frame from the car side.
LM Jade

Installation of drive unit


Installation instruction
01
M-01.501.230-E

Status: 11/06 Page 8 of 10

Transport of drive by mounting support

The drive is put on as a com-


plete unit with base plate
(see delivery condition Fig.
012 ). 2
Pull the car frame with a
chain hoist upward until the
mounting platform is level
with the machine support

Fig. 012

To avoid slipping upon trans-


port on the mounting plat-
form, the base plate of the
drive has to be screwed 1x
with the mounting platform .

(Hexagon screw M12x80


& hexagon nut M12)

Fig. 013
LM Jade

Installation of drive unit


Installation instruction
01
M-01.501.230-E

Status: 11/06 Page 9 of 10

Position of load hooks in the shaft ceiling

Load hook (2000kg)


Above car centre
Load hook (1000kg)

Load hook (1000kg)

approx. 550mm-
650mm approx. 50-
100mm

Fig. 014

Comparison position of load hook – see general arrangement drawing !


LM Jade

Installation of drive unit


Installation instruction
01
M-01.501.230-E

Status: 11/06 Page 10 of 10

Fixing of the “sling rope“


4
Chain hoist to be
mounted here

1
1

Hang on the
sling rope to
the load hook

Fig. 015

Chain hoist for 4


the car frame to
be mounted
here 2
2

Fig. 016
1. Hang in sling rope and chain hoist
2. Remove the locking screw Correct placing of the sling rope at the drive
3. Raise slightly
4. Shift the drive onto the drive support

Fig. 017
LM Jade

Brake resistor fitting


Installation instruction
08
M-08.500.030-E

Status: 11/05 Page 1 of 3

Installation instruction
Brake resistor fitting
LM Jade

Brake resistor fitting


Installation instruction
08
M-08.500.030-E

Status: 11/05 Page 2 of 3

I. General description

The brake resistor is to be mounted near the control cabi-


net to one of the counterweight rails, according to the
length of the cable (6m).

The brake resistor is to be screwed on an aluminium plate which is


to befixed to the rail by means of clamping screws.

The terminal box is to be positioned as shown in Fig. 001 below.


LM Jade

Brake resistor fitting


Installation instruction
08
M-08.500.030-E

Status: 11/05 Page 3 of 3

Fixation to the guide rail

Counterweight
guide rail

Fig. 002
Clamping
screw Type
11,5 A

Fixation of brake resistor

Hexagon nut
M4 with
washer

Brake resistor

Terminal
box

Aluminium
plate

Fig. 003
Fig. 001
LM Jade

Ropes & rope suspensions


Installation instruction
05
M-05.500.001-E

Status: 03/07 Page 1 of 11

Installation instruction
Ropes & rope suspensions
LM Jade

Ropes & rope suspensions


Installation instruction
05
M-05.500.001-E

Status: 03/07 Page 2 of 11

Table of contents

1. Preparation for installation ………………………………………………………… 3


1.1. Scope of supplied elements .……………………………………………………………… 3
1.2. Description ……………………………………………………………… 3
1.3. Storage ……………………………………………………………… 3
1.4. Sequence of installation ……………………………………………………………… 3
2. Installation of ropes ………………………………………………………… 4
2.1. Fitting of rope suspensions ……………………………………………………... 4
2.2. Fitting the wedge socket ……………………………………………………… 5
2.2.1. Fitting the wedge socket ……………………………………………………… 5
2.2.2. Rope suspension with pre-fabricated pressed thimble (on counterweight) ...... 6
2.2.3. Rope suspensions (on car side) ………..……..…………………………………….. 7
2.3. Check of the rope engagement ...…………………………………………………… 8
2.4. Securing the ropes against twisting ……………………………………………. 8
2.4.1. Rope suspensions with rope sockets acc. to DIN 15315 ……………….. 8
2.4.2. Rope suspensions with wedge sockets acc. to DIN 43148 ……………….. 8
2.4.3. Rope suspensions with wooden Clamp (counterweight side) ……………….. 9
3. Tensioning of ropes ……………………………………………………...… 10
3.1. Rope tension check and adjustment …………………………………… ……… 10
3.2. Table of measurements ………………………………………………………………. 11
LM Jade

Ropes & rope suspensions


Installation instruction
05
M-05.500.001-E

Status: 03/07 Page 3 of 11

1. Preparation for installation

1.1. Scope of supplied elements


The supply consists of the following parts:
• Steel ropes in required number and length (plus reserve length) in coils or on a reel, with
pressed thimble and eyebolt at one side
• Wedge sockets together with eye bolts and buffer elements (plastic insert)
• Rope clips,
• Fastener kit
• Various washers.

1.2. Description
The ropes are fitted with wedge sockets, rope clips and spring-buffered eyebolts. The reeved
ropes are to be secured against twisting by putting a piece of the governor rope through the
eyebolts. The rope ends are protected against untwisting by means of pressed sleeves or similar
means.

1.3. Storage
The ropes are supplied pre-lubricated, however are to be protected against corrosion if a
longer storage time is expected. For that, commercial rope preserving agents are
available (from LM also). Storage should be on wooden board in dry and slightly heated
rooms.
Take care that under no circumstances the ropes will be getting in contact with dust,
particularly cement dust.

1.4. Sequence of installation


• align driving unit and rope pulleys
• unreel and install the ropes
• check the ropes for damages
• hang in the rope suspension
• fasten the rope suspension to the dead end point
• check the rope engagement
• secure the ropes against twisting
• mount the rope skip-off protection

Before starting normal lift operation:


• check the rope tension
LM Jade

Ropes & rope suspensions


Installation instruction
05
M-05.500.001-E

Status: 03/07 Page 4 of 11

2. Installation of ropes

2.1. Rope unreeling and reeving

Proceed with utmost care upon unreeling and reeving of the ropes.
Basic rules:
• ear protective gloves,
• unreel the ropes always in reeling direction (see picture),

• in case of sharp-edged parts (concrete or steel edges) use auxiliary rollers or rounded
wooden beams for deflection,
• do not slip the ropes over a dusty or sandy ground.
• put on the ropes
upon reeving check the ropes for corrosion, damages and dirt

Do not install defective ropes.


The rope shall be reeved without twisting it.
LM Jade

Ropes & rope suspensions


Installation instruction
05
M-05.500.001-E

Status: 03/07 Page 5 of 11

2.2. Fitting of rope suspensions

Highest safety requirements are applied on the ropes, above all on the rope end fixations
of a lift.
Therefore, the installation and the following fixation to the dead end beams is to be
carried out in accordance with the current safety rules.

2.2.1. Fitting the wedge socket


• insert the wedge sockets as shown below

Check whether the size of the wedge socket and the rope diameter matches.
The rope shall be cramped firmly and without any clearance between wedge and wedge
socket.

wedge sockets:
rope wedge for rope
Ø 6-7mm with 3 indicating

Fig.001
application of rope sockets acc. to DIN
15315 follow Fig. 001 1.1
application of wedge sockets
acc. to DIN 43148 follow Fig. 001.1
3

Always put the U-clamp of the wire rope clip over the
unstressed rope end.

• fix the loose rope end with adhesive tape Fig.001.1


LM Jade

Ropes & rope suspensions


Installation instruction
05
M-05.500.001-E

Status: 03/07 Page 6 of 11

Pos. Units Designation Type


Standard
1 1 rope socket, complete DIN 15315
1.1 1 wedge socket, complete DIN 43148
2 1 Rope wedge --
3 1 Wire rope clip DIN 1142

Ensure before starting installation whether all ropes are secured against slipping.

