You are on page 1of 1226

GENERAL RATE ANALYSIS VOLUME – III

FOR FINISHED ITEMS OF WORK PART - III


PUBLICATION NO.52

EXCAVATION AND EARTH WORKS

FIST FILL THIS SHEET FOR MATERIAL AND LABOUR ONLY.


BELOW ALL RATE ANALYSIS ARE AUTOMATICALY FILLED BY THIS DATA.

S No Rate Unite

1 Coolies, Mate , Bellow Man. 250 P.day.

2 Dresser,Skilled Collie,Bhishti, 250 P.day


Hammer Man , Quarry Man,
Smithy Cooly.

3 Black Smith (G-11) , Chiseller. 400 P.Day

4 Kharkar 4500 P.Month

5 Belchaman, Langri ,Contiman 4000 P.Month


Chowkidars, Topalalies,Dobashi.

6 Bullock Main with 1/2 Pair of Bullock 400 P.Day

7 Bullock Main with Pair of Bullock. 500 P.Day

8 Corpenter 400 P.day.

9 Boat man with lange boat 500 P. day.

Material
1 Cost of Powder & Fuse 300 Each
2 Atta 35 Kg.
3 Kitchen Expenses. 400 P.Belcha
4 Cost of dondey 75000
5 Bhoosa 300 P.Mand
6 Grains 1000 P.Mand
7 Steel ordinary. 32.21 P.Lbs
8 Char Coal 675 P.Mand
9 Cost of Tent. 13500 Each.

5 Earth work excavation in


irrigation profiles excavated
material disposed off and
dressed within 50 ft. lead.

(a) Ordinaly Soil

(b) Hard Siol

(c) Very Hard Soil

(d) Shingle and gravel formation

6 Excavation in rock, dressed to


designed section, grades and
profiles, excavated material

Chapter No. 1 1/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

RATE ANALYSIS FOR EARTH WORK.


S/N E A R T H W O R K.
======================
D E S C R I P T I O N.

1. Earth work excavation undressed lead up to a single throw of


khassi, Phaorah or shovel. (Excavation and Embankment)

(a) In ashes, sand, soft soil or silt clearance.


____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging 3.75 Nos: 250.00 P.Day 937.50
(including dagbelling for
barrow pits)

Sundries. 10.00 % 93.75


________________________________ _______ _______ ________ _______ ___________
TOTAL 1031.25
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 103.13
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 1134.38
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 1134.38
____ ________________________________ _______ _______ ________ _______ ___________
____ ________________________________ _______ _______ ________ _______ ___________
S/N E A R T H W O R K.
======================
D E S C R I P T I O N.

1. Earth work excavation undressed lead up to a single throw of


khassi, Phaorah or shovel. (Excavation and Embankment)

(b) In ordinary soil.


____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging 4.50 Nos: 250.00 P.Day 1125.00
(including dagbelling for
barrow pits)

Sundries. 10.00 % 112.50


________________________________ _______ _______ ________ _______ ___________
TOTAL 1237.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 123.75
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 1361.25
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 1361.25
____ ________________________________ _______ _______ ________ _______ ___________
1.36125
____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 2/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================

2. Earth work excavation in ashes sand, soft or silt clearance


undressed lead up to 50 ft.
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging filling 2.50 Nos: 250.00 P.Day 625.00
lifting (including
dagbelling for barrow pits)

Coolies for carrying. 3.00 Nos: 100.00 P.Day 300.00


________________________________ _______ _______ ________ _______ ___________
TOTAL 925.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 92.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 1017.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 101.75
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 1119.25
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 1119.25
Labour rate per 1000 Cft. Say Rs: 1119.25
____ ________________________________ _______ _______ ________ _______ ___________
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================

3. Barrow pit excavation undressed lead up to 100 Cft.

(a) Ordinary or soft soil.


____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging and 4.00 Nos: 250.00 P.Day 1000.00
filling.

Coolies for carrying. 3.00 Nos: 250.00 P.Day 750.00


________________________________ _______ _______ ________ _______ ___________
TOTAL 1750.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 175.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 1925.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 192.50
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 2117.50
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 2117.50
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 3/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================

3. Barrow pit excavation undressed lead up to 100 Cft.

(b) Hard soil.


____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging and 5.60 Nos: 250.00 P.Day 1400.00
filling.

Coolies for carrying. 3.00 Nos: 250.00 P.Day 750.00


________________________________ _______ _______ ________ _______ ___________
TOTAL 2150.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 215.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 2365.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 236.50
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 2601.50
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 2601.50
____ ________________________________ _______ _______ ________ _______ ___________
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
4. Excavation in shingle or gravel formation and rock not required
blasting undressed lead upto 100 ft.

(a) Dry soil.


____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging. 9.00 Nos: 250.00 P.Day 2250.00

Coolies for filling. 4.00 Nos: 250.00 P.Day 1000.00

Coolies for carrying. 6.00 Nos: 250.00 P.Day 1500.00


________________________________ _______ _______ ________ _______ ___________
TOTAL 4750.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 475.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 5225.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 522.50
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 5747.50
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 5747.50
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 4/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
4. Excavation in shingle or gravel formation and rock not required
blasting undressed lead upto 100 ft.

(b) Wet soil.


____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging. 10.00 Nos: 250.00 P.Day 2500.00

Coolies for filling. 5.00 Nos: 250.00 P.Day 1250.00

Coolies for carrying. 7.00 Nos: 250.00 P.Day 1750.00


________________________________ _______ _______ ________ _______ ___________
TOTAL 5500.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 550.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 6050.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 605.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 6655.00
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 6655.00
____ ________________________________ _______ _______ ________ _______ ___________
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
4. Excavation in shingle or gravel formation and rock not required
blasting undressed lead upto 100 ft.

(c) Inflowing water.


____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging. 14.00 Nos: 250.00 P.Day 3500.00

Coolies for filling. 6.50 Nos: 250.00 P.Day 1625.00

Coolies for carrying. 7.50 Nos: 250.00 P.Day 1875.00


________________________________ _______ _______ ________ _______ ___________
TOTAL 7000.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 700.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 7700.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 770.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 8470.00
Labour rate per 1000 Cft. Rs: 8470.00
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 5/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
5. Earth work excavation in Irrigation Channels drains etc, dressed
to designed section, grades & profiles excavated material
disposed off with in 50 ft: lead and dressed.
(a) Ordinary soil.
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging, 4.00 Nos: 250.00 P.Day 1000.00
filling & degbelling.
Coolies for carrying. 3.00 Nos: 250.00 P.Day 750.00

Dresser (for slopes & bed) 1.00 Nos: 250.00 P.Day 250.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 2000.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 200.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 2200.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 220.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 2420.00
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 2420.00
____ ________________________________ _______ _______ ________ _______ ___________
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
5. Earth work excavation in Irrigation Channels drains etc, dressed
to designed section, grades & profiles excavated material
disposed off with in 50 ft: lead and dressed.
(b) Hard soil.
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging, 5.60 Nos: 250.00 P.Day 1400.00
filling & degbelling.
Coolies for carrying. 3.00 Nos: 250.00 P.Day 750.00

Dresser (for slopes & bed) 1.00 Nos: 250.00 P.Day 250.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 2400.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 240.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 2640.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 264.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 2904.00
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 2904.00
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 6/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
5. Earth work excavation in Irrigation Channels drains etc, dressed
to designed section, grades & profiles excavated material
disposed off with in 50 ft: lead and dressed.
(c) Very hard soil.
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging, 7.30 Nos: 250.00 P.Day 1825.00
filling & degbelling.
Coolies for carrying. 3.00 Nos: 250.00 P.Day 750.00

Dresser (for slopes & bed) 1.00 Nos: 250.00 P.Day 250.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 2825.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 282.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 3107.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 310.75
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 3418.25
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 3418.25
____ ________________________________ _______ _______ ________ _______ ___________
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
5. Earth work excavation in Irrigation Channels drains etc, dressed
to designed section, grades & profiles excavated material
disposed off with in 50 ft: lead and dressed.
(d) Shingle and gravel formation.
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging, 13.00 Nos: 250.00 P.Day 3250.00
filling & degbelling.
Coolies for carrying. 6.00 Nos: 250.00 P.Day 1500.00

Dresser (for slopes & bed) 2.00 Nos: 250.00 P.Day 500.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 5250.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 525.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 5775.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 577.50
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 6352.50
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 6352.50
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 7/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
6. Excavation in rock dressed to designed section grades & profile,
excavated material disposed off within 100 ft: & lift upto 5 ft:

(a) Soft rock slate shale schist or laterite work with pick & crow
bar.
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Diggers. 14.00 Nos: 250.00 P.Day 3500.00

Dresser and carriers. 9.00 Nos: 250.00 P.Day 2250.00

Bhishti. 1.00 Nos: 250.00 P.Day 250.00


________________________________ _______ _______ ________ _______ ___________
TOTAL 6000.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 600.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 6600.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 660.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 7260.00
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 7260.00
____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 8/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
6. Excavation in rock dressed to designed section grades & profile,
excavated material disposed off within 100 ft: & lift upto 5 ft:

(b) Medium hard rock requiring occasional blasting.

____ ________________________________ _______ _______ ________ _______ ___________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _______ _______ ________ _______ ___________
Cost of gun powder and fuse. 3.00 Nos: 300.00 Each 900.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 900.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 90.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 990.00

____ ________________________________ _______ _______ ________ _______ ___________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for boring holes 3.00 Nos: 250.00 P.Day 750.00
with steel jumper.

Cooly for tempering and 0.13 Nos: 250.00 P.Day 31.25


fixing 3 charges.

Coolies for digging. 12.00 Nos: 250.00 P.Day 3000.00

Coolies for breaking stone 9.00 Nos: 250.00 P.Day 2250.00


and removing the soil.

Mate. 0.50 Nos: 250.00 P.Day 125.00

Hammer man. 1.00 Nos: 250.00 P.Day 250.00

Black smith for repairing 1.00 Nos: 400.00 P.Day 400.00


tools.

Bellow man. 1.00 Nos: 250.00 P.Day 250.00

Dressers. 2.00 Nos: 250.00 P.Day 500.00


________________________________ _______ _______ ________ _______ ___________
TOTAL 7556.25
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 755.63
________________________________ _______ _______ ________ _______ ___________
TOTAL 8311.88
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 831.19
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " B " 9143.06
________________________________ _______ _______ ________ _______ ___________
TOTAL (MATERIAL + LABOUR) 10133.06
________________________________ _______ _______ ________ _______ ___________
Total material and labour rate per 1000 Cft. Rs: 10133.00
____ ________________________________ _______ _______ ________ __________________
____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 9/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
7. Excavation in hard rock requiring blasting and disposal of
excavated material blasted material upto 50 ft: lead including
dressing and levelling to designed section etc, complete.

(a) Grade-I.
____ ________________________________ _______ _______ ________ _______ ___________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _______ _______ ________ _______ ___________
Cost of gun powder and fuse. 3.00 Nos: 300.00 Each 900.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 900.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 90.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 990.00
____ ________________________________ _______ _______ ________ _______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Quarry men for boring holes 3.00 Nos: 250.00 P.Day 750.00
and firing etc.

Quarry men for digging and 7.00 Nos: 250.00 P.Day 1750.00
breaking large stones into
small ones.

Coolies for removing the 6.00 Nos: 250.00 P.Day 1500.00


soil up to 50 ft: lead.

Black Smith. 0.25 Nos: 400.00 P.Day 100.00

Smithy cooly. 0.25 Nos: 250.00 P.Day 62.50

Chiseller for stone 1.00 Nos: 400.00 P.Day 400.00


dressing.

Bahishti. 0.50 Nos: 250.00 P.Day 125.00


________________________________ _______ _______ ________ _______ ___________
TOTAL 4687.50
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 468.75
________________________________ _______ _______ ________ _______ ___________
TOTAL 5156.25
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 515.63
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " B " 5671.88
________________________________ _______ _______ ________ _______ ___________
TOTAL (MATERIAL + LABOUR) 6661.88
________________________________ _______ _______ ________ _______ ___________
Total material and labour rate per 1000 Cft. Rs: 6662.00
____ ________________________________ _______ _______ ________ _______ ___________
____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 10/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
7. Excavation in hard rock requiring blasting and disposal of
excavated material blasted material upto 50 ft: lead including
dressing and levelling to designed section etc, complete.

(b) Grade-II.
____ ________________________________ _______ _______ ________ _______ ___________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _______ _______ ________ _______ ___________
Cost of gun powder and fuse. 5.00 Nos: 300.00 Each 1500.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 1500.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 150.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 1650.00
____ ________________________________ _______ _______ ________ _______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Quarry men for boring holes 4.00 Nos: 250.00 P.Day 1000.00
and firing etc.

Quarry men for digging and 7.00 Nos: 250.00 P.Day 1750.00
breaking large stones into
small ones.

Coolies for removing the 6.00 Nos: 250.00 P.Day 1500.00


soil up to 50 ft: lead.

Black Smith. Grade-II 0.50 Nos: 400.00 P.Day 200.00

Smithy cooly. 0.50 Nos: 250.00 P.Day 125.00

Chiseller for stone 1.00 Nos: 400.00 P.Day 400.00


dressing.

Bahishti. 0.50 Nos: 250.00 P.Day 125.00


________________________________ _______ _______ ________ _______ ___________
TOTAL 5100.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 510.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 5610.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 561.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " B " 6171.00
________________________________ _______ _______ ________ _______ ___________
TOTAL (MATERIAL + LABOUR) 7821.00
________________________________ _______ _______ ________ _______ ___________
Total material and labour rate per 1000 Cft. Rs: 7821.00
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 11/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
7. Excavation in hard rock requiring blasting and disposal of
excavated material blasted material upto 50 ft: lead including
dressing and levelling to designed section etc, complete.

(c) Grade-III.
____ ________________________________ _______ _______ ________ _______ ___________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _______ _______ ________ _______ ___________
Cost of gun powder and fuse. 6.00 Nos: 300.00 Each 1800.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 1800.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 180.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 1980.00
____ ________________________________ _______ _______ ________ _______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Quarry men for boring holes 5.00 Nos: 250.00 P.Day 1250.00
and firing etc.

Quarry men for digging and 8.50 Nos: 250.00 P.Day 2125.00
breaking large stones into
small ones.

Coolies for removing the 6.00 Nos: 250.00 P.Day 1500.00


soil up to 50 ft: lead.

Black Smith. 0.75 Nos: 400.00 P.Day 300.00

Smithy cooly. 0.75 Nos: 250.00 P.Day 187.50

Chiseller for stone 1.50 Nos: 400.00 P.Day 600.00


dressing.

Bahishti. 0.75 Nos: 250.00 P.Day 187.50


________________________________ _______ _______ ________ _______ ___________
TOTAL 6150.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 615.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 6765.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 676.50
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " B " 7441.50
________________________________ _______ _______ ________ _______ ___________
TOTAL (MATERIAL + LABOUR) 9421.50
________________________________ _______ _______ ________ _______ ___________
Total material and labour rate per 1000 Cft. Rs: 9421.50
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 12/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
7. Excavation in hard rock requiring blasting and disposal of
excavated material blasted material upto 50 ft: lead including
dressing and levelling to designed section etc, complete.

(d) Grade-IV.
____ ________________________________ _______ _______ ________ _______ ___________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _______ _______ ________ _______ ___________
Cost of gun powder and fuse. 7.00 Nos: 300.00 Each 2100.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 2100.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 210.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 2310.00
____ ________________________________ _______ _______ ________ _______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Quarry men for boring holes 6.00 Nos: 250.00 P.Day 1500.00
and firing etc.

Quarry men for digging and 9.00 Nos: 250.00 P.Day 2250.00
breaking large stones into
small ones.

Coolies for removing the 6.00 Nos: 250.00 P.Day 1500.00


soil up to 50 ft: lead.

Black Smith. 1.00 Nos: 400.00 P.Day 400.00

Smithy cooly. 1.00 Nos: 250.00 P.Day 250.00

Chiseller for stone 2.00 Nos: 400.00 P.Day 800.00


dressing.

Bahishti. 0.75 Nos: 250.00 P.Day 187.50


________________________________ _______ _______ ________ _______ ___________
TOTAL 6887.50
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 688.75
________________________________ _______ _______ ________ _______ ___________
TOTAL 7576.25
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 757.63
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " B " 8333.88
________________________________ _______ _______ ________ _______ ___________
TOTAL (MATERIAL + LABOUR) 10643.88
________________________________ _______ _______ ________ _______ ___________
Total material and labour rate per 1000 Cft. Rs: 10643.88
____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 13/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
7. Excavation in hard rock requiring blasting and disposal of
excavated material blasted material upto 50 ft: lead including
dressing and levelling to designed section etc, complete.

(e) Grade-V.
____ ________________________________ _______ _______ ________ _______ ___________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _______ _______ ________ _______ ___________
Cost of gun powder and fuse. 8.00 Nos: 300.00 Each 2400.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 2400.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 240.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 2640.00
____ ________________________________ _______ _______ ________ _______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Quarry men for boring holes 7.00 Nos: 250.00 P.Day 1750.00
and firing etc.

Quarry men for digging and 10.00 Nos: 250.00 P.Day 2500.00
breaking large stones into
small ones.

Coolies for removing the 6.00 Nos: 250.00 P.Day 1500.00


soil up to 50 ft: lead.

Black Smith. 1.00 Nos: 400.00 P.Day 400.00

Smithy cooly. 1.00 Nos: 250.00 P.Day 250.00

Chiseller for stone 2.50 Nos: 400.00 P.Day 1000.00


dressing.

Bahishti. 1.00 Nos: 250.00 P.Day 250.00


________________________________ _______ _______ ________ _______ ___________
TOTAL 7650.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 765.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 8415.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 841.50
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " B " 9256.50
________________________________ _______ _______ ________ _______ ___________
TOTAL (MATERIAL + LABOUR) 11896.50
________________________________ _______ _______ ________ _______ ___________
Total material and labour rate per 1000 Cft. Rs: 11896.50
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 14/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
7(a) Excavation in hard rock requiring blasting and disposal of
excavated material blasted material upto 50 ft: lead including
dressing and levelling to designed section etc, complete.

(f) Grade-VI.
____ ________________________________ _______ _______ ________ _______ ___________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _______ _______ ________ _______ ___________
Cost of gun powder and fuse. 9.00 Nos: 300.00 Each 2700.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 2700.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 270.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 2970.00
____ ________________________________ _______ _______ ________ _______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Quarry men for boring holes 8.00 Nos: 250.00 P.Day 2000.00
and firing etc.

Quarry men for digging and 10.00 Nos: 250.00 P.Day 2500.00
breaking large stones into
small ones.

Coolies for removing the 6.00 Nos: 250.00 P.Day 1500.00


soil up to 50 ft: lead.

Black Smith. 1.25 Nos: 400.00 P.Day 500.00

Smithy cooly. 1.25 Nos: 250.00 P.Day 312.50

Chiseller for stone 3.00 Nos: 400.00 P.Day 1200.00


dressing.

Bahishti. 1.00 Nos: 250.00 P.Day 250.00


________________________________ _______ _______ ________ _______ ___________
TOTAL 8262.50
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 826.25
________________________________ _______ _______ ________ _______ ___________
TOTAL 9088.75
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 908.88
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " B " 9997.63
________________________________ _______ _______ ________ _______ ___________
TOTAL (MATERIAL + LABOUR) 12967.63
________________________________ _______ _______ ________ _______ ___________
Total material and labour rate per 1000 Cft. Rs: 12968.00
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________


S/N D E S C R I P T I O N.
======================
7(b) Excavation in hard rock requiring blasting but blasting 25936.00
prohibited and disposal for excavated material upto 50 ft: lead
including dressing & levelling to designed section etc,complete.
Note:-Add 100% to the rate as applicable in item no:7(a) above.
____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 15/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
8. Extra for every 50 ft: additional lead or a part there of.
(1) Earth work excavation in ashes sand soft soil or silt lead
500 ft: by means of donkey labour.
Actual expensive of 4 Nos: Balchas.
____ ________________________________ _______ _______ ________ _______ ___________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
I Labour on monthly basis for 30 days.
________________________________ _______ _______ ________ _______ ___________
(a) 28 men detailed as below.

1. Kharkar(owner)pemonstrater. 1.00 Nos: 4500.0 P.Month 4500.0


2. Belchaman (Man for 8.00 Nos: 4000.0 P.Month 32000.0
excavation)
3. Contiman ( Men with pick 4.00 Nos: 4000.0 P.Month 16000.0
axes)
4. Topalalies ( Men with 10.00 Nos: 4000.0 P.Month 40000.0
donkeys for carrying earth)
5. Langri. (Cooks) 2.00 Nos: 4000.0 P.Month 8000.0
6. Chowkidars. 2.00 Nos: 4000.0 P.Month 8000.0
7. Dobashi(Men for supervision) 1.00 Nos: 4000.0 P.Month 4000.0
________________________________ _______ _______ ________ _______ ___________
TOTAL Rs: 112500.0
________________________________ _______ _______ ________ _______ ___________
Expenditure per day 84600/30 = Rs: 3750.00
________________________________ _______ _______ ________ _______ ___________
Expenditure per day Rs: 3750.00
________________________________ _______ _______ ________ _______ ___________
(b) Jamadari Commission for
supplying labour. 6.00 % 225.00
____ ________________________________ _______ _______ ________ _______ ___________
TOTAL Rs: 225.00
____ ________________________________ _______ _______ ________ _______ ___________
(c) Food etc: as under:-
(i) One seer Atta per man 28 Seer 35.00 Per Kilo. 890.91
daily for 28 men.
(ii) Kitchen expenses tea meat, 4 Nos: 400.00 P.Balcha 1600.00
milk,fuel,fat & spices etc:
(iii Lantern patromax lamp L.S 60.00 P.day 60.00
depriciation and Kerosine
oil consumption.
(iv) Kitchen utensils, cost of L.S 60.00 P.day 60.00
repair & replacement etc:
____ ________________________________ _______ _______ ________ _______ ___________
TOTAL Rs: 2610.91
____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 16/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ________________________________ _______ _______ ________ _______ ___________


(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
II 28 Nos: Donkeys work in 500 ft: Lead in 4-Balcha.7 Donkeys/Balcha.
________________________________ _______ _______ ________ _______ ___________
(i) Donkeys.

Average working life of 6.00 Yrs:


one donkey.

Average cost of one donkey. Rs: 10,000/-

Amount per day. (28 * 10000)/(6 * 365) = 958.90

(ii) Food etc: for 28 donkeys.


Bhoosa etc: 5 seers per 3.50 Mand 300.00 P.Mand 1050.00
day per donkey.

Grains 2 seers per day per 1.40 Mand 1000.00 P.Mand 1400.00
donkey.
________________________________ _______ _______ ________ _______ ___________
TOTAL Rs: 3408.90
____ ________________________________ _______ _______ ________ _______ ___________
III MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _______ _______ ________ _______ ___________
The following articles are
required.
(a) 4 Nos: of pick axes and 8 12.00 Nos: 4.00 Per day 48.00
Nos: of balchas, cost of
repairs and replacement.

(b) Sharpening expenses for 12.00 Nos: 4.00 Each 48.00


pick axes & balchas.

(c) Palana with namda complete 1.00 Nos: 61.00 Each 61.00
for one donkey Rs:240/-
Average life of 4 months
cost per day.
(d) Sacks daily consumption 7.00 Nos: 14.00 Each 98.00
repairs & replacement etc:
(e) Sutli consumption. L.S 50.00 Per day 50.00
____ ________________________________ _______ _______ ________ _______ ___________
TOTAL Rs: 305.00
____ ________________________________ _______ _______ ________ _______ ___________
IV Camp Equipment.
(a) 4 Nos: of tents are used
for labour of 4 balchas,
cost of one tent =Rs:4500/-
Average life of 1 year,
hence cost per day. 4 Nos: 36.99 Per day 147.95
(b) Donkey Hut expenditure. 1.00 Nos: 8.22 Per day 8.22
cost of Hut = Rs:1500/-
Average life of 6-Months,
hence cost per day.
____ ________________________________ _______ _______ ________ _______ ___________
TOTAL Rs: 156.16
____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 17/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ________________________________ _______ _______ ________ _______ ___________


MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _______ _______ ________ _______ ___________
V Medical Expenditure.
For 28 men and 28 Donkeys. 10.00 Each 560.00 Per day 560.00
10 *28*2=560
____ ________________________________ _______ _______ ________ _______ ___________
TOTAL 560.00
________________________________ _______ _______ ________ _______ ___________
Grand Total(I+II+III+IV+V) Rs: 11015.98
________________________________ _______ _______ ________ _______ ___________
TOTAL Rs: 11015.98
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 1101.60
________________________________ _______ _______ ________ _______ ___________
Grand Total Rs: 12117.58
____ ________________________________ _______ _______ ________ _______ ___________
Cost for 4 balchas comes to Rs: 12117.58
____ ________________________________ _______ _______ ________ _______ ___________
Cost for per balchas comes to Rs: 3029.39
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
8. Extra for every 50 ft: additional lead or a part there of.
(a) Earth work excavation in ashes sand soft soil or silt.

____ ________________________________ _______ _______ ________ _______ ___________


(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Cost for per balcha for lead of 500 ft: Rs: 3029.39
________________________________ _______ _______ ________ _______ ___________

Progress per balcha in


ashes, sand, soft soil or
silt = 1630 Cft.
Rate for 1000 cft & lead 1000 Cft. 1858.52 %0 Cft. 1858.52
500 ft: =1632.01*(1000/1630)

Rate for 1000 cft & lead 1000 Cft. 1119.25 %0 Cft. 1119.25
50 ft: As per Item No:2 P- 2 _______ _______ ________ _______ ___________

Difference for lead 450 ft: Rs: 739.27


________________________________ _______ _______ ________ _______ ___________
Rate for every 50' add: lead or part there of. Rs: 82.14
Say Rs: 82.14
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________


S/N D E S C R I P T I O N.
======================
8. Extra for every 50 ft: additional lead or a part there of.
(ii) Earth work excavation in ordinary soil.
____ ________________________________ _______ _______ ________ _______ ___________
Cost for per balcha for lead of 500 ft: Rs: 3029.39
________________________________ _______ _______ ________ _______ ___________
Progress per balcha in
ordinary soil = 1250 Cft.

Rate for 1000 cft & lead 1000 Cft. 2423.52 %0 Cft. 2423.52
500 ft: =1632.01*(1000/1250)

Rate for 1000 cft & lead 1000 Cft. 2420.00 %0 Cft. 2420.00
50 ft: As per Item No:5(a) _______ _______ ________ _______ ___________
Difference for lead 450 ft: Rs: 3.52
________________________________ _______ _______ ________ _______ ___________
Rate for every 50' add: lead or part there of. Rs: 0.39
Say Rs: 0.39
____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 18/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
8. Extra for every 50 ft: additional lead or a part there of.
(iii) Earth work excavation in Hard soil.
____ ________________________________ _______ _______ ________ _______ ___________
Cost for per balcha for lead of 500 ft: Rs: 3029.39
________________________________ _______ _______ ________ _______ ___________
Progress per balcha in
Hard soil = 1100 Cft.

Rate for 1000 cft & lead 1000 Cft. 2753.99 %0 Cft. 2753.99
500 ft: =1632.01*(1000/1100)

Rate for 1000 cft & lead 1000 Cft. 2904.00 %0 Cft. 2904.00
50 ft: As per Item No:5(b) _______ _______ ________ _______ ___________
Difference for lead 450 ft: Rs: -150.01
________________________________ _______ _______ ________ _______ ___________
Rate for every 50' add: lead or part there of. Rs: -16.67
Say Rs: -16.67
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
8. Extra for every 50 ft: additional lead or a part there of.
(iv) Earth work excavation in Very hard soil.
____ ________________________________ _______ _______ ________ _______ ___________
Cost for per balcha for lead of 500 ft: Rs: 3029.39
________________________________ _______ _______ ________ _______ ___________
Progress per balcha in
Hard soil = 980 Cft.
Rate for 1000 cft & lead 1000 Cft. 3091.22 %0 Cft. 3091.22
500 ft: =1632.01*(1000/980)
Rate for 1000 cft & lead 1000 Cft. 3418.25 %0 Cft. 3418.25
50 ft: As per Item No:5(c) _______ _______ ________ _______ ___________
Difference for lead 450 ft: Rs: -327.03
________________________________ _______ _______ ________ _______ ___________
Rate for every 50' add: lead or part there of. Rs: -36.34
Say Rs: -36.00
____ ________________________________ _______ _______ ________ _______ ___________
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
8. Extra for every 50 ft: additional lead or a part there of.
(a) Earth work excavation in soft, ordinary, hard and Very hard soil.
____ ________________________________ _______ _______ ________ _______ ___________
Extra lead for every 50 ft:
or part there of as per
detail above from(i)to (iv) 1000 Cft. -36.00 %0 Cft. -36.00
S/N D E S C R I P T I O N.
======================
8. Extra for every 50 ft: additional lead or a part there of.
(b) Earth work excavation in for gravel shingle or rock.
____ ________________________________ _______ _______ ________ _______ ___________
Extra labour required for
100 Cft.
The carraige of soil from
these formation over and
above. That required for
soil is 20%
Therefore rate for 0/00 cft 1000 Cft. -43.20 %0 Cft. -43.20
Note This rate shall apply to
lead upto half mile when
the lead is more than half
mile lead shall be paid as
carraige of material by
mechanical means.
____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 19/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================

9. Rehandling of earth work .

(a) Lead upto single throw of khassi, Phaorah or shovel.


____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies. 2.50 Nos: 250.00 P.Day 625.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 625.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 62.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 687.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 68.75
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 756.25
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 756.25

S/N D E S C R I P T I O N.
======================
9. Rehandling of earth work .

(b) Lead upto 50 ft:


____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies. 1.50 Nos: 250.00 P.Day 375.00

Coolies for carrying. 2.00 Nos: 250.00 P.Day 500.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 875.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 87.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 962.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 96.25
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 1058.75
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 1058.75
____ ________________________________ _______ _______ ________ _______ ___________
____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 20/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
10. Rehandling of gravel work on excavated rock lead upto 50 ft:

____ ________________________________ _______ _______ ________ _______ ___________


LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for filling and 4.00 Nos: 250.00 P.Day 1000.00
lifting.

Coolies for carrying. 6.00 Nos: 250.00 P.Day 1500.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 2500.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 250.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 2750.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 275.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 3025.00
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 3025.00
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
11. Dressing and levelling of earth work to designed section etc,
complete.

(a) Ashes and silt or soft soil.


____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Dresser earth work. 0.20 Nos: 250.00 P.Day 50.00

Cooly. 0.12 Nos: 250.00 P.Day 30.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 80.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 8.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 88.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 8.80

________________________________ _______ _______ ________ _______ ___________


TOTAL PART " A " 96.80
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 43.55
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 21/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
11. Dressing and levelling of earth work to designed section etc,
complete.

(b) Ordinary or hard soil.


____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Dresser earth work. 0.50 Nos: 250.00 P.Day 125.00

Cooly. 0.12 Nos: 250.00 P.Day 30.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 155.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 15.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 170.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 17.05
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 187.55
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 87.10
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________


S/N D E S C R I P T I O N.
======================
11. Dressing and levelling of earth work to designed section etc,
complete.

(c) Gravel work of soft rock not requiring blasting.


____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Quarry men for dressing. 1.00 Nos: 250.00 P.Day 250.00

Cooly. 0.50 Nos: 250.00 P.Day 125.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 375.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 37.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 412.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 41.25
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 453.75
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 453.75
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 22/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
12. Dowel dressing ( The rate is in addition to payment for dressed
earth work)

____ ________________________________ _______ _______ ________ _______ ___________


LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Dresser earth work. 0.25 Nos: 250.00 P.Day 62.50

Cooly. 0.10 Nos: 250.00 P.Day 25.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 87.50
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 8.75
________________________________ _______ _______ ________ _______ ___________
TOTAL 96.25
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 9.63
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 105.88
________________________________ _______ _______ ________ _______ ___________
Labour rate per chain. Rs: 105.88
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________


S/N D E S C R I P T I O N.
======================

13. Earth work compaction. (soft ordinary or hard soil)

(a) Laying earth in 6" layers levelling & dressing complete.

____ ________________________________ _______ _______ ________ _______ ___________


LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Cooly. 0.12 Nos: 250.00 P.Day 30.00

Dresser earth work. 0.75 Nos: 250.00 P.Day 187.50

________________________________ _______ _______ ________ _______ ___________


TOTAL 217.50
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 21.75
________________________________ _______ _______ ________ _______ ___________
TOTAL 239.25
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 23.93
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 263.18
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 263.00
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 23/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
13. Earth work compaction. (soft ordinary or hard soil)

(b) Laying earth in 6" layers levelling & dressing & watering for
compaction etc, complete.
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Cooly. 0.12 Nos: 250.00 P.Day 30.00

Bahishti. 0.30 Nos: 250.00 P.Day 75.00

Dresser earth work. 0.75 Nos: 250.00 P.Day 187.50

________________________________ _______ _______ ________ _______ ___________


TOTAL 292.50
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 29.25
________________________________ _______ _______ ________ _______ ___________
TOTAL 321.75
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 32.18
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 353.93
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 354.00
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
13. Earth work compaction.

(c) Compaction by rolling (This rate does not includes the hire
i charges of the roller) (1-soft or sandy soil)
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Bullock man with 1/2 pair 1.00 Nos: 400.00 P.Day 400.00
of bullock.

Cooly. 0.50 Nos: 250.00 P.Day 125.00

TOTAL 525.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 52.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 577.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 57.75
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 635.25
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 635.25
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 24/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
13. Earth work compaction.

(c) Compaction by rolling (This rate does not includes the hire
ii charges of the roller) (ii-Ordinary soil)
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Bullock man with 1/2 pair 1.25 Nos: 400.00 P.Day 500.00
of bullock.

Cooly. 0.50 Nos: 250.00 P.Day 125.00


________________________________ _______ _______ ________ _______ ___________
TOTAL 625.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 62.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 687.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 68.75
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 756.25
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 756.00
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________


S/N D E S C R I P T I O N.
======================
13. Earth work compaction.

(c) Compaction by rolling (This rate does not includes the hire
iii charges of the roller) (iii-Hard soil)
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Bullock man with 1/2 pair 1.25 Nos: 400.00 P.Day 500.00
of bullock.

Cooly. 0.75 Nos: 250.00 P.Day 187.50


________________________________ _______ _______ ________ _______ ___________
TOTAL 687.50
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 68.75
________________________________ _______ _______ ________ _______ ___________
TOTAL 756.25
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 75.63
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 831.88
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 832.00
____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 25/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
======================
13. Earth work compaction.

(c) Compaction by rolling (This rate does not includes the hire
charges of the roller) (iv-Admixture of shingle)
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Bullock man with 1/2 pair 1.50 Nos: 400.00 P.Day 600.00
of bullock.

Cooly. 0.75 Nos: 250.00 P.Day 187.50

________________________________ _______ _______ ________ _______ ___________


TOTAL 787.50
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 78.75
________________________________ _______ _______ ________ _______ ___________
TOTAL 866.25
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 86.63
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 952.88
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 952.88
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________


S/N D E S C R I P T I O N.
======================
13. Earth work compaction.

(d) Raming earth (all type of soil)

____ ________________________________ _______ _______ ________ _______ ___________


LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Cooly. 1.50 Nos: 250.00 P.Day 375.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 375.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 37.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 412.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 41.25
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 453.75
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 453.75
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 26/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
13. Earth work compaction.

(e) Ramming earth work behind retaining wall.

____ ________________________________ _______ _______ ________ _______ ___________


LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for watering and 2.00 Nos: 250.00 P.Day 500.00
ramming.

________________________________ _______ _______ ________ _______ ___________


TOTAL 500.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 50.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 550.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 55.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 605.00
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 605.00
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________


S/N D E S C R I P T I O N.
======================
14. Extra for puddling.

____ ________________________________ _______ _______ ________ _______ ___________


LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Bahishties. 1.50 Nos: 250.00 P.Day 375.00

Coolies. 4.75 Nos: 250.00 P.Day 1187.50


________________________________ _______ _______ ________ _______ ___________
TOTAL 1562.50
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 156.25
________________________________ _______ _______ ________ _______ ___________
TOTAL 1718.75
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 171.88
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 1890.63
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 1890.63

____ ________________________________ _______ _______ ________ _______ ___________


____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 27/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
15. Extra for wet earth work.
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging, 3.50 Nos: 250.00 P.Day 875.00
filling & lifting.
________________________________ _______ _______ ________ _______ ___________
TOTAL 875.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 87.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 962.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 96.25
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 1058.75
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 1058.75
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
16. Extra Labour for slush daldal including dewatering.

____ ________________________________ _______ _______ ________ _______ ___________


LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging, 8.00 Nos: 500.00 P.Day 4000.00
filling, lifting and
dewatering.
________________________________ _______ _______ ________ _______ ___________
TOTAL 4000.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 400.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 4400.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 440.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 4840.00
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 4840.00
Labour rate For per Cft. Rs: 4.84
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________


S/N D E S C R I P T I O N.
======================
17. Earth work on small rain water drains along canal banks, roads &
plantation drains dressed etc: complete.

____ ________________________________ _______ _______ ________ _______ ___________


LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging. 0.95 Nos: 250.00 P.Day 237.50
TOTAL 237.50
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 23.75
________________________________ _______ _______ ________ _______ ___________
TOTAL 261.25
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 26.13
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 287.38
________________________________ _______ _______ ________ _______ ___________
Labour rate per 100 Lft. Rs: 287.38

S/N D E S C R I P T I O N.

Chapter No. 1 28/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
======================
18. Excavation in foundation of building and bridges and other
structures including dagbelling, dressing filling around
structure with excavated earth watering & ramming lead upto one
chain and lift upto 5 ft:

(a) In sand, ashes or loose soil.


____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies. 5.00 Nos: 250.00 P.Day 1250.00

Coolies for carrying earth. 3.00 Nos: 250.00 P.Day 750.00

Dresser for dressing. 1.00 Nos: 250.00 P.Day 250.00


________________________________ _______ _______ ________ _______ ___________
TOTAL 2250.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 225.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 2475.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 247.50
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 2722.50
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 2722.50
____ ________________________________ _______ _______ ________ _______ ___________
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
18. Excavation in foundation of building and bridges and other
structures including dagbelling, dressing filling around
structure with excavated earth watering & ramming lead upto one
chain and lift upto 5 ft:
(b) In ordinary soil.
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging. 6.00 Nos: 250.00 P.Day 1500.00
Coolies for carrying earth. 3.00 Nos: 250.00 P.Day 750.00
Dresser for dressing. 1.50 Nos: 250.00 P.Day 375.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 2625.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 262.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 2887.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 288.75
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 3176.25
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 3176.25
____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 29/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
======================
18. Excavation in foundation of building and bridges and other
structures including dagbelling, dressing filling around
structure with excavated earth watering & ramming lead upto one
chain and lift upto 5 ft:
(c) In hard soil or soft moorum.
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Coolies for digging. 7.00 Nos: 250.00 P.Day 1750.00
Coolies for carrying earth. 3.00 Nos: 250.00 P.Day 750.00
Dresser for dressing. 1.75 Nos: 250.00 P.Day 437.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 2937.50
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 293.75
________________________________ _______ _______ ________ _______ ___________
TOTAL 3231.25
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 323.13
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 3554.38
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 3554.38
S/N D E S C R I P T I O N.

19. Cutting hard rock such as granite, ballast, hard lime stone or
sand stone etc: with chisels & hammers for small foundations.
(Unit of rate per 1000 Cft.)
____ ________________________________ _______ _______ ________ _______ ___________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _______ _______ ________ _______ ___________
Steel. 50.00 Lbs. 32.21 P.Lb 1610.50

Charcoal. 6.0 Mand 675.00 P.Mand. 4050.00


________________________________ _______ _______ ________ _______ ___________
TOTAL 5660.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 566.05
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 6226.55
________________________________ _______ _______ ________ _______ ___________
(B) LABOUR
________________________________ _______ _______ ________ _______ ___________
Hammer man. 28.00 Nos: 250.00 P.day 7000.00
4 Nos: for 7 days.

Skilled coolies. 28.00 Nos: 250.00 P.day 7000.00


4 Nos: for 7 days.

Black smith. 7.00 Nos: 400.00 P.day 2800.00


1 No: for 7 days.

Cooly for carrying. 7.00 Nos: 250.00 P.day 1750.00


1 No: for 7 days.
________________________________ _______ _______ ________ _______ ___________
18550.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 1855.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 20405.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 2040.50
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " B " Rs: 22445.50
________________________________ _______ _______ ________ _______ ___________
TOTAL (MATERIAL + LABOUR) Rs: 28672.05
________________________________ _______ _______ ________ _______ ___________
Total Rate Material and Labour for 1000 Cft. Rs: 28672.05

Chapter No. 1 30/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
20. Extra for excavation requiring shoring.
(Unit of rate per 1000 Cft.)
____ ________________________________ _______ _______ ________ _______ ___________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _______ _______ ________ _______ ___________
Wood for shoring. L.S 140.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 140.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 14.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 154.00
________________________________ _______ _______ ________ _______ ___________
(B) LABOUR
________________________________ _______ _______ ________ _______ ___________
Cooly. 1.00 Nos: 250.00 P.day 250.00
Carpentor. 0.25 Nos: 400.00 P.day 100.00
________________________________ _______ _______ ________ _______ ___________
350.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 35.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 385.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 38.50
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " B " Rs: 423.50
________________________________ _______ _______ ________ _______ ___________
TOTAL (MATERIAL + LABOUR) Rs: 577.50
________________________________ _______ _______ ________ _______ ___________
Total Rate Material and Labour for 1000 Cft. Rs: 356.70
____ ________________________________ _______ _______ ________ _______ ___________
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
21. Filling watering & ramming earth in floor with surplus earth
from foundation lead upto one chain and lift upto 5 ft:
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for ramming. 1.50 Nos: 250.00 P.Day 375.00
Coolies for carrying earth. 2.00 Nos: 250.00 P.Day 500.00
Dresser for earth work. 1.00 Nos: 250.00 P.Day 250.00
Bahishti. 0.50 Nos: 250.00 P.Day 125.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 1250.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 125.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 1375.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 137.50
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 1512.50
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 1512.50
____ ________________________________ _______ _______ ________ _______ ___________
____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 31/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
22. Filling watering & ramming earth under floor with new earth
excavated from outside lead upto one chain & lift upto 5 ft:
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Diggers. 5.00 Nos: 250.00 P.Day 1250.00
Coolies for carrying earth. 4.00 Nos: 250.00 P.Day 1000.00
Dresser for earth work. 1.00 Nos: 250.00 P.Day 250.00
Rammers. 1.50 Nos: 250.00 P.Day 375.00
Bahishti. 0.50 Nos: 250.00 P.Day 125.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 3000.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 300.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 3300.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 330.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 3630.00
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 3630.00
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________


S/N D E S C R I P T I O N.
======================
23. Filling & compacting earth & boulders behind retaining walls
(including excavation of soil) and lead upto 50 ft:
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for filling. 7.00 Nos: 250.00 P.Day 1750.00

Coolies for watering and 2.00 Nos: 250.00 P.Day 500.00


compacting.
________________________________ _______ _______ ________ _______ ___________
TOTAL 2250.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 225.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 2475.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 247.50
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 2722.50
________________________________ _______ _______ ________ _______ ___________
Labour rate per 1000 Cft. Rs: 2722.00
____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 32/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
24. Dressing slopes of banks or ground surface ( to be paid only
when exclusively dressing is done and no earth work is carried
out in embankment or cutting)
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Dressers for earth work. 1.25 Nos: 250.00 P.Day 312.50

________________________________ _______ _______ ________ _______ ___________


TOTAL 312.50
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 31.25
________________________________ _______ _______ ________ _______ ___________
TOTAL 343.75
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 34.38
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " 378.13
________________________________ _______ _______ ________ _______ ___________
Labour rate per 100 Sft. Rs: 378.13
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________


S/N D E S C R I P T I O N.
======================
25. Dagbelling 3" deep.

____ ________________________________ _______ _______ ________ _______ ___________


LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Dressers for earth work. 1.40 Nos: 250.00 P.Day 350.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 350.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 35.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 385.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 38.50
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 423.50
________________________________ _______ _______ ________ _______ ___________
Progress per day = 2500 Rft. Rs: 423.50
Labour rate for 1 Mile =5000*203.28/2500= Rs: 847
________________________________ _______ _______ ________ _______ ___________
Labour rate for 1 Mile Rs: 406.55
____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 33/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
26. Dagbelling 9" wide and 6" deep in all type of soil except in
rocks (for RLY).
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Cooly. 0.25 Nos: 250.00 P.Day 62.50

________________________________ _______ _______ ________ _______ ___________


TOTAL 62.50
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 6.25
________________________________ _______ _______ ________ _______ ___________
TOTAL 68.75
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 6.88
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 75.63
________________________________ _______ _______ ________ _______ ___________
Progress per day = 100 Rft. Rs: 75.63
________________________________ _______ _______ ________ _______ ___________
Labour rate for 100 Rft. Rs: 75.63
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________


S/N D E S C R I P T I O N.
======================
27. Turfing slopes of banks or lawns with grass side including
ploughing laying setting and watering.(Turf got from within a
distance of 5 miles and maintenance for 15 days.
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging seeds. 0.50 Nos: 250.00 P.Day 125.00

Cooly for carraige lead 5 1.00 Nos: 250.00 P.Day 250.00


miles.
Cooly for laying seeds and 1.00 Nos: 250.00 P.Day 250.00
watering.
Cooly for watering. 1.50 Nos: 250.00 P.Day 375.00
0.10 No: for 15 days.
________________________________ _______ _______ ________ _______ ___________
TOTAL 1000.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 100.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 1100.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 110.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 1210.00
________________________________ _______ _______ ________ _______ ___________
Labour rate for 100 Sft. Rs: 1210.00
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 34/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
28. Berm cutting.
(a) Lead upto single throw of khassi, Phaora or shovel.

____ ________________________________ _______ _______ ________ _______ ___________


LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Same as per item No:(1.B)
p-1
Labour rate 1000 cft. 1000 Cft. 1361.25 %0 Cft. 1361.25
________________________________ _______ _______ ________ _______ ___________
TOTAL 1361.25
________________________________ _______ _______ ________ _______ ___________
Labour rate for 1000 Cft. Rs: 1361.25
____ ________________________________ _______ _______ ________ _______ ___________
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
28. Berm cutting.
(b) Lead upto 50 ft:
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Same as per item No:5(a)
p-5
Labour rate 1000 cft. 1000 Cft. 2420.00 %0 Cft. 2420.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 2420.00
________________________________ _______ _______ ________ _______ ___________
Labour rate for 1000 Cft. Rs: 2420.00
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
29. Berm trimming both sides.
(a) Canal upto 3.50 ft: depth.
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Dressers earth work for 2.00 Nos: 250.00 P.Day 500.00
dagbelling & dressing.
Coolies for trimming etc: 12.00 Nos: 250.00 P.Day 3000.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 3500.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 350.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 3850.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 385.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 4235.00
________________________________ _______ _______ ________ _______ ___________
Labour rate for one Mile. Rs: 4235.00
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 35/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
29. Berm trimming both sides.
(b) Channel from 3.50 ft: to 5 ft: depth.
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Dressers earth work for 3.00 Nos: 250.00 P.Day 750.00
dagbelling & dressing.
Coolies for trimming etc: 15.50 Nos: 250.00 P.Day 3875.00

Mate earth work for 1.00 Nos: 250.00 P.Day 250.00


supervision.
________________________________ _______ _______ ________ _______ ___________
TOTAL 4875.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 487.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 5362.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 536.25
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 5898.75
________________________________ _______ _______ ________ _______ ___________
Labour rate for one Mile. Rs: 5898.75
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
29. Berm trimming both sides.
(c) Channel from 5.0 ft: to 8.0 ft: depth.
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Dressers earth work for 4.00 Nos: 250.00 P.Day 1000.00
dagbelling & dressing.
Coolies for trimming etc: 25.50 Nos: 250.00 P.Day 6375.00

Mate earth work for 1.00 Nos: 250.00 P.Day 250.00


supervision.
________________________________ _______ _______ ________ _______ ___________
TOTAL 7625.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 762.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 8387.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 838.75
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 9226.25
________________________________ _______ _______ ________ _______ ___________
Labour rate for one Mile. Rs: 9226.25
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 36/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
30. Ploughing & levelling barrow pits ( area to be measured).

____ ________________________________ _______ _______ ________ _______ ___________


LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Bullockmen with a pair of 2.00 Nos: 500.00 P.Day 1000.00
bullock.
Coolies for levelling. 2.00 Nos: 250.00 P.Day 500.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 1500.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 150.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 1650.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 165.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 3465.00
________________________________ _______ _______ ________ _______ ___________
Labour rate for one acre. Rs: 3465.00
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
31 Making Boundary or service roads i/c dagbelling in un ploughed
land. (Extra Rs:2.00 may be paid for ploughed land)
(a) From 10 ft: to 20 ft: wide.
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Earh work dresser. 0.50 Nos: 250.00 P.Day 125.00

Cooly. 1.00 Nos: 250.00 P.Day 250.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 375.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 37.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 412.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 41.25
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 453.75
________________________________ _______ _______ ________ _______ ___________
Labour rate for one chain. Rs: 453.75
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 37/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
31 Making Boundary or service roads i/c dagbelling in un ploughed
land. (Extra Rs:2.00 may be paid for ploughed land)
(b) From 21 ft: to 40 ft: wide.
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Earh work dresser. 1.00 Nos: 250.00 P.Day 250.00

Cooly. 1.00 Nos: 250.00 P.Day 250.00

________________________________ _______ _______ ________ _______ ___________


TOTAL 500.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 50.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 550.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 55.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 605.00
________________________________ _______ _______ ________ _______ ___________
Labour rate for one chain. Rs: 605.00
Note:-Extra Rs:2.00 may be paid for ploughed land.

____ ________________________________ _______ _______ ________ _______ ___________


S/N D E S C R I P T I O N.
======================
32. Earth work by boat i/c hire of boat.(for ordinary soil)
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging filling 4.00 Nos: 250.00 P.Day 1000.00
in baskets & lifting.
Coolies for carrying and 3.50 Nos: 250.00 P.Day 875.00
loading in boat.
________________________________ _______ _______ ________ _______ ___________
TOTAL 1875.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 187.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 2062.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 206.25
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 2268.75
________________________________ _______ _______ ________ _______ ___________
Labour rate for 1000 cft. Rs: 2268.75
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 38/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
(b) Carraige by boat upto 10 chains. Labour rate for 1000 cft.
(Capacity of boat is 200 cft 15 trips in a day/ rate for one
trip.)
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Boat man with large boat 0.07 Nos: 500 P.day 35.00
per trip. (15 trips in a
day)
8 Nos: extra boatman. 0.533 Nos: 250 P.day 133.25
________________________________ _______ _______ ________ _______ ___________
TOTAL 168.25
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 16.83
________________________________ _______ _______ ________ _______ ___________
TOTAL 185.08
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 18.51
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 203.58
________________________________ _______ _______ ________ _______ ___________
Labour rate for 1000 cft per trip. Rs: 203.58
Labour rate for 1000 cft 5 trips. Rs: 1017.91
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
(c) Extra for distance beyond 10 chains.

____ ________________________________ _______ _______ ________ _______ ___________


LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Extra Boat-man required for
one chain lead.
Extra boat-man. 0.2 Nos: 250 P.day 50.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 50.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 5.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 55.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 5.50
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 60.50
________________________________ _______ _______ ________ _______ ___________
Labour rate for 1000 cft for extra each chain. Rs: 29.05
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 39/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
======================
(d) Unloading earth from boat.

____ ________________________________ _______ _______ ________ _______ ___________


LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________

Coolies. 3.5 Nos: 250 P.day 875.00


________________________________ _______ _______ ________ _______ ___________
TOTAL 875.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 87.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 962.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 96.25
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 1058.75
________________________________ _______ _______ ________ _______ ___________
Labour rate for 1000 cft. Rs: 1058.75
____ ________________________________ _______ _______ ________ _______ ___________
S/N D E S C R I P T I O N.
======================
33. Unloading earth from B.G. trucks & clearing 5 ft: from rail.

____ ________________________________ _______ _______ ________ _______ ___________


LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for un loading & 3 Nos: 250 P.day 750.00
clearing 5' from rail.

________________________________ _______ _______ ________ _______ ___________


TOTAL 750.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 75.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 825.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 82.50
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 907.50
________________________________ _______ _______ ________ _______ ___________
Labour rate for 1000 cft. Rs: 907.50
____ ________________________________ _______ _______ ________ _______ ___________

____ ________________________________ _______ _______ ________ _______ ___________


S/N D E S C R I P T I O N.
======================
34. Earth work by trumways digging & leading of truck with 50 ft:
lead.
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for digging and 7.00 Nos: 250 P.day 1750.00
loading.

________________________________ _______ _______ ________ _______ ___________


TOTAL 1750.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 175.00
________________________________ _______ _______ ________ _______ ___________
TOTAL 1925.00
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 192.50
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 2117.50
________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 40/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
Labour rate for 1000 cft. Rs: 2117.50
S/N D E S C R I P T I O N.
======================
35. Unloading earth from B.G. trucks & spreading upto 15 ft: from
rail.
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for unloading. 2.50 Nos: 250 P.day 625.00

Coolies for spreading. 2.00 Nos: 250 P.day 500.00


________________________________ _______ _______ ________ _______ ___________
TOTAL 1125.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 112.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 1237.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 123.75
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 1361.25
________________________________ _______ _______ ________ _______ ___________
Labour rate for 1000 cft. Rs: 1361.25
S/N D E S C R I P T I O N.
======================
36. Supply of clean screened pit sand of river with in 5 chains i/c
removal of top crest of earth or over burden & royality to the
government or cost to the private owner.
____ ________________________________ _______ _______ ________ _______ ___________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ________________________________ _______ _______ ________ _______ ___________
Coolies for excavation of 0.50 Nos: 250 P.day 125.00
sand and removal of top
earth loading & cleaning
etc:
________________________________ _______ _______ ________ _______ ___________
TOTAL 125.00
________________________________ _______ _______ ________ _______ ___________
Sundries. 10.00 % 12.50
________________________________ _______ _______ ________ _______ ___________
TOTAL 137.50
________________________________ _______ _______ ________ _______ ___________
Contractor's profit 10.00 % 13.75
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " A " Rs: 151.25
________________________________ _______ _______ ________ _______ ___________
Carraige of 1st chain. Rs: 52.30
Carraige of 2nd chain. Rs: 9.65
Carraige of 3rd chain. Rs: 7.25
Carraige of 4th chain. Rs: 7.25
Carraige of 5th chain. Rs: 7.25
________________________________ _______ _______ ________ _______ ___________
TOTAL Rs: 83.70
________________________________ _______ _______ ________ _______ ___________
Royalty. L.S Rs: 20.00
________________________________ _______ _______ ________ _______ ___________
TOTAL PART " B " Rs: 103.70
________________________________ _______ _______ ________ _______ ___________
Total Rate Material and Labour for 100 cft. Rs: 254.95
Total Rate Material and Labour for 100 cft. Rs: 254.95
____ ________________________________ _______ _______ ________ _______ ___________

Chapter No. 1 41/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

DISMANTLING.
FIRST FILL THIS SHEET.
Labour.

1 Cooly 250 P.day

2 Skilled Cooly 250 P. day

3 Fitter, Carpenter 400 P. day


black Smith, Masson.

Chapter No. 2 42/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

The rates includes removal of dismantled material with in one chain.

Note:- (1) Rate for all finished works include the removal of surplus
debris, unused material and by-products.

(2) For handling of all types of materials for a short leads


including carraige upto 3 chains nothing is to be paid as
extra where handling and carraige involves and extra lead
beyond 3-chains, carraige for whole of the distance should
be paid.

(3) The rates for dismantling roofs or upper storey floors


include the dismantling of all materials, except roof
supports such as beams and trusses.
____ ______________________________ ______ _____ ______ ________ _________
S/N D E S C R I P T I O N.
1. Dismantling dry stone masonry.
(Unit of rate one hundred Cft.)
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Skilled Cooly. 0.85 Nos: 250.00 P.Day 212.50
Sundries. 10.00 % 21.25
TOTAL 233.75
Contractor's profit 10.00 % 23.38
TOTAL PART " A " 257.13
Labour rate per 100 Cft. Rs: 257.00
S/N D E S C R I P T I O N.
2. Dismantling stone masonry in mud morter.
(Unit of rate one hundred Cft.)
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Skilled Cooly. 1.25 Nos: 250.00 P.Day 312.50
Sundries. 10.00 % 31.25
TOTAL 343.75
Contractor's profit 10.00 % 34.38
TOTAL PART " A " 378.13
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 378.13

Chapter No. 2 43/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ _________

Chapter No. 2 44/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.

Dismantling stone masonry in lime or cement.


____ (Unit of rate one hundred Cft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
3. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Cooly. 3 Nos: 250.00 P.Day 750.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 75.00
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 825.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 82.50
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 907.50
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 907.50
______________________________ ______ _____ ______ ________ _________
D E S C R I P T I O N.
Dismantling dry stone (Spawls) pitching.
(Unit of rate one hundred Cft.)
____ ______________________________ ______ _____ ______ ________ _________
S/N LABOUR QUANTITY RATE UNIT AMOUNT
4(a Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ SkilledCooly. 1.5 Nos: 250.00 P.Day 375.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 37.50
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 412.50
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 41.25
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 453.75
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 453.75

Chapter No. 2 45/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ _________


______________________________ ______ _____ ______ ________ _________
D E S C R I P T I O N.
Dismantling stone or spawl pitching (mud grouted)
____ (Unit of rate one hundred Cft.)
____ ______________________________ ______ _____ ______ ________ _________
S/N LABOUR QUANTITY RATE UNIT AMOUNT
4(b) Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Cooly. 1.9 Nos: 250.00 P.Day 475.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 47.50
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 522.50
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 52.25
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 574.75
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 575.00
______________________________ ______ _____ ______ ________ _________
D E S C R I P T I O N.
Dismantling stone(Spawls)pitching and apron in silted condition.
(Unit of rate one hundred Cft.)
____ ______________________________ ______ _____ ______ ________ _________
S/N LABOUR QUANTITY RATE UNIT AMOUNT
5. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Cooly. 2.5 Nos: 250.00 P.Day 625.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 62.50
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 687.50
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 68.75
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 756.25
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 756.25

Chapter No. 2 46/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.
Dismantling stone or spawl pitching cement or lime grouted.
(Unit of rate one hundred Cft.)
______________________________ ______ _____ ______ ________ _________
S/N LABOUR QUANTITY RATE UNIT AMOUNT
6. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Cooly. 4 Nos: 250.00 P.Day 1000.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 100.00
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 1100.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 110.00
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 1210.00
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 1210.00
______________________________ ______ _____ ______ ________ _________
______________________________ ______ _____ ______ ________ _________
D E S C R I P T I O N.
Dismantling stone in crates.
____ (Unit of rate one hundred Cft.)
____ ______________________________ ______ _____ ______ ________ _________
S/N LABOUR QUANTITY RATE UNIT AMOUNT
7. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Cooly. 2 Nos: 250.00 P.Day 500.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 50.00
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 550.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 55.00
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 605.00
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 605.00

______________________________ ______ _____ ______ ________ _________

Chapter No. 2 47/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.
Dismantling stone in wire crates.
____ (Unit of rate one hundred Cft.)
______________________________ ______ _____ ______ ________ _________
S/N LABOUR QUANTITY RATE UNIT AMOUNT
7(b) Rs: Rs:
____ Skilled Cooly. 2.5 Nos: 250.00 P.Day 625.00
Sundries. 10.00 % 62.50
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 687.50
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 68.75
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 756.25
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 756.25
D E S C R I P T I O N.
Dismantling stone ware drain including base concrete.
(Unit of rate one hundred Cft.)
______________________________ ______ _____ ______ ________ _________
S/N LABOUR QUANTITY RATE UNIT AMOUNT
8. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Coolies skilled. 1.4 Nos: 250.00 P.Day 350.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 35.00
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 385.00
Contractor's profit 10.00 % 38.50
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 423.50
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 203.30
______________________________ ______ _____ ______ ________ _________
D E S C R I P T I O N.
Brick Work.
Dismantling mud/pise walling. (Unit of rate one hundred Cft.)
____ ______________________________ ______ _____ ______ ________ _________
S/N LABOUR QUANTITY RATE UNIT AMOUNT
9. Rs: Rs:
____ Skilled Coolies. 0.5 Nos: 250.00 P.Day 125.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 12.50
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 137.50
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 13.75
TOTAL PART " A " 151.25

Chapter No. 2 48/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Labour rate per 100 Cft. Rs: 151.25

Chapter No. 2 49/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.

____ Dismantling sun dried brick masonary.


____ (Unit of rate one hundred Cft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
10. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Coolies. 1.25 Nos: 250.00 P.Day 312.50
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 31.25
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 343.75
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 34.38
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 378.13
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 378.13
D E S C R I P T I O N.

Dismantling dry brick masonary.


(Unit of rate one hundred Cft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
11. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Coolies. 0.85 Nos: 250.00 P.Day 212.50
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 21.25
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 233.75
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 23.38
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 257.13
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 257.13

Chapter No. 2 50/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ _________

Chapter No. 2 51/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.

Dismantling brick work in mud morter.


____ (Unit of rate one hundred Cft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
12. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Coolies. 1.75 Nos: 250.00 P.Day 437.50
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 43.75
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 481.25
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 48.13
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 529.38
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 529.38
______________________________ ______ _____ ______ ________ _________
D E S C R I P T I O N.

Dismantling brick work in lime or cement morter.


____ (Unit of rate one hundred Cft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
13. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Coolies. 4.25 Nos: 250.00 P.Day 1062.50
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 106.25
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 1168.75
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 116.88
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 1285.63
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 1285.63

Chapter No. 2 52/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.

Dismantling cement block masonary.


(Unit of rate one hundred Cft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
14. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Coolies. 3.75 Nos: 250.00 P.Day 937.50
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 93.75
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 1031.25
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 103.13
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 1134.38
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 1134.38
______________________________ ______ _____ ______ ________ _________
D E S C R I P T I O N.

Dismantling Dhajji walling.


____ (Unit of rate one hundred Sft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
15. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ SkilledCoolies. 1 Nos: 250.00 P.Day 250.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 25.00
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 275.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 27.50
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 302.50
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Sft. Rs: 302.50

Chapter No. 2 53/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ _________

Chapter No. 2 54/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.

Dismantling mud concrete.


____ (Unit of rate one hundred Cft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
16. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ SkilledCoolies. 2 Nos: 250.00 P.Day 500.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 50.00
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 550.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 55.00
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 605.00
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 605.00

D E S C R I P T I O N.

Dismantling lime concrete.


(Unit of rate one hundred Cft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
17. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ SkilledCoolies. 2.75 Nos: 250.00 P.Day 687.50
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 68.75
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 756.25
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 75.63
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 831.88
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 831.88

Chapter No. 2 55/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ _________


D E S C R I P T I O N.

Dismantling lime or cement concrete under water.


____ (Unit of rate one hundred Cft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
18. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ SkilledCoolies. 10.5 Nos: 250.00 P.Day 2625.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 262.50
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 2887.50
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 288.75
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 3176.25
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 3176.25
______________________________ ______ _____ ______ ________ _________
D E S C R I P T I O N.

Dismantling cement concrete plain 1:2:4.


____ (Unit of rate one hundred Cft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
19. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ SkilledCoolies. 5.5 Nos: 250.00 P.Day 1375.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 137.50
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 1512.50
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 151.25
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 1663.75
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 1663.75

Chapter No. 2 56/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.
Dismantling cement concrete plain 1:3:6.
(Unit of rate one hundred Cft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
19(b Rs: Rs:
____ Coolies. 9 Nos: 120.00 P.Day 1080.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 108.00
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 1188.00
Contractor's profit 10.00 % 118.80
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 1306.80
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 1306.80
______________________________ ______ _____ ______ ________ _________
D E S C R I P T I O N.

Dismantling cement concrete plain 1:2:4.


____ (Unit of rate one hundred Cft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
19(c Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ SkilledCoolies. 11 Nos: 250.00 P.Day 2750.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 275.00
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 3025.00
Contractor's profit 10.00 % 302.50
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 3327.50
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 3327.50
D E S C R I P T I O N.
Dismantling cement concrete with brick aggregate.
(Unit of rate one hundred Cft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
19(d Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Coolies. 3.00 Nos: 250.00 P.Day 750.00
Sundries. 10.00 % 75.00
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 825.00
Contractor's profit 10.00 % 82.50
TOTAL PART " A " 907.50

Chapter No. 2 57/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Labour rate per 100 Cft. Rs: 907.50

Chapter No. 2 58/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.

Dismantling D.P.C. of cement concrete 1-1/2" thick and clearing


the site etc: (Unit of rate one hundred Cft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
19(e Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ SkilledCoolies. 1.50 Nos: 250.00 P.Day 375.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 37.50
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 412.50
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 41.25
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 453.75
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 453.75
______________________________ ______ _____ ______ ________ _________
D E S C R I P T I O N.
Dismantling cement concrete reinforced seperating reinforcement
from concrete cleaning and straightening the same.
____ (Unit of rate one hundred Cft.)
S/N ______________________________ ______ _____ ______ ________ _________
20. LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ SkilledCoolies. 18.00 Nos: 250.00 P.Day 4500.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 450.00
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 4950.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 495.00
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 5445.00
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Cft. Rs: 5445.00

Chapter No. 2 59/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.
ROOFING.
Dismantling sirki sarkanda or thatched roofing supported on
____ battens or ballies. (Unit of rate one hundred Sft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
21. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Coolies. 0.60 Nos: 250.00 P.Day 150.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 15.00
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 165.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 16.50
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 181.50
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Sft. Rs: 817.10

D E S C R I P T I O N.
ROOFING.
Dismantling Ist class tile roofing.
(Unit of rate one hundred Sft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
22(a Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Coolies. 1.50 Nos: 250.00 P.Day 375.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 37.50
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 412.50
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 41.25
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 453.75
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Sft. Rs: 453.75

Chapter No. 2 60/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ _________


D E S C R I P T I O N.
ROOFING.
Dismantling 2nd class tile roofing.
____ (Unit of rate one hundred Sft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
22(b Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Coolies. 1.25 Nos: 250.00 P.Day 312.50
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 31.25
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 343.75
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 34.38
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 378.13
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Sft. Rs: 378.13
______________________________ ______ _____ ______ ________ _________
D E S C R I P T I O N.

Dismantling from any hieght asbestos sheets and ridge coping.


____ (Unit of rate one hundred Sft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
23. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Fitter. 0.25 Nos: 400.00 P.Day 100.00

Skilled Coolies. 0.50 Nos: P.Day


250.00 125.00
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 225.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 22.50
______________________________ ______ _____ ______ ________ _________
TOTAL 247.50
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 24.75
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 272.25
______________________________ ______ _____ ______ ________ _________

Chapter No. 2 61/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Labour rate per 100 Sft. Rs: 272.25

Chapter No. 2 62/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.
Dismantling roof of wooden planks and battens upto any hieght.

S/N (Unit of rate one hundred Sft.)


______________________________ ______ _____ ______ ________ _________
24(a LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Carpentar. 0.20 Nos: 400.00 P.Day 80.00

Skilled Coolies. 0.20 Nos: 250.00 P.Day 50.00


____ ______________________________ ______ _____ ______ ________ _________
TOTAL 130.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 13.00
______________________________ ______ _____ ______ ________ _________
TOTAL 143.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 14.30
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 157.30
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Sft. Rs: 157.00
______________________________ ______ _____ ______ ________ _________
D E S C R I P T I O N.
____
Dismantling wooden cieling above 20' hieght in difficult
____ position i/c lifting with care and special scafolding along with
S/N electric wires and with machines under neath.
(Unit of rate one hundred Sft.)
24(b ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Carpentar. 0.60 Nos: 400.00 P.Day 240.00

Skilled Coolies. 1.80 Nos: P.Day


250.00 450.00
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 690.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 69.00
TOTAL 759.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 75.90
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 834.90
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Sft. Rs: 834.90

Chapter No. 2 63/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.

Dismantling jack arch roofing i/c removal of joists.


____
S/N (Unit of rate one hundred Sft.)
______________________________ ______ _____ ______ ________ _________
25. LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Coolies. 2.00 Nos: 250.00 P.Day 500.00
______________________________ ______ _____ ______ ________ _________
TOTAL 500.00
____ ______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 50.00
______________________________ ______ _____ ______ ________ _________
TOTAL 550.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 55.00
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 605.00
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Sft. Rs: 605.00
______________________________ ______ _____ ______ ________ _________

______________________________ ______ _____ ______ ________ _________


D E S C R I P T I O N.
____
Dismantling R.B. roof complete with mud & mud plaster i/c
____ separating reinforcement cleaning and straightening.
S/N (Unit of rate one hundred Sft.)
______________________________ ______ _____ ______ ________ _________
26. LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Coolies. 2.50 Nos: 250.00 P.Day 625.00
______________________________ ______ _____ ______ ________ _________
TOTAL 625.00
____ ______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 62.50
______________________________ ______ _____ ______ ________ _________
TOTAL 687.50
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 68.75
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 756.25
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Sft. Rs: 756.25

Chapter No. 2 64/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ D E S C R I P T I O N.

Dismantling full or half sleeper roof.


____
S/N (Unit of rate one hundred Sft.)
______________________________ ______ _____ ______ ________ _________
27. LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Coolies. 1.00 Nos: 250.00 P.Day 250.00
______________________________ ______ _____ ______ ________ _________
TOTAL 250.00
____ ______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 25.00
______________________________ ______ _____ ______ ________ _________
TOTAL 275.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 27.50
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 302.50
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Sft. Rs: 302.50
______________________________ ______ _____ ______ ________ _________

______________________________ ______ _____ ______ ________ _________


D E S C R I P T I O N.
____
Stripping and stackings slates or tiles from the truss roofing.
____
S/N (Unit of rate one hundred Sft.)
______________________________ ______ _____ ______ ________ _________
28(a LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled coolies. 1.50 Nos: 250.00 P.Day 375.00
______________________________ ______ _____ ______ ________ _________
TOTAL 375.00
____ ______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 37.50
______________________________ ______ _____ ______ ________ _________
TOTAL 412.50
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 41.25
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 453.75
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Sft. Rs: 453.75

Chapter No. 2 65/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.

Stripping and stackings C.I sheet roof.


____
S/N (Unit of rate one hundred Sft.)
______________________________ ______ _____ ______ ________ _________
28(b LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Fitter. 0.12 Nos: 400.00 P.Day 48.00

Skilled Coolies. 1.00 Nos: 250.00 P.Day 250.00


____ ______________________________ ______ _____ ______ ________ _________
TOTAL 298.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 29.80
______________________________ ______ _____ ______ ________ _________
TOTAL 327.80
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 32.78
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 360.58
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Sft. Rs: 360.58
______________________________ ______ _____ ______ ________ _________
D E S C R I P T I O N.
____
Extra for dismantling C.I sheet roof above 20' hieght in
____ difficult position including lifting with special scafolding
S/N along live electric wire with machine under neath.

28(c (Unit of rate one hundred Sft.)


______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Black smith 1.00 Nos: 400.00 P.Day 400.00

Skilled Coolies. 0.25 Nos: 250.00P.Day 62.50


____ ______________________________ ______ _____ ______ ________ _________
TOTAL 462.50
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 46.25
______________________________ ______ _____ ______ ________ _________
TOTAL 508.75
Contractor's profit 10.00 % 50.88
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 559.63

Chapter No. 2 66/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Labour rate per 100 Sft. Rs: 559.63

Chapter No. 2 67/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.
____
Dismantling slates or tiles including battens purlins and
____ planking.
S/N (Unit of rate one hundred Sft.)
______________________________ ______ _____ ______ ________ _________
29. LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Coolies. 2.00 Nos: 250.00 P.Day 500.00
______________________________ ______ _____ ______ ________ _________
TOTAL 500.00
____ ______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 50.00
______________________________ ______ _____ ______ ________ _________
TOTAL 550.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 55.00
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 605.00
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Sft. Rs: 605.00
______________________________ ______ _____ ______ ________ _________

______________________________ ______ _____ ______ ________ _________


D E S C R I P T I O N.
____
Dismantling brick or flagged flooring without concrete
____ foundation.
S/N
(Unit of rate one hundred Sft.)
30. ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Coolies. 0.85 Nos: 250.00 P.Day 212.50
______________________________ ______ _____ ______ ________ _________
TOTAL 212.50
____ ______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 21.25
______________________________ ______ _____ ______ ________ _________
TOTAL 233.75
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 23.38
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 257.13
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Sft. Rs: 257.00

Chapter No. 2 68/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.

Dismantling plank or wooden block flooring etc:


(Unit of rate one hundred Sft.)
S/N ______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
31. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ SkilledCoolies. 1.25 Nos: 250.00 P.Day 312.50
______________________________ ______ _____ ______ ________ _________
TOTAL 312.50
____ ______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 31.25
______________________________ ______ _____ ______ ________ _________
TOTAL 343.75
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 34.38
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 378.13
______________________________ ______ _____ ______ __________________
Labour rate per 100 Sft. Rs: 378.13

Chapter No. 2 69/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ __________________

D E S C R I P T I O N.

Dismantling and removing earthen ware or R.C.C. pipes from


____ trench and stacking outside.
S/N 6" to 12" Dia. (Unit of rate per Rft.)
______________________________ ______ _____ ______ ________ _________
32. LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
(a) ______________________________ ______ _____ ______ ________ _________
____ For disjoining the pipe
inside the trench one
mason will take 1/2 hour
____ for disjoining each joint
(i) day's out put is 16 joints
i.e 100 Rft.
Mason (2nd class) 1.00 Nos: 400.00 P.Day 400.00
SkilledCoolies. 1.00 Nos: 250.00 P.Day 250.00

For dismantling the pipe


line and removal of the
pipe from trench and
stacking outside.
(ii)
Skilled Coolies. 1.00 Nos: 250.00P.Day 250.00
______________________________ ______ _____ ______ ________ _________
TOTAL 900.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 90.00
______________________________ ______ _____ ______ ________ _________
TOTAL 990.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 99.00
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 1089.00
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Rft. Rs: 1089.00
Labour rate per Rft. Rs: 10.89

(1) Bends, Elbows, sluice valves etc, should not be paid for
extra if fixed in the lenth of pipe line that is being
dismantled.
(2) The rate does not include the cost of excavation and
Note refilling of trenches or the dismantling of any masonary or
brick work.
______________________________ ______ _____ ______ ________ _________

Chapter No. 2 70/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ _________

Chapter No. 2 71/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.
____
Dismantling and removing earthen ware or R.C.C. pipes from
____ trench and stacking outside.
S/N 12" to 24" Dia. (Unit of rate per Rft.)
______________________________ ______ _____ ______ ________ _________
32. LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
(b) ______________________________ ______ _____ ______ ________ _________
____ For disjoining the pipe
inside the trench one
mason will take 1/2 hour
____ for disjoining each joint
(i) day's out put is 16 joints
i.e 100 Rft.
Mason (2nd class) 1.00 Nos: 400.00 P.Day 400.00
Skilled Coolies. 1.00 Nos: 250.00 P.Day 250.00

For dismantling the pipe


line and removal of the
pipe from trench and
stacking outside.
(ii)
Skilled Coolies. 3.00 Nos: 250.00 P.Day 750.00
______________________________ ______ _____ ______ ________ _________
TOTAL 1400.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 140.00
______________________________ ______ _____ ______ ________ _________
TOTAL 1540.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 154.00
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 1694.00
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Rft. Rs: 1694.00
Labour rate per Rft. Rs: 16.94
______________________________ ______ _____ ______ ________ _________
(1) Bends, Elbows, sluice valves etc, should not be paid for
extra if fixed in the lenth of pipe line that is being
dismantled.
(2) The rate does not include the cost of excavation and
Note refilling of trenches or the dismantling of any masonary or
brick work.

Chapter No. 2 72/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.
____
Dismantling and removing earthen ware or R.C.C. pipes from
____ trench and stacking outside.
S/N 24" to 36" Dia. (Unit of rate per Rft.)
______________________________ ______ _____ ______ ________ _________
32. LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
(c) ______________________________ ______ _____ ______ ________ _________
____ For disjoining the pipe
inside the trench one
mason will take 1/2 hour
____ for disjoining each joint
(i) day's out put is 16 joints
i.e 100 Rft.
Mason (2nd class) 1.50 Nos: 400.00 P.Day 600.00
Skilled Coolies. 1.50 Nos: 250.00 P.Day 375.00

For dismantling the pipe


line and removal of the
pipe from trench and
stacking outside.
(ii)
Skilled Coolies. 4.00 Nos: 250.00 P.Day 1000.00
______________________________ ______ _____ ______ ________ _________
TOTAL 1975.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 197.50
______________________________ ______ _____ ______ ________ _________
TOTAL 2172.50
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 217.25
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 2389.75
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Rft. Rs: 2389.75
Labour rate per Rft. Rs: 23.90
______________________________ ______ _____ ______ ________ _________
(1) Bends, Elbows, sluice valves etc, should not be paid for
extra if fixed in the lenth of pipe line that is being
dismantled.
(2) The rate does not include the cost of excavation and
Note refilling of trenches or the dismantling of any masonary or
brick work.

Chapter No. 2 73/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.
____
Dismantling and removing earthen ware or R.C.C. pipes from
____ trench and stacking outside.
S/N Above 36" Diameter. (Unit of rate per Rft.)
______________________________ ______ _____ ______ ________ _________
32. LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
(d) ______________________________ ______ _____ ______ ________ _________
____ For disjoining the pipe
inside the trench one
mason will take 1/2 hour
____ for disjoining each joint
(i) day's out put is 8 joints
i.e 100 Rft.
Mason (2nd class) 2.00 Nos: 400.00 P.Day 800.00
SkilledCoolies. 2.00 Nos: 250.00 P.Day 500.00

For dismantling the pipe


line and removal of the
pipe from trench and
stacking outside.
(ii)
SkilledCoolies. 6.00 Nos: 250.00 P.Day 1500.00
______________________________ ______ _____ ______ ________ _________
TOTAL 2800.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 280.00
______________________________ ______ _____ ______ ________ _________
TOTAL 3080.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 308.00
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 3388.00
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Rft. Rs: 3388.00
Labour rate per Rft. Rs: 33.88
______________________________ ______ _____ ______ ________ _________
(1) Bends, Elbows, sluice valves etc, should not be paid for
extra if fixed in the lenth of pipe line that is being
dismantled.
(2) The rate does not include the cost of excavation and
Note refilling of trenches or the dismantling of any masonary or
brick work.

Chapter No. 2 74/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.
WOOD WORK.
____ ==========
Removing doors with chowkats.
S/N (Unit of rate per No:)
______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
33(a Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Coolies. 0.15 Nos: 250.00 P.Day 37.50

Mason. 0.15 Nos: 400.00 P.Day 60.00


____
Carpenter. 0.05 Nos: P.Day
400.00 20.00
______________________________ ______ _____ ______ ________ _________
TOTAL 117.50
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 11.75
______________________________ ______ _____ ______ ________ _________
TOTAL 129.25
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 12.93
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 142.18
______________________________ ______ _____ ______ ________ _________
Labour rate per No: Rs: 142.18

Chapter No. 2 75/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.
____ WOOD WORK.
==========
____ Removing windows & sky lights without chowkats.
S/N (Unit of rate per No:)
______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
33(b. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Mason. 0.10 Nos: 400.00 P.Day 40.00

Skilled Coolies. 0.10 Nos: 250.00 P.Day 25.00


____
Carpenter. 0.05 Nos: 400.00 P.Day 20.00
______________________________ ______ _____ ______ ________ _________
TOTAL 85.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 8.50
______________________________ ______ _____ ______ ________ _________
TOTAL 93.50
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 9.35
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 102.85
______________________________ ______ _____ ______ ________ _________
Labour rate per No: Rs: 102.85
D E S C R I P T I O N.
WOOD WORK.
==========
Removing ventilators and wooden sunshed etc:
S/N (Unit of rate per No:)
______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
34. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Mason. 0.05 Nos: 400.00 P.Day 20.00

SkilledCoolies. 0.05 Nos: 250.00 P.Day 12.50


____
Carpenter. 0.025 Nos: 400.00 P.Day 10.00
______________________________ ______ _____ ______ ________ _________
TOTAL 42.50
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 4.25
______________________________ ______ _____ ______ ________ _________
TOTAL 46.75
Contractor's profit 10.00 % 4.68
TOTAL PART " A " 51.43

Chapter No. 2 76/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Labour rate per No: Rs: 51.45

Chapter No. 2 77/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.
____ WOOD WORK.
==========
____ Dismantling wooden beams upto 12' in lenth.
S/N (Unit of rate per No:)
______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
35(a Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Coolies. 0.25 Nos: 250.00 P.Day 62.50
______________________________ ______ _____ ______ ________ _________
TOTAL 62.50
____ ______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 6.25
______________________________ ______ _____ ______ ________ _________
TOTAL 68.75
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 6.88
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 75.63
______________________________ ______ _____ ______ ________ _________
Labour rate per No: Rs: 75.63

____ ______________________________ ______ _____ ______ ________ _________


D E S C R I P T I O N.
WOOD WORK.
==========
____ Dismantling wooden beams upto 13' to 23' in lenth.
S/N (Unit of rate per No:)
______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
35(b Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Skilled Coolies. 0.50 Nos: 250.00 P.Day 125.00
______________________________ ______ _____ ______ ________ _________
TOTAL 125.00
____ ______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 12.50
______________________________ ______ _____ ______ ________ _________
TOTAL 137.50
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 13.75
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 151.25
______________________________ ______ _____ ______ ________ _________
Labour rate per No: Rs: 151.25
______________________________ ______ _____ ______ ________ _________

Chapter No. 2 78/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ _________

Chapter No. 2 79/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.
____ WOOD WORK.
==========
____ Dismantling wooden partition Jaffrey work etc:
S/N (Unit of rate per 100 Sft.)
______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
36 Rs: Rs:
____ Labour for 600 Sft.
Carpentor. 1.00 Nos: 400.00 P.Day 400.00

____ Skilled Coolies. 2.00 Nos: P.Day


250.00 500.00
______________________________ ______ _____ ______ ________ _________
TOTAL 900.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 90.00
______________________________ ______ _____ ______ ________ _________
TOTAL 990.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 99.00
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 1089.00
______________________________ ______ _____ ______ ________ _________
Labour rate per 600 Sft. Rs: 1089.00
Labour rate per 100 Sft.=617.10/6 = Rs: 181.50
D E S C R I P T I O N.
WOOD WORK.
==========
____ Dismantling wooden trusses.
S/N (Unit of rate per Cwt.)
______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
37. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Labour for 5 Cwt.
Blacksmith. 0.25 Nos: 400.00 P.Day 100.00

____ Skilled Coolies. 4.00 Nos: P.Day


250.00 1000.00
______________________________ ______ _____ ______ ________ _________
TOTAL 1100.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 110.00
TOTAL 1210.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 121.00
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 1331.00
Labour rate per 5 Cwt. Rs: 1331.00

Chapter No. 2 80/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Labour rate per Cwt. = Rs: 266.20

Chapter No. 2 81/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.
____

____ Dismantling sleepers huts.


S/N (Unit of rate per 100 Sft.)
______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
38. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____
Skilled Coolies. 2.00 Nos: 250.00 P.Day 500.00
______________________________ ______ _____ ______ ________ _________
____ TOTAL 500.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 50.00
______________________________ ______ _____ ______ ________ _________
TOTAL 550.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 55.00
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 605.00
______________________________ ______ _____ ______ ________ _________
Labour rate per 100 Sft. Rs: 605.00
D E S C R I P T I O N.

