Seismic Bracing For Water-Based Fire Protection Systems According To FM Global Loss Prevention Data Sheet 2-8 (May 2010)
Seismic Bracing For Water-Based Fire Protection Systems According To FM Global Loss Prevention Data Sheet 2-8 (May 2010)
FM GLOBAL
EXCEPTIONS TO NFPA 13
CALCULATING FORCES
FM APPROVALS
DESIGN ACCORDING TO FM GLOBAL LOSS PREVENTION DATA SHEET 2-8 (MAY 2010)
WHAT FM REQUIRES
QUESTIONS
Fwp = G x Wp
FM 2-8
APPENDIX A GLOSSARY OF TERMS
Pipe Schedule 40
Pipe Schedule 10
Only Approved Angles
bracing member Rods (Threaded full lenght)
Rods (Threaded at Ends Only)
Shall be
3. Providing clearance between piping or equipment and structural members, walls, floors, or other objects
Each side of the assembly is considered as end of pipe for bracing purpose
LAYOUT TO REVIEW
Calculation Form
• Bracing pipe
• Type
• Schedule
• Size Structural Attachments
• Angle (Load Capacity)
• Load Capacity
Pipe Attachment
(Load Capacity)
Structural Attachments
Anchor
(Load Capacity)
Horizontal loads
Zone of Influence Load Capacity of different
(ZOI) Elements has to be bigger than
Horizontal forces
• Location of clearances.
• Anchorage or seismic design details for storage racks that have in-rack sprinklers.
• For fire pump installations, all seismic design details as outlined in Section 2.2.5.
• For water storage tanks or reservoirs, all seismic design details as outlined in Section 2.2.6.