• Counter the hexagon nuts right above the cotter pin

The remaining thread length can be used later for the compensation of small differences in rope
tension.

• Tighten the ropes until all pressure springs of the counterweight suspension are compressed to
about the same height.

Rope-ø Wire rope clip


(mm) DIN 1142
6-8 S8

2.2.2. Rope suspension with pre-fabricated pressed thimble (on counterweight side)

Rubber buffers to be sticked


together with their “noses“

Counter nut

Spring tray

Rubber buffer

Fig.002

Fig.003

Ropes are supplied with prefab-


ricated pressed thimble as per
DIN 3090 incl. cylindric pressed
clamp DIN 3093 and eyebolt
LM Jade

Ropes & rope suspensions


Installation instruction
05
M-05.500.001-E

Status: 03/07 Page 7 of 11

2.2.3. Rope suspensions (on car side)

Before start of installation, ensure whether all ropes are secured against slipping.

Put the cotter pin


again after installation!

Fig. 004

2
Fig. 005

Mind the correct sequence of


ropes upon installation.
1

Pos. Units Designation Type


Standard
1 1 Rope socket, complete DIN 15315
1.1 1 Wedge socket, complete DIN 43148
2 1 Eyelet bolt, complete DIN 444
3 1 Pressure spring, complete --
4 1 Dead end hitch --
Counter the hexagon nuts right above the cotter pin

The remaining thread length can be used later for the


compensation of small differences in rope tension.

Rope-ø Rope clip Eyelet bolt


(mm) DIN 1142 DIN 444
6 - 6,5 S 6,5 M 12x300
Fig. 006

1.1
Wedge sockets acc. to DIN 43148 against rope sockets acc. to
DIN 15315 must be turn around 90° to wall with there conical side
(follow Fig. 006).
LM Jade

Ropes & rope suspensions


Installation instruction
05
M-05.500.001-E

Status: 03/07 Page 8 of 11

2.3. Check of the rope engagement

Check whether the ropes are engaging centrical in the grooves of traction sheave, diverter pulley,
etc.

In case of twisted ropes or of rope pulleys with axles not absolutely


parallel a diagonal pull can occur. If the diagonal pull is too much it will re-
sult in an extreme wear (see picture) of the grooves and ropes.

Fig. Rope engaging with a deviation

2.4. Securing the ropes against twisting

2.4.1. Rope suspensions with rope sockets


acc. to DIN 15315

Fig. 007

rope Ø 2,5mm
Pressure clamp
Fig. 008
2.4.2. Rope suspensions with rope sockets
acc. To DIN 43148

rope Ø 2,5mm
Fig. 009
Pressure clamp Fig. 010
LM Jade

Ropes & rope suspensions


Installation instruction
05
M-05.500.001-E

Status: 03/07 Page 9 of 11

2.4.3. Rope suspensions with wooden Clamp


(counterweight side)

Abb. 011
LM Jade

Ropes & rope suspensions


Installation instruction
05
M-05.500.001-E

Status: 03/07 Page 10 of 11

3. Tensioning of ropes

3.1. Rope tension check and adjustment

Check all ropes for symmetrical tension shortly after starting the initial lift
operation, at latest after 6 weeks.
For high-rise lifts a rope forces check by pressing or pulling the ropes will
not suffice. In this case the application of a rope tension checking device is
recommended.

Distance 1 m • before the check is going to be started run the lift several times up and
down
• move car and counterweight to the same level.

With the rope tension checking device a tension in all ropes as regular as
possible should be achieved.
The actual rope tension however is not measurable by this means; only a
comparison among the individual ropes is possible.

• Number the ropes consecutively, starting from the gear side


• Check all ropes, starting from the car side, and write the result into the
list below.

Hook-in the checking device with a distance of at least 1 m from the rope
suspensions resp. the rope pulleys.

Take care that during the checking procedure no additional load is applied
on the car or the counterweight.

• calculate the mean value and readjust the rope tension accordingly
• run the lift several times upward and downward
repeat the measurements until about identical values are achieved

Distance 1 m
Pos. Units Designation Type
Standard
1 1 Rope tension checking device --
2 1 Adjusting screw --
3 1 Spring scale --
3.2. Table of measurements
Corrections
Rope Installed condition
st nd rd th th
no. 1 measurement 2 measurement 3 measurement 4 measurement 5 measurement

Status: 03/07

Ropes & rope suspensions

LM Jade
Sum

Installation instruction
Number of
ropes
Mean value

M-05.500.001-E
Page 11 of 11
= Car = Counterweight Mean value = Sum / number of ropes

05
LM Jade Installation instruction

Counterweight protection & rope length compensation


06
M-06.231.000-E

Status: 09/07 Page 1 of 4

Installation instruction
Counterweight protection & rope length
compensation
LM Jade Installation instruction

Counterweight protection & rope length compensation


06
M-06.231.000-E

Status: 09/07 Page 2 of 4

I. General description

The counterweight protection is a component that is to be adapted


depending from the order.
Please observe accordingly the following details when installing the
counterweight protection.

Counterweight protection in
mounted condition Counterweight protecti-
on in delivered condition

Fig. 002
Fig. 001

Presentation of a
counterweight rail gauge
of 635mm
LM Jade Installation instruction

Counterweight protection & rope length compensation


06
M-06.231.000-E

Status: 09/07 Page 3 of 4

Fixation

Fig. 003

After mounting bend the


lugs above and below the
counterweight protection
toward the inside
(Direction of guide rails)

Counterweight protection is fixed


to the guide rails by means of
clamping bolts.

Fig. 004
LM Jade Installation instruction

Counterweight protection & rope length compensation


06
M-06.231.000-E

Status: 09/07 Page 4 of 4

Rope length compensation

Rope length
compensation

Fig. 005

Fig. 006

100mm
LM Jade

Suspension for travelling cables


Installation instruction
08
M-08.470.002-E

Status: 11/05 Page 1 of 4

Installation instruction
Suspension for travelling cables
LM Jade

Suspension for travelling cables


Installation instruction
08
M-08.470.002-E

Status: 11/05 Page 2 of 4

I. General description

The suspension for travelling cables is, by means of a mounting


bracket, on one end fixed to the car bottom, on the other end to the
shaft wall.

Please take further instruction from the following details.

Screws, nuts and washers are


enclosed to the mounting bracket

Mounting
bracket

Fig. 001

Fig. 002

Flat-cable
suspension
LM Jade

Suspension for travelling cables


Installation instruction
08
M-08.470.002-E

Status: 11/05 Page 3 of 4

Mounting of travelling cable suspension to car bottom

The position of the travelling cable


in relation to the mounting bracket
approx. 50mm
at the car bottom to be taken from
the general arrangement drawing!

∅11mm
∅11mm

Fig. 003

Fig. 004

Fig. 005
LM Jade

Suspension for travelling cables


Installation instruction
08
M-08.470.002-E

Status: 11/05 Page 4 of 4

Mounting of travelling cable suspension to the wall

Drilling on site
Travelling cable
suspension
Dowel

Screws

Fig. 006

Fig. 007

The travelling cable suspension is mounted to the shaft wall by means of dowels.