____ Dismantling sleeper walls.


S/N (Unit of rate per sleeper.)
______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
39. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Labour for 25 sleepers.
Skilled Coolies. 1.00 Nos: 250.00P.Day 250.00
______________________________ ______ _____ ______ ________ _________
____ TOTAL 250.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 25.00
______________________________ ______ _____ ______ ________ _________
TOTAL 275.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 27.50
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 302.50
______________________________ ______ _____ ______ ________ _________
Labour rate per 25 sleepers. Rs: 302.50
Labour rate per sleeper. Rs: 12.10
______________________________ ______ _____ ______ ________ _________

Chapter No. 2 82/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ _________


D E S C R I P T I O N.
____ Dismantling wooden palisade fencing.
S/N (Unit of rate per Rft.)
______________________________ ______ _____ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
40. Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Labour for 50 Rft.
Carpenter. 1.00 Nos: 400.00 P.Day 400.00

____ Skilled Coolies. 1.00 Nos: 250.00 P.Day 250.00


______________________________ ______ _____ ______ ________ _________
TOTAL 650.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 65.00
______________________________ ______ _____ ______ ________ _________
TOTAL 715.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 71.50
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 786.50
______________________________ ______ _____ ______ ________ _________
Labour rate per 50 Rft. Rs: 786.50
Labour rate per Rft. Rs: 15.73
D E S C R I P T I O N.
____ IRON WORK.
==========
____ Dismantling iron work of trusses sheds water tanks, etc,
S/N excluding cutting of rivets.
(Unit of rate per Cwt.)
______________________________ ______ _____ ______ ________ _________
41. LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Labour for 5 Cwt.
Blacksmith. 1.00 Nos: 400.00 P.Day 400.00

____ skilled Coolies. 3.00 Nos: 250.00 P.Day 750.00


______________________________ ______ _____ ______ ________ _________
TOTAL 1150.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 115.00
______________________________ ______ _____ ______ ________ _________
TOTAL 1265.00
Contractor's profit 10.00 % 126.50
TOTAL PART " A " 1391.50

Chapter No. 2 83/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Labour rate per 5 Cwt. Rs: 1391.50


Labour rate per Cwt. Rs: 278.30

Chapter No. 2 84/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.
____ IRON WORK.
==========
____ Dismantling rolled steel beams or iron rail etc:
S/N
(Unit of rate per Cwt.)
______________________________ ______ _____ ______ ________ _________
42. LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Labour for 12 Cwt.
Skilled Coolies. 5.00 Nos: 250.00 P.Day 1250.00
______________________________ ______ _____ ______ ________ _________
____ TOTAL 1250.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 125.00
______________________________ ______ _____ ______ ________ _________
TOTAL 1375.00
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 137.50
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 1512.50
______________________________ ______ _____ ______ ________ _________
Labour rate per 12 Cwt. Rs: 1512.50
Labour rate per Cwt. Rs: 126.04
D E S C R I P T I O N.
____ IRON WORK.
==========
____ Dismantling iron laterine.
S/N
(Unit of rate per unit of 2-seats.)
______________________________ ______ _____ ______ ________ _________
43. LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Fitters. 0.50 Nos: 400.00 P.Day 200.00

Skilled Coolies. 1.25 Nos: P.Day


250.00 312.50
____ ______________________________ ______ _____ ______ ________ _________
TOTAL 512.50
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 51.25
______________________________ ______ _____ ______ ________ _________
TOTAL 563.75
______________________________ ______ _____ ______ ________ _________
Contractor's profit 10.00 % 56.38
TOTAL PART " A " 620.13
______________________________ ______ _____ ______ ________ _________

Chapter No. 2 85/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Labour rate per unit of 2-seats. Rs: 620.13

Chapter No. 2 86/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.
____ IRON WORK.
==========
____ Dismantling tees bends or sluice valves upto 12" bore.
S/N
(Unit of rate per bore.)
______________________________ ______ _____ ______ ________ _________
44. LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ Labour for 5 Nos: 12" bore.
Fitters. 1.00 Nos: 400.00 P.Day 400.00

____ Skilled Coolies. 1.00 Nos: 250.00P.Day 250.00


______________________________ ______ _____ ______ ________ _________
TOTAL 650.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 65.00
______________________________ ______ _____ ______ ________ _________
TOTAL 715.00
Contractor's profit 10.00 % 71.50
______________________________ ______ _____ ______ ________ _________
TOTAL PART " A " 786.50
Labour rate per 5 bores of 12" Rs: 786.50
Labour rate each per inch bore = Rs: 13.08
D E S C R I P T I O N.
IRON WORK.
==========
Dismantling B.G. water column.
S/N
(Unit of rate Each.)
______________________________ ______ _____ ______ ________ _________
45(a LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ _________
____ Mason mistry. 1.00 Nos: 400.00 P.Day 400.00

Blacksmith. 1.00 Nos: 400.00 P.Day 400.00


____
Skilled Coolies. 10.00 Nos: 250.00P.Day 2500.00
______________________________ ______ _____ ______ ________ _________
TOTAL 3300.00
______________________________ ______ _____ ______ ________ _________
Sundries. 10.00 % 330.00
______________________________ ______ _____ ______ ________ _________
TOTAL 3630.00
Contractor's profit ______ _____ ______ ________ _________
______________________________ 10.00 % 363.00
TOTAL PART " A " ______ _____ ______ ________ _________

Chapter No. 2 87/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Labour rate for each. ______ _____ ______ ________ _________

Chapter No. 2 88/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N. ______ _____ ______ ________ _________


____ IRON WORK.
Dismantling M.G. or N.G. water column.
______________________________ (Unit of rate Each.)
LABOUR ______ _____ ______ ________ _________
45(b QUANTITY RATE UNIT AMOUNT
______________________________ Rs: Rs:
Mason mistry. ______ _____ ______ ________ _________
____ 0.50 Nos: 400.00 P.Day 200.00
Blacksmith.
1.00 Nos: 400.00 P.Day 400.00
____ Skilled Coolies.
______________________________ 6.50 Nos: 250.00 P.Day 1625.00
TOTAL ______ _____ ______ ________ _________
______________________________ 2225.00
Sundries. ______ _____ ______ ________ _________
______________________________ 10.00 % 222.50
TOTAL ______ _____ ______ ________ _________
______________________________ 2447.50
Contractor's profit ______ _____ ______ ________ _________
______________________________ 10.00 % 244.75
TOTAL PART " A " ______ _____ ______ ________ _________
______________________________ 2692.25
Labour rate for each. ______ _____ ______ ________ _________
D E S C R I P T I O N. Rs: 2692.25
IRON WORK.
==========
Dismantling all types of wire fencing i/c rolling the wires into
bundles & collecting materials.
S/N
______________________________ (Unit of rate one hundred Rft.)
LABOUR ______ _____ ______ ________ _________
46 QUANTITY RATE UNIT AMOUNT
______________________________ Rs: Rs:
Labour for 230 Rft. ______ _____ ______ ________ _________
____
Skilled Coolies.
______________________________ 2.00 Nos: 250.00 P.Day 500.00
____ TOTAL ______ _____ ______ ________ _________
______________________________ 500.00
Sundries. ______ _____ ______ ________ _________
______________________________ 10.00 % 50.00
TOTAL ______ _____ ______ ________ _________
______________________________ 550.00
Contractor's profit ______ _____ ______ ________ _________
______________________________ 10.00 % 55.00
TOTAL PART " A " ______ _____ ______ ________ _________
______________________________ 605.00

Chapter No. 2 89/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Labour rate for 230 Rft. ______ _____ ______ ________ _________
Labour rate for 100 Rft. Rs: 605.00

Chapter No. 2 90/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N. ______ _____ ______ ________ _________


IRON WORK.
Dismantling tie bar or Bains fencing i/c rolling the wires into
____ bundles & collecting materials.
______________________________ (Unit of rate one hundred Rft.)
LABOUR ______ _____ ______ ________ _________
47 QUANTITY RATE UNIT AMOUNT
______________________________ Rs: Rs:
Labour for 25 Rft. ______ _____ ______ ________ _________
Skilled Coolies.
______________________________ 2.00 Nos: 250.00 P.Day 500.00
____ TOTAL ______ _____ ______ ________ _________
______________________________ 500.00
Sundries. ______ _____ ______ ________ _________
______________________________ 10.00 % 50.00
TOTAL ______ _____ ______ ________ _________
______________________________ 550.00
Contractor's profit ______ _____ ______ ________ _________
______________________________ 10.00 % 55.00
TOTAL PART " A " ______ _____ ______ ________ _________
______________________________ 605.00
Labour rate for 25 Rft. ______ _____ ______ ________ _________
Labour rate per 100 Rft. Rs: 605.00
D E S C R I P T I O N. ______ _____ ______ ________ _________
IRON WORK.
____ ==========
Dismantling boiler tube fencing.
S/N
______________________________ (Unit of rate one hundred Rft.)
LABOUR ______ _____ ______ ________ _________
48. QUANTITY RATE UNIT AMOUNT
______________________________ Rs: Rs:
Labour for 20 Rft. ______ _____ ______ ________ _________
____
Skilled Coolies.
______________________________ 2.00 Nos: 250.00 P.Day 500.00
____ TOTAL ______ _____ ______ ________ _________
______________________________ 500.00
Sundries. ______ _____ ______ ________ _________
______________________________ 10.00 % 50.00
TOTAL ______ _____ ______ ________ _________
______________________________ 550.00
Contractor's profit ______ _____ ______ ________ _________
______________________________ 10.00 % 55.00
TOTAL PART " A " ______ _____ ______ ________ _________
______________________________ 605.00
Labour rate for 20 Rft. ______ _____ ______ ________ _________
Labour rate per 100 Rft. Rs: 605.00

Chapter No. 2 91/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ Rs: 3025.00

Chapter No. 2 92/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N. ______ _____ ______ ________ _________


MISCELLANEOUS.
____ ==============
Dismantling wire netting of tennis courts and frame work.
____
S/N
______________________________ (Unit of rate one hundred Sft.)
LABOUR ______ _____ ______ ________ _________
49. QUANTITY RATE UNIT AMOUNT
______________________________ Rs: Rs:
______ _____ ______ ________ _________
____ Skilled Coolies.
______________________________ 0.40 Nos: 250.00 P.Day 100.00
TOTAL ______ _____ ______ ________ _________
____ ______________________________ 100.00
Sundries. ______ _____ ______ ________ _________
______________________________ 10.00 % 10.00
TOTAL ______ _____ ______ ________ _________
______________________________ 110.00
Contractor's profit ______ _____ ______ ________ _________
______________________________ 10.00 % 11.00
TOTAL PART " A " ______ _____ ______ ________ _________
______________________________ 121.00
Labour rate for 100 Sft. ______ _____ ______ ________ _________
____ D E S C R I P T I O N. ______ _____ ______ ________ _________
MISCELLANEOUS.
==============
Dismantling cloth cieling and supporting timber.
____
S/N
______________________________ (Unit of rate one hundred Sft.)
LABOUR ______ _____ ______ ________ _________
50. QUANTITY RATE UNIT AMOUNT
______________________________ Rs: Rs:
______ _____ ______ ________ _________
____ Skilled Coolies.
______________________________ 0.75 Nos: 250.00 P.Day 187.50
TOTAL ______ _____ ______ ________ _________
____ ______________________________ 187.50
Sundries. ______ _____ ______ ________ _________
______________________________ 10.00 % 18.75
TOTAL ______ _____ ______ ________ _________
______________________________ 206.25
Contractor's profit ______ _____ ______ ________ _________
______________________________ 10.00 % 20.63
TOTAL PART " A " ______ _____ ______ ________ _________
______________________________ 226.88
Labour rate for 100 Sft. ______ _____ ______ ________ _________

Chapter No. 2 93/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ Rs: 226.88

Chapter No. 2 94/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N. ______ _____ ______ ________ _________


MISCELLANEOUS.
Dismantling and removing road metalling.
S/N
______________________________ (Unit of rate one hundred Cft.)
LABOUR ______ _____ ______ ________ _________
51. QUANTITY RATE UNIT AMOUNT
______________________________ Rs: Rs:
______ _____ ______ ________ _________
____ Skilled Coolies.
______________________________ 2.00 Nos: 250.00 P.Day 500.00
TOTAL ______ _____ ______ ________ _________
____ ______________________________ 500.00
Sundries. ______ _____ ______ ________ _________
______________________________ 10.00 % 50.00
TOTAL ______ _____ ______ ________ _________
______________________________ 550.00
Contractor's profit ______ _____ ______ ________ _________
______________________________ 10.00 % 55.00
TOTAL PART " A " ______ _____ ______ ________ _________
______________________________ 605.00
Labour rate for 100 Cft. ______ _____ ______ ________ _________
D E S C R I P T I O N. ______ _____ ______ ________ _________
MISCELLANEOUS.
==============
Removing mud plaster from walls.
____
S/N
______________________________ (Unit of rate one hundred Sft.)
LABOUR ______ _____ ______ ________ _________
52. QUANTITY RATE UNIT AMOUNT
______________________________ Rs: Rs:
Labour for 500 Sft. ______ _____ ______ ________ _________
____ Skilled Coolies.
______________________________ 1.00 Nos: 250.00 P.Day 250.00
TOTAL ______ _____ ______ ________ _________
____ ______________________________ 250.00
Sundries. ______ _____ ______ ________ _________
______________________________ 10.00 % 25.00
TOTAL ______ _____ ______ ________ _________
______________________________ 275.00
Contractor's profit ______ _____ ______ ________ _________
______________________________ 10.00 % 27.50
TOTAL PART " A " ______ _____ ______ ________ _________
______________________________ 302.50
Labour rate for 500 Sft. ______ _____ ______ ________ _________
Labour rate for 100 Sft. Rs: 302.50
Labour rate for 100 Sft. Rs: 60.5

Chapter No. 2 95/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ Say Rs: 60.5

Chapter No. 2 96/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N. ______ _____ ______ ________ _________


MISCELLANEOUS.
____ ==============
Removing cement or lime plaster from walls.
______________________________ (Unit of rate one hundred Sft.)
LABOUR ______ _____ ______ ________ _________
53. QUANTITY RATE UNIT AMOUNT
______________________________ Rs: Rs:
Labour for 250 Sft. ______ _____ ______ ________ _________
____ Skilled Coolies.
______________________________ 1.00 Nos: 250.00 P.Day 250.00
TOTAL ______ _____ ______ ________ _________
____ ______________________________ 250.00
Sundries. ______ _____ ______ ________ _________
______________________________ 10.00 % 25.00
TOTAL ______ _____ ______ ________ _________
______________________________ 275.00
Contractor's profit ______ _____ ______ ________ _________
______________________________ 10.00 % 27.50
TOTAL PART " A " ______ _____ ______ ________ _________
______________________________ 302.50
Labour rate for 250 Sft. ______ _____ ______ ________ _________
Labour rate for 100 Sft. Rs: 302.50
Labour rate for 100 Sft. Rs: 121
______________________________ Say Rs: 121.00
D E S C R I P T I O N. ______ _____ ______ ________ _________
SCRAPING.
____ =========
White wash or colour wash.
____
S/N ______________________________ (Unit of rate one hundred Sft.)
LABOUR ______ _____ ______ ________ _________
QUANTITY RATE UNIT AMOUNT
54(a ______________________________ Rs: Rs:
Skilled Coolies. ______ _____ ______ ________ _________
____ ______________________________ 0.25 Nos: 250.00 P.Day 62.50
TOTAL ______ _____ ______ ________ _________
______________________________ 62.50
____ Sundries. ______ _____ ______ ________ _________
______________________________ 10.00 % 6.25
TOTAL ______ _____ ______ ________ _________
______________________________ 68.75
Contractor's profit ______ _____ ______ ________ _________
______________________________ 10.00 % 6.88
TOTAL PART " A " ______ _____ ______ ________ _________
______________________________ 75.63
Labour rate for 100 Sft. ______ _____ ______ ________ _________
Labour rate for 100 Sft. Rs: 75.63

Chapter No. 2 97/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ Say Rs: 75.63

Chapter No. 2 98/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N. ______ _____ ______ ________ _________


SCRAPING.
____ =========
Ordinary distemper oil bound distemper or paint on walls.
____
S/N ______________________________ (Unit of rate one hundred Sft.)
LABOUR ______ _____ ______ ________ _________
QUANTITY RATE UNIT AMOUNT
54(b ______________________________ Rs: Rs:
Skilled Coolies. ______ _____ ______ ________ _________
____ ______________________________ 0.75 Nos: 250.00 P.Day 187.50
TOTAL ______ _____ ______ ________ _________
______________________________ 187.50
____ Sundries. ______ _____ ______ ________ _________
______________________________ 10.00 % 18.75
TOTAL ______ _____ ______ ________ _________
______________________________ 206.25
Contractor's profit ______ _____ ______ ________ _________
______________________________ 10.00 % 20.63
TOTAL PART " A " ______ _____ ______ ________ _________
______________________________ 226.88
Labour rate for 100 Sft. ______ _____ ______ ________ _________
Labour rate for 100 Sft. Rs: 226.88
Say Rs: 226.88
D E S C R I P T I O N. ______ _____ ______ ________ _________
____

Dismantling glazed or encaustic tiles.


____
S/N ______________________________ (Unit of rate one hundred Sft.)
LABOUR ______ _____ ______ ________ _________
QUANTITY RATE UNIT AMOUNT
55 ______________________________ Rs: Rs:
Mason. ______ _____ ______ ________ _________
____ 1.00 Nos: 400.00 P.Day 400.00
Skilled Coolies.
______________________________ 1.00 Nos: 250.00 P.Day 250.00
____ TOTAL ______ _____ ______ ________ _________
______________________________ 650.00
Sundries. ______ _____ ______ ________ _________
______________________________ 10.00 % 65.00
TOTAL ______ _____ ______ ________ _________
______________________________ 715.00
Contractor's profit ______ _____ ______ ________ _________
______________________________ 10.00 % 71.50
TOTAL PART " A " ______ _____ ______ ________ _________
______________________________ 786.50
Labour rate for 100 Sft. ______ _____ ______ ________ _________

Chapter No. 2 99/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ Rs: 786.50

Chapter No. 2 100/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N. ______ _____ ______ ________ _________

____
Scraping boulders.
____
S/N ______________________________ (Unit of rate one hundred Cft.)
LABOUR ______ _____ ______ ________ _________
QUANTITY RATE UNIT AMOUNT
56 ______________________________ Rs: Rs:
Skilled Coolies. ______ _____ ______ ________ _________
____ ______________________________ 3.50 Nos: 250.00 P.Day 875.00
TOTAL ______ _____ ______ ________ _________
______________________________ 875.00
____ Sundries. ______ _____ ______ ________ _________
______________________________ 10.00 % 87.50
TOTAL ______ _____ ______ ________ _________
______________________________ 962.50
Contractor's profit ______ _____ ______ ________ _________
______________________________ 10.00 % 96.25
TOTAL PART " A " ______ _____ ______ ________ _________
______________________________ 1058.75
Labour rate for 100 Cft. ______ _____ ______ ________ _________
Rs: 1058.75
D E S C R I P T I O N. ______ _____ ______ ________ _________

Cleaning lime or cement morter of old stones to re-used in


masonary.
____ ______________________________ (Unit of rate one hundred Cft.)
S/N LABOUR ______ _____ ______ ________ _________
QUANTITY RATE UNIT AMOUNT
57. ______________________________ Rs: Rs:
SkilledCoolies. ______ _____ ______ ________ _________
____ ______________________________ 1.75 Nos: 250.00 P.Day 437.50
TOTAL ______ _____ ______ ________ _________
______________________________ 437.50
____ Sundries. ______ _____ ______ ________ _________
______________________________ 10.00 % 43.75
TOTAL ______ _____ ______ ________ _________
______________________________ 481.25
Contractor's profit ______ _____ ______ ________ _________
______________________________ 10.00 % 48.13
TOTAL PART " A " ______ _____ ______ ________ _________
______________________________ 529.38
Labour rate for 100 Cft. ______ _____ ______ ________ _________
______________________________ Rs: 529.38
______ _____ ______ ________ _________

Chapter No. 2 101/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____

Chapter No. 2 102/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

CONRETE.
FIRST FILL THIS SHEET.

MATERIAL. Rate Unite

1 Brick ,Stone, ballast. 2000 % Cft.

2 Earth 500 % Cft.

3 Lime Slaked 375 P.Mand.

4 Surkhi 2250 % Cft.

5 Sand 2425 % Cft.

6 Cement 400 P.Bag

7 Aggregate (Stone Creshed)1' Ring. 3100 % Cft.

8 Partal wood 1700 P.Cft

9 hire charges of mixture machine 7000 P.day

10 Bituman 86213 P.M Ton

11 Steel 3550 P.Cwt.

12 Binding wire 46 P.Lbs

13 Shingle 3/8 - 3/4 3075 % Cft

14 Deodar wood (Second quality) 4000 P.Cft

15 Swaing of wood 800 % Cft.

16 Bajri. 2650 % Cft.


17 Tor Steel. 3700 P.Cwt.

LABOUR Rate Unit

1 Masson, Carpenter, Black Smith,(G-1) 450 P.day

2 Coolies. 250 P.day

3 Bahishti 250 P.day

4 Carpenter (G-II ) 400 P.day

Chapter No. 3 103/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N CONCRETE
===============
D E S C R I P T I O N.

1. Mud concrete in foundation including watering and ramming.

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Brick/ Stone ballast. 100.0 Cft. 2000.00 % Cft. 2000.00
11/2gauge

Earth. 50.00 Cft. 500.00 % Cft. 250.00

________________________________ _________ _____ _______ _______ _________


TOTAL 2250.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 225.00
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 2475.00
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Mason. 0.13 Nos: 450.00 P.day. 58.50

Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

________________________________ _________ _____ _______ _______ _________


Rs: 1121.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 112.10
________________________________ _________ _____ _______ _______ _________
TOTAL 1233.10
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 123.31
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 1356.41
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 3831.41
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 3616.91
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 104/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N CONCRETE
===============
D E S C R I P T I O N.

2. Dry rammed brick or stone ballast 1-1/2" to 2" gauge.

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Brick/ Stone ballast 1-1/2" 110.0 Cft. 2000.00 % Cft. 2200.00
to 2" gauge.

________________________________ _________ _____ _______ _______ _________


TOTAL 2200.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 220.00
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 2420.00
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Coolies. 3.00 Nos: 250.00 P.day. 750.00

________________________________ _________ _____ _______ _______ _________


Rs: 750.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 75.00
________________________________ _________ _____ _______ _______ _________
TOTAL 825.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 82.50
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 907.50
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 3327.50
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 3327.50
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 105/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

3. Lime concrete including grinding of morter.

(a) Brick/ stone ballast 1" to 1-1/2" gauge ratio 1:1:1 (lime 1,
Surkhi 1, Sand 1 )
____ ________________________________ _________ _____ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Brick/ Stone ballast 1" to 100.0 Cft. 2000.00 % Cft. 2000.00
to 1-1/2" gauge.

Lime slaked. 6.70 Mand 375.00 P.Mand. 2512.50

Surkhi. 17.0 Cft. 2250.00 % Cft. 382.50

Sand. 17.0 Cft. 2425.00 % Cft. 412.25

________________________________ _________ _____ _______ _______ _________


TOTAL 5307.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 530.73
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 5837.98
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason. 0.25 Nos: 450.00 P.day. 112.50

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


________________________________ _________ _____ _______ _______ _________
Rs: 1487.50
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 148.75
________________________________ _________ _____ _______ _______ _________
TOTAL 1636.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 163.63
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 1799.88
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7637.85
Total material & labour for 100 Cft. Rs: 7637.85

Chapter No. 3 106/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

3. Lime concrete including grinding of morter.

(b) Brick/ stone ballast 1" to 1-1/2" gauge ratio 1:2 (lime 1,
Surkhi 2 )

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Brick/ Stone ballast 1" to 100.0 Cft. 2000.00 % Cft. 2000.00
to 1-1/2" gauge.

Lime slaked. 6.70 Mand 375.00 P.Mand. 2512.50

Surkhi. 34.0 Cft. 2250.00 % Cft. 765.00

________________________________ _________ _____ _______ _______ _________


TOTAL 5277.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 527.75
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 5805.25
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason. 0.25 Nos: 450.00 P.day. 112.50

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

________________________________ _________ _____ _______ _______ _________


Rs: 1487.50
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 148.75
________________________________ _________ _____ _______ _______ _________
TOTAL 1636.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 163.63
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 1799.88
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7605.13
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 7605.13
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 107/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4. Cement concrete brick or stone ballast 1-1/2" to 2" gauge.

(a) Ratio 1:3:6

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 13.0 Cwt. 400.00 P.bag. 5200.00

Sand. 46.0 Cft. 2425.00 % Cft. 1115.50

Brick/ Stone ballast 92.0 Cft. 2000.00 % Cft. 1840.00


1-1/2"-2" guage.
________________________________ _________ _____ _______ _______ _________
TOTAL 8155.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 815.55
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 8971.05
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason Grade-I. 0.25 Nos: 450.00 P.day. 112.50

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

________________________________ _________ _____ _______ _______ _________


Rs: 1487.50
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 148.75
________________________________ _________ _____ _______ _______ _________
TOTAL 1636.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 163.63
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 1799.88
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 10770.93
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 10770.93

Chapter No. 3 108/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4. Cement concrete brick or stone ballast 1-1/2" to 2" gauge.

(b) Ratio 1:4:8


____ ________________________________ _________ _____ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 9.6 Cwt. 400.00 P.bag. 3840.00

Sand. 48.0 Cft. 2425.00 % Cft. 1164.00

Brick/ Stone ballast. 96.0 Cft. 2000.00 % Cft. 1920.00


________________________________ _________ _____ _______ _______ _________
TOTAL 6924.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 692.40
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 7616.40
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason Grade-I. 0.25 Nos: 450.00 P.day. 112.50

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

________________________________ _________ _____ _______ _______ _________


Rs: 1487.50
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 148.75
________________________________ _________ _____ _______ _______ _________
TOTAL 1636.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 163.63
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 1799.88
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 9416.28
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 9416.28
____ ________________________________ _________ _____ _______ _______ _________

____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 109/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4. Cement concrete brick or stone ballast 1-1/2" to 2" gauge.

(c) Ratio 1:5:10

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 7.8 Cwt. 400.00 P.bag. 3120.00

Sand. 49.0 Cft. 2425.00 % Cft. 1188.25

Brick/ Stone ballast. 98.0 Cft. 2000.00 % Cft. 1960.00


________________________________ _________ _____ _______ _______ _________
TOTAL 6268.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 626.83
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 6895.08
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason Grade-I. 0.25 Nos: 450.00 P.day. 112.50

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

________________________________ _________ _____ _______ _______ _________


Rs: 1487.50
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 148.75
________________________________ _________ _____ _______ _______ _________
TOTAL 1636.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 163.63
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 1799.88
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 8694.95
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 8694.95
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 110/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4. Cement concrete brick or stone ballast 1-1/2" to 2" gauge.

(d) Ratio 1:6:12

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 6.5 Cwt. 400.00 P.bag. 2600.00

Sand. 49.0 Cft. 2425.00 % Cft. 1188.25

Brick/ Stone ballast. 98.0 Cft. 2000.00 % Cft. 1960.00

________________________________ _________ _____ _______ _______ _________


TOTAL 5748.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 574.83
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 6323.08
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason Grade-I. 0.25 Nos: 450.00 P.day. 112.50

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


________________________________ _________ _____ _______ _______ _________
Rs: 1487.50
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 148.75
________________________________ _________ _____ _______ _______ _________
TOTAL 1636.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 163.63
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 1799.88
________________________________ _________ _____ _______ _______ _________

Chapter No. 3 111/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (MATERIAL + LABOUR) 8122.95


Total material & labour for 100 Cft. Rs: 8122.95

S/N D E S C R I P T I O N.

4. Cement concrete brick or stone ballast 1-1/2" to 2" gauge.

(e) Ratio 1:6:18

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 5.0 Cwt. 400.00 P.bag. 2000.00

Sand. 37.0 Cft. 2425.00 % Cft. 897.25

Brick/ Stone ballast. 112.0 Cft. 2000.00 % Cft. 2240.00


________________________________ _________ _____ _______ _______ _________
TOTAL 5137.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 513.73
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 5650.98
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason Grade-I. 0.25 Nos: 450.00 P.day. 112.50

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

________________________________ _________ _____ _______ _______ _________


Rs: 1487.50
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 148.75
________________________________ _________ _____ _______ _______ _________
TOTAL 1636.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 163.63
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 1799.88
________________________________ _________ _____ _______ _______ _________

Chapter No. 3 112/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (MATERIAL + LABOUR) 7450.85


________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 7450.85
____ ________________________________ _________ _____ _______ _______ _________

S/N D E S C R I P T I O N.

4. Cement concrete brick or stone ballast 1-1/2" to 2" gauge.

(f) Ratio 1:7:20

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 4.4 Cwt. 400.00 P.bag. 1760.00

Sand. 38.5 Cft. 2425.00 % Cft. 933.63

Brick/ Stone ballast. 110.0 Cft. 2000.00 % Cft. 2200.00

________________________________ _________ _____ _______ _______ _________


TOTAL 4893.63
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 489.36
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 5382.99
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason Grade-I. 0.25 Nos: 450.00 P.day. 112.50

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


________________________________ _________ _____ _______ _______ _________
Rs: 1487.50
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 148.75
________________________________ _________ _____ _______ _______ _________
TOTAL 1636.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 163.63

Chapter No. 3 113/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

________________________________ _________ _____ _______ _______ _________


TOTAL PART " B " 1799.88
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7182.86
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 7182.86

S/N D E S C R I P T I O N.

5. Cement concrete plain including placing compacting, finishing


and curing complete (including screening and washing of stone
aggregate without shuttering.

(a) Ratio 1:1:2

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 31.5 Cwt. 400.00 P.bag. 12600.00

Sand. 39.0 Cft. 2425.00 % Cft. 945.75

Aggregate (stone) 78.0 Cft. 3100.00 % Cft. 2418.00


________________________________ _________ _____ _______ _______ _________
TOTAL 15963.75
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 1596.38
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 17560.13
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason Grade-I. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

________________________________ _________ _____ _______ _______ _________


Rs: 2075.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 207.50
________________________________ _________ _____ _______ _______ _________
TOTAL 2282.50
________________________________ _________ _____ _______ _______ _________

Chapter No. 3 114/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit %
10.00 228.25
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 2510.75
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 20070.88
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 20070.88
____ ________________________________ _________ _____ _______ _______ _________

S/N D E S C R I P T I O N.

5. Cement concrete plain including placing compacting, finishing


and curing complete (including screening and washing of stone
aggregate without shuttering.

(b) Ratio 1:1-1/2:1-1/2

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 31.5 Cwt. 400.00 P.bag. 12600.00

Sand. 58.0 Cft. 2425.00 % Cft. 1406.50

Aggregate (stone) 58.0 Cft. 3100.00 % Cft. 1798.00

________________________________ _________ _____ _______ _______ _________


TOTAL 15804.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 1580.45
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 17384.95
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason Grade-I. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


________________________________ _________ _____ _______ _______ _________
Rs: 2075.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 207.50

Chapter No. 3 115/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

________________________________ _________ _____ _______ _______ _________


TOTAL 2282.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 228.25
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 2510.75
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 19895.70
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 19895.70

Chapter No. 3 116/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Cement concrete plain including placing compacting, finishing


and curing complete (including screening and washing of stone
aggregate without shuttering.

(c) Ratio 1:1-1/2:3

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 22.5 Cwt. 400.00 P.bag. 9000.00

Sand. 42.0 Cft. 2425.00 % Cft. 1018.50

Aggregate (stone) 84.0 Cft. 3100.00 % Cft. 2604.00

________________________________ _________ _____ _______ _______ _________


TOTAL 12622.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 1262.25
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 13884.75
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason Grade-I. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

2075.00
________________________________ _________ _____ _______ _______ _________
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 207.50
________________________________ _________ _____ _______ _______ _________
TOTAL 2282.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 228.25
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 2510.75
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 16395.50
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 16395.50
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 117/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Cement concrete plain including placing compacting, finishing


and curing complete (including screening and washing of stone
aggregate without shuttering.

(d) Ratio 1:2:3

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 21.0 Cwt. 400.00 P.bag. 8400.00

Sand. 52.0 Cft. 2425.00 % Cft. 1261.00

Aggregate (stone) 78.00 Cft. 3100.00 % Cft. 2418.00

________________________________ _________ _____ _______ _______ _________


TOTAL 12079.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 1207.90
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 13286.90
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason Grade-I. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

________________________________ _________ _____ _______ _______ _________


Rs: 2075.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 207.50
________________________________ _________ _____ _______ _______ _________
TOTAL 2282.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 228.25
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 2510.75
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 15797.65
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 15797.65
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 118/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Cement concrete plain including placing compacting, finishing


and curing complete (including screening and washing of stone
aggregate without shuttering.

(e) Ratio 1:3:3

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 17.6 Cwt. 400.00 P.bag. 7040.00

Sand. 66.0 Cft. 2425.00 % Cft. 1600.50

Aggregate (stone) 66.00 Cft. 3100.00 % Cft. 2046.00

________________________________ _________ _____ _______ _______ _________


TOTAL 10686.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 1068.65
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 11755.15
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason Grade-I. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

________________________________ _________ _____ _______ _______ _________


Rs: 2075.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 207.50
________________________________ _________ _____ _______ _______ _________
TOTAL 2282.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 228.25
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 2510.75
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 14265.90
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 14265.90

Chapter No. 3 119/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Cement concrete plain including placing compacting, finishing


and curing complete (including screening and washing of stone
aggregate without shuttering.

(f) Ratio 1:2:4

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 17.6 Cwt. 400.00 P.bag. 7040.00

Sand. 44.0 Cft. 2425.00 % Cft. 1067.00

Aggregate (stone) 88.00 Cft. 3100.00 % Cft. 2728.00


________________________________ _________ _____ _______ _______ _________
TOTAL 10835.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 1083.50
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 11918.50
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason Grade-I. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

________________________________ _________ _____ _______ _______ _________


Rs: 2075.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 207.50
________________________________ _________ _____ _______ _______ _________
TOTAL 2282.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 228.25
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 2510.75
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 14429.25
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 14429.25
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 120/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Cement concrete plain including placing compacting, finishing


and curing complete (including screening and washing of stone
aggregate without shuttering.

(g) Ratio 1:2:6

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 13.7 Cwt. 400.00 P.bag. 5480.00

Sand. 34.0 Cft. 2425.00 % Cft. 824.50

Aggregate (stone) 102.0 Cft. 3100.00 % Cft. 3162.00

________________________________ _________ _____ _______ _______ _________


TOTAL 9466.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 946.65
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 10413.15
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason Grade-I. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

________________________________ _________ _____ _______ _______ _________


Rs: 2075.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 207.50
________________________________ _________ _____ _______ _______ _________
TOTAL 2282.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 228.25
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 2510.75
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12923.90
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 12923.90

Chapter No. 3 121/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Cement concrete plain including placing compacting, finishing


and curing complete (including screening and washing of stone
aggregate without shuttering.

(h) Ratio 1:3:6

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 13.0 Cwt. 400.00 P.bag. 5200.00

Sand. 46.0 Cft. 2425.00 % Cft. 1115.50

Aggregate (stone) 92.0 Cft. 3100.00 % Cft. 2852.00

________________________________ _________ _____ _______ _______ _________


TOTAL 9167.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 916.75
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 10084.25
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason Grade-I. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

________________________________ _________ _____ _______ _______ _________


Rs: 2075.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 207.50
________________________________ _________ _____ _______ _______ _________
TOTAL 2282.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 228.25
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 2510.75
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12595.00
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 12595.00
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 122/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Cement concrete plain including placing compacting, finishing


and curing complete (including screening and washing of stone
aggregate without shuttering.

(i) Ratio 1:4:8

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 9.6 Cwt. 400.00 P.bag. 3840.00

Sand. 48.0 Cft. 2425.00 % Cft. 1164.00

Aggregate (stone) 96.0 Cft. 3100.00 % Cft. 2976.00

________________________________ _________ _____ _______ _______ _________


TOTAL 7980.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 798.00
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 8778.00
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason Grade-I. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


________________________________ _________ _____ _______ _______ _________
Rs: 2075.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 207.50
________________________________ _________ _____ _______ _______ _________
TOTAL 2282.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 228.25
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 2510.75
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 11288.75
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 11288.75
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 123/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
6. Reinforced cement concrete work including all labour andmaterial
(a) except the cost of steel reinforcement and its labour for
bending and binding which willbe paid separately. The rate
includes all kinds of forms, moulds, lifting, centering,
shuttering, curing, rendering and finishing the exposed surface.
(including screening and washing of shingle)
(i) R.C.C. work in roof slab, beams, column, rafts,lintels and other
structural members laid in situ or precast laid in position
complete in all respects.(i) Ratio 1:2:4 90 Lbs of cement. 2 Cft
sand and 4 Cft shingle 1/8" to 3/4" gauge.
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 17.6 Cwt. 400.00 P.bag. 7040.00
Sand. 44.0 Cft. 2425.00 % Cft. 1067.00
Aggregate (stone) 88.0 Cft. 3100.00 % Cft. 2728.00
Cement for preparing 1.5 Cwt. 400.00 P.bag. 600.00
surface for R.C.C. work.
Hill sand. 4.0 Cft. 2425.00 % Cft. 97.00
Partal wood for shuttering 5.5/4 operation 5.5 Cft. 1700.00 P.Cft. 9350.00
and centering.
Nuts, nails, etc. L.S 50.00
Oiling & greasing the top L.S 50.00
surface of shuttering.
________________________________ _________ _____ _______ _______ _________
TOTAL 20982.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 2098.20
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 23080.20
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Mason Grade-I. 3.00 Nos: 450.00 P.day. 1350.00
Carpanters. 6.00 Nos: 450.00 P.day. 2700.00
Coolies. 13.00 Nos: 250.00 P.day. 3250.00
Bahishti. 3.00 Nos: 250.00 P.day. 750.00
Hire charges of Vibrator, 0.10 Nos: 7000.0 P.day. 700.00
Mixer machine & Lifter, etc.
Rs: 8750.00
Sundries except Hire charges. 10.00 % 805.00
TOTAL 9555.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 955.50
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 10510.50
________________________________ _________ _____ _______ _______ 105.11
TOTAL (MATERIAL + LABOUR) 33590.70
Total material & labour for 100 Cft. Rs: 33590.70

Chapter No. 3 124/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for one Cft. Rs: 335.91


Total material & labour for one Cft. say Rs: 335.91
S/N D E S C R I P T I O N.
6. Reinforced cement concrete work including all labour andmaterial
(a) except the cost of steel reinforcement and its labour for
bending and binding which willbe paid separately. The rate
includes all kinds of forms, moulds, lifting, centering,
shuttering, curing, rendering and finishing the exposed surface.
(including screening and washing of shingle)
(ii) R.C.C. work in roof slab, beams, column, rafts,lintels and other
structural members laid in situ or precast laid in position
complete in all respects.(ii) Ratio 1:1-1/2:3
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 22.5 Cwt. 400.00 P.bag. 9000.00
Sand. 42.0 Cft. 2425.00 % Cft. 1018.50
Aggregate (stone) 84.0 Cft. 3100.00 % Cft. 2604.00

CheelPartal wood for shuttering 5.5 Cft. 1700.00 P.Cft. 9350.00


5.5/4 operation and centering.
Nuts, nails, etc. L.S 50.00
Oiling & greasing the top L.S 50.00
surface of shuttering.
________________________________ _________ _____ _______ _______ _________
TOTAL 22072.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 2207.25
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 24279.75
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Mason Grade-I. 3.00 Nos: 450.00 P.day. 1350.00
Carpanters. 6.00 Nos: 450.00 P.day. 2700.00
Coolies. 13.00 Nos: 250.00 P.day. 3250.00
Bahishti. 3.00 Nos: 250.00 P.day. 750.00
Hire charges of Vibrator, 0.10 Nos: 7000.0 P.day. 700.00
Mixer machine & Lifter, etc.
________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 8750.00
________________________________ _________ _____ _______ _______ _________
Sundries except Hire charges. 10.00 % 805.00
________________________________ _________ _____ _______ _______ _________
TOTAL 9555.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 955.50
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 10510.50
________________________________ _________ _____ _______ _______ 105.11

Chapter No. 3 125/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (MATERIAL + LABOUR) 34790.25


Total material & labour for 100 Cft. Rs: 34790.25
Total material & labour for one Cft. Rs: 347.90
Total material & labour for one Cft. say Rs: 347.90
S/N D E S C R I P T I O N.
6. Reinforced cement concrete work including all labour andmaterial
(b) except the cost of steel reinforcement and its labour for
bending and binding which willbe paid separately. The rate
includes all kinds of forms, moulds, lifting, centering,
shuttering, curing, rendering and finishing the exposed surface.
(including screening and washing of shingle)
(i) Precast reinforced cement concrete in columns, beams, lintels,
stair cases, shelves, etc.
(i) Ratio 1:2:4 90 Lbs of cement. 2 Cft sand and 4 Cft shingle
1/8" to 3/4" gauge.
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 17.6 Cwt. 400.00 P.bag. 7040.00
Sand. 44.0 Cft. 2425.00 % Cft. 1067.00
Aggregate (stone) 88.0 Cft. 3100.00 % Cft. 2728.00
Cement for preparing 1.5 Cwt. 400.00 P.bag. 600.00
surface for R.C.C. work.
Hill sand. 4.0 Cft. 2425.00 % Cft. 97.00
Partal wood for shuttering 5.5 Cft. 1700.00 P.Cft. 9350.00
and centering.
Nuts, nails, etc. L.S 100.00
Oiling & greasing the top L.S 100.00
surface of shuttering.
________________________________ _________ _____ _______ _______ _________
TOTAL 21082.00
Contractor's profit 10.00 % 2108.20
TOTAL PART " A " 23190.20
(B) LABOUR
Mason Grade-I. 3.00 Nos: 450.00 P.day. 1350.00
Carpanters. 3.50 Nos: 450.00 P.day. 1575.00
Coolies. 10.00 Nos: 250.00 P.day. 2500.00
Bahishti. 1.50 Nos: 250.00 P.day. 375.00
Hire charges of Vibrator, 1.10 Nos: 7000.0 P.day. 700.00
Mixer machine & Lifter, etc.
________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 6500.00
________________________________ _________ _____ _______ _______ _________
Sundries except Hire charges. 10.00 % 580.00
________________________________ _________ _____ _______ _______ _________
TOTAL 7080.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 708.00
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 7788.00

Chapter No. 3 126/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

________________________________ _________ _____ _______ _______ 77.8877.88


TOTAL (MATERIAL + LABOUR) 30978.20
________________________________ _________ _____ _______ _______ 309.78
Total material & labour for 100 Cft. Rs: 30978.20
Total material & labour for one Cft. Rs: 309.78
Total material & labour for one Cft. say Rs: 310.00
S/N D E S C R I P T I O N.
6. Reinforced cement concrete work including all labour andmaterial
(b) except the cost of steel reinforcement and its labour for
bending and binding which willbe paid separately. The rate
includes all kinds of forms, moulds, lifting, centering,
shuttering, curing, rendering and finishing the exposed surface.
(including screening and washing of shingle)
Precast reinforced cement concrete in columns, beams, lintels,
stair cases, shelves, etc.
(ii) (ii) Ratio 1:1-1/2:3
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 22.5 Cwt. 400.00 P.bag. 9000.00
Sand. 42.0 Cft. 2425.00 % Cft. 1018.50
Aggregate (stone) 84.0 Cft. 3100.00 % Cft. 2604.00

Partal wood for shuttering 5.5 Cft. 1700.00 P.Cft. 9350.00


and centering.
Nuts, nails, etc. L.S 100.00
Oiling & greasing the top L.S 100.00
surface of shuttering.
________________________________ _________ _____ _______ _______ _________
TOTAL 22172.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 2217.25
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 24389.75
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Mason Grade-I. 3.00 Nos: 450.00 P.day. 1350.00
Carpanters. 3.50 Nos: 450.00 P.day. 1575.00
Coolies. 10.00 Nos: 250.00 P.day. 2500.00
Bahishti. 1.50 Nos: 250.00 P.day. 375.00
Hire charges of Vibrator, 1.10 Nos: 7000.0 P.day. 700.00
Mixer machine & Lifter, etc.
________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 6500.00
________________________________ _________ _____ _______ _______ _________
Sundries except Hire charges. 10.00 % 580.00
________________________________ _________ _____ _______ _______ _________
TOTAL 7080.00
________________________________ _________ _____ _______ _______ _________

Chapter No. 3 127/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 708.00


________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 7788.00
________________________________ _________ _____ _______ _______ 77.8877.88
TOTAL (MATERIAL + LABOUR) 32177.75
Total material & labour for 100 Cft. Rs: 32177.75
Total material & labour for one Cft. Rs: 321.78
Total material & labour for one Cft. say Rs: 321.78
S/N D E S C R I P T I O N.
6. Reinforced cement concrete work including all labour andmaterial
(c) except the cost of steel reinforcement and its labour for
bending and binding which willbe paid separately. The rate
includes all kinds of forms, moulds, lifting, centering,
shuttering, curing, rendering and finishing the exposed surface.
(including screening and washing of shingle)
Erecting and fixing in position precast cement concrete or stone
slab in roofs or lintels, etc, lift upto 20 feet including all
charges.

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Sand 1.0 Cft. 2425.00 % Cft. 24.25
Bitumen. 0.250 Cwt. 86213.0 P.Ton 1077.66

________________________________ _________ _____ _______ _______ _________


TOTAL 1101.91
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 110.19
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 1212.10
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Mason Grade-I. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 8.00 Nos: 250.00 P.day. 2000.00


________________________________ _________ _____ _______ _______ _________
Rs: 2450.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 245.00
________________________________ _________ _____ _______ _______ _________
TOTAL 2695.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 269.50
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 2964.50

Chapter No. 3 128/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

________________________________ _________ _____ _______ _______ 29.6529.65


TOTAL (MATERIAL + LABOUR) 4176.60
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 4176.60
Total material & labour for one Cft. Rs: 41.77
Total material & labour for one Cft. say Rs: 41.77
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 129/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
6. Reinforced cement concrete work including all labour andmaterial
except the cost of steel reinforcement and its labour for
bending and binding which willbe paid separately. The rate
includes all kinds of forms, moulds, lifting, centering,
shuttering, curing, rendering and finishing the exposed surface.
(including screening and washing of shingle)
(d) Add extra labour for R.C. concrete in 2nd and subsequent storeys.

____ ________________________________ _________ _____ _______ _______ _________


(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Skilled Coolies. 0.04 Nos: 500.00 P.day. 20.00
________________________________ _________ _____ _______ _______ _________
Rs: 20.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 2.00
________________________________ _________ _____ _______ _______ _________
TOTAL 22.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 2.20
________________________________ _________ _____________ _______ _________
TOTAL PART " B " 24.20
________________________________ _________ _____ _______ _______ _________
Total labour rate for one Cft. Rs: 12.10
____ ________________________________ _________ _____ _______ _______ _________

RATE ANALYSIS
Sr.No. DESCRIPTION.
1 P/Applying Hi Bond (Sealer ) water proofing polymer Modified comontitions slurries (WPMCS) to be used as
water proofing, anticorrosion, weater resistance or curring membranc for fresh concrete having thickness
upto 2mm in two coats upto 20' height testured or trowel finish grey or coloured i/c preparing the surface
for application aas directed by Engineer Inchare.
Calculation for 100 Sft. unit % sft
(A) MATERIAL QUANTITY RATE RS: UNIT AMOUNT RS:
(i) Hi Bond Universal i/c 10% wastage (coverage 35-S2.85x1.10=3.14Kg 425 P.Kg. 1334.5
(ii) Brash etc. L.sum 45
Rs: 1379.5
TOTAL
Contractor's Profit 10 % 137.9
TOTAL PART "A" 1517.45

(B) LABOUR QUANTITY RATE RS: UNIT AMOUNT RS:


(i) Painter 0.75 Nos: 450 P.day 337.5
(ii) Coolie /Helper 0.75 Nos. 250 P.Day 187.5
(iii) Bhishti 0.25 Nos. 250 P.Day 62.5
(iv) Coolies T&P etc. L.Sum 45
Rs; 632.5
Sundries. 10 % 63.25
TOTAL 695.75
Contractor's Profit 10 % 69.57

Chapter No. 3 130/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL PART "B" 765.32


G.TOTAL (A+B) 2282.77

S/N D E S C R I P T I O N.

7(a) Fabrication of mild steel reinforcement for cement concrete


including cutting bendind laying in position making joints and
fastening including cost of binding wire (also includes removal
of rust from bars)

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Steel bars. 1.0 Cwt. 3550.00 P.Cwt. 3550.00
Add for over laps 10% 0.1 Cwt. 3550.00 P.Cwt. 355.00
Binding wire. 2.00 Lbs. 46.00 P.Lbs. 92.00

________________________________ _________ _____ _______ _______ _________


TOTAL 3997.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 399.70
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 4396.70
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Blacksmith. 0.50 Nos: 450.00 P.day. 225.00

Coolies for helping & 0.50 Nos: 250.00 P.day. 125.00


lifting.

________________________________ _________ _____ _______ _______ _________


Rs: 350.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 35.00
________________________________ _________ _____ _______ _______ _________
TOTAL 385.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 38.50
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 423.50
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 4820.20

Chapter No. 3 131/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

________________________________ _________ _____ _______ _______ _________


Total material & labour for 1 Cwt. Rs: 4820.20
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 132/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7(b) Fabrication of mild steel reinforcement for cement concrete


including cutting bendind laying in position making joints and
fastening including cost of binding wire (also includes removal
of rust from bars)
(b) Tor bars.

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Steel bars. 1.0 Cwt. 3700.00 P.Cwt. 3700.00
Add for over laps 10% 0.1 Cwt. 3700.00 P.Cwt. 370.00
Binding wire. 2.00 Lbs. 46.00 P.Lbs. 92.00

________________________________ _________ _____ _______ _______ _________


TOTAL 4162.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 416.20
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 4578.20
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Blacksmith. 0.50 Nos: 450.00 P.day. 225.00

Coolies for helping & 0.50 Nos: 250.00 P.day. 125.00


lifting.

________________________________ _________ _____ _______ _______ _________


Rs: 350.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 35.00
________________________________ _________ _____ _______ _______ _________
TOTAL 385.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 38.50
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 423.50
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 5001.70
________________________________ _________ _____ _______ _______ _________
Total material & labour for 1 Cwt. Rs: 5001.70
____ ________________________________ _________ _____ _______ _________________

Chapter No. 3 133/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

8. Precast cement concrete solid or face blocks (1:2:4) including


cost of templates.

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 17.6 Cwt. 400.00 P.bag. 7040.00
Sand. 44.0 Cft. 2425.00 % Cft. 1067.00
Shingle. 88.0 Cft. 3100.00 % Cft. 2728.00
Wooden planks or steel L.S 106.00
plates for moulds.

________________________________ _________ _____ _______ _______ _________


TOTAL 10941.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 1094.10
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 12035.10
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Masons. 2.00 Nos: 450.00 P.day. 900.00

Coolies. 3.00 Nos: 250.00 P.day. 750.00

Carpanter or Blacksmith. 0.50 Nos: 450.00 P.day. 225.00

Bahishti. 1.00 Nos: 250.00 P.day. 250.00


________________________________ _________ _____ _______ _______ _________
Rs: 2125.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 212.50
________________________________ _________ _____ _______ _______ _________
TOTAL 2337.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 233.75
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 2571.25
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 14606.35
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 14606.35
Total material & labour for one Cft. Rs: 146.06
Total material & labour for one Cft. say Rs: 146.06

Chapter No. 3 134/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

9. Precast cement concrete hollow blocks (1:2:4) including cost of


templates and constructing walls there of.

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 9.8 Cwt. 400.00 P.bag. 3920.00
Sand. 28.0 Cft. 2425.00 % Cft. 679.00
Aggregate (stone) 56.0 Cft. 3100.00 % Cft. 1736.00
Wood for templates. L.S 106.00

________________________________ _________ _____ _______ _______ _________


TOTAL 6441.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 644.10
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 7085.10
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Masons. 4.50 Nos: 450.00 P.day. 2025.00

Coolies. 8.00 Nos: 250.00 P.day. 2000.00

Bahishti. 1.50 Nos: 250.00 P.day. 375.00

Carpanter or Blacksmith. 0.50 Nos: 450.00 P.day. 225.00


________________________________ _________ _____ _______ _______ _________
Rs: 4625.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 462.50
________________________________ _________ _____ _______ _______ _________
TOTAL 5087.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 508.75
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 5596.25
________________________________ _________ _____ _______ _______ 55.9655.96
TOTAL (MATERIAL + LABOUR) 12681.35
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 12681.35
Total material & labour for one Cft. Rs: 126.81
Total material & labour for one Cft. say Rs: 126.81
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 135/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
10. Providing and fixing ornamental cement jali 2" thick (1:2:4)
without steel.
____ ________________________________ _________ _____ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 0.3 Cwt. 400.00 P.bag. 120.00
Sand. 0.8 Cft. 2425.00 % Cft. 18.19
Aggregate (StoneShingle) 56.0 Cft. 3075.00 % Cft. 1722.00
Wood for templates. L.S 2.00
________________________________ _________ _____ _______ _______ _________
TOTAL 1862.19
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 186.22
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 2048.41
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Masons. 0.25 Nos: 450.00 P.day. 112.50
Coolies. 0.25 Nos: 250.00 P.day. 62.50
________________________________ _________ _____ _______ _______ _________
Rs: 175.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 17.50
________________________________ _________ _____ _______ _______ _________
TOTAL 192.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 19.25
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 211.75
________________________________ _________ _____ _______ _______ 21.1821.18
TOTAL (MATERIAL + LABOUR) 2260.16
________________________________ _________ _____ _______ _______ _________
Total material & labour for 10 Sft. Rs: 2260.16
Total material & labour for one Sft. Rs: 226.02

____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 136/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
11(a. Extra labour for laying concrete plain or reinforced above 20'
upto 40 ft: hieght.
____ ________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00
________________________________ _________ _____ _______ _______ _________
Rs: 1000.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 100.00
________________________________ _________ _____ _______ _______ _________
TOTAL 1100.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 110.00
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 1210.00
________________________________ _________ _____ _______ _______ _________
Total labour rate for 100 Cft. Rs: 1210.00
S/N D E S C R I P T I O N.
11(b. Extra labour for laying concrete plain or reinforced for every s
additional 10ft: hieght.
____ ________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00
________________________________ _________ _____ _______ _______ _________
Rs: 625.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 62.50
________________________________ _________ _____ _______ _______ _________
TOTAL 687.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 68.75
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 756.25
________________________________ _________ _____ _______ _______ _________
Total labour rate for 100 Cft. Rs: 756.25
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 137/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
12. Extra labour for work of weirs rails or road bridges, syphones
and concreting in super structure.
____ ________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Skilled Coolies. 1.00 Nos: 250.00 P.day. 250.00
________________________________ _________ _____ _______ _______ _________
Rs: 250.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 25.00
________________________________ _________ _____ _______ _______ _________
TOTAL 275.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 27.50
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 302.50
________________________________ _________ _____ _______ _______ _________
Total labour rate for 100 Cft. Rs: 302.50
____ ________________________________ _________ _____ _______ _______ _________
S/N D E S C R I P T I O N.
13. Reinforced cement concrete spout including fixing in position
2-1/2" * 6" * 5".
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement, sand, bajri, steel L.S 45.00
& wood for form work.
________________________________ _________ _____ _______ _______ _________
TOTAL 45.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 4.50
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 49.50
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Masons. 0.25 Nos: 450.00 P.day. 112.50
Coolies. 0.25 Nos: 250.00 P.day. 62.50
________________________________ _________ _____ _______ _______ _________
Rs: 175.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 17.50
________________________________ _________ _____ _______ _______ _________
TOTAL 192.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 19.25
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 211.75
________________________________ _________ _____ _______ _______ _________

Chapter No. 3 138/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (MATERIAL + LABOUR) 261.25


Total material & labour for each No: Rs: 261.25
S/N D E S C R I P T I O N.
14. Making holes upto 3" dia and 18" depth in cement concrete or
stone masonary walls and repairing.
____ ________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Mason. 0.70 Nos: 450.00 P.day. 315.00
Coolies. 0.70 Nos: 250.00 P.day. 175.00
________________________________ _________ _____ _______ _______ _________
Rs: 490.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 49.00
________________________________ _________ _____ _______ _______ _________
TOTAL 539.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 53.90
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 592.90
________________________________ _________ _____ _______ _______ _________
Total labour rate for each hole. Rs: 313.40
____ ________________________________ _________ _____ _______ _______ _________
S/N D E S C R I P T I O N.
15. Skipping concrete in walls including mixing.

____ ________________________________ _________ _____ _______ _______ _________


(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Mason. 1.00 Nos: 450.00 P.day. 450.00
Coolies. 12.00 Nos: 250.00 P.day. 3000.00
Bahishti. 0.50 Nos: 250.00 P.day. 125.00
________________________________ _________ _____ _______ _______ _________
Rs: 3575.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 357.50
________________________________ _________ _____ _______ _______ _________
TOTAL 3932.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 393.25
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 4325.75
________________________________ _________ _____ _______ _______ _________
Total labour rate for 100 Cft. Rs: 4325.75

Chapter No. 3 139/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
16. Nicking concrete surface.
(a) Cement concrete surface.
____ ________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Mason. 0.50 Nos: 450.00 P.day. 225.00
________________________________ _________ _____ _______ _______ _________
Rs: 225.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 22.50
________________________________ _________ _____ _______ _______ _________
TOTAL 247.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 24.75
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 272.25
________________________________ _________ _____ _______ _______ _________
Total labour rate for 100 Sft. Rs: 272.25
____ ________________________________ _________ _____ _______ _______ _________

____ ________________________________ _________ _____ _______ _______ _________


S/N D E S C R I P T I O N.
16. Nicking concrete surface.
(b) Lime concrete surface.
____ ________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________
_________ _____ _______ _______ _________
Mason. 0.165 Nos: 450.00 P.day. 74.25
________________________________
_________ _____ _______ _______ _________
Rs: 74.25
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 7.43
________________________________ _________ _____ _______ _______ _________
TOTAL 81.68
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 8.17
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 89.84
________________________________ _________ _____ _______ _______ _________
Total labour rate for 100 Sft. Rs: 89.84
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 140/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
17(a Preparing watering and ramming surface for laying concrete ( for
head works only) Horizontal floor.
____ ________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Mason. 0.280 Nos: 450.00 P.day. 126.00
Skilled Cooly. 0.250 Nos: 250.00 P.day. 62.50
________________________________ _________ _____ _______ _______ _________
Rs: 188.50
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 18.85
________________________________ _________ _____ _______ _______ _________
TOTAL 207.35
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 20.74
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 228.09
________________________________ _________ _____ _______ _______ _________
Total labour rate for 100 Sft. Rs: 228.09
____ ________________________________ _________ _____ _______ _______ _________
S/N D E S C R I P T I O N.
17(b Preparing watering and ramming surface for laying concrete ( for
head works only) Glacis and crest.
____ ________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Mason. 0.500 Nos: 450.00 P.day. 225.00
Skilled Cooly. 0.250 Nos: 250.00 P.day. 62.50
________________________________ _________ _____ _______ _______ _________
Rs: 287.50
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 28.75
________________________________ _________ _____ _______ _______ _________
TOTAL 316.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 31.63
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 347.88
________________________________ _________ _____ _______ _______ _________
Total labour rate for 100 Sft. Rs: 347.88
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 141/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 142/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
17(c Preparing watering and ramming surface for laying concrete ( for
head works only) Inverted filters.
____ ________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Mason. 0.125 Nos: 450.00 P.day. 56.25
'Skilled Cooly. 0.125 Nos: 250.00 P.day. 31.25
________________________________ _________ _____ _______ _______ _________
Rs: 87.50
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 8.75
________________________________ _________ _____ _______ _______ _________
TOTAL 96.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 9.63
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 105.88
________________________________ _________ _____ _______ _______ _________
Total labour rate for 100 Sft. Rs: 105.88

____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 143/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
18. Erection and removal of centering for R.C.C. or plain cement
(a)concrete work Deodar wood 2nd class.
(i) Horizontal.
____ ________________________________ _________ _____ _______ _______ _________
Taking a room of size:- Length = 20' Breadth = 14' Hieght = 14'
Area of room = 20' * 14' = 280 sft.
Timber requirements.
Bottom planks 1" thick = 20 Nos: * 14' * 1' * 0.833 = 23.34 Cft.
Joists for supports (section 3"*3")= 5*0.25*0.25*14'= 4.38 Cft.
Vertical posts (section 3"*3") = 4*5*0.25*0.25*14'= 17.50 Cft.
Other pieces of wood = L.S =
----------------------------------------------------- ---------------- -------- ------------ ------------ ---------------
Total = 45.50 Cft.
----------------------------------------------------- ---------------- -------- ------------ ------------ ---------------
Add wastage 10% = 4.55 Cft.
----------------------------------------------------- ---------------- -------- ------------ ------------ ---------------
Total quantity = 50.0 Cft.
----------------------------------------------------- ---------------- -------- ------------ ------------ ---------------
This wood can be used for eight (08) times hence wood
required for one operation for hundred sft: =(50*100/280)/12 = 1.49 Cft.
____ ________________________________ _________ _____ _______ _______ _________
(A) MATERIAL. QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Deodar wood (Second quality) 1.49 Cft. 4000.00 P.Cft. 5960.00

Bolts, Nuts and Nails. L.S 50.00

Oiling, greasing,Soap, etc. L.S 50.00

________________________________ _________ _____ _______ _______ _________


TOTAL 6060.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 606.00
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 6666.00
____ ________________________________ _________ _____ _______ _______ _________

____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 144/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Sawing of wood.
Bottom planks = 19 * 14 * 1 = 266 Sft.
Joists for supports = 5 * 0.75 * 14 = 52 Sft.
Vertical posts = 19 * 0.75 * 14 = 200 Sft.
----------------------------------------------------- ---------------- -------- ------------ ------------ ---------------
Total quantity = 518 Sft.
----------------------------------------------------- ---------------- -------- ------------ ------------ ---------------
Quantity of sawing for one operation = 518/16 = 32.50 Sft.
________________________________ _________ _____ _______ _______ _________
Sawing of wood. 32.50 Sft. 800.00 % Sft. 260.00
Labour for erection and
removal including earth
work and oiling, greasing,
etc.
Carpanter 2nd class. 0.75 Nos: 400.00 P.day. 300.00

Skilled Coolies. 1.25 Nos: 250.00 P.day. 312.50


________________________________ _________ _____ _______ _______ _________
Rs: 872.50
________________________________ _________ _____ _______ _______ _________
Sundries. (except sawing) 10.00 % 61.25
________________________________ _________ _____ _______ _______ _________
TOTAL 933.75
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 93.38
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 1027.13
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7693.13
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Sft. Rs: 7435.73

Chapter No. 3 145/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
18. Erection and removal of centering for R.C.C. or plain cement
(a)concrete work Deodar wood 2nd class.
(ii) Vertical.
____ ________________________________ _________ _____ _______ _______ _________
Considering a R.C.C. wall of size:-L = 30', H = 5', T = 0.25 ft:
Superficial area of both sides = (1+1)* 30 * 5 = 300 Sft.
Contents of concrete = 30' * 5' * 0.25' =
Timber requirements.
side planks 1" thick = (1+1) * 30' * 5' * 0.0833 = 25.0 Cft.
Horizontal braces = (1+1)*2*30'*0.25'*0.125' = 3.75 Cft.
Struts & stays(section 3"*3"*4')=(1+1)*2*0.25*0.25*4'= 6.00 Cft.
Additional pieces of wood = L.S =
----------------------------------------------------- ---------------- -------- ------------ ------------ ---------------
Total = 35.00 Cft.
----------------------------------------------------- ---------------- -------- ------------ ------------ ---------------
Add wastage 10% = 3.50 Cft.
----------------------------------------------------- ---------------- -------- ------------ ------------ ---------------
Total quantity = 38.50 Cft.
----------------------------------------------------- ---------------- -------- ------------ ------------ ---------------
This wood can be used for (12) twelve times hence wood
required for one operation for hundred sft:=38.50/12*3 = 1.20 Cft.
____ ________________________________ _________ _____ _______ _______ _________
(A) MATERIAL. QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
deodar wood (Second quality) 1.20 Cft. 4000.00 P.Cft. 4800.00
Bolts, Nuts and Nails. L.S 50.00
Oiling, greasing,Soap, etc. L.S 50.00
________________________________ _________ _____ _______ _______ _________
TOTAL 4900.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 490.00
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 5390.00
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 146/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Sawing of wood.
Side planks = 1 * 0.5 No: * 90' * 5' = 225 Sft.
Horizontal braces =(1+1)*2*12*30*0.25*0.25 = 90 Sft.
Strurts and stays =(1+1)*2*6*0.25*0.25*4 = 72 Sft.
----------------------------------------------------- ---------------- -------- ------------ ------------ ---------------
Total quantity = 387 Sft.
----------------------------------------------------- ---------------- -------- ------------ ------------ ---------------
Quantity of sawing for one operation = 387/8 = 50 Sft.
________________________________ _________ _____ _______ _______ _________
Sawing of wood. 50.00 Sft. 800.00 % Sft. 400.00
Labour for erection and
removal including earth
work and oiling, greasing,
etc.

Carpanter 2nd class. 1.25 Nos: 400.00 P.day. 500.00

Skilled Coolies. 2.00 Nos: 250.00 P.day. 500.00


________________________________ _________ _____ _______ _______ _________
Rs: 1400.00
________________________________ _________ _____ _______ _______ _________
Sundries. (except sawing) 10.00 % 100.00
________________________________ _________ _____ _______ _______ _________
TOTAL 1500.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit (except sawing) 10.00 % 110.00
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 1610.00
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7000.00
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Sft. Rs: 6640.00

Chapter No. 3 147/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
18 Erection and removal of centering for R.C.C. or plain cement
(b)concrete work Partal Wood.
(i) Horizontal.
____ ________________________________ _________ _____ _______ _______ _________
Taking a room of size:- Length = 20' Breadth = 14' Hieght = 14'
Area of room = 20' * 14' = 280 sft.
Timber requirements.
Bottom planks 1" thick = 20 Nos: * 14' * 1' * 0.833 = 23.34 Cft.
Joists for supports (section 3"*3")= 5*0.25*0.25*14'= 4.38 Cft.
Vertical posts (section 3"*3") = 4*5*0.25*0.25*14'= 17.50 Cft.
Other pieces of wood = L.S =
----------------------------------------------------- ---------------- -------- ------------ ------------ ---------------
Total = 45.50 Cft.
----------------------------------------------------- ---------------- -------- ------------ ------------ ---------------
Add wastage 10% = 4.55 Cft.
----------------------------------------------------- ---------------- -------- ------------ ------------ ---------------
Total quantity = 50.0 Cft.
----------------------------------------------------- ---------------- -------- ------------ ------------ ---------------
This wood can be used for twelve times hence wood
required for one operation for hundred sft: =100*50/280*12 = 1.48 Cft.
____ ________________________________ _________ _____ _______ _______ _________
(A) MATERIAL. QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Partal wood. 1.48 Cft. 1700.00 P.Cft. 2516.00

Bolts, Nuts and Nails. L.S 50.00

Oiling, greasing,Soap, etc. L.S 50.00


________________________________ _________ _____ _______ _______ _________
TOTAL 2616.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 261.60
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 2877.60
____ ________________________________ _________ _____ _______ _______ _________

____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 148/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Labour for erection and
removal including earth
work and oiling, greasing,
etc.
Carpanter 2nd class. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00


________________________________ _________ _____ _______ _______ _________
Rs: 587.50
________________________________ _________ _____ _______ _______ _________
Sundries. (except sawing) 10.00 % 58.75
________________________________ _________ _____ _______ _______ _________
TOTAL 646.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 64.63
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 710.88
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 3588.48
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Sft. Rs: 3588.48
____ ________________________________ _________ _____ _______ _______ _________

____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 149/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.

Chapter No. 3 150/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.

Chapter No. 3 151/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

Cement sand mortar (1:6)

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
MATERIAL FOR MORTAR 100 Cft.
Cement. 16.40 Cwt. 400.00 P.bag. 6560.00
Sand. 142.0 Cft. 2425.00 % Cft. 3443.50
________________________________ _________ _____ _______ _______ _________
TOTAL 10003.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 1000.35
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 11003.85
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Labour for 100 Cft mortar.
For measuring, curing
depositing & mixing etc.
Coolies. 2.50 Nos: 250.00 P.day. 625.00
Bahishti. 1.50 Nos: 250.00 P.day. 375.00
________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 1000.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 100.00
________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 1100.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 110.00
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 1210.00
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12213.85
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Cft. Rs: 12213.85
Total material & labour for one Cft. Rs: 122.14
Total material & labour for one Cft. say Rs: 122.14
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 152/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

19. Providing and laying 1:4:8 cement concrete solid block masonary
set in 1:6 cement sand mortar in plinth & foundation i/c racking
of joints and curing, etc, complete.
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Material&labour for 120 cft.
Screened & graded bajri of 96.0 Cft. 3100.00 % Cft. 2976.00
required gauge.
Sand (Hill) 48.00 Cft. 2425.00 % Cft. 1164.00
Cement. 9.60 Cwt. 400.00 P.bag. 3840.00
MATERIAL FOR MORTAR 20 Cft. 20.00 Cft. 10003.5 % Cft. 2000.70
________________________________ _________ _____ _______ _______ _________
TOTAL 9980.70
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 998.07
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 10978.77
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
LABOUR FOR MAKING BLOCKS
________________________________ _________ _____ _______ _______ _________
Masons. 0.03 Nos: 450.00 P.day. 12.15
Coolies. 0.03 Nos: 250.00 P.day. 6.76
Bhishti. 0.03 Nos: 250.00 P.day. 6.76
25.66
For making block of
12"*9"*6" size 266 Nos: or
99.75 cft. 99.75 Cft. 25.66 P.Cft. 2559.93
Laying & curing B.Masonary.
Mason. 1.50 Nos: 450.00 P.day. 675.00
Coolies. 1.50 Nos: 250.00 P.day. 375.00
Bahishti. 1.50 Nos: 250.00 P.day. 375.00
Labour for 20 Cft mortar.
For measuring, curing 20.00 Cft. 1100.00 % Cft. 220.00
depositing & mixing etc.
________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 4204.93
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 420.49
________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 4625.43
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 462.54
TOTAL PART " B " 4239.98 5087.97
________________________________ _________ _____ _______ % Cft _________
TOTAL (MATERIAL + LABOUR) 16066.74
Total material & labour for 120 Cft. Rs: 16066.74

Chapter No. 3 153/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Cft. Rs: 13388.95


Total material & labour for 100 Cft. Say Rs: 13388.95
S/N D E S C R I P T I O N.

20. Providing and laying 1:4:8 cement concrete solid block masonary
wall above 6" in thickness set in 1:6 cement sand mortar in
ground floor superstructure i/c racking of joints and curing,
etc, complete.

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Material&labour for 120 cft.
Screened & graded bajri of 96.0 Cft. 3100.00 % Cft. 2976.00
required gauge.
Sand (Hill) 48.00 Cft. 2425.00 % Cft. 1164.00
Cement. 9.60 Cwt. 400.00 P.bag. 3840.00
MATERIAL FOR MORTAR 20 Cft. 20.00 Cft. 10003.5 % Cft. 2000.70
________________________________ _________ _____ _______ _______ _________
TOTAL 9980.70
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 998.07
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 10978.77
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
For making block of
12"*9"*6" size 266 Nos: or
99.75 cft. 99.75 Cft. 25.66 P.Cft. 2559.93
Laying & curing B.Masonary.
Mason. 2.00 Nos: 450.00 P.day. 900.00
Coolies. 2.00 Nos: 250.00 P.day. 500.00
Bahishti. 1.50 Nos: 250.00 P.day. 375.00
Labour for 20 Cft mortar.
For measuring, curing 20.00 Cft. 1100.00 % Cft. 220.00
depositing & mixing etc.
TOTAL Rs: 4554.93
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 455.49
________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 5010.43
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 501.04
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 4592.89 5511.47
________________________________ _________ _____ _______ % Cft. _________
TOTAL (MATERIAL + LABOUR) 16490.24

Chapter No. 3 154/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

________________________________ _________ _____ _______ _______ _________


Total material & labour for 120 Cft. Rs: 16490.24
Total material & labour for 100 Cft. Rs: 13741.87
Total material & labour for 100 Cft. Say Rs: 13741.87
S/N D E S C R I P T I O N.

21 Providing and laying 1:3:6 cement concrete solid block masonary


set in 1:6 cement sand mortar in plinth & foundation i/c racking
of joints and curing, etc, complete.

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Material&labour for 120 cft.
Screened & graded bajri of 88.9 Cft. 3100.00 % Cft. 2757.14
required gauge.
Sand (Hill) 44.47 Cft. 2425.00 % Cft. 1078.40
Cement. 12.76 Cwt. 400.00 P.bag. 5104.00
MATERIAL FOR MORTAR 20 Cft. 20.00 Cft. 10003.5 % Cft. 2000.70
________________________________ _________ _____ _______ _______ _________
TOTAL 10940.24
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 1094.02
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 12034.26
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
For making block of
12"*9"*6" size 266 Nos: or
99.75 cft. 99.75 Cft. 25.66 P.Cft. 2559.93
Laying & curing B.Masonary.
Mason. 1.50 Nos: 450.00 P.day. 675.00
Coolies. 1.50 Nos: 250.00 P.day. 375.00
Bahishti. 1.50 Nos: 250.00 P.day. 375.00
Labour for 20 Cft mortar.
For measuring, curing 20.00 Cft. 1100.00 % Cft. 220.00
depositing & mixing etc.
________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 4204.93
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 420.49
________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 4625.43
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 462.54
________________________________ _________ _____ _______ _______ _________

Chapter No. 3 155/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL PART " B " 4239.98 5087.97


________________________________ _________ _____ _______ % Cft. _________
TOTAL (MATERIAL + LABOUR) 17122.23
Total material & labour for 120 Cft. Rs: 17122.23
Total material & labour for 100 Cft. Rs: 14268.526
Total material & labour for 100 Cft. Say Rs: 14268.53
S/N D E S C R I P T I O N.

22. Providing and laying 1:3:6 cement concrete solid block masonary
wall above 6" in thickness set in 1:6 cement sand mortar in
ground floor superstructure i/c racking of joints and curing,
etc, complete.

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Material&labour for 120 cft.
Screened & graded bajri of 88.9 Cft. 3100.00 % Cft. 2757.14
required gauge.
Sand (Hill) 44.47 Cft. 2425.00 % Cft. 1078.40
Cement. 12.76 Cwt. 400.00 P.bag. 5104.00
MATERIAL FOR MORTAR 20 Cft. 20.00 Cft. 10003.5 % Cft. 2000.70
________________________________ _________ _____ _______ _______ _________
TOTAL 10940.24
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 1094.02
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 12034.26
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
For making block of 12"*9"*6" size
266 Nos : or 99.75 cft. 99.75 Cft. 25.66 P.Cft. 2559.93
Laying & curing B.Masonary.
Mason. 2.00 Nos: 450.00 P.day. 900.00
Coolies. 2.00 Nos: 250.00 P.day. 500.00
Bahishti. 1.50 Nos: 250.00 P.day. 375.00
Labour for 20 Cft mortar.
For measuring, curing 20.00 Cft. 1100.00 % Cft. 220.00
depositing & mixing etc.
________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 4554.93
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 455.49
________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 5010.43
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 501.04

Chapter No. 3 156/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

________________________________ _________ _____ _______ _______ _________


TOTAL PART " B " 4592.89 5511.47
________________________________ _________ _____ _______ % Cft. _________
TOTAL (MATERIAL + LABOUR) 17545.73
Total material & labour for 120 Cft. Rs: 17545.73
Total material & labour for 100 Cft. Rs: 14621.44
Total material & labour for 100 Cft. Say Rs: 14621.44
S/N D E S C R I P T I O N.

23. Providing and laying 1:3:6 cement concrete solid block masonary
wall above 6" and below in thickness set in 1:6 cement sand
mortar in ground floor superstructure i/c racking of joints and
curing, etc, complete.

____ ________________________________ _________ _____ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Material&labour for 120 cft.
Screened & graded bajri of 88.94 Cft. 3100.00 % Cft. 2757.14
required gauge.
Sand (Hill) 44.47 Cft. 2425.00 % Cft. 1078.40
Cement. 12.76 Cwt. 400.00 P.bag. 5104.00
MATERIAL FOR MORTAR 20 Cft. 20.00 Cft. 10003.5 % Cft. 2000.70
________________________________ _________ _____ _______ _______ _________
TOTAL 10940.24
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 1094.02
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 12034.26
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
For making block of
12"*9"*4" size 798 Nos:
Mason. 6.00 Nos: 450.00 P.day. 2700.00
Cooly. 4.00 Nos: 250.00 P.day. 1000.00
Laying & curing B.Masonary.
Mason. 2.00 Nos: 450.00 P.day. 900.00
Coolies. 2.00 Nos: 250.00 P.day. 500.00
Bahishti. 1.50 Nos: 250.00 P.day. 375.00
Labour for 20 Cft mortar.
For measuring, curing 20.00 Cft. 1100.00 % Cft. 220.00
depositing & mixing etc.
________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 5695.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 569.50
________________________________ _________ _____ _______ _______ _________

Chapter No. 3 157/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL Rs: 6264.50


________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 626.45
TOTAL PART " B " 5742.46 6890.95
________________________________ _________ _____ _______ % Cft. _________
TOTAL (MATERIAL + LABOUR) 18925.21
Total material & labour for 120 Cft. Rs: 18925.21
Total material & labour for 100 Cft. Rs: 15771.01
Total material & labour for 100 Cft. Say Rs: 15771.01
S/N D E S C R I P T I O N.

24 Drilling holes in R.C. trough.


Assume for 10 Nos. (Unit of rate per No.)
____ ________________________________ _________ _____ _______ _______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Blacksmith. 1.00 Nos: 450.00 P.day. 450.00
Coolies. 1.00 Nos: 250.00 P.day. 250.00
________________________________ _________ _____ _______ _______ _________
Rs: 700.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 70.00
________________________________ _________ _____ _______ _______ _________
TOTAL 770.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 77.00
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 847.00
________________________________ _________ _____ _______ _______ _________
TOTAL (LABOUR) 847.00
________________________________ _________ _____ _______ _______ _________
Total labour rate per 10 Nos. Rs: 847.00
Total labour rate per No. Rs: 84.70
____ ________________________________ _________ _____ _______ _______ _________

____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 158/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

25 Erecting and carting sun shades of precast R.C. concrete (upto


5.0'*2.5')
Assume for 5 Nos. (Unit of rate for each No.)
____ ________________________________ _________ _____ _______ _______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Mason. 0.50 Nos: 450.00 P.day. 225.00
Coolies. 2.00 Nos: 250.00 P.day. 500.00
________________________________ _________ _____ _______ _______ _________
Rs: 725.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 72.50
________________________________ _________ _____ _______ _______ _________
TOTAL 797.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 79.75
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 877.25
________________________________ _________ _____ _______ _______ _________
TOTAL (LABOUR) 877.25
________________________________ _________ _____ _______ _______ _________
Total labour rate for 5 Nos. Rs: 877.25
Total labour rate per each No. say Rs: 175.45
____ ________________________________ _________ _____ _______ _______ _________

____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 159/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
26 Reinforced cement concrete spout including fixing in position
with top and bottom khuras.
(Unit of rate for each No.)
____ ________________________________ _________ _____ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 0.25 Cwt. 400.00 P.Cwt. 100.00
Sand. 1.00 Cft. 2425.00 % Cft. 24.25
Stone aggregates.(Shingle) 2.00 Cft. 3075.00 % Cft. 61.50

________________________________ _________ _____ _______ _______ _________


TOTAL. 185.75
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 18.58
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 204.33
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Mason. 0.40 Nos. 450.00 P.day. 180.00
Coolies. 0.40 Nos. 250.00 P.day. 100.00

________________________________ _________ _____ _______ _______ _________


TOTAL Rs: 280.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 28.00
________________________________ _________ _____ _______ _______ _________
TOTAL 308.00
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 30.80
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 338.80
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 543.13
________________________________ _________ _____ _______ _______ _________
Total material & labour for each No. Rs: 543.13
Total material & labour for each No. say Rs: 524.98
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 160/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N _
27 Damp proof course with cement sand and shingle concrete (1:2:4)
including 2-coats of asphaltic mixture.
(a) 1-1/2" thick.
(Unit of rate for 100 Sft.)
____ ________________________________ _________ _____ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 2.25 Cwt. 435.00 P.Cwt. 978.75
Sand. 5.50 Cft. 3535.57 % Cft. 194.46
Stone aggregates. 11.00 Cft. 3271.88 % Cft. 359.91
Depreciation charges of L.S. 20.00
wood & templates.
Fuel and Brush. L.S. 20.00
Bitumen. 20.00 Lbs. 800.0 P.Ton. 7.14

________________________________ _________ _____ _______ _______ _________


TOTAL. 1580.26
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 158.03
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 1738.28
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Mason. 0.50 Nos. 450.00 P.day. 225.00
Coolies. 2.00 Nos. 250.00 P.day. 500.00
Bahishti. 0.25 Nos. 250.00 P.day. 62.50
Carpenter. 0.15 Nos. 400.00 P.day. 60.00
________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 847.50
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 84.75
________________________________ _________ _____ _______ _______ _________
TOTAL 932.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 93.23
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 1025.48
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 2763.76
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Sft. Rs: 2763.76
Total material & labour for 100 Sft. say Rs: 2586.00
____ ________________________________ _________ _____ _______ _______ _________

____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 161/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N _
27 Damp proof course with cement sand and shingle concrete (1:2:4)
including 2-coats of asphaltic mixture.
(b) 2" thick.
(Unit of rate for 100 Sft.)
____ ________________________________ _________ _____ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 2.93 Cwt. 400.00 P.Cwt. 1172.00
Sand. 7.50 Cft. 2425.00 % Cft. 181.88
Stone aggregates. (Shingle). 15.00 Cft. 3075.00 % Cft. 461.25
Depreciation charges of L.S. 20.00
wood & templates.
Fuel and Brush. L.S. 20.00
Bitumen. 20.00 Lbs. 86213.0 P.Ton. 769.76

________________________________ _________ _____ _______ _______ _________


TOTAL. 2624.88
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 262.49
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 2887.37
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Mason. 0.50 Nos. 450.00 P.day. 225.00
Coolies. 2.00 Nos. 250.00 P.day. 500.00
Bahishti. 0.25 Nos. 250.00 P.day. 62.50
Carpenter. 0.15 Nos. 400.00 P.day. 60.00
________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 847.50
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 84.75
________________________________ _________ _____ _______ _______ _________
TOTAL 932.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 93.23
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 1025.48
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 3912.85
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Sft. Rs: 3912.85
Total material & labour for 100 Sft. say Rs: 3913.00
____ ________________________________ _________ _____ _______ _______ _________

____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 162/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N _
27 Damp proof course with cement sand and shingle concrete (1:2:4)
including 2-coats of asphaltic mixture.
(c) 3" thick.
(Unit of rate for 100 Sft.)
____ ________________________________ _________ _____ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
________________________________ _________ _____ _______ _______ _________
Cement. 4.50 Cwt. 400.00 P.Cwt. 1800.00
Sand. 11.00 Cft. 2425.00 % Cft. 266.75
Stone aggregates.(Shingle) 22.00 Cft. 3075.00 % Cft. 676.50
Depreciation charges of L.S. 20.00
wood & templates.
Fuel and Brush. L.S. 20.00
Bitumen. 20.00 Lbs. 86213.0 P.Ton. 769.76

________________________________ _________ _____ _______ _______ _________


TOTAL. 3553.01
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 355.30
________________________________ _________ _____ _______ _______ _________
TOTAL PART " A " 3908.31
________________________________ _________ _____ _______ _______ _________
(B) LABOUR
________________________________ _________ _____ _______ _______ _________
Mason. 0.50 Nos. 450.00 P.day. 225.00
Coolies. 2.00 Nos. 250.00 P.day. 500.00
Bahishti. 0.25 Nos. 250.00 P.day. 62.50
Carpenter. 0.25 Nos. 400.00 P.day. 100.00
________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 887.50
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 88.75
________________________________ _________ _____ _______ _______ _________
TOTAL 976.25
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 97.63
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 1073.88
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 4982.18
________________________________ _________ _____ _______ _______ _________
Total material & labour for 100 Sft. Rs: 4982.18
Total material & labour for 100 Sft. say Rs: 4982.00
____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 163/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

NEW ITEMS 2002


____ ________________________________ _________ _____ _______ _______ _________

S/N D E S C R I P T I O N.

28 Extra labour for lifting of steel above first floor for every additional flour.
____ ________________________________ _________ _____ _______ _______ _________

(B) LABOUR
________________________________ _________ _____ _______ _______ _________

Coolies.for lifting 0.50 Nos: 250.00 P.day. 125.00


________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 125.00
________________________________ _________ _____ _______ _______ _________
Sundries. 10.00 % 12.50
________________________________ _________ _____ _______ _______ _________
TOTAL Rs: 137.50
________________________________ _________ _____ _______ _______ _________
Contractor's profit 10.00 % 13.75
________________________________ _________ _____ _______ _______ _________
TOTAL PART " B " 151.25
________________________________ _________ _____ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 302.50
________________________________ _________ _____ _______ _______ _________
Total labour for P.cwt. Rs: 302.50
Total labour for P.cwt. Say Rs: 302.50

____ ________________________________ _________ _____ _______ _______ _________

Chapter No. 3 164/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

BRICK MASONARY.
FIRST FILL THIS SHEET.

MATERIAL. RATE UNITE

1 Pucca Brick.(9"x4-1/2"x3") 5000 % 0 Nos


(Ist Class)
2 Earth ,Stiffclay 500 % Cft

3 Cement. 400 P.bag

4 Sand 2425 % Cft.

5 Slaked Lime 375 P.Mand

6 Surkhi 2250 % Cft.

7 partal wood 1700 P.Cft.

8 Fire clay Brick. 5300 % 0 Nos.

9 Aluminia Cement. 650 P.bag

10 Crushed fire bricks. 2500 % Cft.

11 Hoop Iron. 2500 P.Cwt

12 Sundried Brick. 1200 % 0 Nos

13 Moulded Brick. 4800 % 0 Nos

14 Pit sand. 900 % Cft.

LABOUR RATE UNITE

1 MASSON (g-1) , Black Smith. 450 P.day

2 Coolies. 250 P.day

3 Bahishti, Skilled.Cooly. 250 P.day

Chapter No. 4 165/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

CHAPTER -5
==================
B R I C K M A S O N A R Y.
============================
(1) The rates are to be reduced proportionately if II or III Class
Bricks are used.
(2) Rates for all finished works include the removal of surplus
debries, un-used material and by-products.
(3) For handling all types of materials for short lead including
carraige upto 3 chains, nothing is to be paid as extra. Where
rehandling and carraige involves an extra lead beyond 3 chains,
carraige for whole of the distance should be provided in the
estimate.
(4) Masonary of boundary wall to be considered as masonary other
than buildings for items 1, 4, 5, 15, 20, 21, 23.
(5) The rate of lime mortar also includes grinding of mortar.
(6) The rates includes the cost of scaffolding and its removal.

Chapter No. 4 166/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
1. Pacca brick work in mud mortar in building.
(a) In foundation and plinth.
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pucca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00
Good earth or stiff clay 35.00 Cft. 500.00 % Cft. 175.00
for mud mortar.
__________________________ _______ ______ _______ _______ _________
TOTAL 6925.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 692.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 7617.50
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
For Masonary Work.
Masons. 1.50 Nos: 450.00 P.day. 675.00
Skilled Coolies. 2.00 Nos: 250.00 P.day. 500.00
Bahishti. 0.125 Nos: 250.00 P.day. 31.25
For Mud Mortar.
Skilled. Coolies. 0.667 Nos: 250.00 P.day. 166.67
Bahishti. 0.333 Nos: 250.00 P.day. 83.33
__________________________ _______ ______ _______ _______ _________
Rs: 1456.25
Sundries. 10.00 % 145.63
__________________________ _______ ______ _______ _______ _________
TOTAL 1601.88
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 160.19
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1762.06
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 9379.56
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 9379.56

Chapter No. 4 167/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

1. Pacca brick work in mud mortar in building.


(b) In ground floor.

_____ __________________________ _______ ______ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pucca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Good earth or stiff clay 35.00 Cft. 500.00 % Cft. 175.00


for mud mortar.
TOTAL 6925.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 692.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 7617.50
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

Bahishti. 0.125 Nos: 250.00 P.day. 31.25


For Mud Mortar.
Skilled Coolies. 0.667 Nos: 250.00 P.day. 166.67

Bahishti. 0.333 Nos: 250.00 P.day. 83.33

__________________________ _______ ______ _______ _______ _________


Rs: 1931.25
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 193.13
__________________________ _______ ______ _______ _______ _________
TOTAL 2124.38
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 212.44
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2336.81
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 168/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (MATERIAL + LABOUR) 9954.31


__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 9954.31
_____ __________________________ _______ ______ _______ _______ _________

S/N D E S C R I P T I O N.

2. Add extra labour in item No:1 for brick work.


(i) In First floor.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.

Masons. 0.25 Nos: 450.00 P.day. 112.50

Skilled Coolies. 1.00 Nos: 250.00 P.day. 250.00


__________________________ _______ ______ _______ _______ _________
Rs: 362.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 36.25
__________________________ _______ ______ _______ _______ _________
TOTAL 398.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 39.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 438.63
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 226.90
_____ __________________________ _______ ______ _______ _______ _________
S/N D E S C R I P T I O N.

2. Add extra labour in item No:1 for brick work.


(ii) In Second floor.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.

Masons. 0.75 Nos: 450.00 P.day. 337.50

Skilled Coolies. 2.00 Nos: 250.00 P.day. 500.00


__________________________ _______ ______ _______ _______ _________
Rs: 837.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 83.75
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 169/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 921.25
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 92.13
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1013.38
Total material & labour for 100 Cft. Rs: 535.45
S/N D E S C R I P T I O N.
2. Add extra labour in item No:1 for brick work.
(iii) In Third Floor.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.

Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled 'Coolies. 3.00 Nos: 250.00 P.day. 750.00


__________________________ _______ ______ _______ _______ _________
Rs: 1312.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 131.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1443.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 144.38
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1588.13
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 844.00
_____ __________________________ _______ ______ _______ _______ _________
S/N D E S C R I P T I O N.

2. Add extra labour in item No:1 for brick work.


(iv) In Fourth and subsequent Floor.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
For Masonary Work.