Screws and dowels are included in the packages of the travelling cable suspension.
LM Jade

Limit switch and accessories


Installation instruction
08
M-08.438.210-E

Status: 11/05 Page 1 of 5

Installation instruction
Limit switches and accessories
LM Jade

Limit switch and accessories


Installation instruction
08
M-08.438.210-E

Status: 11/05 Page 2 of 5

I. General description

The limit switch is mounted to the cantilevered car frame; for the
assembly of this frame please consult the respective assembly
drawing.

The cam operating the limit switch is fixed to the car guide rail.
The position depends on the limit switch holder at the cantilevered
car frame

Limit switch and accessories (position in the lift shaft)

Governor rope Limit switch Limit switch


operating cam
Governor rope

Holder

Clamping screw Clamping screw


Magnet
Fig. 001

Shaft wall
LM Jade

Limit switch and accessories


Installation instruction
08
M-08.438.210-E

Status: 11/05 Page 3 of 5

Mounting of limit switch to cantilevered frame

Holder

Limit switch
operating cam
Arrangement at
top landing

Holder

Limit switch
Fig. 002
LM Jade

Limit switch and accessories


Installation instruction
08
M-08.438.210-E

Status: 11/05 Page 4 of 5

Fixation of limit switch operating cam to guide rail

Clamping screw

Holder

Hexagon screw
Clamping screw M8x25 incl.
hexagon nut &
washers

Holder Limit switch


operating cam

Hexagon screw
M8x25 incl.
hexagon nut &
washers

Fig. 003
LM Jade

Limit switch and accessories


Installation instruction
08
M-08.438.210-E

Status: 11/05 Page 5 of 5

Endschalterkurvenbefestigung bei reduziertem Schachtkopf

Fig. 004

Bei einem reduzierten Schachtkopf muss im Bedarfsfall die Endschalterkurve vor


Ort angepasst werden. Welche dann nach Ausrichtung neu verbohrt und dann mit
der an den vorhanden Langlöchern der Reglerkonsole verschraubt wird.
LM Jade

Filler element
Installation instruction
06
M-06.309.022-E

Status: 04/06 Page 1 of 3

Installation instruction
Filler element
LM Jade

Filler element
Installation instruction
06
M-06.309.022-E

Status: 04/06 Page 2 of 3

I. General description

The filler element shall protect the area beneath the return pulley of
the car frame toward the pit bottom, in case of shaft pits with a re-
duced pit depth.

This element (if needed) is to be mounted under the return pulley of


the car frame, directly to the pit bottom.

Scope of material of the filler element

Hexagon screws M8x45 with


washers and (brass) expansion
anchors are included in the
package
Fig. 001
LM Jade

Filler element
Installation instruction
06
M-06.309.022-E

Status: 04/06 Page 3 of 3

Representation of installation of filler element

Fig. 002

min. 300 mm
to <500mm
from bottom side
of return pulley
with filler
element

>500mm
without filler Fig. 003
element
LM Jade

Foldable ceiling
Installation instruction
03
for reduced headroom M-03.420.100-E

Status: 03/07 Page 1 of 9

Installation instruction
Foldable ceiling
for reduced headroom
LM Jade

Foldable ceiling
Installation instruction
03
for reduced headroom M-03.420.100-E

Status: 03/07 Page 2 of 9

Foldable ceiling with one segment

Fig. 001

View for single entrance with cabin-


dimension 1100mm x 1400mm

Fig. 002
LM Jade

Foldable ceiling
Installation instruction
03
for reduced headroom M-03.420.100-E

Status: 03/07 Page 3 of 9

Foldable ceiling with two segments

Fig. 003

View for single entrance with cabin


dimension 1100mm x 2100mm

Fig. 004
LM Jade

Foldable ceiling
Installation instruction
03
for reduced headroom M-03.420.100-E

Status: 03/07 Page 4 of 9

Befestigung der seitlichen Verkleidungsbleche


Support brackets for light screen at transom

Backside covering

Side covering

Side
covering

Fig. 005

Support brackets

Covering plate
respectively
support brackets
Hexagon nut incl.
washer
Clamping plate

Fig. 006

C-Profile
Fig. 007 Hexagon screw
LM Jade

Foldable ceiling
Installation instruction
03
for reduced headroom M-03.420.100-E

Status: 03/07 Page 5 of 9

contact and contactbridge at closing edge

Position of contact switch and


contact bridge always at
closing edge of the hatch.

(compare fig. 008 – switch is


close to the locking
mechanism located)

support for
contact switch

Locking mechanism Fig. 008

Cabin roof

Contact switch

Fixation material for switch is in-


cluded (in cabin package or screw
set for cabin roof)

Contact bridge

foldable
ceiling

Fig. 009
LM Jade

Foldable ceiling
Installation instruction
03
for reduced headroom M-03.420.100-E

Status: 03/07 Page 6 of 9

Fixation of car top box & control unit of load weighing device

Fig. 010

The car top box and the control unit of the load weighing device are fixed
with self-cutting tapping screws at the stiffening profile of the foldable
ceiling.

Dimension of car top box: H/W/TD- 300mm/500mm/125mm


Drilling template for car top box: H/W 235mm x 430mm
LM Jade

Foldable ceiling
Installation instruction
03
for reduced headroom M-03.420.100-E

Status: 03/07 Page 7 of 9

Fitting of the light screen

approx. 35mm

e.g. monitored area


for cabin width 1100mm = 886mm

drive unit
side

Fig. 011

Entrance
LM Jade

Foldable ceiling
Installation instruction
03
for reduced headroom M-03.420.100-E

Status: 03/07 Page 8 of 9

Fixation of light screen controller & connection of light screen

140mm

The light screen controller is


fixated with self-cutting tapping
screws at one of the side cover-
ing plates. (noncommittal sug-
gestion)

Please take care that the with


RX and TX marked light screens
Fig. 012
are right connected to the RX
and TX inputs of the light screen
controller box.

See fig. 013… fig. 015

Marked inputs at controller unit Light screen marked with TX

Fig. 014

Fig. 013
Light screen marked with RX

Fig. 015
LM Jade

Foldable ceiling
Installation instruction
03
for reduced headroom M-03.420.100-E

Status: 03/07 Page 9 of 9

Attaching of safety label

The safety label has to be attached at the


cabin roof.

It must be readable from the main entrance


(doorside) !

Fig. 016

Fig. 017
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 1 of 20

Installation instruction
Cable plan
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 2 of 20

Table of content

1. Terminals controller cabinet……………………………………. 09.815.003


2. Overview …………………………………………. 09.815.004
3. Motor terminal (X1 & X3) ………………………… 09.815.005
4. Direction monitoring ..………………………. 09.815.006
5. Terminals overspeed governor … … … … …….…… 09.815.007
6. Pit control unit … … ..………………………… 09.815.008
7. Tension weight … … … ………………………………… 09.815.009
8. UPS (for emergency operation) ………………………… 09.815.010
9. Shaft light … … … … … …………………………………… 09.815.011
10. System earth doors & door lock contact shaft doors ... 09.815.012
11. Landing operation panels … … … … … … ………….. 09.815.013
12. car top control unit … … … … … … … … … … …… 09.815.014
13. Limit switch ………………………………… 09.815.015
14. Safety gear switch ……………………………………. 09.815.016
15. Shaft information system ………………………………. 09.815.017
16. Car operation panel … … ………………………… 09.815.018
17. Door operator & light screen … … … … … ……….. 09.815.019
18. Load weighing control unit … … … … .………………… 09.815.020
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 3 of 20

Terminals controller cabinet


4 D- sLink

X.DM
3 D+ sLink
2 GND

Door safety
3 PE 1 +12V

X25
2 DoorB

circuit
1 DoorA 4 TxA- Shaftbus

Shaft bus
3 TxA+ Shaftbus

X56
Pit control unit safetycir-
6 13 Emergency stop pit 2 TxV- Shaftbus
5 12 Emergency stop pit 1 TxV+ Shaftbus
4 4 Slack rope switch
X10

cuit
3 3 Slack rope switch 5 Shield shield
2 2 Return wire door B 4 TxA- CAN_Lo

X55
1 1 Return wire door A 3 TxA+ CAN_Hi
2 TxV- sLink2
Alarm, light,

8 PE power socket 1 TxV+ sLink1


7 N power socket
power supply

6 L1 power socket 12 PE
5 Shaft light push button 11 D Extern xomsys D
X11

Pit control unit

8 PE PE 4 Alarm button no 10 CoDC Extern comsys C


7 40 COM Brake 1&2 3 Alarm button no 9 B Extern comsys B
6 42 Brake2 180VDC 2 Alarm button nc 8 A Extern comsys A
Brake

5 41 Brake1 180VDC 1 Alarm button nc 7 IC2 Intercom b


X59

4 X53 6 IC1 Intercom a


3 Brake opened 7 PE 5 NR Alarmsignal
Overspeed governor

2 Brake closed 6 S27.2 Safety circuit 4 AL+ Alarmsignal +12V


1 200 COM 5 S27.1 Safety circuit 3 1N N door operator
X12

4 FR A2 Coil reset A2 2 200 GND


5 PE 3 FR A1 Coil reset A1 1 100 +24VDC
(inside the shaft)
Brake resistor

4 T2 Temp monitoring 2 FA A2 Coil remote tripping A2


X4

3 T1 Temp monitoring 1 FA A1 Coil remote tripping A1 12 179 Doorzone 2


2 BR- Brake resistor 11 178 Doorzone 1
Shaftlight

1 BR+ Brake resistor 3 PE 10 144D Inspection down


X.SL

2 2N 9 144U Inspection up
Motor PTC

3 PE 1 L33 8 144 Inspection off


X3

2 PTC2 7 247B door open signal B


X52

1 PTC1 8 GND GND for alarm bell 6 246B door closed signal B
7 NR+ Alarmbell +12VDC 5 247A door open signal A
Emergency call

4 PE 6 K.NR voltage free contact 4 246A door closed signal A


terminal

system
X.SAX
Motor-

3 W 5 K.NR voltage free contact 3 CoDC Com door operator


X2

2 V 4 D 2 200 GND
1 U 3 C 1 100 +24VDC
2 B
Important! Same N-wire for in- and output 1 A 12 PE
5 PE 11 2N N power socket
UPS-supply
(optional)

Temperature

4 N 4 150 Temp. monitoring 10 2L36 230V power socket


monitoring
X400

3 5L1 3 200 COM 9 2L38 Shaft light switch


X58

2 N 2 150T Internal (mot. monitoring) 8 1L40 230V door operator


1 4L1 1 200 COM 7 SL
X51

6 SL
PE 5 200 COM 5 SL
Main supply

Firecontrol

N 4 146B Firestop 2 4 SL
X57
X1

L3 3 146A Firestop 2 3 SL
L2 2 200 COM 2 SL
L1 1 146 Fireman 1 SL
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 4 of 20

Fig. 001
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 5 of 20

Motor (Terminal X2 & X3)

Brake wiring to
controller cabinet
Terminal X59

Fig. 002

Motorcable to
Encodercable to controller cabinet
Frequency inverter PTC cable to Terminal X2
- Plug XE controller cabinet
Terminal X3
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 6 of 20

Direction monitoring

Fig. 003

Cable direction
monitoring to
controller cabinet
Terminal X.DM
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 7 of 20

Terminals overspeed governor (OSG)

Cable to distribution
box shaft head
Controller cabinet
Terminal X12

Distribution box
shaft head
Distribution box
shaft head Fig. 004

Cable distribution
box shaft head
Controller cabinet Connection
Safety circuit
Terminal X12

Fig. 005

Spare for OSG


reset

Connection for OSG


Connection OSG remote tripping
safety circuit

Connection for OSG


remote tripping
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 8 of 20

Pit control unit

Cable Pit control unit


to controller cabinet
Terminal X10 & X11

Pit control unit


with Stop button,
alarmbutton, shaft-
light button, power
socket

Cable to slack
rope switch

Cable door lock


main entrance
(1.door) min.
1200mm
System earth
doors main en-
trance (1.door)

Cable for door lock


open trough side
(2. door)

Fig. 006

Connection box
for system earth
(open trough side)
Fig. 007
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 9 of 20

Tension weight

Cable from pit


control unit

Slack rope switch

Fig. 008
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 10 of 20

UPS (for emergency operation) option


position in pit

Fig. 009

Cable emergency supply to


controller cabinet
Terminal X.400 1/2/5 Cable emergency supply to
controller cabinet
Terminal X.400 3/4/5
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 11 of 20

Shaft light

Cable shaft light to approx. 500mm


controller cabinet from top
Terminal X.SL

Fig. 010

approx. 500mm
from bottom
Fig. 011
Pluggable shaft light 50Lux with max. 2000mm
distance between the tubes
(Attention: distance between tubes is limited due
to the max. connection cable length of 2000mm!)
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 12 of 20

System earth- & Door look contact shaft doors

Shaft door
header

Door lock cable to next


door above or if top door to
controller cabinet

System earth cable to next


door above or if top door to
controller cabinet

System earth cable to next


door below or if lowest door to
pit control unit

Door lock cable to next door


below or if lowest door to pit Fig. 012
control unit
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 13 of 20

Landing operation panels

Wall cut out Ø30mm


(by builder / others)

Center of push
button (or lowest
push button in case
of 2-button control)
= Center of wall cut
out for LOP
connection cable

(900mm – 1100mm)

Fig. 014

Connection cable LOP


to controller cabinet
Fig. 013
Terminal X56
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 14 of 20

Car top control unit

Fig. 015

Fixation part
(2 pcs.) for car top
control unit mounted on C-
profile at cabin roof

car top control unit


mounted at fixation parts

Fig. 017
Fig. 016
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 15 of 20

Limit switch S25

Fig. 018

Mounting of limit switch


see installation
instruction car frame

To car top control


Terminal X21

Fig. 019
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 16 of 20

Safety gear switch S20

Fig. 020

Installation of safety
gear switch see
installation instruction
car frame

To car top control


Terminal X21

Fig. 021
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 17 of 20

Shaft information system

MS485.LVL (option)
MS485.POS (standard)

Fig. 022

Both connection cables are already connected at car


top control unit (If there´s only one sensor necessary
then you will only find one connection cable)
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 18 of 20

Car operation panel

Trailing cable X51; X52; X53; X55

Fig. 023

Cable already connected at car top


control unit

To car operation panel


Terminal X72
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 19 of 20

Door operator & light screen

Light screen Fig. 024


door B
Door operator (open trough side)
door B
Terminal X48
(open trough side)
Terminal X47

Light screen
door A
(main entrance)
Terminal X48

Light screen
door A
(main entrance)
Terminal X46

Fig. 025
LM Jade

Cable plan
Installation instruction
08
M-08.470.001-E

Status: 07/06 Page 20 of 20

Load weighing control unit

Load weighing control unit


mounted above car top
control unit

Mounting of control unit is also


possible inside the car operation
panel (backside)