Masons. 2.25 Nos: 450.00 P.day. 1012.50

Skilled bCoolies. 4.50 Nos: 250.00 P.day. 1125.00


__________________________ _______ ______ _______ _______ _________
Rs: 2137.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 213.75
__________________________ _______ ______ _______ _______ _________
TOTAL 2351.25

Chapter No. 4 170/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

__________________________ _______ ______ _______ _______ _________


Contractor's profit 10.00 % 235.13
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2586.38
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 1388.50

Chapter No. 4 171/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
3. Pacca brick work in mud mortar other than building.
(i) Upto 20 feet hieght.
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pucca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00
Good earth or stiff clay 35.00 Cft. 500.00 % Cft. 175.00
for mud mortar.
__________________________ _______ ______ _______ _______ _________
TOTAL 6925.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 692.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 7617.50
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00
Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00
For Mud Mortar.
Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00
Bahishti. 0.333 Nos: 250.00 P.day. 83.33
__________________________ _______ ______ _______ _______ _________
Rs: 1983.33
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 198.33
__________________________ _______ ______ _______ _______ ________
TOTAL 2181.67
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 218.17
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2399.83
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 10017.33
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 10017.33
_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 172/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
3. Pacca brick work in mud mortar other than building.
(ii) Extra labour for every 5 feet additional hieght.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
Masons. 0.25 Nos: 450.00 P.day. 112.50
Skilled Coolies. 1.00 Nos: 250.00 P.day. 250.00
__________________________ _______ ______ _______ _______ _________
TOTAL Rs: 362.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 36.25
__________________________ _______ ______ _______ _______ _________
TOTAL 398.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 39.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 438.63
__________________________ _______ ______ _______ _______ _________
Labour rate for 100 Cft. Rs: 226.90

_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 173/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ __________________________ _______ ______ _______ _______ _________

S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(i) In cement sand mortar.
(a) 1:2
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 8.00 Cwt. 400.00 P.bag 3200.00

Sand. 20.00 Cft. 2425.00 % Cft. 485.00

TOTAL 10435.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 1043.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 11478.50
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 192.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2112.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 211.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2324.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 13802.71

Chapter No. 4 174/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

__________________________ _______ ______ _______ _______ _________


Total material & labour for 100 Cft. Rs: 13802.71

S/N D E S C R I P T I O N.

4. Pacca brick work in foundation and plinth


(i) In cement sand mortar.
(b) 1:3
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 6.00 Cwt. 400.00 P.bag 2400.00

Sand. 22.50 Cft. 2425.00 % Cft. 545.63

TOTAL 9695.63
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 969.56
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 10665.19
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 192.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2112.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 211.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2324.21
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 175/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (MATERIAL + LABOUR) 12989.40


__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 4401.95

S/N D E S C R I P T I O N.

4. Pacca brick work in foundation and plinth


(i) In cement sand mortar.
(c) 1:4
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 4.80 Cwt. 400.00 P.bag 1920.00

Sand. 24.00 Cft. 2425.00 % Cft. 582.00

TOTAL 9252.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 925.20
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 10177.20
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 192.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2112.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 211.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2324.21

Chapter No. 4 176/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

__________________________ _______ ______ _______ _______ _________


TOTAL (MATERIAL + LABOUR) 12501.41
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 12501.41

Chapter No. 4 177/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4. Pacca brick work in foundation and plinth


(i) In cement sand mortar.
(d) 1:5
_____ __________________________ _______ ______ _______ _______ ssssssssss
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 6000.00 %0 Nos: 8100.00

Cement. 4.00 Cwt. 575.00 P.bag 2300.00

Sand. 25.00 Cft. 3000.00 % Cft. 750.00


TOTAL 11150.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 25.00 % 2787.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 13937.50
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 1200.00 P.day. 2400.00

Skilled Coolies. 2.50 Nos: 800.00 P.day. 2000.00

Bahishti. 0.250 Nos: 800.00 P.day. 200.00


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 800.00 P.day. 666.67

Bahishti. 0.500 Nos: 800.00 P.day. 400.00

__________________________ _______ ______ _______ _______ _________


Rs: 5666.67
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 566.67
__________________________ _______ ______ _______ _______ _________
TOTAL 6233.33
__________________________ _______ ______ _______ _______ _________
Contractor's profit 25.00 % 1558.33
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 7791.67
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 21729.17
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 21729.17

Chapter No. 4 178/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4. Pacca brick work in foundation and plinth


(i) In cement sand mortar.
(e) 1:6
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 3.44 Cwt. 400.00 P.bag 1376.00

Sand. 25.70 Cft. 2425.00 % Cft. 623.23


TOTAL 8749.23
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 874.92
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9624.15
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 1920.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 192.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2112.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 211.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2324.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 11948.36
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 3865.15

Chapter No. 4 179/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4. Pacca brick work in foundation and plinth


(i) In cement sand mortar.
(f) 1:7
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 3.00 Cwt. 400.00 P.bag 1200.00

Sand. 26.50 Cft. 2425.00 % Cft. 642.63


TOTAL 8592.63
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 859.26
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9451.89
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 1920.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 192.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2112.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 211.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2324.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 11776.10
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 3773.85

Chapter No. 4 180/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4. Pacca brick work in foundation and plinth


(i) In cement sand mortar.
(g) 1:8
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 2.66 Cwt. 400.00 P.bag 1064.00

Sand. 26.67 Cft. 2425.00 % Cft. 646.75


TOTAL 8460.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 846.07
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9306.82
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 1920.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 192.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2112.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 211.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2324.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 11631.03
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 11631.03

Chapter No. 4 181/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(ii) In lime cement sand mortar.
(a) 1:1:6
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.60 Mand 375.00 P.Mand 600.00

Cement. 3.20 Cwt. 400.00 P.bag 1280.00

Sand. 24.00 Cft. 2425.00 % Cft. 582.00


TOTAL 9212.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 921.20
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 10133.20
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 192.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2112.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 211.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2324.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12457.41
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 182/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Cft. Rs: 12457.41


S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(ii) In lime cement sand mortar.
(b) 1:1:7
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.42 Mand 375.00 P.Mand 532.50

Cement. 2.85 Cwt. 400.00 P.bag 1140.00

Sand. 24.78 Cft. 2425.00 % Cft. 600.92

__________________________ _______ ______ _______ _______ _________


TOTAL 9023.42
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 902.34
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9925.76
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00


__________________________ _______ ______ _______ _______ _________
Rs: 1920.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 192.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2112.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 211.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2324.21

Chapter No. 4 183/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (MATERIAL + LABOUR) 12249.96


Total material & labour for 100 Cft. Rs: 3899.05
S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(ii) In lime cement sand mortar.
(c) 1:1:8
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.28 Mand 375.00 P.Mand 480.00

Cement. 2.56 Cwt. 400.00 P.bag 1024.00

Sand. 25.60 Cft. 2425.00 % Cft. 620.80


TOTAL 8874.80
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 887.48
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9762.28
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 192.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2112.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 211.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2324.21
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 184/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (MATERIAL + LABOUR) 12086.49


__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 3823.85
S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(ii) In lime cement sand mortar.
(d) 1:1:9
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.16 Mand 375.00 P.Mand 435.00

Cement. 2.32 Cwt. 400.00 P.bag 928.00

Sand. 26.20 Cft. 2425.00 % Cft. 635.35


TOTAL 8748.35
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 874.84
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9623.19
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: P.day.


250.00 125.00
Rs: 1920.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 192.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2112.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 211.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2324.21
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 185/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (MATERIAL + LABOUR) 11947.39


__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 3760.80

Chapter No. 4 186/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(ii) In lime cement sand mortar.
(e) 1:1:10
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.07 Mand 375.00 P.Mand 401.25

Cement. 2.14 Cwt. 400.00 P.bag 856.00

Sand. 26.66 Cft. 2425.00 % Cft. 646.51


TOTAL 8653.76
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 865.38
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9519.13
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
Sundries. 10.00 % 192.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2112.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 211.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2324.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 11843.34
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 3713.55

Chapter No. 4 187/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(iii In lime sand surkhi mortar.
(a) 1:1:1
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 4.65 Mand 375.00 P.Mand 1743.75

Sand. 11.67 Cft. 2425.00 % Cft. 283.00

Surkhi. 11.67 Cft. 2250.00 % Cft. 262.58


TOTAL 9039.32
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 903.93
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9943.25
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
Sundries. 10.00 % 192.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2112.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 211.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2324.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12267.46
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 3668.05

Chapter No. 4 188/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(iv) In lime sand mortar.
1:2
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 4.67 Mand 375.00 P.Mand 1751.25

Sand. 23.33 Cft. 2425.00 % Cft. 565.75


TOTAL 9067.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 906.70
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9973.70
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 1920.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 192.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2112.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 211.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2324.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12297.91
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 189/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Cft. Rs: 3657.05

S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(v) In lime surkhi mortar.
(a) 2:3
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 5.60 Mand 375.00 P.Mand 2100.00

Surkhi. 21.00 Cft. 2250.00 % Cft. 472.50


__________________________ _______ ______ _______ _______ _________
TOTAL 9322.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 932.25
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 10254.75
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

SkilledCoolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
SkilledCoolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 192.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2112.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 211.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2324.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12578.96

Chapter No. 4 190/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

__________________________ _______ ______ _______ _______ _________


Total material & labour for 100 Cft. Rs: 12578.96

S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(v) In lime surkhi mortar.
(b) 1:2
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 4.67 Mand 375.00 P.Mand 1751.25

Surkhi. 23.33 Cft. 2250.00 % Cft. 524.93


__________________________ _______ ______ _______ _______ _________
TOTAL 9026.18
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 902.62
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9928.79
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 192.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2112.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 211.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2324.21
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 191/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (MATERIAL + LABOUR) 12253.00


__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 3683.15

Chapter No. 4 192/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(v) In lime surkhi mortar.
(c) 1:3
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 3.50 Mand 375.00 P.Mand 1312.50

Surkhi. 26.25 Cft. 2250.00 % Cft. 590.63


TOTAL 8653.13
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 865.31
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9518.44
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 1920.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 192.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2112.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 211.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2324.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 11842.65
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 3562.50

Chapter No. 4 193/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5 Pacca brick work in ground floor (including striking of joints)


(i) In cement sand mortar.
(a) 1:2
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 8.00 Cwt. 400.00 P.bag 3200.00

Sand. 20.00 Cft. 2425.00 % Cft. 485.00

__________________________ _______ ______ _______ _______ _________


TOTAL 10435.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 1043.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 11478.50
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 2520.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 252.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2772.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 277.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 3050.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 14528.71
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 194/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Cft. Rs: 14528.71


S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(i) In cement sand mortar.
(b) 1:3
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 6.00 Cwt. 400.00 P.bag 2400.00

Sand. 22.50 Cft. 2425.00 % Cft. 545.63


TOTAL 9695.63
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 969.56
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 10665.19
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2520.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 252.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2772.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 277.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 3050.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 13715.40
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 195/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Cft. Rs: 4783.10

Chapter No. 4 196/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(i) In cement sand mortar.
(c) 1:4
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 4.80 Cwt. 400.00 P.bag 1920.00

Sand. 24.00 Cft. 2425.00 % Cft. 582.00


TOTAL 9252.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 925.20
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 10177.20
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2520.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 252.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2772.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 277.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 3050.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 13227.41
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 13227.41

Chapter No. 4 197/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(i) In cement sand mortar.
(d) 1:5
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 4.00 Cwt. 400.00 P.bag 1600.00

Sand. 25.00 Cft. 2425.00 % Cft. 606.25


TOTAL 8956.25
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 895.63
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9851.88
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2520.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 252.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2772.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 277.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 3050.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12902.08
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 4363.70

Chapter No. 4 198/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(i) In cement sand mortar.
(e) 1:6
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 3.44 Cwt. 400.00 P.bag 1376.00

Sand. 25.70 Cft. 2425.00 % Cft. 623.23


TOTAL 8749.23
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 874.92
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9624.15
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2520.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 252.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2772.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 277.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 3050.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12674.36
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 4246.30

Chapter No. 4 199/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(i) In cement sand mortar.
(f) 1:7
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 3.00 Cwt. 400.00 P.bag 1200.00

Sand. 26.50 Cft. 2425.00 % Cft. 642.63


TOTAL 8592.63
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 859.26
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9451.89
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2520.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 252.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2772.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 277.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 3050.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12502.10
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 4155.00

Chapter No. 4 200/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(i) In cement sand mortar.
(g) 1:8
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 2.66 Cwt. 400.00 P.bag 1064.00

Sand. 26.67 Cft. 2425.00 % Cft. 646.75


TOTAL 8460.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 846.07
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9306.82
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2520.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 252.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2772.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 277.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 3050.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12357.03
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 4082.70

Chapter No. 4 201/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(ii) In lime cement sand mortar.
(a) 1:1:6
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.60 Mand 375.00 P.Mand 600.00

Cement. 3.20 Cwt. 400.00 P.bag 1280.00

Sand. 24.00 Cft. 2425.00 % Cft. 582.00


TOTAL 9212.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 921.20
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 10133.20
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 2520.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 252.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2772.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 277.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 3050.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 13183.41
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 202/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Cft. Rs: 4373.05


S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(ii) In lime cement sand mortar.
(b) 1:1:7
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.42 Mand 375.00 P.Mand 532.50

Cement. 2.85 Cwt. 400.00 P.bag 1140.00

Sand. 24.78 Cft. 2425.00 % Cft. 600.92


TOTAL 9023.42
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 902.34
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9925.76
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Sundries. 10.00 % #REF!
__________________________ _______ ______ _______ _______ _________
TOTAL #REF!
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % #REF!
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " #REF!
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) #REF!
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 203/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Cft. Rs: 4280.20

Chapter No. 4 204/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(ii) In lime cement sand mortar.
(c) 1:1:8
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.28 Mand 375.00 P.Mand 480.00

Cement. 2.56 Cwt. 400.00 P.bag 1024.00

Sand. 25.60 Cft. 2425.00 % Cft. 620.80


TOTAL 8874.80
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 887.48
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9762.28
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: P.day.


250.00 125.00
Rs: 2520.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 252.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2772.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 277.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 3050.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12812.49
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 4204.95

Chapter No. 4 205/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(ii) In lime cement sand mortar.
(d) 1:1:9
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.16 Mand 375.00 P.Mand 435.00

Cement. 2.32 Cwt. 400.00 P.bag 928.00

Sand. 26.20 Cft. 2425.00 % Cft. 635.35


TOTAL 8748.35
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 874.84
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9623.19
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 2520.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 252.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2772.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 277.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 3050.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12673.39
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 206/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Cft. Rs: 4141.95


S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(ii) In lime cement sand mortar.
(e) 1:1:10
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.07 Mand 375.00 P.Mand 401.25

Cement. 2.14 Cwt. 400.00 P.bag 856.00

Sand. 26.66 Cft. 2425.00 % Cft. 646.51


TOTAL 8653.76
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 865.38
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9519.13
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: P.day.


250.00 125.00
Rs: 2520.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 252.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2772.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 277.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 3050.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12569.34
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 207/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Cft. Rs: 4094.75

Chapter No. 4 208/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(iii In lime sand surkhi mortar.
1:1:1
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 4.65 Mand 375.00 P.Mand 1743.75

Sand. 11.67 Cft. 400.00 % Cft. 46.68

Surkhi. 11.67 Cft. 2250.00 % Cft. 262.58


TOTAL 8803.01
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 880.30
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9683.31
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2520.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 252.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2772.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 277.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 3050.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12733.51

Chapter No. 4 209/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Cft. Rs: 4029.30


S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(iv) In lime sand mortar.
1:2
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 4.67 Mand 375.00 P.Mand 1751.25

Sand. 23.33 Cft. 2425.00 % Cft. 565.75


TOTAL 9067.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 906.70
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9973.70
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2520.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 252.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2772.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 277.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 3050.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 13023.91
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 210/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Cft. Rs: 4038.65

Chapter No. 4 211/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Pacca brick work in grund floor (including striking of joints)


(v) In lime surkhi mortar.
(a) 2:3
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 5.60 Mand 375.00 P.Mand 2100.00

Surkhi. 21.00 Cft. 2250.00 % Cft. 472.50


TOTAL 9322.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 932.25
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 10254.75
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2520.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 252.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2772.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 277.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 3050.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 13304.96
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 13304.96

Chapter No. 4 212/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor including striking of joints)


(v) In lime surkhi mortar.
(b) 1:2
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 4.67 Mand 375.00 P.Mand 1751.25

Surkhi. 23.33 Cft. 2250.00 % Cft. 524.93


TOTAL 9026.18
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 902.62
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9928.79
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2520.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 252.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2772.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 277.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 3050.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12979.00
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 4064.30

Chapter No. 4 213/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(v) In lime surkhi mortar.
(c) 1:3
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 3.50 Mand 375.00 P.Mand 1312.50

Surkhi. 26.25 Cft. 2250.00 % Cft. 590.63


TOTAL 8653.13
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 865.31
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9518.44
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2520.83
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 252.08
__________________________ _______ ______ _______ _______ _________
TOTAL 2772.92
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 277.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 3050.21
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12568.65
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 3943.65

Chapter No. 4 214/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

6. Add extra labour in item No:5 for brick work.


(i) In First floor.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.

Masons. 0.25 Nos: 450.00 P.day. 112.50

Skilled Coolies. 1.00 Nos: 250.00 P.day. 250.00


__________________________ _______ ______ _______ _______ _________
Rs: 362.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 36.25
__________________________ _______ ______ _______ _______ _________
TOTAL 398.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 39.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 438.63
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 226.90
_____ __________________________ _______ ______ _______ _______ _________
S/N D E S C R I P T I O N.

6. Add extra labour in item No:5 for brick work.


(ii) In Second floor.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.

Masons. 0.75 Nos: 450.00 P.day. 337.50

Skilled Coolies. 2.00 Nos: 250.00 P.day. 500.00


__________________________ _______ ______ _______ _______ _________
Rs: 837.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 83.75
__________________________ _______ ______ _______ _______ _________
TOTAL 921.25
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 92.13
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1013.38

Chapter No. 4 215/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Cft. Rs: 535.45


S/N D E S C R I P T I O N.

6. Add extra labour in item No:5 for brick work.


(iii) In Third Floor.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.

Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00


__________________________ _______ ______ _______ _______ _________
Rs: 1312.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 131.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1443.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 144.38
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1588.13
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 844.00
S/N D E S C R I P T I O N.

6. Add extra labour in item No:5 for brick work.


(iv) In Fourth and subsequent Floor.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.25 Nos: 450.00 P.day. 1012.50

Skilled Coolies. 4.50 Nos: 250.00 P.day. 1125.00


__________________________ _______ ______ _______ _______ _________
Rs: 2137.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 213.75
__________________________ _______ ______ _______ _______ _________
TOTAL 2351.25
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 235.13
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2586.38
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 216/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Cft. Rs: 1388.50

Chapter No. 4 217/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(i) In cement sand mortar.
(a) 1:2
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 8.00 Cwt. 400.00 P.bag 3200.00

Sand. 20.00 Cft. 2425.00 % Cft. 485.00


TOTAL 10435.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 1043.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 11478.50
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2250.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 225.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2475.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2722.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 14201.00
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 5045.15
_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 218/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(i) In cement sand mortar.
(b) 1:3
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 6.00 Cwt. 400.00 P.bag 2400.00

Sand. 22.50 Cft. 2425.00 % Cft. 545.63


TOTAL 9695.63
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 969.56
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 10665.19
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2250.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 225.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2475.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2722.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 13387.69
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 4625.80
_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 219/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(i) In cement sand mortar.
(c) 1:4
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 4.80 Cwt. 400.00 P.bag 1920.00

Sand. 24.00 Cft. 2425.00 % Cft. 582.00


TOTAL 9252.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 925.20
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 10177.20
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2250.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 225.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2475.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2722.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12899.70
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 4374.15
_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 220/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(i) In cement sand mortar.
(d) 1:5
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 4.00 Cwt. 400.00 P.bag 1600.00

Sand. 25.00 Cft. 2425.00 % Cft. 606.25


TOTAL 8956.25
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 895.63
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9851.88
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2250.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 225.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2475.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2722.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12574.38
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 4206.40
_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 221/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(i) In cement sand mortar.
(e) 1:6
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 3.44 Cwt. 400.00 P.bag 1376.00

Sand. 25.70 Cft. 2425.00 % Cft. 623.23


TOTAL 8749.23
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 874.92
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9624.15
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2250.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 225.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2475.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2722.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12346.65
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 4089.00
_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 222/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(i) In cement sand mortar.
(f) 1:7
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 3.00 Cwt. 400.00 P.bag 1200.00

Sand. 26.50 Cft. 2425.00 % Cft. 642.63


TOTAL 8592.63
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 859.26
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9451.89
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2250.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 225.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2475.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2722.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12174.39
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 3997.70
_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 223/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(i) In cement sand mortar.
(g) 1:8
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 2.66 Cwt. 400.00 P.bag 1064.00

Sand. 26.67 Cft. 2425.00 % Cft. 646.75


TOTAL 8460.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 846.07
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9306.82
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2250.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 225.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2475.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2722.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12029.32
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 3925.40
_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 224/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(ii) In lime cement sand mortar.
(a) 1:1:6
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.60 Mand 375.00 P.Mand 600.00

Cement. 3.20 Cwt. 400.00 P.bag 1280.00

Sand. 24.00 Cft. 2425.00 % Cft. 582.00


TOTAL 9212.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 921.20
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 10133.20
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00


__________________________ _______ ______ _______ _______ _________
Rs: 2250.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 225.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2475.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2722.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12855.70
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 4215.75

Chapter No. 4 225/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(ii) In lime cement sand mortar.
(b) 1:1:7
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.42 Mand 375.00 P.Mand 532.50

Cement. 2.85 Cwt. 400.00 P.bag 1140.00

Sand. 24.78 Cft. 2425.00 % Cft. 600.92


TOTAL 9023.42
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 902.34
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9925.76
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 2250.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 225.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2475.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2722.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12648.26
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 4122.90

Chapter No. 4 226/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(ii) In lime cement sand mortar.
(c) 1:1:8
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.28 Mand 375.00 P.Mand 480.00

Cement. 2.56 Cwt. 400.00 P.bag 1024.00

Sand. 25.60 Cft. 2425.00 % Cft. 620.80


TOTAL 8874.80
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 887.48
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9762.28
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 2250.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 225.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2475.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2722.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12484.78
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 4047.65

Chapter No. 4 227/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(ii) In lime cement sand mortar.
(d) 1:1:9
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.16 Mand 375.00 P.Mand 435.00

Cement. 2.32 Cwt. 400.00 P.bag 928.00

Sand. 26.20 Cft. 2425.00 % Cft. 635.35


__________________________ _______ ______ _______ _______ _________
TOTAL 8748.35
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 874.84
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9623.19
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00


__________________________ _______ ______ _______ _______ _________
Rs: 2250.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 225.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2475.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2722.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12345.69
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 228/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Cft. Rs: 3984.65


S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(ii) In lime cement sand mortar.
(e) 1:1:10
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.07 Mand 375.00 P.Mand 401.25

Cement. 2.14 Cwt. 400.00 P.bag 856.00

Sand. 26.66 Cft. 2425.00 % Cft. 646.51

TOTAL 8653.76
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 865.38
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9519.13
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 2250.00
Sundries. 10.00 % 225.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2475.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2722.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12241.63
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 229/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Cft. Rs: 3937.40

Chapter No. 4 230/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(iii In lime sand surkhi mortar.
(a) 1:1:1
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 4.65 Mand 375.00 P.Mand 1743.75

Sand. 11.67 Cft. 400.00 % Cft. 46.68

Surkhi. 11.67 Cft. 2425.00 % Cft. 283.00


TOTAL 8823.43
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 882.34
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9705.77
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 2250.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 225.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2475.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2722.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12428.27
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 3859.20

Chapter No. 4 231/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(iv) In lime sand mortar.
1:2
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 4.67 Mand 375.00 P.Mand 1751.25

Sand. 23.33 Cft. 2425.00 % Cft. 565.75


TOTAL 9067.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 906.70
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9973.70
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2250.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 225.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2475.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2722.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12696.20
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 3881.35

Chapter No. 4 232/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(v) In lime surkhi mortar.
(a) 2:3
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 5.60 Mand 375.00 P.Mand 2100.00

Surkhi. 21.00 Cft. 2250.00 % Cft. 472.50


TOTAL 9322.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 932.25
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 10254.75
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2250.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 225.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2475.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2722.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12977.25
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 4002.90

Chapter No. 4 233/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(v) In lime surkhi mortar.
(b) 1:2
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 4.67 Mand 375.00 P.Mand 1751.25

Surkhi. 23.33 Cft. 2250.00 % Cft. 524.93


TOTAL 9026.18
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 902.62
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9928.79
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2250.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 225.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2475.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2722.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12651.29
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 3907.00

Chapter No. 4 234/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(v) In lime surkhi mortar.
(c) 1:3
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 3.50 Mand 375.00 P.Mand 1312.50

Surkhi. 26.25 Cft. 2250.00 % Cft. 590.63


TOTAL 8653.13
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 865.31
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 9518.44
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 2250.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 225.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2475.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2722.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12240.94
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 3786.35

Chapter No. 4 235/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
8. Pacca brick work in mud mortar other than building.
Extra labour for every 5 feet additional hieght.

_____ __________________________ _______ ______ _______ _______ _________


(B) LABOUR
__________________________ _______ ______ _______ _______ _________
Masons. 0.25 Nos: 450.00 P.day. 112.50

Skilled Coolies. 1.00 Nos: P.day.


250.00 250.00
Rs: 362.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 36.25
__________________________ _______ ______ _______ _______ _________
TOTAL 398.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 39.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 438.63
__________________________ _______ ______ _______ _______ _________
Labour rate for 100 Cft. Rs: 226.90
_____ __________________________ _______ ______ _______ _______ _________

_____ __________________________ _______ ______ _______ _______ _________


S/N D E S C R I P T I O N.
9. Extra labour for arch work in brick masonary including labour
for centering and decentering.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
Masons. 1.50 Nos: 450.00 P.day. 675.00
Skilled Coolies. 0.50 Nos: 250.00 P.day. 125.00
__________________________ _______ ______ _______ _______ _________
Rs: 800.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 80.00
__________________________ _______ ______ _______ _______ _________
TOTAL 880.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 88.00
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 968.00
__________________________ _______ ______ _______ _______ _________
Labour rate for 100 Cft. Rs: 562.65
_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 236/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
10. Extra for pacca brick in staining of wells or any circular
masonary.
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 82 Nos: 5000.00 %0 Nos: 410.00
__________________________ _______ ______ _______ _______ _________
TOTAL 410.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 41.00
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 451.00
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
Masons. 1.25 Nos: 450.00 P.day. 562.50
__________________________ _______ ______ _______ _________
Rs: 562.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 56.25
__________________________ _______ ______ _______ _______ _________
TOTAL 618.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 61.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 680.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 1131.63
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 516.60
_____ __________________________ _______ ______ _______ _______ _________

_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 237/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
11. Extra labour for profile and flared walls.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
Masons. 0.43 Nos: 450.00 P.day. 193.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 19.35
__________________________ _______ ______ _______ _______ _________
TOTAL 212.85
Contractor's profit 10.00 % 21.29
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 234.14
__________________________ _______ ______ _______ _______ _________
Labour rate for 100 Cft. Rs: 140.50
_____ __________________________ _______ ______ _______ _______ _________
12 Extra labour for pacca brick work in piers & abutments.
(i) From 10' to 20' Hieght.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
Masons. 0.12 Nos: 450.00 P.day. 54.00
Skilled Coolies. 0.50 250.00 P.day. 125.00
__________________________ _______ ______ _______ _______ _________
Rs: 179.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 17.90
__________________________ _______ ______ _______ _______ _________
TOTAL 196.90
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 19.69
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 216.59
__________________________ _______ ______ _______ _______ _________
Labour rate for 100 Cft. Rs: 216.59
_____ __________________________ _______ ______ _______ _______ _________
12 Extra labour for pacca brick work in piers & abutments.
(ii) Above 20' Hieght.

Chapter No. 4 238/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ __________________________ _______ ______ _______ _______ _________


(B) LABOUR
__________________________ _______ ______ _______ _______ _________
Masons. 0.25 Nos: 450.00 P.day. 112.50
Skilled Coolies. 1.00 250.00 P.day. 250.00
__________________________ _______ ______ _______ _______ _________
TOTAL Rs: 362.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 36.25
__________________________ _______ ______ _______ _______ _________
TOTAL 398.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 39.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 438.63
__________________________ _______ ______ _______ _______ _________
Labour rate for 100 Cft. Rs: 226.90
_____ __________________________ _______ ______ _______ _______ _________

_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 239/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

13. Reinforced brick work in lintels of openings laid in 1:3 cement


mortar including all labour, material, forms, moulds, lifting
and shuttering etc, but excluding cost and labour of steel
reinforcement which shall be paid for separately.
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Considering lintel over
verandah opening say 1.5 ft
* 10' * 0.75 =11.75 Cft.
Pacca bricks. 113 Nos: 5000.00 %0 Nos: 565.00
Cement. 1.23 Cwt. 400.00 P.bag 492.00
Sand. 4.60 Cft. 2425.00 % Cft. 111.55
Centering & shuttering 0.14 Cft. 1700.00 P.Cft 238.00
(Partal woood for
centering & shuttering
10'*15'*0.2' can be used
for 20 times)
TOTAL 1406.55
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 140.66
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 1547.21
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
Masons. 0.75 Nos: 450.00 P.day. 337.50

Skilled Coolies. 1.25 Nos: 250.00 P.day. 312.50

Bahishti. 0.250 Nos: P.day.


250.00 62.50
Rs: 712.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 71.25
__________________________ _______ ______ _______ _______ _________
TOTAL 783.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 78.38
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 76.63 862.13
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 2409.33
__________________________ _______ ______ _______ _______ _________
Total material & labour for 11.25 Cft. Rs: 2409.33
Total material & labour for one Cft. Rs: 214.16

Chapter No. 4 240/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for one Cft. Say Rs: 214.16
S/N D E S C R I P T I O N.
14 Dressing of chamfering of bricks.

(B) LABOUR
__________________________ _______ ______ _______ _______ _________
Masons. 3.00 Nos: 450.00 P.day. 1350.00
Cooly. 0.34 250.00 P.day. 85.00
__________________________ _______ ______ _______ _______ _________
TOTAL Rs: 1435.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 143.50
__________________________ _______ ______ _______ _______ _________
TOTAL 1578.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 157.85
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1736.35
__________________________ _______ ______ _______ _______ _________
_____ __________________________ _______ ______ _______ _______ _________
S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(i) In Mud Mortar.

_____ __________________________ _______ ______ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00
Earth. 8.75 Cwt. 500.00 % Cft. 43.75
__________________________ _______ ______ _______ _______ _________
TOTAL 1733.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 173.38
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 1907.13

Chapter No. 4 241/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

__________________________ _______ ______ _______ _______ _________


(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.00 Nos: 450.00 P.day. 450.00
Skilled Coolies. 1.83 Nos: 250.00 P.day. 457.50
Bahishti. 0.230 Nos: 250.00 P.day. 57.50
__________________________ _______ ______ _______ _______ _________
Rs: 965.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 96.50
__________________________ _______ ______ _______ _______ _________
TOTAL 1061.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 106.15
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1167.65
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 3074.78
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 1082.55

Chapter No. 4 242/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(ii) In cement sand mortar.
(a) 1:2
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Cement. 2.00 Cwt. 400.00 P.bag 800.00

Sand. 5.00 Cft. 2425.00 % Cft. 121.25


TOTAL 2611.25
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 261.13
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 2872.38
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

__________________________ _______ ______ _______ _______ _________


Rs: 1262.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 126.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1388.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 138.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1527.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 4400.00
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 1709.35

Chapter No. 4 243/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(ii) In cement sand mortar.
(b) 1:3
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Cement. 1.50 Cwt. 400.00 P.bag 600.00

Sand. 5.60 Cft. 2425.00 % Cft. 135.80


__________________________ _______ ______ _______ _______ _________
TOTAL 2425.80
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 242.58
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 2668.38
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

__________________________ _______ ______ _______ _______ _________


Rs: 1262.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 126.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1388.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 138.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1527.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 4196.01
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 4196.01

Chapter No. 4 244/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(ii) In cement sand mortar.
(c) 1:4
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Cement. 1.20 Cwt. 400.00 P.bag 480.00

Sand. 6.00 Cft. 2425.00 % Cft. 145.50


TOTAL 2315.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 231.55
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 2547.05
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

__________________________ _______ ______ _______ _______ _________


Rs: 1262.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 126.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1388.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 138.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1527.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 4074.68
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 1541.60

Chapter No. 4 245/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(ii) In cement sand mortar.
(d) 1:5
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Cement. 1.00 Cwt. 400.00 P.bag 400.00

Sand. 6.25 Cft. 2425.00 % Cft. 151.56


TOTAL 2241.56
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 224.16
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 2465.72
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

__________________________ _______ ______ _______ _______ _________


Rs: 1262.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 126.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1388.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 138.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1527.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 3993.34
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 1499.65

Chapter No. 4 246/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(ii) In cement sand mortar.
(e) 1:6
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Cement. 0.86 Cwt. 400.00 P.bag 344.00

Sand. 6.40 Cft. 2425.00 % Cft. 155.20


TOTAL 2189.20
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 218.92
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 2408.12
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

__________________________ _______ ______ _______ _______ _________


Rs: 1262.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 126.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1388.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 138.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1527.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 3935.75
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 1470.20

Chapter No. 4 247/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(ii) In cement sand mortar.
(f) 1:7
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Cement. 0.75 Cwt. 400.00 P.bag 300.00

Sand. 6.58 Cft. 2425.00 % Cft. 159.57


TOTAL 2149.57
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 214.96
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 2364.52
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

__________________________ _______ ______ _______ _______ _________


Rs: 1262.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 126.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1388.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 138.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1527.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 3892.15
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 1447.30

Chapter No. 4 248/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(ii) In cement sand mortar.
(g) 1:8
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Cement. 0.67 Cwt. 400.00 P.bag 268.00

Sand. 6.67 Cft. 2425.00 % Cft. 161.75


TOTAL 2119.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 211.97
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 2331.72
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

__________________________ _______ ______ _______ _______ _________


Rs: 1262.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 126.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1388.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 138.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1527.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 3859.35
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 1430.50

Chapter No. 4 249/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(iii In lime cement sand mortar.
(a) 1:1:6
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 0.40 Mand 375.00 P.Mand 150.00

Cement. 0.80 Cwt. 400.00 P.bag 320.00

Sand. 6.00 Cft. 2425.00 % Cft. 145.50


TOTAL 2305.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 230.55
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 2536.05
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

__________________________ _______ ______ _______ _______ _________


Rs: 1262.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 126.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1388.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 138.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1527.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 4063.68
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 1502.00
_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 250/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(iii In lime cement sand mortar.
(b) 1:1:7
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 0.36 Mand 375.00 P.Mand 135.00

Cement. 0.71 Cwt. 400.00 P.bag 284.00

Sand. 6.13 Cft. 2425.00 % Cft. 148.65


TOTAL 2257.65
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 225.77
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 2483.42
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

__________________________ _______ ______ _______ _______ _________


Rs: 1262.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 126.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1388.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 138.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1527.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 4011.04
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 1478.55

Chapter No. 4 251/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(iii In lime cement sand mortar.
(c) 1:1:8
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 0.33 Mand 375.00 P.Mand 123.75

Cement. 0.64 Cwt. 400.00 P.bag 256.00

Sand. 6.40 Cft. 2425.00 % Cft. 155.20


TOTAL 2224.95
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 222.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 2447.45
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

Rs: 1262.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 126.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1388.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 138.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1527.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 3975.07
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 1461.15
_____ __________________________ _______ ______ _______ _______ _________

_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 252/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(iii In lime cement sand mortar.
(d) 1:1:9
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 0.29 Mand 375.00 P.Mand 108.75

Cement. 0.58 Cwt. 400.00 P.bag 232.00

Sand. 6.50 Cft. 2425.00 % Cft. 157.63

__________________________ _______ ______ _______ _______ _________


TOTAL 2188.38
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 218.84
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 2407.21
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00


__________________________ _______ ______ _______ _______ _________
Rs: 1262.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 126.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1388.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 138.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1527.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 3934.84
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 1444.05
_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 253/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(iii In lime cement sand mortar.
(e) 1:1:10
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 0.27 Mand 375.00 P.Mand 101.25

Cement. 0.54 Cwt. 400.00 P.bag 216.00

Sand. 6.70 Cft. 2425.00 % Cft. 162.48


TOTAL 2169.73
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 216.97
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 2386.70
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00


__________________________ _______ ______ _______ _______ _________
Rs: 1262.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 126.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1388.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 138.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1527.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 3914.32
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 1433.90
_____ __________________________ _______ ______ _______ _______ _________

_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 254/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(iv) In lime sand surkhi mortar.
1:1:1
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 1.17 Mand 375.00 P.Mand 438.75

Sand. 2.92 Cft. 2425.00 % Cft. 70.81

Surkhi. 2.92 Cft. 2250.00 % Cft. 65.70

TOTAL 2265.26
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 226.53
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 2491.79
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos:P.day.


250.00 95.00
Rs: 1262.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 126.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1388.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 138.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1527.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 4019.41
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 1421.95
_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 255/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ __________________________ _______ ______ _______ _______ _________

S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(v) In lime sand mortar.
1:2
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 1.17 Mand 375.00 P.Mand 438.75

Sand. 5.58 Cft. 2425.00 % Cft. 135.32


TOTAL 2264.07
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 226.41
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 2490.47
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

__________________________ _______ ______ _______ _______ _________


Rs: 1262.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 126.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1388.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 138.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1527.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 4018.10

Chapter No. 4 256/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

__________________________ _______ ______ _______ _______ _________


Total material & labour for 100 Sft. Rs: 1417.70

S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(vi) In lime surkhi mortar.
(a) 2:3
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 1.40 Mand 375.00 P.Mand 525.00

Surkhi. 5.25 Cft. 2250.00 % Cft. 118.13


TOTAL 2333.13
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 233.31
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 2566.44
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

__________________________ _______ ______ _______ _______ _________


Rs: 1262.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 126.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1388.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 138.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1527.63
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 257/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (MATERIAL + LABOUR) 4094.06


__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 1448.80

S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(vi) In lime surkhi mortar.
(b) 1:2
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 1.17 Mand 375.00 P.Mand 438.75

Surkhi. 5.83 Cft. 2250.00 % Cft. 131.18


TOTAL 2259.93
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 225.99
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 2485.92
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

__________________________ _______ ______ _______ _______ _________


Rs: 1262.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 126.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1388.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 138.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1527.63

Chapter No. 4 258/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

__________________________ _______ ______ _______ _______ _________


TOTAL (MATERIAL + LABOUR) 4013.54
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 1425.10

S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(vi) In lime surkhi mortar.
(c) 1:3
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 0.875 Mand 375.00 P.Mand 328.13

Surkhi. 6.56 Cft. 2250.00 % Cft. 147.60


TOTAL 2165.73
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 216.57
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 2382.30
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: P.day.


250.00 95.00
Rs: 1262.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 126.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1388.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 138.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1527.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 3909.92
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 1394.65

Chapter No. 4 259/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ __________________________ _______ ______ _______ _______ _________

_____ __________________________ _______ ______ _______ _______ _________

S/N D E S C R I P T I O N.

16. Add extra labour in item No:5 for brick work.


(i) In First floor.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.

Masons. 0.12 Nos: 450.00 P.day. 54.00

Skilled Coolies. 0.50 Nos: 250.00 P.day. 125.00


__________________________ _______ ______ _______ _______ _________
Rs: 179.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 17.90
__________________________ _______ ______ _______ _______ _________
TOTAL 196.90
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 19.69
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 216.59
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 216.59
_____ __________________________ _______ ______ _______ _______ _________
S/N D E S C R I P T I O N.
16. Add extra labour in item No:5 for brick work.
(ii) In Second floor.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.

Masons. 0.38 Nos: 450.00 P.day. 168.75

Skilled Coolies. 1.00 Nos: 250.00 P.day. 250.00


__________________________ _______ ______ _______ _______ _________
Rs: 418.75
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 41.88
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 260/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 460.63
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 46.06
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 506.69
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 267.70
S/N D E S C R I P T I O N.

16. Add extra labour in item No:5 for brick work.


(iii) In Third Floor.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.

Masons. 0.625 Nos: 450.00 P.day. 281.25

Skilled Coolies. 1.50 Nos: 250.00 P.day. 375.00


__________________________ _______ ______ _______ _______ _________
Rs: 656.25
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 65.63
__________________________ _______ ______ _______ _______ _________
TOTAL 721.88
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 72.19
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 794.06
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 422.00
_____ __________________________ _______ ______ _______ _______ _________
S/N D E S C R I P T I O N.

16. Add extra labour in item No:5 for brick work.


(iv) In Fourth and subsequent Floor.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.

Masons. 1.125 Nos: 450.00 P.day. 506.25

Skilled Coolies. 2.25 Nos: 250.00 P.day. 562.50


__________________________ _______ ______ _______ _______ _________
Rs: 1068.75
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 261/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Sundries. 10.00 % 106.88


__________________________ _______ ______ _______ _______ _________
TOTAL 1175.63
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 117.56
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1293.19
Total material & labour for 100 Sft. Rs: 694.25
S/N D E S C R I P T I O N.

17 Perforated pacca brick walling 9" thick in ground floor.


(i) In Mud Mortar.

_____ __________________________ _______ ______ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Earth. 17.50 Cwt. 500.00 % Cft. 87.50


TOTAL 3462.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 346.25
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 3808.75
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.50 Nos: 450.00 P.day. 675.00

Skilled Coolies. 2.75 Nos: 250.00 P.day. 687.50

Bahishti. 0.350 Nos: 250.00 P.day. 87.50

__________________________ _______ ______ _______ _______ _________


Rs: 1450.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 145.00
__________________________ _______ ______ _______ _______ _________
TOTAL 1595.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 159.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1754.50

Chapter No. 4 262/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

__________________________ _______ ______ _______ _______ _________


TOTAL (MATERIAL + LABOUR) 5563.25
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 1852.35
_____ __________________________ _______ ______ _______ _______ _________

_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 263/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(ii) In cement sand mortar.
(a) 1:2
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Cement. 4.00 Cwt. 400.00 P.bag 1600.00

Sand. 10.00 Cft. 2425.00 % Cft. 242.50


TOTAL 5217.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 521.75
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 5739.25
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

__________________________ _______ ______ _______ _______ _________


Rs: 1900.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 190.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2090.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 209.00
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2299.00
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 8038.25
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 3015.15

Chapter No. 4 264/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(ii) In cement sand mortar.
(b) 1:3
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Cement. 3.00 Cwt. 400.00 P.bag 1200.00

Sand. 11.25 Cft. 2425.00 % Cft. 272.81

TOTAL 4847.81
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 484.78
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 5332.59
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

__________________________ _______ ______ _______ _______ _________


Rs: 1900.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 190.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2090.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 209.00
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2299.00
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7631.59
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 2805.50

Chapter No. 4 265/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(ii) In cement sand mortar.
(c) 1:4
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Cement. 2.40 Cwt. 400.00 P.bag 960.00

Sand. 12.00 Cft. 2425.00 % Cft. 291.00


TOTAL 4626.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 462.60
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 5088.60
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

__________________________ _______ ______ _______ _______ _________


Rs: 1900.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 190.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2090.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 209.00
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2299.00
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7387.60
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 2679.65

Chapter No. 4 266/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(ii) In cement sand mortar.
(d) 1:5
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Cement. 2.00 Cwt. 400.00 P.bag 800.00

Sand. 12.50 Cft. 2425.00 % Cft. 303.13


__________________________ _______ ______ _______ _______ _________
TOTAL 4478.13
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 447.81
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 4925.94
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

__________________________ _______ ______ _______ _______ _________


Rs: 1900.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 190.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2090.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 209.00
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2299.00
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7224.94
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 2595.80

Chapter No. 4 267/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(ii) In cement sand mortar.
(e) 1:6
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Cement. 1.72 Cwt. 400.00 P.bag 688.00

Sand. 12.80 Cft. 2425.00 % Cft. 310.40

TOTAL 4373.40
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 437.34
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 4810.74
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

__________________________ _______ ______ _______ _______ _________


Rs: 1900.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 190.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2090.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 209.00
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2299.00
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7109.74
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 2536.90
_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 268/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ __________________________ _______ ______ _______ _______ _________


S/N D E S C R I P T I O N.

17 Perforated pacca brick walling 9" thick in ground floor.


(ii) In cement sand mortar.
(f) 1:7
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Cement. 1.50 Cwt. 400.00 P.bag 600.00

Sand. 13.13 Cft. % Cft.


2425.00 318.40
__________________________ _______ ______ _______ _______ _________
TOTAL 4293.40
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 429.34
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 4722.74
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

__________________________ _______ ______ _______ _______ _________


Rs: 1900.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 190.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2090.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 209.00
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2299.00
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7021.74
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 2490.95
_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 269/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ __________________________ _______ ______ _______ _______ _________

S/N D E S C R I P T I O N.

17 Perforated pacca brick walling 9" thick in ground floor.


(ii) In cement sand mortar.
(g) 1:8
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Cement. 1.33 Cwt. 400.00 P.bag 532.00

Sand. 13.34 Cft. 2425.00 % Cft. 323.50

TOTAL 4230.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 423.05
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 4653.54
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

__________________________ _______ ______ _______ _______ _________


Rs: 1900.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 190.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2090.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 209.00
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2299.00
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 6952.54
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 2455.30
_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 270/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(iii In lime cement sand mortar.
(a) 1:1:6
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 0.80 Mand 375.00 P.Mand 300.00

Cement. 1.60 Cwt. 400.00 P.bag 640.00

Sand. 12.00 Cft. 2425.00 % Cft. 291.00


TOTAL 4606.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 460.60
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 5066.60
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

__________________________ _______ ______ _______ _______ _________


Rs: 1900.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 190.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2090.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 209.00
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2299.00
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7365.60

Chapter No. 4 271/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

__________________________ _______ ______ _______ _______ _________


Total material & labour for 100 Sft. Rs: 2600.45
_____ __________________________ _______ ______ _______ _______ _________

S/N D E S C R I P T I O N.

17 Perforated pacca brick walling 9" thick in ground floor.


(iii In lime cement sand mortar.
(b) 1:1:7
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 0.71 Mand 375.00 P.Mand 266.25

Cement. 1.42 Cwt. 400.00 P.bag 568.00

Sand. 12.39 Cft. 2425.00 % Cft. 300.46

__________________________ _______ ______ _______ _______ _________


TOTAL 4509.71
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 450.97
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 4960.68
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: P.day.


250.00 137.50
Rs: 1900.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 190.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2090.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 209.00
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2299.00
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7259.68

Chapter No. 4 272/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

__________________________ _______ ______ _______ _______ _________


Total material & labour for 100 Sft. Rs: 2552.95
_____ __________________________ _______ ______ _______ _______ _________

_____ __________________________ _______ ______ _______ _______ _________


S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(iii In lime cement sand mortar.
(c) 1:1:8
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 0.64 Mand 375.00 P.Mand 240.00

Cement. 1.28 Cwt. 400.00 P.bag 512.00

Sand. 12.80 Cft. 2425.00 % Cft. 310.40

TOTAL 4437.40
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 443.74
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 4881.14
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

__________________________ _______ ______ _______ _______ _________


__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % #REF!
__________________________ _______ ______ _______ _______ _________
TOTAL #REF!
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % #REF!
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " #REF!

Chapter No. 4 273/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

__________________________ _______ ______ _______ _______ _________


TOTAL (MATERIAL + LABOUR) #REF!
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 2516.45

S/N D E S C R I P T I O N.

17 Perforated pacca brick walling 9" thick in ground floor.


(iii In lime cement sand mortar.
(d) 1:1:9
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 0.58 Mand 375.00 P.Mand 217.50

Cement. 1.16 Cwt. 400.00 P.bag 464.00

Sand. 13.10 Cft. 2425.00 % Cft. 317.68

__________________________ _______ ______ _______ _______ _________


TOTAL 4374.18
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 437.42
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 4811.59
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

Rs: 1900.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 190.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2090.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 209.00

Chapter No. 4 274/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

__________________________ _______ ______ _______ _______ _________


TOTAL PART " B " 2299.00
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7110.59
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 2484.90

S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(iii In lime cement sand mortar.
(e) 1:1:10
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 0.54 Mand 375.00 P.Mand 202.50

Cement. 1.07 Cwt. 400.00 P.bag 428.00

Sand. 13.33 Cft. 2425.00 % Cft. 323.25

TOTAL 4328.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 432.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 4761.63
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

__________________________ _______ ______ _______ _______ _________


Rs: 1900.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 190.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2090.00
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 275/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 209.00


__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2299.00
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7060.63
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 2461.85

S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(iv) In lime sand surkhi mortar.
1:1:1
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 2.33 Mand 375.00 P.Mand 873.75

Sand. 5.84 Cft. 2425.00 % Cft. 141.62

Surkhi. 5.83 Cft. 2250.00 % Cft. 131.18


__________________________ _______ ______ _______ _______ _________
TOTAL 4521.55
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 452.15
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 4973.70
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

__________________________ _______ ______ _______ _______ _________


Rs: 1900.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 190.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2090.00

Chapter No. 4 276/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

__________________________ _______ ______ _______ _______ _________


Contractor's profit 10.00 % 209.00
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2299.00
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7272.70
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 2439.10

S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(v) In lime sand mortar.
1:2
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 2.33 Mand 375.00 P.Mand 873.75

Sand. 11.67 Cft. 2425.00 % Cft. 283.00

TOTAL 4531.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 453.17
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 4984.92
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

__________________________ _______ ______ _______ _______ _________


Rs: 1900.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 190.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2090.00
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 277/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 209.00


__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2299.00
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7283.92
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 2432.70
_____ __________________________ _______ ______ _______ _______ _________

_____ __________________________ _______ ______ _______ _______ _________


S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(vi) In lime surkhi mortar.
(a) 2:3
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 2.80 Mand 375.00 P.Mand 1050.00

Surkhi. 10.50 Cft. 2250.00 % Cft. 236.25


TOTAL 4661.25
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 466.13
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 5127.38
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: P.day.


250.00 137.50
Rs: 1900.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 190.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2090.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 209.00
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2299.00

Chapter No. 4 278/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

__________________________ _______ ______ _______ _______ _________


TOTAL (MATERIAL + LABOUR) 7426.38
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 2494.05
_____ __________________________ _______ ______ _______ _______ _________

_____ __________________________ _______ ______ _______ _______ _________

S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 4-1/2" thick in ground floor.


(vi) In lime surkhi mortar.
(b) 1:2
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 2.34 Mand 375.00 P.Mand 877.50

Surkhi. 11.67 Cft. 2250.00 % Cft. 262.58

__________________________ _______ ______ _______ _______ _________


TOTAL 4515.08
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 451.51
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 4966.58
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

__________________________ _______ ______ _______ _______ _________


Rs: 1900.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 190.00
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 279/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 2090.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 209.00
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2299.00
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7265.58
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 2446.70
_____ __________________________ _______ ______ _______ _______ _________

_____ __________________________ _______ ______ _______ _______ _________


S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(vi) In lime surkhi mortar.
(c) 1:3
_____ __________________________ _______ ______ _______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 1.750 Mand 375.00 P.Mand 656.25

Surkhi. 13.12 Cft. 2250.00 % Cft. 295.20


TOTAL 4326.45
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 432.65
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 4759.10
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

Rs: 1900.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 190.00
__________________________ _______ ______ _______ _______ _________
TOTAL 2090.00
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 280/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 209.00


__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2299.00
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7058.10
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 2385.75
_____ __________________________ _______ ______ _______ _______ _________

_____ __________________________ _______ ______ _______ _______ _________

S/N D E S C R I P T I O N.

18. Add extra labour in item No:17 for brick work.


(i) In First floor.
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.

Masons. 0.188 Nos: 450.00 P.day. 84.38

Skilled Coolies. 0.75 Nos: 250.00 P.day. 187.50


__________________________ _______ ______ _______ _______ _________
Rs: 271.88
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 27.19
__________________________ _______ ______ _______ _______ _________
TOTAL 299.06
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 29.91
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 328.97
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 170.15
S/N D E S C R I P T I O N.

18. Add extra labour in item No:5 for brick work.


(ii) In Second floor.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.

Masons. 0.563 Nos: 450.00 P.day. 253.13

Chapter No. 4 281/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Skilled Coolies. 1.50 Nos: 250.00 P.day. 375.00


__________________________ _______ ______ _______ _______ _________
Rs: 628.13
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 62.81
__________________________ _______ ______ _______ _______ _________
TOTAL 690.94
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 69.09
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 760.03
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 401.55

S/N D E S C R I P T I O N.

18. Add extra labour in item No:17 for brick work.


(iii) In Third Floor.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.

Masons. 0.938 Nos: 450.00 P.day. 421.88

Skilled Coolies. 2.25 Nos: 250.00 P.day. 562.50


__________________________ _______ ______ _______ _______ _________
Rs: 984.38
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 98.44
__________________________ _______ ______ _______ _______ _________
TOTAL 1082.81
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 108.28
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1191.09
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 633.00
_____ __________________________ _______ ______ _______ _______ _________
S/N D E S C R I P T I O N.

18. Add extra labour in item No:17 for brick work.


(iv) In Fourth and subsequent Floor.
_____ __________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.

Chapter No. 4 282/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Masons. 1.688 Nos: 450.00 P.day. 759.38

Skilled Coolies. 3.38 Nos: 250.00 P.day. 843.75


__________________________ _______ ______ _______ _______ _________
Rs: 1603.13
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 160.31
__________________________ _______ ______ _______ _______ _________
TOTAL 1763.44
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 176.34
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1939.78
Total material & labour for 100 Sft. Rs: 1041.35
S/N D E S C R I P T I O N.

19. Fire brick masonary in fire clay mortar.


(i) Upto 20 feet hieght including all charges.

_____ __________________________ _______ ______ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Fire clay bricks 9" * 1350 Nos: 5300.0 %0 Nos: 7155.00
4-1/2"* 3"
Aluminia Cement. 8.800 Cwt. 650.00 P.bag 5720.00

Crushed fire bricks graded 22.00 Cft. 2500.00 % Cft. 550.00


as sand.
TOTAL 13425.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 1342.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 14767.50
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 3.00 Nos: 450.00 P.day. 1350.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Mortar.
Coolies. 1.00 Nos: 250.00 P.day. 250.00

Chapter No. 4 283/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Bahishti. 0.250 Nos: 250.00 P.day. 62.50

Rs: 2475.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 247.50
__________________________ _______ ______ _______ _______ _________
TOTAL 2722.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 272.25
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2994.75
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 17762.25
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 6928.35

S/N D E S C R I P T I O N.
19. Fire brick masonary in fire clay mortar.
(ii) Extra for every 5 feet additional hieght.

(B) LABOUR
__________________________ _______ ______ _______ _______ _________
Masons. 0.25 Nos: 450.00 P.day. 112.50

Skilled Coolies. 1.00 Nos: 250.00 P.day. 250.00


__________________________ _______ ______ _______ _______ _________
Rs: 362.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 36.25
__________________________ _______ ______ _______ _______ _________
TOTAL 398.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 39.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 438.63
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 226.90
_____ __________________________ _______ ______ _______ _______ _________

_____ __________________________ _______ ______ _______ _______ _________


S/N D E S C R I P T I O N.

20. Pacca brick walling laid in 1:3 cement sand mortar reinforced
with 1" wide 18 gauge hoop iron:-
(i) 4-1/2" thick walling with hoop iron bonding 6" apart.

_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 284/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca bricks 9" * 4-1/2"*3" 525 Nos: 5000.00 %0 Nos: 2625.00

Cement. 2.400 Cwt. 400.00 P.bag 960.00

Sand. 9.00 Cft. 2425.00 % Cft. 218.25

Hoop Iron. 45.00 Lbs: 2500.00 P.Cwt 1004.46

__________________________ _______ ______ _______ _______ _________


TOTAL 4807.71
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 480.77
TOTAL PART " A " 5288.49
__________________________ _______ ______ _______ _______ _________

(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.00 Nos: 450.00 P.day. 450.00

Skilled Coolies. 1.42 Nos: 250.00 P.day. 355.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50

Blacksmith. 0.10 Nos: 450.00 P.day. 45.00

__________________________ _______ ______ _______ _______ _________


Rs: 912.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 91.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1003.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 100.38
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1104.13
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 6392.61
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 6392.61

Chapter No. 4 285/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ __________________________ _______ ______ _______ _______ _________

S/N D E S C R I P T I O N.

20. Pacca brick walling laid in 1:3 cement sand mortar reinforced
with 1" wide 18 gauge hoop iron:-
(ii) 4-1/2" thick walling with hoop iron bonding 12" apart.

(A) MATERIAL QUANTITY


RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca bricks 9" * 4-1/2"*3" 525 Nos: 5000.00 %0 Nos: 2625.00

Cement. 2.400 Cwt. 400.00 P.bag 960.00

Sand. 9.00 Cft. 2425.00 % Cft. 218.25

Hoop Iron. 22.50 Lbs: 2500.00 P.Cwt 502.23

__________________________ _______ ______ _______ _______ _________


TOTAL 4305.48
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 430.55
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 4736.03
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 1.00 Nos: 450.00 P.day. 450.00

Chapter No. 4 286/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Skilled Coolies. 1.42 Nos: 250.00 P.day. 355.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50

Blacksmith. 0.10 Nos: 450.00 P.day. 45.00

Rs: 912.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 91.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1003.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 100.38
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1104.13
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 5840.16
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 5840.16
S/N D E S C R I P T I O N.

20. Pacca brick walling laid in 1:3 cement sand mortar reinforced
with 1" wide 18 gauge hoop iron:-
(iii) 3" thick walling with hoop iron bonding 6" apart.

_____ __________________________ _______ ______ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca bricks 9" * 4-1/2"*3" 350 Nos: 5000.00 %0 Nos: 1750.00

Cement. 1.800 Cwt. 400.00 P.bag 720.00

Sand. 6.50 Cft. 2425.00 % Cft. 157.63

Hoop Iron. 45.00 Lbs: 2500.00 P.Cwt 1004.46


TOTAL 3632.09
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 363.21
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 3995.30
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 0.75 Nos: 450.00 P.day. 337.50

Chapter No. 4 287/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Skilled Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.200 Nos: 250.00 P.day. 50.00

Blacksmith. 0.15 Nos: 450.00 P.day. 67.50

Rs: 705.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 70.50
__________________________ _______ ______ _______ _______ _________
TOTAL 775.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 77.55
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 853.05
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 4848.35
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 4848.35

S/N D E S C R I P T I O N.

20. Pacca brick walling laid in 1:3 cement sand mortar reinforced
with 1" wide 18 gauge hoop iron:-
(iv) 3" thick walling with hoop iron bonding 12" apart.

_____ __________________________ _______ ______ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pacca bricks 9" * 4-1/2"*3" 350 Nos: 5000.00 %0 Nos: 1750.00

Cement. 1.800 Cwt. 400.00 P.bag 720.00

Sand. 6.50 Cft. 2425.00 % Cft. 157.63

Hoop Iron. 20.00 Lbs: 2500.00 P.Cwt 446.43


TOTAL 3074.05
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 307.41
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 3381.46
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 0.75 Nos: 450.00 P.day. 337.50

Chapter No. 4 288/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Skilled Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.200 Nos: 250.00 P.day. 50.00

Blacksmith. 0.10 Nos: 450.00 P.day. 45.00


__________________________ _______ ______ _______ _______ _________
Rs: 682.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 68.25
__________________________ _______ ______ _______ _______ _________
TOTAL 750.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 75.08
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 825.83
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 4207.28
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 4207.28

S/N D E S C R I P T I O N.

21. Ghilafi work 1' - 1-1/2" thick wall.

_____ __________________________ _______ ______ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
(i) Material same as per Item
No:1(i)-(A)/2 3808.75

(ii) Material same as per Item


No:23-(A)/2 987.25
TOTAL PART " A " 4796.00
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 3.67 Nos: 250.00 P.day. 917.50

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Chapter No. 4 289/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

__________________________ _______ ______ _______ _______ _________


Rs: 1942.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 194.25
__________________________ _______ ______ _______ _______ _________
TOTAL 2136.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 213.68
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 2350.43
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7146.43
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Sft. Rs: 2563.50
_____ __________________________ _______ ______ _______ _______ _________

_____ __________________________ _______ ______ _______ _______ _________

S/N D E S C R I P T I O N.

22. Dry brick pitching.

_____ __________________________ _______ ______ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
First class burnt bricks. 1350 Nos: 5000.00 %0 Nos: 6750.00

__________________________ _______ ______ _______ _______ _________


TOTAL 6750.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 675.00
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 7425.00
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________

Masons. 1.00 Nos: 450.00 P.day. 450.00

Chapter No. 4 290/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Skilled Coolies. 2.00 Nos: 250.00 P.day. 500.00

__________________________ _______ ______ _______ _______ _________


Rs: 950.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 95.00
__________________________ _______ ______ _______ _______ _________
TOTAL 1045.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 104.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1149.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 8574.50
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 8574.50
_____ __________________________ _______ ______ _______ _______ _________

_____ __________________________ _______ ______ _______ _______ _________


S/N D E S C R I P T I O N.

23. Sundried bricks in mud mortar.

_____ __________________________ _______ ______ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Sun dried bricks. 1350 Nos: 1200.00 %0 Nos: 1620.00

Stiff clay. 35.00 Cft. 500.00 % Cft. 175.00

__________________________ _______ ______ _______ _______ _________


TOTAL 1795.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 179.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 1974.50
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________

Chapter No. 4 291/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Masons. 1.50 Nos: 450.00 P.day. 675.00

Skilled Coolies. 3.50 Nos: 250.00 P.day. 875.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

__________________________ _______ ______ _______ _______ _________


Rs: 1612.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 161.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1773.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 177.38
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 1951.13
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 3925.63
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 1819.40
_____ __________________________ _______ ______ _______ _______ _________

S/N D E S C R I P T I O N.

24. Pise wall. (Mud Wall)


(B) LABOUR
__________________________ _______ ______ _______ _______ _________

Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Bahishti. 0.50 Nos: P.day.


250.00 125.00
Rs: 750.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 75.00
__________________________ _______ ______ _______ _______ _________
TOTAL 825.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 82.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 907.50
__________________________ _______ ______ _______ _______ _________
Labour rate for 100 Cft. Rs: 907.50
S/N D E S C R I P T I O N.

Chapter No. 4 292/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

25. Eave brick moulded, weathered and throated with back bricks or
drip course cornice in 1:3 cement mortar.
(i) 3" thick drip coarse cornice.

_____ __________________________ _______ ______ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Assume for 100 Rft.
Moulded bricks. 280 Nos: 4800.0 %0 Nos: 1344.00
(100*12*2/9 + 13)
Cement for laying and 1.50 Cwt. 400.00 P.bag 600.00
plastering.
Sand. 5.00 Cft. 2425.00 % Cft. 121.25
Deduct cost of ordinary 140.0 Nos: 5000.00 %0 Nos: -700.00
bricks. 280/2 =140 Nos:

__________________________ _______ ______ _______ _______ _________


TOTAL 1365.25
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 136.53
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 1501.78
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________

Masons. 1.75 Nos: 450.00 P.day. 787.50

Skilled Coolies. 1.75 Nos: 250.00 P.day. 437.50

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

__________________________ _______ ______ _______ _______ _________


Rs: 1287.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 128.75
__________________________ _______ ______ _______ _______ _________
TOTAL 1416.25
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 141.63
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 15.58 1557.88
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 3059.65

Chapter No. 4 293/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

__________________________ _______ ______ _______ _______ _________


Total material & labour for 100 Rft. Rs: 3059.65
Total material & labour for one Rft. Rs: 30.60
Total material & labour for one Rft. say Rs: 16.05

_____ __________________________ _______ ______ _______ _______ _________

_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 294/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

25. Eave brick moulded, weathered and throated with back bricks or
drip course cornice in 1:3 cement mortar.
(ii) 4-1/2" thick drip coarse cornice.

_____ __________________________ _______ ______ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Assume for 100 Rft.
Moulded bricks. 420 Nos: 4800.0 %0 Nos: 2016.00
(100*12/3 + 20)
Cement for laying and 1.75 Cwt. 400.00 P.bag 700.00
plastering.
Sand. 6.00 Cft. 2425.00 % Cft. 145.50
Deduct cost of ordinary 210.0 Nos: 5000.00 %0 Nos: -1050.00
bricks. 420/2 =140 Nos:

TOTAL 1811.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 181.15
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 1992.65
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.25 Nos: P.day.


250.00 62.50
Rs: 1462.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 146.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1608.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 160.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 17.70 1769.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 3762.28
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Rft. Rs: 3762.28
Total material & labour for one Rft. Rs: 37.62
Total material & labour for one Rft. say Rs: 19.8

Chapter No. 4 295/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

25. Eave brick moulded, weathered and throated with back bricks or
drip course cornice in 1:3 cement mortar.
(iii 4-1/2" thick eave brick with back brick.

_____ __________________________ _______ ______ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Assume for 100 Rft.
Moulded bricks i/c wastage. 465 Nos: 4800.0 %0 Nos: 2232.00
Ordinary bricks. 465 Nos: 5000.00 %0 Nos: 2325.00
Cement for laying and 1.20 Cwt. 400.00 P.bag 480.00
plastering.
Sand. 5.00 Cft. 2425.00 % Cft. 121.25

__________________________ _______ ______ _______ _______ _________


TOTAL 5158.25
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 515.83
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 5674.08
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________

Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 1.00 Nos: P.day.


250.00 250.00
Rs: 1150.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 115.00
__________________________ _______ ______ _______ _______ _________
TOTAL 1265.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 126.50
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 13.92 1391.50
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 7065.58
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Rft. Rs: 7065.58
Total material & labour for one Rft. Rs: 70.66
Total material & labour for one Rft. say Rs: 26.60

Chapter No. 4 296/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

26. Laying dressed or moulded brick cornices in 1:6 cement mortar,


plastering or pointing complete.
(i) One brick.

_____ __________________________ _______ ______ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Assume for 100 Rft. Moulded bricks:- Bricks = 268 Nos:
Wastage 10% = 27 Nos: Total = 300 Nos: The rate is only for
projected portion so that the bricks will be=300*1/5 = 60 Nos:
__________________________ _______ ______ _______ _______ _________
Bricks. 60 Nos: 5000.00 %0 Nos: 300.00
Cement for laying and 1.60 Cwt. 400.00 P.bag 640.00
plastring.
Sand. 6.00 Cft. 2425.00 % Cft. 145.50

__________________________ _______ ______ _______ _______ _________


TOTAL 1085.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 108.55
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 1194.05
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________

Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.25 Nos: P.day.


250.00 62.50
Rs: 1462.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 146.25
__________________________ _______ ______ _______ _______ _________
TOTAL 1608.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 160.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 17.70 1769.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 2963.68
Total material & labour for 100 Rft. Rs: 2963.68
Total material & labour for one Rft. Rs: 29.64

Chapter No. 4 297/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for one Rft. say Rs: 14.25
S/N D E S C R I P T I O N.

26. Laying dressed or moulded brick cornices in 1:6 cement mortar,


plastering or pointing complete.
(ii) Two bricks.

_____ __________________________ _______ ______ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Bricks. 175 Nos: 5000.00 %0 Nos: 875.00

Cement for laying and 5.00 Cwt. 400.00 P.bag 2000.00


plastring.

Sand. 18.00 Cft. 2425.00 % Cft. 436.50

TOTAL 3311.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 331.15
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 3642.65
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________

Masons. 3.00 Nos: 450.00 P.day. 1350.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

Rs: 2162.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 216.25
__________________________ _______ ______ _______ _______ _________
TOTAL 2378.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 237.88
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 26.17 2616.63
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 6259.28
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Rft. Rs: 6259.28
Total material & labour for one Rft. Rs: 62.59

Chapter No. 4 298/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for one Rft. say Rs: 28.25

Chapter No. 4 299/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

26. Laying dressed or moulded brick cornices in 1:6 cement mortar,


plastering or pointing complete.
(iii Three bricks.

_____ __________________________ _______ ______ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Bricks. 270 Nos: 5000.00 %0 Nos: 1350.00

Cement for laying and 8.00 Cwt. 400.00 P.bag 3200.00


plastring.

Sand. 28.00 Cft. 2425.00 % Cft. 679.00

__________________________ _______ ______ _______ _______ _________


TOTAL 5229.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 522.90
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 5751.90
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________

Masons. 4.00 Nos: 450.00 P.day. 1800.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.33 Nos: P.day.


250.00 82.50
Rs: 2882.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 288.25
__________________________ _______ ______ _______ _______ _________
TOTAL 3170.75
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 317.08
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 34.88 3487.83
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 9239.73
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Rft. Rs: 9239.73
Total material & labour for one Rft. Rs: 92.40
Total material & labour for one Rft. say Rs: 41.15

Chapter No. 4 300/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

26 Laying dressed or moulded brick cornices in 1:6 cement mortar,


plastering or pointing complete.
(iv) Four bricks.

_____ __________________________ _______ ______ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Bricks. 580 Nos: 5000.00 %0 Nos: 2900.00

Cement for laying and 10.00 Cwt. 400.00 P.bag 4000.00


plastring.

Sand. 37.00 Cft. 2425.00 % Cft. 897.25


TOTAL 7797.25
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 779.73
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 8576.98
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________

Masons. 5.00 Nos: 450.00 P.day. 2250.00

Skilled Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

Rs: 3625.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 362.50
__________________________ _______ ______ _______ _______ _________
TOTAL 3987.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 398.75
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 43.86 4386.25
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 12963.23
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Rft. Rs: 12963.23
Total material & labour for one Rft. Rs: 129.63
Total material & labour for one Rft. say Rs: 54.85
_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 301/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
27 Cleaning bricks dismantled from katcha pacca masonary.

_____ __________________________ _______ ______ _______ _______ _________


(B) LABOUR
__________________________ _______ ______ _______ _______ _________
Coolis. 1.75 Nos: 250.00 P.day. 437.50
__________________________ _______ ______ _______ _______ _________
TOTAL Rs: 437.50
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 43.75
__________________________ _______ ______ _______ _______ _________
TOTAL 481.25
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 48.13
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 529.38
__________________________ _______ ______ _______ _______ _________
Labour rate for 1000 Nos: Rs: 211.75
_____ __________________________ _______ ______ _______ _______ _________
S/N D E S C R I P T I O N.
28. Scraping bricks dismantled from pacca masonary.

_____ __________________________ _______ ______ _______ _______ _________


(B) LABOUR
__________________________ _______ ______ _______ _______ _________
Coolis. 3.30 Nos: 250.00 P.day. 825.00
__________________________ _______ ______ _______ _______ _________
TOTAL Rs: 825.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 82.50
__________________________ _______ ______ _______ _______ _________
TOTAL 907.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 90.75
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 998.25
__________________________ _______ ______ _______ _______ _________
Labour rate for 1000 Nos: Rs: 998.25

_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 302/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ __________________________ _______ ______ _______ _______ _________


S/N D E S C R I P T I O N.

29 Supplying and filling sand under floor and plugging in walls.

_____ __________________________ _______ ______ _______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
__________________________ _______ ______ _______ _______ _________
Pit Sand. 100 Cft. 900.00 % Cft. 900.00

__________________________ _______ ______ _______ _______ _________


TOTAL 900.00
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 90.00
__________________________ _______ ______ _______ _______ _________
TOTAL PART " A " 990.00
__________________________ _______ ______ _______ _______ _________
(B) LABOUR
__________________________ _______ ______ _______ _______ _________

Coolies. 0.50 Nos: 250.00 P.day. 125.00

__________________________ _______ ______ _______ _______ _________


Rs: 125.00
__________________________ _______ ______ _______ _______ _________
Sundries. 10.00 % 12.50
__________________________ _______ ______ _______ _______ _________
TOTAL 137.50
__________________________ _______ ______ _______ _______ _________
Contractor's profit 10.00 % 13.75
__________________________ _______ ______ _______ _______ _________
TOTAL PART " B " 151.25
__________________________ _______ ______ _______ _______ _________
TOTAL (MATERIAL + LABOUR) 1141.25
__________________________ _______ ______ _______ _______ _________
Total material & labour for 100 Cft. Rs: 203.50
_____ __________________________ _______ ______ _______ _______ _________

Chapter No. 4 303/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

FIRST FILL THIS SHEET.


STONE MASONARY.
MATERIAL. RATE UNITE
1 Quarried stone 1050 % Cft.

2 Headers 1.5' x 8" x 10" 450 Each

3 Good Earth 500 % Cft

4 Lime Slaked 375 P.Mand

5 Sand 2425 % Cft

6 Surkhi 2250 % Cft

7 Cement 400 P. Bag

8 Char Coal 675 P.Mand

9 Steel (Mild) 3550 P.Cwt

10 Deador wood (2nd Qualty) 4000 P.Cft

11 Shingle 3/4" 3075 % Cft

12 Bajri 2650 % Cft

13 Stone Boulders 9" to 12" 1400 % Cft

14 Pitching Stone. 2000 % .Cft

15 Spikes 3/4" 25 P.doz

16 Wire Nails 4" 110 P.Kg

17 Wood Preservative. 1450 P.Gall.

18 Stone 5"to6" thick 8" deep &12"to15" 65 Each


LABOUR RATE UNITE.

1 Mason , Black Smith,Carpenter 450 P.day

2 Cooles, Below Man 250 P.day

3 Bahishtis. 250 P.day

4 Coolies (skilled) 250 P.day

S T O N E M A S O N A R Y.

Chapter No. 5 354/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

============================
I Rates for all finished works include the removal of the surplus
debris un-used material and by-products.
II For handling of all types of materials for short leads including
carraige upto 3 chains nothing is to be paid extra where
handling and carraige involves an extra lead beyond 3 chains
carraige for whole of the distance should be paid.
III The rates include the cost of scaffolding and its removal.
_____ _______________________________ _______ ______ _______ ______ _________
S/N D E S C R I P T I O N.
FOUNDATION AND PLINTH.
======================
1. Random, rubble masonary. (Un-coursed)
(a) Dry Masonary.
_____ _______________________________ _______ ______ _______ ______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos:)

TOTAL 10050.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1005.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 11055.00
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Coolies. 3.00 Nos: 250.00 P.day. 750.00

Rs: 1650.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 165.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 1815.00
Contractor's profit 10.00% 181.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 1996.50
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 13051.50
Total material & labour for 100 Cft. Rs: 13051.50
S/N D E S C R I P T I O N.

FOUNDATION AND PLINTH.

Chapter No. 5 355/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

======================
1. Random, rubble masonary. (Un-coursed)
(b) In Mud Mortar.
_____ _______________________________ _______ ______ _______ ______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Good earth. 45.00 Cft. 500.00 % Cft. 225.00
TOTAL 10275.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1027.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 11302.50
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Coolies. 3.50 Nos: 250.00 P.day. 875.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50


Rs: 2062.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 206.25
_______________________________ _______ ______ _______ ______ _________
TOTAL 2268.75
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 226.88
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 2495.63
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 13798.13
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 13798.13
Total material & labour for 100 Cft. say Rs: 13798.13
_____ _______________________________ _______ ______ _______ ______ _________

Chapter No. 5 356/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

FOUNDATION AND PLINTH.


======================
1. Random, rubble masonary. (Un-coursed)
(C) In Lime Mortar (i) 1 Lime : 2 Sand.
_____ _______________________________ _______ ______ _______ ______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Lime slacked (Ground) 6.00 Mand 375.00 P.Mand 2250.00

Sand. 30.00 Cft. 2425.00 % Cft. 727.50


TOTAL 13027.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1302.75
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 14330.25
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.00 Nos: 450.00 P.day. 1800.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


_______________________________ _______ ______ _______ ______ _________
Rs: 3175.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 317.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3492.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 349.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 3841.75
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 18172.00
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 18172.00
Total material & labour for 100 Cft. say Rs: 18172.00

Chapter No. 5 357/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
FOUNDATION AND PLINTH.
======================
1. Random, rubble masonary. (Un-coursed)
(C) In Lime Mortar (ii) 1 Lime : 1 Sand : 1 Surkhi.

(A) MATERIAL QUANTITYRATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Lime slacked (Ground) 6.00 Mand 375.00 P.Mand 2250.00

Surkhi. 15.00 Cft. 2250.00 % Cft. 337.50

Sand. 15.00 Cft. 2425.00 % Cft. 363.75

TOTAL 13001.25
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1300.13
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 14301.38
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.00 Nos: 450.00 P.day. 1800.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


Rs: 3175.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 317.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3492.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 349.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 3841.75
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 18143.13
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 18143.13
Total material & labour for 100 Cft. say Rs: 18143.13

S/N D E S C R I P T I O N.

Chapter No. 5 358/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

FOUNDATION AND PLINTH.


======================
1. Random, rubble masonary. (Un-coursed)
(C) In Lime Mortar (iii) 1 Lime : 2 Surkhi.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Lime slacked (Ground) 6.00 Mand 375.00 P.Mand 2250.00

Surkhi. 30.00 Cft. 2250.00 % Cft. 675.00


_______________________________ _______ ______ _______ ______ _________
TOTAL 12975.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1297.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 14272.50
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.00 Nos: 450.00 P.day. 1800.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


Rs: 3175.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 317.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3492.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 349.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 3841.75
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 18114.25
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 18114.25
Total material & labour for 100 Cft. say Rs: 18114.00

Chapter No. 5 359/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
FOUNDATION AND PLINTH.
======================
1. Random, rubble masonary. (Un-coursed)
(d) In Cement Sand Mortar (i) 1 Cement : 3 Sand.

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Cement. 9.00 Cwt. 400.00 P.bag. 3600.00

Sand. 33.75 Cft. 2425.00 % Cft. 818.44


_______________________________ _______ ______ _______ ______ _________
TOTAL 14468.44
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1446.84
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 15915.28
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.00 Nos: 450.00 P.day. 1800.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


Rs: 3175.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 317.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3492.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 349.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 3841.75
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 19757.03
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 19757.03
Total material & labour for 100 Cft. say Rs: 19757.00

Chapter No. 5 360/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
FOUNDATION AND PLINTH.
======================
1. Random, rubble masonary. (Un-coursed)
(d) In Cement Sand Mortar (ii) 1 Cement : 4 Sand.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Cement. 7.20 Cwt. 400.00 P.bag. 2880.00

Sand. 36.00 Cft. 2425.00 % Cft. 873.00


TOTAL 13803.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1380.30
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 15183.30
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.00 Nos: 450.00 P.day. 1800.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


Rs: 3175.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 317.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3492.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 349.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 3841.75
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 19025.05
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 19025.05
Total material & labour for 100 Cft. say Rs: 19025.00

Chapter No. 5 361/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
FOUNDATION AND PLINTH.
======================
1. Random, rubble masonary. (Un-coursed)
(d) In Cement Sand Mortar (iii) 1 Cement : 6 Sand.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Cement. 5.14 Cwt. 400.00 P.bag. 2056.00

Sand. 38.57 Cft. 2425.00 % Cft. 935.32

TOTAL 13041.32
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1304.13
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 14345.45
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.00 Nos: 450.00 P.day. 1800.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


Rs: 3175.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 317.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3492.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 349.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 3841.75
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 18187.20
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 18187.00

Chapter No. 5 362/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
FOUNDATION AND PLINTH.
======================
1. Random, rubble masonary. (Un-coursed)
(d) In Cement Sand Mortar (iv) 1 Cement : 8 Sand.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Cement. 4.00 Cwt. 400.00 P.bag. 1600.00

Sand. 40.00 Cft. 2425.00 % Cft. 970.00


_______________________________ _______ ______ _______ ______ _________
TOTAL 12620.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1262.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 13882.00
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.00 Nos: 450.00 P.day. 1800.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


Rs: 3175.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 317.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3492.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 349.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 3841.75
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 17723.75
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 17723.00
_____ _______________________________ _______ ______ _______ ______ _________

Chapter No. 5 363/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
FOUNDATION AND PLINTH.
======================
2. Coursed rubble masonary including hammer dressing.
(a) Dry Masonary.
_____ _______________________________ _______ ______ _______ ______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos:)
TOTAL 10050.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1005.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 11055.00
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 3.00 Nos: 450.00 P.day. 1350.00

Coolies. 3.00 Nos: 250.00 P.day. 750.00


Rs: 2100.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 210.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 2310.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 231.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 2541.00
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 13596.00
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 13596.00

_____ _______________________________ _______ ______ _______ ______ _________


_____ _______________________________ _______ ______ _______ ______ _________

Chapter No. 5 364/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

FOUNDATION AND PLINTH.


======================
2. Coursed rubble masonary including hammer dressing.
(b) In Mud Mortar.
_____ _______________________________ _______ ______ _______ ______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Good earth. 45.00 Cft. 500.00 % Cft. 225.00
TOTAL 10275.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1027.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 11302.50
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.00 Nos: 450.00 P.day. 1800.00

Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


_______________________________ _______ ______ _______ ______ _________
Rs: 2925.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 292.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3217.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 321.75
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 3539.25
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 14841.75
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 4365.35
_____ _______________________________ _______ ______ _______ ______ _________

Chapter No. 5 365/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

FOUNDATION AND PLINTH.


======================
2. Coursed rubble masonary including hammer dressing.
(C) In Lime Mortar (i) 1 Lime : 2 Sand.
_____ _______________________________ _______ ______ _______ ______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Lime slacked (Ground) 5.33 Mand 375.00 P.Mand 1998.75

Sand. 26.67 Cft. 2425.00 % Cft. 646.75

TOTAL 12695.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1269.55
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 13965.05
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.75 Nos: 450.00 P.day. 2137.50

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 3575.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 357.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3932.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 393.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4325.75
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 18290.80
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 18291.00

Chapter No. 5 366/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
FOUNDATION AND PLINTH.
======================
2. Coursed rubble masonary including hammer dressing.
(C) In Lime Mortar (ii) 1 Lime : 1 Sand : 1 Surkhi.
_____ _______________________________ _______ ______ _______ ______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 35.00 Nos: 450.00 Each. 15750.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Lime slacked (Ground) 5.33 Mand 375.00 P.Mand 1998.75

Surkhi. 13.34 Cft. 2250.00 % Cft. 300.15

Sand. 13.34 Cft. 2425.00 % Cft. 323.50

TOTAL 19422.40
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1942.24
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 21364.63
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.75 Nos: 450.00 P.day. 2137.50

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 3575.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 357.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3932.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 393.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4325.75
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 25690.38
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 25690.00

Chapter No. 5 367/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
FOUNDATION AND PLINTH.
======================
2. Coursed rubble masonary including hammer dressing.
(C) In Lime Mortar (iii) 1 Lime : 2 Surkhi.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 35.00 Nos: 450.00 Each. 15750.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Lime slacked (Ground) 5.33 Mand 375.00 P.Mand 1998.75

Surkhi. 26.67 Cft. 2250.00 % Cft. 600.08

TOTAL 19398.83
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1939.88
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 21338.71
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.75 Nos: 450.00 P.day. 2137.50

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 3575.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 357.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3932.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 393.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4325.75
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 25664.46
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 25664.46
_____ _______________________________ _______ ______ _______ ______ _________

Chapter No. 5 368/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
FOUNDATION AND PLINTH.
======================
2. Coursed rubble masonary including hammer dressing.
(d) In Cement Sand Mortar (i) 1 Cement : 3 Sand.

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 35.00 Nos: 450.00 Each. 15750.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Cement. 8.00 Cwt. 400.00 P.bag. 3200.00

Sand. 30.00 Cft. 2425.00 % Cft. 727.50

_______________________________ _______ ______ _______ ______ _________


TOTAL 20727.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 2072.75
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 22800.25
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.75 Nos: 450.00 P.day. 2137.50

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 3575.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 357.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3932.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 393.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4325.75
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 27126.00
Total material & labour for 100 Cft. Rs: 27126.00

Chapter No. 5 369/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
FOUNDATION AND PLINTH.
======================
2. Coursed rubble masonary including hammer dressing.
(d) In Cement Sand Mortar (ii) 1 Cement : 4 Sand.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 35.00 Nos: 450.00 Each. 15750.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Cement. 6.40 Cwt. 400.00 P.bag. 2560.00

Sand. 32.00 Cft. 2425.00 % Cft. 776.00


TOTAL 20136.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 2013.60
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 22149.60
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.75 Nos: 450.00 P.day. 2137.50

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 3575.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 357.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3932.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 393.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4325.75
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 26475.35
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 26475.00
_____ _______________________________ _______ ______ _______ ______ _________

Chapter No. 5 370/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
FOUNDATION AND PLINTH.
======================
2. Coursed rubble masonary including hammer dressing.
(d) In Cement Sand Mortar (iii) 1 Cement : 6 Sand.

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 35.00 Nos: 450.00 Each. 15750.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Cement. 4.57 Cwt. 400.00 P.bag. 1828.00

Sand. 34.20 Cft. 2425.00 % Cft. 829.35

_______________________________ _______ ______ _______ ______ _________


TOTAL 19457.35
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1945.74
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 21403.09
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.75 Nos: 450.00 P.day. 2137.50

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50

Rs: 3575.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 357.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3932.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 393.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4325.75
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 25728.84
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 25729.00

Chapter No. 5 371/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
FOUNDATION AND PLINTH.
======================
2. Coursed rubble masonary including hammer dressing.
(d) In Cement Sand Mortar (iv) 1 Cement : 8 Sand.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 35.00 Nos: 450.00 Each. 15750.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Cement. 3.56 Cwt. 400.00 P.bag. 1424.00

Sand. 35.60 Cft. 2425.00 % Cft. 863.30


TOTAL 19087.30
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1908.73
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 20996.03
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
For Masonary Work.
Masons. 4.75 Nos: 450.00 P.day. 2137.50

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 3575.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 357.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3932.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 393.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4325.75
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 25321.78
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 25321.00

Chapter No. 5 372/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
Ground Floor or 20 ft: hieght of un-covered wall.
3. Random, rubble masonary. (Un-coursed)
(a) Dry Masonary.
_____ _______________________________ _______ ______ _______ ______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos:)
TOTAL 10050.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1005.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 11055.00
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Coolies. 3.00 Nos: 250.00 P.day. 750.00

Rs: 1875.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 187.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 2062.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 206.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 2268.75
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 13323.75
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 13323.75

_____ _______________________________ _______ ______ _______ ______ _________

_____ _______________________________ _______ ______ _______ ______ _________

Chapter No. 5 373/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

SUPER STRUCTURE.
================
Ground Floor or 20 ft: hieght of un-covered wall.
1. Random, rubble masonary. (Un-coursed)
(b) In Mud Mortar.
_____ _______________________________ _______ ______ _______ ______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Good earth. 45.00 Cft. 500.00 % Cft. 225.00
TOTAL 10275.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1027.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 11302.50
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 3.00 Nos: 450.00 P.day. 1350.00

Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


Rs: 2475.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 247.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 2722.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 272.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 2994.75
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 14297.25
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 14297.00
_____ _______________________________ _______ ______ _______ ______ _________

Chapter No. 5 374/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
Ground Floor or 20 ft: hieght of un-covered wall.
3. Random, rubble masonary. (Un-coursed)
(C) In Lime Mortar (i) 1 Lime : 2 Sand.
_____ _______________________________ _______ ______ _______ ______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Lime slacked (Ground) 6.00 Mand 375.00 P.Mand 2250.00

Sand. 30.00 Cft. 2425.00 % Cft. 727.50


_______________________________ _______ ______ _______ ______ _________
TOTAL 13027.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1302.75
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 14330.25
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.50 Nos: 450.00 P.day. 2025.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


_______________________________ _______ ______ _______ ______ _________
Rs: 3462.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 346.25
_______________________________ _______ ______ _______ ______ _________
TOTAL 3808.75
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 380.88
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4189.63
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 18519.88
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 18520.00

Chapter No. 5 375/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
Ground Floor or 20 ft: hieght of un-covered wall.
3. Random, rubble masonary. (Un-coursed)
(C) In Lime Mortar (ii) 1 Lime : 1 Sand : 1 Surkhi.