Installation of mechanical load


weighing part (Strain Link 942)
see installation instruction
car frame

Fig. 026 Connection to mechanical load


weighing part
(Strain Link 942)

Load weighing control unit


Terminal X48

Fig. 027
LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 1 of 21

Instruction for Commissioning,


Testing and Maintenance
Machineroomless Traction Lift “Jade”
„reduced headroom”
LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 2 of 21

Table of Contents

1. General notes...................................................................................................... 3
2. Maintenance and installation area: Shaft headroom ........................................... 3
2.1 Drive in the shaft head room .................................................................................. 3
2.2 Controller and frequency inverter outside the shaft ................................................ 3
2.3 Maintenance area inside cabin............................................................................... 4
3. Commissioning of Control - Inverter - Drive ......................................................... 6
3.1 Required documentation ........................................................................................ 6
3.2 Gearless drive SM200B .......................................................................................... 6
3.3 Frequency inverter ARTDriveL ............................................................................... 8
3.4 Commissioning of the control .................................................................................. 8
3.4.1 Safety circuit – emergency operation control........................................................ 8
3.4.2 Control menu ....................................................................................................... 9
3.4.3 First run with emergency control .......................................................................... 9
4. Lift guard unit .................................................................................................... 10
5. Examinations by TÜV........................................................................................ 11
6. Examination of light screen on cabin roof .......................................................... 15
7. Check of dual-circuit brake ................................................................................ 15
8. Release of trapped persons .............................................................................. 16
9. Troubleshooting ................................................................................................ 18
10. Parameterlisting ................................................................................................ 19
11. Configuration of Controller Inputs SM01 and cabin interface SM02................... 21
LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 3 of 21

1. General notes
This instruction shall enable the lift technician to become familiar with the lift and its specific
characteristics and to carry out installation and commissioning in accordance with the intended
use.
It includes important information to commission the lift appropriately and its strict observance
contributes to avoid risks, to reduce the time for commissioning and to pass the acceptance
examination successfully.

Any person involved in the installation and commissioning of the lift shall read this in-
struction carefully and strictly adhere to.

If any questions regarding installation, commissioning or examination of the lift may be remain-
ing please contact LM LIFTMATERIAL.

2. Maintenance and installation area: Shaft headroom


The JADE Lift is a type certificated (according EN81-1/A2) machineroomless elevator with
drive unit located in the shaft head. The controller including the frequency inverter is located
outside the lift shaft.

At JADE Lift with reduced shafthead it is not allowed to stand on the cabin roof.
This is monitored with a light screen at the cabin roof.
If the necessity arises to replace the drive/brake, this is only possible and allowed by
means of an additionally installed mounting platform.

Maintenance/Inspection is done from inside the cabin by use of a foldable ceiling.

2.1 Drive in the shaft head room


The drive of the MRL is arranged in the shaft headroom on a special mounting element on the
top of the car guide rails, according to the type drawing.

The drive unit is a frequency controlled, gearless machine with a dual-circuit disc brake. The
drive is mounted on the machine frame. The loads are led via machine frame to the car guide
rails.

2.2 Controller and frequency inverter outside the shaft

The lift controller is placed outside the lift shaft. In the controller cabinet the frequency inverter
is integrated therefore the lift could be controlled from outside the shaft. All tests could be done
from outside the shaft too.
LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 4 of 21

2.3 Maintenance area inside cabin

Maintenance/Inspection is done from inside the cabin by use of a foldable ceiling.

Is not allowed to stand on the cabin roof. On the cabin roof it is reminded of the
danger with a sign:

REDUCED SHAFT HEAD!


STEP ONTO CABIN ROOF
NOT ALLOWED

DANGER !
The area which is not monitored with the light screen is manufactured so that trespassing on
cabin roof is not possible. The light screen is integrated in the safety circuit of the lift controller.

If the cabin roof is entered unauthorized the light screen interrupts the safety circuit and a
movement of the lift is prevented.
The electrical opening of the brake with the the lift guard unit in the control cabinet is prevented
too.
For maintenance the lift technician has to bring the ladder/trestle inside the cabin (preferred
standing height is 700mm).
LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 5 of 21

Then the foldable ceiling has to be folded down from inside the cabin. This foldable ceiling is
monitored with a safety switch (S.IK) and allows with opened ceiling only operation in inspec-
tion mode.

With folded ceiling the lift technician can access the inspection box and he can move the lift with inspection.
If he would get trough the monitoring area of the light screen while he is moving the lift the movement will
be stopped immediately. A movement of the lift is only possible when the lift technician is inside the cabin
respectively below the monitoring area.

When the lift is in stopped condition the lift technician can use the ladder/trestle to bring himself in position
to do the maintenance and inspection work. Until the light screen is interrupted no movement is possible.
A movement of the lift car is only possible again when the light screen is not interrupted, that means when
the lift technician is back inside the cabin below the monitoring area.
LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 6 of 21

3. Commissioning of Control - Inverter - Drive


3.1 Required documentation

Please ensure that on commissioning the following documentation is available:


- Manual Lift Control MRL JADE smartCom II
- Circuit diagram for machineroomless lift JADE
- Operating instruction Zetatop SM200B
- Operating instruction/Instruction Manual ARTDriveL

3.2 Gearless drive SM200B

Please observe that the motor conductors are connected in phase.


The following allocations are imperative:
Motor Control cabinet
U1 (black) X2.U
V1 (brown) X2.V
W1 (grey) X2.W

Any change of these allocations is not allowed!


LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 7 of 21

Please check that you have done the right Brake connection for Brake circuit 1 and
Brake circuit 2 – compare with wiring diagram page 3 + page 10:

X59.5 X59.7 X59.1 X59.3 X59.2 X59.6 X59.7 X59.1 X59.3 X59.2 Connector Cabinet
5 7 1 3 2 6 7 1 3 2 Wire Number

(Wire 1, 2, 3 and 7 from brake 1 are parallel connected to the contacts of brake circuit 2)
LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 8 of 21

3.3 Frequency inverter ARTDriveL

The frequency inverter is preset to the SM200B drive system.


The encoder-offset is also preset.
If any problems are arising on commissioning please contact LM Liftmaterial.
Alternatively you can look up the complete commissioning procedure in chapter 7.2 Commis-
sioning for AVy…BR/BR4 (Brushless Motors).
Please ensure that:
- The brake resistor is connected to terminal X4 in the control cabinet
(Page 1 in the circuit diagram)
- The motor encoder cable is connected to connector XE at the frequency inverter.
Please plug the cable with completely switched off inverter only!

3.4 Commissioning of the control

3.4.1 Safety circuit – emergency operation control


Ensure at first that the safety circuit is closed.

If any areas in the safety circuit are to be bridged it is necessary to observe special pre-
caution measures upon moving the car/car frame.
Ensure that there are no persons within the door area or in the shaft!

First of all connect all available safety switches and elements.