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Lime slacked (Ground) 6.00 Mand 375.00 P.Mand 2250.00

Surkhi. 15.00 Cft. 2250.00 % Cft. 337.50

Sand. 15.00 Cft. 2425.00 % Cft. 363.75

TOTAL 13001.25
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1300.13
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 14301.38
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.50 Nos: 450.00 P.day. 2025.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 3462.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 346.25
_______________________________ _______ ______ _______ ______ _________
TOTAL 3808.75
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 380.88
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4189.63
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 18491.00
Total material & labour for 100 Cft. Rs: 18491.00

Chapter No. 5 376/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
Ground Floor or 20 ft: hieght of un-covered wall.
3. Random, rubble masonary. (Un-coursed)
(C) In Lime Mortar (iii) 1 Lime : 2 Surkhi.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Lime slacked (Ground) 6.00 Mand 375.00 P.Mand 2250.00

Surkhi. 30.00 Cft. 2250.00 % Cft. 675.00

TOTAL 12975.00
Contractor's profit 10.00 % 1297.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 14272.50
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.50 Nos: 450.00 P.day. 2025.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 3462.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 346.25
_______________________________ _______ ______ _______ ______ _________
TOTAL 3808.75
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 380.88
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4189.63
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 18462.13
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 18462.00

Chapter No. 5 377/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
Ground Floor or 20 ft: hieght of un-covered wall.
3. Random, rubble masonary. (Un-coursed)
(d) In Cement Sand Mortar (i) 1 Cement : 3 Sand.

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Cement. 9.00 Cwt. 400.00 P.bag. 3600.00

Sand. 33.75 Cft. 2425.00 % Cft. 818.44


_______________________________ _______ ______ _______ ______ _________
TOTAL 14468.44
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1446.84
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 15915.28
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.50 Nos: 450.00 P.day. 2025.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50

Rs: 3462.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 346.25
_______________________________ _______ ______ _______ ______ _________
TOTAL 3808.75
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 380.88
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4189.63
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 20104.91
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 20105.00

Chapter No. 5 378/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
Ground Floor or 20 ft: hieght of un-covered wall.
3. Random, rubble masonary. (Un-coursed)
(d) In Cement Sand Mortar (ii) 1 Cement : 4 Sand.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Cement. 7.20 Cwt. 400.00 P.bag. 2880.00

Sand. 36.00 Cft. 2425.00 % Cft. 873.00

TOTAL 13803.00
Contractor's profit 10.00 % 1380.30
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 15183.30
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.50 Nos: 450.00 P.day. 2025.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 3462.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 346.25
_______________________________ _______ ______ _______ ______ _________
TOTAL 3808.75
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 380.88
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4189.63
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 19372.93
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 19373.00
_____ _______________________________ _______ ______ _______ ______ _________

Chapter No. 5 379/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
Ground Floor or 20 ft: hieght of un-covered wall.
3. Random, rubble masonary. (Un-coursed)
(d) In Cement Sand Mortar (iii) 1 Cement : 6 Sand.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Cement. 5.14 Cwt. 400.00 P.bag. 2056.00

Sand. 38.57 Cft. 2425.00 % Cft. 935.32


TOTAL 13041.32
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1304.13
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 14345.45
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.50 Nos: 450.00 P.day. 2025.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 3462.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 346.25
_______________________________ _______ ______ _______ ______ _________
TOTAL 3808.75
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 380.88
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4189.63
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 18535.08
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 18535.00

Chapter No. 5 380/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
Ground Floor or 20 ft: hieght of un-covered wall.
3. Random, rubble masonary. (Un-coursed)
(d) In Cement Sand Mortar (iv) 1 Cement : 8 Sand.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Cement. 4.00 Cwt. 400.00 P.bag. 1600.00

Sand. 40.00 Cft. 2425.00 % Cft. 970.00


TOTAL 12620.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1262.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 13882.00
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 4.50 Nos: 450.00 P.day. 2025.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 3462.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 346.25
_______________________________ _______ ______ _______ ______ _________
TOTAL 3808.75
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 380.88
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4189.63
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 18071.63
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 18071.63

Chapter No. 5 381/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
(i) First Floor.
3. Random, rubble masonary. (Un-coursed)
(e) Add extra labour in item No:3 for stone work.
_____ _______________________________ _______ ______ _______ ______ _________
LABOUR. QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 0.40 Nos: 450.00 P.day. 180.00

Coolies. 1.35 Nos: 250.00 P.day. 337.50


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 517.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 51.75
_______________________________ _______ ______ _______ ______ _________
TOTAL 569.25
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 56.93
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 626.18
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 294.05
_____ _______________________________ _______ ______ _______ ______ _________
S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
(ii) Second Floor.
3. Random, rubble masonary. (Un-coursed)
(e) Add extra labour in item No:3 for stone work.

LABOUR. QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 1.20 Nos: 450.00 P.day. 540.00

Coolies. 2.60 Nos: 250.00 P.day. 650.00


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 1190.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 119.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 1309.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 130.90
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 1439.90
Total labour rate for 100 Cft. say Rs: 1440.00
S/N D E S C R I P T I O N.

Chapter No. 5 382/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

SUPER STRUCTURE.
================
(iii) Third Floor.
3. Random, rubble masonary. (Un-coursed)
(e) Add extra labour in item No:3 for stone work.
_____ _______________________________ _______ ______ _______ ______ _________
LABOUR. QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 2.00 Nos: 450.00 P.day. 900.00

Coolies. 3.90 Nos: 250.00 P.day. 975.00


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 1875.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 187.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 2062.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 206.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 2268.75
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 2269.00
S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
(iv) Fourth Floor and subsequent Floor.
3. Random, rubble masonary. (Un-coursed)
(e) Add extra labour in item No:3 for stone work.
_____ _______________________________ _______ ______ _______ ______ _________
LABOUR. QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 3.60 Nos: 450.00 P.day. 1620.00

Coolies. 5.60 Nos: 250.00 P.day. 1400.00


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 3020.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 302.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 3322.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 332.20
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 3654.20
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 1853.70
S/N D E S C R I P T I O N.
SUPER STRUCTURE.

Chapter No. 5 383/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

================
3. Random, rubble masonary. (Un-coursed)
(f) Add extra labour for every 5 feet additional hieght of
un-covered wall.
LABOUR. QUANTITYRATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 0.50 Nos: 450.00 P.day. 225.00

Coolies. 1.00 Nos: 250.00 P.day. 250.00


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 475.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 47.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 522.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 52.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 574.75
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 574.75

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================

Chapter No. 5 384/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

4. Coursed rubble masonary including hammer dressing.


(a) Dry Masonary.
_____ _______________________________ _______ ______ _______ ______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos:)
TOTAL 10050.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1005.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 11055.00
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 3.50 Nos: 450.00 P.day. 1575.00

Coolies. 3.50 Nos: 250.00 P.day. 875.00


Rs: 2450.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 245.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 2695.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 269.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 2964.50
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 14019.50
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 14019.00

S/N D E S C R I P T I O N.

SUPER STRUCTURE.
================

Chapter No. 5 385/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Ground Floor or 20 ft: hieght of un-covered wall.


4. Coursed rubble masonary including hammer dressing.
(b) In Mud Mortar.
_____ _______________________________ _______ ______ _______ ______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Good earth. 45.00 Cft. 500.00 % Cft. 225.00
TOTAL 10275.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1027.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 11302.50
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 5.00 Nos: 450.00 P.day. 2250.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


Rs: 3625.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 362.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3987.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 398.75
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4386.25
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 15688.75
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 15689.00
_____ _______________________________ _______ ______ _______ ______ _________

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
Ground Floor or 20 ft: hieght of un-covered wall.
4. Coursed rubble masonary including hammer dressing.

Chapter No. 5 386/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(C) In Lime Mortar (i) 1 Lime : 2 Sand.


_____ _______________________________ _______ ______ _______ ______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 20.00 Nos: 450.00 Each. 9000.00


(Having special size of
1.5' * 8" * 10" * 20Nos: =
17 Cft.)
Lime slacked (Ground) 5.33 Mand 375.00 P.Mand 1998.75

Sand. 26.67 Cft. 2425.00 % Cft. 646.75

_______________________________ _______ ______ _______ ______ _________


TOTAL 12695.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1269.55
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 13965.05
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 5.50 Nos: 450.00 P.day. 2475.00

Coolies. 5.50 Nos: 250.00 P.day. 1375.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 4037.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 403.75
_______________________________ _______ ______ _______ ______ _________
TOTAL 4441.25
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 444.13
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4885.38
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 18850.42
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 18850.00

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
4. Coursed rubble masonary including hammer dressing.
(C) In Lime Mortar (ii) 1 Lime : 1 Sand : 1 Surkhi.

Chapter No. 5 387/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 35.00 Nos: 450.00 Each. 15750.00


(Having special size of
1.5' * 8" * 10" * 35 Nos: =
30 Cft.)
Lime slacked (Ground) 5.33 Mand 375.00 P.Mand 1998.75

Surkhi. 13.34 Cft. 2250.00 % Cft. 300.15

Sand. 13.34 Cft. 2425.00 % Cft. 323.50

TOTAL 19422.40
Contractor's profit 10.00 % 1942.24
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 21364.63
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 5.50 Nos: 450.00 P.day. 2475.00

Coolies. 5.50 Nos: 250.00 P.day. 1375.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 4037.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 403.75
_______________________________ _______ ______ _______ ______ _________
TOTAL 4441.25
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 444.13
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4885.38
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 26250.01
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 26250.00

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
4. Coursed rubble masonary including hammer dressing.
(C) In Lime Mortar (iii) 1 Lime : 2 Surkhi.

_____ _______________________________ _______ ______ _______ ______ _________

Chapter No. 5 388/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 35.00 Nos: 450.00 Each. 15750.00


(Having special size of
1.5' * 8" * 10" * 35 Nos: =
30 Cft.)
Lime slacked (Ground) 5.33 Mand 375.00 P.Mand 1998.75

Surkhi. 26.67 Cft. 2250.00 % Cft. 600.08

TOTAL 19398.83
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1939.88
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 21338.71
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 5.50 Nos: 450.00 P.day. 2475.00

Coolies. 5.50 Nos: 250.00 P.day. 1375.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 4037.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 403.75
_______________________________ _______ ______ _______ ______ _________
TOTAL 4441.25
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 444.13
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4885.38
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 26224.08
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 26224.00

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
4. Coursed rubble masonary including hammer dressing.
(d) In Cement Sand Mortar (i) 1 Cement : 3 Sand.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT

Chapter No. 5 389/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 35.00 Nos: 450.00 Each. 15750.00


(Having special size of
1.5' * 8" * 10" * 35 Nos: =
30 Cft.)
Cement. 8.00 Cwt. 400.00 P.bag. 3200.00

Sand. 30.00 Cft. 2425.00 % Cft. 727.50


_______________________________ _______ ______ _______ ______ _________
TOTAL 20727.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 2072.75
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 22800.25
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 5.50 Nos: 450.00 P.day. 2475.00

Coolies. 5.50 Nos: 250.00 P.day. 1375.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 4037.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 403.75
_______________________________ _______ ______ _______ ______ _________
TOTAL 4441.25
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 444.13
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4885.38
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 27685.63
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 27685.00

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
4. Coursed rubble masonary including hammer dressing.
(d) In Cement Sand Mortar (ii) 1 Cement : 4 Sand.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:

Chapter No. 5 390/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ _______ ______ _______ ______ _________


Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 35.00 Nos: 450.00 Each. 15750.00


(Having special size of
1.5' * 8" * 10" * 35 Nos: =
30 Cft.)
Cement. 6.40 Cwt. 400.00 P.bag. 2560.00

Sand. 32.00 Cft. 2425.00 % Cft. 776.00

TOTAL 20136.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 2013.60
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 22149.60
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 5.50 Nos: 450.00 P.day. 2475.00

Coolies. 5.50 Nos: 250.00 P.day. 1375.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 4037.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 403.75
_______________________________ _______ ______ _______ ______ _________
TOTAL 4441.25
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 444.13
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4885.38
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 27034.98
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. Rs: 27035.00

Chapter No. 5 391/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
4. Coursed rubble masonary including hammer dressing.
(d) In Cement Sand Mortar (iii) 1 Cement : 6 Sand.

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 35.00 Nos: 450.00 Each. 15750.00


(Having special size of
1.5' * 8" * 10" * 35 Nos: =
30 Cft.)
Cement. 4.57 Cwt. 400.00 P.bag. 1828.00

Sand. 34.20 Cft. 2425.00 % Cft. 829.35

_______________________________ _______ ______ _______ ______ _________


TOTAL 19457.35
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1945.74
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 21403.09
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
Masons. 5.50 Nos: 450.00 P.day. 2475.00

Coolies. 5.50 Nos: 250.00 P.day. 1375.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 4037.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 403.75
_______________________________ _______ ______ _______ ______ _________
TOTAL 4441.25
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 444.13
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4885.38
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 26288.46
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 26288.00

S/N D E S C R I P T I O N.

Chapter No. 5 392/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

SUPER STRUCTURE.
================
4. Coursed rubble masonary including hammer dressing.
(d) In Cement Sand Mortar (iv) 1 Cement : 8 Sand.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 100 Cft. 1050.00 % Cft. 1050.00

Headers or through stones. 35.00 Nos: 450.00 Each. 15750.00


(Having special size of
1.5' * 8" * 10" * 35 Nos: =
30 Cft.)
Cement. 3.56 Cwt. 400.00 P.bag. 1424.00

Sand. 35.60 Cft. 2425.00 % Cft. 863.30

TOTAL 19087.30
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1908.73
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 20996.03
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.
For Masonary Work.
Masons. 5.50 Nos: 450.00 P.day. 2475.00

Coolies. 5.50 Nos: 250.00 P.day. 1375.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


Rs: 4037.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 403.75
_______________________________ _______ ______ _______ ______ _________
TOTAL 4441.25
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 444.13
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4885.38
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 25881.41
Total material & labour for 100 Cft. say Rs: 25881.00

Chapter No. 5 393/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
(i) First Floor.
4. Coursed rubble masonary including hammer dressing.
(e) Add extra labour in item No:3 for stone work.
LABOUR. QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 0.40 Nos: 450.00 P.day. 180.00

Coolies. 1.35 Nos: 250.00 P.day. 337.50


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 517.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 51.75
_______________________________ _______ ______ _______ ______ _________
TOTAL 569.25
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 56.93
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 626.18
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 626.00
_____ _______________________________ _______ ______ _______ ______ _________
S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
(ii) Second Floor.
4. Coursed rubble masonary including hammer dressing.
(e) Add extra labour in item No:3 for stone work.

LABOUR. QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 1.20 Nos: 450.00 P.day. 540.00

Coolies. 2.60 Nos: 250.00 P.day. 650.00


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 1190.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 119.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 1309.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 130.90
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 1439.90
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 1440.00
S/N D E S C R I P T I O N.

Chapter No. 5 394/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

SUPER STRUCTURE.
================
(iii) Third Floor.
4. Coursed rubble masonary including hammer dressing.
(e) Add extra labour in item No:3 for stone work.

LABOUR. QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 2.00 Nos: 450.00 P.day. 900.00

Coolies. 3.90 Nos: 250.00 P.day. 975.00


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 1875.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 187.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 2062.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 206.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 2268.75
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 2269.00
S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
(iv) Fourth Floor and subsequent Floor.
4. Coursed rubble masonary including hammer dressing.
(e) Add extra labour in item No:3 for stone work.

_____ _______________________________ _______ ______ _______ ______ _________


LABOUR. QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 3.60 Nos: 450.00 P.day. 1620.00

Coolies. 5.60 Nos: 250.00 P.day. 1400.00


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 3020.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 302.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 3322.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 332.20
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 3654.20
Total labour rate for 100 Cft. say Rs: 3654.00
S/N D E S C R I P T I O N.
SUPER STRUCTURE.

Chapter No. 5 395/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

================
4. Coursed rubble masonary including hammer dressing.
(f) Add extra labour for every 5 feet additional hieght of
un-covered wall.
LABOUR. QUANTITYRATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 0.50 Nos: 450.00 P.day. 225.00

Coolies. 1.00 Nos: 250.00 P.day. 250.00


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 475.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 47.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 522.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 52.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 574.75
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 574.75
S/N D E S C R I P T I O N.

5. Ashler block in course or scabbled masonary (including dressing


etc:)
(a) In Lime Mortar. i) 1 lime : 2 Sand.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 200 Cft. 1050.00 % Cft. 2100.00

Lime Slaked (ground) 4.00 Cft. 375.00 P.Mand. 1500.00

Sand. 20.00 Cft. 2425.00 % Cft. 485.00

Charcoal. 30.00 Lbs. 675.00 P.Mand. 246.95

Steel. 3.30 Lbs. 3550.00 P.Cwt. 104.60


TOTAL 4436.55
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 443.65
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 4880.20
_______________________________ _______ ______ _______ ______ _________

Chapter No. 5 396/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.

Masons. 10.00 Nos: 450.00 P.day. 4500.00

Coolies. 10.00 Nos: 250.00 P.day. 2500.00

Bahishti. 1.00 Nos: 250.00 P.day. 250.00

Black-smith 1.00 Nos: 450.00 P.day. 450.00

Bellow man. 1.00 Nos: 250.00 P.day. 250.00

_______________________________ _______ ______ _______ ______ _________


Rs: 7950.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 795.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 8745.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 874.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 9619.50
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 14499.70
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 14499.70

Chapter No. 5 397/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Ashler block in course or scabbled masonary (including dressing


etc:)
(a) In Lime Mortar. ii) 1 lime : 1 Surkhi : 1 Sand.
_____ _______________________________ _______ ______ _______ ______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 200 Cft. 1050.00 % Cft. 2100.00

Lime Slaked (ground) 4.00 Cft. 375.00 P.Mand. 1500.00

Surkhi. 10.00 Cft. 2250.00 % Cft. 225.00

Sand. 10.00 Cft. 2425.00 % Cft. 242.50

Charcoal. 30.00 Lbs. 675.00 P.Mand. 246.95

Steel. 3.30 Lbs. 3550.00 P.Cwt. 104.60

TOTAL 4419.05
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 441.90
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 4860.95
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.

Masons. 10.00 Nos: 450.00 P.day. 4500.00

Coolies. 10.00 Nos: 250.00 P.day. 2500.00

Bahishti. 1.00 Nos: 250.00 P.day. 250.00

Black-smith 1.00 Nos: 450.00 P.day. 450.00

Bellow man. 1.00 Nos: 250.00 P.day. 250.00


Rs: 7950.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 795.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 8745.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 874.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 9619.50
TOTAL (MATERIAL + LABOUR) 14480.45
Total material & labour for 100 Cft. say Rs: 14480.00
S/N D E S C R I P T I O N.

Chapter No. 5 398/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

5. Ashler block in course or scabbled masonary (including dressing


etc:)
(a) In Lime Mortar. iii) 1 lime : 2 Surkhi.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 200 Cft. 1050.00 % Cft. 2100.00

Lime Slaked (ground) 4.00 Cft. 375.00 P.Mand. 1500.00

Surkhi. 20.00 Cft. 2250.00 % Cft. 450.00

Charcoal. 30.00 Lbs. 675.00 P.Mand. 246.95

Steel. 3.30 Lbs. 3550.00 P.Cwt. 104.60


TOTAL 4401.55
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 440.15
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 4841.70
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.

Masons. 10.00 Nos: 450.00 P.day. 4500.00

Coolies. 10.00 Nos: 250.00 P.day. 2500.00

Bahishti. 1.00 Nos: 250.00 P.day. 250.00

Black-smith 1.00 Nos: 450.00 P.day. 450.00

Bellow man. 1.00 Nos: 250.00 P.day. 250.00


Rs: 7950.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 795.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 8745.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 874.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 9619.50
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 14461.20
Total material & labour for 100 Cft. say Rs: 14461.00
S/N D E S C R I P T I O N.

Chapter No. 5 399/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

5. Ashler block in course or scabbled masonary (including dressing


etc:)
(b) In Cement Sand Mortar. i) 1 Cement : 3 Sand.

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 200 Cft. 1050.00 % Cft. 2100.00

Cement. 6.00 Cwt. 400.00 P.Bag. 2400.00

Sand. 22.50 Cft. 2425.00 % Cft. 545.63

Charcoal. 30.00 Lbs. 675.00 P.Mand. 246.95

Steel. 3.30 Lbs. 3550.00 P.Cwt. 104.60


TOTAL 5397.17
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 539.72
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 5936.89
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.

Masons. 10.00 Nos: 450.00 P.day. 4500.00

Coolies. 10.00 Nos: 250.00 P.day. 2500.00

Bahishti. 1.00 Nos: 250.00 P.day. 250.00

Black-smith 1.00 Nos: 450.00 P.day. 450.00

Bellow man. 1.00 Nos: 250.00 P.day. 250.00

Rs: 7950.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 795.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 8745.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 874.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 9619.50
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 15556.39
Total material & labour for 100 Cft. say Rs: 15556.00
S/N D E S C R I P T I O N.

5. Ashler block in course or scabbled masonary (including dressing

Chapter No. 5 400/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

etc:)
(b) In Cement Sand Mortar. ii) 1 Cement : 4 Sand.
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 200 Cft. 1050.00 % Cft. 2100.00

Cement. 4.80 Cwt. 400.00 P.Bag. 1920.00

Sand. 24.00 Cft. 2425.00 % Cft. 582.00

Charcoal. 30.00 Lbs. 675.00 P.Mand. 246.95

Steel. 3.30 Lbs. 3550.00 P.Cwt. 104.60


TOTAL 4953.55
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 495.35
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 5448.90
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.

Masons. 10.00 Nos: 450.00 P.day. 4500.00

Coolies. 10.00 Nos: 250.00 P.day. 2500.00

Bahishti. 1.00 Nos: 250.00 P.day. 250.00

Black-smith 1.00 Nos: 450.00 P.day. 450.00

Bellow man. 1.00 Nos: 250.00 P.day. 250.00


Rs: 7950.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 795.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 8745.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 874.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 9619.50
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 15068.40
Total material & labour for 100 Cft. say Rs: 15068.00

Chapter No. 5 401/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Ashler block in course or scabbled masonary (including dressing


etc:)
(b) In Cement Sand Mortar. iii) 1 Cement : 6 Sand.

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 200 Cft. 1050.00 % Cft. 2100.00

Cement. 3.44 Cwt. 400.00 P.Bag. 1376.00

Sand. 25.70 Cft. 2425.00 % Cft. 623.23

Charcoal. 30.00 Lbs. 675.00 P.Mand. 246.95

Steel. 3.30 Lbs. 3550.00 P.Cwt. 104.60


TOTAL 4450.77
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 445.08
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 4895.85
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.

Masons. 10.00 Nos: 450.00 P.day. 4500.00

Coolies. 10.00 Nos: 250.00 P.day. 2500.00

Bahishti. 1.00 Nos: 250.00 P.day. 250.00

Black-smith 1.00 Nos: 450.00 P.day. 450.00

Bellow man. 1.00 Nos: 250.00 P.day. 250.00


Rs: 7950.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 795.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 8745.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 874.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 9619.50
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 14515.35
Total material & labour for 100 Cft. say Rs: 14515.00

Chapter No. 5 402/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
(i) First Floor.
5. Ashler block in course or scabbled masonary(i/c dressing etc:)
(c) Add extra labour in item No:5 for stone work.
LABOUR. QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 0.40 Nos: 450.00 P.day. 180.00

Coolies. 1.35 Nos: 250.00 P.day. 337.50


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 517.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 51.75
_______________________________ _______ ______ _______ ______ _________
TOTAL 569.25
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 56.93
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 626.18
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 626.00
S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
(ii) Second Floor.
5. Ashler block in course or scabbled masonary(i/c dressing etc:)
(c) Add extra labour in item No:5 for stone work.

_____ _______________________________ _______ ______ _______ ______ _________


LABOUR. QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 1.20 Nos: 450.00 P.day. 540.00

Coolies. 2.60 Nos: 250.00 P.day. 650.00


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 1190.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 119.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 1309.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 130.90
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 1439.90
Total labour rate for 100 Cft. say Rs: 1439.00

S/N D E S C R I P T I O N.

Chapter No. 5 403/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

SUPER STRUCTURE.
================
(iii) Third Floor.
5. Ashler block in course or scabbled masonary(i/c dressing etc:)
(c) Add extra labour in item No:5 for stone work.
LABOUR. QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 2.00 Nos: 450.00 P.day. 900.00

Coolies. 3.90 Nos: 250.00 P.day. 975.00


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 1875.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 187.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 2062.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 206.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 2268.75
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 2269.00
S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
(iv) Fourth Floor and subsequent Floor.
5. Ashler block in course or scabbled masonary(i/c dressing etc:)
(c) Add extra labour in item No:5 for stone work.

LABOUR. QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 3.60 Nos: 450.00 P.day. 1620.00

Coolies. 5.60 Nos: 250.00 P.day. 1400.00


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 3020.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 302.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 3322.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 332.20
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 3654.20
Total labour rate for 100 Cft. say Rs: 3654.00

S/N D E S C R I P T I O N.

Chapter No. 5 404/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

6. Ashler fine masonary (including dressing etc:)

(a) In Lime Mortar. i) 1 lime : 1 Surkhi : 1 Sand.


(A) MATERIAL QUANTITY
RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 250 Cft. 1050.00 % Cft. 2625.00

Lime Slaked (ground) 2.00 Cft. 375.00 P.Mand. 750.00

Surkhi. 5.00 Cft. 2250.00 % Cft. 112.50

Sand. 5.00 Cft. 2425.00 % Cft. 121.25

Charcoal. 60.00 Lbs. 675.00 P.Mand. 493.90

Steel. 4.00 Lbs. 3550.00 P.Cwt. 126.79


TOTAL 4229.44
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 422.94
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 4652.38
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.

Masons. 20.00 Nos: 450.00 P.day. 9000.00

Coolies. 8.00 Nos: 250.00 P.day. 2000.00

Bahishti. 1.00 Nos: 250.00 P.day. 250.00

Black-smith 1.50 Nos: 450.00 P.day. 675.00

Bellow man. 1.50 Nos: 250.00 P.day. 375.00


Rs: 12300.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 1230.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 13530.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1353.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 14883.00
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 19535.38
Total material & labour for 100 Cft. say Rs: 19535.38
S/N D E S C R I P T I O N.

6. Ashler fine masonary (including dressing etc:)

Chapter No. 5 405/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(a) In Lime Mortar. ii) 1 lime : 2 Surkhi.

(A) MATERIAL QUANTITYRATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 250 Cft. 1050.00 % Cft. 2625.00

Lime Slaked (ground) 2.00 Cft. 375.00 P.Mand. 750.00

Surkhi. 10.00 Cft. 2250.00 % Cft. 225.00

Charcoal. 60.00 Lbs. 675.00 P.Mand. 493.90

Steel. 4.00 Lbs. 3550.00 P.Cwt. 126.79


TOTAL 4220.69
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 422.07
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 4642.76
(B) LABOUR
For Masonary Work.

Masons. 20.00 Nos: 450.00 P.day. 9000.00

Coolies. 8.00 Nos: 250.00 P.day. 2000.00

Bahishti. 1.00 Nos: 250.00 P.day. 250.00

Black-smith 1.50 Nos: 450.00 P.day. 675.00

Bellow man. 1.50 Nos: 250.00 P.day. 375.00


Rs: 12300.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 1230.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 13530.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1353.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 14883.00
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 19525.76
Total material & labour for 100 Cft. say Rs: 19525.76

Chapter No. 5 406/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

6. Ashler fine masonary (including dressing etc:)

(a) In Lime Mortar. iii) 1 lime : 2 Sand.

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 250 Cft. 1050.00 % Cft. 2625.00

Lime Slaked (ground) 2.00 Cft. 375.00 P.Mand. 750.00

Sand. 10.00 Cft. 2425.00 % Cft. 242.50

Charcoal. 0.75 Mand 675.00 P.Mand. 506.25

Steel. 4.00 Lbs. 3550.00 P.Cwt. 126.79


TOTAL 4250.54
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 425.05
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 4675.59
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.

Masons. 20.00 Nos: 450.00 P.day. 9000.00

Coolies. 8.00 Nos: 250.00 P.day. 2000.00

Bahishti. 1.00 Nos: 250.00 P.day. 250.00

Black-smith 1.50 Nos: 450.00 P.day. 675.00

Bellow man. 1.50 Nos: 250.00 P.day. 375.00


Rs: 12300.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 1230.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 13530.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1353.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 14883.00
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 19558.59
Total material & labour for 100 Cft. say Rs: 19558.59

Chapter No. 5 407/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

6. Ashler fine masonary (including dressing etc:)

(b) In Cement Sand Mortar. i) 1 Cement : 3 Sand.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 250 Cft. 1050.00 % Cft. 2625.00

Cement. 3.00 Cwt. 400.00 P.Bag. 1200.00

Sand. 11.25 Cft. 2425.00 % Cft. 272.81

Charcoal. 0.73 Mand 675.00 P.Mand. 492.75

Steel. 4.00 Lbs. 3550.00 P.Cwt. 126.79


TOTAL 4717.35
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 471.73
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 5189.08
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.

Masons. 20.00 Nos: 450.00 P.day. 9000.00

Coolies. 8.00 Nos: 250.00 P.day. 2000.00

Bahishti. 1.00 Nos: 250.00 P.day. 250.00

Black-smith 1.50 Nos: 450.00 P.day. 675.00

Bellow man. 1.50 Nos: 250.00 P.day. 375.00


Rs: 12300.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 1230.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 13530.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1353.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 14883.00
TOTAL (MATERIAL + LABOUR) 20072.08
Total material & labour for 100 Cft. say Rs: 20072.08

Chapter No. 5 408/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

6. Ashler fine masonary (including dressing etc:)

(b) In Cement Sand Mortar. ii) 1 Cement : 4 Sand.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 250 Cft. 1050.00 % Cft. 2625.00

Cement. 2.40 Cwt. 400.00 P.Bag. 960.00

Sand. 12.00 Cft. 2425.00 % Cft. 291.00

Charcoal. 60.00 Lbs. 675.00 P.Mand. 493.90

Steel. 4.00 Lbs. 3550.00 P.Cwt. 126.79


TOTAL 4496.69
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 449.67
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 4946.36
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.

Masons. 20.00 Nos: 450.00 P.day. 9000.00

Coolies. 8.00 Nos: 250.00 P.day. 2000.00

Bahishti. 1.00 Nos: 250.00 P.day. 250.00

Black-smith 1.50 Nos: 450.00 P.day. 675.00

Bellow man. 1.50 Nos: 250.00 P.day. 375.00


Rs: 12300.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 1230.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 13530.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1353.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 14883.00
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 19829.36
Total material & labour for 100 Cft. say Rs: 19829.36
S/N D E S C R I P T I O N.

Chapter No. 5 409/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

6. Ashler fine masonary (including dressing etc:)

(b) In Cement Sand Mortar. iii) 1 Cement : 6 Sand.

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Quarried stone. 250 Cft. 1050.00 % Cft. 2625.00

Cement. 1.73 Cwt. 400.00 P.Bag. 692.00

Sand. 13.00 Cft. 2425.00 % Cft. 315.25

Charcoal. 60.00 Lbs. 675.00 P.Mand. 493.90

Steel. 4.00 Lbs. 3550.00 P.Cwt. 126.79

TOTAL 4252.94
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 425.29
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 4678.23
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
For Masonary Work.

Masons. 20.00 Nos: 450.00 P.day. 9000.00

Coolies. 8.00 Nos: 250.00 P.day. 2000.00

Bahishti. 1.00 Nos: 250.00 P.day. 250.00

Black-smith 1.50 Nos: 450.00 P.day. 675.00

Bellow man. 1.50 Nos: 250.00 P.day. 375.00


Rs: 12300.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 1230.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 13530.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1353.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 14883.00
TOTAL (MATERIAL + LABOUR) 19561.23
Total material & labour for 100 Cft. say Rs: 19561.23

S/N D E S C R I P T I O N.
SUPER STRUCTURE.

Chapter No. 5 410/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

================
(i) First Floor.
6. Ashler fine masonary (including dressing etc:)
(c) Add extra labour in item No:6 for stone work.

LABOUR. QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 0.40 Nos: 450.00 P.day. 180.00

Coolies. 1.35 Nos: 250.00 P.day. 337.50


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 517.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 51.75
_______________________________ _______ ______ _______ ______ _________
TOTAL 569.25
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 56.93
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 626.18
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 626.00
S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
(ii) Second Floor.
6. Ashler fine masonary (including dressing etc:)
(c) Add extra labour in item No:6 for stone work.

LABOUR. QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 1.20 Nos: 450.00 P.day. 540.00

Coolies. 2.60 Nos: 250.00 P.day. 650.00


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 1190.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 119.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 1309.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 130.90
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 1439.90
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 1440.00
S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================

Chapter No. 5 411/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(iii) Third Floor.


6. Ashler fine masonary (including dressing etc:)
(c) Add extra labour in item No:6 for stone work.

LABOUR. QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 2.00 Nos: 450.00 P.day. 900.00

Coolies. 3.90 Nos: 250.00 P.day. 975.00


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 1875.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 187.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 2062.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 206.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 2268.75
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 2269.00
S/N D E S C R I P T I O N.
SUPER STRUCTURE.
================
Fourth Floor and subsequent Floor.
6. Ashler fine masonary (including dressing etc:)
(c) Add extra labour in item No:6 for stone work.

LABOUR. QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 3.60 Nos: 450.00 P.day. 1620.00

Coolies. 5.60 Nos: 250.00 P.day. 1400.00


_______________________________ _______ ______ _______ ______ _________
Total. Rs: 3020.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 302.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 3322.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 332.20
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 3654.20
Total labour rate for 100 Cft. say Rs: 3654.00
_____ _______________________________ _______ ______ _______ ______ _________
S/N D E S C R I P T I O N.

7. Extra for arch work in stone masonary including centring and


decentering, etc.

Chapter No. 5 412/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Sami circular opening 15*1.5*1.5 = 33.8 Cft.
Deodar wood 3.75 Cft to be used for 60 times or 3.75/60 =0.06 Cft.
_______________________________ _______ ______ _______ ______ _________
Material for 100 Cft.
Wood = 0.06 *100/33.8 =0.18
Wood deodar 2nd class. 0.18 Cft. 4000.00 P.Cft. 710.06

Earth. L.S 147.93


= 5.0 * 100/33.8 =Rs:14.79

_______________________________ _______ ______ _______ ______ _________


TOTAL 857.99
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 85.80
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 943.79
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
Masons. 2.00 Nos: 450.00 P.day. 900.00

Coolies. 2.00 Nos: 250.00 P.day. 500.00


Rs: 1400.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 140.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 1540.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 154.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 1694.00
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 2637.79
Total material & labour for 100 Cft. say Rs: 2638.00

S/N D E S C R I P T I O N.

8. Moulding and dressing stone, etc.


(a) Extra for coping and caps.

Chapter No. 5 413/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Stone 12" and over. 30.00 Cft. 1400.00 % Cft. 420.00

Steel. 0.75 Lbs. 3550.00 P.Cwt. 23.77

Charcoal. 10 Lbs. 675.00 P.Mand. 82.32


TOTAL 526.09
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 52.61
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 578.70
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________

Masons. 10.00 Nos: 450.00 P.day. 4500.00


_______________________________ _______ ______ _______ ______ _________
Rs: 4500.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 450.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 4950.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 495.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 5445.00
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 6023.70
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 6023.70

_____ _______________________________ _______ ______ _______ ______ _________

S/N D E S C R I P T I O N.
8. Moulding and dressing stone, etc.
(b) Extra labour rate for cornice and string course.
_____ _______________________________ _______ ______ _______ ______ _________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:

Chapter No. 5 414/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ _______ ______ _______ ______ _________


Masons. 10.00 Nos: 450.00 P.day. 4500.00
_______________________________ _______ ______ _______ ______ _________
Rs: 4500.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 450.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 4950.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 495.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 5445.00
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 5445.00

Chapter No. 5 415/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ _______________________________ _______ ______ _______ ______ _________


S/N D E S C R I P T I O N.

9. STONE DRESSING.
===============
I This rate of dressing shall be paid only when the supply of
un-dressed stone is made.

II In case of masonary dressing is already included and this rate


shall not be added there to.

III Only dressed surface of stone shall be measured.

(a) Hammer dressed.


_____ _______________________________ _______ ______ _______ ______ _________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 3.00 Nos: 450.00 P.day. 1350.00
Coolies. 2.50 Nos: 250.00 P.day. 625.00
_______________________________ _______ ______ _______ ______ _________
Rs: 1975.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 197.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 2172.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 217.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 2389.75
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Sft. say Rs: 2390.00
(b) Rough Tooled dressed.
_____ _______________________________ _______ ______ _______ ______ _________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 5.00 Nos: 450.00 P.day. 2250.00
Coolies. 4.00 Nos: 250.00 P.day. 1000.00
_______________________________ _______ ______ _______ ______ _________
Rs: 3250.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 325.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 3575.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 357.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 3932.50
Total labour rate for 100 Sft. say Rs: 3932.50
_____ _______________________________ _______ ______ _______ ______ _________

Chapter No. 5 416/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(c) Chiesel dressing.


_____ _______________________________ _______ ______ _______ ______ _________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 6.00 Nos: 450.00 P.day. 2700.00
Coolies. 5.00 Nos: 250.00 P.day. 1250.00
_______________________________ _______ ______ _______ ______ _________
Rs: 3950.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 395.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 4345.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 434.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 4779.50
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Sft. say Rs: 4779.50
(d) Fine dressing.
_____ _______________________________ _______ ______ _______ ______ _________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 14.00 Nos: 450.00 P.day. 6300.00
Coolies. 5.00 Nos: 250.00 P.day. 1250.00
Black-smith. 1.00 Nos: 450.00 P.day. 450.00
_______________________________ _______ ______ _______ ______ _________
Rs: 8000.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 800.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 8800.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 880.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 9680.00
Total labour rate for 100 Sft. say Rs: 9680.00

Chapter No. 5 417/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

10. Pavement of 8" deep stone sets chiesel dressed set in lime
mortar. (1 Lime : 2 Surkhi.)

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Stone 5" to 6" thick 8" 220.0 Nos: 65.00 Each. 14300.0
deep & 12' to 15" long.

Lime Slaked (ground) 2.40 Mands 375.00 P.Mand 900.00

Surkhi. 12 Cft. 2250.00 % Cft. 270.00

Steel. 1.50 Lbs. 3550.00 P.Cwt. 47.54

Charcoal. 2.5 Lbs. 675.00 P.Mand. 20.58


TOTAL 15538.12
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1553.81
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 17091.94
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________

Masons. 4.00 Nos: 450.00 P.day. 1800.00

Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


Rs: 2925.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 292.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3217.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 321.75
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 3539.25
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 20631.19
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Sft. say Rs: 20631.19

Chapter No. 5 418/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

11. Pavement of 8" deep stone sets chiesel dressed set in lime
mortar. (1 Lime : 1 Surkhi : 1 Sand.)

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Stone 5" to 6" thick 8" 220.0 Nos: 65.00 Each. 14300.00
deep & 12' to 15" long.

Lime Slaked (ground) 2.40 Mands 375.00 P.Mand 900.00

Surkhi. 6 Cft. 2250.00 % Cft. 135.00

Sand. 6 Cft. 2425.00 % Cft. 145.50


_______________________________ _______ ______ _______ ______ _________
TOTAL 15480.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 1548.05
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 17028.55
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________

Masons. 4.00 Nos: 450.00 P.day. 1800.00

Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


Rs: 2925.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 292.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 3217.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 321.75
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 3539.25
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 20567.80
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Sft. say Rs: 20567.00

Chapter No. 5 419/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

12. Grouting stone pitching or apron in 1:3 cement mortar.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Cement. 6.0 Cwt. 400.00 P.Bag 2400.00

Sand. 22.5 Cft. 2425.00 % Cft. 545.63


TOTAL 2945.63
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 294.56
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 3240.19

_______________________________ _______ ______ _______ ______ _________

(B) LABOUR
Masons. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50


Rs: 1025.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 102.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 1127.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 112.75
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 1240.25
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 4480.44
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Sft. say Rs: 4480.00

Chapter No. 5 420/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

13. Sand grouting in stone apron with high pressure hose including
carraige of sand upto two hains.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Sand. 50 Cft. 2425.00 % Cft. 1212.50
TOTAL 1212.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 121.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 1333.75
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
Masons. 0.25 Nos: 450.00 P.day. 112.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00


Rs: 362.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 36.25
_______________________________ _______ ______ _______ ______ _________
TOTAL 398.75
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 39.88
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 438.63
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 1772.38
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Sft. say Rs: 1772.38

Chapter No. 5 421/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

14. Levelling and dressing stone filling under blocks and grouting
with shingle.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Shingle. 30 Cft. 3075.00 % Cft. 922.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 922.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 92.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 1014.75
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________

Masons. 0.25 Nos: 450.00 P.day. 112.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

_______________________________ _______ ______ _______ ______ _________


Rs: 362.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 36.25
_______________________________ _______ ______ _______ ______ _________
TOTAL 398.75
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 39.88
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 438.63
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 1453.38
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Sft. say Rs: 1453.00

Chapter No. 5 422/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15. Grouting jharies between blocks with bajri, including carraige


of bajri upto 2 chains.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Bajri. 20 Cft. 2650.00 % Cft. 530.00

TOTAL 530.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 53.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 583.00
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________

Masons. 0.25 Nos: 450.00 P.day. 112.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

_______________________________ _______ ______ _______ ______ _________


Rs: 362.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 36.25
_______________________________ _______ ______ _______ ______ _________
TOTAL 398.75
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 39.88
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 438.63
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 1021.63
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 1022.00
_____ _______________________________ _______ ______ _______ ______ _________

_____ _______________________________ _______ ______ _______ ______ _________

Chapter No. 5 423/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

16. Stone filling dry hand packed as filling behind retaining walls
or in pitching and aprons.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Stone. 135 Cft. 1400.00 % Cft. 1890.00

_______________________________ _______ ______ _______ ______ _________


TOTAL 1890.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 189.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 2079.00
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________

Coolies (Skilled) 1.00 Nos: 250.00 P.day. 250.00

Coolies. 1.00 Nos: 250.00 P.day. 250.00


Rs: 500.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 50.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 550.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 55.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 605.00
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 2684.00
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 2684.00

Chapter No. 5 424/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

17. Grouting stone filling or pitching with bajri including carraige


of bajri with in 2 chains.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Bajri. 30 Cft. 2650.00 % Cft. 795.00

_______________________________ _______ ______ _______ ______ _________


TOTAL 795.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 79.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 874.50
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________

Coolies (Skilled) 1.25 Nos: 250.00 P.day. 312.50

_______________________________ _______ ______ _______ ______ _________


Rs: 312.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 31.25
_______________________________ _______ ______ _______ ______ _________
TOTAL 343.75
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 34.38
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 378.13
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 1252.63
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 1253.00

Chapter No. 5 425/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

18. Breaking stone ballast screened and stacked.


(a) 2" ring.
_____ _______________________________ _______ ______ _______ ______ _________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Coolies. 3.50 Nos: 250.00 P.day. 875.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 87.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 962.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 96.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 1058.75
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 1059.00
_____ _______________________________ _______ ______ _______ ______ _________
(b) 1-1/2" ring.
_____ _______________________________ _______ ______ _______ ______ _________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Coolies. 4.00 Nos: 250.00 P.day. 1000.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 100.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 1100.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 110.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 1210.00
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 1210.00
(c) 1" ring.
_____ _______________________________ _______ ______ _______ ______ _________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Coolies. 4.50 Nos: 250.00 P.day. 1125.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 112.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 1237.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 123.75
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 1361.25
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 1361.00
(d) 1/2" ring.

Chapter No. 5 426/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ _______________________________ _______ ______ _______ ______ _________


(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Coolies. 6.00 Nos: 250.00 P.day. 1500.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 150.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 1650.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 165.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 1815.00
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 1815.00
_____ _______________________________ _______ ______ _______ ______ _________
(e) 3/8" to 1/4" ring.
_____ _______________________________ _______ ______ _______ ______ _________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Coolies. 10.00 Nos: 250.00 P.day. 2500.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 250.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 2750.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 275.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 3025.00
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 3025.00
_____ _______________________________ _______ ______ _______ ______ _________
19. Breaking stone into spawls and stacking.

LABOUR QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Coolies. 1.50 Nos: 250.00 P.day. 375.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 37.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 412.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 41.25
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 453.75
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 454.00
20. Screening and stacking stone ballast, shingle or bajri, etc.

Chapter No. 5 427/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

LABOUR QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Coolies. 1.00 Nos: 250.00 P.day. 250.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 25.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 275.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 27.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 302.50
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 302.50
_____ _______________________________ _______ ______ _______ ______ _________
21. Washing ballast, shingle or bajri, etc.

_______________________________ _______ ______ _______ ______ _________


LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Coolies. 1.00 Nos: 250.00 P.day. 250.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 25.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 275.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 27.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 302.50
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 302.50
_____ _______________________________ _______ ______ _______ ______ _________
22. Crushing stone ballast by machine.

_______________________________ _______ ______ _______ ______ _________


LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Coolies. 3.00 Nos: 250.00 P.day. 750.00
Sundries. 10.00 % 75.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 825.00
Contractor's profit 10.00 % 82.50
Total labour rate for 100 Cft. say Rs: 907.50
_____ _______________________________ _______ ______ _______ ______ _________

Chapter No. 5 428/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Note This rate does not includes the charges for working of crushers,
but includes menual labour for carriage of stone with in 3
chains and also stacking the product after crushing within 3
chains.
S/N D E S C R I P T I O N.

23. Stone pitching including sub-base with hammer dressed stones on


surface, laid in courses, including carraige of materials within
3 chains.
_____ _______________________________ _______ ______ _______ ______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Pitching Stone. 120 Cft. 2000.00 % Cft. 2400.00
TOTAL 2400.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 240.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 2640.00
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
Masons. 2.25 Nos: 450.00 P.day. 1012.50

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

_______________________________ _______ ______ _______ ______ _________


Rs: 2262.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 226.25
_______________________________ _______ ______ _______ ______ _________
TOTAL 2488.75
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 248.88
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 2737.63
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 5377.63
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 5378.00

Chapter No. 5 429/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

24. Stone pitching hand packed with surface levelled off to correct
section with hammer dressed stone and voids filled in 1:8 cement
mortar in floors of bridges and along banks and in aprons, etc,
including three chains lead.

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Pitching Stone. 120 Cft. 2000.00 % Cft. 2400.00

Cemet. 2.70 Cwt. 400.00 P.Bag 1080.00

Sand. 26.4 Cft. 2425.00 % Cft. 640.20


TOTAL 4120.20
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 412.02
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 4532.22
_______________________________ _______ ______ _______ ______ _________
(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Coolies. (Skilled) 6.00 Nos: 250.00 P.day. 1500.00

_______________________________ _______ ______ _______ ______ _________


Rs: 2625.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 262.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 2887.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 288.75
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 3176.25
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 7708.47
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 100 Cft. say Rs: 7708.00

_____ _______________________________ _______ ______ _______ ______ _________

_____ _______________________________ _______ ______ _______ ______ _________

Chapter No. 5 430/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

25. Dismantling stone pitching top layer and re-laying it after


making good damaged slopes.
_____ _______________________________ _______ ______ _______ ______ _________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
(a) For Dismantling.
Coolies. 1.50 Nos: 250.00 P.day. 375.00
(b) For Re-pitching.
Mason. 2.00 Nos: 450.00 P.day. 900.00
Coolies. 3.00 Nos: 250.00 P.day. 750.00
_______________________________ _______ ______ _______ ______ _________
Rs: 2025.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 202.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 2227.50
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 222.75
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 2450.25
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 2450.00
_____ _______________________________ _______ ______ _______ ______ _________
S/N D E S C R I P T I O N.

26. Collecting and stacking boulders from nallah beds or loose shale
from any other site, within three chains.

_____ _______________________________ _______ ______ _______ ______ _________


(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Coolies. 2.00 Nos: 250.00 P.day. 500.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 50.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 550.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 55.00
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 605.00
Total labour rate for 100 Cft. say Rs: 605.00

Chapter No. 5 431/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

27. Stone pitching for top layer only 1.3' to 1.5' thick.
(a) On Slope.
_____ _______________________________ _______ ______ _______ ______ _________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 2.00 Nos: 450.00 P.day. 900.00
Coolies. 5.00 Nos: 250.00 P.day. 1250.00

_______________________________ _______ ______ _______ ______ _________


Rs: 2150.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 215.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 2365.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 236.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 2601.50
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 2601.50
_____ _______________________________ _______ ______ _______ ______ _________
S/N D E S C R I P T I O N.

27. Stone pitching for top layer only 1.3' to 1.5' thick.
(b) In bed.
_____ _______________________________ _______ ______ _______ ______ _________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 2.00 Nos: 450.00 P.day. 900.00
Coolies. 3.00 Nos: 250.00 P.day. 750.00
_______________________________ _______ ______ _______ ______ _________
Total 1650.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 165.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 1815.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 181.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 1996.50
Total labour rate for 100 Cft. say Rs: 1996.50

Chapter No. 5 432/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

28. Laying stone or spawl filling.


(a) On Level.
_____ _______________________________ _______ ______ _______ ______ _________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 0.25 Nos: 450.00 P.day. 112.50
Coolies. 1.00 Nos: 250.00 P.day. 250.00

_______________________________ _______ ______ _______ ______ _________


Rs: 362.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 36.25
_______________________________ _______ ______ _______ ______ _________
TOTAL 398.75
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 39.88
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 438.63
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 438.63
_____ _______________________________ _______ ______ _______ ______ _________
S/N D E S C R I P T I O N.
28. Laying stone or spawl filling.
(b) On Slopes.
_____ _______________________________ _______ ______ _______ ______ _________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Masons. 0.48 Nos: 450.00 P.day. 216.00
Coolies. 1.00 Nos: 250.00 P.day. 250.00
_______________________________ _______ ______ _______ ______ _________
Total 466.00
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 46.60
_______________________________ _______ ______ _______ ______ _________
TOTAL 512.60
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 51.26
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 563.86
_______________________________ _______ ______ _______ ______ _________
Total labour rate for 100 Cft. say Rs: 564.00

Chapter No. 5 433/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
29. Dhajji walling 5"*5" thick deodar framing with stone laid in 1:6
cement plaster on both sides.
_____ _______________________________ _______ ______ _______ ______ _________
Taking wall of 18' long and 13' high = 18 * 13 = 234 Sft.
(A) Detail of Wood.
(i) Top bottom breasmer= 2 * (18' * 5' * 5')/(12 * 12) = 6.25 Cft.
(ii) Vertical posts @ 4' apart =6 * 13' * 5'/12 * 5'/12 = 13.55 Cft.
(iii) Horizontal pieces = 3 * 18' * 5'/12 * 1'/4 = 5.62 Cft.
(iv) Diagonal Struts. = 20 * 6 * 5'/12 * 1'/8 = 6.25 Cft.
Total = 31.67 Cft.
Add for wastage = 20% = = 6.34 Cft.
Total quantity of wood required for 234 Sft = 38.00 Cft.
Total quantity of wood required for 100 Sft = 16.00 Cft.
(B) Stone quarried. = 1 * 18' * 13' * 5'/12 = 98.00 Cft.
Deduct scantling. ( - ) = 32.00 Cft.
Net quantity of quarried stone = 66.00 Cft.
_______________________________ _______ ______ _______ ______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Wood deodar 2nd class. 38.00 Cft. 4000.00 P.Cft. 152000.0
Spikes 3/4" 30.00 Nos: 25.00 P.doz. 62.50
Wire nails 4" 5.00 Chtk: 110.00 P.Seer 34.38
Wood preservative. 0.75 Lbs. 1450.00 P.Gallon 241.67
Stone quarried. 112 Cft. 1050.00 % Cft. 1176.00
Cement for 1:6 ratio for 3.00 Cwt. 400.00 P.Bag 1200.00
laying.
Cement for 1:4 ratio for 3.40 Cwt. 400.00 P.Bag 1360.00
plastering.
Sand. 40 Cft. 2425.00 % Cft. 970.00
Steel. 3 Lbs. 3550 P.Cwt. 95.09
Charcoal. 0.50 Mand. 675.00 P.Mand 337.50
_______________________________ _______ ______ _______ ______ _________
TOTAL 157477.13
Contractor's profit 10.00 % 15747.71
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 173224.8
_______________________________ _______ ______ _______ ______ _________

Chapter No. 5 434/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
Carpanter for wood work. 2.00 Nos: 450.00 P.day. 900.00
Coolies. 2.00 Nos: 250.00 P.day. 500.00
Mason for dressing of stone 3.00 Nos: 450.00 P.day. 1350.00
and laying.
Coolies for laying. 3.00 Nos: 250.00 P.day. 750.00
Mason for plastering. 3.00 Nos: 450.00 P.day. 1350.00
Coolies for plastering. 3.00 Nos: 250.00 P.day. 750.00
Black-smith 0.50 Nos: 450.00 P.day. 225.00
Bellow man. 0.50 Nos: 250.00 P.day. 125.00
_______________________________ _______ ______ _______ ______ _________
TOTAL Rs: 5950.00
Sundries. 10.00 % 595.00
_______________________________ _______ ______ _______ ______ _________
TOTAL 6545.00
Contractor's profit 10.00 % 654.50
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 7199.50
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 234 Sft. Rs: 180424.3
Total material & labour for 100 Sft. Rs: 77104.4205
Total material & labour for 100 Sft. Say Rs: 77104.42

S/N D E S C R I P T I O N.

30. Fixing stone blocks from 2 Cft to 6 Cft. each including lift
upto 20 ft:
_____ _______________________________ _______ ______ _______ ______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Labour & material for 4 Cft.

Mortar. L.S 25.60


TOTAL 25.60
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 2.56
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 28.16
_______________________________ _______ ______ _______ ______ _________

Chapter No. 5 435/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
Masons. 0.25 Nos: 450.00 P.day. 112.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.12 Nos: 250.00 P.day. 30.00


Rs: 392.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 39.25
_______________________________ _______ ______ _______ ______ _________
TOTAL 431.75
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 43.18
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 118.73 474.93
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 503.09
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 4 Cft. Rs: 503.09
Total material & labour for 1 Cft. Rs: 125.77
Total material & labour for 1 Cft. Say Rs: 126.00
S/N D E S C R I P T I O N.

31. Fixing stone blocks under 2 Cft. each including lift upto 20 ft:

_____ _______________________________ _______ ______ _______ ______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ _______ ______ _______ ______ _________
Labour & material for 1 Cft.

Mortar. L.S 7.00


TOTAL 7.00
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 0.70
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " A " 7.70
_______________________________ _______ ______ _______ ______ _________

Chapter No. 5 436/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(B) LABOUR
_______________________________ _______ ______ _______ ______ _________
Masons. 0.05 Nos: 450.00 P.day. 22.50

Coolies. 0.25 Nos: 250.00 P.day. 62.50

Bahishti. 0.03 Nos: 250.00 P.day. 7.50

_______________________________ _______ ______ _______ ______ _________


Rs: 92.50
_______________________________ _______ ______ _______ ______ _________
Sundries. 10.00 % 9.25
_______________________________ _______ ______ _______ ______ _________
TOTAL 101.75
_______________________________ _______ ______ _______ ______ _________
Contractor's profit 10.00 % 10.18
_______________________________ _______ ______ _______ ______ _________
TOTAL PART " B " 111.93
_______________________________ _______ ______ _______ ______ _________
TOTAL (MATERIAL + LABOUR) 119.63
_______________________________ _______ ______ _______ ______ _________
Total material & labour for 1 Cft. Say Rs: 120.00
_____ _______________________________ _______ ______ _______ ______ _________

Chapter No. 5 437/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
FIRST FILL THIS SHEET.
ROOFING
MATERIAL. RATE UNITE.

1 Tiles 12"x 6" x 1- 1/2" (first class) 8500 % 0 Nos.

2 Cement 400 P.Bag

3 Sand 2425 % Cft.

4 Earth 500 % Cft.

5 Bhoosa 300 P.Mand

6 Cow dung 500 % Cft.

7 Bitumen, Coaltar 86213 Ton

8 Fuel wood 900 P.Mand

9 Tiles (2nd class) 12" x 6" x2" 5825 % 0 Nos.

10 Deodar wood (2nd quality) 4000 P. Cft

11 Wire Vails 110 P.Kg

12 Bajri 2650 % Cft.

13 Bricks ordinary 5000 % 0 Nos

14 Clay Tiles 9" x 4" x 2" 5400 % 0 Nos

15 Bamboos 2" dia 11 Ft. Long 160 Each

16 Matting Sarkanda 400 % Sft

17 Sirki 275 % Sft

18 Stone aggregate 825 % Cft.

19 Shingle 3075 % Cft

20 Bamboos 1-1/4" dia 11' Long. 125 Each

21 Thatching Sarkanda 475 % Cft

22 6" to 12 thick grass thatching two 300 % Cft.


Layers 3" thick.

23 Palm Matting (Chatter) 675 % Sft.

24 Sheets of 20-22 gauge 5000 P.Cwt

25 Wind Tie (rod) 4750 P.Cwt

Chapter No. 6 438/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
26 Limpet Washers 115 P.doz

27 G.I Bold & Nuts 225 P.doz

28 G.I Hooks, Bold & Nuts. 200 P.doz

29 Bitumen Washers. 41 P.doz

30 Char Coal 675 P.Mand.

31 G.I Sheets 4450 P.Cwt.

32 C.I Pipes 4" dia. 300 P.Rft.

33 Hold Fast 210 Each

34 C.I Shoe bend or Off Sets 385 Each

35 Deodar wood (1st quality) 4500 P.Cft

36 Screw of Sorts 315 P.gross

37 Nails of Sorts 110 P.Kg

38 Rolls 5" wide 16.0' Longe 3375 P.Cwt

39 Corrugated A.C Sheet. 6750 % Sft.

40 A.C Ridge Sheet 160 P.Rft.

41 Wrought Iron bracket 65 Each

42 Iron strap 1/8" 1800 P.Cwt

43 Polythene Sheet 9 P.Sft

44 Tile 12" x 8" x 1" (Khaprial) 3450 % Nos

45 Tile 15" x 8" x 1- 1/2" 3250 % Nos.

46 Bamboos 1-1/2" dia 10' Long. 160 each

47 Bitumen felt paper 60 lbs 22 psft

48 Kerosine oil 110 litre

49 thermo sheet 50 p sft

50 Aluminum T section 8.5 prft

51 steel 3550 pcwt

52 Plaster of paris 85 psft

53 solignum paint 1525 p gall

54 Jute felt paper 65 Sft

Chapter No. 6 439/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

LABOUR RATE UNITE.

1 Masson (G-I ) , Carpentar (G-I) 450 P.day


Black Smith.

2 Coolies 250 P.day

3 Bahishti , Cooly Skilled 250 P.day

4 Painter (G-II) , Pipe Fitter. 400 P.day

R O O F I N G.
==============
I Rates for all finished works include the removal of the surplus
debris un-used material and by-products.
II For handling of all types of materials for short leads including
carriage upto 3 chains nothing is to be paid extra where
handling and carriage involves an extra lead beyond 3 chains
carriage for whole of the distance should be paid.
III The rates include the cost of scaffolding and its removal.
IV Add extra 13% , 32% and 51% on labour rates only or 6%, 15% and
23% on composite rates. for 2nd, 3rd, fourth and subsequent
floors respectively. floor

Chapter No. 6 440/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
1. First class tile roofing consisting of 4" earth and 1" mud
plaster with gobri leeping over 1/2" thick cement plaster 1:6
with 34 lbs of hot bitumen coating sand blinded provided over
two laers of tiles 12" * 6" * 1-1/4" laid in 1:6 cement mortar
with 1/2" thick sand-wiched layer of 1:6 mortar including 1:2
cement pointing under side of tiles, complete including curing.
(Unit of rate per 100 Sft.)
____________________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Tiles 12" * 6" * 1-1/2" 400 Nos: 8500.0 %0 Nos: 3400.00
Cement for laying. 0.26 Cwt. 400.00 P.Bag 104.00
Cement for pointing 1:2. 0.17 Cwt. 400.00 P.Bag 68.00
Cement for plastering b/w 1.10 Cwt. 400.00 P.Bag 440.00
ansd over tiles 1:6.
Cement for plastering 0.23 Cwt. 400.00 P.Bag 92.00
along parapet.
Sand for laying. In 1:6 mortar 1.96 Cft. 2425.00 % Cft. 47.53
Sand for pointing 1:2. 0.41 Cft. 2425.00 % Cft. 9.94
Sand for plaster 1:6 8.28 Cft. 2425.00 % Cft. 200.79
Sand for plaster along 1.71 Cft. 2425.00 % Cft. 41.47
parapet 1:6.
Sand for blindg: of bitumen. 1.00 Cft. 2425.00 % Cft. 24.25
Earth upto 100'lead& 5'Lift
Earth for 1" mud plaster. 10.00 Cft. 500.00 % Cft. 50.00
Earth for 4" filling over. 33.00 Cft. 500.00 % Cft. 165.00
Bhoosa for top layer. 17.00 Seer. 500.00 P.Mand 212.50
Clay for gobri leeping. 0.75 Cft. 500.00 % Cft. 3.75
Cow dung for gobri leeping. 0.75 Cft. 300.00 % Cft. 2.25
Two coats of bitumen. 34.00 Lbs. 86213.00 Ton. 1308.59
Fuel wood. 0.20 Mand 900.00 P.Mand 180.00
____________________________ ________ ______ ________ ______ __________
TOTAL 6350.07
Contractor's profit 10.00 % 635.01
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 6985.08
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Mason for laying tiles. 1.50 Nos: 450.00 P.day. 675.00
Mason for pointing. 0.75 Nos: 450.00 P.day. 337.50
Mason for cement plaster. 1.00 Nos: 450.00 P.day. 450.00
Mason for mud plaster. 0.40 Nos: 450.00 P.day. 180.00
Coolies. 6.00 Nos: 250.00 P.day. 1500.00
Bahishti. 1.25 Nos: 250.00 P.day. 312.50
____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 3455.00
Sundries. 10.00 % 345.50
____________________________ ________ ______ ________ ______ __________
TOTAL 3800.50
Contractor's profit 10.00 % 380.05
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 4180.55
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 11165.63
____________________________ ________ ______ ________ ______ __________

Chapter No. 6 441/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
Total material & labour for 100 Sft. say Rs: 11165.63
S/N D E S C R I P T I O N.
2. Secod class tile roofing consisting of 4" earth and 1" mud
plaster with gobri leeping over 1/2" thick cement plaster 1:6
with 34 lbs of hot bitumen coating sand blinded provided over
one layer of tiles 12" * 6" * 2" size laid in 1:6 cement mortar
including 1:2 cement pointing under neath of tiles, complete
including curing etc.
(Unit of rate per 100 Sft.)
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Tiles 12" * 6" * 2" 200 Nos: 5825.0 %0 Nos: 1165.00
Cement for laying. 0.23 Cwt. 400.00 P.Bag 92.00
Cement for pointing 1:2. 0.17 Cwt. 400.00 P.Bag 68.00
Cement for plastering. 0.55 Cwt. 400.00 P.Bag 220.00
Cement for plastering 0.23 Cwt. 400.00 P.Bag 92.00
along parapet.
Sand for laying. 1.60 Cft. 2425.00 % Cft. 38.80
Sand for pointing 1:2. 0.43 Cft. 2425.00 % Cft. 10.43
Sand for plaster 1:6 4.14 Cft. 2425.00 % Cft. 100.40
Sand for plaster along 1.71 Cft. 2425.00 % Cft. 41.47
parapet 1:6.
Sand for blindg: of bitumen. 1.00 Cft. 2425.00 % Cft. 24.25
Earth upto 100'lead& 5'Lift
Earth for 1" mud plaster. 10.00 Cft. 500.00 % Cft. 50.00
Earth for 4" filling over. 33.00 Cft. 500.00 % Cft. 165.00
Bhoosa for top layer. 17.00 Seer. 500.00 P.Mand 212.50
Clay for gobri leeping. 0.75 Cft. 500.00 % Cft. 3.75
Cow dung for gobri leeping. 0.75 Cft. 500.00 % Cft. 3.75
Two coats of bitumen. 34.00 Lbs. 86213.00 Ton. 1308.59
Fuel wood. 0.20 Mand 900.00 P.Mand 180.00
____________________________ ________ ______ ________ ______ __________
TOTAL 3775.93
Contractor's profit 10.00 % 377.59
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 4153.52
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Mason for laying tiles. 2.50 Nos: 450.00 P.day. 1125.00
Coolies. 5.00 Nos: 250.00 P.day. 1250.00
Bahishti. 1.00 Nos: 250.00 P.day. 250.00
____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 2625.00
Sundries. 10.00 % 262.50
____________________________ ________ ______ ________ ______ __________
TOTAL 2887.50
Contractor's profit 10.00 % 288.75
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 3176.25
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 7329.77
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 7329.77

Chapter No. 6 442/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

3. Covering Mud roof with coal tar and fine sand.

(Unit of rate per 100 Sft.)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________

Coaltar. 34.00 Lbs. 86213.0 P.Ton. 1308.59

Fine sand. 1.00 Cft. 2425.00 % Cft. 24.25

Charcoal for heating L.S 40.00


coaltar i/c brushes.

____________________________ ________ ______ ________ ______ __________


TOTAL 1372.84
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 137.28
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 1510.12
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Mason for laying tiles. 0.12 Nos: 450.00 P.day. 54.00

Coolies. 0.25 Nos: 250.00 P.day. 62.50

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 116.50
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 11.65
____________________________ ________ ______ ________ ______ __________
TOTAL 128.15
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 12.82
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 140.97
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 1651.09
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 1651.09

Chapter No. 6 443/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

4. Filling spaces in between:


(a) Wooden battens over beams filled with deodar wood pieces(spacers)
(Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Deodar Wood 2 * 10 *
(9-1/4" *1"* 5")=0.54 Cft. 0.54 Cft. 4000.0 P.Cft. 2160.00
Wastage 20% = 0.10 Cft. 0.10 Cft. 750.00 P.Cft. 75.00

Wire Nails. 40.00 gm 110.00 P.Kg 4.40

TOTAL 2239.40
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 223.94
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 2463.34
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Carpentars for making 0.50 Nos: 450.00 P.day. 225.00
grooves in battens and
fixing of wooden strips.

Cooly. 0.50 Nos: 250.00 P.day. 125.00

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 350.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 35.00
____________________________ ________ ______ ________ ______ __________
TOTAL 385.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 38.50
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 423.50
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 2886.84
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 2886.84
______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 444/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4. Filling spaces in between:


(b) R.C.C. battens filled with R.C.C. blocks (1:3:6)
(Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
9" * 3/4" * 2/3" * 5'/12 = = 1.875 Cft.
2" * 1/2" * 2"/3 * 5'/12 = = 0.278 Cft.
Total = 2.153 Cft.
____________________________ ________ ______ ________ ______ __________
Cement for blocks. 0.27 CWt. 400.00 P.Bag 108.00
Cement for laying. 0.17 CWt. 400.00 P.Bag 68.00
Sand for blocks. 1.02 Cft. 2425.00 % Cft. 24.74
Sand for laying. 0.65 Cft. 2425.00 % Cft. 15.76
Bajri. 2.04 Cft. 2650.00 % Cft. 54.06
____________________________ ________ ______ ________ ______ __________
TOTAL 270.56
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 27.06
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 297.61
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Masons. 0.50 Nos: 450.00 P.day. 225.00

Cooly. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.13 Nos: 250.00 P.day. 31.25

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 506.25
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 50.63
____________________________ ________ ______ ________ ______ __________
TOTAL 556.88
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 55.69
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 612.56
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 910.18
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 910.18

Chapter No. 6 445/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4. Filling spaces in between:


(c) Space filled with bricks.
(Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Bricks i/c wastage (30+15) 45.00 Nos: 5000.0 %0 Nos: 225.00

Cement. 0.20 CWt. 400.0 P.Bag 80.00

Sand. 0.75 Cft. 2425.00 % Cft. 18.19

TOTAL 323.19
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 32.32
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 355.51
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Masons. 0.17 Nos: 450.00 P.day. 76.50

Cooly. 0.17 Nos: 250.00 P.day. 42.50

Bahishti. 0.10 Nos: 250.00 P.day. 25.00

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 144.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 14.40
____________________________ ________ ______ ________ ______ __________
TOTAL 158.40
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 15.84
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 174.24
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 529.75
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 529.75
______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 446/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
5. Single layer of tiles 9"*4"-1/2*2" laid over 4" earth and 1" mud
plaster without bhoosa, grouted with cement sand 1:3 on top of
R.C.C roof slab provided with 34 lbs of bitumen coating sand
blinded.
(Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Clay Tiles 9"*4"-1/2*2" 350.0 Nos: 5400.0 %0 Nos: 1890.00
Sand for grouting. 2.00 Cft. 2425.00 % Cft. 48.50
Sand for blinding. 1.00 Cft. 2425.00 % Cft. 24.25
Cement. 0.50 CWt. 400.0 P.Bag 200.00
Good Earth lead upto 100 ft: 43.00 Cft. 500.00 % Cft. 215.00
and lift upto 20 ft:
Two coats of bitumen. 34.00 Lbs. 86213.00 P.Ton 1308.59
TOTAL 3686.34
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 368.63
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 4054.97
____________________________ ________ ______ ________ ______ __________
(B) LABOUR Masons for mud plastering.
____________________________ ________ ______ ________ ______ __________
Masons for plastering. 0.125 Nos: 450.00 P.day. 56.25
Masons for laying. 0.50 Nos: 450.00 P.day. 225.00
Masons for grouting. 0.125 Nos: 450.00 P.day. 56.25
Cooly for mud plastering. 0.50 Nos: 250.00 P.day. 125.00
Cooly for Laying. 0.75 Nos: 250.00 P.day. 187.50
Cooly for grouting. 0.25 Nos: 250.00 P.day. 62.50
Painter for bitumen 0.50 Nos: 400.00 P.day. 200.00
painting. (II Class)
Bahishti. 0.50 Nos: 250.00 P.day. 125.00
____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 1037.50
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 103.75
____________________________ ________ ______ ________ ______ __________
TOTAL 1141.25
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 114.13
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 1255.38
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 5310.35
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 5310.35
______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 447/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
6. 3rd class mud roof consisting of 4" mud plaster over one layer
of sarkanda matting and one layer of sirki.

(Unit of rate per 100 Sft.)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Bamboos 2" dia 11 ft long. 11.0 Nos: 160.0 Each. 1760.00
Matting sarkanda. 100.0 Sft. 400.00 % Sft. 400.00
Sirki. 100.0 Sft. 275.00 % Sft. 275.00
Earth. 43.00 Cft. 500.00 % Cft. 215.00
Bhoosa. 17.00 Seer. 300.00 P.Mand 127.50

____________________________ ________ ______ ________ ______ __________


TOTAL 2777.50
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 277.75
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 3055.25
____________________________ ________ ______ ________ ______ __________
(B) LABOUR Masons for mud plastering.
____________________________ ________ ______ ________ ______ __________
Masons for plastering. 0.330 Nos: 450.00 P.day. 148.50

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Bahishti. 0.10 Nos: 250.00 P.day. 25.00


____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 548.50
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 54.85
____________________________ ________ ______ ________ ______ __________
TOTAL 603.35
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 60.34
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 663.69
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 3718.94
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 3718.94

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 448/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
7. Jack arch roofing 4-1/2" thick laid in 1:5 cement mortar
including an average depth of 4 inches thick cement concrete in
haunches and over crown with 3" earth and 1' mud plaster soffits
of arches cement plastered 1:6 and 1/2" thick. The rate also
includes bitumen coating centering, laying skew bricks in cement
sand mortar (1:3) and encasing exposed flanges of the joists
with fine cement concrete (1:2:4). Using stone aggregate:-
(a) Cement concrete in haunches 1:6:12
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Bricks 9"*4'-1/2*3" 550.0 Nos: 5000.0 %0 Nos: 2750.00
Cement for laying. 1.6 Cwt. 400.00 P.Bag 640.00
Cement for plaster haunches. 0.57 Cwt. 400.00 P.Bag 228.00
Cement for concrete in 2.00 Cwt. 400.00 P.Bag 800.00
haunches.
Cement for concrete in 0.60 Cwt. 400.00 P.Bag 240.00
flanges.
Sand for laying. 10.00 Cft. 2425.00 % Cft. 242.50
Sand for plaster Haunches. 4.26 Cft. 2425.00 % Cft. 103.31
Sand for concrete in 16.20 Cft. 2425.00 % Cft. 392.85
haunches.
Sand for concrete in 1.50 Cft. 2425.00 % Cft. 36.38
flanges.
Stone aggregates for 32.00 Cft. 825.00 % Cft. 264.00
concrete in haunches.
Stone aggregates for 3.00 Cft. 825.00 % Cft. 24.75
concrete in flanges.
Earth for filling & plaster 33.00 Cft. 500.00 % Cft. 165.00
Bhoosa. 17.00 Seer. 300.00 P.Mand 127.50
Fine clay. 0.75 Cft. 500.00 % Cft. 3.75
Cow dung. 0.75 Cft. 500.00 % Cft. 3.75
Bitumen. 34.00 Lbs. 86213.00 P.ton 1308.59
Fuel. 0.20 Mand. 900.00 P.Mand 180.00
Centering. L.S 256.00
TOTAL 7766.37
Contractor's profit 10.00 % 776.64
TOTAL PART " A " 8543.01
(B) LABOUR
Masons. 3.500 Nos: 450.00 P.day. 1575.00
Carpenter. 0.500 Nos: 450.00 P.day. 225.00
Coolies. 7.00 Nos: 250.00 P.day. 1750.00
Bahishti. 1.00 Nos: 250.00 P.day. 250.00
TOTAL Rs: 3800.00
Sundries. 10.00 % 380.00
TOTAL 4180.00
Contractor's profit 10.00 % 418.00
TOTAL PART " B " 4598.00
TOTAL (MATERIAL + LABOUR) 13141.01
Total material & labour for 100 Sft. say Rs: 13141.01

Chapter No. 6 449/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
7. Jack arch roofing 4-1/2" thick laid in 1:5 cement mortar
including an average depth of 4 inches thick cement concrete in
haunches and over crown with 3" earth and 1' mud plaster soffits
of arches cement plastered 1:6 and 1/2" thick. The rate also
includes bitumen coating centering, laying skew bricks in cement
sand mortar (1:3) and encasing exposed flanges of the joists
with fine cement concrete (1:2:4). Using stone aggregate:-
(b) Cement concrete in haunches 1:3:6
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Bricks 9"*4'-1/2*3" 550.0 Nos: 5000.0 %0 Nos: 2750.00
Cement for laying. 1.60 Cwt. 400.00 P.Bag 640.00
Cement for plaster haunches. 0.57 Cwt. 400.00 P.Bag 228.00
Cement for concrete in 4.10 Cwt. 400.00 P.Bag 1640.00
haunches.
Cement for concrete in 0.60 Cwt. 400.00 P.Bag 240.00
flanges.
Sand for laying. 10.00 Cft. 2425.00 % Cft. 242.50
Sand for plaster Haunches. 4.26 Cft. 2425.00 % Cft. 103.31
Sand for concrete in 15.40 Cft. 2425.00 % Cft. 373.45
haunches.
Sand for concrete in 1.50 Cft. 2425.00 % Cft. 36.38
flanges.
Stone aggregates for 31.00 Cft. 825.00 % Cft. 255.75
concrete in haunches.
Stone aggregates for 3.00 Cft. 825.00 % Cft. 24.75
concrete in flanges.
Earth for filling & plaster 33.00 Cft. 500.00 % Cft. 165.00
Bhoosa. 17.00 Seer. 300.00 P.Mand 127.50
Fine clay. 0.75 Cft. 500.00 % Cft. 3.75
Cow dung. 0.75 Cft. 500.00 % Cft. 3.75
Bitumen. 34.00 Lbs. 86213.00 P.Ton 1308.59
Fuel. 0.20 Mand. 900.00 P.Mand 180.00
Centering. L.S 256.00
TOTAL 8578.72
Contractor's profit 10.00 % 857.87
TOTAL PART " A " 9436.59
(B) LABOUR
Masons. 3.500 Nos: 450.00 P.day. 1575.00
Carpenter. 0.500 Nos: 450.00 P.day. 225.00
Coolies. 7.00 Nos: 250.00 P.day. 1750.00
Bahishti. 1.00 Nos: 250.00 P.day. 250.00
TOTAL Rs: 3800.00
Sundries. 10.00 % 380.00
TOTAL 4180.00
Contractor's profit 10.00 % 418.00
TOTAL PART " B " 4598.00
TOTAL (MATERIAL + LABOUR) 14034.59
Total material & labour for 100 Sft. say Rs: 14034.59

Chapter No. 6 450/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
8. Jack arch roofing 4-1/2" thick laid in 1:5 cement mortar
including an average depth of 4 inches thick cement concrete in
haunches and over crown with 1/2" cement plaster on top (except
earth filling and mud plaster and gobri) soffits of arches
cement plastered 1:6 and 1/2" thick. The rate also includes
bitumen coating centering, laying skew bricks in cement sand
mortar (1:3) and encasing exposed flanges of the joists with
fine cement concrete (1:2:4). Using stone aggregate:-
(a) Cement concrete in haunches 1:6:12
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Bricks 9"*4'-1/2*3" 550.0 Nos: 5000.0 %0 Nos: 2750.00
Cement for laying. 1.60 Cwt. 400.00 P.Bag 640.00
Cement for plastering top. 0.51 Cwt. 400.00 P.Bag 204.00
Cement for conc: in soffits 0.57 Cwt. 400.00 P.Bag 228.00
Cement for concrete in 2.00 Cwt. 400.00 P.Bag 800.00
haunches.
Cement for concrete in 0.60 Cwt. 400.00 P.Bag 240.00
flanges.
Sand for laying. 10.00 Cft. 2425.00 % Cft. 242.50
Sand for plaster top. 3.84 Cft. 2425.00 % Cft. 93.12
Sand for plaster soffits. 4.26 Cft. 2425.00 % Cft. 103.31
Sand for concrete in 16.20 Cft. 2425.00 % Cft. 392.85
haunches.
Sand for concrete in 1.50 Cft. 2425.00 % Cft. 36.38
flanges.
Stone aggregates for 32.00 Cft. 825.00 % Cft. 264.00
concrete in haunches.
Stone aggregates for 3.00 Cft. 825.00 % Cft. 24.75
concrete in flanges.
Bitumen. 34.00 Lbs. 86213.00 P.Ton 1308.59
Fuel. 0.20 Mand. 900.00 P.Mand 180.00
Deodar wood for centering. L.S 256.00
TOTAL 7763.49
Contractor's profit 10.00 % 776.35
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 8539.84
(B) LABOUR
Masons. 2.750 Nos: 450.00 P.day. 1237.50
Carpenter. 0.500 Nos: 450.00 P.day. 225.00
Coolies. 5.50 Nos: 250.00 P.day. 1375.00
Bahishti. 1.00 Nos: 250.00 P.day. 250.00
TOTAL Rs: 3087.50
Sundries. 10.00 % 308.75
TOTAL 3396.25
Contractor's profit 10.00 % 339.63
TOTAL PART " B " 3735.88
TOTAL (MATERIAL + LABOUR) 12275.71
Total material & labour for 100 Sft. say Rs: 12275.71
______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 451/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
8. Jack arch roofing 4-1/2" thick laid in 1:5 cement mortar
including an average depth of 4 inches thick cement concrete in
haunches and over crown with 1/2" cement plaster on top (except
earth filling and mud plaster and gobri) soffits of arches
cement plastered 1:6 and 1/2" thick. The rate also includes
bitumen coating centering, laying skew bricks in cement sand
mortar (1:3) and encasing exposed flanges of the joists with
fine cement concrete (1:2:4). Using stone aggregate:-
(b) Cement concrete in haunches 1:3:6
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Bricks 9"*4'-1/2*3" 550.0 Nos: 5000.0 %0 Nos: 2750.00
Cement for laying. 1.60 Cwt. 400.00 P.Bag 640.00
Cement for plastering top. 0.51 Cwt. 400.00 P.Bag 204.00
Cement for conc: in soffits 0.57 Cwt. 400.00 P.Bag 228.00
Cement for concrete in 4.10 Cwt. 400.00 P.Bag 1640.00
haunches.
Cement for concrete in 0.60 Cwt. 400.00 P.Bag 240.00
flanges.
Sand for laying. 10.00 Cft. 2425.00 % Cft. 242.50
Sand for plaster top. 3.84 Cft. 2425.00 % Cft. 93.12
Sand for plaster soffits. 4.26 Cft. 2425.00 % Cft. 103.31
Sand for concrete in 15.40 Cft. 2425.00 % Cft. 373.45
haunches.
Sand for concrete in 1.50 Cft. 2425.00 % Cft. 36.38
flanges.
Stone aggregates for 31.00 Cft. 825.00 % Cft. 255.75
concrete in haunches.
Stone aggregates for 3.00 Cft. 825.00 % Cft. 24.75
concrete in flanges.
Bitumen. 34.00 Lbs. 86213.00 P.Ton 1308.59
Fuel. 0.20 Mand. 900.00 P.Mand 180.00
Deodar wood for centering. L.S 256.00
TOTAL 8575.84
Contractor's profit 10.00 % 857.58
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 9433.42
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Masons. 2.750 Nos: 450.00 P.day. 1237.50
Carpenter. 0.500 Nos: 450.00 P.day. 225.00
Coolies. 5.50 Nos: 250.00 P.day. 1375.00
Bahishti. 1.00 Nos: 250.00 P.day. 250.00
TOTAL Rs: 3087.50
Sundries. 10.00 % 308.75
TOTAL 3396.25
Contractor's profit 10.00 % 339.63
TOTAL PART " B " 3735.88
TOTAL (MATERIAL + LABOUR) 13169.30
Total material & labour for 100 Sft. say Rs: 13169.30

Chapter No. 6 452/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

9. Extra for vaulted jack arch roofing.

______ ____________________________ ________ ______ ________ ______ __________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Masons. 1.000 Nos: 450.00 P.day. 450.00
Carpenter. 1.000 Nos: 450.00 P.day. 450.00

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 900.00
Sundries. 10.00 % 90.00
____________________________ ________ ______ ________ ______ __________
TOTAL 990.00
Contractor's profit 10.00 % 99.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 1089.00
____________________________ ________ ______ ________ ______ __________
TOTAL (LABOUR) 1089.00
____________________________ ________ ______ ________ ______ __________
Total labour rate for 100 Sft. say Rs: 1089.00

______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 453/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
10. Jack arch roofing of shingle and cement concrete (1:3:6) 4"-1"/2
thick at crown with 1"/2 cement plaster including cost of
supplying erecting and dismentling centering.

______ ____________________________ ________ ______ ________ ______ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Cement. 7.46 Cwt. 400.00 P.Bag 2984.00
Sand. 28.00 Cft. 2425.00 % Cft. 679.00
Shingle. 56.00 Cft. 3075.00 % Cft. 1722.00
Deodar wood for centering. L.S 256.00
____________________________ ________ ______ ________ ______ __________
TOTAL 5641.00
Contractor's profit 10.00 % 564.10
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 6205.10
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Masons. 0.500 Nos: 450.00 P.day. 225.00
Carpenter. 1.000 Nos: 450.00 P.day. 450.00
Coolies for stacking and 3.00 Nos: 250.00 P.day. 750.00
mixing.
Coolies for ramming. 3.00 Nos: 250.00 P.day. 750.00
Coolies for carrying. 2.00 Nos: 250.00 P.day. 500.00
Coolies for carpenter. 1.00 Nos: 250.00 P.day. 250.00
Bahishti. 1.00 Nos: 250.00 P.day. 250.00
____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 3175.00
Sundries. 10.00 % 317.50
____________________________ ________ ______ ________ ______ __________
TOTAL 3492.50
Contractor's profit 10.00 % 349.25
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 3841.75
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 10046.85
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 10046.85

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 454/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______ ____________________________ ________ ______ ________ ______ __________


S/N D E S C R I P T I O N.
11. Earth filling over roof including watering ramming with 1" mud
plaster finished with gobri leeping.
(a) 3" thick earth filling and 1" mud plaster.
(Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Earth lead upto 100' and 33.00 Cft. 500.00 % Cft. 165.00
lift upto 20'

Bhoosa. 17.00 Seer. 300.00 P.Mand 127.50

Clay. 0.75 Cft. 500.00 % Cft. 3.75

Cow dung. 0.75 Cft. 500.00 % Cft. 3.75


____________________________ ________ ______ ________ ______ __________
TOTAL 300.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 30.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 330.00
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________

Bahishti. 0.12 Nos: 250.00 P.day. 30.00

Coolies for lifting and 1.00 Nos: 250.00 P.day. 250.00


ramming earth.

Masons. 0.120 Nos: 450.00 P.day. 54.00


____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 334.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 33.40
____________________________ ________ ______ ________ ______ __________
TOTAL 367.40
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 36.74
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 404.14
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 734.14
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 734.14
______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 455/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
11. Eath filling over roof including watering ramming with 1" mud
plaster finished with gobri leeping.
(b) 4" thick earth filling and 1" mud plaster.
(Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Earth lead upto 100' and 43.00 Cft. 500.00 % Cft. 215.00
lift upto 20'

Bhoosa. 17.00 Seer. 300.00 P.Mand 127.50

Clay. 0.75 Cft. 500.00 % Cft. 3.75

Cow dung. 0.75 Cft. 500.00 % Cft. 3.75


____________________________ ________ ______ ________ ______ __________
TOTAL 350.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 35.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 385.00
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________

Bahishti. 0.18 Nos: 250.00 P.day. 45.00

Coolies for lifting and 1.00 Nos: 250.00 P.day. 250.00


ramming earth.

Masons. 0.120 Nos: 450.00 P.day. 54.00


____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 349.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 34.90
____________________________ ________ ______ ________ ______ __________
TOTAL 383.90
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 38.39
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 422.29
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 807.29
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 807.29
______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 456/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

12. 1/8" thick gobri leeping on roofs or floors.

(Unit of rate per 100 Sft.)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Fine clay. 0.75 Cft. 500.00 % Cft. 3.75

Cow dung. 0.75 Cft. 500.00 % Cft. 3.75

____________________________ ________ ______ ________ ______ __________


TOTAL 7.50
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 0.75
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 8.25
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________

Mason. 0.12 Nos: 450.00 P.day. 54.00

Bahishti. 0.06 Nos: 250.00 P.day. 15.00

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 69.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 6.90
____________________________ ________ ______ ________ ______ __________
TOTAL 75.90
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 7.59
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 83.49
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 91.74
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 91.74
______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 457/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

13. Two coats of bitumen laid hot using 34 lbs per % sft over roof
and blinded with sand at 1 cft per % sft.

(Unit of rate per 100 Sft.)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Sand. 1.00 Cft. 2425.00 % Cft. 24.25

Bitumen. 34.00 Lbs. 86213.00 P.Ton 1308.59

Fuel. 0.12 Mand. 900.00 P.Mand 108.00


____________________________ ________ ______ ________ ______ __________
TOTAL 1440.84
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 144.08
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 1584.92
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Cooly for heating and 1.00 Nos: 250.00 P.day. 250.00
laying.