Should this not be possible, bridge the following areas in the safety circuit:

X10.3 to X21.1

X21.1 to X25.1

X25.1 to X51.6

Provide the following bridge for the emergency operation control:


X52.8 to X52.2
Attention! This is a low-voltage signal (GND signal of the control)
LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 9 of 21

3.4.2 Control menu


Please check the parameters of the digital inputs in the lift control.
These can be found in menu:
Parameters
PARAMETER
INPUT TYPE

The configuration of the INPUT TYPES has to be checked


(normally closed = NC / normally open = NO)

INPUT X 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
NC NO NO NO NO NC NC NC NC NO NO NC NO NO NO NC

INPUT X 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
NC NC NO NO NC NO NC NC NO NO NO NO NO NO NO NO

The table above is applicable for normal operation.

For operation without the shaft information switches the input TYPE for X5, X6, X7 and
X8 has to be changed to NO contact (see page 9 for controller login).
To enable this change, the control has to be set to emergency operation.
After calling menu item INPUT TYPE “OK” has to be pressed, the cursor changes from small
( _ ) to big ( █ ). Select the desired input by means of the direction keys. By pressing the OK-
key again the type of input can be changed. For leaving the menu press the ESC-key.
After the parameters have been changed select menu item SAVE and confirm by OK.

3.4.3 First run with emergency control


After verification that there is no risk of collision the first run with emergency control can be
carried out.

In case that the lift is not moving in the direction predetermined by the control, the
correct direction of rotation has to be set only at the frequency inverter.

Select the following menu item:

TRAVEL
Speed setpoint
Speedref inv src
change the set value from ZERO to ONE
resp. from ONE to ZERO.
LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 10 of 21

4. Lift guard unit

The lift guard unit is integrated in the upper part of the lockable control cabinet.
All live parts are protected against inadverted contact.
The following components are integrated:
• Telephone handset
• Main Switch F1
• Drive Monitor (DM) with integrated indication of flush position, running direction, speed
• Residual current circuit breaker for: control circuit (FI1), light circuit (FI2)
• Autom. circuit breaker for: control (F2), door control unit (F3), shaft light (F4),
car light (F5).
• Push button for shaft light (S93)
• Switch to activate the emergency power supply (PWR in position UPS)
• Push button for brake opening, for brake circuit A and B (Brake 1 release and Brake 2 re-
lease)
• Switch for emergency operation
• Push button for remote tripping of the overspeed governor (governor test – S.FA)

In case of a breakdown of the lift these functional elements enable the lift guard to get in
speech contact with the trapped persons, to verify the flush position of the car and the speed
and travelling direction and, if possible, to attempt releasing the trapped persons by
activating the emergency control resp. by using the push buttons for brake opening.

Eye contact to the drive and to the ropes is not necessary.


LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 11 of 21

5. Examinations by TÜV
Examinations prior to commissioning as per appendix D of EN 81-1:1998, examinations after
an important modification or after an accident as well as periodical examinations as per infor-
mative appendix E of EN81-1:1998 are considered.

The following table shows the deviations, if any, in the examination procedures of the
machineroomless lift against those carried out at a conventional one.

The examinations of the drive have to be carried out from the control area.

In order to avoid that any persons are still in the car during examination, we recommend
locking of the doors during these examinations.

This is carried out as follows:

At first, a registration is required:

Select menu item “Login” in the main menu:

In the LOGIN window the cursor is blinking beside the PIN. Activate the PIN-input with”Ok”.
Factory setting is “0“. Thus you only have to press “Ok“ once and the PINs of the individual
levels are appearing. The PIN is maximum five digits.
Now you can modify the individual PINs. Three levels with different authorizations are
available.
The level with most authorizations is level 3. In line 1 the momentary authorization level can be
identified. If you don’t explicitly log-off, an automatic log-off will be carried out after the elapse of
10 min of inactivity.
LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 12 of 21

Select menu item “Parameters” in the main menu:

Select menu item TEST RUN in menu Parameters:

In menu TEST RUN: place the cursor before “Tür“ and change √ to X by pressing the OK key

Ensure before that no persons are in the car any longer.

As soon as the first menu line shows

PAR x Tür REG 1

the doors will be locked.


LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 13 of 21

Prescribed examinations prior to Procedure of examinations on a lift without a


commissioning acc. to EN 81-1:1998, machine room
appendix D 2 :

a) Interlocking of landing doors Check of interlocks from inside the cabin with folded
ceiling.

b) Traction means and their fixations Check of ropes and rope terminals from inside the
cabin with folded ceiling.

c) Brakes With inspector in the topmost landing, in front of the


control cabinet.

By activating fuse F2 an emergency stop occurs and


the brake applies.

By switching on at a defined position, i.e. upon pass-


ing at a landing floor, the braking distance can be
measured.
To check a brake circuit, the examination of the brake
is carried out as per item 3.6.

d) Measuring of current/power and speed Check of data by reading from the display of the
frequency inverter (menu item MONITOR).

e) Electrical lines Check from inside the cabin with folded ceiling.

f) Emergency limit switch No difference – same as for a lift with machine room

g) Rope traction The inspector is in front of the emergency release


Slipping test unit.
When the car is passing the respective landing next
to the last one (identifyable on the controller status
menu monitor) he is braking the car (which is running
with rated speed) by by disengaging the main switch.

Impact-on-buffer test The sense of rotation of the motor can be indicated by


the inverter monitor and by the indicating arrows of
the drive monitor as well.

If an encoder is used at the overspeed governor, the


movement of the car can be monitored in the status
menu of the control by indication v=…m/s.
If there is no incremental encoder used at the over-
speed governor, the movement of the car shall be
monitored by putting a pointer that reaches through
the gap of the car door.
LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 14 of 21

Prescribed examinations prior to Procedure of examinations on a lift without a


commissioning acc. to EN 81-1:1998, machine room
appendix D 2 :
If the car does not move with rotating motor (no mo-
tion at the pointer resp. v = 0 m/s) impact-on-buffer
test is completed.

Counterweight compensation Measuring of the current by reading from inverter


display.

h) Overspeed governor Activation of the overspeed governor mounted in the


shaft headroom and equipped with remote tripping, by
means of a push button (governor test) from the con-
trol cabinet, with rated speed.
Alternatively, the test of the overspeed governor can
be carried out also by repositioning the governor rope
to the test groove. After that, run the lift with a normal
command in downward direction.

i) Safety gear on the car No difference.


To bring the car out of the braked position the emer-
gency control has to be applied. In case of difficulties
either some test weights must be removed or the car
has to be pulled free by means of a hoist.

j) Safety gear on the counterweight Alternatively, the counterweight is equipped with a


safety gear.
The car with rated load is set onto the buffer by
k) Buffer means of the emergency control.
Implementation of a functional test.
l) Emergency call device (Alarm)

m) Protection of the upward running car To bring the car out of the braked position the emer-
against overspeed gency control has to be applied.
In case of difficulties either some test weights must be
added or the car has to be pulled downward by
means of a hoist.
LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 15 of 21

6. Examination of light screen on cabin roof

The function of the light screen on the cabin roof has to be checked before doing
maintenance work.
For this check first the lift technician has to bring in the ladder/trestle inside the cabin
(preferred standing height is 700mm). Then the foldable ceiling has to be folded down
from inside the cabin. This foldable ceiling is monitored with a safety switch (S.IK) and
allows with opened ceiling only operation in inspection mode.

If somebody gets trough the monitoring area a warning signal must appear and the
movement of the lift must be impossible. A movement of the lift car is only possible
again when the light screen is not interrupted, that means when the lift technician is
back inside the cabin below the monitoring area.