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 250.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 25.00
____________________________ ________ ______ ________ ______ __________
TOTAL 275.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 27.50
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 302.50
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 1887.42
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 1887.42
______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 458/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

14. Thatched roof complete with bambo frame and matting including
cost of all materials and labour.
(a) Upto 4-1/2" thick thatched roof (Sarkanda)
(Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Bamboos 1-1/4" dia 11'long. 11.0 Nos: 125.0 Each. 1375.00

Matting sarkanda. 100.0 Sft. 400.00 % Sft. 400.00

Thatching - Sarkanda. 38.0 Cft. 475.00 % Cft. 180.50

____________________________ ________ ______ ________ ______ __________


TOTAL 1955.50
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 195.55
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 2151.05
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Cooly (skilled) 0.75 Nos: 250.00 P.day. 187.50

Cooly for helping and 0.75 Nos: 250.00 P.day. 187.50


lifting.

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 375.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 37.50
____________________________ ________ ______ ________ ______ __________
TOTAL 412.50
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 41.25
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 453.75
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 2604.80
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 2604.80
______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 459/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

14. Thatched roof complete with bambo frame and matting including
cost of all materials and labour.
(b) Upto 6" thick thatched roof (grass)
(Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Bamboos 1-1/4" dia 11'long. 22.0 Nos: 125.0 Each. 2750.00

Matting sarkanda. 100.0 Sft. 400.00 % Sft. 400.00

6" thick grass thatching 50.0 Cft. 300.00 % Cft. 150.00


two layers 3" thick.
____________________________ ________ ______ ________ ______ __________
TOTAL 3300.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 330.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 3630.00
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Cooly (skilled) 1.00 Nos: 250.00 P.day. 250.00

Cooly for helping and 1.00 Nos: 250.00 P.day. 250.00


lifting.

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 500.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 50.00
____________________________ ________ ______ ________ ______ __________
TOTAL 550.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 55.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 605.00
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 4235.00
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 4235.00
______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 460/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

14. Thatched roof complete with bambo frame and matting including
cost of all materials and labour.
(c) Upto 9" thick thatched roof (grass)
(Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Bamboos 1-1/4" dia 11'long. 22.0 Nos: 125.0 Each. 2750.00

Matting sarkanda. 100.0 Sft. 400.00 % Sft. 400.00

9" thick grass thatching 75.0 Cft. 300.00 % Cft. 225.00


three layers 3" thick.

____________________________ ________ ______ ________ ______ __________


TOTAL 3375.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 337.50
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 3712.50
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Cooly (skilled) 1.00 Nos: 250.00 P.day. 250.00

Cooly for helping and 1.00 Nos: 250.00 P.day. 250.00


lifting.

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 500.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 50.00
____________________________ ________ ______ ________ ______ __________
TOTAL 550.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 55.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 605.00
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 4317.50
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 4317.50
______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 461/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

14. Thatched roof complete with bambo frame and matting including
cost of all materials and labour.
(d) Upto 12" thick thatched roof (grass)
(Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Bamboos 1-1/2" dia 10'long. 22.0 Nos: 160.0 Each. 3520.00

Matting sarkanda. 100.0 Sft. 400.00 % Sft. 400.00

12" thick grass thatching 100.0 Cft. 300.00 % Cft. 300.00


four layers 3" thick.
TOTAL 4220.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 422.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 4642.00
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Cooly (skilled) 1.00 Nos: 250.00 P.day. 250.00

Cooly for helping and 1.50 Nos: 250.00 P.day. 375.00


lifting.

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 625.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 62.50
____________________________ ________ ______ ________ ______ __________
TOTAL 687.50
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 68.75
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 756.25
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 5398.25
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 5398.25
______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 462/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
15. Date palm chattai roofing including cost of bamboos except
ballies.

(Unit of rate per 100 Sft.)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Bamboos 2" dia 11 ft long. 11.0 Nos: 160.0 Each. 1760.00
Matting sarkanda. 100.0 Sft. 400.00 % Sft. 400.00
Chattai. (Palm matting) 100.0 Sft. 675.00 % Sft. 675.00
Earth. 43.00 Cft. 500.00 % Cft. 215.00
Bhoosa. 17.00 Seer. 300.00 P.Mand 127.50

____________________________ ________ ______ ________ ______ __________


TOTAL 3177.50
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 317.75
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 3495.25
____________________________ ________ ______ ________ ______ __________
(B) LABOUR Masons for mud plastering.
____________________________ ________ ______ ________ ______ __________
Masons for plastering. 0.330 Nos: 450.00 P.day. 148.50

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Bahishti. 0.10 Nos: 250.00 P.day. 25.00


____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 548.50
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 54.85
____________________________ ________ ______ ________ ______ __________
TOTAL 603.35
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 60.34
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 663.69
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 4158.94
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 4158.94

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 463/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
16. Fixing corrugated and galvanised iron sheets with G.I bolts,
nuts, limpet and bitumen washers, wind ties complete in all
respect without varleys and ridges.
(a) 20-B.W.G. (Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Sheets of 20 gauge 2.0 Cwt. 5000.0 P.Cwt. 10000.00
including over lapping and
120 Sft = 2.00 Cwt.

Wind tie (rod) 22.00 Lbs. 4750.00 P.Cwt. 933.04

Limpet washers. 2.00 Doz. 115.00 P.doz. 230.00

G.I. bolts and nuts. 2.00 Doz. 225.00 P.doz. 450.00

G.I. hooks, bolts and nuts. 2.00 Doz. 200.00 P.doz. 400.00

Bitumen washers. 3.50 Doz. 41.00 P.doz. 143.50

Charcoal. 4.00 Seer. 675.00 P.Mand 67.50


____________________________ ________ ______ ________ ______ __________
TOTAL 12224.04
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 1222.40
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 13446.44
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Black-smith. 1.000 Nos: 450.00 P.day. 450.00

Coolies. 1.00 Nos: 250.00 P.day. 250.00


TOTAL Rs: 700.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 70.00
____________________________ ________ ______ ________ ______ __________
TOTAL 770.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 77.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 847.00
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 14293.44
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 14293.44

Chapter No. 6 464/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
16. Fixing corrugated and galvanised iron sheets with G.I bolts,
nuts, limpet and bitumen washers, wind ties complete in all
respect without varleys and ridges.
(b) 22-B.W.G. (Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Sheets of 22 gauge 1.7 Cwt. 5000.0 P.Cwt. 8500.00
including over lapping and
120 Sft = 1.70 Cwt.

Wind tie (rod) 22.00 Lbs. 4750.00 P.Cwt. 933.04

Limpet washers. 2.00 Doz. 115.00 P.doz. 230.00

G.I. bolts and nuts. 2.00 Doz. 225.00 P.doz. 450.00

G.I. hooks, bolts and nuts. 2.00 Doz. 200.00 P.doz. 400.00

Bitumen washers. 3.50 Doz. 41.00 P.doz. 143.50

Charcoal. 4.00 Seer. 675.00 P.Mand 67.50


____________________________ ________ ______ ________ ______ __________
TOTAL 10724.04
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 1072.40
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 11796.44
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Black-smith. 1.000 Nos: 450.00 P.day. 450.00

Coolies. 1.00 Nos: 250.00 P.day. 250.00


____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 700.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 70.00
____________________________ ________ ______ ________ ______ __________
TOTAL 770.00
Contractor's profit 10.00 % 77.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 847.00
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 12643.44
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 12643.44

Chapter No. 6 465/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
16. Fixing corrugated and galvanised iron sheets with G.I bolts,
nuts, limpet and bitumen washers, wind ties complete in all
respect without varleys and ridges.
(c) 24-B.W.G. (Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Sheets of 22 gauge 1.3 Cwt. 5000.0 P.Cwt. 6700.00
including over lapping and
120 Sft = 1.34 Cwt.

Wind tie (rod) 22.00 Lbs. 4750.00 P.Cwt. 933.04

Limpet washers. 2.00 Doz. 115.00 P.doz. 230.00

G.I. bolts and nuts. 2.00 Doz. 225.00 P.doz. 450.00

G.I. hooks, bolts and nuts. 2.00 Doz. 200.00 P.doz. 400.00

Bitumen washers. 3.50 Doz. 41.00 P.doz. 143.50

Charcoal. 4.00 Seer. 675.00 P.Mand 67.50


____________________________ ________ ______ ________ ______ __________
TOTAL 8924.04
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 892.40
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 9816.44
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Black-smith. 1.000 Nos: 450.00 P.day. 450.00

Coolies. 1.00 Nos: 250.00 P.day. 250.00


TOTAL Rs: 700.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 70.00
____________________________ ________ ______ ________ ______ __________
TOTAL 770.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 77.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 847.00
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 10663.44
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 10663.44

Chapter No. 6 466/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
17. Khassi pernalas in cement sand mortar (1:2) 12" outside width
finished smooth with a floating coat of neat cement.

(Unit of rate per Rft.)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Take for 12 Rft.

Cement for 1/2" plaster. 0.18 Cwt. 400.00 P.Bag 72.00

Cement for floating coat. 0.06 Cwt. 400.00 P.Bag 24.00

Cement for side filled. 0.26 Cwt. 400.00 P.Bag 104.00

Sand. 1.10 Cft. 2425.00 % Cft. 26.68


____________________________ ________ ______ ________ ______ __________
TOTAL 226.68
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 22.67
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 249.34
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Mason. 0.670 Nos: 450.00 P.day. 301.50

Coolies. 0.67 Nos: 250.00 P.day. 167.50

Bahishti. 0.09 Nos: 250.00 P.day. 22.50


____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 491.50
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 49.15
____________________________ ________ ______ ________ ______ __________
TOTAL 540.65
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 54.07
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 49.56 594.72
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 844.06
____________________________ ________ ______ ________ ______ __________
Total material & labour for 12 Rft. Rs: 844.06
Total material & labour for 1 Rft. Rs: 70.34
______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 467/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
18. Khuras, on roof size 2' * 2' * 6"

(Unit of rate per No:)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________

Cement. 0.30 Cwt. 400.00 P.Bag 120.00

Sand. 0.90 Cft. 2425.00 % Cft. 21.83

Aggregates (stone) 2.00 Cft. 825.00 % Cft. 16.50


TOTAL 158.33
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 15.83
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 174.16
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Mason. 0.200 Nos: 450.00 P.day. 90.00

Coolies. 0.20 Nos: 250.00 P.day. 50.00

Bahishti. 0.05 Nos: 250.00 P.day. 12.50


____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 152.50
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 15.25
____________________________ ________ ______ ________ ______ __________
TOTAL 167.75
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 16.78
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 184.53
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 358.68
____________________________ ________ ______ ________ ______ __________
Total material & labour for each. Rs: 358.68
Total material & labour for each. say Rs: 358.68

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 468/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
19. Bottom khuras of brick masonary in cement mortar (1:6) 4' * 2' *
4-1/2" over 3" cement concrete 1:4:8.
(Unit of rate per No:)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Stone (brick aggregates) 2.00 Cft. 825.00 % Cft. 16.50

Cement. 0.37 Cwt. 400.00 P.Bag 148.00

Sand. 2.00 Cft. 2425.00 % Cft. 48.50

Bricks. 42.00 Nos: 5000.00 %0 Nos: 210.00

____________________________ ________ ______ ________ ______ __________


TOTAL 423.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 42.30
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 465.30
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Mason. 0.200 Nos: 450.00 P.day. 90.00

Coolies. 0.20 Nos: 250.00 P.day. 50.00

Bahishti. 0.05 Nos: 250.00 P.day. 12.50


____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 152.50
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 15.25
____________________________ ________ ______ ________ ______ __________
TOTAL 167.75
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 16.78
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 184.53
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 649.83
____________________________ ________ ______ ________ ______ __________
Total material & labour for each. Rs: 649.83
Total material & labour for each. say Rs: 649.83
______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 469/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
20. Plain galvanized iron sheets of 22 S.W.G. rain water down pipe
including clamps and fixed in place.

(a) 4" dia down pipe. (Unit of rate per Rft.)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
G.I sheets = 1.05 Sft 1.50 Lbs. 1450.00 P.Cwt. 19.42
Add 10% for joints
& wastage. = 0.10 Sft.
1.15 * 1.31 = 1.50 Lbs.

Add for clamps bolts, nuts L.S 8.00


and revits.

____________________________ ________ ______ ________ ______ __________


TOTAL 27.42
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 2.74
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 30.16
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Black-smith. 0.030 Nos: 450.00 P.day. 13.50

Coolies. 0.03 Nos: 250.00 P.day. 7.50

Mason. 0.03 Nos: 450.00 P.day. 13.50


____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 34.50
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 3.45
____________________________ ________ ______ ________ ______ __________
TOTAL 37.95
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 3.80
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 41.75
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 71.91
____________________________ ________ ______ ________ ______ __________
Total material & labour per Rft. say Rs: 71.91
______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 470/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
20. Plain galvanized iron sheets of 22 S.W.G. rain water down pipe
including clamps and fixed in place.

(b) 5" dia down pipe. (Unit of rate per Rft.)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
G.I sheets = 1.13 Sft 1.90 Lbs. 1450.00 P.Cwt. 24.60
Add 10% for joints
& wastage. = 0.13 Sft.
1.44 * 1.31 = 1.90 Lbs.

Add for clamps bolts, nuts L.S 16.00


and revits.
____________________________ ________ ______ ________ ______ __________
TOTAL 40.60
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 4.06
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 44.66
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Black-smith. 0.030 Nos: 450.00 P.day. 13.50

Coolies. 0.03 Nos: 250.00 P.day. 7.50

Mason. 0.03 Nos: 450.00 P.day. 13.50


____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 34.50
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 3.45
____________________________ ________ ______ ________ ______ __________
TOTAL 37.95
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 3.80
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 41.75
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 86.40
____________________________ ________ ______ ________ ______ __________
Total material & labour per Rft. say Rs: 86.40
______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 471/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
21. Plain galvanized iron sheet flashing of 22 S.W.G.

(Unit of rate per Rft.)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
G.I sheets 22 gauge. 1.00 Lbs. 1450.00 P.Cwt. 12.95

Fixture. L.S 6.00

____________________________ ________ ______ ________ ______ __________


TOTAL 18.95
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 1.89
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 20.84
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Black-smith. 0.030 Nos: 450.00 P.day. 13.50

Coolies. 0.03 Nos: 250.00 P.day. 7.50

Mason. 0.05 Nos: 450.00 P.day. 22.50


____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 43.50
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 4.35
____________________________ ________ ______ ________ ______ __________
TOTAL 47.85
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 4.79
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 52.64
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 73.48
____________________________ ________ ______ ________ ______ __________
Total material & labour per Rft. say Rs: 73.48

______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 472/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
22. Cast iron rain water down pipe fixed in place excluding heads
and shoes but including painting and clamps , etc.
(a) 4" dia C.I down pipe. (Unit of rate per Rft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Assume for 6 Rft.
C.I pipe 4" dia. 6.00 Rft. 300.00 P.Rft. 1800.00

Hold fasts with bolts. 1.0 No: 210.00 Each. 210.00

Cement mortar for fixing L.S 40.00


hold fasts.

Painting. L.S 32.00

____________________________ ________ ______ ________ ______ __________


TOTAL 2082.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 208.20
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 2290.20
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Mason 0.200 Nos: 450.00 P.day. 90.00

Coolies. 0.20 Nos: 250.00 P.day. 50.00


TOTAL Rs: 140.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 14.00
____________________________ ________ ______ ________ ______ __________
TOTAL 154.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 15.40
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 28.23 169.40
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 2459.60
____________________________ ________ ______ ________ ______ __________
Total material & labour for 6 Rft. Rs: 2459.60
Total material & labour per Rft. Rs: 409.93
Total material & labour per Rft. say Rs: 409.93

Chapter No. 6 473/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
22. Cast iron rain water down pipe fixed in place excluding heads
and shoes but including painting and clamps , etc.
(b) 3" dia C.I down pipe. (Unit of rate per Rft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Assume for 6 Rft.
C.I pipe 3" dia. 6.00 Rft. 300.00 P.Rft. 1800.00

Hold fasts with bolts. 1.0 No: 210.00 Each. 210.00

Cement mortar for fixing L.S 40.00


hold fasts.

Painting. L.S 25.00


TOTAL 2075.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 207.50
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 2282.50
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Mason 0.200 Nos: 450.00 P.day. 90.00

Coolies. 0.20 Nos: 250.00 P.day. 50.00

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 140.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 14.00
____________________________ ________ ______ ________ ______ __________
TOTAL 154.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 15.40
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 28.23 169.40
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 2451.90
____________________________ ________ ______ ________ ______ __________
Total material & labour for 6 Rft. Rs: 2451.90
Total material & labour per Rft. Rs: 408.65
Total material & labour per Rft. say Rs: 408.65
______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 474/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
23. Rain water down pipe cast iron heads fixed in place including
cost of clamps, hold fast and painting.
(Unit of rate per No:)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________

C.I. Heads. 1.0 No: 385.00 Each. 385.00

Hold fasts with bolts. 1.0 No: 210.00 Each. 210.00

Cement mortar for fixing L.S 40.00


hold fasts.

Painting. LS 25.00
TOTAL 660.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 66.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 726.00
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Mason 0.090 Nos: 450.00 P.day. 40.50

Coolies. 0.09 Nos: 250.00 P.day. 22.50

Pipe Fiter. 0.09 Nos: 400.00 P.day. 36.00


____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 99.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 9.90
____________________________ ________ ______ ________ ______ __________
TOTAL 108.90
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 10.89
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 119.79
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 845.79
____________________________ ________ ______ ________ ______ __________
Total material & labour for each. Rs: 845.79
______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 475/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
24. Shoe bends or offsets for cast iron rain water down pipe
including fixing and painting.
(Unit of rate per No:)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________

C.I. shoe bend or offsets. 1.0 No: 385.00 Each. 385.00

Pig lead. L.S 16.00

Painting. LS 20.00

TOTAL 421.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 42.10
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 463.10
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________

Coolies. 0.05 Nos: 250.00 P.day. 12.50

Pipe Fiter. 0.05 Nos: 400.00 P.day. 20.00

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 32.50
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 3.25
____________________________ ________ ______ ________ ______ __________
TOTAL 35.75
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 3.58
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 39.33
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 502.43
____________________________ ________ ______ ________ ______ __________
Total material & labour for each. Rs: 502.43

______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 476/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
25. Plain G.I sheet iron spouts fixed in place including painting.

(Unit of rate per No:)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________

G.I sheet 22 gauge. 1.5 Lbs. 4450.00 P.Cwt. 59.60


Lenth = 28" , Width= 6"
= 28*6/144 *1.28 =1.5 Lbs.

Cost of cement mortar. L.S 32.00

____________________________ ________ ______ ________ ______ __________


TOTAL 91.60
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 9.16
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 100.76
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Mason. 0.10 Nos: 450.00 P.day. 45.00

Black-smith. 0.10 Nos: 450.00 P.day. 45.00

Coolies. 0.10 Nos: 250.00 P.day. 25.00

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 115.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 11.50
____________________________ ________ ______ ________ ______ __________
TOTAL 126.50
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 12.65
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 139.15
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 239.91
____________________________ ________ ______ ________ ______ __________
Total material & labour for each. Rs: 239.91

Chapter No. 6 477/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
26. Laying 1/2" thick deodar cieling complete. (including sawing
plaining and fixing)
(Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________

Dedar wood (First quality) 5.0 Cft. 4500.00 P.Cft. 22500.00

Screws of sorts. 6 Doz: 315.00 P.Gross 157.50

Nails of sorts. 1.7 kg 110.00 P.Kilo 187.00

____________________________ ________ ______ ________ ______ __________


TOTAL 22844.50
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 2284.45
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 25128.95
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Carpenters. 4.00 Nos: 450.00 P.day. 1800.00

Coolies. 3.00 Nos: 250.00 P.day. 750.00

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 2550.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 255.00
____________________________ ________ ______ ________ ______ __________
TOTAL 2805.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 280.50
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 3085.50
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 28214.45
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. Rs: 28214.45
______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 478/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
27. Flat sheet roof with galvanized iron plain sheets including
battens rolls, screws clips etc. (Planking to be paid for
seperately)
(a) 22 - B.W.G. sheets roofing. (Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
G.I sheets in 400 sft area including over lapping and 25%
wastage for 100 Sft = 5.85/4 = 1.46 Cwt.
Rolls 5" wide 16' long or 16 * 5 * 7/12 = 0.54/4 =0.14 Cwt.
(7 Nos: or 47 Sft or 1.27 lbs/Sft = 0.54 Cwt.)
Deodar wood for battens 2"*1-1/2" size 7 Nos: of 16' length =
(7*16*1/6 *1/8 = 2.33 Cft. + wastage 25% = 0.58 Cft.)= 2.91 Cft.
____________________________ ________ ______ ________ ______ __________
G.I sheets. 5.85 Cwt. 4450.00 P.Cwt. 26032.50

Rolls 5" wide 16' long. 0.54 Cwt. 3375.00 P.Cwt. 1822.50

Deodar wood. (II Class) 2.9 Cft. 4000.00 P.Cft. 11640.00

Bolts, nuts, and limpet L.S 96.00


washers.
G.I clips. L.S 48.00
TOTAL 39639.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 3963.90
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 43602.90
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Black-smith. 8.00 Nos: 450.00 P.day. 3600.00

Coolies. 12.00 Nos: 250.00 P.day. 3000.00

Carpenters. 1.50 Nos: 450.00 P.day. 675.00

TOTAL Rs: 7275.00


____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 727.50
TOTAL 8002.50
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 800.25
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 2200.69 8802.75
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 52405.65
____________________________ ________ ______ ________ ______ __________
Total material & labour for 400 Sft. Rs: 52405.65
Total material & labour for 100 Sft. Rs: 13101.41
Total material & labour for 100 Sft. say Rs: 13101.41

Chapter No. 6 479/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
27. Flat sheet roof with galvanized iron plain sheets including
battens rolls, screws clips etc. (Planking to be paid for
seperately)
(b) 24 - B.W.G. sheet roofing. (Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
G.I sheets in 400 sft area including over lapping and 25%
wastage = 500 Sft. = 5 Cwt.
Rolls 5" wide 16' long or 16 * 5 * 7/12 = 0.43 Cwt.
( 47 Sft or 0.43 Cwt.)
Deodar wood for battens 2"*1-1/2" size 7 Nos: of 16' length =
(7*16*1/6 *1/8 = 2.33 Cft. + wastage 25% = 0.58 Cft.)= 2.91 Cft.
____________________________ ________ ______ ________ ______ __________
G.I sheets. 5.00 Cwt. 4450.00 P.Cwt. 22250.00

Rolls. 0.43 Cwt. 3375.00 P.Cwt. 1451.25

Deodar wood. (II Class) 2.9 Cft. 4000.00 P.Cft. 11640.00

Bolts, nuts, and limpet L.S 96.00


washers.
G.I clips. L.S 48.00
TOTAL 35485.25
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 3548.53
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 39033.78
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Black-smith. 8.00 Nos: 450.00 P.day. 3600.00

Coolies. 12.00 Nos: 250.00 P.day. 3000.00

Carpenters. 1.50 Nos: 450.00 P.day. 675.00


TOTAL Rs: 7275.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 727.50
____________________________ ________ ______ ________ ______ __________
TOTAL 8002.50
Contractor's profit 10.00% 800.25
TOTAL PART " B " 2200.69 8802.75
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 47836.53
____________________________ ________ ______ ________ ______ __________
Total material & labour for 400 Sft. Rs: 47836.53
Total material & labour for 100 Sft. Rs: 11959.13
Total material & labour for 100 Sft. say Rs: 11959.13

Chapter No. 6 480/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
28. Absestos cement corrugated sheet roofing including necessary
over laps and G.I hooks, bolts, nuts, screws, washers and
bitumen washers etc. (excluding valleys and ridges )
(Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Corrugated A.C.Sheets with 125.0 Sft. 6750.0 P.Sft. 8437.50
25% over lapping & wastage.

G.I. or limpet washers and 7.00 Doz. 115.00 P.doz. 805.00


bitumen washers.
G.I. bolts and nuts. 2.00 Doz. 225.00 P.doz. 450.00

G.I. hooks, bolts and nuts. 1.50 Doz. 200.00 P.doz. 300.00
6" * 5/16"

____________________________ ________ ______ ________ ______ __________


TOTAL 9992.50
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 999.25
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 10991.75
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Carpenter. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 2.00 Nos: 250.00 P.day. 500.00

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 950.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 95.00
____________________________ ________ ______ ________ ______ __________
TOTAL 1045.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 104.50
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 1149.50
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 12141.25
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 12141.25

Chapter No. 6 481/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
29. Extra labour for erection of C.I sheets flat sheet or asbestos
sheet roofing above 20 feet hieght in difficult position
including lifting with care & special scaffolding along live
wires. (Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Fitter. 0.06 Nos: 400.00 P.day. 24.00

Coolies. 0.50 Nos: 250.00 P.day. 125.00

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 149.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 14.90
____________________________ ________ ______ ________ ______ __________
TOTAL 163.90
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 16.39
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 180.29
____________________________ ________ ______ ________ ______ __________
Total labour rate for 100 Sft. say Rs: 180.29

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 482/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
______ ____________________________ ________ ______ ________ ______ __________
S/N D E S C R I P T I O N.
30. Fixing asbestos cement sheet ridges and valleys 1/4" thick.

(Unit of rate per Rft.)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
A.C ridge sheet for a shed 61.0 Rft. 160.00 P.Rft. 9760.00
of 60' * 30' or 61 Rft.

G.I. bolts and nut with 5.00 Doz. 225.00 P.doz. 1125.00
washers.
Bitumen washers. 5.00 Doz. 41.00 P.doz. 205.00

____________________________ ________ ______ ________ ______ __________


TOTAL 11090.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 1109.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 12199.00
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Carpenter. 1.50 Nos: 450.00 P.day. 675.00

Coolies. 2.00 Nos: 250.00 P.day. 500.00

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 1175.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 117.50
____________________________ ________ ______ ________ ______ __________
TOTAL 1292.50
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 129.25
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 23.31 1421.75
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 13620.75
____________________________ ________ ______ ________ ______ __________
Total material & labour for 61 Rft. Rs: 13620.75
Total material & labour for 1 Rft. Rs: 223.29

Chapter No. 6 483/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
31. Plain galvanized iron sheet ridging including fixture, timber
for ridge roll and ridge sheeting.
(a) 6" lap and 18" over all of 22 G.I. sheet ridging.
(Unit of rate per Rft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
G.I. sheet 22 gauge=1.5 Sft 2.1 Lbs. 4450.00 P.Cwt. 83.83
10% wastage. =0.15 Sft
(1.65 Sft = 2.11 Lbs)
Deodar wood. 0.1 Cft. 4000.00 P.Cft. 320.00
TOTAL 403.83
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 40.38
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 444.22
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Carpenter. 0.03 Nos: 450.00 P.day. 13.50

Black-smith. 0.03 Nos: 450.00 P.day. 13.50

Coolies. 0.03 Nos: 250.00 P.day. 7.50

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 34.50
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 3.45
____________________________ ________ ______ ________ ______ __________
TOTAL 37.95
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 3.80
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 41.75
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 485.96
____________________________ ________ ______ ________ ______ __________
Total material & labour per Rft. Rs: 485.96

Chapter No. 6 484/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________


S/N D E S C R I P T I O N.
31. Plain galvanized iron sheet ridging including fixture, timber
for ridge roll and ridge sheeting.
(b) 9" lap and 24" over all of 24 G.I. sheet ridging.
(Unit of rate per Rft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
G.I. sheet 24 gauge=2.1 Sft 2.50 Lbs. 4450.00 P.Cwt. 99.33
10% wastage. =0.21 Sft
(2.31 Sft = 2.50 Lbs)
Deodar wood. 0.07 Cft. 4000.00 P.Cft. 280.00

____________________________ ________ ______ ________ ______ __________


TOTAL 379.33
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 37.93
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 417.26
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Carpenter. 0.03 Nos: 450.00 P.day. 13.50

Black-smith. 0.03 Nos: 450.00 P.day. 13.50

Coolies. 0.06 Nos: 250.00 P.day. 15.00

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 42.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 4.20
____________________________ ________ ______ ________ ______ __________
TOTAL 46.20
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 4.62
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 50.82
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 468.08
____________________________ ________ ______ ________ ______ __________

Chapter No. 6 485/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
Total material & labour per Rft. Rs: 468.08
S/N D E S C R I P T I O N.
31. Plain galvanized iron sheet ridging including fixture, timber
for ridge roll and ridge sheeting.
(c) 12" lap and 30" over all of 22 G.I. sheet ridging.
(Unit of rate per Rft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
G.I. sheet 22 gauge=2.5 Sft 3.60 Lbs. 4450.00 P.Cwt. 143.04
10% wastage. =0.25 Sft
(2.75 Sft = 3.60 Lbs)
Deodar wood. 0.07 Cft. 4000.00 P.Cft. 280.00

____________________________ ________ ______ ________ ______ __________


TOTAL 423.04
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 42.30
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 465.34
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Carpenter. 0.03 Nos: 450.00 P.day. 13.50

Black-smith. 0.03 Nos: 450.00 P.day. 13.50

Coolies. 0.06 Nos: 250.00 P.day. 15.00

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 42.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 4.20
____________________________ ________ ______ ________ ______ __________
TOTAL 46.20
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 4.62
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 50.82
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 516.16
____________________________ ________ ______ ________ ______ __________
Total material & labour per Rft. Rs: 516.16

Chapter No. 6 486/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________


S/N D E S C R I P T I O N.

32. Plain 22 gauge G.I. sheet gutter semi circular 8" diameter.

(Unit of rate per No:)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
G.I. sheet. 1.38 Lbs. 4450.00 P.Cwt. 54.83

Wrought iron bracket 1.00 No: 65.00 Each. 65.00


complete with bolts, nuts
and revits etc.

____________________________ ________ ______ ________ ______ __________


TOTAL 119.83
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 11.98
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 131.81
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Carpenter. 0.03 Nos: 450.00 P.day. 13.50

Coolies. 0.03 Nos: 250.00 P.day. 7.50

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 21.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 2.10
____________________________ ________ ______ ________ ______ __________
TOTAL 23.10
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 2.31
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 25.41
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 157.22
____________________________ ________ ______ ________ ______ __________
Total material & labour per Rft. Rs: 157.22

Chapter No. 6 487/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

33. Making and fixing cowl roof ventiletors of sheet iron.

(Unit of rate per No:)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Take 4 Nos:
G.I sheet 20 S.W.G. =4 * 3.5' * 1.75 @ 1.59 lbs/sft. = 39.0 Lbs.
Iron strap 1/8 thick = 4*2*8/12 *3/24 @ 5.1 lbs/sft. = 3.41 lbs.
____________________________ ________ ______ ________ ______ __________
G.I. sheet. 39.00 Lbs. 4450.00 P.Cwt. 1549.55

Wastage 10% 4.0 Lbs. 1450.00 P.Cwt. 51.79

Iron strap 1/8" thick i/c 4.00 Lbs. 1800.00 P.Cwt. 64.29
wastage.(3.41+0.34 =3.75)
say 4 lbs.

Rivets. L.S 25.00

____________________________ ________ ______ ________ ______ __________


TOTAL 1690.63
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 169.06
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 1859.69
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Fitter. 1.00 Nos: 400.00 P.day. 400.00

Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 2.00 Nos: 250.00 P.day. 500.00


____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 1350.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 135.00
____________________________ ________ ______ ________ ______ __________
TOTAL 1485.00
Contractor's profit 10.00 % 148.50
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 408.38 1633.50
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 3493.19
____________________________ ________ ______ ________ ______ __________
Total material & labour for 4 Nos: Rs: 3493.19
Total material & labour for 1 No: Rs: 873.30

Chapter No. 6 488/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
34. Fixing cowl roof ventiletor.
(Unit of rate per No:)
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Assume for 8 Nos:
Mason. 1.00 Nos: 450.00 P.day. 450.00
Coolies. 1.00 Nos: 250.00 P.day. 250.00
TOTAL Rs: 700.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 70.00
____________________________ ________ ______ ________ ______ __________
TOTAL 770.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 77.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 847.00
____________________________ ________ ______ ________ ______ __________
Total labour rate for 8 Nos: Rs: 847.00
Total labour rate for Each. Rs: 105.88
Total labour rate for Each. say Rs: 105.88
S/N D E S C R I P T I O N.

35. Making masonary ventilators.


(Unit of rate each)
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Pacca bricks. 50.00 Nos: 5000.00 %0 Nos: 250.00

Surkhi. 1.0 Cft. 275.00 % Cft. 2.75

lime 10.0 Seer 105.00 P.Mand 26.25


TOTAL 279.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 27.90
TOTAL PART " A " 306.90
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 1.00 Nos: 250.00 P.day. 250.00


TOTAL Rs: 700.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 70.00
TOTAL 770.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 77.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 847.00
TOTAL (MATERIAL + LABOUR) 1153.90
Total material & labour for each. Rs: 1153.90

Chapter No. 6 489/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

36. Fixing earthen ware syphon ventilators.


(Unit of rate each)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Assume 9 Nos:
Surkhi. 2.0 Cft. 275.00 % Cft. 5.50

Lime. 20.0 Seer 105.00 P.Mand 52.50


TOTAL 58.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 5.80
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 63.80
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 1.00 Nos: 250.00 P.day. 250.00

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 700.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 70.00
____________________________ ________ ______ ________ ______ __________
TOTAL 770.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 77.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 94.11 847.00
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 910.80
____________________________ ________ ______ ________ ______ __________
Total material & labour for 9 Nos: Rs: 910.80
Total material & labour for Each. Rs: 101.20
Total material & labour for Each. say Rs: 101.20

Chapter No. 6 490/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

S/N D E S C R I P T I O N.
37. Fixing water spouts for parnalas.
(Unit of rate each No:)
______ ____________________________ ________ ______ ________ ______ __________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:

Mason. 0.25 Nos: 450.00 P.day. 112.50


Coolies. 0.25 Nos: 250.00 P.day. 62.50
____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 175.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 17.50
____________________________ ________ ______ ________ ______ __________
TOTAL 192.50
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 19.25
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 211.75
____________________________ ________ ______ ________ ______ __________
Total labour rate for Each. say Rs: 211.75
S/N D I S C R I P T I O N.

38. Providing and laying single layer of polythene sheet 0.13 m.m
thick for water proofing as per specifiation and instructions of
Engineer Incharge.
(Unit of rate per Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
For 100 Sft.

Polythene sheet i.c 5% 105.0 Sft. 9.00 P.Sft. 945.00


wastage & overlaping.
TOTAL 945.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 94.50
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 1039.50
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
Skilled Cooly. 0.12 Nos: 250.00 P.day 30.00
Rs: 30.00
Sundries. 10.00 % 3.00
TOTAL 33.00
Contractor's profit 10.00 % 3.30
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 0.36 36.30
TOTAL (MATERIAL + LABOUR) 1075.80
Total material & labour for 100 Sft. Rs: 1075.80
Total material & labour for 1 Sft. Rs: 10.76

Chapter No. 6 491/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
Total material & labour per sft. say Rs: 10.76
S/N D I S C R I P T I O N.

39 Khaprial of cement concrete 12" * 8" *1" of approved design/


shape laid flat in 1:2 grey cement mortar over a bed of 3/4"
thick grey cement mortar 1:2.

(Unit of rate per 100 Sft.)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Tiles (12"*8"*1") 175.0 Nos: 3450.0 100 Nos: 6037.50
i/c 15% for overlapping.
Grey Cement. 1.87 Cwt. 400.00 P.Bag. 748.00

Sand. 4.70 Cft. 2425.00 % Cft. 113.98


____________________________ ________ ______ ________ ______ __________
TOTAL 6899.48
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 689.95
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 7589.42
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 1147.50
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 114.75
____________________________ ________ ______ ________ ______ __________
TOTAL 1262.25
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 126.23
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 1388.48
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 8977.90
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 8977.90

Chapter No. 6 492/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________


S/N D I S C R I P T I O N.

40. Khaprial (Manglore) Tiles 15" * 8" *1-1/2" of approved design/


shape laid flat in 1:2 grey cement mortar over a bed of 3/4"
thick grey cement mortar 1:2.

(Unit of rate per 100 Sft.)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Tiles (15"*8"*1-1/2") 140.0 Nos: 8500.01000 Nos: 1190.00
i/c 15% for overlapping.
Grey Cement. 1.87 Cwt. 400.00 P.Bag. 748.00

Sand. 4.70 Cft. 2425.00 % Cft. 113.98

____________________________ ________ ______ ________ ______ __________


TOTAL 2051.98
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 205.20
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 2257.17
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00


____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 1147.50
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 114.75
____________________________ ________ ______ ________ ______ __________
TOTAL 1262.25
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 126.23
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 1388.48
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 3645.65
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 3645.65
______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 493/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

NEW ITEMS 2002.

______ ____________________________ ________ ______ ________ ______ __________


S/N D I S C R I P T I O N.

41 Provding and fixing with bitumen felt paper of 60 Lbs over roof i/c cleaning of roof with wire
brush an removing dust, applying bitumen coat at the rate of 34 Lbs per % Sft as premix
inter coats and then laying felt papper with 10% over laps, then applying and spreading
hill sand at the rate of 1 cft for 100 sft. The cost also i/c necessary fore material, kerosene
oil, wood ete:
(Unit of rate per 100 Sft.)
______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Bitumen felt pater 60 Lbs 110.0 Sft. 22.0 P.Sft. 2420.00
i/c 10% over lapes

Bitumen. 34.0 Lbs. 86213 P.Ton 1308.6

Hill Sand 1.0 Cft. 2425 %.Cft. 24.3

Wood for fuel 0.5 Md 900 Md 450.0

Kerosino oil. 2.0 Lit 110 Lit. 220.0


TOTAL 4422.84
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 442.28
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 4865.12
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Coolie for laying & heating & 2.00 No 250.00 P.day 500.00
Spreading Sand.
TOTAL Rs: 500.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 50.00
____________________________ ________ ______ ________ ______ __________
TOTAL 550.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 55.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 605.00
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 5470.12
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 5470.12
Total material & labour for Sft. say 54.70

Chapter No. 6 494/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________


S/N D I S C R I P T I O N.

42 Provding and fixing with jute felt paper of 60 Lbs over roof i/c cleaning of roof with wire
brush an removing dust, applying bitumen coat at the rate of 34 Lbs per % Sft as premix
inter coats and then laying felt papper with 10% over laps, then applying and spreading
hill sand at the rate of 1 cft for 100 sft. The cost also i/c necessary fore material, kerosene
oil, wood ete:

(Unit of rate per 100 Sft.)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Juite felt 60 Lbs i/e 10% over Laps. 110.0 Sft 65.0 P.Sft. 7150.00

Bitumen. 34.0 Lbs. 86213.0 P.Ton. 1308.59

Hill Sand 1.00 Cft. 2425.00 %.Cft. 24.25

Wood for fuel 0.5 Md 900 P.Md 450

Kerosino oil. 2 Lit 110 P.Lit 220

____________________________ ________ ______ ________ ______ __________


TOTAL 9152.84
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 915.28
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 10068.12
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Coolie for laying & heating & 2.00 No 250.00 P.day 500.00
Spreading Sand.
TOTAL Rs: 500.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 50.00
____________________________ ________ ______ ________ ______ __________
TOTAL 550.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 55.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 605.00
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 10673.12
____________________________ ________ ______ ________ ______ __________
Total material & labour for 100 Sft. say Rs: 10673.12
Total material & labour for Sft. say 106.73

Chapter No. 6 495/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.

43 Provding & fixing false ceiling of thermopile in panels of required design and size
including frame work of Aluminum T-section hanged with nail wire to ceiling etc:
completed.

(Unit of rate per Sft.)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______________ ______ __________
Room 12x12=144
Thermofide sheet i/c 10% wastage. 158.4 Sft 50.0 P.Sft. 7920.00
12x12x1.1=158.40

Alluminum T-section i/c 10% 184.8 Rft. 8.5 P.Rft. 1570.8


wastage (panvel 2.0x2'.0)
2x7x12x1.1=184.80

Iron bars for Holding 3/4" dia. 14.6 Lbs. 3550 P.cwt 462.767857
25x3.5x0.167=14.61

Nails ,/Screw all sorts L.s 50

TOTAL 10003.57
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 1000.36
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 11003.92
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Carpenter 2.50 No 450.00 Each 1125.00

Coolie. 2.50 No 250.00Each 625.00


TOTAL Rs: 1750.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 175.00
____________________________ ________ ______ ________ ______ __________
TOTAL 1925.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 192.50
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 14.70 2117.50
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 13121.42
____________________________ ________ ______ ________ ______ __________
Total material & labour for 144 Sft. say Rs: 13121.42
Total material & labour for Sft. say Rs: 91.12

Chapter No. 6 496/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.

44 Providing & fixing plaster of paris ceiling border of 8" -10" width of specified design &
thickness i/c fixing besides ceiling with nails/ screws with jetties.

(Unit of rate per Rft.)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Plaster of paris border 7.5 Sft. 85.0 P.sft 637.50

Solignum paint 0.1 Gall 1525 P.Gall 152.50

Nails / serews. L.S 10


TOTAL 800.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 80.00
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 880.00
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Carpenter 0.15 No 450.00 P.day 67.50

Painter. 0.10 No 450.00 P.day 45.00

Coolie. 0.05 No 250.00 P.day 12.50


____________________________ ________ ______ ________ ______ __________
TOTAL Rs: 125.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 12.50
____________________________ ________ ______ ________ ______ __________
TOTAL 137.50
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 13.75
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 151.25
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 1031.25
____________________________ ________ ______ ________ ______ __________
Total material & labour for 10 Rft. say Rs: 1031.25
Total material & labour for Rft. say Rs: 103.13
______ ____________________________ ________ ______ ________ ______ __________

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 497/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.

45 Providng & fixing plaster of paris centre pieces of 2' -0 dia i/c fixing in ceiling with jetties

(Unit of rate per Each.)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Plaster of paris centre piece2'-0 dia 1.0 No 85.0 Each 85.00

Solignum paint 0.08 Gall 1525 P.Gall 122.00

Nails / serews. L.S 10


TOTAL 217.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 21.70
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 238.70
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Carpenter 0.10 No 450.00 P.day 45.00

Painter. 0.05 No 450.00 P.day 22.50

Coolie. 0.05 No 250.00 P.day 12.50

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 80.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 8.00
____________________________ ________ ______ ________ ______ __________
TOTAL 88.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 8.80
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 96.80
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 335.50
____________________________ ________ ______ ________ ______ __________
Total material & labour for Each. say Rs: 335.50

Chapter No. 6 498/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.

46 Providng & fixing plaster of paris centre pieces cover pieces triangle shape i/c fixing in
ceiling with nails / screws.

(Unit of rate per Each.)


______ ____________________________ ________ ______ ________ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____________________________ ________ ______ ________ ______ __________
Plaster of paris corner pieces 1.0 No 85.0 Each 85.00

Solignum paint 0.08 Gall 1525 P.Gall 122.00

Nails / serews. L.S 10

____________________________ ________ ______ ________ ______ __________


TOTAL 217.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 21.70
____________________________ ________ ______ ________ ______ __________
TOTAL PART " A " 238.70
____________________________ ________ ______ ________ ______ __________
(B) LABOUR
____________________________ ________ ______ ________ ______ __________
Carpenter 0.10 No 450.00 P.day 45.00

Painter. 0.05 No 450.00 P.day 22.50

Coolie. 0.05 No 250.00 P.day 12.50

____________________________ ________ ______ ________ ______ __________


TOTAL Rs: 80.00
____________________________ ________ ______ ________ ______ __________
Sundries. 10.00 % 8.00
____________________________ ________ ______ ________ ______ __________
TOTAL 88.00
____________________________ ________ ______ ________ ______ __________
Contractor's profit 10.00 % 8.80
____________________________ ________ ______ ________ ______ __________
TOTAL PART " B " 96.80
____________________________ ________ ______ ________ ______ __________
TOTAL (MATERIAL + LABOUR) 335.50
____________________________ ________ ______ ________ ______ __________
Total material & labour for Each say Rs: 335.50

______ ____________________________ ________ ______ ________ ______ __________

Chapter No. 6 499/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

FIRST FILL THIS SHEET.


FLOORING
MATERIALS RATE UNITE.

1 9"thick rubble or booken hard bricks 1500 % Cft

2 Hard Murrum or fine powdery Muru 1800 % Cft.

3 Earth 500 % Cft

4 Bhoosa 300 P.Mand

5 Cow dung 500 % Cft

6 Bricks 5000 % 0 Nos

7 Pit Sand 900 % Cft

8 Cement 400 P.bag

9 Sand 2425 % Cft.

10 Lime (Slaked 375 P.Mand.

11 Surkhi 2250 % Cft

12 Tiles 12" x 6" x 2" 5825 % 0 Nos

13 Tiles x 4- 1/2" x 1- 1/2" 4850 % 0 Nos

14 Cement tiles 8" x 8" x 3/4" 3250 % Nos.

15 Cement tiles 11-15/16 x 11 -15/16 x 2525 % Nos.

16 Cement tiles 8- 15/16 x 8- 15/16 x 3 1870 % Nos

17 Cement tiles 5- x 15/16 x 5 - 15/16 1250 % Nos

18 Coloured Cement tiles 8" x 8" x 3/4" 3250 % Nos

19 Pigment 62 P.Lbs

20 Shingle 3075 % Cft

21 Wax Polish 300 Lbs

22 Dressed Stone 2' x 2' x 2" 500 Each

23 Dressed Stone 2' x 2' x 3" 475 Each

24 Bitumen 86213.00 P. Cwt.

Chapter No. 7 500/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
25 Steem Coal 4000 P.Ton

26 Marble Chips 375 P.Cwt

27 Carborandum Stone 560 Each

28 Tartane acid (White) 80 P.Lb

29 Tile glazed 6" x 6" x 1/4" 625 P.daz

30 White Cement 700 P. bag

31 Coloured glazed tile 6" x 6" x 1/4" 625 P.bag

32 Caustic Soda 45 Lbs.

33 Hassien cloth 60 P.Mand

34 White marble slap 3/4" th dressed 400 P.S


upto 4.0'

35 Turpentine Oil. 450 P.gal

36 Gum and Fum Resin 175 P.Lb

37 White marble slab 1" th dressed 450 P.Sft


upto 4'

38 Shisham wood (1st quality) 2300 P.Cft

39 Deadar wood (1st quality) 4500 P.Cft

40 Fire wood 900 P.Mand

41 Brass Screw 2" 185 % Nos

42 Sand paper sheet 150 P.doz

43 Deodar wood (2nd quality) 4000 P.Cft

44 Teak wood 2900 P.Cft

45 Primer Coat 1800 P.gal

46 Kiker wood 1400 P.Cft

47 Cement tiles 8" x 8" x 15/16" 2000 % 0 Nos

48 Mosaic tiles 8" x 8" x 1" 3350 % 0 Nos

49 Glazed tiles 6" x 6" x 1/4" 625 P.daz

Chapter No. 7 501/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
50 Mosaic tiles 8" x 8" x 1' of gray cem 3350 % 0 Nos

51 Mosic tiles of white cement 8" x 8" x 3800 % Nos

52 Mosic tiles of white cement 8" x 8" 1 4425 % Nos


with khapcha

53 Mosic tile of gray cement 12" x 12" 3550 % Nos

54 Mosic tile of gray cement with khap 4500 % Nos


12" x 12" x 1"

55 Mosic tiles of white cement with kh 6000 % Nos


12' x 12' x1

56 Mosic chequer tiles 8" x 8" x 1-1/4" 525 P.daz

57 Mosic chequer tiles 11" x 8" x 1-1/4 180 P.doz

58 Coloured cement tiles (Pattern ) 6100 % Nos


12" x 12" 1"

59 Hala Pattern glazed tile 6" x 6" x1/4 1050 P.doz

60 %Sft 1275 P.daz

61 Rubber tiles 12" x 12" x 1/8" (PVC) 125 Each

62 Adhesine mixture 1100 P.gal

63 Mosic Marble tiles 1" th 3800 % Nos

64 Marble tiles 8" x 4" or 6" x 4" 70 P.Sft

65 Split tiles 1/4 th Matt glazed 153 P.Sft

66 Mosaic tile 12*12*1 in white cement 4400 nos


ew
67 chemical polish 525 lbs

68 paving block natural colour 60mm 150 psft

69 paving block pigmented 60mm 170 psft

70 paving block natural colour 80mm 170 psft

71 paving block pigmented 80mm 190 psft

72 glass strip 1" wide 80 psft

LABOUR. RATE UNITE

Chapter No. 7 502/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
1 Masson , Carpenter, 450 P.day

2 Coolies. 250 P.day

3 Bahishti , Skilled Coolies. 250 P.day.

F L O O R I N G.
================
I Rates for all finished works include the removal of the surplus
debris un-used material and by-products.
II For handling of all types of materials for short leads including
carriage upto 3 chains nothing is to be paid extra where
handling and carriage involves an extra lead beyond 3 chains
carriage for whole of the distance should be paid.
S/N D E S C R I P T I O N.

1. Laying Murum flooring consisting of 1" layer of fine powdery or


flakey variety of Murum laid over 6" good hard layer of Murum
spread over 9" thick sub-base comprising of hand packed rubble
or broken bricks properly watered and rammed provided over well
rammed earth.
(Unit of rate per 100 Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
9" thick rubble or broken 80.00 Cft. 1500.00 % Cft. 1200.00
hard bricks( Q.S )

6" hard murum. 55.00 Cft. 1800.00 % Cft. 990.00

1" fine powdery murum. 9.00 Cft. 1800.00 % Cft. 162.00


TOTAL 2352.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 235.20
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 2587.20
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 0.50 Nos: 450.00 P.day. 225.00

Coolies. 3.00 Nos: 250.00 P.day. 750.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 1100.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 110.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 1210.00
___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 503/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
Contractor's profit 10.00 % 121.00
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1331.00
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 3918.20
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 3918.20

S/N D E S C R I P T I O N.

2. Earth flooring consisting of 6" thick consolidated layer of


moistured earth including ramming.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Earth (loose measured) 50.00 Cft. 500.00 % Cft. 250.00

___________________________ ________ ____ ________ _______ _____________


TOTAL 250.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 25.00
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 275.00
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 0.125 Nos: 450.00 P.day. 56.25

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 368.75
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 36.88
___________________________ ________ ____ ________ _______ _____________
TOTAL 405.63
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 40.56
___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 504/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
TOTAL PART " B " 446.19
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 721.19
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 721.19

S/N D E S C R I P T I O N.

3. Mud flooring consisting of 6" thick consolidated layer of


moistened earth and finished off with 1" mud plaster and gobri
leeping.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Earth for filling. 50.00 Cft. 500.00 % Cft. 250.00

Earth for mud plaster. 10.00 Cft. 500.00 % Cft. 50.00

Bhoosa. 34.00 Lbs. 300.00 P.Mand. 124.39

Fine clay for gobri leeping. 0.75 Cft. 500.00 % Cft. 3.75

Cow dung. 0.75 Cft. 500.00 % Cft. 3.75

TOTAL 431.89
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 43.19
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 475.08
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 0.250 Nos: 450.00 P.day. 112.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 675.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 67.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 742.50

Chapter No. 7 505/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 74.25
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 816.75
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 1291.83
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 1291.83

Chapter No. 7 506/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___ ___________________________ ________ ____ ________ _______ _____________
S/N D E S C R I P T I O N.

4. Dry brick paving laid flat, grouted including preparation of bed


by watering ramming and bringing the same to proper camber by
1/2" mud plaster.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Brick 9" size. 350.0 Nos: 5000.00 %0 Nos: 1750.00

Pit Sand. 5.00 Cft. 900.00 % Cft. 45.00

Earth for 1/2" mud plaster. 6.00 Cft. 500.00 % Cft. 30.00

___________________________ ________ ____ ________ _______ _____________


TOTAL 1825.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 182.50
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 2007.50
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 0.50 Nos: 450.00 P.day. 225.00

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.083 Nos: 250.00 P.day. 20.75

TOTAL Rs: 495.75


___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 49.58
___________________________ ________ ____ ________ _______ _____________
TOTAL 545.33
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 54.53
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 599.86
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 2607.36
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 2607.36
___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 507/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ ___________________________ ________ ____ ________ _______ _____________

S/N D E S C R I P T I O N.

5. Dry brick on edge paving sand grouted including preparation of


bed by watering, ramming and bringing the same to proper camber
by 1/2" thick mud plaster.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Brick 9" size. 525.0 Nos: 5000.00 %0 Nos: 2625.00

Pit Sand. 6.00 Cft. 900.00 % Cft. 54.00

Earth for 1/2" mud plaster. 6.00 Cft. 500.00 % Cft. 30.00
TOTAL 2709.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 270.90
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 2979.90
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 0.67 Nos: 450.00 P.day. 301.50

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Bahishti. 0.083 Nos: 250.00 P.day. 20.75

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 697.25
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 69.73
___________________________ ________ ____ ________ _______ _____________
TOTAL 766.98
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 76.70
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 843.67
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 3823.57

Chapter No. 7 508/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 3823.57
S/N D E S C R I P T I O N.

6. Grouting 4-1/2" dry brick work with cement mortar ratio 1:5.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Cement. 0.70 Cwt. 400.00 P.Bag. 280.00

Sand. 4.50 Cft. 2425.00 % Cft. 109.13

___________________________ ________ ____ ________ _______ _____________


TOTAL 389.13
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 38.91
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 428.04
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 0.50 Nos: 450.00 P.day. 225.00

Coolies. 0.50 Nos: 250.00 P.day. 125.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 475.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 47.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 522.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 52.25
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 574.75
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 1002.79
___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 509/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
Total material & labour for 100 Sft. say Rs: 1002.79

Chapter No. 7 510/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

7. Flat brick flooring laid in 1:6 cement mortar over a bed of 3/4"
thick cement mortar 1:6.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Brick 9" size. 350.0 Nos: 5000.00 %0 Nos: 1750.00

Cement for laying. 0.50 Cwt. 400.00 P.Bag. 200.00

Cement for bedding mortar. 0.80 Cwt. 400.00 P.Bag. 320.00

Sand for laying. 4.00 Cft. 2425.00 % Cft. 97.00

Sand for bedding mortar. 6.00 Cft. 2425.00 % Cft. 145.50

___________________________ ________ ____ ________ _______ _____________


TOTAL 2512.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 251.25
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 2763.75
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 837.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 83.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 921.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 92.13
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1013.38
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 3777.13
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 3777.13

Chapter No. 7 511/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

8. Flat brick flooring laid in lime mortar over a bed of 3/4"


thick lime bedding mortar 1:1:1 (Lime, Surkhi and Sand)

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Bricks 9" size. 350.0 Nos: 5000.00 %0 Nos: 1750.00

Lime slaked (ground) 1.80 Mand. 375.00 P.Mand 675.00

Surkhi. 4.50 Cft. 2250.00 % Cft. 101.25

Sand. 4.50 Cft. 2425.00 % Cft. 109.13

TOTAL 2635.38
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 263.54
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 2898.91
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

TOTAL Rs: 837.50


___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 83.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 921.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 92.13
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1013.38
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 3912.29
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 3912.29

Chapter No. 7 512/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___ ___________________________ ________ ____ ________ _______ _____________

___ ___________________________ ________ ____ ________ _______ _____________


S/N D E S C R I P T I O N.

9. Brick on edge flooring laid in 1:6 cement mortar over a bed of


3/4" thick cement mortar 1:6.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Brick 9" size. 525.0 Nos: 5000.00 %0 Nos: 2625.00

Cement for laying. 0.85 Cwt. 400.00 P.Bag. 340.00

Cement for bedding mortar. 0.79 Cwt. 400.00 P.Bag. 316.00

Sand for laying. 7.00 Cft. 2425.00 % Cft. 169.75

Sand for bedding mortar. 6.00 Cft. 2425.00 % Cft. 145.50

___________________________ ________ ____ ________ _______ _____________


TOTAL 3596.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 359.63
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 3955.88
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 1075.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 107.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 1182.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 118.25
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1300.75
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 5256.63

Chapter No. 7 513/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 5256.63
S/N D E S C R I P T I O N.

10. Brick on edge flooring laid in lime mortar over a bed of 3/4"
thick lime surkhi mortar 1:2 ratio.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Bricks 9" size. 525.0 Nos: 5000.00 %0 Nos: 2625.00

Lime slaked (ground) 2.25 Mand. 375.00 P.Mand 843.75

Surkhi. 11.20 Cft. 2250.00 % Cft. 252.00


TOTAL 3720.75
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 372.08
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 4092.83
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1075.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 107.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 1182.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 118.25
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1300.75
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 5393.58
___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 514/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
Total material & labour for 100 Sft. say Rs: 5393.58

Chapter No. 7 515/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

11. Tile size (12"*6"*2") laid in 1:6 cement mortar over a bed of
3/4" thick cement mortar 1:6.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Tiles 12"*6"*2" 210.0 Nos: 5825.0 %0 Nos: 1223.25

Cement. 1.10 Cwt. 400.00 P.Bag. 440.00

Sand. 8.00 Cft. 2425.00 % Cft. 194.00


TOTAL 1857.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 185.73
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 2042.98
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 837.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 83.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 921.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 92.13
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1013.38
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 3056.35
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 3056.35

Chapter No. 7 516/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

12. Tile size (9"*4"-1/2*1"-1/2) laid flat in 1:3 cement mortar over a bed of
3/4" thick cement mortar 1:6.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Tile size(9"*4"-1/2*1"-1/2) 350.0 Nos: 4850.0 %0 Nos: 1697.50

Cement. 1.40 Cwt. 400.00 P.Bag. 560.00

Sand. 12.00 Cft. 2425.00 % Cft. 291.00

TOTAL 2548.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 254.85
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 2803.35
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 950.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 95.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 1045.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 104.50
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1149.50
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 3952.85
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 3952.85

Chapter No. 7 517/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

13. Cement tiles size (8"*8"*3/4") laid flat in 1:2 cement mortar
over a bed of 3/4" thick cement mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Cement tiles (8"*8"*3/4") 240.0 Nos: 3250.00 % Nos: 7800.00

Cement. 1.87 Cwt. 400.00 P.Bag. 748.00

Sand. 4.70 Cft. 2425.00 % Cft. 113.98

___________________________ ________ ____ ________ _______ _____________


TOTAL 8661.98
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 866.20
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 9528.17
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 10916.65
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 10916.65
___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 518/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

14. Cement concrete tiles laid flat in 1:2 cement mortar over a bed
of 3/4" thick cement mortar 1:2.

(a) 11-15"/16 * 11-15"/16 * 1"

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Cement concrete tiles. 105.0 Nos: 2525.00 % Nos: 2651.25

Cement. 1.86 Cwt. 400.00 P.Bag. 744.00

Sand. 4.67 Cft. 2425.00 % Cft. 113.25


___________________________ ________ ____ ________ _______ _____________
TOTAL 3508.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 350.85
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 3859.35
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 5247.82
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 5247.82
___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 519/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___ ___________________________ ________ ____ ________ _______ _____________
S/N D E S C R I P T I O N.

14. Cement concrete tiles laid flat in 1:2 cement mortar over a bed
of 3/4" thick cement mortar 1:2.

(b) 8-15"/16 * 8-15"/16 * 3"/4

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Cement concrete tiles. 186.0 Nos: 1870.00 % Nos: 3478.20

Cement. 1.85 Cwt. 400.00 P.Bag. 740.00

Sand. 4.67 Cft. 2425.00 % Cft. 113.25

TOTAL 4331.45
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 433.14
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 4764.59
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 6153.07
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 6153.07
___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 520/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

14. Cement concrete tiles laid flat in 1:2 cement mortar over a bed
of 3/4" thick cement mortar 1:2.

(c) 5-15"/16 * 5-15"/16 * 3"/4

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Cement concrete tiles. 420.0 Nos: 1250.00 % Nos: 5250.00

Cement. 1.90 Cwt. 400.00 P.Bag. 760.00

Sand. 4.74 Cft. 2425.00 % Cft. 114.95

___________________________ ________ ____ ________ _______ _____________


TOTAL 6124.95
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 612.49
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 6737.44
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.50 Nos: 450.00 P.day. 675.00

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1260.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 126.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 1386.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 138.60
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1524.60
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 8262.04
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 8262.04
___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 521/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ ___________________________ ________ ____ ________ _______ _____________


S/N D E S C R I P T I O N.

15. Coloured cement tiles(8" * 8" * 3"/4) of approved dark shade


laid flat in 1:2 cement mortar over a bed of 3/4" thick cement
mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Tiles(8" * 8" * 3"/4) 240.0 Nos: 3250.00 % Nos: 7800.00

Cement. 1.87 Cwt. 400.00 P.Bag. 748.00

Sand. 4.70 Cft. 2425.00 % Cft. 113.98

Pigment. 0.67 Lb 62.00 P.Lb 41.54

TOTAL 8703.52
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 870.35
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 9573.87
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 10962.34
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 10962.34

Chapter No. 7 522/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

16. Providing and laying 1" thick topping of cement concrete (1:2:4)
including surface finishing & dividing into panels.

(a) 1" thick.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________

Cement. 1.50 Cwt. 400.00 P.Bag. 600.00

Sand. 3.70 Cft. 2425.00 % Cft. 89.73

Shingle. 7.40 Cft. 3075.00 % Cft. 227.55

Form work. L.S % Sft. 20.00


___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % #REF!
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " #REF!
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 0.50 Nos: 250.00 P.day. 125.00

Bahishti. 0.10 Nos: 250.00 P.day. 25.00

Carpenter. 0.25 Nos: 450.00 P.day. 112.50

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 712.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 71.25
___________________________ ________ ____ ________ _______ _____________
TOTAL 783.75
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 78.38
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 862.13
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) #REF!
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: #REF!

Chapter No. 7 523/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

16. Providing and laying 1" thick topping of cement concrete (1:2:4)
including surface finishing & dividing into panels.

(b) 1"-1/2 thick.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________

Cement. 2.20 Cwt. 400.00 P.Bag. 880.00

Sand. 5.50 Cft. 2425.00 % Cft. 133.38

Shingle. 11.00 Cft. 3075.00 % Cft. 338.25

Form work. L.S % Sft. 15.00


TOTAL 1366.63
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 136.66
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 1503.29
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.15 Nos: 250.00 P.day. 37.50

Carpenter. 0.25 Nos: 450.00 P.day. 112.50

TOTAL Rs: 850.00


___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 85.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 935.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 93.50
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1028.50
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 2531.79
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 2531.79

Chapter No. 7 524/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

16. Providing and laying 1" thick topping of cement concrete (1:2:4)
including surface finishing & dividing into panels.

(c) 2" thick.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________

Cement. 3.00 Cwt. 400.00 P.Bag. 1200.00

Sand. 7.40 Cft. 2425.00 % Cft. 179.45

Shingle. 14.70 Cft. 3075.00 % Cft. 452.03

Form work. L.S % Sft. 30.00


___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % #REF!
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " #REF!
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Bahishti. 0.20 Nos: 250.00 P.day. 50.00

Carpenter. 0.25 Nos: 450.00 P.day. 112.50

TOTAL Rs: 987.50


___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 98.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1086.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 108.63
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1194.88
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) #REF!
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: #REF!

Chapter No. 7 525/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

16. Providing and laying 1" thick topping of cement concrete (1:2:4)
including surface finishing & dividing into panels.

(d) 3" thick.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________

Cement. 4.40 Cwt. 400.00 P.Bag. 1760.00

Sand. 11.00 Cft. 2425.00 % Cft. 266.75

Shingle. 22.00 Cft. 3075.00 % Cft. 676.50

Form work. L.S % Sft. 35.00

TOTAL 2738.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 273.83
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 3012.08
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

Carpenter. 0.25 Nos: 450.00 P.day. 112.50

TOTAL Rs: 1125.00


___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 112.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 1237.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 123.75
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1361.25
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 4373.33
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 4373.33

Chapter No. 7 526/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

17. Add extra in cement concrete floor topping, if finished with


pigment and polishing.
(Unit of rate per 100 Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________

Grey cement 1/16" thick for 0.40 Cwt. 400.00 P.Bag. 160.00
polishing.
Pigment. 4.50 Lbs. 62.00 P.Lb 279.00

Wax polish. 0.50 Lbs. 300.00 P.Lb 150.00

___________________________ ________ ____ ________ _______ _____________


TOTAL 589.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 58.90
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 647.90
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 0.50 Nos: 450.00 P.day. 225.00

Coolies. 0.50 Nos: 250.00 P.day. 125.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 350.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 35.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 385.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 38.50
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 423.50
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 1071.40
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 1071.40

Chapter No. 7 527/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___ ___________________________ ________ ____ ________ _______ _____________

___ ___________________________ ________ ____ ________ _______ _____________


S/N D E S C R I P T I O N.

18. Extra labour for each storey above ground for mosaic conglomerate
or tiles, stone and wooden floor.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Cooly for carraige of 0.75 Nos: 250.00 P.day. 187.50
material.
___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 187.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 18.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 206.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 20.63
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 226.88
___________________________ ________ ____ ________ _______ _____________
Labour rate for 100 Sft. say Rs: 226.88

Chapter No. 7 528/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

19. Flag stone flooring laid in lime mortar 1:2 over 3/4" bedding
mortar in plateforms and floors etc.

(a) 2" thick.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Dressed stones 2' * 2' 25.0 Nos: 500.00 Each. 12500.00

Lime slaked (ground) 1.30 Mand. 375.00 P.Mand 487.50

Surkhi. 6.50 Cft. 2250.00 % Cft. 146.25

Steel and charcoal. L.S % Sft. 40.00

TOTAL 13173.75
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 1317.38
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 14491.13
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 2.50 Nos: 450.00 P.day. 1125.00

Coolies. 3.00 Nos: 250.00 P.day. 750.00

Bahishti. 0.12 Nos: 250.00 P.day. 30.00

Black-smith. 0.10 Nos: 450.00 P.day. 45.00

Bellow man. 0.10 Nos: 250.00 P.day. 25.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1975.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 197.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 2172.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 217.25
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 2389.75
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 16880.88

Chapter No. 7 529/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 16880.88
S/N D E S C R I P T I O N.

19. Flag stone flooring laid in lime mortar 1:2 over 3/4" bedding
mortar in plateforms and floors etc.

(b) 3" thick.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Dressed stones 2' * 2' * 3" 25.0 Nos: 475.00 Each. 11875.00

Lime slaked (ground) 1.40 Mand. 375.00 P.Mand 525.00

Surkhi. 7.00 Cft. 2250.00 % Cft. 157.50

Steel and charcoal. L.S % Sft. 55.00


___________________________ ________ ____ ________ _______ _____________
TOTAL 12612.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 1261.25
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 13873.75
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 2.50 Nos: 450.00 P.day. 1125.00

Coolies. 3.00 Nos: 250.00 P.day. 750.00

Bahishti. 0.12 Nos: 250.00 P.day. 30.00

Black-smith. 0.10 Nos: 450.00 P.day. 45.00

Bellow man. 0.10 Nos: 250.00 P.day. 25.00


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 1975.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 197.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 2172.50
Contractor's profit %
10.00 217.25
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 2389.75
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 16263.50
___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 530/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
Total material & labour for 100 Sft. say Rs: 16263.50

Chapter No. 7 531/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

20 Asphalt flooring including preparation of proper base,re-melting,


setting it and finishing complete.

(a) 1" thick (topping)

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Asphalt. Bitument. 2.4 Cwt. 86213.00 P.ton 10173.13

Steam coal. 0.50 Mand. 4000.00 P.Ton 15.61

Fine aggregate 9.00 Cft. 2425.00 % Cft. 218.25

Form work. L.S 15.00


TOTAL 10421.99
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 1042.20
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 11464.19
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason for setting out and 0.25 Nos: 450.00 P.day. 112.50
laying.

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Carpenter. 0.25 Nos: 450.00 P.day. 112.50

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 725.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 72.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 797.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 79.75
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 877.25
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 12341.44
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 12341.44
___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 532/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ ___________________________ ________ ____ ________ _______ _____________


S/N D E S C R I P T I O N.

20 Asphalt flooring including preparation of proper base,re-melting,


setting it and finishing complete.

(b) 1/2" thick (topping)

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Asphalt. 1.2 Cwt. 86213.00 P.ton 5172.78

Steam coal. 0.25 Mand. 4000.00 P.Ton 7.80

Fine aggregate. 4.50 Cft. 2425.00 % Cft. 109.13

Form work. L.S % Sft. 15.00


TOTAL 5304.71
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 530.47
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 5835.18
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason for setting out and 0.20 Nos: 450.00 P.day. 90.00
laying.

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Carpenter. 0.25 Nos: 450.00 P.day. 112.50


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 577.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 57.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 635.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 63.53
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 698.78
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 6533.95
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 6533.95
___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 533/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___ ___________________________ ________ ____ ________ _______ _____________
S/N D E S C R I P T I O N.

20 Asphalt flooring including preparation of proper base,re-melting,


setting it and finishing complete.

(c) 1/4" thick (topping)

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Asphalt. 0.6 Cwt. 86213.00 P.ton 2586.39

Steam coal. 0.25 Mand. 4000.00 P.Ton 7.80

Fine aggregate. 2.50 Cft. 350.00 % Cft. 8.75

Form work. L.S 15.00


___________________________ ________ ____ ________ _______ _____________
TOTAL 2617.94
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 261.79
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 2879.73
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason for setting out and 0.17 Nos: 450.00 P.day. 76.50
laying.

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Carpenter. 0.25 Nos: 450.00 P.day. 112.50


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 439.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 43.90
___________________________ ________ ____ ________ _______ _____________
TOTAL 482.90
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 48.29
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 531.19
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 3410.92
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 3410.92

Chapter No. 7 534/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___ ___________________________ ________ ____ ________ _______ _____________
S/N D E S C R I P T I O N.

21. 1-1/2" thick mosaic flooring consisting of 3/8" mosaic topping


of one part of grey cement to two parts of marble chips over 1"
thick flooring of 1:2:4 cement concree including rubbing and
polishing complete.
(Unit of rate per 100 Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Cement for 3/8" thick 1.5 Cwt. 400.00 P.Bag 600.00
topping.
Marble chips. 3.00 Cwt. 375.00 P.Cwt. 1125.00

Corborandum stones. 3.00 Nos: 560.00 Each. 1680.00

Wax polish. 0.50 Lbs. 300.00 P.Lb 150.00

Tartaric acid. 0.34 Lbs. 80.00 P.Lb 27.20

Linen cotton wood and L.S 35.00


cloth, form work.
TOTAL 3617.20
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 361.72
___________________________ ________ ____ ________ _______ _____________
Add for 1" thick C.Concrete #REF!
topping 1:2:4 as per item
No:16(a)
TOTAL PART " A " #REF!
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason for laying. 2.00 Nos: 450.00 P.day. 900.00

Coolies. 1.25 Nos: 250.00 P.day. 312.50

Coolies skilled for rubbing 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 2900.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 290.00
TOTAL 3190.00
Contractor's profit 10.00 % 319.00
TOTAL PART " B " 3509.00
TOTAL (MATERIAL + LABOUR) #REF!
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: #REF!

Chapter No. 7 535/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

22. 1-1/2" thick mosaic flooring consisting of 1/2" mosaic topping


of one part of grey cement to two parts of marble chips over 1"
thick flooring of 1:2:4 cement concree including rubbing and
polishing complete.
(Unit of rate per 100 Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Cement for 1/2" thick 1.75 Cwt. 400.00 P.Bag 700.00
topping.
Marble chips. 4.16 Cwt. 375.00 P.Cwt. 1560.00

Corborandum stones. 3.00 Nos: 560.00 Each. 1680.00

Wax polish. 0.50 Lbs. 300.00 P.Lb 150.00

Tartaric acid. 0.34 Lbs. 80.00 P.Lb 27.20

Linen cotton wood and L.S 35.00


cloth form work.
TOTAL 4152.20
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 415.22
___________________________ ________ ____ ________ _______ _____________
Add for 1" thick C.Concrete #REF!
topping 1:2:4 as per item
No:16(a)
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " #REF!
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason for laying. 2.00 Nos: 450.00 P.day. 900.00

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Coolies skilled for rubbing 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 0.80 Nos: 250.00 P.day. 200.00


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 2975.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 297.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 3272.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 327.25
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 3599.75
___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 536/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
TOTAL (MATERIAL + LABOUR) #REF!
Total material & labour for 100 Sft. say Rs: #REF!
___ ___________________________ ________ ____ ________ _______ _____________

___ ___________________________ ________ ____ ________ _______ _____________


S/N D E S C R I P T I O N.

23. Laying flooring of mosaic marble chips tiles of approved shade


including finishing complete.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mason 1.50 Nos: 450.00 P.day. 675.00

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00

Extra Labour.

Mason 0.34 Nos: 450.00 P.day. 153.00

Coolies. 2.00 Nos: 250.00 P.day. 500.00


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 1913.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 191.30
___________________________ ________ ____ ________ _______ _____________
TOTAL 2104.30
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 210.43
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 2314.73
___________________________ ________ ____ ________ _______ _____________
Labour rate for 100 Sft. say Rs: 2314.73
___ ___________________________ ________ ____ ________ _______ _____________

___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 537/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

24. Laying flooring of approved white glazed tile 1/4" thick in


white cement 1:2 over 3/4" thick cement mortar 1:2 complete.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Tile glazed 6"*6"*1/4" 420.0 Nos: 625.0 P.doz 21875.00
including 5% breakage.(S.Q)
White Cement for laying. 0.10 Cwt. 700.00 P.Bag. 70.00

Grey Cement for bed. 2.16 Cwt. 400.00 P.Bag. 864.00

Sand. 5.20 Cft. 2425.00 % Cft. 126.10

___________________________ ________ ____ ________ _______ _____________


TOTAL 22935.10
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 2293.51
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 25228.61
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason for laying. 2.00 Nos: 450.00 P.day. 900.00

Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 2025.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 202.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 2227.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 222.75
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 2450.25
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 27678.86
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 27678.86
___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 538/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

25. Laying flooring of approved coloured glazed tile 1/4" thick in


white cement 1:2 over 3/4" thick cement mortar 1:2 complete.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Coloured glazed tiles 6"*6" 420.0 Nos: 625.0 P.doz 21875.00
*1/4" including 5% breakage.

White Cement for laying. 0.10 Cwt. 700.00 P.Bag. 70.00

Grey Cement for bed. 2.16 Cwt. 400.00 P.Bag. 864.00

Sand. 5.20 Cft. 2425.00 % Cft. 126.10

Pigment. 1.00 Lbs. 62.00 P.Lb 62.00


TOTAL 4212.00 22997.10
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 2299.71
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 4633.20 25296.81
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason for laying. 2.00 Nos: 450.00 P.day. 900.00

Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


TOTAL 950.00 Rs: 2025.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 202.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 1045.00 2227.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 222.75
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1149.50 2450.25
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 5782.70 27747.06
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say 10415.90 Rs: 27747.06
___ ___________________________ ________ ____ ________ _______ _____________

___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 539/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

26. Rubbing and polishing old mosaic floor.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Corborandum stones. 0.50 Nos: 560.00 Each. 280.00

Wax polish. 0.75 Lbs. 300.00 P.Lb 225.00

Tartaric acid. 0.34 Lbs. 80.00 P.Lb 27.20

Linen cotton wood and L.S 35.00


cloth.
___________________________ ________ ____ ________ _______ _____________
TOTAL 567.20
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 56.72
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 623.92
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Coolies. 1.00 Nos: 250.00 P.day. 250.00

Coolies skilled for rubbing 1.00 Nos: 250.00 P.day. 250.00


& polishing.
___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 500.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 50.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 550.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 55.00
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 605.00
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 1228.92
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 1228.92
___ ___________________________ ________ ____ ________ _______ _____________

___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 540/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

27. Cleaning and washing mosaic or marble floor with caustic soda
mixture.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Caustic soda. 1.00 Lbs. 45.00 P.Lb 45.00

Hassien cloth. 0.50 Mtr: 60.00 P.Meter 30.00

___________________________ ________ ____ ________ _______ _____________


TOTAL 75.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 7.50
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 82.50
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Coolies. 0.25 Nos: 250.00 P.day. 62.50

Bahishti. 0.12 Nos: 250.00 P.day. 30.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 92.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 9.25
___________________________ ________ ____ ________ _______ _____________
TOTAL 101.75
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 10.18
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 111.93
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 194.43
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 194.43
___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 541/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

28. Laying white marble flooring fine dressed on the surface without
windings set in lime putty laid over 3/4" thick lime mortar 1:2
including rubbing and polishing of the joints.
(a) 3/4" thick flooring.
(Unit of rate per Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
White marble slab 3/4" 105.0 Nos: 400.00 P.Sft. 42000.00
thick dressed upto 4 Ft.

Lime. 1.00 Mand. 375.00 P.Mand. 375.00

Surkhi. 5.00 Cft. 2250.00 % Cft. 112.50

Lime for making putty. 0.40 Mand. 375.00 P.Mand. 150.00

Turpentine oil. 0.625 Galn 450.00 P.Gallon. 281.25

Gum and Gum Resin. 2.00 Lbs. 175.00 P.Lb 350.00

Corborandum stones. 7.00 Nos: 560.00 Each. 3920.00


TOTAL 47188.75
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 4718.88
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 51907.63
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 5.00 Nos: 450.00 P.day. 2250.00

Coolies. 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 1.00 Nos: 250.00 P.day. 250.00


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 4000.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 400.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 4400.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 440.00
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 48.40 4840.00
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 56747.63
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 56747.63

Chapter No. 7 542/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
Total material & labour for one Sft. Rs: 567.48
Total material & labour per Sft. say Rs: 567.48
___ ___________________________ ________ ____ ________ _______ _____________
S/N D E S C R I P T I O N.
28. Laying white marble flooring fine dressed on the surface without
windings set in lime putty laid over 3/4" thick lime mortar 1:2
including rubbing and polishing of the joints.
(b) 1" thick flooring.
(Unit of rate per Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
White marble slab 1" 105.0 Nos: 400.00 P.Sft. 42000.00
thick dressed upto 4 Ft.

Lime for making putty. 0.40 Mand. 375.00 P.Mand. 150.00

Cement. 1.90 Cwt. 400.00 P.bag. 760.00

Sand. 5.00 Cft. 2425.00 % Cft. 121.25

Turpentine oil. 0.500 Galn 450.00 P.Gallon. 225.00

Gum and Gum Resin. 2.00 Lbs. 175.00 P.Lb 350.00

Corborandum stones. 7.00 Nos: Each.


560.00 3920.00
TOTAL Each.
4785.00 47526.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 4752.63
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 5263.50 52278.88
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 5.00 Nos: 450.00 P.day. 2250.00

Coolies. 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 1.00 Nos: 250.00 P.day. 250.00

TOTAL 950.00 Rs: 4000.00


___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 400.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 95.00 4400.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 440.00
TOTAL PART " B " 104.50 48.40 4840.00
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 5368.00 57118.88
Total material & labour for 100 Sft. 5368.00 Rs: 57118.88

Chapter No. 7 543/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
Total material & labour for one Sft. 53.68 Rs: 571.19

Chapter No. 7 544/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.
29. Shisham wood boarding or strips flooring 3/4" thick (sawn to
required sizes) and tongued and grooved or splayed rebated fixed
with brass screws on deodar wood battens 1-1/2" * 2" placed at
12" centre to centre including two coats of bitumen laid hot on
the base ( FIRST QUALITY )
(Unit of rate per 100 Sft.)
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Shisham wood = 100 * 3/4" * 1/12" = 6.25 Cft.
Shisham wooden rebates 5% = 0.31 Cft.
Total = 6.56 Cft.
Add wastage 75% = 4.92 Cft.
---------------------------------------------- -------------- -------- ------------- ------------ ----------------------
G.Total = 11.48 Cft.
---------------------------------------------- -------------- -------- ------------- ------------ ----------------------
Deodar wood battens = 11 * 10'*1/8'*1/6' = 2.29 Cft.
Add wastage 50% = 1.15 Cft.
---------------------------------------------- -------------- -------- ------------- ------------ ----------------------
G.Total = 3.44 Cft.
___________________________ ________ ____ ________ _______ _____________
Shisham wood.(ist quality) 11.48 Cft. 2300.00 P.Cft. 26404.00
Deodar wood ( First Quality ) 3.44 Cft. 4500.00 P.Cft. 15480.00
Bitumen. 35.00 Lbs. 86213.0 P.Ton. 1347.08
Fire wood. 0.125 Mand 900.00 P.Mand. 112.50
Brass screws 2". 7.00 Doz: 185.00 % Nos: 155.40
Sand paper sheet. 1.50 Doz: 150.00 P.doz 225.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 43723.98
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 4372.40
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 48096.38
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Carpenters. 10.00 Nos: 450.00 P.day. 4500.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 5750.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 575.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 6325.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 632.50
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 6957.50
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 55053.88

Chapter No. 7 545/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 55053.88
S/N D E S C R I P T I O N.
30. Deodar wood boarding or strips flooring 3/4" thick (sawn to
required sizes) and tongued and grooved or splayed rebated fixed
with brass screws on deodar wood battens 1-1/2" * 2" placed at
12" centre to centre including two coats of bitumen laid hot on
the base.
(Unit of rate per 100 Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Deodar wood planks = 100 * 3/4" * 1/12" = 6.25 Cft.
Deodar wooden rebates 5% = 0.31 Cft.
Total = 6.56 Cft.
Deodar wood battens = 11 * 10'*1/8'*1/6' = 2.29 Cft.
---------------------------------------------- -------------- -------- ------------- ------------ ----------------------
Total = 8.85 Cft.
---------------------------------------------- -------------- -------- ------------- ------------ ----------------------
Add wastage 50% = 4.43 Cft.
---------------------------------------------- -------------- -------- ------------- ------------ ----------------------
G.Total = 13.28 Cft.
___________________________ ________ ____ ________ _______ _____________
Deodar wood ( Second Quality ) 13.28 Cft. 4000.00 P.Cft. 53120.00

Bitumen. 34.00 Lbs. 86213.0 P.Ton. 1308.59

Fire wood. 0.125 Mand 900.00 P.Mand. 112.50

Brass screws 2". 7.00 Doz: 185.00 % Nos: 155.40

Sand paper sheet. 1.00 Doz: P.doz150.00 150.00


___________________________ ________ ____ ________ _______ _____________
TOTAL 54846.49
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 5484.65
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 60331.14
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Carpenters. 6.00 Nos: 450.00 P.day. 2700.00
Coolies. 6.00 Nos: 250.00 P.day. 1500.00
___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 4200.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 420.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 4620.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 462.00

Chapter No. 7 546/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 5082.00
TOTAL (MATERIAL + LABOUR) 65413.14
Total material & labour for 100 Sft. Rs: 65413.14
S/N D E S C R I P T I O N.
31. Teak wood boarding or strips flooring 1/2" thick (sawn to
required sizes) and tongued and grooved or splayed rebated fixed
with brass screws on deodar wood battens 1-1/2" * 2" placed at
12" centre to centre including two coats of bitumen laid hot on
the base.
(Unit of rate per 100 Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Teak wood = 100 * 1/2" * 1/12" = 4.20 Cft.
Teak wooden rebates 5% = 0.20 Cft.
Total = 4.40 Cft.
Add wastage 20% = 0.88 Cft.
---------------------------------------------- -------------- -------- ------------- ------------ ----------------------
G.Total = 5.28 Cft.
---------------------------------------------- -------------- -------- ------------- ------------ ----------------------
Deodar wood battens = 11 * 10'*1/8'*1/6' = 2.29 Cft.
Add wastage 50% = 1.15 Cft.
---------------------------------------------- -------------- -------- ------------- ------------ ----------------------
G.Total = 3.44 Cft.
___________________________ ________ ____ ________ _______ _____________
Teak wood ( First Quality ) 5.28 Cft. 2900.0 P.Cft. 15312.00
Deodar wood ( Second Quality ) 3.44 Cft. 4000.00 P.Cft. 13760.00
Bitumen. 34.00 Lbs. 86213.0 P.Ton. 1308.59
Fire wood. 0.125 Mand 900.00 P.Mand. 112.50
Brass screws 2". 7.00 Doz: 185.00 % Nos: 155.40
Sand paper sheet. 2.00 Doz: 150.00 P.doz 300.00
TOTAL 30948.49
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 3094.85
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 34043.34
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Carpenters. 10.00 Nos: 450.00 P.day. 4500.00
Coolies. 5.00 Nos: 250.00 P.day. 1250.00
___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 5750.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 575.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 6325.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 632.50
___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 547/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
TOTAL PART " B " 6957.50
TOTAL (MATERIAL + LABOUR) 41000.84
Total material & labour for 100 Sft. Rs: 41000.84

Chapter No. 7 548/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

32. Shisham wood block flooring 1" thick cut to required size fixed
on a layer of asphalt bitumen laid on base.
(Unit of rate per 100 Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Shisham wood of best quality = 100' * 1/12" = 8.33 Cft.
Add wastage 100% = 8.33 Cft.
---------------------------------------------- -------------- -------- ------------- ------------ ----------------------
G.Total = 16.66 Cft.
___________________________ ________ ____ ________ _______ _____________
Shisham wood. 16.66 Cft. 2300.0 P.Cft. 38318.00
Bitumen for laying and 80.00 Lbs. 86213.0 P.Ton. 3079.04
dipping blocks..
Primer coat. 270/28=9.64 5.00 Lbs. 1800.00 P.Gallon 9000.00

Fire wood. 0.250 Mand 900.00 P.Mand. 225.00

Sand paper. 2.00 Doz: 150.00 P.doz 300.00


___________________________ ________ ____ ________ _______ _____________
TOTAL 50922.04
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 5092.20
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 56014.24
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Carpenters. 6.00 Nos: 450.00 P.day. 2700.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 3950.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 395.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 4345.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 434.50
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 4779.50
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 60793.74
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 60793.74
___ ___________________________ ________ ____ ________ _______ _____________

___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 549/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

33. Teak wood block flooring 1" thick cut to required size fixed on
a layer of asphalt bitumen laid on base.
(Unit of rate per 100 Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Teak wood of best quality = 100' * 1/12" = 8.33 Cft.
Add wastage 40% = 3.33 Cft.
---------------------------------------------- -------------- -------- ------------- ------------ ----------------------
G.Total = 11.66 Cft.
___________________________ ________ ____ ________ _______ _____________
Teak wood. (II class) 11.66 Cft. 2900.0 P.Cft. 33814.0
Bitumen for laying and 80.00 Lbs. 86213.0 P.Ton. 3079.04
dipping blocks..
Primer coat. 5.00 Lbs. 1800.00 P.Gallon 9000.00

Fire wood. 0.125 Mand 900.00 P.Mand. 112.50

Sand paper. 2.00 Doz: 150.00 P.doz 300.00


___________________________ ________ ____ ________ _______ _____________
TOTAL 46305.54
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 4630.55
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 50936.09
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Carpenters. 10.00 Nos: 450.00 P.day. 4500.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 5750.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 575.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 6325.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 632.50
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 6957.50
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 57893.59
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 57893.59
___ ___________________________ ________ ____ ________ _______ _____________

___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 550/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

34 Laying wooden paying of hard wood on edge in


(a) coal tar and asphalt.