7. Check of dual-circuit brake


The check of the dual-circuit brake is carried out from the control, acc. to the following se-
quences (see also circuit diagram, page 3):

At first, the normal brake function is established by “brake test number 1”:
The car, running downward with rated speed and loaded with the test load, is braked by activa-
tion of fuse F2 at an defined point, for example when passing a landing.
The required braking distance can be established by measuring out the car position.
Now, the braking distance has a certain length, e.g. 50 cm;

Now, with “brake test number 2” the function of one brake circuit only is checked:
The car is moved to the original position where the brake test was started.
Set Switch S500 (PWR) to position UPS.
Set the car in motion by means of a call.
As soon as the car starts moving, push button S501 / brake 1 release must be pressed perma-
nently.
Upon passing the braking point an emergency braking is carried out by switching off control
fuse F2.
Push button S501 / brake 1 release must be operated until the car has come to a standstill.
If the car does not brake, the push button shall be immediately released.
Now, as expected, the braking distance will be a bit longer, e.g. 80 cm, but the braking effect
should suffice to decelerate the car resp. not to let it run faster. It is permissible that the lift is
overrunning the terminal landing and is hitting the buffer with rated speed.

After that, with “brake test number 3” the second braking circuit is checked analogous to
“brake test number 2”:
Move the car to its original position. Repeat the check analogous to “brake test number 2”,
however keep the braking circuit 2 positively open with push button S502 / brake 2 release.
LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 16 of 21

8. Release of trapped persons

According to lift directive 95/16/EG lifts have to be provided with facilities by which persons
trapped in the car can be released and evacuated within an acceptable period of time.

The emergency release is carried out by the lift guard unit.

By means of the intercom the contact to the car will be established. If there are any persons
trapped in the car and if the car is within a landing zone, the lift guard or the maintenance per-
sonnel can try to move the car to the next landing level by means of the emergency control in
the lift guard panel.
If the car is positioned level in a landing, this is signalized on the Drive-Monitor.

DM: Drive Monitor

When the emergency control becomes ineffective owing to a power failure or a technical
defect, the main switch shall be disconnected and the release action be carried out as
follows:

• Switch off the main switch and switch on the emergency power supply.
For that, bring switch PWR into UPS position and inform the trapped persons about the
ongoing release action.
• Press the push buttons ”brake 1 release“ and ”brake 2 release“ simultaneously, this way
opening the brake of the lift. Now, the car starts moving upward or downward, depending
on the car load.

Caution!
Release the push buttons ”brake 1 release“ and ”brake 2 release“ immediately
when the STOP-indicator starts flashing.
LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 17 of 21

• Check speed and travelling direction of the car at the drive monitor. If the speed of 0.3m/s
is exceeded the STOP-indicator is flashing. Release the brake lifting push buttons at
once.
• Release the push buttons when a landing level is reached.
• When you have reached a landing level the trapped persons can be evacuated through
the door.
• When the car does not start moving you should call the maintenance contractor.
• Now close the control cabinet to prevent unauthorized access!

Optionally, there is a possibility to equip the lift with a battery-fed evacuation module and to
perform a fully automatic release action. As this feature is not a part of the basic equipment
of the lift, the option should not be considered in the risk assessment regarding “Trapping of
persons and their release”.

Option: automatic release by means of EVA (fed by an uninteruptable power supply):

If the control is equipped with an adequately dimensioned and uninterruptible power supply
the control initiates after a power failure, with closed safety circuit and functional technique, an
automatic release run to the next landing with creeping speed. The landing is selected depend-
ing on the condition of the car load.

This function may involve a risk for the lift technician only if he is within the lift sphere during a
power failure and is not observing the usual protective measures, like switching on the emer-
gency stop switch or hanging-in the pit ladder into the door sill.
Therefore the risk potential is identical to that of a lift user setting a command under normal
operation conditions.

By disconnecting the main switch also the release run is switched off, i.e. it cannot be activated
suddenly with a technician being within the danger zone of the lift.

See also: Release of trapped persons in document Operating instruction


LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 18 of 21

9. Troubleshooting

Learn trip not correct finished


- check distance between magnet stripe and sensor
ideal distance is 6mm
- limit switch is activated before inspection end top (ieo) is reached

Lift overruns level (floor to floor)


- reduce Multi speed 5 at frequency inverter (e.g. 850mm/s)
(TRAVEL- Speed profile – Multi speed 5)

Corresponding speeds at frequency inverter


Multi speed 0 = 0mm/s
Multi speed 1 = not used
Multi speed 2 = not used
Multi speed 3 = levelling speed (35mm/s)
Multi speed 4 = inspection speed (200mm/s)
Multi speed 5 = nominal speed floor to floor (e.g. 850mm/s)
Multi speed 6 = nominal speed over 2 floors (e.g. 1000mm/s)
Multi speed 7 = nominal speed over 3 floors (e.g. 1000mm/s)

Noise at stop (after break is deactivated)


Check controller parameter Group F- No. 17 (Brake release time) –
adjust to 14 (x50ms)
Check controller parameter Group F- No. 47 (Motor contactor release time) –
adjust to 16
Check inverter parameter (Activation with password 12345 at Service menu necessary)
CUSTOM FUNCTIONS – Pad parameters – Pad param word
Note Pad 0, Pad 1, Pad 2 und Pad 3 and inform LM Liftmaterial
(possible configuration Pad 0 = 100; Pad 1 = 4000;
or Pad 0 = 1, Pad 1= 2, Pad 2 = 100, Pad 3 = 4000)
Change of this parameters are only allowed after reconfirmation with
LM Liftmaterial.
TRAVEL – Lift sequence
Cont close delay = 0 ms
Brake open delay = 504 ms
Brake close delay = 0 ms
Cont open delay = 400 ms
LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 19 of 21

Frequency inverter tripps with BU overload while travelling with empty car upwards
Check if counterweight is correct balanced
Change (increase) at Frequency Inverter in menu
STARTUP-Startup config- BU protection
the value for BU res OL factor to 20
Please save changed value with Safe config

Remote tripping is not working


Check internal connection between X25.1 and X61.7 (compare wiring diagramm page 3)

10. Parameterlisting

JADE Controller parameter list  Parameters – PARAMETER – GROUP F

Only with analog speed control

Factory setting With Jade elevator system


With motor shaft information With OSG shaft information
Encodercable connected to JP7 Encoder cable connected to JP8
JP5+6 at 1-2 JP5+6 at 2-3
Nr Parameter
0 Rated speed 1.0 1.0
1 Motor speed (1:1=80) 2:1= 160 95 with GB200
2 Encoder puls 2048 4096
3 No. Of stops 2 customized
4 Floor offset 0 customized
5 Drive Mode 0 (Multistep) 1 (Analog) Antrieb Typ 0 0
6 acceleration 0,4m/s² not relevant
7 deceleration 0,4m/s² not relevant
8 Jerk 0 1,3s not relevant
9 Jerk 1 1,1s not relevant
10 Jerk 2 1,1s not relevant
11 Jerk 3 1,3s not relevant
12 V insp. 0,25 m/s not relevant
13 V rel. (nachh.) 0,06 m/s not relevant
14 Hall call door open time 5s 8
15 Car call door open time 3s 7
16 Brake activation delay 10x50ms 10x50ms
17 Brake release delay 5x50ms 14x50ms
18 Homing floor (Dplx. home 1) 1 customized
19 Dplx. home 2 1 customized
LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 20 of 21

20 Fire home 1 customized


21 not used 1 not used
22 Forced stop 0 customized
23 not used 1 not used
24 Homing delay 0s customized
25 Grp.Status 0 customized
26 not used 0 not used
27 Fire mode with or without key in COP 0 0= with key; 1= without key
Brake SW monitoring 0 x50ms;
28 with 0 monitoring is deactivated 0 20
29 Fire return home 1 (Input X13) 0 customized
30 Fire return home 2 (Input X14) 0 customized
31 not used 0 not used
32 not used 0 not used
33 DFÜ ID 255 customized
34 V1 dec. Distance (unit is cm not mm)! 160 150 (related to Multi speed 5, customized)
35 V2 dec. Distance (unit is cm not mm)! 320 150 (related to Multi speed 6, customized)
36 V3 dec. Distance (unit is cm not mm)! 320 150 (related to Multi speed 7, customized)
37 Parkfahrt Aktivierung mit Wert 1 0 customized
38 Level Adjust 73 70
39 Down adjust 80 80
40 Up adjust 80 80

Preopening door; 0= not activated;


41 1=preopening door; 2=relevelling; 3=both 0 customized
42 Relevelling (0 don´t change) use par. No. 41 0
Door mode
0= Door hold off 1=door close hold (AT15, AT25,
Sematic Encoder) 2=door open hold
43 3 = both 1 1
44 Drive monitoring (20s) 50 20 (customized)
45 Door A delay (without door limit switch connected) 0 0 (door limit switch connected)
46 Door B delay (without door limit switch connected 0 0 (door limit switch connected)
47 Motor contacter release time 16 16
LM Jade

Instruction for Commissioning, Testing and Maintenance


09
“reduced headroom” I-09.500.122-E

Status: 09/06 Page 21 of 21

11. Configuration of Controller Inputs SM01 and cabin interface SM02


Parameters – PARAMETER – INPUT TYPE

SM01:

X X
0 NC 16 NC
1 NO 17 NC
2 NO 18 NO
3 NO 19 NO
4 NO 20 NC
5 NC 21 NO
6 NC 22 NC
7 NC 23 NC
8 NC 24 NO
9 NO 25 NO
10 NO 26 NO
11 NC 27 NO
12 NO 28 NO
13 NO 29 NO
14 NO 30 NO
15 NC 31 NO

Remark: It is possible that X3 and X4 is configurated to NC in combination with short floors

SM02:

TX TX
0 NC 16 NO
1 NC 17 NO
2 NO 18 NO
3 NC 19 NO
4 NO 20 NO
5 NO 21 NO
6 NO 22 NO
7 NC 23 NO
8 NO 24 NO
9 NO 25 NO
10 NO 26 NO
11 NC 27 NO
12 NC 28 NO
13 NO 29 NO
14 NO 30 NO
15 NO 31 NO
LM Jade Spareparts
09
E-09.500.120-E

Status: 08/06 Seite 1 von 8

Spareparts
LM Jade Spareparts
09
E-09.500.120-E

Status: 08/06 Seite 2 von 8

Assembly Item Serial No. Picture

Car frame
Lubricator (Material: synthetic),
blade width 5 - 16 mm

Impact buffer for car and coun-


terweight (Material: Cellasto )

Guide shoe inserts for guide


shoes 1400 G and 1500 SG (ND-
Polyäthylen S-GRÜN) blade width
16 mm

Guide shoe, Type 1400 G

SL-safety for tripping lever

Limit switch

Safety gear switch


LM Jade Spareparts
09
E-09.500.120-E

Status: 08/06 Seite 3 von 8

Assembly Item Serial No. Picture

POS-sensor for magnet type shaft


information system (relevelling,
door zone, correction, learning- 0701000053
trip limit switch, pre-limit
switch/optional)

LVL-sensor for magnet type shaft


information system (door zone, 0701000054
relevelling on side B)

Guide shoe inserts 1405 GE


counterweight (Material: Elastollan), parallel
rubbing surfaces, blade width
5mm

Impact buffer for car and coun-


terweight (Material: Cellasto )

Guide shoe, Type 1400 G

Lubricator (Material: synthetic),


blade width 5 - 16 mm

Load weighing device for mount-


Load weighting ing to the bending girder , ÜL
device (overload) evaluation + VL (full
0745000259
load) relay 24 V, max. travel
height 30 m, w/o weight limit, incl.
screws, washers & nuts
LM Jade Spareparts
09
E-09.500.120-E

Status: 08/06 Seite 4 von 8

Assembly Item Serial No. Picture

Rope pulley for Emerald (Material:


Rope pulleys Optamid, yellow)

Oil tray Oil tray (Material: synthetic), uni-


versally applicable for blade width
5-16mm

Drive
Rotary encoder ERN 1387 0745000255

Brake, Type ROBA-stop®-R

SPD-sensor to recognize sense


0701000052
of rotation

Frequency inverter Frequency inverter JADE


0746000281/
AVY2055-KBL-BR4
0746000282
AVY2075-KBL-BR4

Mains filter for JADE 074600283


EMI-C 480-25
LM Jade Spareparts
09
E-09.500.120-E

Status: 08/06 Seite 5 von 8

Assembly Item Serial No. Picture

Line reactor for JADE


0746000285 /
LR3Y-2055
0746000286
LR3Y-2075

Flat resistor 68Ohm for AVY2055


0746000303
and AVY2075

Control
Main module SM01sup 0701000055

Car module SM02

Command module SM03

Landing module SM04

Remote tripping device 220 V for


Overspeed supplementary installation, direct
governor connection, for HJ 200/300, incl. 0409080241
pipe clamp, fixing material and
plug
LM Jade Spareparts
09
E-09.500.120-E

Status: 08/06 Seite 6 von 8

Assembly Item Serial No. Picture

Incremental encoder for speed


0745000252
governor - optional

Tensioning weight with switch

Tensioning pulley with pin, type


S2WB Ø 208 mm, v = 1.0 m/s

Slack rope switch with trip cam


and screw kit

Overspeed governor rope,


0501010121
Ø 6.5 mm

Ropes PAWO special rope with steel


0501010241
core, Type F3 Ø 6 mm

Info on PAWO special rope (with


prefabricated pressed thimble and
eyebolt)
LM Jade Spareparts
09
E-09.500.120-E

Status: 08/06 Seite 7 von 8

Assembly Item Serial No. Picture

Landing doors Upper suspension roller for door


hanger Ø 53 mm 0236010005
(SEM.2000/C144AANP-E)

Counter roller Ø 29 mm with


eccentric pin for door hanger 0236010519
(SEM.2000/*C144AAOP01)

Contact bridge PZ 21
0236010699
(SEM.2000/CX00XAAXAAU)

Door guide element (PTFE) for


SEM.2000 and SEM.III 0236011329
(SEM.2000/C116AAAP*)

Drag rope Ø 3.2 mm for


SEM.2000 and SEM.III GW-
0236011349
airplane rope, zinq coated
(SEM.2000/*C088AAAF)

Car door
Dunker motor IP20 (B105AANX) 0236011794

Door control unit


SRS DC-PWM
LM Jade Spareparts
09
E-09.500.120-E

Status: 08/06 Seite 8 von 8

Assembly Item Serial No. Picture

Door control unit


0236011781
Sematic Drive 3.0

Toothed belt RPP 8M/15 with


parabolic section
(CX00XAAXACV)

Door guide, screwed (with Teflon


element) for glass panel
(SEM.2000/B128AAAX)

You might also like