(a) Shisham wood

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Shisham wood 10.83 Cft 2300.00 P.CFT 24909.00

Bitumen 34.00 Lbs. 86213.00 P.ton 1308.59


___________________________ ________ ____ ________ _______ _____________
TOTAL 26217.59
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 2621.76
___________________________ ________ ____ ________ _______ _____________

___________________________ ________ ____ ________ _______ _____________


TOTAL PART " A " 28839.35
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Carpenters 1.00 Nos: 450.00 P.day. 450.00

Mason 1.00 Nos: 450.00 P.day. 450.00

Coolies 3.00 Nos: 250.00 P.day. 750.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1650.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 165.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 1815.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 181.50
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1996.50
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 30835.85
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 30835.85
___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 551/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 552/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

34 Laying wooden paying of hard wood on edge in


(b) coal tar and asphalt.

(a) KIKAR WOOD

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Kikar wood 11.66 Cft 1400.00 P.CFT 16324.00

Bitumen 34.00 Lbs. 86213.00 P.ton 1308.59


___________________________ ________ ____ ________ _______ _____________
TOTAL 17632.59
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 1763.26
___________________________ ________ ____ ________ _______ _____________

___________________________ ________ ____ ________ _______ _____________


TOTAL PART " A " 19395.85
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Carpenters 1.00 Nos: 450.00 P.day. 450.00

Mason 1.00 Nos: 450.00 P.day. 450.00

Coolies 3.00 Nos: 250.00 P.day. 750.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1650.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 165.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 1815.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 181.50
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1996.50
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 21392.35
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 21392.35

Chapter No. 7 553/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

35. Tile skirting laid in 1:2 cement mortar over 3/4" thick
cement mortar 1:2 including cement washing & filling
joints complete.

a Cement tiles
(Unit of rate per 100 Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Cement tiles 8"*8"*15/16" 240.0 Nos: 1870.0 % Nos 4488.00
including 5% breakage.

Cement for laying.& pointing ceme 2.45 Cwt. 400.00 P.Bag. 980.00
tile

Sand. 6.00 Cft. 2425.00 % Cft. 145.50

Pigment. 1.00 Lbs. 62.00 P.Lb 62.00


___________________________ ________ ____ ________ _______ _____________
TOTAL 5675.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 567.55
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 6243.05
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason 1.56 Nos: 450.00 P.day. 702.00

Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 1412.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 141.20
___________________________ ________ ____ ________ _______ _____________
TOTAL 1553.20
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 155.32
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1708.52
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 7951.57
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 7951.57
___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 554/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

35. Tile skirting laid in 1:2 cement mortar over 3/4" thick cement mortar 1:2 including
cement martar 1:2 including cement washing and filling joints comlete.
including rubbing and polishing of the joints.

(b) Mosaic tiles.

___ ___________________________ ________ ____ ________ _______ _____________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosaic tiles 8 " * 8 "*1" 240.0 Nos: 3800.00 %Nos. 9120.00
including 5% breakage.

Cement for laying & pointing 2.45 Bag 400.00 P.Bag 980.00
Cement tiles.

Sand. 6.00 Cft. 2425.00 % Cft. 145.50

pigment. 1.000 Lbs 62.00 P.Lbs 62.00

White cement. 0.08 Cwt. 700.00 P.bag 56.00

TOTAL 10363.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 1036.35
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 11399.85
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.56 Nos: 450.00 P.day. 702.00

Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00

TOTAL Rs: 1412.00


___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 141.20
TOTAL 1553.20
Contractor's profit 10.00 % 155.32
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1708.52
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 13108.37
Total material & labour for 100 Sft. Rs: 13108.37

Chapter No. 7 555/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

36 Providing grey cement skirting or dado 3/8" thick including rounding of carner and
straightening of top edge and finishing to smooth surface after plastering.

(a) 1:2 cement sand mortar.

(Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Cement. 1.0 Cwt. 400.00 P.bag 384.00

Sand 2.50 Cft. 2425.00 % Cft 60.63

___________________________ ________ ____ ________ _______ _____________


TOTAL 444.63
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 44.46
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 489.09
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 2.50 Nos: 450.00 P.day. 1125.00

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1585.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 158.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 1743.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 174.35
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1917.85
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 2406.94
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 2406.94

___ ___________________________ ________ ____ ________ _______ _____________


___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 556/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

36 Providing grey cement skirting or dado 3/8" thick including rounding of carner and
straightening of top edge and finishing to smooth surface after plastering.

(b) 1:3 cement sand mortar.

(Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Cement. 0.7 Cwt. 400.00 P.bag 264.00

Sand 2.55 Cft. 2425.00 % Cft 61.84

___________________________ ________ ____ ________ _______ _____________


TOTAL 325.84
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 32.58
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 358.42
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 2.50 Nos: 450.00 P.day. 1125.00

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1585.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 158.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 1743.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 174.35
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1917.85
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 2276.27
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 2276.27

___ ___________________________ ________ ____ ________ _______ _____________


___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 557/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

36 Providing grey cement skirting or dado 3/8" thick including rounding of carner and
straightening of top edge and finishing to smooth surface after plastering.

(c) Extra if skirting or dado finished with pigment of any colour.

(Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Pigment. 6.0 Lbs. 62.00 P.Lb. 372.00

___________________________ ________ ____ ________ _______ _____________


TOTAL 372.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 37.20
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 409.20
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Cooly for mixing. 0.50 Nos. 250.00 P.day. 125.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 125.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 12.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 250.00 137.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 13.75
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 151.25
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 560.45
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 560.45

Chapter No. 7 558/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ ___________________________ ________ ____ ________ _______ _____________


___ ___________________________ ________ ____ ________ _______ _____________
S/N D E S C R I P T I O N.

37 White glazed tile 1/4" thick dado jointed in white cement and laid over 1:2 cement
Sand mortar 3/4"thick including finishing complete.

(Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Glazed tiles 6" * 6" * 1/4" 420.0 Nos: 625.00 P.doz 21875.00

White cement. 0.10 Cwt. 700.00 P.bag 70.00

Grey'Cement for bed 2.16 Bag 400.00 P.Bag 864.00

Sand. 5.20 Cft. 2425.00 % Cft. 126.10

___________________________ ________ ____ ________ _______ _____________


TOTAL 22935.10
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 2293.51
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 25228.61
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Masonfor laying. 2.50 Nos: 450.00 P.day. 1125.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.5 Nos: 250.00 P.day. 125.00

TOTAL Rs: 2500.00


___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 250.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 2750.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 275.00
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 3025.00
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 28253.61

Chapter No. 7 559/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
Total material & labour for 100 Sft. Rs: 28253.61

___ ___________________________ ________ ____ ________ _______ _____________


S/N D E S C R I P T I O N.

38 White glazed tile 1/4" thick dado jointed in white cement and laid over 1:2 cement
Sand mortar 3/4" thick including finishing complete.

(Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Glazed tiles 6" * 6" * 1/4" 420.0 Nos: 625.00 P.doz 21875.00
including 5% breakage.
White cement. 0.10 Cwt. 700.00 P.Bag 70.00

Grey'Cement for bed. 2.16 Bag 400.00 P.Bag 864.00

Sand. 5.20 Cft. 2425.00 % Cft. 126.10

Pigment. 0.67 Lbs. 62.00 P.Lbs. 41.54

TOTAL 22976.64
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 2297.66
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 25274.30
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Masonfor laying. 2.50 Nos: 450.00 P.day. 1125.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.5 Nos: 250.00 P.day. 125.00

TOTAL Rs: 2500.00


Sundries. 10.00 % 250.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 2750.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 275.00
TOTAL PART " B " 3025.00
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 28299.30

Chapter No. 7 560/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
Total material & labour for 100 Sft. Rs: 28299.30

Chapter No. 7 561/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

39 Mosaic dado or skirting one part of grey cement and two parts of marble chips laid
over 1/2" thick plaster 1:3 complete with finishing.

(a) 3/8" thick.


(Unit of rate per Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Cement. 1.3 Cwt. 400.00 P.Bag 500.00

Marble chips. 3.00 Cwt. 375.00 P.Cwt. 1125.00

Corborandum stones. 2.50 Nos 560.00 Each 1400.00

Wax polish. 0.50 Lbs. 300.00 P.Lbs. 150.00

Tartaroc acid. 0.34 Lbs. 80.00 27.20

Linen cotton wood and cloth L.S 30.00

Cement for plaster. 1 Cwt. 400 400

Sand for plaster. 4.50 Cft. 2425.00 109.13


___________________________ ________ ____ ________ _______ _____________
TOTAL 3741.33
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 374.13
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 4115.46
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason for laying polishing & 8.50 Nos: 450.00 P.day. 3825.00
rubbing.
Coolies. 3.00 Nos: 250.00 P.day. 750.00

bashishti for curing 1.00 Nos: 250.00 P.day. 250.00


TOTAL Rs: 4825.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 482.50
TOTAL 5307.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 530.75
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 5838.25
TOTAL (MATERIAL + LABOUR) 9953.71
Total material & labour for 100 Sft. Rs: 9953.71

Chapter No. 7 562/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

39 Mosaic dado or skirting one part of grey cement and two parts of marble chips laid
over 1/2" thick plaster 1:3 complete with finishing.

(b ) 1/2" thick.
(Unit of rate per Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Cement. 2.9 Cwt. 400.00 P.Bag 1160.00

Marble chips. 4.16 Cwt. 375.00 P.Cwt. 1560.00

Corborandum stones. 2.17 Nos 560.00 P.Bag 1215.20

Wax polish. 0.50 Lbs. 300.00 P.Lbs. 150.00

Tartaroc acid. 0.34 Lbs. 80.00 P.Lbs. 27.20

Linen cotton wood and cloth L.S 45.00

Sand 4.50 Cft. 2425.00 % Cft. 109.13


TOTAL 4266.53
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 426.65
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 4693.18
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason for laying polishing & 8.50 Nos: 450.00 P.day. 3825.00
rubbing.
Coolies. 3.00 Nos: 250.00 P.day. 750.00

bashishti for curing 1 Nos: 250.00 P.day. 250.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 4825.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 482.50
TOTAL 5307.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 530.75
TOTAL PART " B " 5838.25
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 10531.43
Total material & labour for 100 Sft. Rs: 10531.43

Chapter No. 7 563/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

40 Mosaic dado or skirting one part of grey cement and two parts of marble chips laid over
1/2" thick plaster 1:3 complete with finishing.

3/8" thick.
(Unit of rate per Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
White 'Cement. 1.3 Cwt. 700.00 P.Bag 875.00

Marble chips. 3.00 Cwt. 375.00 P.Cwt. 1125.00

Corborandum stones. 2.50 Nos 560.00 Each. 1400.00

Wax polish. 0.50 Lbs. 300.00 P.Lbs. 150.00

Tartaroc acid. 0.34 Lbs. 80.00 P.Lbs. 27.20

Linen cotton wood and cloth L.S 30.00

Cement for plaster. 1.00 Cwt. 400 P.bag 400.00

Sand for plaster. 4.50 2425.00 109.13


TOTAL 4116.33
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 411.63
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 4527.96
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason for laying polishing & 8.50 Nos: 450.00 P.day. 3825.00
rubbing.
Coolies. 3.00 Nos: 250.00 P.day. 750.00

bashishti for curing 1.00 Nos: 250.00 P.day. 250.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 4825.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 482.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 5307.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 530.75
TOTAL PART " B " 5838.25
TOTAL (MATERIAL + LABOUR) 10366.21
Total material & labour for 100 Sft. Rs: 10366.21

Chapter No. 7 564/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.
41 Mosaic dado or skirting one part of white cement and two parts
of marble chips laid over 1/2" thick plaster 1:3 complete with
finishing.

(b) 1/2" thick.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
White Cement. 1.90 Cwt. 700.00 P.Bag 1330.00

Marble chips. 4.16 Cwt. 375.00 P.Cwt. 1560.00

Corborandum stones. 2.17 Nos: 560.00 Each. 1215.20

Wax polish. 0.50 Lbs. 300.00 P.Lb 150.00

Tartaric acid. 0.34 Lbs. 80.00 P.Lb 27.20

Linen cotton wood and L.S 30.00


cloth.
Cement for plaster. 1.00 Cwt. 400.00 P.Bag 400.00
Sand. 4.50 Cft. 2425.00 % Cft. 109.13
TOTAL 4821.53
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 482.15
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 5303.68
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason for laying polishing 8.50 Nos: 450.00 P.day. 3825.00
& rubbing.
Coolies. 3.00 Nos: 250.00 P.day. 750.00

Bahishti for curing. 1.00 Nos: 250.00 P.day. 250.00

TOTAL Rs: 4825.00


___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 482.50
TOTAL 5307.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 530.75
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 5838.25
TOTAL (MATERIAL + LABOUR) 11141.93
Total material & labour for 100 Sft. say Rs: 11141.93

Chapter No. 7 565/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.

42 Coloured cement tiles(8" * 8" * 3"/4) of approved dark shade


laid flat in 1:2 white cement mortar over a bed of 3/4" thick
lime mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Tiles(8" * 8" * 3"/4) 240.0 Nos: 3250.00 % Nos: 7800.00

White Cement. 0.51 Cwt. 700.00 P.Bag. 357.00

Sand. 0.82 Cft. 2425.00 % Cft. 19.89

Pigment. 0.67 Lb 62.00 P.Lb 41.54

Lime (slaked) 1.00 Mand 375.00 P.Mand 375.00

Surkhi. 5.00 Cft. 2250.00 % Cft. 112.50


TOTAL 8705.93
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 870.59
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 9576.52
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 10964.99
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 10964.99

Chapter No. 7 566/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.

43 Mosaic tiles of grey cement 8" * 8" * 1" of approved shade


laid flat in 1:2 white cement mortar over a bed of 3/4" thick
lime mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosai Tiles (8" * 8" * 1") 240.0 Nos: 3350.00 % Nos: 8040.00

White Cement. 0.51 Cwt. 700.00 P.Bag. 357.00

Sand. 0.82 Cft. 2425.00 % Cft. 19.89

Pigment. 0.67 Lb 62.00 P.Lb 41.54

Lime (slaked) 1.00 Mand 375.00 P.Mand 375.00

Surkhi. 5.00 Cft. 2250.00 % Cft. 112.50

___________________________ ________ ____ ________ _______ _____________


TOTAL 8945.93
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 894.59
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 9840.52
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00


TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
TOTAL (MATERIAL + LABOUR) 11228.99
Total material & labour for 100 Sft. say Rs: 11228.99
___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 567/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.

44 Mosaic tiles of grey cement 8" * 8" * 1" of approved shade


with Khapcha laid flat in 1:2 white cement mortar over a bed
of 3/4" thick lime mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosai Tiles (8" * 8" * 1") 240.0 Nos: 3350.0 % Nos: 8040.00

White Cement. 0.51 Cwt. 700.00 P.Bag. 357.00

Sand. 0.82 Cft. 2425.00 % Cft. 19.89

Pigment. 0.67 Lb 62.00 P.Lb 41.54

Lime (slaked) 1.00 Mand 375.00 P.Mand 375.00

Surkhi. 5.00 Cft. 2250.00 % Cft. 112.50


___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % #REF!
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " #REF!
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) #REF!
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: #REF!

Chapter No. 7 568/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___ ___________________________ ________ ____ ________ _______ _____________
S/N D I S C R I P T I O N.

45 Mosaic tiles of white cement 8" * 8" * 1" of approved shade


laid flat in 1:2 white cement mortar over a bed of 3/4" thick
lime mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosaic Tiles (8" * 8" * 1") 240.0 Nos: 3800.0 % Nos: 9120.00

White Cement. 0.51 Cwt. 700.00 P.Bag. 357.00

Sand. 0.82 Cft. 2425.00 % Cft. 19.89

Pigment. 0.67 Lb 62.00 P.Lb 41.54

Lime (slaked) 1.00 Mand 375.00 P.Mand 375.00

Surkhi. 5.00 Cft. 2250.00 % Cft. 112.50

___________________________ ________ ____ ________ _______ _____________


TOTAL 10025.93
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 1002.59
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 11028.52
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00


TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
TOTAL (MATERIAL + LABOUR) 12416.99
Total material & labour for 100 Sft. say Rs: 12416.99

Chapter No. 7 569/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___ ___________________________ ________ ____ ________ _______ _____________
S/N D I S C R I P T I O N.

46. Mosaic tiles of white cement 8" * 8" * 1" of approved shade
with Khapcha laid flat in 1:2 white cement mortar over a bed
of 3/4" thick lime mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosai Tiles (8" * 8" * 1") 240.0 Nos: 4425.0 % Nos: 10620.00

White Cement. 0.51 Cwt. 700.00 P.Bag. 357.00

Sand. 0.82 Cft. 2425.00 % Cft. 19.89

Pigment. 0.67 Lb 62.00 P.Lb 41.54

Lime (slaked) 1.00 Mand 375.00 P.Mand 375.00

Surkhi. 5.00 Cft. 2250.00 % Cft. 112.50

___________________________ ________ ____ ________ _______ _____________


TOTAL 11525.93
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 1152.59
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 12678.52
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00


TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
TOTAL (MATERIAL + LABOUR) 14066.99
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 14066.99

Chapter No. 7 570/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.

47. Mosaic tiles of grey cement 12" * 12" * 1" of approved shade
laid flat in 1:2 white cement mortar over a bed of 3/4" thick
lime mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosaic Tiles (12"*12"*1") 105.0 Nos: 3550.0 % Nos: 3727.50

White Cement. 0.51 Cwt. 700.00 P.Bag. 357.00

Sand. 0.82 Cft. 2425.00 % Cft. 19.89

Pigment. 0.67 Lb 62.00 P.Lb 41.54

Lime (slaked) 1.00 Mand 375.00 P.Mand 375.00

Surkhi. 5.00 Cft. 2250.00 % Cft. 112.50

___________________________ ________ ____ ________ _______ _____________


TOTAL 4633.43
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 463.34
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 5096.77
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00


TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
TOTAL (MATERIAL + LABOUR) 6485.24
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 6485.24

Chapter No. 7 571/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.

48. Mosaic tiles of grey cement 12"*12"*1" of approved shade


with Khapcha laid flat in 1:2 white cement mortar over a bed
of 3/4" thick lime mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosaic Tiles (12"*12"*1") 105.0 Nos: 4500.0 % Nos: 4725.00

White Cement. 0.51 Cwt. 700.00 P.Bag. 357.00

Sand. 0.82 Cft. 2425.00 % Cft. 19.89

Pigment. 0.67 Lb 62.00 P.Lb 41.54

Lime (slaked) 1.00 Mand 375.00 P.Mand 375.00

Surkhi. 5.00 Cft. 2250.00 % Cft. 112.50

___________________________ ________ ____ ________ _______ _____________


TOTAL 5630.93
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 563.09
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 6194.02
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00


TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
TOTAL (MATERIAL + LABOUR) 7582.49
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 7582.49

Chapter No. 7 572/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.

49. Mosaic tiles of white cement 12"*12"*1" of approved shade


laid flat in 1:2 white cement mortar over a bed of 3/4" thick
lime mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosaic Tiles (12"*12"*1") 105.0 Nos: 4400.0 % Nos: 4620.00

White Cement. 0.51 Cwt. 700.00 P.Bag. 357.00

Sand. 0.82 Cft. 2425.00 % Cft. 19.89

Pigment. 0.67 Lb 62.00 P.Lb 41.54

Lime (slaked) 1.00 Mand 375.00 P.Mand 375.00

Surkhi. 5.00 Cft. 2250.00 % Cft. 112.50

___________________________ ________ ____ ________ _______ _____________


TOTAL 5525.93
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 552.59
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 6078.52
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00

TOTAL Rs: 1147.50


___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
TOTAL (MATERIAL + LABOUR) 7466.99
Total material & labour for 100 Sft. say Rs: 7466.99

Chapter No. 7 573/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.

50. Mosaic tiles of white cement 12"*12"*1" of approved shade


with Khapcha laid flat in 1:2 white cement mortar over a bed
of 3/4" thick lime mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosai Tiles (12"*12"*1") 105.0 Nos: 6000.0 % Nos: 6300.00

White Cement. 0.51 Cwt. 700.00 P.Bag. 357.00

Sand. 0.82 Cft. 2425.00 % Cft. 19.89

Pigment. 0.67 Lb 62.00 P.Lb 41.54

Lime (slaked) 1.00 Mand 375.00 P.Mand 375.00

Surkhi. 5.00 Cft. 2250.00 % Cft. 112.50

___________________________ ________ ____ ________ _______ _____________


TOTAL 7205.93
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 720.59
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 7926.52
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00


TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 9314.99
Total material & labour for 100 Sft. say Rs: 9314.99

Chapter No. 7 574/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.

51. Mosaic tiles of grey cement 8" * 8" * 1" of approved shade
with Khapcha laid flat in 1:2 grey cement mortar over a bed
of 3/4" thick grey cement mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosai Tiles (8" * 8" * 1") 240.0 Nos: 3350.0 % Nos: 8040.00

Grey Cement. 1.87 Cwt. 400.00 P.Bag. 748.00

Sand. 4.70 Cft. 2425.00 % Cft. 113.98

Pigment. 0.67 Lb 62.00 P.Lb 41.54


TOTAL 8943.52
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 894.35
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 9837.87
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 11226.34
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 11226.34

Chapter No. 7 575/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___ ___________________________ ________ ____ ________ _______ _____________

___ ___________________________ ________ ____ ________ _______ _____________


S/N D I S C R I P T I O N.

52. Mosaic tiles of white cement 8" * 8" * 1" of approved shade
with Khapcha laid flat in 1:2 white cement mortar over a bed
of 3/4" thick grey cement mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosai Tiles (8" * 8" * 1") 240.0 Nos: 4425.0 % Nos: 10620.00

White Cement. 0.08 Cwt. 700.00 P.Bag. 56.00

Sand. 4.70 Cft. 2425.00 % Cft. 113.98

Pigment. 0.67 Lb 62.00 P.Lb 41.54

Grey Cement. 1.79 Cwt. 400.00 P.Bag. 716.00

___________________________ ________ ____ ________ _______ _____________


TOTAL 11547.52
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 1154.75
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 12702.27
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00


TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
TOTAL (MATERIAL + LABOUR) 14090.74

Chapter No. 7 576/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 14090.74
S/N D I S C R I P T I O N.

53. Mosaic tiles of grey cement 12"*12"*1" of approved shade


with Khapcha laid flat in 1:2 grey cement mortar over a bed
of 3/4" thick grey cement mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosaic Tiles (12"*12"*1") 105.0 Nos: 4500.0 % Nos: 4725.00

Grey Cement. 1.87 Cwt. 400.00 P.Bag. 748.00

Sand. 4.70 Cft. 2425.00 % Cft. 113.98

Pigment. 0.67 Lb 62.00 P.Lb 41.54

___________________________ ________ ____ ________ _______ _____________


TOTAL 5628.52
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 562.85
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 6191.37
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00


TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 7579.84

Chapter No. 7 577/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
Total material & labour for 100 Sft. say Rs: 7579.84

Chapter No. 7 578/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.

54. Mosaic tiles of white cement 12"*12"*1" of approved shade


with Khapcha laid flat in 1:2 white cement mortar over a bed
of 3/4" thick grey cement mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosai Tiles (12"*12"*1") 105.0 Nos: 6000.0 % Nos: 6300.00

White Cement. 0.08 Cwt. 700.00 P.Bag. 56.00

Sand. 4.70 Cft. 2425.00 % Cft. 113.98

Pigment. 0.67 Lb 62.00 P.Lb 41.54

Grey cement. 1.79 Cwt. 400.00 P.Bag. 716.00

___________________________ ________ ____ ________ _______ _____________


TOTAL 7227.52
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 722.75
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 7950.27
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
TOTAL PART " B " 1388.48
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 9338.74
Total material & labour for 100 Sft. say Rs: 9338.74

Chapter No. 7 579/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.

55. Laying mosaic topping 1/2" thick in pannels of approved any


pattern of one part of white cement to two parts of marble chips
of required shade and size and of approved pigment in the ratio
of 1:12 of cement used in topping including rubbing and
polishing etc, complete.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
White Cement. 1.75 Cwt. 700.00 P.Bag 1225.00
Marble chips. 4.16 Cwt. 375.00 P.Cwt. 1560.00
Corborandum stones. 3.00 Nos: 625.00 Each. 1875.00
Wax polish. 0.50 Lbs. 300.00 P.Lb 150.00
Tartaric acid. 0.714 Lbs. 80.00 P.Lb 57.12
Linen cotton wood and L.S 10.00
cloth.
Pigment. 20.33 Lbs. 62.00 P.Lb 1260.46
___________________________ ________ ____ ________ _______ _____________
TOTAL 6137.58
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 613.76
___________________________ ________ ____ ________ _______ _____________
Add for 1" thick cement #REF!
concrete flooring of 1:2:4
as per item No:16(a)
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " #REF!
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason for laying topping. 3.50 Nos: 450.00 P.day. 1575.00
Coolies. 2.00 Nos: 250.00 P.day. 500.00
Coolies for mixing of 0.625 Nos: 250.00 P.day. 156.25
pigment.
Skilled coolies for 6.00 Nos: 250.00 P.day. 1500.00
rubbing & polishing.
Bahishti. 0.70 Nos: 250.00 P.day. 175.00
TOTAL Rs: 3906.25
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 390.63
TOTAL 4296.88
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 429.69
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 4726.56
TOTAL (MATERIAL + LABOUR) #REF!
Total material & labour for 100 Sft. say Rs: #REF!

Chapter No. 7 580/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.

56. Mosaic chequer tiles of 8" * 8" * 1-1/4" of approved shade laid
flat in 1:2 grey cement mortar over a bed of 3/4" thick grey
cement mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosaic chequer tiles 240.0 Nos: 525.0 P.Doz: 10500.00
(8"*8"*1-1/4") i/c 5% Wast:
Sand. 4.70 Cft. 2425.00 % Cft. 113.98

Pigment. 0.67 Lb 62.00 P.Lb 41.54

Grey Cement. 2.19 Cwt. 400.00 P.Bag. 876.00


TOTAL 11531.52
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 1153.15
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 12684.67
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00

TOTAL Rs: 1147.50


___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 14073.14
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 14073.14

Chapter No. 7 581/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___ ___________________________ ________ ____ ________ _______ _____________

___ ___________________________ ________ ____ ________ _______ _____________

S/N D I S C R I P T I O N.

57. Mosaic chequer tiles of 11" * 8" * 1-1/4" of approved shade laid
flat in 1:2 grey cement mortar over a bed of 3/4" thick grey
cement mortar 1:2.
(Unit of rate per 100 Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosaic chequer tiles 172.0 Nos: 180.0 P.Doz: 2580.00
(11"*8"*1-1/4") i/c 5% Wast:
Sand. 4.70 Cft. 2425.00 % Cft. 113.98

Pigment. 0.67 Lb 62.00 P.Lb 41.54

Grey Cement. 2.19 Cwt. 400.00 P.Bag. 876.00


TOTAL 3611.52
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 361.15
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 3972.67
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 5361.14

Chapter No. 7 582/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 5361.14
___ ___________________________ ________ ____ ________ _______ _____________

___ ___________________________ ________ ____ ________ _______ _____________


S/N D I S C R I P T I O N.

58. Coloured cement tiles (Pattern) 8" * 8" * 3/4" of approved


shade and pattern laid flat in 1:2 grey cement mortar over a
bed of 3/4" thick grey cement mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Tiles (8" * 8" * 3/4") 240.0 Nos: 3250.0 % Nos: 7800.00
i/c 5% wastage.
Grey Cement. 1.87 Cwt. 400.00 P.Bag. 748.00

Sand. 4.70 Cft. 2425.00 % Cft. 113.98

Pigment. 0.67 Lb 62.00 P.Lb 41.54


TOTAL 8703.52
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 870.35
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 9573.87
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00


TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 10962.34
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 10962.34

Chapter No. 7 583/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___ ___________________________ ________ ____ ________ _______ _____________

___ ___________________________ ________ ____ ________ _______ _____________


S/N D I S C R I P T I O N.

59. Coloured cement tiles (Pattern) 12"*12"*1" of approved shade


and pattern laid flat in 1:2 grey cement mortar over a bed of
3/4" thick grey cement mortar 1:2.

(Unit of rate per 100 Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Tiles (12"*12"*1") 105.0 Nos: 6100.0 % Nos: 6405.00
i/c 5% wastage.
Grey Cement. 1.87 Cwt. 400.00 P.Bag. 748.00

Sand. 4.70 Cft. 2425.00 % Cft. 113.98

Pigment. 0.67 Lb 62.00 P.Lb 41.54


TOTAL 7308.52
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 730.85
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 8039.37
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos: 250.00 P.day. 85.00


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 9427.84
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. say Rs: 9427.84
___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 584/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___ ___________________________ ________ ____ ________ _______ _____________

S/N D I S C R I P T I O N.

60. Providing and laying tiles glazed 6" * 6" * 1/4" on floor or
wall facing in required colour and pattern of STILE
specification jointed in white cement and pigment over a base of
1:2 grey cement morter 3/4" thick including washing and filling
of joints with slurry of white cement and pigment in desired
shape with finishing, cleaning and coat of wax polish etc,
complete including cutting tiles to proper profile.
(Unit of rate per 100 Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Glazed tiles 6"*6"*1/4" 440.0 Nos: 1050.0 P.doz: 38500.00
including 10% wastage.

White Cement. 0.10 Cwt. 700.00 P.Bag. 70.00

Grey Cement for bed. 2.16 Cwt. 400.00 P.Bag. 864.00

Sand. 5.20 Cft. 2425.00 % Cft. 126.10

Pigment. 1.00 Lbs. 62.00 P.Lb 62.00

Wax Polish. 0.50 Lbs. 300.00 P.Lb 150.00


___________________________ ________ ____ ________ _______ _____________
TOTAL 39772.10
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 3977.21
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 43749.31
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason for laying. 3.00 Nos: 450.00 P.day. 1350.00

Skilled Coolies. 2.00 Nos: 250.00 P.day. 500.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


TOTAL Rs: 3225.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 322.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 3547.50
Contractor's profit 10.00 % 354.75
TOTAL PART " B " 3902.25
TOTAL (MATERIAL + LABOUR) 47651.56

Chapter No. 7 585/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
Total material & labour for 100 Sft. say Rs: 47651.56

Chapter No. 7 586/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.

61. Providing and laying HALA or Pattern tiles glazed 6" * 6" *1/4"
on floor or wall facing in required pattern of STILE
specification jointed in white cement and pigment over a base of
1:2 grey cement morter 3/4" thick including washing and filling
of joints with slurry of white cement and pigment in desired
shape with finishing, cleaning and coat of wax polish etc,
complete including cutting tiles to proper profile.
(Unit of rate per 100 Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Glazed tiles 6"*6"*1/4" 440.0 Nos: 1050.0 P.doz: 38500.00
including 10% wastage.

White Cement. 0.10 Cwt. 700.00 P.Bag. 70.00

Grey Cement for bed. 2.16 Cwt. 400.00 P.Bag. 864.00

Sand. 5.20 Cft. 2425.00 % Cft. 126.10

Pigment. 1.00 Lbs. 62.00 P.Lb 62.00

Wax Polish. 0.50 Lbs. 300.00 P.Lb 150.00


___________________________ ________ ____ ________ _______ _____________
TOTAL 39772.10
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 3977.21
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 43749.31
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason for laying. 3.00 Nos: 450.00 P.day. 1350.00

Skilled Coolies. 2.00 Nos: 250.00 P.day. 500.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


TOTAL Rs: 3225.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 322.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 3547.50
Contractor's profit 10.00 % 354.75
TOTAL PART " B " 3902.25
TOTAL (MATERIAL + LABOUR) 47651.56
Total material & labour for 100 Sft. say Rs: 47651.56

Chapter No. 7 587/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D I S C R I P T I O N.

62. Providing and laying HALA or Pattern tiles glazed 8" * 8" *1/4"
on floor or wall facing in required pattern of STILE
specification jointed in white cement and pigment over a base of
1:2 grey cement morter 3/4" thick including washing and filling
of joints with slurry of white cement and pigment in desired
shape with finishing, cleaning and coat of wax polish etc,
complete including cutting tiles to proper profile.
(Unit of rate per 100 Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Glazed tiles 8"*8"*1/4" 250.0 Nos: 1275.0 P.doz: 26562.50
including 10% wastage.

White Cement. 0.10 Cwt. 700.00 P.Bag. 70.00

Grey Cement for bed. 2.16 Cwt. 400.00 P.Bag. 864.00

Sand. 5.20 Cft. 2425.00 % Cft. 126.10

Pigment. 1.00 Lbs. 62.00 P.Lb 62.00

Wax Polish. 0.50 Lbs. 300.00 P.Lb 150.00


TOTAL 27834.60
Contractor's profit 10.00 % 2783.46
TOTAL PART " A " 30618.06
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason for laying. 3.00 Nos: 450.00 P.day. 1350.00

Skilled Coolies. 2.00 Nos: 250.00 P.day. 500.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00


TOTAL Rs: 3225.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 322.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 3547.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 354.75
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 3902.25
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 34520.31
Total material & labour for 100 Sft. say Rs: 34520.31
FROM ITEM NO 41 TO 62 WILL BE AVALABLE RA NEW 95 FROM S NO 15 a to 33

Chapter No. 7 588/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
and FROM S. NO 36 TO 38

Chapter No. 7 589/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

63 Rubber flooring consisting of 12" * 12" * 1/8" rubber tiles laid on firm foundation.

(Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Rubber tiles 12"*12" * 1/8" includin 105.0 Nos: 125.00 Each. 13125.00
wastage. (PVC)

Adhesive mixture. 0.66 Galn 1100.00 P.Gallon 726.00

Brushes etc. L.S 18.00

TOTAL 13869.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 1386.90
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 15255.90
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 1.50 Nos: 250.00 P.day. 375.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 825.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 82.50
___________________________ ________ ____ ________ _______ _____________
TOTAL 907.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 90.75
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 998.25
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 16254.15
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 16254.15
Total material & labour for one Sft. Rs: 162.54
Total material & labour per Sft. say Rs: 162.54

Chapter No. 7 590/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___ ___________________________ ________ ____ ________ _______ _____________

S/N D E S C R I P T I O N.

64 Flooring of mosaic marble chips tiles of white cement laid flat in 1:2 white cement
mortar over 3/4" thick bed of white cement mortar 1:2.

(Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosaic marble tiles of 1"thick white 240.0 Nos: 3800.00 % Nos. 9120.00
cement i/c watage.

White cement. 1.79 Cwt. 700.00 P.bag 1253.00

White Cement joints. 0.08 Cwt. 700.00 P.bag 56.00

Sand. 4.70 Cft. 2425.00 % Cft. 113.98


TOTAL 10542.98
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 1054.30
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 11597.27
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Bahishti. 0.34 Nos. 250 P.day 85.00


___________________________ ________ ____ ________ _______ _____________
TOTAL Rs: 910.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 91.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 1001.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 100.10
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1101.10
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 12698.37
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 12698.37
Total material & labour for one Sft. Rs: 126.98
Total material & labour per Sft. say Rs: 126.98

Chapter No. 7 591/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

65 Flooring of mosaic marble chips tiles of white cement laid flat in 1:2 white cement
mortar over 3/4" thick bed of white cement mortar 1:2.

(Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosaic marble tiles of 1"thick white 240.0 Nos: 3350.00 % Nos. 8040.00
cement i/c watage.

Grey cement. 1.79 Cwt. 400.00 P.bag 0.00

Grey Cement joints. 0.08 Cwt. 400.00 P.bag 32.00

Sand. 4.70 Cft. 2425.00 % Cft. 113.98


TOTAL 8185.98
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 818.60
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 9004.57
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos. 250 P.day 85.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 10393.05
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 10393.05
Total material & labour for one Sft. Rs: 103.93
Total material & labour per Sft. say Rs: 103.93

Chapter No. 7 592/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

66 Flooring of mosaic marble chips tiles of white cement laid flat in 1:2 white cement
mortar over 3/4"thick bed of white cement mortar 1:2.

(Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Mosaic marble tiles of 1"thick white 240.0 Nos: 3800.00 % Nos. 9120.00
cement i/c watage.

Grey cement.for bed. 1.79 Cwt. 400.00 P.bag 716.00

White Cement joints. 0.08 Cwt. 700.00 P.bag 56.00

Sand. 4.70 Cft. 2425.00 % Cft. 113.98

___________________________ ________ ____ ________ _______ _____________


TOTAL 10005.98
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 1000.60
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 11006.57
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.34 Nos. 250 P.day 85.00


TOTAL Rs: 1147.50
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 114.75
___________________________ ________ ____ ________ _______ _____________
TOTAL 1262.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 126.23
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 1388.48
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 12395.05
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 12395.05
Total material & labour for one Sft. Rs: 123.95
Total material & labour per Sft. say Rs: 123.95

Chapter No. 7 593/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

67 Laying mosaic topping 1/2" thick in pannels of approved any paattern of one part of
white cement to two partsof marble chips of required shade and size and of approved
pigment in the rate of 1: 12 of cement used in topping including rubbing and polished
etc , complete.
(Unit of rate per Sft.)
___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
White Cement. 1.8 Cwt. 700.00 P.bag. 1225.00

Marble chips. 4.16 Cwt. 375.00 P.Cwt. 1560.00

Corborandum stones. 3.00 Nos. 560.00 Each. 1680.00

Wax polish. 0.50 300.00 P.Lbs. 150.00

Tartaroc acod. 0.71 Lbs. 80.00 P.Lbs. 57.12

Linen cotton wood and cloth L.S 18.00

Pigment. 20.33 Lbs 62.00 P.Lbs. 1260.46


TOTAL 5950.58
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 595.06
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 6545.64
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason for laying topping 3.50 Nos: 450.00 P.day. 1575.00

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Coolies for maxing if pigment. 0.625 Nos. 250 P.day 156.25

Skilled coolies for rubbing & Polishi 6 Nos. 250 P.day 1500.00
Bahishti. 0.70 Nos. 250.00 P.day 175.00
TOTAL Rs: 3906.25
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 390.63
___________________________ ________ ____ ________ _______ _____________
TOTAL 4296.88
Contractor's profit 10.00 % 429.69
TOTAL PART " B " 4726.56
TOTAL (MATERIAL + LABOUR) 11272.20
Total material & labour for 100 Sft. Rs: 11272.20
Total material & labour for one Sft. Rs: 112.72
Total material & labour per Sft. say Rs: 112.72

Chapter No. 7 594/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

68
Providing and fixing 3/8" thick marble tiles of approved quality and colour and shade size
8" 4" or 6" x 4" in dado skirting and facing removal / tucking of existing plaster surface etc.
Over 1/2" thick base of cement mortar 1:3 setting of tiles in slurry of white cement over
mortar base including filling the joints and washing the tiles with white cement slurry, currint
finishing, cleaning and plosishing etc, complete.

(a) For new works. (Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Marble tiles 8" * 4" /6"8" size includ 105.0 Sft 70.00 P.Sft. 7350.00
5% 'breakage.
Cement 0.88 cwt 400.00 pcwt 352.00
sand 3.40 cft 2425.00 %cft 82.45
White cement 0.25 Cwt. 700.00 P.Bag 175.00

Tarpenting oil 0.63 Galn. 450.00 P.Gallon 281.25

carborandum stones. 7.00 Nos. 560.00 Each 3920.00

Gum and Gum Resin. 2.00 Lbs. 175.00 P.Lb 350.00


TOTAL 12510.70
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 1251.07
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 13761.77
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Masons. 5.00 Nos: 450.00 P.day. 2250.00

Colies. 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 1 Nos.
250 P.day 250.00
TOTAL Rs: 4000.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 400.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 4400.00
Contractor's profit 10.00 % 440.00
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 48.4 4840.00
___________________________ ________ ____ ________ _____________________
TOTAL (MATERIAL + LABOUR) 18601.77
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 18601.77
Total material & labour for one Sft. Rs: 186.02
Total material & labour per Sft. say Rs: 186.02

Chapter No. 7 595/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

68 Providing and fixing 3/8" thick marble tiles of approved quality and colour and shade size
8" 4" or 6" x 4" in dado skirting and facing removal / tucking of existing plaster surface etc.
Over 1/2" thick base of cement mortar 1:3 setting of tiles in slurry of white cement over
mortar base including filling the joints and washing the tiles with white cement slurry, currint
finishing, cleaning and plosishing etc, complete.

(b) For old works. (Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Marble tiles 8" * 4" /6"8" size includ 105.0 Sft 70.00 P.Sft. 7350.00
5% 'breakage.
Cement mortat 1:3 1/2 " thick P. 49 100.00 Sft. 434.45 P.% Sft. 434.45

White cement 0.25 Cwt. 700.00 P.Bag 175.00

Tarpenting oil 0.63 Galn. 175.00 P.Gallon 109.38

carborandum stones. 7.00 Nos. 560.00 Each 3920.00

Gum and Gum Resin. 2.00 Lbs. 175.00 P.Lb 350.00


TOTAL 12338.83
Contractor's profit 10.00 % 1233.88
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 13572.71
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Masons. 5.00 Nos: 450.00 P.day. 2250.00
Colies. 6.00 Nos: 250.00 P.day. 1500.00
Bahishti. 1 Nos. 250 P.day 250.00
Add for removal / taking off existing
plaster.
Masons. 2.00 Nos: 450.00 P.day. 900.00
Colies. 2.00 Nos: 250.00 P.day. 500.00
TOTAL Rs: 5400.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 540.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 5940.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 594.00
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 65.34 6534.00
TOTAL (MATERIAL + LABOUR) 20106.71
Total material & labour for 100 Sft. Rs: 20106.71
Total material & labour for one Sft. Rs: 201.07
Total material & labour per Sft. say Rs: 201.07

Chapter No. 7 596/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

69 Slit atiles 1/4" thick matt glazed or double glazed jointed in white cement and laid over
1:2 grey cement sand mortar 3/4" tjhick including finishing complete. (flooring and
facing).

(Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Split tiles 1/4" thick matt glazed or 100.0 Nos: 153.00 P. Nos. 15300.00
double glazed.

White Cement joints. 0.10 Cwt. 700.00 P.bag 70.00

Grey Cement. 2.16 Cwt. 400 P.bag. 864

Sand. 5.20 Cft. 2425.00 % Cft. 126.10


TOTAL 16360.10
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 1636.01
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 17996.11
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason. 2.50 Nos: 450.00 P.day. 1125.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.5 Nos. 250 P.day 125.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 2500.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 250.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 2750.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 275.00
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 30.25 3025.00
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 21021.11
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 21021.11
Total material & labour for one Sft. Rs: 210.21
Total material & labour per Sft. say Rs: 210.21

Chapter No. 7 597/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
NEW ITEMS 2002.

___ ___________________________ ________ ____ ________ _______ _____________


S/N D E S C R I P T I O N.

70 Applying chemical polishing on existing mosaic /Marble flooring / dado including cleaning ,
grinding with carborandum stone /sand paper and applying chemical polish as per
requirement.

(Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
i Carborandum stone 1.5 Nos 560.00 P.Each 840.00

ii Sand paper Imported 18.00 No 150.00 P.Daz 225.00

iii Chemical polish 1.50 Lbs. 525.00 P.Lbs. 787.50

iv Linen cotton wood & cloth. L.S 50.00

___________________________ ________ ____ ________ _______ _____________


TOTAL 1902.50
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 190.25
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 2092.75
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
i Coolies shitted for rubbing 3.00 No 250.00 P.day 750.00

ii Mason 1.00 No 450.00 P.day 450.00

iii Hire charges of grinding Machine L.S 50.00


TOTAL Rs: 1250.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 125.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 1375.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 137.50
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 15.13 1512.50
TOTAL (MATERIAL + LABOUR) 3605.25
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 3605.25
Total material & labour for one Sft. Rs: 36.05

Chapter No. 7 598/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

71 Providing & fixing cement paving blocks flooring having size of 197 x 97 x 60 (mm) of
city /quddra / cobble shape with natural colours, having strength b/w 5000 psi to 8500 psi
i/c filling the joints with hill sand and laying in specified manner / pattern and design etc:
complete.

(Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
i Enviret blocks i/c 10% wastage nat 110.0 Sft. 150.00 Sft. 16500.00
colours60 mm

ii Hill sand for joint L.sum & 5 Cft for 5.00 Cft. 2425.00 Cft 121.25
100Sft.
___________________________ ________ ____ ________ _______ _____________
TOTAL 16621.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 1662.13
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 18283.38
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason Skilled 2.00 No 450.00 P.day 900.00

Coolie 2.00 No 250 P.day 500.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1400.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 140.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 1540.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 154.00
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 16.94 1694.00
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 19977.38
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 19977.38
Total material & labour for one Sft. Rs: 199.77
___ ___________________________ ________ ____ ________ _______ _____________

___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 599/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

72 Providing & fixing cement paving blocks flooring having size of 197 x 97 x 60 (mm) of
city /quddra / cobble shape with pigmented, having strength b/w 5000 psi to 8500 psi i/c
filling the joints with hill sand and laying in specified manner/ pattern and design etc:
complete.

(Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
i Pigmented blocks i/c 10 % wastage 110.0 Sft. 170.00 P.Sft. 18700.00
60 mm

ii Hill sand 5.00 Cft. 2425.00 P.Cft. 121.25


___________________________ ________ ____ ________ _______ _____________
TOTAL 18821.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 1882.13
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 20703.38
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason Skilled 2.00 No 450.00 P.day 900.00

Coolie 2.00 No 250 P.day 500.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1400.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 140.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 1540.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 154.00
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 16.94 1694.00
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 22397.38
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 22397.38
Total material & labour for one Sft. Rs: 223.97

Chapter No. 7 600/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ ___________________________ ________ ____ ________ _______ _____________

___ ___________________________ ________ ____ ________ _______ _____________


S/N D E S C R I P T I O N.

73 Providing & fixing cement paving blocks flooring having size of 197 x 97 x 80 (mm) of
city /quddra / cobble shape with pigmented, having strength b/w 5000 psi to 8500 psi i/c
filling the joints with hill sand and laying in specified manner/ pattern and design etc:
complete.

(Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Paving block natural coloure 80 mm 110.0 Sft. 170.00 Sft 18700.00
10 % wastage.

Hill sand 5.00 Cft 2425.00 Cft 121.25

___________________________ ________ ____ ________ _______ _____________


TOTAL 18821.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 1882.13
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 20703.38
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason Skilled 2.00 No 450.00 P.day 900.00

Coolie 2.00 No 250 P.day 500.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1400.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 140.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 1540.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 154.00
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 16.94 1694.00
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 22397.38
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 22397.38
Total material & labour for one Sft. Rs: 223.97

Chapter No. 7 601/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___ ___________________________ ________ ____ ________ _______ _____________

___ ___________________________ ________ ____ ________ _______ _____________

S/N D E S C R I P T I O N.

74 Providing & fixing cement paving blocks flooring having size of 197 x 97 x 80 (mm) of
city /quddra / cobble shape with pigmented, having strength b/w 5000 psi to 8500 psi i/c
filling the joints with hill sand and laying in specified manner/ pattern and design etc:
complete.

(Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
Pigmented blocks 80 mm i/c 10 % 110.0 Sft. 190.00 P.Sft. 20900.00
wastage.

Hill sand 5.00 Cft 2425.00 P.Cft 121.25

___________________________ ________ ____ ________ _______ _____________


TOTAL 21021.25
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 2102.13
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 23123.38
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason Skilled 2.00 No 450.00 P.day 900.00

Coolie 2.00 No 250 P.day 500.00

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 1400.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 140.00
___________________________ ________ ____ ________ _______ _____________
TOTAL 1540.00
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 154.00
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 16.94 1694.00
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 24817.38
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 24817.38
Total material & labour for one Sft. Rs: 248.17

Chapter No. 7 602/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
___ ___________________________ ________ ____ ________ _______ _____________

Chapter No. 7 603/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

75 Providing & fixing glass strips 4 mm for floorint upto 1" depth i/c fixing in flooring with
cement in flooring with cement in specified pattern & design.

(Unit of rate per Sft.)


___ ___________________________ ________ ____ ________ _______ _____________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
___________________________ ________ ____ ________ _______ _____________
i Glass sheet for 1" wide glass strip 9.2 Sft. 80.00 P.Sft. 733.60
i/c 10 % wastage.

ii Cement sand Mortar L.S 25.00


___________________________ ________ ____ ________ _______ _____________
TOTAL 758.60
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 75.86
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " A " 834.46
___________________________ ________ ____ ________ _______ _____________
(B) LABOUR
___________________________ ________ ____ ________ _______ _____________
Mason Skilled 0.33 No 450.00 P.day 148.50

Coolie 0.33 No 250 P.day 82.50

___________________________ ________ ____ ________ _______ _____________


TOTAL Rs: 231.00
___________________________ ________ ____ ________ _______ _____________
Sundries. 10.00 % 23.10
___________________________ ________ ____ ________ _______ _____________
TOTAL 254.10
___________________________ ________ ____ ________ _______ _____________
Contractor's profit 10.00 % 25.41
___________________________ ________ ____ ________ _______ _____________
TOTAL PART " B " 2.80 279.51
___________________________ ________ ____ ________ _______ _____________
TOTAL (MATERIAL + LABOUR) 1113.97
___________________________ ________ ____ ________ _______ _____________
Total material & labour for 100 Sft. Rs: 1113.97
Total material & labour for one Sft. Rs: 11.14

Chapter No. 7 604/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

SURFACE RENDERING

FIRST FILL THIS SHEET

MATERIAL RATE UNIT

1 CLAY , MUD , EARTH 500 %CFT

2 BHOOSA 300 P.MAND

3 LI.ME SLACKED 375 DO

4 SAND 2425 %CFT

5 SURKHI 2250 %CFT

6 CEMENT 400 P.CWT

7 CHOPPED JUTE 25 P.LB

8 SHINGLE 3075 %CFT

9 CHALK 45 P.KG

10 DISTEMPER 200 P.LITRE

11 RICE 40 P.KG

12 COLOURING MATERIAL 80 P.LBS

13 COWDUNG/ MANUR 500 %CFT

14 BITUMEN 86213 P.TON

15 PIT SAND 900 %CFT

16 BAJRI 2650 %CFT

17 DUROCEM 150 P.KG

18 BRUSH 4" 450 EACH

19 MATT FINISHED PAINT 2350 P.GALL

Chapter No. 8 605/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

20 PREMIER (Good quality) 450 P.LIT

21 ZINK 155 P.KG

22 VARNISH 1800 P.GALL

23 RUBBING BRICK (Slicon carida) 675 EACH

24 SAND PAPER 12.5 EACH

25 MIXING /KEROSINE OIL 110 P.LIT

26 WEATHER SHIELD 2450 P.GALL

27 PLASTER OF PARIS 140 P.KG

28 PLASTIC EMULTION 2200 P.GALKL

29 ACRYLIC QUARTZ CO POLYMEER 30 P.SFT

30 COLOR CRETE MIXTURE 45 P.SFT

31 EMULSION PAINT 1850 P.GALL

LABOURE RATE UNIT


1 MASSON , PAINTER 450 P.DAY

2 COOLIES 250 P.DAY

3 BAHISHTI , SKILLED COLLI 250 P.DAY

4 PAINTER (G II) 400 P.DAY

SURFACE RENDERING
================
I Plastering Pointing, White washing, Colour washing and
distempering.
II Rates for all finished works include the removal of the surplus
debris un- used material and by-Products.
The rates include the cost of scaffolding and its removal.

Chapter No. 8 606/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N
1. Mud plaster on walls:-
(a) 1/2" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Calay. 6.00 Cft. 500.00 % Cft. 30.00

Bhoosa. 6.00 Seer 300.00 P.Mand. 45.00


TOTAL 75.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 7.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 82.50
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ ________________ ________ ______ ________
Mason. 0.17 Nos: 450.00 P.day. 76.50
__________
Coolies. 0.50 Nos: 250.00 P.day. 125.00

Bahishti. 0.05 Nos: 250.00 P.day. 12.50


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 214.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 21.40
_____________________________ __________ _____ ________ ______ ________
TOTAL 235.40
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 23.54
TOTAL PART " B " 258.94
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 341.44
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 341.00

Chapter No. 8 607/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
1 Mud plaster on walls:-

(b) 1" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Clay. 12.00 Cft. 500.00 % Cft. 60.00

Bhoosa. 16.00 Seer 300.00 P.mand. 120.00


_____________________________ __________ _____ ________ ______ ________
TOTAL 180.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 18.00
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 198.00
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.200 Nos: 450.00 P.day. 90.00

Coolies. 0.75 Nos: 250.00 P.day. 187.50

Bahishti. 0.07 Nos: 250.00 P.day. 17.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 295.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 29.50
_____________________________ __________ _____ ________ ______ ________
TOTAL 324.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 32.45
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 356.95
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 554.95
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 555.00

Chapter No. 8 608/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

2 Mud plaster on roof or floor.

1" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Clay. 12.00 Cft. 500.00 % Cft. 60.00

Bhoosa. 16.00 Cft. 300.00 P.Mand. 120.00


TOTAL 180.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 18.00
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 198.00
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.200 Nos: 450.00 P.day. 90.00

Coolies. 0.75 Nos: 250.00 P.day. 187.50

Bahishti. 0.07 Nos: 250.00 P.day. 17.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 295.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 29.50
_____________________________ __________ _____ ________ ______ ________
TOTAL 324.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 32.45
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 356.95
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 554.95
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 609/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Sft. say Rs: 555.00
_____ _____________________________ __________ _____ ________ ______ ________
S/N D E S C R I P T I O N.

3 Lime plaster (ground in mills)

(a) 1/2" thick 1:1: 3 Lime, Sand and Surkhi.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Lime slaked (ground) 0.4 Mand 375.00 P.Mand 150.00

Sand. 1.00 Cft 2425.00 % Cft 24.25

Surkhi. 3.00 Cft 2250.00 % Cft 67.50

_____________________________ __________ _____ ________ ______ ________


TOTAL 241.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 24.18
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 265.93
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 650.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 715.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 786.50

Chapter No. 8 610/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


TOTAL (MATERIAL + LABOUR) 1052.43
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1052.00
S/N D E S C R I P T I O N.

3 Lime plaster (ground in mills)

(b) 1/2" thick 1: 1: 1 Lime, Sand and Surkhi.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Lime slaked (ground) 0.7 P. Man 375.00 P.Mand. 255.00

Sand. 1.70 Cft. 2425.00 % Cft. 41.23

Surkhi. 1.70 Cft. 2250.00 % Cft. 38.25


TOTAL 334.48
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 33.45
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 367.92
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 650.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 715.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 71.50

Chapter No. 8 611/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1154.42
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1154.42
S/N D E S C R I P T I O N.

3 Lime plaster (ground in mills).

(c) 1/2" thick 1:2 Lime and Surkhi.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Lime slaked (ground) 0.68 Mand 375.00 P.Mand 255.00

Surkhi. 3.40 Cft. 2250.00 % Cft. 76.50


TOTAL 331.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 33.15
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 364.65
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 650.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 715.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 612/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL PART " B " 786.50


_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1151.15
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1151.15
_____ _____________________________ __________ _____ ________ ______ ________

_____ _____________________________ __________ _____ ________ ______ ________


S/N D E S C R I P T I O N.

3 Lime plaster (ground in mills)

(d) 1/2" thick 2:3 Lime and Surkhi.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Lime slaked (ground) 0.80 Mand 375.00 P.Mand 300.00

Surkhi. 3.00 Cft. 2250.00 % Cft. 67.50


TOTAL 367.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 36.75
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 404.25
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 650.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 715.00

Chapter No. 8 613/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1190.75
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1190.75
_____ _____________________________ __________ _____ ________ ______ ________

S/N D E S C R I P T I O N.

4 Cement lime plaster 1: 7: 12.

(a) 1/4" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.1 Cwt. 400.00 P.Bag 40.00

Lime slaked (ground) 0.34 Mand 375.00 P.Mand 127.50

Sand. 1.40 Cft. 2425.00 % Cft. 33.95

TOTAL 201.45
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 20.15
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 221.60
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 650.00
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 614/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Sundries. 10.00 % 65.00


_____________________________ __________ _____ ________ ______ ________
TOTAL 715.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1008.10
_____________________________ __________ _____ ______________ ________
Total material & labour for 100 Sft. say 1008.10

S/N D E S C R I P T I O N.

4 Cement lime plaster 1:7:12.

(b) 1/2" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.2 Cwt 400.00 P.Bag 80.00

Lime slaked (ground) 0.68 Mand 375.00 P.Mand. 255.00

Sand. 2.80 Cft. 2425.00 % Cft. 67.90

_____________________________ __________ _____ ________ ______ ________


TOTAL 402.90
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 40.29
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 443.19
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

Chapter No. 8 615/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 650.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 715.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1229.69
Total material & labour for 100 Sft. say Rs: 1229.69
S/N D E S C R I P T I O N.

5 Cement neru plaster 1:2.

(a) 1/4" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.6 Cwt. 400.00 P.Bag 240.00

Sand. 1.54 Cft. 2425.00 % Cft. 37.35

Chopped Jute. 3.10 Lbs. 25.00 P.Lb. 77.50


_____________________________ __________ _____ ________ _______________
TOTAL 354.85
_____________________________ __________ _____ ________ _______________
Contractor's profit 10.00 % 35.48
_____________________________ __________ _____ ________ _______________
TOTAL PART " A " 390.33
_____________________________ __________ _____ ________ _______________
(B) LABOUR
_____________________________ __________ _____ ________ _______________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Chapter No. 8 616/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Bahishti. 0.25 Nos: 250.00 P.day. 62.50


TOTAL Rs: 650.00
_____________________________ __________ _____ ________ _______________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ _______________
TOTAL 715.00
_____________________________ __________ _____ ________ _______________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ _______________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ _______________
TOTAL (MATERIAL + LABOUR)
_____________________________ __________ _____ ________ ______ 1176.83
Total material & labour for 100 Sft. say Rs:
_____ _____________________________ __________ _____ ________ ______ ________

S/N D E S C R I P T I O N.

5 Cement neru plaster 1:2.

(b) 1/2" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.9 Cwt. 400.0 P.Bag. 368.00

Sand. 3.08 Cft. 2425.00 % Cft. 74.69

Choped Jute. 6.00 Lbs. 25.00 P.Lb 150.00

TOTAL 592.69
_____________________________ __________ _____ ________ _______________
Contractor's profit 10.00 % 59.27
_____________________________ __________ _____ ________ _______________
TOTAL PART " A " 651.96
_____________________________ __________ _____ ________ _______________
(B) LABOUR
_____________________________ __________ _____ ________ _______________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Chapter No. 8 617/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

TOTAL Rs: 650.00


_____________________________ __________ _____ ________ _______________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ _______________
TOTAL 715.00
_____________________________ __________ _____ ________ _______________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ _______________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ _______________
TOTAL (MATERIAL + LABOUR)
_____________________________ __________ _____ ________ ______ 1438.46
Total material & labour for 100 Sft. say Rs: 1438.46
_____ _____________________________ __________ _____ ________ ______ ________
S/N D E S C R I P T I O N.

6 Lime neru plaster 1:2 (Lime and Surkhi.)

(a) 3/4" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Lime slaked (ground) 1.0 Mand 375.0 P.Mand 375.00

Surkhi. 5.00 Cft. 2250.00 % Cft. 112.50

Choped Jute. 10.00 Lbs. 25.00 P.Lb. 250.00


_____________________________ __________ _____ ________ _______________
TOTAL 737.50
_____________________________ __________ _____ ________ _______________
Contractor's profit 10.00 % 73.75
_____________________________ __________ _____ ________ _______________
TOTAL PART " A " 811.25
_____________________________ ________________ ________ _______________
(B) LABOUR
_____________________________ ________________ ________ _______________

Chapter No. 8 618/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ _______________


TOTAL Rs: 650.00
_____________________________ __________ _____ ________ _______________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ _______________
TOTAL 715.00
_____________________________ __________ _____ ________ _______________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR)
_____________________________ __________ _____ ________ ______ 1597.75
Total material & labour for 100 Sft. say Rs: 1597.75
S/N D E S C R I P T I O N.

6 Lime neru plaster 1:2 (Lime and Surkhi).

(b) 1/2" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Lime slaked (ground) 0.7 Mand 375.00 P.Mand 255.00

Surkhi. 3.40 Cft. 2250.00 % Cft. 76.50

Choped Jute. 8.00 Lbs. 25.00 P.Lb. 200.00

_____________________________ __________ _____ ________ _______________


TOTAL 531.50
_____________________________ __________ _____ ________ _______________
Contractor's profit 10.00 % 53.15
_____________________________ __________ _____ ________ _______________
TOTAL PART " A " 584.65

Chapter No. 8 619/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ _______________


(B) LABOUR
_____________________________ __________ _____ ________ _______________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ _______________


TOTAL Rs: 650.00
_____________________________ __________ _____ ________ _______________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ _______________
TOTAL 715.00
_____________________________ __________ _____ ________ _______________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ _______________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ _______________
TOTAL (MATERIAL + LABOUR)
Total material & labour for 100 Sft. say Rs. #REF!
S/N D E S C R I P T I O N.

6 Lime neru plaster 1:2 (lime and Surkhi).

(c) 1/4" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Lime slaked (ground) 0.3 Mand 375.00 P.Mand. 127.50

Surkhi. 1.70 Cft. 0.00 %Cft. 0.00

Choped Jute. 4.00 Lbs. 25.00 P.Lb. 100.00


TOTAL 227.50
_____________________________ __________ _____ ________ _______________
Contractor's profit 10.00 % 22.75
_____________________________ __________ _____ ________ _______________
TOTAL PART " A " 250.25

Chapter No. 8 620/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ _______________


TOTAL Rs: 650.00
_____________________________ __________ _____ ________ _______________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ _______________
TOTAL 715.00
_____________________________ __________ _____ ________ _______________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ _______________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR)
_____________________________ __________ _____ ________ ______ 1036.75
Total material & labour for 100 Sft. say Rs: 1036.75
S/N D E S C R I P T I O N.
7 Lime neru plaster 1:2 with fine finish of neru plaster mixed with 10% of
Cement.

(a) 1/2" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Lime slaked (ground ) 0.7 Mand 375.00 P.Mand 255.00

Surkhi. 3.40 Cft. 2250.00 % Cft. 76.50

Choped Jute. 8.00 Lbs. 25.00 P.Lb. 200.00

Cement. 0.13 Cwt. 400.00 P.Bag. 52.00

Chapter No. 8 621/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 583.50
_____________________________ __________ _____ ________ _______________
Contractor's profit 10.00 % 58.35
_____________________________ __________ _____ ________ _______________
TOTAL PART " A " 641.85
_____________________________ __________ _____ ________ _______________
(B) LABOUR
_____________________________ __________ _____ ________ _______________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

TOTAL Rs: 650.00


_____________________________ __________ _____ ________ _______________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ _______________
TOTAL 715.00
_____________________________ __________ _____ ________ _______________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ _______________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ _______________
TOTAL (MATERIAL + LABOUR)
Total material & labour for 100 Sft. say Rs: #REF!
S/N D E S C R I P T I O N.
7 Lime neru plaster 1:2 with fine finish of neru plaster mixed with 10% of
Cement.

(b) 1/4" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Lime slaked (ground ) 0.3 Mand 375.00 P.Mand 116.25

Surkhi. 1.70 Cft. 2250.00 % Cft. 38.25

Choped Jute. 4.00 Lbs. 25.00 P.Lb. 100.00

Chapter No. 8 622/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Cement. 0.07 Cwt. 400.00 P.Bag. 28.00


TOTAL 282.50
_____________________________ __________ _____ ________ _______________
Contractor's profit 10.00 % 28.25
_____________________________ __________ _____ ________ _______________
TOTAL PART " A " 310.75
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 650.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 715.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1097.25
_____________________________ __________ _____ ________ ______
Total material & labour for 100 Sft. say Rs: 1097.25
S/N D E S C R I P T I O N.

8 2" stucco cement plaster 1: 2:4 (cement , sand and shingle)

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement 3.7 Cwt. 400.00 P.Bag. 1480.00

Sand. 7.40 Cft. 2425.00 % Cft. 179.45

Shingle. 15.00 Cft. 3075.00 % Cft. 461.25

TOTAL 2120.70
_____________________________ __________ _____ ________ _______________

Chapter No. 8 623/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 212.07


_____________________________ __________ _____ ________ _______________
TOTAL PART " A " 2332.77
_____________________________ __________ _____ ________ _______________
(B) LABOUR
_____________________________ __________ _____ ________ _______________
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.30 Nos: 250.00 P.day. 75.00

_____________________________ __________ _____ ________ _______________


TOTAL Rs: 1525.00
_____________________________ __________ _____ ________ _______________
Sundries. 10.00 % 152.50
_____________________________ __________ _____ ________ _______________
TOTAL 1677.50
_____________________________ __________ _____ ________ _______________
Contractor's profit 10.00 % 167.75
_____________________________ __________ _____ ________ _______________
TOTAL PART " B " 1845.25
_____________________________ __________ _____ ________ _______________
TOTAL (MATERIAL + LABOUR)
_____________________________ __________ _____________ ______ 4178.02
Total material & labour for 100 Sft. say Rs: 4178.02
S/N D E S C R I P T I O N.

9 Cement plaster 1:2 upto 20' Ft: hieght

(a) 3/8" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 624/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Cement. 1.25 Cwt. 400.00 P.Bag. 500.00

Sand. 3.00 Cft. 2425.00 % Cft. 72.75

_____________________________ __________ _____ ________ ______


TOTAL 572.75
_____________________________ __________ _____ ________ _______________
Contractor's profit 10.00 % 57.28
_____________________________ __________ _____ ________ _______________
TOTAL PART " A " 630.03
_____________________________ __________ _____ ________ ______
(B) LABOUR
_____________________________ __________ _____ ________ _______________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50


_____________________________ __________ _____ ________ ______
TOTAL Rs: 587.50
_____________________________ __________ _____ ________ _______________
Sundries. 10.00 % 58.75
_____________________________ __________ _____ ________ _______________
TOTAL 646.25
_____________________________ __________ _____ ________ _______________
Contractor's profit 10.00 % 0.00
_____________________________ __________ _____ ________ _______________
TOTAL PART " B " 646.25
_____________________________ __________ _____ ________ _______________
TOTAL (MATERIAL + LABOUR) 1276.28
_____________________________ __________ _____ ________ _______________
Total material & labour for 100 Sft. say Rs: 1276.28
S/N D E S C R I P T I O N.
9 Cement plaster 1:2 upto 20' Ft: hieght

(b) 1/2" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 625/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Cement. 1.25 Cwt. 400.00 P.Bag. 500.00

Sand. 3.00 Cft. 2425.00 % Cft. 72.75

TOTAL 572.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 57.28
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 630.03
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 650.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 715.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1416.53
__________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1416.53
S/N D E S C R I P T I O N.
9 Cement plaster 1:2 upto 20' Ft: hieght

(c) 3/4" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 626/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Cement. 1.92 Cwt. 400.00 P.Bag. 768.00

Sand. 5.00 Cft. 2425.00 % Cft. 121.25

_____________________________ __________ _____ ________ ______ ________


TOTAL 889.25
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 88.93
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 978.18
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 1.25 Nos: 250.00 P.day. 312.50

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 825.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 82.50
_____________________________ __________ _____ ________ ______ ________
TOTAL 907.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 90.75
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 998.25
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1976.43
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1976.43
_____ _____________________________ __________ _____ ________ ______ ________
S/N D E S C R I P T I O N.

10 Cement plaster 1:3 upto 20' Ft: hieght.

(a) 3/8" thick.

(Unit of rate per 100 Sft.)

Chapter No. 8 627/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ _____________________________ __________ _____ ________ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________

Cement. 0.66 Cwt. 400.00 P.Bag. 264.00

Sand. 2.55 Cft. 2425.00 % Cft. 61.84

TOTAL 325.84
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 32.58
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 358.42
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

TOTAL Rs: 650.00


_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 715.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1144.92
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1144.92

S/N D E S C R I P T I O N.
10 Cement plaster 1:3 upto 20' Ft: hieght.

(b) 1/2" thick.

Chapter No. 8 628/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.88 Cwt. 400.00 P.Bag. 352.00

Sand. 3.40 Cft. 2425.00 % Cft. 82.45


_____________________________ __________ _____ ________ ______ ________
TOTAL 434.45
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 43.45
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 477.90
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 650.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 715.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1264.40
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1264.40
S/N D E S C R I P T I O N.
10 Cement plaster 1:3 upto 20' Ft: hieght.

(c) 3/4" thick.

Chapter No. 8 629/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 1.32 Cwt. 400.00 P.Bag. 528.00

Sand. 5.10 Cft. 2425.00 % Cft. 123.68


TOTAL 651.68
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 65.17
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 716.84
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 1.25 Nos: 250.00 P.day. 312.50

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 825.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 82.50
_____________________________ __________ _____ ________ ______ ________
TOTAL 907.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 90.75
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 998.25
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1715.09
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1715.09
S/N D E S C R I P T I O N.

11 Cement plaster 1:4 upto 20' Ft: hieght.

Chapter No. 8 630/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(a) 3/8" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.57 Cwt. 400.00 P.Bag. 228.00

Sand. 3.00 Cft. 2425.00 % Cft. 72.75

_____________________________ __________ _____ ________ ______ ________


TOTAL 300.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 30.08
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 330.83
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 650.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 715.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1117.33
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1117.33
_____ _____________________________ __________ _____ ________ ______ ________
S/N D E S C R I P T I O N.

Chapter No. 8 631/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

11 Cement plaster 1:4 upto 20' Ft: hieght.

(b) 1/2" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.73 Cwt. 400.00 P.Bag. 292.00

Sand. 3.60 Cft. 2425.00 % Cft. 87.30

_____________________________ __________ _____ ________ ______ ________


TOTAL 379.30
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 37.93
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 417.23
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

TOTAL Rs: 650.00


_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 715.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1203.73
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1203.73

Chapter No. 8 632/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

11 Cement plaster 1:4 upto 20' Ft: hieght.

(c) 3/4" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 1.14 Cwt. 400.00 P.Bag. 456.00

Sand. 5.50 Cft. 2425.00 % Cft. 133.38

_____________________________ __________ _____ ________ ______ ________


TOTAL 589.38
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 58.94
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 648.31
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 1.25 Nos: 250.00 P.day. 312.50

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 825.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 82.50
_____________________________ __________ _____ ________ ______ ________
TOTAL 907.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 90.75
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 998.25
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 633/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (MATERIAL + LABOUR) 1646.56


_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1646.56
S/N D E S C R I P T I O N.

12 Cement plaster 1:5 upto 20' Ft: hieght.

(a) 3/8" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.50 Cwt. 400.00 P.Bag. 200.00

Sand. 3.00 Cft. 2425.00 % Cft. 72.75


_____________________________ __________ _____ ________ ______ ________
TOTAL 272.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 27.28
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 300.03
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 650.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 715.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 634/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL PART " B " 786.50


_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1086.53
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1086.53
S/N D E S C R I P T I O N.
12 Cement plaster 1:5 upto 20' Ft: hieght.

(b) 1/2" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.61 Cwt. 400.00 P.Bag. 244.00

Sand. 4.00 Cft. 2425.00 % Cft. 97.00

_____________________________ __________ _____ ________ ______ ________


TOTAL 341.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 34.10

_____________________________ __________ _____ ________ ______ ________


TOTAL PART " A " 375.10
_____________________________ __________ _____ ________ ______
(B) LABOUR
_____________________________ __________ _____ ________ ______
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 650.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 715.00
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 635/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 71.50


_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1161.60
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1161.60
S/N D E S C R I P T I O N.

12 Cement plaster 1: 5 upto 20' Ft: hieght.

(c) 3/4" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 1.00 Cwt. 400.00 P.Bag. 400.00

Sand. 6.00 Cft. 2425.00 % Cft. 145.50


TOTAL 545.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 54.55
_____________________________ __________ _____ ________ ______ ________

________

_____________________________ __________ _____ ________ ______ ________


TOTAL PART " A " 600.05
_____________________________ __________ _____ ________ ______
(B) LABOUR
_____________________________ __________ _____ ________ ______
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 1.25 Nos: 250.00 P.day. 312.50

Bahishti. 0.25 Nos: 250.00 P.day. 62.50


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 825.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 82.50
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 636/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 907.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 90.75
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 998.25
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1598.30
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1598.30
S/N D E S C R I P T I O N.
13 Cement plaster 1: 6 upto 20' Ft: hieght.

(a)

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.40 Cwt. 400.00 P.Bag. 160.00

Sand. 3.00 Cft. 2425.00 % Cft. 72.75

_____________________________ __________ _____ ________ ______ ________


TOTAL 232.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 23.28
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 256.03
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 650.00
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 637/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Sundries. 10.00 % 65.00


_____________________________ __________ _____ ________ ______ ________
TOTAL 715.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1042.53
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1042.53
S/N D E S C R I P T I O N.
13 Cement plaster 1: 6 upto 20' Ft: hieght.

(b) 1/2"" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.53 Cwt. 400.00 P.Bag. 212.00

Sand. 4.00 Cft. 2425.00 % Cft. 97.00

_____________________________ __________ _____ ________ ______


TOTAL 309.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 30.90
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 339.90
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR.
_____________________________ __________ _____ ________ ______ ________
Mason 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 650.00

Chapter No. 8 638/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 715.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1126.40
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1126.40
_____ _____________________________ __________ _____ ________ ______ ________
S/N D E S C R I P T I O N.

13 Cement plaster 1:6 upto 20' Ft: hieght.

(c) 3/4" thick.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.80 Cwt. 400.00 P.Bag. 320.00

Sand. 6.00 Cft. 2425.00 % Cft. 145.50

_____________________________ __________ _____ ________ ______ ________


TOTAL 465.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 46.55
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 512.05
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason 1.00 Nos: 450.00 P.day. 450.00

Coolies. 1.25 Nos: 250.00 P.day. 312.50

Chapter No. 8 639/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Bahishti. 0.25 Nos: 250.00 P.day. 62.50


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 825.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 82.50
_____________________________ __________ _____ ________ ______ ________
TOTAL 907.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 90.75
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 998.25
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1510.30
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1510.30
S/N D E S C R I P T I O N.
1 Applying floating coat of Hi Bond
(Universal) as a bond coat or as an
adhesive link between old & fresh
concrete or plaster as directed by
Engineer Incharge.

UNIT P % SFT.
RATE UNIT AMOUNT
(A) MATERIAL QUANTITY
Rs: Rs:
(i) Hi Bond Universal i/c 10% wastage 1.43X1.10=1.5 Kg 125 P.Kg. 196.62
(coverage 70-Sft /Kg). Rs: 196.62
TOTAL 196.62
Contractor's Profit 10 % 19.66
TOTAL PART "A" 216.28

RATE UNIT AMOUNT


(B) LABOUR QUANTITY
Rs: Rs:
(i) Mason 0.5 Nos: 270 P.day 135
(ii) Coolie. 0.5 Nos. 100 P.Day 50
(iii) T&P Carriage etc. L.Sum 25
Rs; 210
Sundries. 10 % 21
TOTAL 231
Contractor's Profit 10 % 23.1
TOTAL PART "B" 254.1
G.TOTAL (A+B) 470.38
Say 686.66

Chapter No. 8 640/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
14 Applying floating coat of cement . (1/32" thick)

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.40 Cwt. 400.00 P.Bag. 160.00

_____________________________ __________ _____ ________ ______ ________


TOTAL 160.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 16.00
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 176.00
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 0.25 Nos: 250.00 P.day. 62.50

Bahishti. 0.10 Nos: 250.00 P.day. 25.00


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 400.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 40.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 440.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 44.00
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 484.00
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 660.00

Chapter No. 8 641/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


Total material & labour for 100 Sft. say Rs: 660.00
S/N D E S C R I P T I O N.

15 Lime pointing flush upto 20' hieght including raking joints:

(a) Ratio 1:1:1: ( Lime, sand and surkhi.)

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________

Lime slaked (ground ) 0.36 Mand 375.00 P.Mand 135.00

Surkhi. 0.90 Cft. 2250.00 % Cft. 20.25

Sand. 0.90 Cft. 2425.00 % Cft. 21.83

_____________________________ __________ _____ ________ ______ ________


TOTAL 177.08
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 17.71
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 194.78
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.50 Nos: 450.00 P.day. 225.00

Coolies. 0.75 Nos: 250.00 P.day. 187.50

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 475.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 47.50
_____________________________ __________ _____ ________ ______ ________
TOTAL 522.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 52.25
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 574.75

Chapter No. 8 642/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


TOTAL (MATERIAL + LABOUR) 769.53
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. Rs: 769.53
S/N D E S C R I P T I O N.

15 Lime pointing flush upto 20' hieght including raking joints:

(b) Ratio 1:2 ( Lime,and sand.)

(Unit of rate per Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________

Lime slaked (ground ) 0.36 Mand 375.00 P.Mand 135.00

Sand 1.8 Cft. 2425.00 % Cft 26.05

_____________________________ __________ _____ ________ ______ ________


TOTAL 161.05
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 16.11
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 177.16
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.50 Nos: 450.00 P.day. 225.00

Coolies. 0.75 Nos: 250.00 P.day. 187.50

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 475.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 47.50
_____________________________ __________ _____ ________ ______ ________
TOTAL 522.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 52.25
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 643/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL PART " B " 574.75


_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 751.91
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. Rs: 751.91

S/N D E S C R I P T I O N.

16 Lime pointing struck joints on walls upto 20' hieght including raking oof joints.

(a) Ratio 1:1:1: (Lime , sand and surkhi)

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________

Lime slaked (ground ) 0.36 Mand 375.00 P.Mand 135.00

Surkhi. 0.90 Cft. 2250.00 % Cft. 20.25

Sand. 0.90 Cft. 2425.00 % Cft. 21.83

_____________________________ __________ _____ ________ ______ ________


TOTAL 177.08
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 17.71
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 194.78
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason . 1.00 Nos. 450.00 P.day 450.00

Coolies. 1.00 Nos. 250 P.day 250.00

Bahishti. 0.25 Nos. 250.00 P.day 62.50


__________ _____ ______ ________
TOTAL Rs: 762.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 76.25
_____________________________ __________ _____ ________ ______ ________
TOTAL 838.75

Chapter No. 8 644/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


Contractor's profit 10.00 % 83.88
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 922.63
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1117.41
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. Rs: 1117.41
S/N D E S C R I P T I O N.
16 Lime pointing struck joints on walls upto 20' hieght including raking oof joints.

(b) Ratio 1:2 (Lime , sand and surkhi)

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________

Lime slaked (ground ) 0.36 Mand 375.00 P.Mand 135.00

Sand 1.8 Cft. 2425.00 % Cft 43.65

_____________________________ __________ _____ ________ ______ ________


TOTAL 178.65
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 17.87
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 196.52
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason . 1.00 Nos. 450.00 P.day 450.00

Coolies. 1.00 Nos. 250 P.day 250.00

Bahishti. 0.25 Nos. 250.00 P.day 62.50

TOTAL Rs: 762.50


_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 76.25
_____________________________ __________ _____ ________ ______ ________
TOTAL 838.75

Chapter No. 8 645/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


Contractor's profit 10.00 % 83.88
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 922.63
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1119.14
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. Rs: 1119.14
_____ _____________________________ __________ _____ ________ ______ ________

_____ _____________________________ __________ _____ ________ ______ ________


S/N D E S C R I P T I O N.

17 Cement pointing flush upto 20' Ft: hieght.

(a) Ratio 1:2

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.72 Cwt. 400.00 P. Bag. 288.00

Sand 1.8 Cft. 2425.00 % Cft 43.65

_____________________________ __________ _____ ________ ______ ________


TOTAL 331.65
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 33.17
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 364.82
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason . 0.75 Nos. 450.00 P.day 337.50

Coolies. 1 Nos. 250 P.day 250

Bahishti. 0.25 Nos. 250.00 P.day 62.50

TOTAL Rs: 650.00


_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 65.00

Chapter No. 8 646/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


TOTAL 715.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1151.32
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. Rs: 1151.32
_____ _____________________________ __________ _____ ________ ______ ________

S/N D E S C R I P T I O N.
17 Cement pointing flush upto 20' Ft: hieght.

(b) Ratio 1:3


(Unit of rate per 100 Sft.)
_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.54 Cwt. 400.00 P. Bag. 216.00

Sand 2 Cft. 2425.00 % Cft 48.50

_____________________________ __________ _____ ________ ______ ________


TOTAL 264.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 26.45
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 290.95
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason . 0.75 Nos. 450.00 P.day 337.50

Coolies. 1 Nos. 250 P.day 250.00

Bahishti. 0.25 Nos. 250.00 P.day 62.50

TOTAL Rs: 650.00


_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 65.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 715.00

Chapter No. 8 647/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


Contractor's profit 10.00 % 71.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 786.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1077.45
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. Rs: 1077.45

_____ _____________________________ __________ _____ ________ ______ ________

S/N D E S C R I P T I O N.
18 Cement pointing flush 1:2 on floor.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.72 Cwt. 400 P. Bag. 288.00

Sand 1.8 Cft. 2425 % Cft 43.65

_____________________________ __________ _____ ________ ______ ________


TOTAL 331.65
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 33.17
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 364.82
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason . 0.50 Nos. 450.00 P.day 225.00

Coolies. 0.75 Nos. 250 P.day 187.50

Bahishti. 0.25 Nos. 250.00 P.day 62.50

TOTAL Rs: 475.00


_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 47.50

Chapter No. 8 648/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


TOTAL 522.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 52.25
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 574.75
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 939.57
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. Rs: 939.57

_____ _____________________________ __________ _____ ________ ______ ________

_____ _____________________________ __________ _____ ________ ______ ________


S/N D E S C R I P T I O N.

19 Cement pointing struck joints on walls.

(a) Ratio 1:2

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.72 Cwt. 400.00 P. Bag. 288.00

Sand. 1.80 Cft. 2425.00 % Cft 43.65

_____________________________ __________ _____ ________ ______ ________


TOTAL 331.65
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 33.17
_____________________________ __________ _____ ________ ______ ________
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 364.82
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason 1.00 Nos: 450.00 P.day. 450.00

Chapter No. 8 649/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Coolies 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos. 250.00 P.day 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 762.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 76.25
_____________________________ __________ _____ ________ ______ ________
TOTAL 838.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 83.88
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 922.63
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1287.44
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1287.44
S/N D E S C R I P T I O N.

19 Cement pointing struck joints on walls.

(b) Ratio 1:3

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.54 Cwt. 400.00 P. Bag. 216.00

Sand. 2.00 Cft. 2425.00 % Cft 48.50


TOTAL 264.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 26.45
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 290.95
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________

Mason 1.00 Nos: 450.00 P.day. 450.00

Chapter No. 8 650/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Coolies 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos. 250.00 P.day 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 762.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 76.25
_____________________________ __________ _____ ________ ______ ________
TOTAL 838.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 83.88
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 922.63
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1213.58
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1213.58

S/N D E S C R I P T I O N.

20 Pointing flush on stone work:

(a) In lime mortar 1:2

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________

Lime slaked (ground) 0.50 Mand 375.00 P.Mand 187.50

Sand. 2.00 Cft. 2425.00 % Cft. 48.50

_____________________________ __________ _____ ________ ______ ________


TOTAL 236.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 23.60
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 259.60

Chapter No. 8 651/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason 1.00 Nos: 450.00 P.day. 450.00

Coolies. 0.50 Nos: 250.00 P.day. 125.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

TOTAL Rs: 637.50


_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 63.75
_____________________________ __________ _____ ________ ______ ________
TOTAL 701.25
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 70.13
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 771.38
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1030.98
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1030.98
S/N D E S C R I P T I O N.
20 Pointing flush on stone work:

(b) In lime mortar 1:3

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.54 Cwt. 400.00 P. Bag. 216.00

Sand. 2.00 Cft. 2425.00 % Cft 48.50

_____________________________ __________ _____ ________ ______ ________


TOTAL 264.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 26.45
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 652/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL PART " A " 290.95


_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason 1.00 Nos: 450.00 P.day. 450.00

Coolies. 0.50 Nos: 250.00 P.day. 125.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 637.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 63.75
_____________________________ __________ _____ ________ ______ ________
TOTAL 701.25
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 70.13
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 771.38
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1062.33
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1062.33
_____ _____________________________ __________ _____ ________ ______ ________
S/N D E S C R I P T I O N.

20 Pointing flush on stone work:

(c) On stone work raised:


(i) In lime mortar 1:2

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Lime slaked (ground) 0.50 Mand 375.00 P.Mand 187.50

Sand. 2.00 Cft. 2425.00 % Cft. 48.50

_____________________________ __________ _____ ________ ______ ________


TOTAL 236.00
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 653/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 23.60


_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 259.60
_____________________________ ________________ ________ ______ ________
(B) LABOUR
_____________________________ ________________ ________ ______ ________
Mason 2.00 Nos: 450.00 P.day. 900.00

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 1212.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 121.25
_____________________________ __________ _____ ________ ______ ________
TOTAL 1333.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 133.38
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 1467.13
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1726.73
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1726.73

S/N D E S C R I P T I O N.
20 Pointing flush on stone work:

(c) On stone work raised:


(ii) In lime mortar 1:3

(Unit of rate per Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement. 0.54 Cwt. 400.00 P. Bag. 216.00

Sand. 2.00 Cft. 2425.00 % Cft 48.50

_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 654/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 264.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 26.45
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 290.95
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 2.00 Nos: 450.00 P.day. 900.00

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 1212.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 121.25
_____________________________ __________ _____ ________ ______ ________
TOTAL 1333.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 133.38
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 1467.13
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1758.08
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. Rs: 1758.08
S/N D E S C R I P T I O N.

21 Racking and washing joints of stone masonary


(old work)
(Unit of rate per100 Sft.)
_____ _____________________________ __________ _____ ________ ______ ________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ _______________

Cooly skilled. 1.00 Nos. 250.00 P.day. 250.00

TOTAL 250.00
_____________________________ __________ _____ 10.00 ______ ________
Sundries. 25.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 275.00
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 655/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 27.50


_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 302.50

Labour rate for 100 Sft. __________ _____ ________ ______ ________

_____ _____________________________ __________ _____ ________ ______ ________


S/N D E S C R I P T I O N.

22 Racking and washing joints of stone masonary (old work)

(Unit of rate per100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ _______________

Cooly skilled. 0.50 Nos. 250.00 P.day. 125.00

TOTAL 125.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 12.50
_____________________________ __________ _____ ________ ______ ________
TOTAL 137.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 13.75
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 151.25
_____________________________ __________ _____ ________ ______ ________

S/N D E S C R I P T I O N.

23 Priming coat of chalk under distemper.

(b) In lime mortar 1:3

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Chalk. 1.00 KG 45.00 P.KG 45.00

Chapter No. 8 656/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


TOTAL 45.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 4.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 49.50
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Painter . 0.10 Nos. 400.00 P.day. 40.00

Coolies. 0.10 Nos. 250.00 P.day. 25.00


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 65.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 6.50
_____________________________ __________ _____ ________ ______ ________
TOTAL 71.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 7.15
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 78.65
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 128.15
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 128.15
S/N D E S C R I P T I O N.

24 Distempering.

(a) One coat (1st: coat over priming coat)

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 657/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Distemper. 0.70 LIT 200.00 P.LIT 140.00

Brushes & sand paper. L.S 25.00

_____________________________ __________ _____ ________ ______ ________


TOTAL 165.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 16.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 181.50
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Painter . 0.17 Nos. 400.00 P.day. 68.00

Coolies. 0.17 Nos. 250.00 P.day. 42.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 110.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 11.05
_____________________________ __________ _____ ________ ______ ________
TOTAL 121.55
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 12.16
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 133.71
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 315.21
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 315.21

S/N D E S C R I P T I O N.

24 Distempering.

(b) Two coats.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT

Chapter No. 8 658/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Distemper. 0.92 LIT 200.00 P.LIT 184.00

Brushes & sand paper. L.S 25.00

_____________________________ __________ _____ ________ ______ ________


TOTAL 209.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 20.90
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 229.90
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Painter . 0.25 Nos. 400.00 P.day. 100.00

Coolies. 0.25 Nos. 250.00 P.day. 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 162.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 16.25
_____________________________ __________ _____ ________ ______ ________
TOTAL 178.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 17.88
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 196.63
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 426.53
Total material & labour for 100 Sft. say Rs: 426.53
S/N D E S C R I P T I O N.

24 Distempering.

(c) Three coats.

(Unit of rate per 100 Sft.)

Chapter No. 8 659/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ _____________________________ __________ _____ ________ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Distemper. 1.15 LIT 200.00 P.LIT 230.00

Brushes & sand paper. L.S 32.00

_____________________________ __________ _____ ________ ______ ________


TOTAL 262.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 26.20
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 288.20
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Painter . 0.33 Nos. 400.00 P.day. 132.00

Coolies. 0.33 Nos. 250.00 P.day. 82.50


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 214.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 21.45
_____________________________ __________ _____ ________ ______ ________
TOTAL 235.95
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 23.60
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 259.55
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 547.75
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 547.75
S/N D E S C R I P T I O N.

25 Colour washing.

(a) Ist : coat over white washed surface.

Chapter No. 8 660/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
White lime. 3.00 Seer 375.00 P.Mand. 28.13

Rice. 1.50 Chtk 40.00 P.Seer. 3.75

Colouring material. 0.17 Lbs. 80.00 P.Lb 13.60

_____________________________ __________ _____ ________ ______ ________


TOTAL 45.48
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 4.55
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 50.02
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Coolies skilled. 0.15 Nos. 250.00 P.day 37.50

Panter. 0.15 Nos. 400.00 P.day 60.00


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 97.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 9.75
_____________________________ __________ _____ ________ ______ ________
TOTAL 107.25
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 10.73
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 117.98
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 168.00
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 168.00
S/N D E S C R I P T I O N.

25 Colour washing.

Chapter No. 8 661/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(b) Two coats.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
White lime. 5.00 Seer 375.00 P.Mand. 46.88

Rice. 2.50 Chtk 40.00 P.Seer. 6.25

Colouring material. 0.17 Lbs. 80.00 P.Lb 13.60

_____________________________ __________ _____ ________ ______ ________


TOTAL 66.73
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 6.67
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 73.40
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Coolies skilled. 0.25 Nos. 250.00 P.day 62.50

Panter. 0.15 Nos. 400.00 P.day 60.00


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 122.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 12.25
_____________________________ __________ _____ ________ ______ ________
TOTAL 134.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 13.48
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 148.23
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 221.62
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 221.62
S/N D E S C R I P T I O N.

26 White washing.

Chapter No. 8 662/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(a) One coats.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
White lime. 2.00 Seer 375.00 P.Mand. 18.75

Rice. 1.00 Chtk 40.00 P.Seer. 2.50

_____________________________ __________ _____ ________ ______ ________


TOTAL 21.25
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 2.13
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 23.38
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Coolies skilled. 0.12 Nos. 250.00 P.day 30.00

Panter. 0.12 Nos. 400.00 P.day 48.00


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 78.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 7.80
_____________________________ __________ _____ ________ ______ ________
TOTAL 85.80
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 8.58
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 94.38
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 117.76
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 117.76
S/N D E S C R I P T I O N.

Chapter No. 8 663/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

26 White washing.

(b) Two coats.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
White lime. 3.00 Seer 375.00 P.Mand. 28.13

Rice. 1.50 Chtk 40.00 P.Seer. 1.50

_____________________________ __________ _____ ________ ______ ________


TOTAL 29.63
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 2.96
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 32.59
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Coolies skilled. 0.18 Nos. 250.00 P.day 45.00

Panter. 0.18 Nos. 400.00 P.day 72.00


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 117.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 11.70
_____________________________ __________ _____ ________ ______ ________
TOTAL 128.70
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 12.87
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 141.57
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 174.16
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 664/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Sft. say Rs: 174.16
S/N D E S C R I P T I O N.

26 White washing.

(c) Three coats.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
White lime. 4.00 Seer 375.00 P.Mand. 37.50

Rice. 2.00 Chtk 40.00 P.Seer. 2.00

_____________________________ __________ _____ ________ ______ ________


TOTAL 39.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 3.95
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 43.45
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Coolies skilled. 0.23 Nos. 250.00 P.day 57.50

Panter. 0.23 Nos. 400.00 P.day 92.00


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 149.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 14.95
_____________________________ __________ _____ ________ ______ ________
TOTAL 164.45
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 16.45
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 180.90
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 665/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (MATERIAL + LABOUR) 224.35


_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 224.35
S/N D E S C R I P T I O N.

27 Gobri leeping.

(a) On walls.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Mud (Good earth) 0.25 Cft. 500.00 % Cft. 1.25

Cow dung. 0.25 Cft. 500.00 %Cft 1.25

_____________________________ __________ _____ ________ ______ ________


TOTAL 2.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 0.25
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 2.75
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.15 Nos. 450.00 P.day 67.50

Bahishite. 0.06 Nos. 250.00 P.day 15.00


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 82.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 8.25
_____________________________ __________ _____ ________ ______ ________
TOTAL 90.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 9.08
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 666/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL PART " B " 99.83


_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 102.58
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 102.58
S/N D E S C R I P T I O N.

27 Gobri leeping.

(b) Over roof.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Mud (Good earth) 0.25 Cft. 500.00 % Cft. 1.25

Cow dung. 0.25 Cft. 500.00 %Cft 1.25

_____________________________ __________ _____ ________ ______ ________


TOTAL 2.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 0.25
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 2.75
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 0.12 Nos. 450.00 P.day 54.00

Bahishite. 0.06 Nos. 250.00 P.day 15.00


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 69.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 6.90
_____________________________ __________ _____ ________ ______ ________
TOTAL 75.90
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 667/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 7.59


_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 83.49
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 86.24
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 86.24
S/N D E S C R I P T I O N.

28 Striking joints of burnt bricks in lime or cement mortar.

(Unit of rate per100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ _______________

Mason. 0.35 Nos. 450.00 P.day. 157.50

_____________________________ __________ _____ ________ ______ ________


TOTAL 157.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 15.75
_____________________________ __________ _____ ________ ______ ________
TOTAL 173.25
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 17.33
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 190.58
190.58
Labour rate for 100 Sft. __________ _____ ________ ______ ________

Chapter No. 8 668/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

29 Extra for lime mud or cement plaster and pointing from 20' and above (for each
additional 10' hieght)

(Unit of rate per100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ _______________

Mason. 0.12 Nos. 450.00 P.day. 54.00

Cooly. 0.25 Nos. 250.00 P.day. 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL 116.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 11.65
_____________________________ __________ _____ ________ ______ ________
TOTAL 128.15
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 12.82
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 140.97

Labour rate for 100 Sft. __________ _____ ________ ______ ________

Chapter No. 8 669/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

30 Caulking joints of sleepers with sand and coalter.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Coalter 10.00 P.Lb 86213.00 P.Ton. 384.88

Pit Sand. 4.00 Cft. 900.00 % Cft. 36.00

Fule. L.S 10.00

_____________________________ __________ _____ ________ ______ ________


TOTAL 430.88
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 43.09
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 473.97
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Coolies skilled. 0.50 Nos. 250.00 P.day 125.00

Coolies. 0.50 Nos. 250.00 P.day. 125.00

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 250.00

Chapter No. 8 670/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


Sundries. 10.00 % 25.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 275.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 27.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 302.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 776.47
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 776.47
_____ _____________________________ __________ _____ ________ ______ ________
S/N D E S C R I P T I O N.

31 Caulking joints of sleepers with Mud and chopped straw.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Good earth. 4.00 Cft. 500.00 % Cft. 20.00

Bhoosa. 1.75 Seer 300.00 P.Mand. 13.13

Cow dung. L.S 6.00

_____________________________ __________ _____ ________ ______ ________


TOTAL 39.13
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 3.91
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 43.04
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Coolies skilled. 0.50 Nos. 250.00 P.day 125.00

Coolies. 0.50 Nos. 250.00 P.day. 125.00

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 250.00

Chapter No. 8 671/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


Sundries. 10.00 % 25.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 275.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 27.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 302.50
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 345.54
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 345.54
_____ _____________________________ __________ _____ ________ ______ ________

_____ _____________________________ __________ _____ ________ ______ ________


S/N D E S C R I P T I O N.

32 Rough cast / stucco cement plaster 3/4" thick in proportin of


1: 1-1/2 : 1 - 1/2 in cement hill sand and bajri in pattern.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Cement . 2.00 Cwt. 400.00 P.Bag. 800.00

Sand. 3.60 Cft. 2425.00 % Cft. 87.30

Bajri. 3.60 Cft. 2650.00 % Cft. 95.40

_____________________________ __________ _____ ________ ______ ________


TOTAL 982.70
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 98.27
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 1080.97
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Mason. 1.00 Nos. 450.00 P.day 450.00

Coolies. 2.00 Nos. 250.00 P.day. 500.00

Chapter No. 8 672/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Bahishti 0.25 Nos 250.00 P.day. 62.50

TOTAL 1012.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 101.25
_____________________________ __________ _____ ________ ______ ________
TOTAL 1113.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 111.38
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 1225.13
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 2306.10
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 2306.10

Chapter No. 8 673/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

33 Duroceming of approved make and shade in 3 coats wall scrubbed into the surface
including finishing smooth at any height in any floor.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Durocem. 4.00 Kg. 150.00 P.Kg. 600.00

Brush 4" 0.25 Nos. 450.00 Each. 112.50

_____________________________ __________ _____ ________ ______ ________


TOTAL 712.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 71.25
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 783.75
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Painter Grade-II 0.75 Nos. 450.00 P.day 337.50

Cooly. 0.75 Nos. 250.00 P.day. 187.50

Bahishti. 0.063 Nos. 250.00 P.day 15.75

TOTAL Rs: 540.75


_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 54.08
_____________________________ __________ _____ ________ ______ ________
TOTAL 594.83
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 59.48
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 654.31
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1438.06

Chapter No. 8 674/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


Total material & labour for 100 Sft. say Rs: 1438.06
S/N D E S C R I P T I O N.

34 Extra labour rate for making grooves of 1" * 1/4" or 3/4" * 1/2" plastered surface
with true edges both vertically and horizontly with uniform depth and with groove base
smoothly finished etc. complete as per instruction of Engineer Incharge.

(Unit of rate per100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ _______________

Labour for 100 Lft.


0.75 450.00 P.day 337.50
Mason ( I-Class) 0.75 250.00 P.day 187.50
Skilled Cooly.

_____________________________ __________ _____ ________ ______ ________


TOTAL 525.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 52.50
_____________________________ __________ _____ ________ ______ ________
TOTAL 577.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 57.75
_____________________________ __________ _____ ________ ______ ________
TOTAL (LABOUR) 635.25
_____________________________
Total material & labour for 100 Rft. 635.25
Total material & labour for 1 Rft. 6.35
Total material & labour per Rft. 6.35

Chapter No. 8 675/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ _____________________________ __________ _____ ________ ______ ________

S/N D E S C R I P T I O N.

35 E xtra labour rate for making cement plaster patter pattas / band around straight or
corved openings and around the edges of roof slabs, the width not less than 6" with fine
finishing as derected by Engineer Incharge.

(Unit of rate per100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ _______________

Labour for 100 Lft.


3.00 450.00 P.day 1350.00
Mason ( I-Class) 1.00 250.00 P.day 250.00
Skilled Cooly.

_____________________________ __________ _____ ________ ______ ________


TOTAL 1600.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 160.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 1760.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 176.00
_____________________________ __________ _____ ________ ______ ________
TOTAL (LABOUR) 1936.00
_____ _____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Rft. 1936.00
Total material & labour for 1 Rft. 19.36
Total material & labour per Rft.

Chapter No. 8 676/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ _____________________________ __________ _____ ________ ______ ________


_____ _____________________________ __________ _____ ________ ______ ________

NEW ITEMS 2002.


S/N D E S C R I P T I O N.
36 Preparing the surface and painting with matt finish i/c rubbing the surface with Bathy
(a) (silicon carbiderubbing brick ) filling the voids with zink / chalk / plaster of paris mixture,
applying first coat premix, making the surface smooth and then painting 3 coat s wit
matt finish of approved make etc.: complete. (new surface).

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Matt finish paint 0.20 Gall 2350.00 Gall 470.00
Premier 0.50 Lit 450.00 Lit 225.00
Chalk 1.00 Kg. 45.00 Kg. 45.00
Zink 0.25 Kg 155.00 Kg 38.75
Varnish 0.15 Gall 1800.00 Gall 270.00
Rubbing Brick 0.10 No 675.00 Each 67.50
Sand paper 1.00 No 12.50 Each 12.50
Mixing oil 2.00 Lit 110.00 Lit 220.00
Brush etc: L.S L.S L.S 10.00

TOTAL 1358.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 135.88
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 1494.63
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
(i) Painter. 0.75 No 450.00 P.dad 337.50

(ii) Coolie. 0.25 No 250.00 P.day 62.50


_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 400.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 40.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 440.00

Chapter No. 8 677/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


Contractor's profit 10.00 % 44.00
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 484.00
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1978.63
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1978.63
S/N D E S C R I P T I O N.
36 Preparing the surface and painting with matt finish i/c rubbing the surface with Bathy
(silicon carbiderubbing brick ) filling the voids with zink / chalk / plaster of paris mixture,
applying first coat premix, making the surface smooth and then painting 3 coat s wit
matt finish of approved make etc.: complete. (new surface).

(b) 2nd & subsequent coat.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
i Matt finish paint 0.15 Gall 2350.00 Gall 352.50

ii Brushes etc. L.S 10.00

_____________________________ __________ _____ ________ ______ ________


TOTAL 362.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 36.25
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 398.75
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
(i) Painter. 0.50 No 450.00 P.day 225.00

(ii) Coolie. 0.15 No 250.00 P.day 37.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 262.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 26.25
_____________________________ __________ _____ ________ ______ ________
TOTAL 288.75

Chapter No. 8 678/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


Contractor's profit 10.00 % 28.88
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 317.63
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 716.38
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 716.38
_____ _____________________________ __________ _____ ________ ______ ________

S/N D E S C R I P T I O N.
37 Preparing the surface & painting with matt finsh paint of approved make to old matt
(a) finish surface.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Matt finish paint. 0.20 Gall 2350.00 P.Gall 470.00

sand paper Brush L.S 20.00

TOTAL 490.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 49.00
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 539.00
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
Painter. 0.75 No 450.00 P.day 337.50

Coolie. 0.25 No 250.00 P.day 62.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 400.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 40.00
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 679/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 440.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 44.00
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 484.00
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1023.00
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1023.00
_____ _____________________________ __________ _____ ________ ______ ________

_____ _____________________________ __________ _____ ________ ______ ________


S/N D E S C R I P T I O N.
37 Preparing the surface & painting with matt finsh paint of approved make to old matt
finish surface.
(b) 2nd & subsequent coat.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Matt finish paint. 0.15 Gall 2350.00 P.Gall 352.50

sand paper Brush L.S 10.00

_____________________________ __________ _____ ________ ______ ________


TOTAL 362.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 36.25
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 398.75
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
(i) Painter. 0.50 No 450.00 P.day 225.00

(ii) Coolie. 0.15 No 250.00 P.day 37.50

Chapter No. 8 680/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 262.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 26.25
_____________________________ __________ _____ ________ ______ ________
TOTAL 288.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 28.88
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 317.63
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 716.38
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 716.38
S/N D E S C R I P T I O N.
38 Preparing the surface and painting with weather coat i/c rubbing the surface with
(a) rubbing brick/ sand Paper, filling the voids with chalk/ plaster of Paris and then painting
with weather coat of approved make.
(Unit of rate per 100 Sft.)
_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
i Weather shield 0.25 gal 2450.00 p.gal 612.50

ii Chalk 1.00 kg 45.00 p.kg 45.00

iii Zink 0.25 kg 155.00 p.kg 38.75

iv Plaster of paris 1.00 kg 140.00 p.kg 140.00

v Rubbing brick 0.10 nos 675.00 each 67.50

vi Sand paper Brush etc. 15.00 15.00


_____________________________ __________ _____ ________ ______ ________
TOTAL 918.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 91.88
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 1010.63
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
(i) Painter. 0.50 No 450.00 p.day 225.00

Chapter No. 8 681/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(ii) Coolie. 0.15 No 250.00 p.day 37.50

TOTAL Rs: 262.50


_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 26.25
_____________________________ __________ _____ ________ ______ ________
TOTAL 288.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 28.88
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 317.63
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1328.25
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1328.25

S/N D E S C R I P T I O N.
38 Preparing the surface and painting with weather coat i/c rubbing the surface with
(b) rubbing brick/ sand Paper, filling the voids with chalk/ plaster of Paris and then painting
with weather coat of approved make.

2nd and Subsequent coat (Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
i Weather shield 0.15 gall 2450.00 p.gall 367.50

ii Brushes etc. l.s 10.00

TOTAL 377.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 37.75
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 415.25
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
(i) Painter. 0.30 No 450.00 p,day 135.00

(ii) Coolie. 0.10 No 250.00 p.day 25.00

Chapter No. 8 682/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 160.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 16.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 176.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 17.60
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 193.60
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 608.85
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 608.85
_____ _____________________________ __________ _____ ________ ______ ________

S/N D E S C R I P T I O N.
39 Preparing the surface and painting with weather coat of approved make to old weather
(a) coat surface.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
i Weather shiled 0.20 Gall 2450.00 P.gall 490.00

ii Brushes etc. L.s 10.00

TOTAL 500.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 50.00
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 550.00
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
(i) Painter. 0.50 No 450.00 P.day 225.00

(ii) Coolie. 0.15 NO 250.00 P>DAY 37.50

Chapter No. 8 683/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 262.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 26.25
_____________________________ __________ _____ ________ ______ ________
TOTAL 288.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 28.88
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 317.63
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 867.63
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 867.63

_____ _____________________________ __________ _____ ________ ______ ________

S/N D E S C R I P T I O N.
39 Preparing the surface and painting with weather coat of approved make to old weather
(b) coat surface.

2nd and subsequent

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
i Weather shiled 0.15 gall 2450.00 p.gall 367.50

ii Brushes etc. L.s 10.00

_____________________________ __________ _____ ________ ______ ________


TOTAL 377.50
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 37.75
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 415.25
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR

Chapter No. 8 684/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


(i) Painter. 0.30 NO 450.00 P.DAY 135.00

(ii) Coolie. 0.10 NO 250.00 P.DAY 25.00

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 160.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 16.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 176.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 17.60
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 193.60
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 608.85
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 608.85
_____ _____________________________ __________ _____ ________ ______ ________

S/N D E S C R I P T I O N.
40 Preparing the surface and painting with plastic emulsion paint of approved make i/c
(a) rubbing the surface with sand Paper, filling the voids with chalk/ plaster of paris and
then painting etc. complete.

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
Plastic emulsion. 0.20 GALL 2200.00 P.GALL 440.00

Chalk 1.00 KG 45.00 P.KG 45.00

Zink. 0.25 KG 155.00 P.KG 38.75

Plaster of Paris 1.00 KG 140.00 P.KG 140.00

Bursh /sand paper etc. L.S 15.00

_____________________________ __________ _____ ________ ______ ________


TOTAL 678.75
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 685/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 67.88


_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 746.63
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
(i) Painter. 0.50 NO 450.00 P.DAY 225.00

(ii) Coolie. 0.15 NO 250.00 P.DAY 37.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 262.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 26.25
_____________________________ __________ _____ ________ ______ ________
TOTAL 288.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 28.88
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 317.63
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 1064.25
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 1064.25
S/N D E S C R I P T I O N.
40 Preparing the surface and painting with plastic emulsion paint of approved make i/c
(b) rubbing the surface with sand Paper, filling the voids with chalk/ plaster of paris and
then painting etc. complete.

2ND AND SUBSEQUENT


(Unit of rate per 100 Sft.)
_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
i Plastic emulsion. 0.15 GALL 2200.00 P.GALL 330.00

ii Brushes etc. L.S 10 10.00

TOTAL 340.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 34.00
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 686/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL PART " A " 374.00


_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
(i) Painter. 0.30 NO 450.00 P.DAY 135.00

(ii) Coolie. 0.10 NO 250.00 P.DAY 25.00

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 160.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 16.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 176.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 17.60
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 193.60
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 567.60
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 567.60
_____ _____________________________ __________ _____ ________ ______ ________

_____ _____________________________ __________ _____ ________ ______ ________


S/N D E S C R I P T I O N.
41 Preparing the surface and painting with plastic emulsion of approvied makd (Old
(a) surface.)

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
i Plastic emulsion. 0.20 GALL 2200.00 P.GALL 440.00

ii Brushes etc. L.S 10.00

TOTAL 450.00
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 687/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 45.00


_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 495.00
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
(i) Painter. 0.50 NO 450.00 P.DAY 225.00

(ii) Coolie. 0.15 NO 250.00 P.DAY 37.50

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 262.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 26.25
_____________________________ __________ _____ ________ ______ ________
TOTAL 288.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 28.88
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 317.63
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 812.63
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 812.63

S/N D E S C R I P T I O N.
41 Preparing the surface and painting with plastic emulsion of approvied makd (Old
(b) surface.)

2ND AND SUBSEQUENT

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
i Plastic emulsion. 0.15 GALL 2200.00 P.GALL 330.00

ii Brushes etc. L.S 10.00

Chapter No. 8 688/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ _____ ________ ______ ________


TOTAL 340.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 34.00
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 374.00
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
(i) Painter. 0.30 NO 450.00 P.DAY 135.00

(ii) Coolie. 0.10 NO 250.00 P.DAY 25.00

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 160.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 16.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 176.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 17.60
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 193.60
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 567.60
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 567.60
_____ _____________________________ __________ _____ ________ ______ ________

S/N D E S C R I P T I O N.
42 Extra Labour for external surface for distemper / paint / while wash/ colour wash/
weather coast above 20' -0 height using long ladder or jhoola for each coat (for every
10'-0 additional height).

(Unit of rate per100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ _______________
i Painter 0.3 NO 450.00 P.DAY 148.50

Chapter No. 8 689/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

ii Coolie. 0.10 NO 250.00 P.DAY 25.00

iii Hire charges of jhoola etc. 15.00

_____________________________ __________ _____ ________ ______ ________


TOTAL 188.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 18.85
_____________________________ __________ _____ ________ ______ ________
TOTAL 207.35
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 20.74
_____________________________ __________ _____ ________ ______ ________
TOTAL (LABOUR) 228.09
_____________________________
Total material & labour for 100 Rft. 228.09
Total material & labour for 1 Rft. 2.28
Total material & labour per Rft. 2.28

_____ _____________________________ __________ _____ ________ ______ ________

_____ _____________________________ __________ _____ ________ ______ ________


S/N D E S C R I P T I O N.
43 Preparing the surface anjd applying rock wall / shield (Natural wall Texture ) coation to
provide durablecrust wall, thickness b/w 2mm to 32mm (1/8" ) with acrylic co-polymer
emulsion, selected marble chips, adhesive and bactericdes, water resistance and fire
and termite resistante (Upto 20' -0 height).

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________

Chapter No. 8 690/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

i Acrylic quartz co-polymeer emulsion 110.00 SFT 30.00 P.SFT 3300.00


compound i/c 10% wastage.
25.00
ii T&P

_____________________________ __________ _____ ________ ______ ________


TOTAL 3325.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 332.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 3657.50
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
(i) Mason skilled 1.00 NO 450.00 P.DAY 450.00

(ii) Coolie. 1.00 NO 250.00 P.DAY 250.00

_____________________________ __________ _____ ________ ______ ________


TOTAL Rs: 700.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 70.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 770.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 77.00
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 847.00
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 4504.50
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 4504.50

Chapter No. 8 691/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
44 Providing & fixing colour Crete to wall surface to provide, durable crust and aesthetics
having thickness upto 3/4" with specified colour having water, fire3 and temite resitance
(upto 20' -0 height).

(Unit of rate per 100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ ______ ________
i Colour crete Mixture i/c 10% wastage. 110.00 SFT 45.00 P.SFT 4950.00

ii T&P. 25.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 4975.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 497.50
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " A " 5472.50
_____________________________ __________ _____ ________ ______ ________
(B) LABOUR
_____________________________ __________ _____ ________ ______ ________
(i) Mason skilled 1.00 NO 450.00 P.DAY 450.00

(ii)
Coolie. 1.00 NO 250.00 P.DAY 250.00
_____________________________ __________ _____ ________ ______ ________
TOTAL Rs: 700.00
_____________________________ __________ _____ ________ ______ ________
Sundries. 10.00 % 70.00
_____________________________ __________ _____ ________ ______ ________
TOTAL 770.00
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 77.00
_____________________________ __________ _____ ________ ______ ________
TOTAL PART " B " 847.00
_____________________________ __________ _____ ________ ______ ________
TOTAL (MATERIAL + LABOUR) 6319.50
_____________________________ __________ _____ ________ ______ ________
Total material & labour for 100 Sft. say Rs: 6319.50
_____ _____________________________ __________ _____ ________ ______ ________

Chapter No. 8 692/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____ _____________________________ __________ _____ ________ ______ ________


S/N D E S C R I P T I O N.
45 Add extra labour for rock wall/ colour Crete above 20,-0 height requiring scaffolding etc:
for every 10' -0 additional height).

(Unit of rate per100 Sft.)


_____ _____________________________ __________ _____ ________ ______ ________
(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ _____ ________ _______________
i Mason skilled 0.3 NO 450.00 P.DAY 112.50

ii Coolie. 0.10 NO 250.00 P.DAY 25.00

iii Hire charges of scafolding 25.00

_____________________________ __________ _____ ________ ______ ________


TOTAL 162.50
_____________________________ __________ _____ ________ ______ ________
Sundries. 16.25
_____________________________ __________ _____ ________ ______ ________
TOTAL 178.75
_____________________________ __________ _____ ________ ______ ________
Contractor's profit 10.00 % 17.88
_____________________________ __________ _____ ________ ______ ________
TOTAL (LABOUR) 196.63
_____________________________
Total material & labour for 100 Rft. 196.63
Total material & labour for 1 Rft. 1.97
Total material & labour per Rft. 1.97
_____ _____________________________ __________ _____ ________ ______ ________

Chapter No. 8 693/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

first fill this sheet


WOOD WORK
MATERIAL RATE UNIT

1 Deodar wood (1st quality) 4500 P.Cft

2 Shisham wood 2300 P.Cft

3 Iron work 4450 P.Cwt

4 Iron screw 1" long 210 % Nos

5 Teak wood (Ist quality) 9300 P.Cft

6 Hinges of 5 " size / Butt Hunges. 400 P.doz

7 Tower bolts 18" size 1225 P.doz

8 Tower bolts 9" size 625 P.doz

9 Handles (Brass) 8" size 210 Each

10 Iron Hold fast 90 Each

11 Hinged chocks of 6" size 375 P.doz

12 Door stoper 8" size (Deodar) 600 P.doz

13 Screws of sorts 315 P.grass

14 Hings of Iron 4" size 310 P.doz

15 Hinged chocks of 4" size 225 P.doz

16 Door stoper 6" size (Deodar) 500 P.doz

17 Wire gauze 144 mesh 50 P.Sft

18 Nails 110 P.Kg

19 Wooden plugs 3 Each

20 Expanded metal 3/32(20 gauge) 39 P.Sft

21 Aungle Iron 3575 P.Cwt

22 Deodar wood (Second quality) 4000 P.Cft

23 Ply wood sheet (3-ply) 75 P.Sft

Chapter No. 9 694/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

24 Mortice lock i/c fixing (English) 1500 Each

25 T-Hinges of 8", 10 " size 390 P.doz

26 Tower bolt 12" size 775 P.doz

27 Bolt with striples for paid lock of 675 P.doz


8" size

28 Haspand staple (Brass) 650 P.doz

29 Handles of 6" size 275 P.doz

30 22 gauge C I Sheet 5000 P.Cwt

31 Bolts of 1-1/2" size 50 Each

32 Brass finger Plates 485 Each

33 Tower bolt (Brass) 6" size 775 P.doz

34 Brass Screw of 1-1/2" size 300 % Nos

35 Brass Screw of 1" size 175 % Nos

36 Screw of 1" and 1-1/2" size 110 P.doz

37 Brass spring hinges complete 690 Each


with screw

38 Sliding bolt complete with 1750 P.doz


screw and Nut 10" Long

39 Sliding bolt complete with 1950 P.doz


screw and Nut 12" Long

40 Brass Tower bolt 9" size 1600 P.doz

41 Brass Hand bolt 6 " size 775 P.doz

42 Brass Butt Hinges 2" size 435 P.doz

43 Rim lock complete with Screw (Pak) 300 Each

44 Brass Hinges of 3" size. 435 P.doz

45 Wooden guttles 1.00 Each

46 Brass Hinges of 4" size 625 P.Doz

47 Sunk handles 315 P.doz

Chapter No. 9 695/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

48 wooden Beading 35 P.Rft

49 Tie Rod 190 P.Rft

50 Wooden Rod with shoes 35 P.Rft

51 Mirror 2' x1" 500 P.Sq.ft

52 Hanger Hook i/c pull uot Rod 260 P.Rft

53 Zink plate 700 P.Sft

54 Iron grill 175 P.Sft

55 Bolt with washer 225 P.doz

56 Hanger of 2" size 175 P.doz

57 Braks Hooks 180 P.doz

58 Sand Paper. 12.50 Each

59 Kail or chir wood 2000 P.Cft

60 Hooks 400 P.doz

61 Masonite / baco lite sheet 160 P.Sft

62 Bolt 1/2" dia and 3" Long 300 P.Sft

63 Steel Rod 4750 P.Cwt

64 Washers 56 P.doz

65 Kikar wood 1400 P.Cft

66 Glass Pan (16 - 18 OZ) 80 P.Sft

67 Glass Pan (24- 26 OZ) 95 P.Sft

68 Plate glan 1/4 " th 125 P.Sft

69 Partal wood 1700 P.Cft

70 Teak ply wood sheet 120 P.sft

71 Iron sliding bolt 12" Long 1950 P.doz

72 Tower Bolt 8" size 600 P.doz

Chapter No. 9 696/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

73 Gums /Glue 386 P.Kg

74 Plaster of paris sheets 85 P.Sft

75 Soliginum paint. 1525 P.Cwt

76 Steel bar ordinary 3550 P.Cwt

77 Wall panel sheet (4mm) 40 P.Sft

78 Wood beeding. 35 P.Rft.

79 Aluminum Sheet 35 P.Sft

80 Aluminum Wire gauge 75 P.Sft

81 Crimped GI mesh 1" - 1/2 gauge 63 P.Sft

82 Window Bilds 60 P.Sft

83 Window Bilds Printed 65 P.Sft

84 Welded Wire 18 P.Sft

85 Welding Rod 35 each

LABOUR RATE UNIT

1 Carpanter , Black smith, Masson. 450 P.day

2 Skilled Coolu ,Hammer man 250 P.day

3 Coolies 250 P.day

4 Sawyer, Carpanter, Glazies 400 P.day

Chapter No. 9 697/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N WOOD WORK


=================
D E S C R I P T I O N.

1. Plain wood work (sawn) wrought planed and framed in position


including cost of nails and screws etc.

(a) Deodar wood.


____ ______________________________ ______ ______ ______ ________ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood = 1.00 Cft.
Wastage 15% = 0.15 Cft.
Total = 1.15 Cft.

______________________________ ______ ______ ______ ________ _________


Deodar wood. 1.15 Cft. 4500.00 P.Cft. 5175.00

Nails and screws. L.S 5.00

______________________________ ______ ______ ______ ________ _________


TOTAL 5180.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 518.00
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 5698.00
______________________________ ______ ______ ______ ________ _________
(B) LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.63 Nos: 450.00 P.day. 283.50

Cooly skilled. 0.25 Nos: 250.00 P.day. 62.50

______________________________ ______ ______ ______ ________ _________


Rs: 346.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 34.60
______________________________ ______ ______ ______ ________ _________
TOTAL 380.60
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 38.06
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 418.66
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 6116.66
______________________________ ______ ______ ______ ________ _________
Total material & labour per Cft. Rs: 6116.66
____ ______________________________ ______ ______ ______ ________ _________

Chapter No. 9 698/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ______________________________ ______ ______ ______ ________ _________


S/N WOOD WORK
=================
D E S C R I P T I O N.

1. Plain wood work (sawn) wrought planed and framed in position


including cost of nails and screws etc.

(b) Shisham wood.


____ ______________________________ ______ ______ ______ ________ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Shisham wood = 1.00 Cft.
Wastage 20% = 0.20 Cft.
Total = 1.20 Cft.

______________________________ ______ ______ ______ ________ _________


Shisham wood. 1.20 Cft. 2300.00 P.Cft. 2760.00

Nails and screws. L.S 5.00

TOTAL 2765.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 276.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 3041.50
______________________________ ______ ______ ______ ________ _________
(B) LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 1.00 Nos: 450.00 P.day. 450.00

Cooly skilled. 0.50 Nos: 250.00 P.day. 125.00

______________________________ ______ ______ ______ ________ _________


Rs: 575.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 57.50
______________________________ ______ ______ ______ ________ _________
TOTAL 632.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 63.25
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 695.75
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 3737.25
______________________________ ______ ______ ______ ________ _________
Total material & labour per Cft. Rs: 3737.25

Chapter No. 9 699/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ______________________________ ______ ______ ______ ________ _________


S/N WOOD WORK
=================
D E S C R I P T I O N.
2. Plain wood work sawing wroughting for regulation karries or
needles, etc.
(a) Deodar wood.
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Take kari 10.2' long 0.4' * 0.4' in section 1.63 Cft.
Wastage 15% 0.24 Cft.
Total wood required for 1.63 Cft of kari. 1.87 Cft.
IRON WORK.
1.60' long iron strip 1-1/2" wide.
1.60 * 0.625 lbs/Rft = 1.00 Lbs.
2*1-1/4' long iron bars 3/4" dia at both ends.
2*1.25*1.502 lbs/Rft = 3.80 Lbs.
Total 4.80 Lbs.
Wastage 10% 0.48 Lbs.
Total iron work 5.28 Lbs.
______________________________ ______ ______ ______ ________ _________
Deodar wood. 1.87 Cft. 4500.00 P.Cft. 8415.00

Iron work. 5.28 Lbs. 4450.00 P.Cwt 209.79

Iron screws 1" long. 8.00 Nos: 210.00 % Nos: 16.80


TOTAL 8641.59
Contractor's profit 10.00 % 864.16
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 9505.74
______________________________ ______ ______ ______ ________ _________
(B) LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.53 Nos: 450.00 P.day. 238.50

Cooly skilled. 0.40 Nos: 250.00 P.day. 100.00


______________________________ ______ ______ ______ ________ _________
Rs: 338.50
Sundries. 10.00 % 33.85
______________________________ ______ ______ ______ ________ _________
TOTAL 372.35
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 37.24
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 251.28 409.59
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 9915.33
______________________________ ______ ______ ______ ________ _________
Total material & labour for 1.63 Cft. Rs: 9915.33
Total material & labour per Cft. Rs: 6083.02
Total material & labour per Cft. say Rs: 6083.02

Chapter No. 9 700/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N WOOD WORK


=================
D E S C R I P T I O N.
2. Plain wood work sawing wroughting for regulation karries or
needles, etc.
(b) Sheesham wood.
____ ______________________________ ______ ______ ______ ________ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Take kari 10.2' long 0.4' * 0.4' in section 1.63 Cft.
Wastage 20% 0.33 Cft.
Total wood required for 1.63 Cft of kari. 1.96 Cft.
IRON WORK.
1.60' long iron strip 1-1/2" wide.
1.60 * 0.625 lbs/Rft = 1.00 Lbs.
2*1-1/4' long iron bars 3/4" dia at both ends.
2*1.25*1.502 lbs/Rft = 3.80 Lbs.
Total 4.80 Lbs.
Wastage 10% 0.48 Lbs.
Total iron work 5.28 Lbs.
______________________________ ______ ______ ______ ________ _________
Sheesham wood. 1.96 Cft. 2300.00 P.Cft. 4508.00

Iron work. 5.28 Lbs. 4450.00 P.Cwt 209.79

Iron screws 1" long. 8.00 Nos: 210.00 % Nos: 16.80


TOTAL 4734.59
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 473.46
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 5208.04
______________________________ ______ ______ ______ ________ _________
(B) LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 1.00 Nos: 450.00 P.day. 450.00

Cooly skilled. 0.40 Nos: P.day.


250.00 100.00
Rs: 550.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 55.00
TOTAL 605.00
Contractor's profit 10.00 % 60.50
TOTAL PART " B " 408.28 665.50
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 5873.54
______________________________ ______ ______ ______ ________ _________
Total material & labour for 1.63 Cft. Rs: 5873.54
Total material & labour per Cft. Rs: 3603.40
Total material & labour per Cft. say Rs: 3603.40

Chapter No. 9 701/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
3. Teak wood wrought framed and fixed in place including chowkhats
hold fasts, tower bolts, chocks, cleats, handles, cord with
hooks and cost of nails and screws, etc.

(a) Panelled or panelled and glazed or fully glazed 2" thick.

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Teak wood for H.rail =1*5'-3/4"*3-1/2"*4-1/2" 0.63 Cft.
Teak wood for V.rail =2*8'-1/4'*3-1/2"*4-1/2" 1.80 Cft.
Double leaf shutters =1*4'-1/2'*7'-2/3'*1/6' 5.75 Cft.
Total 8.18 Cft.
Wastage 10% 0.82 Cft.
Teak wood required for door of 5'*8' size 9.00 Cft.
______________________________ ______ ______ ______ ________ _________
Teak wood. 9.00 Cft. 9300.0 P.Cft. 83700.00
Hinges of 5" size. 6.00 Nos: 18.00 P.doz: 9.00
Tower bolts 18" size. 2.00 Nos: 1225.00 P.doz: 204.17
Tower bolts 9" size. 2.00 Nos: 625.00 P.doz: 104.17
Handles. (BRASS) 8" size. 3.00 Nos: 210.00 Each. 630.00
Iron hold fasts. 6.00 Nos: 90.00 Each. 540.00
Hinged chocks of 6" size. 2.00 Nos: 375.00 P.doz: 62.50
Door stopers of 8" size. 2.00 Nos: 600.00 P.doz: 100.00
Screws of sorts. 2.50 Doz: 315.00 P.Gross 65.63
Spikes. L.S 9.00
Glue. L.S 22.00
TOTAL 85446.46
Contractor's profit 10.00 % 8544.65
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 93991.10
(B) LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 13.50 Nos: 450.00 P.day. 6075.00

Cooly skilled. 3.00 Nos: 250.00 P.day. 750.00


______________________________ ______ ______ ______ ________ _________
Rs: 6825.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 682.50
TOTAL 7507.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 750.75
TOTAL PART " B " 206.46 8258.25
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 102249.35
Total material & labour for 40 Sft. Rs: 102249.35
Total material & labour per Sft. Rs: 2556.23
Total material & labour per Sft. say Rs: 2556.23
S/N D E S C R I P T I O N.

Chapter No. 9 702/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

3. Teak wood wrought framed and fixed in place including chowkhats


hold fasts, tower bolts, chocks, cleats, handles, cord with
hooks and cost of nails and screws, etc.

(b) Panelled or panelled and glazed or fully glazed 1-3/4" thick.

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
Teak wood for H.rail =1*4'-3/4'*3"*4-1/2" 0.45 Cft.
Teak wood for V.rail =2*7'-1/4'*3"*4-1/2" 1.36 Cft.
Double leaf shutters=1*3'-7/12'*6'-2/3'*1-3/4" 3.48 Cft.
Total 5.29 Cft.
Wastage 12% 0.63 Cft.
Teak wood required for door of 4'*7' size 5.92 Cft.
______________________________ ______ ______ ______ ________ _________
Teak wood. 5.92 Cft. 9300.0 P.Cft. 55056.00
Hinges of 4" size. 6.00 Nos: 310.00 P.doz: 155.00
Tower bolts 9" size. 3.00 Nos: 625.00 P.doz: 156.25
Handles. 8" size. 3.00 Nos: 210.00 Each. 630.00
Iron hold fasts. 4.00 Nos: 90.00 Each. 360.00
Hinged chocks of 4" size. 2.00 Nos: 225.00 P.doz: 37.50
Door stopers of 6" size. 2.00 Nos: 500.00 P.doz: 83.33
Screws of sorts. 2.50 Doz: 315.00 P.Gross 65.63
Spikes. L.S 9.00
Glue. L.S 22.00
TOTAL 56574.71
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 5657.47
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 62232.18
(B) LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 9.50 Nos: 450.00 P.day. 4275.00

Cooly skilled. 2.00 Nos: 250.00 P.day. 500.00


______________________________ ______ ______ ______ ________ _________
Rs: 4775.00
Sundries. 10.00 % 477.50
______________________________ ______ ______ ______ ________ _________
TOTAL 5252.50
Contractor's profit 10.00 % 525.25
TOTAL PART " B " 206.35 5777.75
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 68009.93
______________________________ ______ ______ ______ ________ _________
Total material & labour for 28 Sft. Rs: 68009.93
Total material & labour per Sft. Rs: 2428.93
Total material & labour per Sft. say Rs: 2428.93

Chapter No. 9 703/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
4. First class teak wood wrought joinery in wire gauze doors and
windows with frames and 22 standard wire gauze 144 mesh per
square inch including brass fittings complete.
(a) Framing including wire gauze with ordinary hinges and fixed in
position 1-3/4" thick.

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Teak wood for Top rail=1*4'-1/2'*4-1/2"*1-3/4" 0.25 Cft.
Teak wood for Lock rail=1*4'-1/2'*7"*1-3/4" 0.38 Cft.
Teak wood for Bottom rail=1*4'-1/2'*9"*1-3/4" 0.49 Cft.
Hanging styles = 2 * 7'-2/3'* 3"-3/8"*1-3/4" 0.63 Cft.
Fillets = 4* 6'-5/24' * 3/4" * 3/4" 0.09 Cft.
Fillets = 4 * 3'-1/4' * 3/4" * 3/4" 0.05 Cft.
Total. 1.89 Cft.
Wastage 10% 0.19 Cft.
Total wood required for 4'-1/2'*7'-5/8'frame. 2.08 Cft.
Wire gauze 144 mesh per sq-inch.
Double leaf shutters =1*3'-7/16'*6'-5/24' 21.34 Sft.
Wastage L.S. 0.66 Sft.
Grand Total 22.00 Sft.
______________________________ ______ ______ ______ ________ _________
Teak wood. 2.08 Cft. 9300.0 P.Cft. 19344.00
Wire gauze 144 mesh/sq-in. 22.00 Sft. 50.00 P.Sft. 1100.00
Hinges of 5" size. 6.00 Nos: 400.00 P.doz: 200.00
Tower bolts 9" size. 2.00 Nos: 625.00 P.doz: 104.17
Handles. 8" size. 2.00 Nos: 210.00 Each. 420.00
Hinged chocks of 6" size. 2.00 Nos: 375.00 P.doz: 62.50
Nails. 0.125 Kg 110.00 P.Kg 13.75
Screws of sorts. 6.00 Doz: 315.00 P.Gross. 157.50
Spikes. L.S 9.00
Glue. L.S 22.00
______________________________ ______ ______ ______ ________ _________
TOTAL 21432.92
Contractor's profit 10.00 % 2143.29

______________________________ ______ ______ ______ ________ _________


TOTAL PART " A " 23576.21
______________________________ ______ ______ ______ ________ _________
(B) LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 3.00 Nos: 450.00 P.day. 1350.00
Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 1600.00
Sundries. 10.00 % 160.00
______________________________ ______ ______ ______ ________ _________
TOTAL 1760.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 176.00

Chapter No. 9 704/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


TOTAL PART " B " 56.08 1936.00
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 25512.21
______________________________ ______ ______ ______ ________ _________
Total material & labour for 34.52 Sft. Rs: 25512.21
Total material & labour per Sft. Rs: 739.06
Total material & labour per Sft. say Rs: 739.06

Chapter No. 9 705/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4. First class teak wood wrought joinery in wire gauze doors and
windows with frames and 22 standard wire gauze 144 mesh per
square inch including brass fittings complete.
(b) Framing including wire gauze with ordinary hinges and fixed in
position 1-1/2" thick.
____ ______________________________ ______ ______ ______ ________ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Teak wood for Top rail=1*3'-7/12'*4"*1-1/2" 0.15 Cft.
Teak wood for Lock rail=1*3'-7/12'*6"*1-1/2" 0.22 Cft.
Teak wood for Bottom rail=1*3'-7/12'*8"*1-1/2" 0.30 Cft.
Horizontal styles = 2*6'-17/24' * 4" * 1-1/2" 0.56 Cft.
Horizontal styles = 2*6'-17/24' * 3" * 1-1/2" 0.42 Cft.
Fillets = 4 * 2'-2/3' * 3/4" * 3/4" 0.04 Cft.
Fillets = 4 * 5'-1/24'* 3/4" * 3/4" 0.08 Cft.
Total. 1.77 Cft.
Wastage 10% 0.17 Cft.
Total wood required for 3'-7/12'*6'-7/12'frame. 1.94 Cft.
Wire gauze 144 mesh per sq-inch.
Double leaf shutters =1*2'-2/3'* 5'-1/12' 13.56 Sft.
Wastage L.S. 0.44 Sft.
Grand Total 14.00 Sft.
______________________________ ______ ______ ______ ________ _________
Teak wood. 1.94 Cft. 9300.0 P.Cft. 18042.00
Wire gauze 144 mesh/sq-in. 14.00 Sft. 50.00 P.Sft. 700.00
Hinges of 5" size. 4.00 Nos: 400.00 P.doz: 133.33
Tower bolts 9" size. 2.00 Nos: 625.00 P.doz: 104.17
Handles.(BRASS) 8" size. 2.00 Nos: 210.00 Each. 420.00
Hinged chocks of 4" size. 2.00 Nos: 225.00 P.doz: 37.50
Nails. 0.125 Kg 110.00 P.Kg 13.75
Screws of sorts. 6.00 Doz: 315.00 P.Gross 157.50
Spikes. L.S 9.00
Glue. L.S 22.00
______________________________ ______ ______ ______ ________ _________
TOTAL 19639.25
Contractor's profit 10.00 % 1963.93
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 21603.18
______________________________ ______ ______ ______ ________ _________
(B) LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 2.25 Nos: 450.00 P.day. 1012.50
Cooly skilled. 0.40 Nos: 250.00 P.day. 100.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 1112.50
Sundries. 10.00 % 111.25
______________________________ ______ ______ ______ ________ _________
TOTAL 1223.75
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 706/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 122.38


______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 57.06 1346.13
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 22949.30
______________________________ ______ ______ ______ ________ _________
Total material & labour for 23.59 Sft. Rs: 22949.30
Total material & labour per Sft. Rs: 972.84
Total material & labour per Sft. say Rs: 972.84

____ ______________________________ ______ ______ ______ ________ _________

Chapter No. 9 707/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4. First class teak wood wrought joinery in wire gauze doors and
windows with frames and 22 standard wire gauze 144 mesh per
square inch including brass fittings complete.
(c) Galvanized wire gauze fixed to chowkhats with 3/4" teak wood
strip and screws.
____ ______________________________ ______ ______ ______ ________ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Teak wood Horizontal strips=2*3'*3"*3/4" 0.09 Cft.
Teak wood Vertical strips =2*3'-1/2'*3"*3/4" 0.11 Cft.
Total. 0.2 Cft.
Wastage 50% 0.10 Cft.
Total wood required for 3' * 4' window 0.30 Cft.
Wire gauze 144 mesh per sq-inch.
Window 3' * 4' 12 Sft.
Wastage L.S. 0.6 Sft.
Grand Total 12.60 Sft.
______________________________ ______ ______ ______ ________ _________
Teak wood. 0.30 Cft. 9300.0 P.Cft. 2790.00
Wire gauze 144 mesh/sq-in. 12.60 Sft. 50.00 P.Sft. 630.00
Nails. 0.063 Kg 110.00 P.Kg 6.88
Screws of sorts. 1.00 Doz: 315.00 P.Gross 26.25
______________________________ ______ ______ ______ ________ _________
TOTAL 3453.13
Contractor's profit 10.00 % 345.31
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 3798.44
______________________________ ______ ______ ______ ________ _________
(B) LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.50 Nos: 450.00 P.day. 225.00
Cooly skilled. 0.25 Nos: 250.00 P.day. 62.50
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 287.50
Sundries. 10.00 % 28.75
______________________________ ______ ______ ______ ________ _________
TOTAL 316.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 31.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 28.99 347.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 4146.31
______________________________ ______ ______ ______ ________ _________
Total material & labour for 12.0 Sft. Rs: 4146.31
Total material & labour per Sft. Rs: 345.53
Total material & labour per Sft. say Rs: 345.53

Chapter No. 9 708/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
4. First class teak wood wrought joinery in wire gauze doors and
windows with frames and 22 standard wire gauze 144 mesh per
square inch including brass fittings complete.
(d) Galvanized wire gauze fixed to chowkhats with 1/2" teak wood
strips on seperate 2" * 2" teak wood frame for C.windows.
C.Widow 4' * 2'
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Teak wood Horizontal rail=2*4'*2"*2" 0.22 Cft.
Teak wood Vertical rail=2*2'*2"*2" 0.11 Cft.
Teak wood Horizontal strips=2*4'*2"*1/2" 0.05 Cft.
Teak wood Vertical strips=2*2'*2"*1/2" 0.03 Cft.
Mouldings. L.S 0.06
Total. 0.47 Cft.
Wastage 40% 0.18 Cft.
Total wood required for 3' * 4' window 0.65 Cft.
Wire gauze 144 mesh per sq-inch.
Window 4' * 2' 8.00 Sft.
Wastage L.S. 1.00 Sft.
Grand Total 9.00 Sft.
______________________________ ______ ______ ______ ________ _________
Teak wood. 0.65 Cft. 9300.0 P.Cft. 6045.00
Wire gauze 144 mesh/sq-in. 9.00 Sft. 50.00 P.Sft. 450.00
Nails. 0.042 Kg 110.00 P.Kg 4.58
Screws of sorts. 1.00 Doz: 315.00 P.Gross. 26.25
Wooden plugs. 4.00 Nos: 3 Each. 12.00
______________________________ ______ ______ ______ ________ _________
TOTAL 6537.83
Contractor's profit 10.00 % 653.78
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 7191.62
______________________________ ______ ______ ______ ________ _________
(B) LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.50 Nos: 450.00 P.day. 225.00
Cooly skilled. 0.25 Nos: 250.00 P.day. 62.50
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 287.50
Sundries. 10.00 % 28.75
______________________________ ______ ______ ______ ________ _________
TOTAL 316.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 31.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 43.48 347.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 7539.49
______________________________ ______ ______ ______ ________ _________
Total material & labour for 8.0 Sft. Rs: 7539.49
Total material & labour per Sft. Rs: 942.44

Chapter No. 9 709/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour per Sft. say Rs: 942.44

Chapter No. 9 710/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

5. Expanded metal 1/2" to 3/4" mesh 16 gauge fixed in chowkhats


with 1" cover moulding and screws including teak wood frame 2" *
2". (C.W 4' * 2' = 8 Sft.)
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Teak wood Horizontal rail=2*4'*2"*2" 0.22 Cft.
Teak wood Vertical rail=2*2'*2"*2" 0.11 Cft.
Teak wood Horizontal strips=2*4'*2"*1/2" 0.05 Cft.
Teak wood Vertical strips=2*2'*2"*1/2" 0.03 Cft.
Mouldings. L.S 0.06
Total. 0.47 Cft.
Wastage 40% 0.18 Cft.
Total wood required for 3' * 4' window 0.65 Cft.
Expanded metal.
Window 4' * 2' 8.00 Sft.
Wastage L.S. 1.00 Sft.
Grand Total 9.00 Sft.
______________________________ ______ ______ ______ ________ _________
Teak wood. 0.65 Cft. 9300.0 P.Cft. 6045.00
Expanded metal. 9.00 Sft. 39.00 P.Sft. 351.00
Nails. 0.250 Kg 110 P.Kg 27.50
Wooden plugs. 4.00 Nos: 3 Each. 12.00
______________________________ ______ ______ ______ ________ _________
TOTAL 6435.50
Contractor's profit 10.00 % 643.55
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 7079.05
______________________________ ______ ______ ______ ________ _________
(B) LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.50 Nos: 450.00 P.day. 225.00
Cooly skilled. 0.25 Nos: 250.00 P.day. 62.50
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 287.50
Sundries. 10.00 % 28.75
______________________________ ______ ______ ______ ________ _________
TOTAL 316.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 31.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 43.48 347.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 7426.93
______________________________ ______ ______ ______ ________ _________
Total material & labour for 8.0 Sft. Rs: 7426.93
Total material & labour per Sft. Rs: 928.37
Total material & labour per Sft. say Rs: 928.37

Chapter No. 9 711/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

6. Expanded metal 1/2" to 3/4" mesh 16 gauge fixed in chowkhats


with 3/4" teak wood strips and screws.
(window size 3' * 4' = 12 Sft.)

____ ______________________________ ______ ______ ______ ________ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Teak wood Horizontal strips=2*3'*3"*3/4" 0.09 Cft.
Teak wood Vertical strips =2*3'-1/2'*3"*3/4" 0.11 Cft.
Total. 0.2 Cft.
Wastage 50% 0.10 Cft.
Total wood required for 3' * 4' window 0.30 Cft.
Expanded material.
Window 3' * 4' 12 Sft.
Wastage L.S. 1 Sft.
Grand Total 13.00 Sft.
______________________________ ______ ______ ______ ________ _________
Teak wood. 0.30 Cft. 9300.0 P.Cft. 2790.00
Expanded material. 13.00 Sft. 39.00 P.Sft. 507.00
Nails and screws.. 0.300 Kg 110 P.Kg 33.00

______________________________ ______ ______ ______ ________ _________


TOTAL 3330.00
Contractor's profit 10.00 % 333.00
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 3663.00
______________________________ ______ ______ ______ ________ _________
(B) LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.50 Nos: 450.00 P.day. 225.00
Cooly skilled. 0.25 Nos: 250.00 P.day. 62.50
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 287.50
Sundries. 10.00 % 28.75
______________________________ ______ ______ ______ ________ _________
TOTAL 316.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 31.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 28.99 347.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 4010.88
______________________________ ______ ______ ______ ________ _________
Total material & labour for 12.0 Sft. Rs: 4010.88
Total material & labour per Sft. Rs: 334.24
Total material & labour per Sft. say Rs: 334.24

Chapter No. 9 712/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
7.
First class deodar wood wrought framed and fixed in place
including chowkhats hold fasts, tower bolts, chocks, cleats,
handles, cord with hooks and cost of nails and screws, etc.
(a)
(A) Panelled or panelled and glazed or fully glazed 2" thick.
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Deodar wood for H.rail=1*5'-3/4"*3-1/2"*4-1/2" 0.63 Cft.
Deodar wood for V.rail=2*8'-1/4'*3-1/2"*4-1/2" 1.80 Cft.
Double leaf shutters =1*4'-1/2'*7'-2/3'*1/6' 5.75 Cft.
Total 8.18 Cft.
Wastage 15% 1.23 Cft.
Deodar wood required for door of 5'*8' size 9.41 Cft.
______________________________ ______ ______ ______ ________ _________
Deodar wood. 9.41 Cft. 4500.00 P.Cft. 42345.00
Hinges of 5" size. 6.00 Nos: 400.00 P.doz: 200.00
Tower bolts 18" size. 2.00 Nos: 1225.00 P.doz: 204.17
Tower bolts 9" size. 2.00 Nos: 625.00 P.doz: 104.17
Handles.(BRASS) 8" size. 3.00 Nos: 210.00 Each. 630.00
Iron hold fasts. 6.00 Nos: 90.00 Each. 540.00
Hinged chocks of 6" size. 2.00 Nos: 375.00 P.doz: 62.50
Door stopers of 8" size. 2.00 Nos: 600.00 P.doz: 100.00
Screws of sorts. 2.50 Doz: 315.00 P.Gross 65.63
Spikes. L.S 9.00
Glue. L.S 22.00
______________________________ ______ ______ ______ ________ _________
TOTAL 44282.46
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 4428.25
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 48710.70
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 7.00 Nos: 450.00 P.day. 3150.00

Cooly skilled. 3.00 Nos: 250.00 P.day. 750.00


______________________________ ______ ______ ______ ________ _________
Rs: 3900.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 390.00
______________________________ ______ ______ ______ ________ _________
TOTAL 4290.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 429.00
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 117.98 4719.00
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 53429.70

Chapter No. 9 713/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


Total material & labour for 40 Sft. Rs: 53429.70
Total material & labour per Sft. Rs: 1335.74
____ Total material & labour per Sft. say Rs: 1335.74
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
7.
First class deodar wood wrought framed and fixed in place
including chowkhats hold fasts, tower bolts, chocks, cleats,
handles, cord with hooks and cost of nails and screws, etc.
(b)
Panelled or panelled and glazed or fully glazed 1-3/4" thick.
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Deodar wood for H.rail =1*4'-3/4'*3"*4-1/2" 0.45 Cft.
Deodar wood for V.rail =2*7'-1/4'*3"*4-1/2" 1.36 Cft.
Double leaf shutters=1*3'-7/12'*6'-2/3'*1-3/4" 3.48 Cft.
Total 5.29 Cft.
Wastage 17% 0.90 Cft.
Deodar wood required for door of 4'*7' size 6.19 Cft.
______________________________ ______ ______ ______ ________ _________
Deodar wood. 6.19 Cft. 4500.0 P.Cft. 27855.00
Hinges of 4" size. 6.00 Nos: 310.00 P.doz: 155.00
Tower bolts 9" size. 3.00 Nos: 625.00 P.doz: 156.25
Handles.(BRASS) 8" size. 3.00 Nos: 210.00 P.doz: 630.00
Iron hold fasts. 4.00 Nos: 90.00 Each. 360.00
Hinged chocks of 4" size. 2.00 Nos: 225.00 P.doz: 37.50
Door stopers of 6" size. 2.00 Nos: 500.00 P.doz: 83.33
Screws of sorts. 2.50 Doz: 315.00 P.Gross 65.63
Spikes. L.S 8.00
Glue. L.S 16.00
TOTAL 29366.71
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 2936.67
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 32303.38
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
Carpenter. 5.00 Nos: 450.00 P.day. 2250.00

Cooly skilled. 2.00 Nos: 250.00 P.day. 500.00


______________________________ ______ ______ ______ ________ _________
Rs: 2750.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 275.00
______________________________ ______ ______ ______ ________ _________
TOTAL 3025.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 302.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 118.84 3327.50

Chapter No. 9 714/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


TOTAL (MATERIAL + LABOUR) 35630.88
______________________________ ______ ______ ______ ________ _________
Total material & labour for 28 Sft. Rs: 35630.88
Total material & labour per Sft. Rs: 1272.53
____ Total material & labour per Sft. say Rs: 1272.53
______________________________ ______ ______ ______ ________ _________
____
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
8.
Providing and fixing in position, doors, windows and ventilators
of 2"*2"*1/4" angle iron frames and 1-3/4" thick commercial ply
wood (3 ply) on both sides, including hold fasts, cleats, iron
tower bolts, handles, hinges and one mortice lock.
____
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Frames Angle iron= 7'-2"+7'-2"+4'-0" = 18'-4" 18.33 Rft.
Wastage 10% 1.83 Rft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
(18.33+1.83)=20.16 Rft * 3.19 Lbs/Rft = 64.31 Lbs.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Hold fasts 4 Nos: of M.S. bars 3/4" dia & 9" long = 3 Rft.
= 3 Rft * 1.50 Lbs/Rft = 4.50 Lbs.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
SHUTTERS.
Core styles = 2 * 6'-11" * 4" *1-3/4" 0.67 Cft.
Rails top & bottom = 2 * 3'-11" * 6" * 1-3/4" 0.57 Cft.
Central lock rail = 1 * 3'-11" * 9" * 1-3/4" 0.43 Cft.
Rails between top rail, central lock rail and
bottom rail 3"wide = 2*3'-11" * 3" * 1-3/4" 0.29 Cft.
Vertical sashes = 4 * 5'-0" * 2" * 1-3/4" = 0.49 Cft.
Total 2.45 Cft.
Wastage 15% 0.37 Cft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total quantity of wood for 7' * 4' size door 2.82 Cft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Ply wood sheets = 2 * 6'-11" * 6'-11" 54.25 Sft.
Wastage 10% 5.43 Sft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total quantity of ply wood. 59.68 Sft.
______________________________ ______ ______ ______ ________ _________
Angle iron. 64.31 Lbs. 3575.0 P.Cwt. 2052.75

Angle iron. 4.50 Lbs. 3575.0 P.Cwt. 143.64

Deodar wood. (2nd class) 2.82 Cft. 4000.0 P.Cft. 11280.00

Ply wood sheets. 59.68 Sft. 75.00 P.Sft. 4476.00

Chapter No. 9 715/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Mortice lock i/c fixing. 1.00 Nos: 1500.00 Each. 1500.00


(ENGLISH)
Hinges of 5" size. 6.00 Nos: 400.00 P.doz: 200.00

Tower bolts 18" size. 2.00 Nos: 1225.00 P.doz: 204.17

Tower bolts 9" size. 2.00 Nos: 625.00 P.doz: 104.17

Handles.(BRASS) 8" size. 3.00 Nos: 210.00 Each. 630.00

Hinged chocks of 6" size. 2.00 Nos: 375.00 P.doz: 62.50

Door stopers of 8" size. 2.00 Nos: 600.00 P.doz: 100.00

____ Screws of sorts. 2.50 Doz: 315.00 P.Gross 65.63

Chapter No. 9 716/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________

Chapter No. 9 717/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N ______________________________ ______ ______ ______ ________ _________


D E S C R I P T I O N.
8.
Providing and fixing in position, doors, windows and ventilators
of 2"*2"*1/4" angle iron frames and 1-3/4" thick commercial ply
wood (3 ply) on both sides, including hold fasts, cleats, iron
tower bolts, handles, hinges and one mortice lock.
____ ( Continued )
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Spikes. L.S 9.00

Glue. L.S 22.00


______________________________ ______ ______ ______ ________ _________
TOTAL 20849.85
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 2084.98
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 22934.83
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 3.50 Nos: 450.00 P.day. 1575.00

Cooly with carpenter. 1.00 Nos: 250.00 P.day. 250.00

Black-smith. 1.00 Nos: 450.00 P.day. 450.00

Cooly with Black-smith. 1.00 Nos: 250.00 P.day. 250.00

Mason for fixing frame. 0.25 Nos: 400.00 P.day. 100.00


______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 2625.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 262.50
______________________________ ______ ______ ______ ________ _________
TOTAL 2887.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 288.75
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 113.44 3176.25
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 26111.08
______________________________ ______ ______ ______ ________ _________
Total material & labour for 28 Sft. Rs: 26111.08
Total material & labour per Sft. Rs: 932.54
____ Total material & labour per Sft. say Rs: 932.54
S/N ______________________________ ______ ______ ______ ________ _________

Chapter No. 9 718/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

9. D E S C R I P T I O N.
Providing and fixing in position doors, windows and ventilators
of first class deodar wood frames, and 1-3/4" thick commercial
ply veneer shutters of first class deodar skeleton (Hollow) and
commercial ply wood (3 ply) on both sides includinghold fasts,
hinges, iron tower bolts, handles and cleats with cord and one
____ Mortice lock and hooks.
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
First class deodar wood
Frames = 7'-2"+7'-2"+4'-0" = 18'-4" 18.33 Rft.
18.33 Rft * 4-1/2" * 3-1/2" 2.00 Cft.
Core styles = 2 * 6'-11" * 4" *1-3/4" 0.67 Cft.
Rails top & bottom = 2 * 3'-11" * 6" * 1-3/4" 0.57 Cft.
Central lock rail = 1 * 3'-11" * 9" * 1-3/4" 0.43 Cft.
Rails between top rail, central lock rail and
bottom rail 3"wide = 2*3'-11" * 3" * 1-3/4" 0.29 Cft.
Vertical sashes = 4 * 5'-0" * 2" * 1-3/4" = 0.49 Cft.
Total 4.45 Cft.
Wastage 15% 0.67 Cft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total quantity of wood for 7' * 4' size door 5.12 Cft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Ply wood sheets = 2 * 6'-11" * 6'-11" 54.25 Sft.
Wastage 10% 5.43 Sft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total quantity of ply wood. 59.68 Sft.
______________________________ ______ ______ ______ ________ _________
Deodar wood. (2nd class) 5.12 Lbs. 4000.0 P.Cft. 20480.00

Ply wood sheets. 59.68 Sft. 75.00 P.Sft. 4476.00

Mortice lock i/c fixing. 1.00 Nos: 1500.00 Each. 1500.00


(ENGLISH)
Hinges of 5" size. 6.00 Nos: 400.00 P.doz: 200.00

Tower bolts 18" size. 2.00 Nos: 1225.00 P.doz: 204.17

Tower bolts 9" size. 2.00 Nos: 625.00 P.doz: 104.17

Handles.(BRASS) 8" size. 3.00 Nos: 210.00 Each. 630.00

Iron hold fasts. 4.00 Nos: 90.00 Each. 360.00

Hinged chocks of 6" size. 2.00 Nos: 375.00 P.doz: 62.50

Door stopers of 8" size. 2.00 Nos: 600.00 P.doz: 100.00

____ Screws of sorts. 2.50 Doz: 315.00 P.Gross 65.63


9. D E S C R I P T I O N.

Chapter No. 9 719/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Providing and fixing in position doors, windows and ventilators


of first class deodar wood frames, and 1-3/4" thick commercial
ply veneer shutters of first class deodar skeleton (Hollow) and
commercial ply wood (3 ply) on both sides includinghold fasts,
hinges, iron tower bolts, handles and cleats with cord and one
Mortice lock and hoos.
____ ( Continued )
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Spikes. L.S 9.00

Glue. L.S 22.00


______________________________ ______ ______ ______ ________ _________
TOTAL 28213.46
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 2821.35
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 31034.80
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 5.00 Nos: 450.00 P.day. 2250.00

Cooly with carpenter. 1.50 Nos: 250.00 P.day. 375.00

Mason for fixing frame. 0.25 Nos: 400.00 P.day. 100.00


______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 2725.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 272.50
______________________________ ______ ______ ______ ________ _________
TOTAL 2997.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 299.75
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 117.76 3297.25
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 34332.05
______________________________ ______ ______ ______ ________ _________
Total material & labour for 28 Sft. Rs: 34332.05
Total material & labour per Sft. Rs: 1226.14
____ Total material & labour per Sft. say Rs: 1226.14
______________________________ ______ ______ ______ ________ _________
____
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
10.
Deodar wood framed braced and battened doors and windows

Chapter No. 9 720/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

complete with iron fittings and fixed in position including


chowkhats.
(a)
2-1/4" thick with 1-1/4" battens and 1" thick planks.
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Deodar wood for Top rail=1*3'-1/4'*3"*4-1/2" 0.35 Cft.
Deodar wood for V.rail =2*7'-1/4'*3"*4-1/2" 1.36 Cft.
Planks =1*2'-7/12'*6'-17/24'*1/12' 1.44 Cft.
Battens =3*6'-1/3' * 3/8'* 5'-9/24' 0.27
Branch. =2*3'-17/48' * 3/8' * 5/48' 0.31
Total 3.73 Cft.
Wastage 15% 0.56 Cft.
Deodar wood required for door of 3'*7' size 4.29 Cft.
______________________________ ______ ______ ______ ________ _________
Deodar wood. 4.29 Cft. 4500.0 P.Cft. 19305.00
T-Hinges of 10" size. 3.00 Nos: 390.00 P.doz: 97.50
Tower bolts 12" size. 1.00 Nos: 775.00 P.doz: 64.58
Tower bolts 9" size. 1.00 Nos: 625.00 P.doz: 52.08
Bolt with striples for paid 1.00 Nos: 675.00 P.doz: 56.25
lock of 8" size.
Iron hold fasts. 6.00 Nos: 90.00 Each. 540.00
Hinged chocks of 4" size. 1.00 Nos: 225.00 P.doz: 18.75
Door stopers of 6" size. 1.00 Nos: 500.00 P.doz: 41.67
Screws of sorts. 2.00 Doz: 315.00 P.Gross 52.50
Nails of sorts. 125 Gm 110.00 P.Kg 13.75
TOTAL 20242.08
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 2024.21
TOTAL PART " A " 22266.29
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 2.33 Nos: 450.00 P.day. 1050.00
Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00
______________________________ ______ ______ ______ ________ _________
Rs: 1300.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 130.00
______________________________ ______ ______ ______ ________ _________
TOTAL 1430.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 143.00
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 74.90 1573.00
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 23839.29
______________________________ ______ ______ ______ ________ _________
Total material & labour for 21 Sft. Rs: 23839.29
Total material & labour per Sft. Rs: 1135.20
____ Total material & labour per Sft. say Rs: 1135.20

Chapter No. 9 721/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N ______________________________ ______ ______ ______ ________ _________


D E S C R I P T I O N.
10.
Deodar wood framed braced and battened doors and windows
complete with iron fittings and fixed in position including
chowkhats.
(b)
1-3/4" thick with 1" battens and 3/4" thick planks.
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood for Top rail=1*3'-3/4'*3"*4-1/2" 0.35 Cft.
Deodar wood for V.rail =2*6'-1/4'*3"*4-1/2" 1.17 Cft.
Planks = 1*2'-7/12'*6'-5/24'*1/16' 1.00 Cft.
Ledges = 3 * 2'-1/3' * 1/3'* 1/12' 0.19
Braces =2*3'-13/20' * 1/3' * 1/12' 0.2
Total 2.91 Cft.
Wastage 15% 0.44 Cft.
Deodar wood required for door of 3'*6-1/2'size 3.35 Cft.
______________________________ ______ ______ ______ ________ _________
Deodar wood. 3.35 Cft. 4500.0 P.Cft. 15075.00
Hinges of 5" size. 3.00 Nos: 400.00 P.doz: 100.00
Tower bolts 9" size. 3.00 Nos: 625.00 P.doz: 156.25
Iron hold fasts. 4.00 Nos: 90.00 Each. 360.00
Hinged chocks of 4" size. 1.00 Nos: 225.00 P.doz: 18.75
Door stopers of 6" size. 1.00 Nos: 500.00 P.doz: 41.67
Screws of sorts. 2.00 Doz: 315.00 P.Gross 52.50
Nails of sorts. 125 Gm 110.00 P.Kg 13.75
TOTAL 15817.92
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 1581.79
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 17399.71
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 2.00 Nos: 450.00 P.day. 900.00
Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00
______________________________ ______ ______ ______ ________ _________
Rs: 1150.00
Sundries. 10.00 % 115.00
TOTAL 1265.00
Contractor's profit 10.00 % 126.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 71.36 1391.50
TOTAL (MATERIAL + LABOUR) 18791.21
Total material & labour for 19.50 Sft. Rs: 18791.21
Total material & labour per Sft. Rs: 963.65
____ Total material & labour per Sft. say Rs: 963.65
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.

Chapter No. 9 722/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

11.
1" thick battened doors and windows fited in position complete
with iron fittings without chowkhats.
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood =1*100' * 1/12' 8.33 Cft.
Wastage. L.S 1.17 Cft.
Cft.

Deodar wood required for 100 sft. 9.50 Cft.


______________________________ ______ ______ ______ ________ _________
Deodar wood. 9.50 Cft. 4500.0 P.Cft. 42750.00
Iron fittings, nails, L.S 288.00
bolts, etc.

______________________________ ______ ______ ______ ________ _________


TOTAL 43038.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 4303.80
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 47341.80
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 18.00 Nos: 450.00 P.day. 8100.00
Cooly skilled. 3.00 Nos: 250.00 P.day. 750.00
______________________________ ______ ______ ______ ________ _________
Rs: 8850.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 885.00
______________________________ ______ ______ ______ ________ _________
TOTAL 9735.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 973.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 107.085 10708.50
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 58050.30
______________________________ ______ ______ ______ ________ _________
Total material & labour for 100 Sft. Rs: 58050.30
Total material & labour per Sft. Rs: 580.50
____ Total material & labour per Sft. say Rs: 580.50
______________________________ ______ ______ ______ ________ _________
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
12.
Deodar battened ledged & braced doors and windows 2-1/4" thick

Chapter No. 9 723/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(1-1/4" thick ledge braces and 1" thick battens) complete with
iron fittings, chowkhats and fixed in position.
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood for Top rail=1*3'-0'* 3" *4-1/2" 0.19 Cft.
Deodar wood for V.rail =2*6'-3/4'*3"*4-1/2" 1.30 Cft.
Leaf = 1*2'-7"* 6'-3"*1/12' 1.35 Cft.
Ledges = 3* 2'-5-1/2" * 4"* 1-1/4" 0.26
Braces = 2 *3'-0' * 4" * 1-1/4" 0.20
Total 3.30 Cft.
Wastage 15% 0.50 Cft.
Deodar wood required for door of 3'*6-1/2'size 3.80 Cft.
______________________________ ______ ______ ______ ________ _________
Deodar wood. 3.80 Cft. 4500.0 P.Cft. 17100.00
Hinged chocks of 4" size. 1.00 Nos: 225.00 P.doz: 18.75
T- hinges of 8" size. 2.00 Nos: 390.00 P.doz: 65.00
Door stopers of 6" size. 1.00 Nos: 500.00 P.doz: 41.67
Tower bolts 9" size. 2.00 Nos: 625.00 P.doz: 104.17
Iron hold fasts. 4.00 Nos: 90.00 Each. 360.00
Hasp and staple. 1.00 Nos: 650.00 P.doz: 54.17
Handles of 6" size. 2.00 Nos: 275.00 P.doz: 45.83
Screws of sorts. 2.00 Doz: 315.00 P.Gross 52.50
Nails of sorts. 0.125 Kg 110 P.Kg 13.75
TOTAL 17855.83
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 1785.58
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 19641.42
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
Carpenter. 2.50 Nos: 450.00 P.day. 1125.00
Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00
______________________________ ______ ______ ______ ________ _________
Rs: 1375.00
Sundries. 10.00 % 137.50
______________________________ ______ ______ ______ ________ _________
TOTAL 1512.50
Contractor's profit 10.00 % 151.25
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 85.32 1663.75
TOTAL (MATERIAL + LABOUR) 21305.17
Total material & labour for 19.50 Sft. Rs: 21305.17
Total material & labour per Sft. Rs: 1092.57
____ Total material & labour per Sft. say Rs: 1092.57
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
13.
Deodar wood frame with braces and 22 gauge C.I sheet facing on
one side including hold fast wooden badings, hinges and locking
arrangement as directed by Engineer- incharge.

Chapter No. 9 724/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(A) ______________________________ ______ ______ ______ ________ _________


MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume 8' * 8' =64 Sft.

Deodar wood. 7.00 Cft. 4500.0 P.Cft. 31500.00

22 gauge C.I sheet 0.73 Cwt. 5000.00 P.Cwt. 3650.00


including wastage 10%

Iron hold fasts with pivot 6.00 Nos: 90.00 Each. 540.00
and clamps..

Bolts of 1-1/2" size. 4.00 Nos: 50.00 Each. 200.00

Screws of sorts. 3.00 Doz: 315.00 P.Gross 78.75

Nails of sorts. 0.25 Kg 110 P.Kg 27.50


______________________________ ______ ______ ______ ________ _________
TOTAL 35996.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 3599.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 39595.88
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 3.50 Nos: 450.00 P.day. 1575.00

Cooly skilled. 1.50 Nos: P.day.


250.00 375.00
Rs: 1950.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 195.00
______________________________ ______ ______ ______ ________ _________
TOTAL 2145.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 214.50
TOTAL PART " B " 36.87 2359.50
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 41955.38
Total material & labour for 64 Sft. Rs: 41955.38
Total material & labour per Sft. Rs: 655.55
____ Total material & labour per Sft. say Rs: 655.55

S/N ______________________________ ______ ______ ______ ________ _________


D E S C R I P T I O N.
14.
First class deodar wood wrought joinery in wire gauze doors and
windows with frames and 22 standard wire gauze 144 mesh per
(a) square inch including brass fittings complete.

Chapter No. 9 725/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Framing including wire gauze with ordinary hinges and fixed in


____ position 1-3/4" thick.

(A) ______________________________ ______ ______ ______ ________ _________


MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood for T.rail=1*4'-1/2'*4-1/2"*1-3/4" 0.25 Cft.
Deodar wood for Lock rail=1*4'-1/2'*7"*1-3/4" 0.38 Cft.
Deodar wood for Bott: rail=1*4'-1/2'*9"*1-3/4" 0.49 Cft.
Hanging styles = 2 * 7'-2/3'* 3"-3/8"*1-3/4" 0.63 Cft.
Fillets = 4* 6'-5/24' * 3/4" * 3/4" 0.09 Cft.
Fillets = 4 * 3'-1/4' * 3/4" * 3/4" 0.05 Cft.
Total. 1.89 Cft.
Wastage 15% 0.28 Cft.
Total wood required for 4'-1/2'*7'-5/8'frame. 2.17 Cft.
Wire gauze 144 mesh per sq-inch.
Double leaf shutters =1*3'-7/16'*6'-5/24' 21.34 Sft.
Wastage L.S. 0.66 Sft.
Grand Total 22.00 Sft.
______________________________ ______ ______ ______ ________ _________
Deodar wood. 2.17 Cft. 4500.0 P.Cft. 9765.00
Wire gauze 144 mesh/sq-in. 22.00 Sft. 50.00 P.Sft. 1100.00
Hinges of 5" size. 6.00 Nos: 400.00 P.doz: 200.00
Tower bolts 9" size. 2.00 Nos: 625.00 P.doz: 104.17
Handles.(BRASS) 8" size. 2.00 Nos: 210.00 Each. 420.00
Hinged chocks of 6" size. 2.00 Nos: 375.00 P.doz: 62.50
Nails. 0.125 Kg. 110.00 P.Kg 13.75
Screws of sorts. 6.00 Doz: 315.00 P.Gross. 157.50
Spikes. L.S 9.00
Glue. L.S 10.00
TOTAL 11841.92
Contractor's profit 10.00 % 1184.19
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 13026.11
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
Carpenter. 4.00 Nos: 450.00 P.day. 1800.00
Cooly skilled. 1.50 Nos: 250.00 P.day. 375.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 2175.00
Sundries. 10.00 % 217.50
______________________________ ______ ______ ______ ________ _________
TOTAL 2392.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 239.25
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 76.24 2631.75
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 15657.86
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 726/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 34.52 Sft. Rs: 15657.86


Total material & labour per Sft. Rs: 453.59
____ Total material & labour per Sft. say Rs: 453.59

S/N ______________________________ ______ ______ ______ ________ _________


D E S C R I P T I O N.
14.
First class deodar wood wrought joinery in wire gauze doors and
windows with frames and 22 standard wire gauze 144 mesh per
(b) square inch including brass fittings complete.
Framing including wire gauze with ordinary hinges and fixed in
____ position 1-1/2" thick.
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 727/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Deodar wood for Top rail=1*3'-7/12'*4"*1-1/2" 0.15 Cft.


Deodar wood for Lock rail=1*3'-7/12'*6"*1-1/2" 0.22 Cft.
Deodar wood for Bot: rail=1*3'-7/12'*8"*1-1/2" 0.30 Cft.
Horizontal styles = 2*6'-17/24' * 4" * 1-1/2" 0.56 Cft.
Horizontal styles = 2*6'-17/24' * 3" * 1-1/2" 0.42 Cft.
Fillets = 4 * 2'-2/3' * 3/4" * 3/4" 0.04 Cft.
Fillets = 4 * 5'-1/24'* 3/4" * 3/4" 0.08 Cft.
Total. 1.77 Cft.
Wastage 15% 0.27 Cft.
Total wood required for 3'-7/12'*6'-7/12'frame. 2.04 Cft.
Wire gauze 144 mesh per sq-inch.
Double leaf shutters =1*2'-2/3'* 5'-1/12' 13.56 Sft.
Wastage L.S. 0.44 Sft.
Grand Total 14.00 Sft.
______________________________ ______ ______ ______ ________ _________
Deodar wood. 2.04 Cft. 4500.0 P.Cft. 9180.00
Wire gauze 144 mesh/sq-in. 14.00 Sft. 50.00 P.Sft. 700.00
Hinges of 5" size. 4.00 Nos: 400.00 P.doz: 133.33
Tower bolts 9" size. 2.00 Nos: 625.00 P.doz: 104.17
Handles.(BRASS) 8" size. 2.00 Nos: 210.00 Each. 420.00
Hinged chocks of 4" size. 2.00 Nos: 225.00 P.doz: 37.50
Nails. 0.125 Kg 110.00 P.Kg 13.75
Screws of sorts. 6.00 Doz: 315.00 P.Gross. 157.50
Spikes. L.S 10.00
Glue. L.S 10.00
______________________________ ______ ______ ______ ________ _________
TOTAL 10766.25
Contractor's profit 10.00 % 1076.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 11842.88
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 2.50 Nos: 450.00 P.day. 1125.00
Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 1375.00
Sundries. 10.00 % 137.50
______________________________ ______ ______ ______ ________ _________
TOTAL 1512.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 151.25
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 69.24 1663.75
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 13506.63
______________________________ ______ ______ ______ ________ _________
Total material & labour for 24.03 Sft. Rs: 13506.63
Total material & labour per Sft. Rs: 562.07
____ Total material & labour per Sft. say Rs: 562.07

Chapter No. 9 728/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N ______________________________ ______ ______ ______ ________ _________


D E S C R I P T I O N.
14.
First class deodar wood wrought joinery in wire gauze doors and
windows with frames and 22 standard wire gauze 144 mesh per
(c) square inch including brass fittings complete.
Galvanized wire gauze fixed to chowkhats with 1/2" deodar wood
strips on seperate 2" * 2" deodar wood frame for C.windows.
____ C.Widow 4' * 2'
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood Horizontal rail=2*4'*2"*2" 0.22 Cft.
Deodar wood Vertical rail=2*2'*2"*2" 0.11 Cft.
Deodar wood Horizontal strips=2*4'*2"*1/2" 0.05 Cft.

Chapter No. 9 729/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Deodar wood Vertical strips=2*2'*2"*1/2" 0.03 Cft.


Mouldings. L.S 0.06
Total. 0.47 Cft.
Wastage 60% 0.28 Cft.
Total wood required for 3' * 4' window 0.75 Cft.
Wire gauze 144 mesh per sq-inch.
Window 4' * 2' 8.00 Sft.
Wastage L.S. 1.00 Sft.
Grand Total 9.00 Sft.
______________________________ ______ ______ ______ ________ _________
Deodar wood. 0.75 Cft. 4500.0 P.Cft. 3375.00
Wire gauze 144 mesh/sq-in. 9.00 Sft. 50.00 P.Sft. 450.00
Nails and screws. 0.300 Kg 110 Kg 33.00
Wooden plugs. 4.00 Nos: 3 Each. 12.00
______________________________ ______ ______ ______ ________ _________
TOTAL 3870.00
Contractor's profit 10.00 % 387.00
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 4257.00
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.50 Nos: 450.00 P.day. 225.00
Cooly skilled. 0.25 Nos: 250.00 P.day. 62.50
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 287.50
Sundries. 10.00 % 28.75
______________________________ ______ ______ ______ ________ _________
TOTAL 316.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 31.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 43.48 347.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 4604.88
______________________________ ______ ______ ______ ________ _________
Total material & labour for 8.0 Sft. Rs: 4604.88
Total material & labour per Sft. Rs: 575.61
____ Total material & labour per Sft. say Rs: 575.61

Chapter No. 9 730/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________

____
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
14.
First class deodar wood wrought joinery in wire gauze doors and
windows with frames and 22 standard wire gauze 144 mesh per
(d) square inch including brass fittings complete.
Galvanized wire gauze fixed to chowkhats with 3/4" deodar wood
____ strip and screws.
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood Horizontal strips=2*3'*3"*3/4" 0.09 Cft.
Deodar wood Vertical strips=2*3'-1/2'*3"*3/4" 0.11 Cft.
Total. 0.2 Cft.
Wastage 25% 0.05 Cft.
Total wood required for 3' * 4' window 0.25 Cft.
Wire gauze 144 mesh per sq-inch.
Window 3' * 4' 12 Sft.
Wastage L.S. 0 Sft.

Chapter No. 9 731/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Grand Total 12.00 Sft.


______________________________ ______ ______ ______ ________ _________
Deodar wood. 0.25 Cft. 4500.0 P.Cft. 1125.00
Wire gauze 144 mesh/sq-in. 12.00 Sft. 50.00 P.Sft. 600.00

Screws of sorts. 0.13 Gs 315 P.Gross 39.38


______________________________ ______ ______ ______ ________ _________
TOTAL 1764.38
Contractor's profit 10.00 % 176.44
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 1940.81
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.50 Nos: 450.00 P.day. 225.00
Cooly skilled. 0.25 Nos: 250.00 P.day. 62.50
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 287.50
Sundries. 10.00 % 28.75
______________________________ ______ ______ ______ ________ _________
TOTAL 316.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 31.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 28.99 347.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 2288.69
______________________________ ______ ______ ______ ________ _________
Total material & labour for 12.0 Sft. Rs: 2288.69
Total material & labour per Sft. Rs: 190.72
____ Total material & labour per Sft. say Rs: 190.72
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
15.
Making and fixing trellies doors and windows complete of deodar
wood.
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 18 Sft.

Deodar wood. 2.30 Cft. 4500.0 P.Cft. 10350.00

Nails and screws. 0.30 Kg 110 P.Kg 33.00

Hinges of 4" size. 4.00 Nos: 310.00 P.doz: 103.33

Tower bolts 9" size. 2.00 Nos: 625.00 P.doz: 104.17

Hasp and staple. 1.00 Nos: 650.00 P.doz: 54.17

Chapter No. 9 732/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


TOTAL 10644.67
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 1064.47
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 11709.13
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 1.50 Nos: 450.00 P.day. 675.00
Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00
______________________________ ______ ______ ______ ________ _________
Rs: 925.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 92.50
______________________________ ______ ______ ______ ________ _________
TOTAL 1017.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 101.75
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 62.18 1119.25
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 12828.38
______________________________ ______ ______ ______ ________ _________
Total material & labour for 18.0 Sft. Rs: 12828.38
Total material & labour per Sft. Rs: 712.69
____ Total material & labour per Sft. say Rs: 712.69
______________________________ ______ ______ ______ ________ _________
____
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
16.
1-1/2" thick deodar wood panelled work including frame work
(except doors).

____
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood =1*10' * 10' * 1.5/12' 12.50 Cft.
Wastage L.S 4.50 Cft.

Deodar wood required for 100 sft. 17.00 Cft.


______________________________ ______ ______ ______ ________ _________
Deodar wood. 17.00 Cft. 4500.0 P.Cft. 76500.00
Nails and screws. 1.00 Kg 110 P.Kg 110.00
TOTAL 76610.00

Chapter No. 9 733/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


Contractor's profit 10.00 % 7661.00
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 84271.00
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 10.00 Nos: 450.00 P.day. 4500.00
Cooly skilled. 3.00 Nos: 250.00 P.day. 750.00
______________________________ ______ ______ ______ ________ _________
Rs: 5250.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 525.00
______________________________ ______ ______ ______ ________ _________
TOTAL 5775.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 577.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 63.525 6352.50
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 90623.50
______________________________ ______ ______ ______ ________ _________
Total material & labour for 100 Sft. Rs: 90623.50
Total material & labour per Sft. Rs: 906.24
____ Total material & labour per Sft. say Rs: 906.24
______________________________ ______ ______ ______ ________ _________
____
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
17.
Extra for providing and fixing double spring hinges with brass
fittings (it shall include brass finger plate 6" tower bolt).
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 3' * 7' =21 Sft.

Double action spring 3.00 Nos: 690.00 Each. 2070.00


hinges of 4" size.(BRASS)

Brass finger plates. 2.00 Nos: 485.00 Each. 970.00

Brass tower bolt of 6" size 1.00 Nos: 775.00 P.doz: 64.58

Brass screws of 1-1/2" size. 2.00 Doz: 300.00 % Nos: 72.00

Brass screws of 1" size. 2.00 Doz: 175.00 % Nos: 42.00


DEDUCT COST OF IRON FITTINGS.
Butt hinge 5" size. 2.00 Nos: 400.00 P.doz: -66.67
Tower bolt 9" size. 2.00 Nos: 625.00 P.doz: -104.17
Handles. 6" size. 2.00 Nos: 275.00 P.doz: -45.83

Chapter No. 9 734/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Hinged chocks. 2.00 Nos: 225.00 P.doz: -37.50


Door stopers. 2.00 Nos: 500.00 P.doz: -83.33
Screws of 1-1/2" size. 3.00 Doz: 300.00 P.doz: -108.00
Screws of 1" size. 3.00 Doz: 110.00 P.doz: -39.60
TOTAL 2733.48
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 273.35
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 3006.83
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.05 Nos: 450.00 P.day. 22.50
Cooly skilled. 0.05 Nos: 250.00 P.day. 12.50
______________________________ ______ ______ ______ ________ _________
Rs: 35.00
Sundries. 10.00 % 3.50
______________________________ ______ ______ ______ ________ _________
TOTAL 38.50
Contractor's profit 10.00 % 3.85
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 2.02 42.35
TOTAL (MATERIAL + LABOUR) 3049.18
______________________________ ______ ______ ______ ________ _________
Total material & labour for 21.0 Sft. Rs: 3049.18
Total material & labour per Sft. Rs: 145.20
____ Total material & labour per Sft. say Rs: 145.20
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
18.
Providing and fixing brass spring hinges to wire gauzed doors.

____
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Brass spring hinges 1.00 Nos: 690.0 Each. 690.00
complete with screws.

TOTAL 690.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 69.00
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 759.00
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 735/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Carpenter. 0.05 Nos: 450.00 P.day. 22.50

Cooly skilled. 0.05 Nos: 250.00 P.day. 12.50

______________________________ ______ ______ ______ ________ _________


Rs: 35.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 3.50
______________________________ ______ ______ ______ ________ _________
TOTAL 38.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 3.85
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 42.35
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 801.35
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for Each. Rs: 801.35

______________________________ ______ ______ ______ ________ _________


____
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
19.
(A) Providing and fixing sliding bolt to doors:-
(i)
Iron sliding bolt 10" long.

____
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 16 Nos:
Sliding bolt complete with 16.00 Nos: 1750.0 P.doz: 2333.33
screw and nut 10" long.

______________________________ ______ ______ ______ ________ _________


TOTAL 2333.33
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 233.33
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 2566.67
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 1.00 Nos: 450.00 P.day. 450.00

Chapter No. 9 736/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Cooly skilled. 0.50 Nos: 250.00 P.day. 125.00

______________________________ ______ ______ ______ ________ _________


Rs: 575.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 57.50
______________________________ ______ ______ ______ ________ _________
TOTAL 632.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 63.25
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 43.48 695.75
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 3262.42
______________________________ ______ ______ ______ ________ _________
Total material & labour for 16 Nos: Rs: 3262.42
Total material & labour for Each. Rs: 203.90
____ Total material & labour for Each. say Rs: 203.90
______________________________ ______ ______ ______ ________ _________
____
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
19.
(A) Providing and fixing sliding bolt to doors:-
(ii)
Iron sliding bolt 12" long.

____
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 16 Nos:
Sliding bolt complete with 16.00 Nos: 1950.0 P.doz: 2600.00
screw and nut 12" long.

______________________________ ______ ______ ______ ________ _________


TOTAL 2600.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 260.00
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 2860.00
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 1.00 Nos: 450.00 P.day. 450.00

Chapter No. 9 737/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Cooly skilled. 0.50 Nos: 250.00 P.day. 125.00

______________________________ ______ ______ ______ ________ _________


Rs: 575.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 57.50
______________________________ ______ ______ ______ ________ _________
TOTAL 632.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 63.25
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 43.48 695.75
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 3555.75
______________________________ ______ ______ ______ ________ _________
Total material & labour for 16 Nos: Rs: 3555.75
Total material & labour for Each. Rs: 222.23
____ Total material & labour for Each. say Rs: 222.23
______________________________ ______ ______ ______ ________ _________
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
19-
B Extra for brass fittings to doors and windows except for hinges
which shall be of iron.
(i)
Deodar panelled or panelled and glazed or fully glazed.
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume 4' * 7' =28 Sft.
BRASS FITTINGS.

Brass tower bolt of 9" size 3.00 Nos: 1600.00 P.doz: 400.00

Handles of 6" size. 3.00 Nos: 775.00 P.doz: 193.75

Butt hinges of 2" size. 2.00 Nos: 435.00 P.doz: 72.50

Brass screws of 1" size. 3.50 Doz: 175.00 % Nos: 73.50

DEDUCT COST OF IRON FITTING


Butt hinge 5" size. 2.00 Nos: 400.00 P.doz: -66.67
Tower bolt 9" size. 3.00 Nos: 625.00 P.doz: -156.25
Handles. 6" size. 3.00 Nos: 275.00 P.doz: -68.75
Screws of 1" size. 3.50 Doz: 175.00 P.Gross -51.04
______________________________ ______ ______ ______ ________ _________
TOTAL 397.04
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 39.70

Chapter No. 9 738/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


TOTAL PART " A " 436.75
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.04 Nos: 450.00 P.day. 18.00

Cooly skilled. 0.04 Nos: 250.00 P.day. 10.00


Rs: 28.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 2.80
______________________________ ______ ______ ______ ________ _________
TOTAL 30.80
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 3.08
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 1.21 33.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 470.63
______________________________ ______ ______ ______ ________ _________
Total material & labour for 28 Sft. Rs: 470.63
Total material & labour for one Sft. Rs: 16.81
____ Total material & labour per Sft. say Rs: 16.81
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
19-
B Extra for brass fittings to doors and windows except for hinges
which shall be of iron.
(ii)
Deodar wood wire gauzed shutters.
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume 4' * 7' =28 Sft.
BRASS FITTINGS.

Brass tower bolt of 9" size 2.00 Nos: 1600.00 P.doz: 266.67

Handles of 6" size. 2.00 Nos: 775.00 P.doz: 129.17

Butt hinges of 2" size. 2.00 Nos: 435.00 P.doz: 72.50

Brass screws of 1" size. 3.00 Doz: 175.00 % Nos: 63.00

DEDUCT COST OF IRON FITTING


Butt hinge 5" size. 2.00 Nos: 400.00 P.doz: -66.67
Tower bolt 9" size. 2.00 Nos: 625.00 P.doz: -104.17
Handles. 6" size. 2.00 Nos: 275.00 P.doz: -45.83
Screws of 1" size. 3.00 Doz: 175.00 P.Gross -43.75
TOTAL 270.92
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 739/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 27.09


______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 298.01
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.03 Nos: 450.00 P.day. 15.00

Cooly skilled. 0.03 Nos: 250.00 P.day. 8.33


Rs: 23.33
Sundries. 10.00 % 2.33
______________________________ ______ ______ ______ ________ _________
TOTAL 25.67
Contractor's profit 10.00 % 2.57
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 1.01 28.23
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 326.24
Total material & labour for 28 Sft. Rs: 326.24
Total material & labour for one Sft. Rs: 11.65
____ Total material & labour per Sft. say Rs: 11.65
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
20
Extra for providing and fixing approved quality rim lock
adjustable, over the style surface.

____
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Rim lock complete with 1.00 Nos: 300.00 Each. 300.00
screws, etc.(PAK)

DEDUCT COST OF IRON FITTING


Handles. 6" size. 2.00 Nos: 275.00 P.doz: -45.83

______________________________ ______ ______ ______ ________ _________


TOTAL 254.17
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 25.42
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 279.58
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 740/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Carpenter. 0.17 Nos: 450.00 P.day. 75.00

Cooly skilled. 0.13 Nos: 250.00 P.day. 31.25

______________________________ ______ ______ ______ ________ _________


Sundries. 10.00 %
______________________________ ______ ______ ______ ________ _________
TOTAL #REF!
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % #REF!
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " #REF!
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) #REF!
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for each. Rs: #REF!
______________________________ ______ ______ ______ ________ _________
____
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
21
Providing and fixing of approved quality Mortice lock.
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY
RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Mortice lock complete with 1.00 Nos: 1500.00 Each. 1500.00
screws.(ENGLISH)

DEDUCT COST OF IRON FITTING


Handles. 6" size. 2.00 Nos: 275.00 P.doz: -45.83

______________________________ ______ ______ ______ ________ _________


TOTAL 1454.17
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 145.42
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 1599.58
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.25 Nos: 450.00 P.day. 112.50

Cooly skilled. 0.17 Nos: 250.00 P.day. 41.67

______________________________ ______ ______ ______ ________ _________

Chapter No. 9 741/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Rs: 154.17
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 15.42
______________________________ ______ ______ ______ ________ _________
TOTAL 169.58
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 16.96
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 186.54
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 1786.13
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for each. Rs: 1786.13

______________________________ ______ ______ ______ ________ _________


____
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
22
(a) Fixing expanded metal with 1" deodar wooden strips and screws.

____
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 48 Sft.
Deodar wood. 2.25 Cft. 4500.0 P.Cft. 10125.00
Expanded material. 54.00 Sft. 39.00 P.Sft. 2106.00
Nails and screws.. 0.500 Kg 110 P.Kg 55.00

______________________________ ______ ______ ______ ________ _________


TOTAL 12286.00
Contractor's profit 10.00 % 1228.60
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 13514.60
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 1.00 Nos: 450.00 P.day. 450.00
Cooly skilled. 0.50 Nos: 250.00 P.day. 125.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 575.00
Sundries. 10.00 % 57.50
______________________________ ______ ______ ______ ________ _________
TOTAL 632.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 63.25
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 742/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL PART " B " 14.49 695.75


______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 14210.35
______________________________ ______ ______ ______ ________ _________
Total material & labour for 48 Sft. Rs: 14210.35
Total material & labour per Sft. Rs: 296.05
____ Total material & labour per Sft. say Rs: 296.05

______________________________ ______ ______ ______ ________ _________


____
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
22 Expanded metal 1/2" to 3/4" mesh 16 gauge fixed with 1" cover moulding and screws
(b) incloding deodar wood frame 2" x 2".
____
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood. 0.85 Cft. 4500.0 P.Cft. 3825.00
Expanded metal. 9.00 Sft. 39.00 P.Sft. 351.00
Nails. 0.150 Kg 110 P.Kg 16.50
Wooden plugs. 4.00 Nos: 3 Each. 12.00
______________________________ ______ ______ ______ ________ _________
TOTAL 4204.50
Contractor's profit 10.00 % 420.45
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 4624.95
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.50 Nos: 450.00 P.day. 225.00
Cooly skilled. 0.25 Nos: 250.00 P.day. 62.50
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 287.50
Sundries. 10.00 % 28.75
______________________________ ______ ______ ______ ________ _________
TOTAL 316.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 31.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 43.48 347.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 4972.83
______________________________ ______ ______ ______ ________ _________
Total material & labour for 8.0 Sft. Rs: 4972.83
Total material & labour per Sft. Rs: 621.60

Chapter No. 9 743/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ Total material & labour per Sft. say Rs: 621.60

______________________________ ______ ______ ______ ________ _________


____
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
23
Providing and fixing deodar Almirah 9" - 12" depth, including
boxing with back shelves, shutters brass fittings complete.
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume 3' * 5' =15 Sft.
Deodar wood. 4.87 Cft. 4500.00 P.Cft. 21915.00

Hinges of 3" size (BRASS) 6.00 Nos: 435.00 P.doz: 217.50

Hasp and staple. (Brass) 1.00 Nos: 650.00 P.doz: 54.17

Brass handle. (BRASS) 2.00 Nos: 775.00 P.doz: 129.17

Nails and screws. 0.75 Kg 110 P.Kg 82.50

Bitumen. L.S 32.00

Wooden plugs. 10.00 Nos: 3.00 Each. 30.00


______________________________ ______ ______ ______ ________ _________
TOTAL 22460.33
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 2246.03
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 24706.37
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 3.00 Nos: 450.00 P.day. 1350.00

Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00


______________________________ ______ ______ ______ ________ _________
Rs: 1600.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 160.00

Chapter No. 9 744/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


TOTAL 1760.00
Contractor's profit 10.00 % 176.00
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 129.07 1936.00
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 26642.37
______________________________ ______ ______ ______ ________ _________
Total material & labour for 15 Sft. Rs: 26642.37
Total material & labour for one Sft. Rs: 1776.16
Total material & labour per Sft. say Rs: 1776.16
NOTE______________________________ ______ ______ ______ ________ _________
(I) Reduce the labour rate by Rs:4.14 per Sft, if the boxing and
back are not provided.

(II) Reduce the composite rate by Rs:55.80 per Sft, if the


____ boxing and back are not provided.
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
24
Providing and fixing deodar wooden ward-robe including boxing
with back shelves, shutters drawers and brass fittings such as
handles locking arrangement, hanger rod, shoe rod, and mirror
measuring 2'*1' complete as per approved design.
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 4'*6-1/2'=26 Sft.
Deodar wood. 11.00 Cft. 4500.00 P.Cft. 49500.00
Hard wood gutties. 25.00 Nos: 1.00 Each. 25.00
Hinges of 4" size (BRASS) 6.00 Nos: 625.00 P.doz: 312.50
Brass handle. (BRASS) 2.00 Nos: 775.00 P.doz: 129.17
Sunk handles. 2.00 Nos: 315.00 P.doz: 52.50
Wooden beading. 21.00 Rft. 35.00 P.Rft. 735.00
Tie rod including fixing 2.00 Rft. 190.00 P.Rft. 380.00
arrangement.
Wooden rod for shoes. 2.00 Rft. 35.00 P.Rft. 70.00
Mirror 2' * 1' 2.00 Sft. 500.00 P.Sft 1000.00
Hanger hook including pull 2.00 Rft. 260.00 P.Rft. 520.00
out rod.
Nails and screws. 1.00 Kg 110 P.Kg 110.00
Bitumen painting. L.S 32.00
TOTAL 52866.17
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 5286.62
TOTAL PART " A " 58152.78
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
Carpenter. 5.00 Nos: 450.00 P.day. 2250.00
Cooly skilled. 2.00 Nos: 250.00 P.day. 500.00
Rs: 2750.00

Chapter No. 9 745/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


Sundries. 10.00 % 275.00
TOTAL 3025.00
Contractor's profit 10.00 % 302.50
TOTAL PART " B " 127.98 3327.50
TOTAL (MATERIAL + LABOUR) 61480.28
Total material & labour for 26.0 Sft. Rs: 61480.28
Total material & labour per Sft. Rs: 2364.63
____ Total material & labour per Sft. say Rs: 2364.63
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
25
Making and fixing frames for door window and C.Windows:-
(a)
Teak wood.

(A) ______________________________ ______ ______ ______ ________ _________


MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Teak wood Horizontal rail=1*4'*1/4'*1/3' 0.33 Cft.
Teak wood Vertical rail=2*7'-1/8'*1/4'*1/3' 1.19 Cft.
Total. 1.52 Cft.
Wastage 15% 0.23 Cft.
Total wood required for 4' * 7' = 28 Sft. 1.75 Cft.
______________________________ ______ ______ ______ ________ _________
Teak wood. 1.75 Cft. 9300.0 P.Cft. 16275.00

Iron hold fasts. 6.00 Nos: 90.00 Each 540.00

Nails and screws. L.S 20.00


______________________________ ______ ______ ______ ________ _________
TOTAL 16835.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 1683.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 18518.50
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 1.00 Nos: 450.00 P.day. 450.00
Cooly skilled. 0.50 Nos: 250.00 P.day. 125.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 575.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 57.50
______________________________ ______ ______ ______ ________ _________
TOTAL 632.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 63.25
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 24.85 695.75

Chapter No. 9 746/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


TOTAL (MATERIAL + LABOUR) 19214.25
______________________________ ______ ______ ______ ________ _________
Total material & labour for 28.0 Sft. Rs: 19214.25
Total material & labour per Sft. Rs: 686.22
____ Total material & labour per Sft. say Rs: 686.22
______________________________ ______ ______ ______ ________ _________
____
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
25
Making and fixing frames for door window and C.Windows:-
(b)
Deodar wood.
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood Horizontal rail=1*4'*1/4'*1/3' 0.33 Cft.
Deodar wood Vertical rail=2*7'-1/8'*1/4'*1/3' 1.19 Cft.
Total. 1.52 Cft.
Wastage 25% 0.38 Cft.
Total wood required for 4' * 7' = 28 Sft. 1.90 Cft.
______________________________ ______ ______ ______ ________ _________
Deodar wood. 1.90 Cft. 4500.0 P.Cft. 8550.00

Iron hold fasts. 6.00 Nos: 90.00 Each 540.00

Nails and screws. 0.300 Kg 110 P.Kg 33.00


______________________________ ______ ______ ______ ________ _________
TOTAL 9123.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 912.30
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 10035.30
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.50 Nos: 450.00 P.day. 225.00
Cooly skilled. 0.25 Nos: 250.00 P.day. 62.50
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 287.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 28.75
______________________________ ______ ______ ______ ________ _________
TOTAL 316.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 31.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 12.42 347.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 10383.18

Chapter No. 9 747/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


Total material & labour for 28.0 Sft. Rs: 10383.18
Total material & labour per Sft. Rs: 370.83
____ Total material & labour per Sft. say Rs: 370.83
______________________________ ______ ______ ______ ________ _________
____
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
25
Making and fixing frames for door window and C.Windows:-
(c)
Shisham wood.
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Sheesham wood Horizontal rail=1*4'*1/4'*1/3' 0.33 Cft.
Shisham wood Vertical rail=2*7'-1/8'*1/4'*1/3' 1.19 Cft.
Total. 1.52 Cft.
Wastage 35% 0.53 Cft.
Total wood required for 4' * 7' = 28 Sft. 2.05 Cft.
______________________________ ______ ______ ______ ________ _________
Sheesham wood. 2.05 Cft. 2300.0 P.Cft. 4715.00

Iron hold fasts. 6.00 Nos: 90.00 Each 540.00

Nails and screws. L.S 10.00


______________________________ ______ ______ ______ ________ _________
TOTAL 5265.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 526.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 5791.50
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.75 Nos: 450.00 P.day. 337.50
Cooly skilled. 0.50 Nos: 250.00 P.day. 125.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 462.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 46.25
______________________________ ______ ______ ______ ________ _________
TOTAL 508.75
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 50.88
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 19.99 559.63
______________________________ ______ ______ ______ _________
TOTAL (MATERIAL + LABOUR) 6351.13
______________________________ ______ ______ ______ ________ _________
Total material & labour for 28.0 Sft. Rs: 6351.13

Chapter No. 9 748/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour per Sft. Rs: 226.83


____ Total material & labour per Sft. say Rs: 226.83
______________________________ ______ ______ ______ ________ _________
____
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
26
Making and fixing deodar first class plaining in Eave boards
etc, planed on both sides rebated and fixed including nails and
screws, bolts and brackets:-
(a)
1" thick.
____
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood. 9.50 Cft. 4500.0 P.Cft. 42750.00

Nails, screws, bolts & 1.000 Kg 110 P.Kg 110.00


brackets.

______________________________ ______ ______ ______ ________ _________


TOTAL 42860.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 4286.00
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 47146.00
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 4.00 Nos: 450.00 P.day. 1800.00
Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 2050.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 205.00
______________________________ ______ ______ ______ ________ _________
TOTAL 2255.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 225.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 24.805 2480.50
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 49626.50
______________________________ ______ ______ ______ ________ _________
Total material & labour for 100 Sft. Rs: 49626.50
Total material & labour per Sft. Rs: 496.27
____ Total material & labour per Sft. say Rs: 496.27

______________________________ ______ ______ ______ ________ _________

Chapter No. 9 749/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
26
Making and fixing deodar first class plaining in Eave boards
etc, planed on both sides rebated and fixed including nails and
screws, bolts and brackets:-
(b)
3/4" thick.
____
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood. 7.12 Cft. 4500.0 P.Cft. 32040.00

Nails, screws, bolts & 1.00 Kg 110 P.Kg 110.00


brackets.

______________________________ ______ ______ ______ ________ _________


TOTAL 32150.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 3215.00
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 35365.00
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 4.00 Nos: 450.00 P.day. 1800.00
Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 2050.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 205.00
______________________________ ______ ______ ______ ________ _________
TOTAL 2255.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 225.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 24.805 2480.50
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 37845.50
______________________________ ______ ______ ______ ________ _________
Total material & labour for 100 Sft. Rs: 37845.50
Total material & labour per Sft. Rs: 378.46
____ Total material & labour per Sft. say Rs: 378.46

______________________________ ______ ______ ______ ________ _________


____
______________________________ ______ ______ ______ ________ _________
S/N D E S C R I P T I O N.

Chapter No. 9 750/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

26
Making and fixing deodar first class plaining in Eave boards
etc, planed on both sides rebated and fixed including nails and
screws, bolts and brackets:-
(c)
1/2" thick.
____
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood. 4.75 Cft. 4500.0 P.Cft. 21375.00

Nails, screws, bolts & 1.000 Kg 110 P.Kg 110.00


brackets.

______________________________ ______ ______ ______ ________ _________


TOTAL 21485.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 2148.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 23633.50
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 4.00 Nos: 450.00 P.day. 1800.00
Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 2050.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 205.00
______________________________ ______ ______ ______ ________ _________
TOTAL 2255.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 225.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 24.805 2480.50
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 26114.00
______________________________ ______ ______ ______ ________ _________
Total material & labour for 100 Sft. Rs: 26114.00
Total material & labour per Sft. Rs: 261.14
____ Total material & labour per Sft. say Rs: 261.14

______________________________ ______ ______ ______ ________ _________

____
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
27

Chapter No. 9 751/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Making and fixing deodar wood shelves including brackets:-

(a) 1" thick.


____
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood. (2nd class) 9.50 Cft. 4000.0 P.Cft. 38000.00

Nails, screws, bolts & 0.750 Kg 110 P.Kg 82.50


brackets.

______________________________ ______ ______ ______ ________ _________


TOTAL 38082.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 3808.25
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 41890.75
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 4.00 Nos: 450.00 P.day. 1800.00
Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 2050.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 205.00
______________________________ ______ ______ ______ ________ _________
TOTAL 2255.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 225.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 24.805 2480.50
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 44371.25
______________________________ ______ ______ ______ ________ _________
Total material & labour for 100 Sft. Rs: 44371.25
Total material & labour per Sft. Rs: 443.71
____ Total material & labour per Sft. say Rs: 443.71

______________________________ ______ ______ ______ ________ _________


____

S/N ______________________________ ______ ______ ______ ________ _________


D E S C R I P T I O N.
27
Making and fixing deodar wood shelves including brackets:-

Chapter No. 9 752/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(b) 1-1/2" thick.


____
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood. (2nd class) 14.25 Cft. 4000.0 P.Cft. 57000.00

Nails, screws, bolts & 0.750 Kg 110 P.Kg 82.50


brackets.

______________________________ ______ ______ ______ ________ _________


TOTAL 57082.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 5708.25
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 62790.75
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 4.00 Nos: 450.00 P.day. 1800.00
Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 2050.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 205.00
______________________________ ______ ______ ______ ________ _________
TOTAL 2255.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 225.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 24.805 2480.50
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 65271.25
______________________________ ______ ______ ______ ________ _________
Total material & labour for 100 Sft. Rs: 65271.25
Total material & labour per Sft. Rs: 652.71
____ Total material & labour per Sft. say Rs: 652.71

______________________________ ______ ______ ______ ________ _________


____
S/N ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
27
Making and fixing deodar wood shelves including brackets:-

Chapter No. 9 753/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(c) 2" thick.


____
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood. (2nd class) 19.00 Cft. 4000.0 P.Cft. 76000.00

Nails, screws, bolts & 0.750 Kg 110 P.Kg 82.50


brackets.

______________________________ ______ ______ ______ ________ _________


TOTAL 76082.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 7608.25
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 83690.75
(B) ______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 4.00 Nos: 450.00 P.day. 1800.00
Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 2050.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 205.00
______________________________ ______ ______ ______ ________ _________
TOTAL 2255.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 225.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 24.805 2480.50
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 86171.25
______________________________ ______ ______ ______ ________ _________
Total material & labour for 100 Sft. Rs: 86171.25
Total material & labour per Sft. Rs: 861.71
____ Total material & labour per Sft. say Rs: 861.71

S/N ______________________________ ______ ______ ______ ________ _________


D E S C R I P T I O N.
28
Deodar wood counter including shutters and shelves complete with
iron fitting (Railway type plan 0.59 etc.)
(A) ______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Deodar wood:-

Chapter No. 9 754/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Counter 4' * 2'-1/2' * 1/6' = 1.67


Shelves 4' * 2'-1/2' * 1/6' = 1.67
Support posts for counter=3*3'-1/2'*1/4'*1/4' 0.66
Draws 2 * 4' * 1/2' * 1/8' 0.5
Side strips for draws 2 * 2'-1/2'*1/2'*1/8' 0.31
Sliding shutters of windows 0.63
2*6'-3/8'*13/48'*1/12' 0.29
Head rail of window 1 * 3' * 13/48' * 3/8' 0.3
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total 6.03
Wastage 15% 0.90
Total wood required for 4' * 2.50' = 10 Sft 6.93
Zink plate 1'-3/4' * 7/16' 0.77
Wastage 10% 0.08
Total 0.85
______________________________ ______ ______ ______ ________ _________
Deodar wood. 6.93 Cft. 4500.0 P.Cft. 31185.00
Zink plate 1'-3/4' * 7/16' 0.85 Sft. 700.00 P.Sft. 595.00
Iron grill 3' * 2'-5/8' 8.00 Sft. 175.00 P.Sft. 1400.00
Screws of sorts. 3.00 Doz: 315.00 P.Gross 78.75
Bolts with washers. 1.00 Doz: 225.00 P.doz: 225.00
Nails of sorts. 0.50 Kg 110.00 P.Kg 55.00
TOTAL 33538.75
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 3353.88
______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 36892.63
LABOUR
Carpenter. 2.00 Nos: 450.00 P.day. 900.00
Cooly skilled. 0.40 Nos: 250.00 P.day. 100.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 1000.00
Sundries. 10.00 % 100.00
TOTAL 1100.00
Contractor's profit 10.00 % 110.00
TOTAL PART " B " 12.100 1210.00
TOTAL (MATERIAL + LABOUR) 38102.63
______________________________ ______ ______ ______ ________ _________
Total material & labour for 10 Sft. Rs: 38102.63
____ Total material & labour per Sft. Rs: 3810.26
Total material & labour per Sft. say Rs: 3810.26
____ ______________________________ ______ ______ ______ ________ _________
S/N
______________________________ ______ ______ ______ ________ _________
29 D E S C R I P T I O N.
(a)
____ Making and fixing cleats for doors & windows including hinges
(A) and screws.
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 755/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Assume for 10 Nos:

Hinges of 2" size. 10.00 Nos: 435.00 P.doz: 362.50

Screws 1" size. 3.50 Doz: 175.00 P.Gross 51.04

Deodar wood. 0.21 Cft. 4500.0 P.Cft. 945.00

______________________________ ______ ______ ______ ________ _________


TOTAL 1358.54
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 135.85
______________________________ ______ ______ ______ ________ _________
(B) TOTAL PART " A " 1494.40
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.50 Nos: 450.00 P.day. 225.00
Cooly skilled. 0.25 Nos: 250.00 P.day. 62.50
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 287.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 28.75
______________________________ ______ ______ ______ ________ _________
TOTAL 316.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 31.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 3.479 347.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 1842.27
______________________________ ______ ______ ______ ________ _________
Total material & labour for 10 Nos: Rs: 1842.27
____ Total material & labour for 1 No: Rs: 184.23
Total material & labour for each. say Rs: 184.23
____ ______________________________ ______ ______ ______ ________ _________
S/N
______________________________ ______ ______ ______ ________ _________
29 D E S C R I P T I O N.
(b)
____ Making and fixing cleats with brass hooks for roof ventilators.
(A)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 1 No:

Chapter No. 9 756/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Brass hooks. 1.00 Nos: 180.00 P.doz: 15.00

Screws & Nails. 0.75 Kg 110 P.Kg 82.50

Deodar wood. 0.01 Cft. 4500.0 P.Cft. 45.00

______________________________ ______ ______ ______ ________ _________


TOTAL 142.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 14.25
______________________________ ______ ______ ______ ________ _________
(B) TOTAL PART " A " 156.75
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.05 Nos: 450.00 P.day. 22.50
Cooly skilled. 0.05 Nos: 250.00 P.day. 12.50
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 35.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 3.50
______________________________ ______ ______ ______ ________ _________
TOTAL 38.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 3.85
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 42.35
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 199.10
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 1 No: Rs: 199.10
Total material & labour for each. say Rs: 199.10
____ ______________________________ ______ ______ ______ ________ _________
S/N
______________________________ ______ ______ ______ ________ _________
30 D E S C R I P T I O N.

Hard wood railing of any shape and design including bends and
corners fixed in position including polishing complete as
(a) directed:-
____
(A) Shisham wood.
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 10 Rft.

Chapter No. 9 757/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Shisham wood. 0.90 Cft. 2300.0 P.Cft. 2070.00

Sand paper. 3.00 Nos: 12.50 Each. 37.50

Polishing material. L.S 70.00


TOTAL 2177.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 217.75
______________________________ ______ ______ ______ ________ _________
(B) TOTAL PART " A " 2395.25
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 1.50 Nos: 450.00 P.day. 675.00
Cooly skilled. 0.75 Nos: 250.00 P.day. 187.50
Sawyer. 0.50 Nos: 400.00 P.day. 200.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 1062.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 106.25
______________________________ ______ ______ ______ ________ _________
TOTAL 1168.75
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 116.88
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 12.856 1285.63
______________________________ ______ ______ ______ _________________
TOTAL (MATERIAL + LABOUR) 3680.88
______________________________ ______ ______ ______ ________ _________
Total material & labour for 10 Rft. Rs: 3680.88
____ Total material & labour per Rft. Rs: 368.09
Total material & labour per Rft. say Rs: 368.09

____ ______________________________ ______ ______ ______ ________ _________


S/N
______________________________ ______ ______ ______ ________ _________
30 D E S C R I P T I O N.

Hard wood railing of any shape and design including bends and
corners fixed in position including polishing complete as
(b) directed:-
____
(A) Teak wood.
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 10 Rft.

Teak wood. 0.90 Cft. 9300.0 P.Cft. 8370.00

Chapter No. 9 758/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Sand paper. 3.00 Nos: 12.50 Each. 37.50

Polishing material. L.S 60.00

______________________________ ______ ______ ______ ________ _________


TOTAL 8467.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 846.75
______________________________ ______ ______ ______ ________ _________
(B) TOTAL PART " A " 9314.25
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 1.75 Nos: 450.00 P.day. 787.50
Cooly skilled. 0.75 Nos: 250.00 P.day. 187.50
Sawyer. 0.50 Nos: 400.00 P.day. 200.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 1175.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 117.50
______________________________ ______ ______ ______ ________ _________
TOTAL 1292.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 129.25
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 14.218 1421.75
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 10736.00
______________________________ ______ ______ ______ ________ _________
Total material & labour for 10 Rft. Rs: 10736.00
____ Total material & labour per Rft. Rs: 1073.60
Total material & labour per Rft. say Rs: 1073.60
____ ______________________________ ______ ______ ______ ________ _________
S/N
______________________________ ______ ______ ______ ________ _________
31 D E S C R I P T I O N.

Deodar wood dado or picture rail 3" * 1-1/4" as per approved


design including moulding and fixed in place cost of screws,
nails, plugs and painting complete.
____
(A)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 10 Rft.

Deodar wood. 0.60 Cft. 4500.0 P.Cft. 2700.00

Sand paper. 1.00 Nos: 12.50 Each. 12.50

Chapter No. 9 759/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Wooden Plugs. 6.00 Nos: 3.00 Each. 18.00

Screws. 0.5 Doz: 315.00 P.Gross 13.13

Painting material. L.S 20.00


TOTAL 2763.63
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 276.36
______________________________ ______ ______ ______ ________ _________
(B) TOTAL PART " A " 3039.99
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.50 Nos: 450.00 P.day. 225.00
Cooly skilled. 0.50 Nos: 250.00 P.day. 125.00
Sawyer. 0.13 Nos: 400.00 P.day. 50.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 400.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 40.00
______________________________ ______ ______ ______ ________ _________
TOTAL 440.00
Contractor's profit 10.00 % 44.00
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 4.840 484.00
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 3523.99
______________________________ ______ ______ ______ ________ _________
Total material & labour for 10 Rft. Rs: 3523.99
____ Total material & labour per Rft. Rs: 352.40
Total material & labour per Rft. say Rs: 352.40
S/N
32 D E S C R I P T I O N.

(a) Sawing wood by hand:-


____ Soft wood (Deodar, Kail or Chir)
(A)
______________________________ ______ ______ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Sawyer. 1.50 Nos: 400.00 P.day. 600.00

Cooly skilled. 1.50 Nos: 250.00 P.day. 375.00


______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 975.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 97.50
______________________________ ______ ______ ______ ________ _________
TOTAL 1072.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 107.25

Chapter No. 9 760/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


TOTAL PART " B " 1179.75
____ ______________________________ ______ ______ ______ ________ _________
Total labour rate for 100 Sft. say Rs: 1179.75
S/N
______________________________ ______ ______ ______ ________ _________
32 D E S C R I P T I O N.
(b) Sawing wood by hand:-

____ Hard wood (Shisham, Kikar, Sal or Teak)


(A)
______________________________ ______ ______ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Sawyer. 3.00 Nos: 400.00 P.day. 1200.00

Cooly skilled. 3.00 Nos: 250.00 P.day. 750.00


______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 1950.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 195.00
______________________________ ______ ______ ______ ________ _________
TOTAL 2145.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 214.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 2359.50
____ ______________________________ ______ ______ ______ ________ _________
Total labour rate for 100 Sft. say Rs: 2359.50
S/N
33 D E S C R I P T I O N.

(a) Sawing wood by Machine:-

____ Soft wood (Deodar, Kail or Chir)


(A)
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
____ ______________________________ ______ ______ ______ ________ _________
____ Sawing wood labour rate per Cft. Rs: 20.00
S/N ______________________________ ______ ______ ______ ________ _________
______________________________ ______ ______ ______ ________ _________
33 D E S C R I P T I O N.

(b) Sawing wood by Machine:-

____ Hard wood (Shisham,Kikar,Sal or Teak)


(A)
______________________________ ______ ______ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:

Chapter No. 9 761/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ______________________________ ______ ______ ______ ________ _________


Sawing wood labour rate per Cft. Rs: 26.00
S/N
______________________________ ______ ______ ______ ________ _________
34 D E S C R I P T I O N.
(a)
Sawing U.S.B.Sleepers in halves, cutting ends and fixing.
(A) Assume 14 sleepers.
______________________________ ______ ______ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Carpenter 2nd class. 2.00 Nos: 400.00 P.day. 800.00
Cooly skilled. 2.00 Nos: 250.00 P.day. 500.00
Carpenter Ist: class. 0.50 Nos: 450.00 P.day. 225.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 1525.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 152.50
TOTAL 1677.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 167.75
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 1845.25
______________________________ ______ ______ ______ ________ _________
Total labour rate for 14 Nos: Rs: 1845.25
____ Total labour rate for each sleeper Rs: 131.80
Total labour rate for each sleeper say Rs: 131.80
S/N
______________________________ ______ ______ ______ ________ _________
34 D E S C R I P T I O N.
(b)
Sawing un-serviceable broad gauge, sleepers in halves, cutting,
ends planing squaring and fixing them, into close planking.

____
(A) Assume 10 sleepers.
______________________________ ______ ______ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Sawyer. 1.00 Nos: 400.00 P.day. 400.00
Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00
Carpenter. 1.00 Nos: 450.00 P.day. 450.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 1100.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 110.00
______________________________ ______ ______ ______ ________ _________
TOTAL 1210.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 121.00

Chapter No. 9 762/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


TOTAL PART " B " 1331.00
______________________________ ______ ______ ______ ________ _________
Total labour rate for 10 Nos: Rs: 1331.00
____ Total labour rate for each sleeper Rs: 133.10
Total labour rate for each sleeper say Rs: 133.10

S/N
35 D E S C R I P T I O N.

Making and fixing sunshade of deodar wood (including fixing


____ brackets) Railway plan Q-35 L/RI.
(A)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood H.Planks on top = 4*5'*1/3'*1/24' 0.28
Vertical frames = 2* 1'-3/4' * 1/6' * 5/48' 0.06
Support post along sunshade=2*3/2'*1/8'*5/48' 0.04
Slanting brackets posts =2* 1' * 1/8' * 5/48' 0.03
Front Eave-Board strips =1 * 5 * 1/4' * 1/12' 0.10
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total. 0.51
Wastage 10% 0.05
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total wood required for 5 Sft sunshade 0.56
______________________________ ______ ______ ______ ________ _________
Deodar wood. 0.56 Cft. 4500.0 P.Cft. 2520.00

Screws and nails. 0.20 Kg 110 P.kg 22.00


TOTAL 2542.00
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 763/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 254.20


______________________________ ______ ______ ______ ________ _________
(B) TOTAL PART " A " 2796.20
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.50 Nos: 450.00 P.day. 225.00
Cooly skilled. 0.15 Nos: 250.00 P.day. 37.50
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 262.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 26.25
______________________________ ______ ______ ______ ________ _________
TOTAL 288.75
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 28.88
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 63.53 317.63
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 3113.83
______________________________ ______ ______ ______ ________ _________
Total material & labour for 5 Sft. Rs: 3113.83
____ Total material & labour per Sft. Rs: 622.77
Total material & labour per Sft. say Rs: 622.77
____ ______________________________ ______ ______ ______ ________ _________
S/N
______________________________ ______ ______ ______ ________ _________
36 D E S C R I P T I O N.

Making and fixing 1" thick Kail or Chir wooden notice board with
____ frame.
(A)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 18 Sft.
Kail or Chir wood. 1.64 Cft. 2000.0 P.Cft. 3280.00

Screws and nails. 0.20 Kg 110 P.Kg 22.00

______________________________ ______ ______ ______ ________ _________


TOTAL 3302.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 330.20
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 764/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(B) TOTAL PART " A " 3632.20


______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 1.50 Nos: 450.00 P.day. 675.00
Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 925.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 92.50
______________________________ ______ ______ ______ ________ _________
TOTAL 1017.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 101.75
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 62.18 1119.25
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 4751.45
______________________________ ______ ______ ______ ________ _________
Total material & labour for 18 Sft. Rs: 4751.45
____ Total material & labour per Sft. Rs: 263.97
Total material & labour per Sft. say Rs: 263.97
____ ______________________________ ______ ______ ______ ________ _________
S/N
______________________________ ______ ______ ______ ________ _________
37 D E S C R I P T I O N.

Making deodar punkha pole 10' * 6" * 6".


____
(A)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Deodar wood. 2.50 Cft. 4500.00 P.Cft. 11250.00

Hooks. 2.00 Doz: 400.00 P.doz: 800.00

______________________________ ______ ______ ______ ________ _________


TOTAL 12050.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 1205.00
______________________________ ______ ______ ______ ________ _________
(B) TOTAL PART " A " 13255.00
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 765/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.50 Nos: 450.00 P.day. 225.00
Cooly skilled. 0.25 Nos: 250.00 P.day. 62.50
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 287.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 28.75
______________________________ ______ ______ ______ ________ _________
TOTAL 316.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 31.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 347.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 13602.88
____ ______________________________ ______ ______ ______ ________ _________
Total material & labour for Each No: Rs: 13602.88

____ ______________________________ ______ ______ ______ ________ _________


S/N
38 D E S C R I P T I O N.
Supplying and fixing 1/4" thick ply wood in panels including
supplying and making deodar wood Ist: class frame work for
____ cieling or partition.
(A)
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
1/4" thick plywood 4' * 8' * 4' 128.00
Wastage 10% 12.80
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total 141
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Deodar wood for frame V.posts= 4*8'*1/3'*1/3' 3.55
Cross styles = 3'* 16' * 1/4' * 1/8' 1.50
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total. 5.05
Wastage 15% 0.76
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total wood required for 128 Sft. 5.81
______________________________ ______ ______ ______ ________ _________
1/4" thick plywood. 141.0 Cft. 75.0 P.Sft. 10575.00

Deodar wood. 5.81 Cft. 4500.0 P.Cft. 26145.00

Nails of sorts. 0.50 Kg 110 P.Kg 55.00

Screws of sorts. 2.00 Doz: 315.00 P.Gross 52.50


TOTAL 36827.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 3682.75

Chapter No. 9 766/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(B) ______________________________ ______ ______ ______ ________ _________


TOTAL PART " A " 40510.25
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 1.50 Nos: 450.00 P.day. 675.00
Cooly skilled. 1.50 Nos: 250.00 P.day. 375.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 1050.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 105.00
______________________________ ______ ______ ______ ________ _________
TOTAL 1155.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 115.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 992.58 1270.50
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 41780.75
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 128 Sft. Rs: 41780.75
Total material & labour per 100 Sft. Rs: 32641.21
____ Total material & labour per 100 Sft. Say Rs: 32641.21
S/N ______________________________ ______ ______ ______ ________ _________
39 ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
Supplying and Fixing masonite, bacolite celutex of card board sheets in
____ pannels including making frame work for cieling or partition.
(A)
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Masonite, bacolite sheet 4' * 8' * 4' 128.00
Wastage 10% 12.80
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total 141
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Deodar wood for frame V.posts= 4*8'*1/3'*1/3' 3.55
Cross styles = 3'* 16' * 1/4' * 1/8' 1.50
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total. 5.05
Wastage 15% 0.76
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total wood required for 128 Sft. 5.81
______________________________ ______ ______ ______ ________ _________
Masonite, bacolite sheet. 141.0 Cft. 160.0 P.Sft. 22560.00

Deodar wood. 5.80 Cft. 4500.0 P.Cft. 26100.00

Nails of sorts. 0.50 kg 110 P.Kg 55.00

Screws of sorts. 2.00 Doz: 315.00 P.Gross 52.50


TOTAL 48767.50

Chapter No. 9 767/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


Contractor's profit 10.00 % 4876.75
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 53644.25
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 1.50 Nos: 450.00 P.day. 675.00
Cooly skilled. 1.50 Nos: 250.00 P.day. 375.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 1050.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 105.00
______________________________ ______ ______ ______ ________ _________
TOTAL 1155.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 115.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 992.58 1270.50
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 54914.75
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 128 Sft. Rs: 54914.75
Total material & labour per 100 Sft. Rs: 42902.15
____ Total material & labour per 100 Sft. say Rs: 42902.15
S/N ______________________________ ______ ______ ______ ________ _________

40 ______________________________ ______ ______ ______ ________ _________


D E S C R I P T I O N.

Dismentaling and refixing Eaves boards.

____
(A)
Assume 60 Rft.
______________________________ ______ ______ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Carpenter. 1.00 Nos: 450.00 P.day. 450.00
Cooly skilled. 0.50 Nos: 250.00 P.day. 125.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 575.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 57.50
______________________________ ______ ______ ______ ________ _________
TOTAL 632.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 63.25
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 695.75
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 768/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ Total labour rate for 60 Rft. Rs: 695.75


Total labour rate for one Rft. Rs: 11.60
____ Total labour rate per Rft. say Rs: 11.60

S/N ______________________________ ______ ______ ______ ________ _________


41 ______________________________ ______ ______ ______ ________ _________
(a) D E S C R I P T I O N.
Making wooden stair cases complete 2' to 3' wide frame 1-1/2"
thick planks of deodar wood Ist: class including hand rails.
(A)
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood 2nd class 2 * 5/6' * 15'* 1/8' 3.12
Steps. 14 * 2'-1/2' * 1' * 5/6' 3.65
Hand rails. 2 * 15' * 1/4' * 1/4' 1.88
Hand rails. 2 * 4 * 3' * 1/4' * 1/4' 1.50
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total. 10.15
Wastage L.S. 0.35
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total wood required for 15 Rft. 10.50
______________________________ ______ ______ ______ ________ _________
Deodar wood II-class. 10.50 Cft. 4000.0 P.Cft. 42000.00

Nails of sorts. 1.00 Kg 110 P.Kg 110.00

Bolts 1/2: dia 3" long. 5.36 Kg 300.00 P.Kg 1607.14

Steel rods 3/4" dia. 15.80 Lbs. 4750.00 P.Cwt. 670.09


(3*3'-6" *1.50 =15.80 Lbs.)

Washers. 12.00 Nos: 4.67 Each. 56.00

Chapter No. 9 769/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 44443.23
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 4444.32
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 48887.56
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 2.00 Nos: 450.00 P.day. 900.00
Black-smith. 0.50 Nos: 450.00 P.day. 225.00
Hammer man. 0.50 Nos: 250.00 P.day. 125.00
Cooly skilled. 2.00 Nos: 250.00 P.day. 500.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 1750.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 175.00
______________________________ ______ ______ ______ ________ _________
TOTAL 1925.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 192.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 141.17 2117.50
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 51005.06
Total material & labour for 15 Rft. Rs: 51005.06
____ Total material & labour per Rft. Rs: 3400.34

S/N ______________________________ ______ ______ ______ ________ _________

41 ______________________________ ______ ______ ______ ________ _________


(b) D E S C R I P T I O N.

Making steps from 2" thick Kikar wood planks.

____
(A)

______________________________ ______ ______ ______ ________ _________


MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 100 Sft.

Kikar wood. 23.00 Cft. 1400.0 P.Cft. 32200.00

Nails of sorts. 0.50 Kg 110 P.Kg 55.00

Screws or bolts. L.S 60.00

TOTAL 32315.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 3231.50
(B) ______________________________ ______ ______ ______ ________ _________

Chapter No. 9 770/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL PART " A " 35546.50


______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Sawyers. 10.00 Nos: 400.00 P.day. 4000.00
Carpenter. 10.00 Nos: 450.00 P.day. 4500.00
Cooly skilled. 15.00 Nos: 250.00 P.day. 3750.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 12250.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 1225.00
______________________________ ______ ______ ______ ________ _________
TOTAL 13475.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 1347.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 148.23 14822.50
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 50369.00
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 100 Sft. Rs: 50369.00
Total material & labour per Sft. Rs: 503.69
____ Total material & labour per Sft. say Rs: 503.69

S/N ______________________________ ______ ______ ______ ________ _________


42 ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
____ Adzing and paning wooden sleepers for rail seats.
(A)
(Unit of rate per 100 Nos:)
______________________________ ______ ______ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 50 Nos:
Carpenter. 1.00 Nos: 450.00 P.day. 450.00

Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00


______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 700.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 70.00
______________________________ ______ ______ ______ ________ _________
TOTAL 770.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 77.00
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 847.00
____ ______________________________ ______ ______ ______ ________ _________
Total labour rate for 50 Nos: Rs: 847.00
____ Total labour rate for 100 Nos: Rs: 1694.00
S/N ______________________________ ______ ______ ______ ________ _________

Chapter No. 9 771/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

43 ______________________________ ______ ______ ______ ________ _________


D E S C R I P T I O N.

____ Cutting ends of sleepers for Railway works only.


(A)
(Unit of rate per 100 Nos: cuts.)
______________________________ ______ ______ ______ ________ _________
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 75 Nos: of cuts.
Carpenter. 1.00 Nos: 450.00 P.day. 450.00

Cooly skilled. 0.50 Nos: 250.00 P.day. 125.00


TOTAL Rs: 575.00
Sundries. 10.00 % 57.50
TOTAL 632.50
Contractor's profit 10.00 % 63.25
TOTAL PART " B " 695.75
____ Total labour rate for 75 Nos: cuts. Rs: 695.75
Total labour rate for 100 Nos: cuts. Rs: 927.67
____ Total labour rate for 100 Nos: cuts. Rs: 927.67
S/N ______________________________ ______ ______ ______ ________ _________
44 ______________________________ ______ ______ ______ ________ _________
(a) D E S C R I P T I O N.
____ Fixing doors including chowkhats.
(A)
LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Mason. 0.33 Nos: 450.00 P.day. 148.50

Cooly. 0.33 Nos: 250.00 P.day. 82.50


______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 231.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 23.10
______________________________ ______ ______ ______ ________ _________
TOTAL 254.10
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 25.41
______________________________ ______ ______ ______ ________ _________
____ TOTAL PART " B " 279.51
______________________________ ______ ______ ______ ________ _________
Total labour rate for each No: Rs: 279.51
____ ______________________________ ______ ______ ______ ________ _________
S/N
44 ______________________________ ______ ______ ______ ________ _________
(b) D E S C R I P T I O N.

____ Fixing windows including chowkhats.

Chapter No. 9 772/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(A)
LABOUR QUANTITY
RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 2 Nos:
Mason. 0.33 Nos: 450.00 P.day. 148.50

Cooly. 0.33 Nos: 250.00 P.day. 82.50


______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 231.00
Sundries. 10.00 % 23.10
TOTAL 254.10
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 25.41
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 279.51
______________________________ ______ ______ ______ ________ _________
____ Total labour rate for 2 Nos: Rs: 279.51
Total labour rate for each No: Rs: 139.76
____ Total labour rate for each No: say Rs: 139.76
S/N ______________________________ ______ ______ ______ ________ _________

45 ______________________________ ______ ______ ______ ________ _________


(a) D E S C R I P T I O N.

Glazing with panes (16 oz. to 18 oz.) including cost of putty.

____
(A)

______________________________ ______ ______ ______ ________ _________


MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 14 Sft.

Glass panes.(16-18 oz:) 14.00 Sft. 80.0 P.Sft. 1120.00


Add 10% wastage. 1.40 Sft. 80.0 P.Sft. 112.00
Cost of putty and nails. L.S 30.00

______________________________ ______ ______ ______ ________ _________


TOTAL 1262.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 126.20
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 1388.20
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Glazier for cutting and 0.25 Nos: 400.00 P.day. 100.00
fixing glass panes
including applying front

Chapter No. 9 773/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

and back putty.

Cooly skilled. 0.25 Nos: 250.00P.day. 62.50


______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 162.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 16.25
______________________________ ______ ______ ______ ________ _________
TOTAL 178.75
Contractor's profit 10.00 % 17.88
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 14.04 196.63
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 1584.83
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 14 Sft. Rs: 1584.83
Total material & labour per Sft. Rs: 113.20
____ Total material & labour per Sft. say Rs: 113.20
S/N ______________________________ ______ ______ ______ ________ _________

45 ______________________________ ______ ______ ______ ________ _________


(b) D E S C R I P T I O N.

Glazing with panes (16 oz. to 18 oz.) using deodar wooden (Ist:
class) fillets and putty.
____
(A)
MATERIAL QUANTITYRATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 14 Sft.

Glass panes.(16-18 oz:) 14.00 Sft. 80.0 P.Sft. 1120.00

Deodar wood. 0.09 Cft. 4500.0 P.Cft. 405.00

Cost of putty and nails. L.S 30.00


TOTAL 1555.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 155.50
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 1710.50
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Glazier for cutting and 0.25 Nos: 400.00 P.day. 100.00
fixing glass panes
including applying front
and back putty.

Cooly skilled. 0.25 Nos: 250.00 P.day. 62.50

Chapter No. 9 774/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Carpenter for preparing 0.125 Nos: 400.00 P.day. 50.00


wooden fillets.
TOTAL Rs: 212.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 21.25
TOTAL 233.75
Contractor's profit 10.00 % 23.38
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 18.37 257.13
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 1967.63
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 14 Sft. Rs: 1967.63
Total material & labour per Sft. Rs: 140.54
____ Total material & labour per Sft. say Rs: 140.54
S/N ______________________________ ______ ______ ______ ________ _________
46 ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
Glazing with panes (24 oz. to 26 oz.) using putty and deodar wooden (Ist:
class) fillets.
____
(A)
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Considering 5 Nos: of panes of average size i.e 18" * 24".
= 5 * 18" * 24"/144 = 15 Sft.
______________________________ ______ ______ ______ ________ _________
Assume for 15 Sft.

Glass panes.(24-26 oz:) 15.00 Sft. 95.0 P.Sft. 1425.00

Wastage 10% 1.50 Sft. 95.0 P.Sft. 142.50

Deodar wood. 0.06 Cft. 4500.0 P.Cft. 270.00

Cost of putty and nails. L.S 20.00


TOTAL 1857.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 185.75
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 2043.25
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Glazier for cutting and 0.38 Nos: 400.00 P.day. 150.00
fixing glass panes
including applying front
and back putty.

Cooly skilled. 0.50 Nos: 250.00 P.day. 125.00

Chapter No. 9 775/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Carpenter for preparing 0.125 Nos: 400.00 P.day. 50.00


wooden fillets.
TOTAL Rs: 325.00
Sundries. 10.00 % 32.50
______________________________ ______ ______ ______ ________ _________
TOTAL 357.50
Contractor's profit 10.00 % 35.75
TOTAL PART " B " 26.22 393.25
TOTAL (MATERIAL + LABOUR) 2436.50
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 15 Sft. Rs: 2436.50
Total material & labour per Sft. Rs: 162.43
____ Total material & labour per Sft. say Rs: 162.43
S/N ______________________________ ______ ______ ______ ________ _________

47 ______________________________ ______ ______ ______ ________ _________


(a) D E S C R I P T I O N.

Cutting to required sizes and fixing glass panes with putty.

____
(A)

______________________________ ______ ______ ______ ________ _________


MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 14 Sft.

Cost of putty and nails. L.S 60.00

______________________________ ______ ______ ______ ________ _________


TOTAL 60.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 6.00
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 66.00
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Glazier for cutting and 0.25 Nos: 400.00 P.day. 100.00
fixing glass panes
including applying front
and back putty.

Cooly skilled. 0.25 Nos: 250.00 P.day. 62.50


______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 162.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 16.25
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 776/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 178.75
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 17.88
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 14.04 196.63
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 262.63
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 14 Sft. Rs: 262.63
Total material & labour per Sft. Rs: 18.76
____ Total material & labour per Sft. say Rs: 18.76

S/N ______________________________ ______ ______ ______ ________ _________


47 ______________________________ ______ ______ ______ ________ _________
(b) D E S C R I P T I O N.

Cutting to required sizes and fixing glass panes with wooden


fillets and putty.
(A)
MATERIAL QUANTITYRATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 16 Sft.

Deodar wood. 0.1 Cft. 4500.0 P.Cft. 450.00

Cost of putty and nails. L.S 30.00

______________________________ ______ ______ ______ ________ _________


TOTAL 480.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 48.00
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 528.00
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Glazier for cutting and 0.33 Nos: 400.00 P.day. 133.33
fixing glass panes
including applying front
and back putty.

Carpenter. 0.125 Nos: 450.00 P.day. 56.25

Cooly skilled. 0.46 Nos: 250.00P.day. 114.58


______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 304.17
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 30.42
______________________________ ______ ______ ______ ________ _________
TOTAL 334.58
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 777/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 33.46


______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 23.00 368.04
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 896.04
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 16 Sft. Rs: 896.04
Total material & labour per Sft. Rs: 56.00
____ Total material & labour per Sft. say Rs: 56.00

S/N ______________________________ ______ ______ ______ ________ _________

48 ______________________________ ______ ______ ______ ________ _________


D E S C R I P T I O N.

(a) Glazing with plate glass 1/4" thick icluding the cost of deodar
wood fillets and putty.
____
(A) Glazing upto 8 square feet.
MATERIAL QUANTITY
RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 8 Sft.

Plate Glass 1/4" thick. 8.00 Sft. 125.0 P.Sft. 1000.00

Wastage 10% 0.80 Sft. 125.0 P.Sft. 100.00

Deodar wood. 0.05 Cft. 4500.0 P.Cft. 225.00

Cost of putty and nails. L.S 15.00


______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % #REF!
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " #REF!
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Glazier. 0.167 Nos: 400.00 P.day. 66.67

Cooly skilled. 0.2292 Nos: 250.00 P.day. 57.29

Carpenter. 0.0625 Nos: 450.00P.day. 28.13


______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 152.08
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 15.21
______________________________ ______ ______ ______ ________ _________
TOTAL 167.29
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 16.73
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 778/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL PART " B " 23.00 184.02


______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) #REF!
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 8 Sft. Rs: #REF!
Total material & labour per Sft. Rs: #REF!
____ Total material & labour per Sft. say Rs: #REF!

S/N ______________________________ ______ ______ ______ ________ _________

48 ______________________________ ______ ______ ______ ________ _________


D E S C R I P T I O N.

(b) Glazing with plate glass 1/4" thick icluding the cost of deodar
wood fillets and putty.
____
(A) Glazing exceeding 8 Sft and not exceeding 24 Sft.
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Assume for 16 Sft.

Plate Glass 1/4" thick. 16.00 Sft. 125.0 P.Sft. 2000.00

Wastage 10% 1.60 Sft. 125.0 P.Sft. 200.00

Deodar wood. 0.1 Cft. 4500.0 P.Cft. 450.00

Cost of putty and nails. L.S 30.00

______________________________ ______ ______ ______ ________ _________


TOTAL 2680.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 268.00
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 2948.00
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Glazier. 0.333 Nos: 400.00 P.day. 133.33

Cooly skilled. 0.4583 Nos: 250.00 P.day. 114.58

Carpenter. 0.125 Nos: 450.00 P.day. 56.25


______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 304.17
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 30.42
TOTAL 334.58
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 33.46
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 779/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL PART " B " 23.00 368.04


TOTAL (MATERIAL + LABOUR) 3316.04
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 16 Sft. Rs: 3316.04
Total material & labour per Sft. Rs: 207.25
____ Total material & labour per Sft. say Rs: 207.25
S/N ______________________________ ______ ______ ______ ________ _________

49 ______________________________ ______ ______ ______ ________ _________


D E S C R I P T I O N.

Supplying wooden keys of Kikar wood for Railway truck only.

____
(A)

______________________________ ______ ______ ______ ________ _________


MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Kikar wood. 7.41 Cft. 1400.0 P.Cft. 10374.00

______________________________ ______ ______ ______ ________ _________


TOTAL 10374.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 1037.40
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 11411.40
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 2.00 Nos: 450.00 P.day. 900.00

Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00

______________________________ ______ ______ ______ ________ _________


TOTAL Rs: 1150.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 115.00
______________________________ ______ ______ ______ ________ _________
TOTAL 1265.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 126.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 1391.50
______________________________ ______ ______ ______ ________ _________
____ TOTAL (MATERIAL + LABOUR) 12802.90
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 780/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ Total material & labour for 100 Sft. say Rs: 12802.90

______________________________ ______ ______ ______ ________ _________


S/N
50 ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.

Providing and fixing vention windows and ventilators of Ist:


class deodar wooden frame and Ist: class deodar wooden louvers.
(A)

______________________________ ______ ______ ______ ________ _________


MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood Frame heads= 2 * 3' * 7/24' * 1/4' 0.437
Side posts 2 * 4' * 7/24' * 1/4' 0.583
Louvers 1/2" thick = 3.5' * 2.5' * 1/24' 0.364
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total. 1.384
Wastage 10% 0.138
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total wood required for 4' * 3' = 12 Sft. 1.522
______________________________ ______ ______ ______ ________ _________
Deodar wood I-class. 1.522 Cft. 4500.0 P.Cft. 6849.00

Nails etc. L.S. 15.00


TOTAL 6864.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 686.40
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 7550.40
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 1.00 Nos: 450.00 P.day. 450.00
Cooly. 0.50 Nos: 250.00 P.day. 125.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 575.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 57.50
______________________________ ______ ______ ______ ________ _________
TOTAL 632.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 63.25
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 57.98 695.75
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 8246.15
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 12 Sft. Rs: 8246.15

Chapter No. 9 781/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour per Sft. Rs: 687.18


____ Total material & labour per Sft. say Rs: 687.18
S/N ______________________________ ______ ______ ______ ________ _________
51
D E S C R I P T I O N.
Providing and fixing in position doors, windows and ventilators
of first class deodar wood frames, and 1-1/2" thick Teak wood
ply shutters of first class deodar wood skeleton (Solid) styles
and rails core of partal wood and Teak ply wood (3 ply) on both
____ sides including hold fasts, hinges, iron tower bolts, handles
(A) and cleats with cord etc, complete.
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
First class deodar wood
Frames = 7'-2"+7'-2"+4'-0" = 18'-4" 18.33 Rft.
18.33 Rft * 3" * 4-1/2"/144 1.72 Cft.
Core styles = 2 * 6'-11" * 4" *1-1/2" 0.577 Cft.
Rails top & bottom = 2 * 3'-11" * 6" * 1-1/2" 0.49 Cft.
Total 2.79 Cft.
Wastage 15% 0.42 Cft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total quantity of D.wood for 7' * 4' size door 3.20 Cft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Partal wood for core. 20 Nos: 5'-11" long 1-1/2" thick & 6" wide.
Vertical sashes 20 Nos: =20*5.92'*2/12'* 3/24' 2.470 Cft.
Wastage 15% 0.371 Cft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total quantity of P.wood for 7' * 4' size door 2.841 Cft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Teak ply wood sheets = 2 * 6'-11" * 6'-11" 54.25 Sft.
Wastage 10% 5.43 Sft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total quantity of Teak ply wood sheet. 59.68 Sft.
______________________________ ______ ______ ______ ________ _________
Dedar wood. 3.20 Cft. 4500.0 P.Cft. 14400.00

Partal wood. 2.841 Cft. 1700.0 P.Cft. 4829.70

Teak ply wood sheets. 59.68 Sft. 120.00 P.Sft. 7161.60

Hinges of 5" size. 4.00 Nos: 400.00 P.doz: 133.33

Iron sliding Bolt 12" long. 2.00 Nos: 1950.00 P.doz: 325.00

Tower bolts 8" size. 2.00 Nos: 600.00 P.doz: 100.00

Handles. 6" size. 2.00 Nos: 275.00 P.doz: 45.83

Iron hold fasts. 3.00 Nos: 90.00 Each. 270.00

Screws 1-1/2" long,12 gauge. 41.00 Nos: 315.00 P.Gross 89.69

Chapter No. 9 782/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Gum/ Glue. 1.50 Kg. 386.00 P.Kg. 579.00


______________________________ ______ ______ ______ ________ _________
TOTAL 27934.15
______________________________ ______ ______ ______ ________ _________
____ Contractor's profit 10.00 % 2793.42
______________________________ ______ ______ ______ ________ _________
____ TOTAL PART " A " 30727.57
S/N ______________________________ ______ ______ ______ ________ _________
51
______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
Providing and fixing in position doors, windows and ventilators
of first class deodar wood frames, and 1-3/4" thick Teak wood
ply shutters of first class deodar wood skeleton (Solid) styles
and rails core of partal wood and Teak ply wood (3 ply) on both
____ sides including hold fasts, hinges, iron tower bolts, handles
(B) and cleats with cord etc, complete.
( Continued )
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 6.00 Nos: 450.00 P.day. 2700.00

Coolies. 2.50 Nos: 250.00 P.day. 625.00

Mason for fixing frame. 0.25 Nos: 450.00 P.day. 112.50


______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 3437.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 343.75
______________________________ ______ ______ ______ ________ _________
TOTAL 3781.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 378.13
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 148.55 4159.38
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 34886.94
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 28 Sft. Rs: 34886.94
Total material & labour per Sft. Rs: 1245.96
____ Total material & labour per Sft. say Rs: 1245.96

Chapter No. 9 783/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________

______________________________ ______ ______ ______ ________ _________


S/N D E S C R I P T I O N.
52 Supplying and fixing false ceiling of plaster of paris in
____ pannels including making frame work of deodar wood i/c painting
(A) with soliginum paint.
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Sheets of plaster of paris 10' * 10' 100.00
Wastage 10% 10.00
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total 110
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
D.wood for frame Main Rafts= 6*10*1/4'*1/6' 2.5
Cross styles = 6* 10' * 1/6' * 1/8' 1.25
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total. 3.750
Wastage 15% 0.562
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total Deodar wood required for 100 Sft. 4.312
______________________________ ______ ______ ______ ________ _________
Iron bars 5/8" dia for holding frame = 4*3*3.5'*1.043 =43.81 Lbs.
______________________________ ______ ______ ______ ________ _________
Sheets. 110.0 Sft. 85.00 P.Sft. 9350.00

Partal Wood. 4.312 Cft. 1700.00 P.Cft. 7330.40

Soliginum paint. 1.5 Galn 1525.00 P.Gallon 2287.50

5/8" dia bars. 43.81 Lbs. 3550.00 P.Cwt. 1388.62


Nails of all sorts. 0.50 Kg 110.00 P.Kg 55.00
Screws of all sorts. 2.00 Doz: 315.00 P.Gross 52.50
______________________________ ______ ______ ______ ________ _________
TOTAL 20464.02
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 2046.40
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 22510.42
______________________________ ______ ______ ______ ________ _________
LABOUR
Carpenter. 2.50 Nos: P.day.
450.00 1125.00
Painter. 0.75 Nos: P.day.
400.00 300.00
Cooly. 3.50 Nos: P.day.
250.00 875.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 2300.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 230.00
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 784/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 2530.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 253.00
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 2783.00
______________________________ ______ ______ ______ ________ _________
____ TOTAL (MATERIAL + LABOUR) 25293.42
______________________________ ______ ______ ______ ________ _________
____ Total material & labour per 100 Sft. Rs: 25293.42
S/N ______________________________ ______ ______ ______ ________ _________
53 ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
Providing & fixing in position fixed glass glazing in first
class deodar wood frame of section 7-1/2 sq-inches etc, complete
size of glass 1/4" thick.
(A)
Assume for 4' * 6' =24 sq-ft.
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Deodar wood Horizontal rail= 2 * 4'* 7.5"/144 0.42 Cft.
Deodar wood Vertical rail =2*6'-2/8'*7.5"/144 0.65 Cft.
Total. 1.07 Cft.
Wastage 25% 0.27 Cft.
Total wood required for 4' * 6' = 24 Sft. 1.33 Cft.
______________________________ ______ ______ ______ ________ _________
Deodar wood. 1.33 Cft. 4500.0 P.Cft. 5985.00

Iron hold fasts. 4.00 Nos: 90.00 Each 360.00

Glass 1/4" thick + wastage. 24.00 Sft. 125.0 P.Sft. 3000.00

Deodar wood for beading. 0.15 Cft. 4500.0 P.Cft. 675.00

Nails, screws & putty. L.S 20.00


TOTAL 10040.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 1004.00
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 11044.00
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 0.50 Nos: 450.00 P.day. 225.00
Glazier. 0.25 Nos: 400.00 P.day. 100.00
Cooly skilled. 0.25 Nos: 250.00 P.day. 62.50
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 387.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 38.75
______________________________ ______ ______ ______ ________ _________
TOTAL 426.25
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 785/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit %
10.00 42.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 19.54 468.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 11512.88
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 24.0 Sft. Rs: 11512.88
Total material & labour per Sft. Rs: 479.70
____ Total material & labour per Sft. say Rs: 479.70
S/N ______________________________ ______ ______ ______ ________ _________
54 ______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.

First class deodar wood wrought framed and fixed in place


including chowkhats hold fasts, tower bolts, chocks, cleats,
handles, cord with hooks and cost of nails and screws, etc.
(A) Panelled or panelled and glazed or fully glazed 1-1/2" thick.
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Deodar wood for H.rail=1*5'-3/4"*3-1/2"*4-1/2" 0.63 Cft.
Deodar wood for V.rail=2*8'-1/4'*3-1/2"*4-1/2" 1.80 Cft.
Double leaf shutters =1*4'-1/2'*7'-2/3'*1.5/12' 4.31 Cft.
Total 6.74 Cft.
Wastage 15% 1.01 Cft.
Deodar wood required for door of 5'*8' size 7.75 Cft.
Deodar wood. 7.75 Cft. 4500.00 P.Cft. 34875.00
Hinges of 5" size. 6.00 Nos: 400.00 P.doz: 200.00
Tower bolts 18" size. 2.00 Nos: 1225.00 P.doz: 204.17
Tower bolts 9" size. 2.00 Nos: 625.00 P.doz: 104.17
Handles.(BRASS) 8" size. 3.00 Nos: 210.00 Each. 630.00
Iron hold fasts. 6.00 Nos: 90.00 Each. 540.00
Hinged chocks of 6" size. 2.00 Nos: 375.00 P.doz: 62.50
Door stopers of 8" size. 2.00 Nos: 600.00 P.doz: 100.00
Screws of sorts. 2.50 Doz: 315.00 P.Gross 65.63
Spikes. L.S 10.00
Glue. L.S 20.00
TOTAL 36811.46
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 3681.15
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 40492.60
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 7.00 Nos: 450.00 P.day. 3150.00

Cooly skilled. 3.00 Nos: 250.00 P.day. 750.00


______________________________ ______ ______ ______ ________ _________
Rs: 3900.00
Sundries. 10.00 % 390.00
______________________________ ______ ______ ______ ________ _________
TOTAL 4290.00

Chapter No. 9 786/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


Contractor's profit 10.00 % 429.00
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 117.98 4719.00
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 45211.60
____ Total material & labour for 40 Sft. Rs: 45211.60
Total material & labour per Sft. Rs: 1130.29
____ Total material & labour per Sft. say Rs: 1130.29
S/N ______________________________ ______ ______ ______ ________ _________

55 ______________________________ ______ ______ ______ ________ _________


D E S C R I P T I O N.

Supplying and fixing commercial ply wood 3-ply in panels


____ including supplying and making deodar wood 2nd class frame work
(A) for partition walls.

______________________________ ______ ______ ______ ________ _________


MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Commercial plywood 3-ply 2 * 4' * 8' * 4' 256.00
Wastage 10% 25.60
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total 282
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Deodar wood for frame V.posts= 4*8'*1/3'*1/3' 3.55
Cross styles = 3'* 16' * 1/4' * 1/8' 1.50
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total. 5.05
Wastage 15% 0.76
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total wood required for 128 Sft. 5.81
______________________________ ______ ______ ______ ________ _________
Commercial plywood. 282.0 Sft. 75.0 P.Sft. 21150.00

Deodar wood.(2nd Class) 5.81 Cft. 4000.0 P.Cft. 23240.00

Nails of sorts. 0.50 Kg 110 P.Kg 55.00

Screws of sorts. 2.00 Doz: 315.00 P.Gross 52.50

______________________________ ______ ______ ______ ________ _________


TOTAL 44497.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 4449.75
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 48947.25
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 787/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 1.50 Nos: 450.00 P.day. 675.00
Cooly skilled. 1.50 Nos: 250.00 P.day. 375.00
______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 1050.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 105.00
______________________________ ______ ______ ______ ________ _________
TOTAL 1155.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 115.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 992.58 1270.50
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 50217.75
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 128 Sft. Rs: 50217.75
Total material & labour per 100 Sft. Rs: 39232.62
____ Total material & labour per 100 Sft. Rs: 39232.62

Chapter No. 9 788/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N ______________________________ ______ ______ ______ ________ _________

56 ______________________________ ______ ______ ______ ________ _________


D E S C R I P T I O N.

Supplying and fixing Wall Panel sheet in panels including


____ supplying and making deodar wood 2nd class frame work for
(A) partition walls.

______________________________ ______ ______ ______ ________ _________


MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Wall Panel Sheet 2 * 4' * 8' * 4' 256.00
Wastage 10% 25.60
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total 282
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Deodar wood for frame V.posts= 4*8'*1/3'*1/3' 3.55
Cross styles = 3'* 16' * 1/4' * 1/8' 1.50
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total. 5.05
Wastage 15% 0.76
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total wood required for 128 Sft. 5.81
______________________________ ______ ______ ______ ________ _________
Wall Panel Sheet. 282.0 Sft. 40.0 P.Sft. 11280.00

Deodar wood.(2nd Class) 5.81 Cft. 4000.0 P.Cft. 23240.00

Nails of sorts. 0.50 Kg 110 P.Kg 55.00

Screws of sorts. 2.00 Doz: 315.00 P.Gross 52.50

Gum & gum resin. 1.00 Kg 386.00 P.Kg 386.00

______________________________ ______ ______ ______ ________ _________


TOTAL 35013.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 3501.35
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 38514.85
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 1.50 Nos: 450.00 P.day. 675.00
Cooly skilled. 1.50 Nos: 250.00 P.day. 375.00

Chapter No. 9 789/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


TOTAL Rs: 1050.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 105.00
______________________________ ______ ______ ______ ________ _________
TOTAL 1155.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 115.50
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 992.58 1270.50
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 39785.35
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 128 Sft. Rs: 39785.35
Total material & labour per 100 Sft. Rs: 31082.30
____ Total material & labour per 100 Sft. Rs: 31082.30

Chapter No. 9 790/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________

S/N D E S C R I P T I O N.
57 Providing and fixing in position doors, windows and ventilators
of first class deodar wood frames, and 1-1/2" thick Teak wood
ply shutters of 2nd class deodar wood skeleton (Solid) styles
and rails core of partal wood and Teak ply wood (3 ply) on both
sides including hold fasts, hinges, iron tower bolts, handles
and cleats with cord etc, complete.
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
______________________________ ______ ______ ______ ________ _________
First class deodar wood
Frames = 7'-2"+7'-2"+4'-0" = 18'-4" 18.33 Rft.
18.33 Rft * 3" * 4-1/2"/144 1.72 Cft.
Core styles = 2 * 6'-11" * 4" *1-1/2" 0.577 Cft.
Rails top & bottom = 2 * 3'-11" * 6" * 1-1/2" 0.49 Cft.
Total 2.79 Cft.
Wastage 15% 0.42 Cft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total quantity of D.wood for 7' * 4' size door 3.20 Cft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Partal wood for core. 20 Nos: 5'-11" long 1-1/2" thick & 6" wide.
Vertical sashes 20 Nos: =20*5.92'*2/12'* 3/24' 2.470 Cft.
Wastage 15% 0.371 Cft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total quantity of P.wood for 7' * 4' size door 2.841 Cft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Teak ply wood sheets = 2 * 6'-11" * 6'-11" 54.25 Sft.
Wastage 10% 5.43 Sft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total quantity of Teak ply wood sheet. 59.68 Sft.
______________________________ ______ ______ ______ ________ _________
Dedar wood. 3.20 Cft. 4000.0 P.Cft. 12800.00

Partal wood. 2.841 Cft. 1700.0 P.Cft. 4829.70

Teak ply wood sheets. 59.68 Sft. 120.00 P.Sft. 7161.60

Hinges of 5" size. 4.00 Nos: 400.00 P.doz: 133.33

Iron sliding Bolt 12" long. 2.00 Nos: 1950.00 P.doz: 325.00

Tower bolts 8" size. 2.00 Nos: 600.00 P.doz: 100.00

Handles. 6" size. 2.00 Nos: 275.00 P.doz: 45.83

Iron hold fasts. 3.00 Nos: 90.00 Each. 270.00

Screws 1-1/2" long,12 gauge. 41.00 Nos: 315.00 P.Gross 89.69

Chapter No. 9 791/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Gum/ Glue. 1.50 Kg. 386.00 P.Kg. 579.00


______________________________ ______ ______ ______ ________ _________
TOTAL 26334.15
______________________________ ______ ______ ______ ________ _________
____ Contractor's profit 10.00 % 2633.42
____ TOTAL PART " A " 28967.57
S/N ______________________________ ______ ______ ______ ________ _________
57
______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
Providing and fixing in position doors, windows and ventilators
of first class deodar wood frames, and 1-1/2" thick Teak wood
ply shutters of second class deodar wood skeleton (Solid) styles
and rails core of partal wood and Teak ply wood (3 ply) on both
____ sides including hold fasts, hinges, iron tower bolts, handles
(B) and cleats with cord etc, complete.
( Continued )
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 6.00 Nos: 450.00 P.day. 2700.00

Coolies. 2.50 Nos: 250.00 P.day. 625.00

Mason for fixing frame. 0.25 Nos: 400.00P.day. 100.00


______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 3425.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 342.50
______________________________ ______ ______ ______ ________ _________
TOTAL 3767.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 376.75
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 148.01 4144.25
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 33111.82
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 28 Sft. Rs: 33111.82
Total material & labour per Sft. Rs: 1182.56
____ Total material & labour per Sft. say Rs: 1182.56

Chapter No. 9 792/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________

______________________________ ______ ______ ______ ________ _________


S/N D E S C R I P T I O N.
58 Providing and fixing in position doors, windows and ventilators
of first class deodar wood frames, and 1-1/2" thick Teak wood
ply shutters of second class deodar wood skeleton (Solid) styles
and rails core of partal wood and commercial plywood (3 ply) on
____ both sides including hold fasts, hinges, iron tower bolts,
(A) handles and cleats with cord etc, complete.
MATERIAL QUANTITY RATE UNIT AMOUNT
First class deodar wood
Frames = 7'-2"+7'-2"+4'-0" = 18'-4" 18.33 Rft.
18.33 Rft * 3" * 4-1/2"/144 1.72 Cft.
Core styles = 2 * 6'-11" * 4" *1-1/2" 0.577 Cft.
Rails top & bottom = 2 * 3'-11" * 6" * 1-1/2" 0.49 Cft.
Total 2.79 Cft.
Wastage 15% 0.42 Cft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total quantity of D.wood for 7' * 4' size door 3.20 Cft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Partal wood for core. 20 Nos: 5'-11" long 1-1/2" thick & 6" wide.
Vertical sashes 20 Nos: =20*5.92'*2/12'* 3/24' 2.470 Cft.
Wastage 15% 0.371 Cft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total quantity of P.wood for 7' * 4' size door 2.841 Cft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
commercial ply sheets =2 * 6'-11" * 6'-11" 54.25 Sft.
Wastage 10% 5.43 Sft.
-------------------------------------------------- ---------- ---------- ----------- ------------- ---------------
Total quantity of Teak ply wood sheet. 59.68 Sft.
______________________________ ______ ______ ______ ________ _________
Dedar wood. (2nd class) 3.20 Cft. 4000.0 P.Cft. 12800.00

Partal wood. 2.841 Cft. 1700.0 P.Cft. 4829.70

Commercial ply wood sheets. 59.68 Sft. 75.00 P.Sft. 4476.00

Hinges of 5" size. 4.00 Nos: 400.00 P.doz: 133.33

Iron sliding Bolt 12" long. 2.00 Nos: 1950.00 P.doz: 325.00

Tower bolts 8" size. 2.00 Nos: 600.00 P.doz: 100.00

Handles. 6" size. 2.00 Nos: 275.00 P.doz: 45.83

Iron hold fasts. 3.00 Nos: 90.00 Each. 270.00

Screws 1-1/2" long,12 gauge. 41.00 Nos: 315.00 P.Gross 89.69

Gum/ Glue. 1.50 Kg. 386.00 P.Kg. 579.00

Chapter No. 9 793/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____________ ________ _________


TOTAL 23648.55
______________________________ ______ ______ ______ ________ _________
____ Contractor's profit 10.00 % 2364.86
______________________________ ______ ______ ______ ________ _________
____ TOTAL PART " A " 26013.41
______________________________ ______ ______ ______ ________ _________
58
______________________________ ______ ______ ______ ________ _________
D E S C R I P T I O N.
Providing and fixing in position doors, windows and ventilators
of first class deodar wood frames, and 1-1/2" thick Teak wood
ply shutters of second class deodar wood skeleton (Solid) styles
and rails core of partal wood and Commercial ply wood (3 ply) on
____ both sides including hold fasts, hinges, iron tower bolts,
(B) handles and cleats with cord etc, complete.
( Continued )
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 6.00 Nos: 450.00 P.day. 2700.00

Coolies. 2.50 Nos: 250.00 P.day. 625.00

Mason for fixing frame. 0.25 Nos: 400.00 P.day. 100.00


______________________________ ______ ______ ______ ________ _________
TOTAL Rs: 3425.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 342.50
______________________________ ______ ______ ______ ________ _________
TOTAL 3767.50
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 376.75
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 148.01 4144.25
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 30157.66
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 28 Sft. Rs: 30157.66
Total material & labour per Sft. Rs: 1077.06
____ Total material & labour per Sft. say Rs: 1077.06

Chapter No. 9 794/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________

59 ______________________________ ______ ______ ______ ________ _________


D E S C R I P T I O N.

First class Sheesham wood wrought framed and fixed in place


including chowkhats hold fasts, tower bolts, chocks, cleats,
handles, cord with hooks and cost of nails and screws, etc.
____
(A) Panelled or panelled and glazed or fully glazed 1-1/2" thick.

______________________________ ______ ______ ______ ________ _________


MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
Shisham wood for H.rail=1*5'-3/4"*3-1/2"*4-1/2" 0.63 Cft.
Shisham wood for V.rail=2*8'-1/4'*3-1/2"*4-1/2" 1.80 Cft.
Double leaf shutters =1*4'-1/2'*7'-2/3'*1.5/12' 4.31 Cft.
Total 6.74 Cft.
Wastage 35% 2.36 Cft.
Deodar wood required for door of 5'*8' size 9.10 Cft.
______________________________ ______ ______ ______ ________ _________
Sheesham wood. 7.75 Cft. 2300.00 P.Cft. 17825.00
Hinges of 5" size. 6.00 Nos: 400.00 P.doz: 200.00
Tower bolts 18" size. 2.00 Nos: 1225.00 P.doz: 204.17
Tower bolts 9" size. 2.00 Nos: 625.00 P.doz: 104.17
Handles.(BRASS) 8" size. 3.00 Nos: 210.00 Each. 630.00
Iron hold fasts. 6.00 Nos: 90.00 Each. 540.00
Hinged chocks of 6" size. 2.00 Nos: 375.00 P.doz: 62.50
Door stopers of 8" size. 2.00 Nos: 600.00 P.doz: 100.00
Screws of sorts. 2.50 Doz: 315.00 P.Gross 65.63
Spikes. L.S 10.00
Glue. L.S 20.00
______________________________ ______ ______ ______ ________ _________
TOTAL 19761.46
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 1976.15
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 21737.60
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter. 7.00 Nos: 450.00 P.day. 3150.00

Cooly skilled. 3.00 Nos: 250.00 P.day. 750.00


______________________________ ______ ______ ______ ________ _________
Rs: 3900.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 390.00

Chapter No. 9 795/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


TOTAL 4290.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 429.00
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 117.98 4719.00
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 26456.60
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 40 Sft. Rs: 26456.60
Total material & labour per Sft. Rs: 661.42
____ Total material & labour per Sft. say Rs: 661.42

______________________________ ______ ______ ______ ________ _________

Chapter No. 9 796/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

60 ______________________________ ______ ______ ______ ________ _________


D I S C R I P T I O N.

Providing and fixing with sunk iron screws Wooden Architrave


approved design/shape having width not less than 2-1/2 inches
as directed by Engineer Incharge.
____
(A)
(Unit of rate per Rft.)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________
For 48 Rft.

Wooden Beeding. 48.00 Rft. 35.00 P.Rft. 1680.00

Add for wastage 20% 9.60 Rft. 35.00 P.Rft. 336.00

Screws. 4.00 Doz: 315.00 Gross 105.00

______________________________ ______ ______ ______ ________ _________


TOTAL 2121.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 212.10
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 2333.10
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______
______ ________ _________
Carpenter 0.12 Nos: 450.00 P.day 54.00
Rs: 54.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 5.40
______________________________ ______ ______ ______ ________ _________
TOTAL 59.40
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 5.94
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 1.36 65.34
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 2398.44
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 48 Rft. Rs: 2398.44
Total material & labour for 1 Rft. Rs: 49.97
____ Total material & labour per Rft. say Rs: 49.97
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 797/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

61 ______________________________ ______ ______ ______ ________ _________


D I S C R I P T I O N.

Providing and fixing Aluminum sheet on doors pasted with glue as per requirement.

____
(A)
(Unit of rate per Sft.)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Aluminum sheet i/c 10% wastage. 110.00 Sft. 35.00 P.Sft. 3850.00

Glue (Adhesive Mixture) 3.00 kg 386.00 P.Kg 1158.00

Brushes etc. L.S 10.00


______________________________ ______ ______ ______ ________ _________
TOTAL 5018.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 501.80
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 5519.80
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter 1.00 Nos: 450.00 P.day 450.00

Coolies. 1.00 Nos P.day


250.00 250.00
Rs: 700.00
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 70.00
______________________________ ______ ______ ______ ________ _________
TOTAL 770.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 77.00
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 8.47 847.00
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 6366.80
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 100 Sft. Rs: 6366.80
Total material & labour for 1 Sft. Rs: 63.67
____ Total material & labour per Sft. say Rs: 63.67
______________________________ ______ ______ ______ ________ _________

62 ______________________________ ______ ______ ______ ________ _________


D I S C R I P T I O N.

Chapter No. 9 798/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Galvanized wire gauge 144 mesh per square inch of 22 S.W.G fixed to choekats
without deodar patti.

____
(A)
(Unit of rate per Sft.)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Wire gauge 144 mesh i/c 5 % 12.60 Sft. 75.00 P.Sft. 945.00
wastage.

Screws/Nails L.S 20.00

______________________________ ______ ______ ______ ________ _________


TOTAL 965.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 96.50
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 1061.50
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter 0.25 Nos: 450.00 P.day 112.50

Skilled Coolies. 0.10 Nos 250.00 P.day 25.00


______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % #REF!
______________________________ ______ ______ ______ ________ _________
TOTAL #REF!
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % #REF!
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " #REF! #REF!
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) #REF!
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 12 Sft. Rs: #REF!
Total material & labour for 1 Sft. Rs: #REF!
____ Total material & labour per Sft. say Rs: #REF!
S/N ______________________________ ______ ______ ______ ________ _________

63 ______________________________ ______ ______ ______ ________ _________


(A) D I S C R I P T I O N.

Chapter No. 9 799/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Nlylon wire gauge 144 mesh per square inch fised to chowkats with 3/4" deodar
strips and screws.
(A)
(Unit of rate per Sft.)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Deodar wood Horizantal strips 0.09 Cft 4500 P.Cft 405.00

Deodar wood vertical strips 0.11 Cft 4500 P.Cft 495

wastage 25 % 0.05 Cft 4500.00 P.Cft 225.00

Wire gauge i/c 5% wastage of 12.60 Sft 50.00 P.Sft 630.00


3.0 x 4.0

Screws for all sorts L.S 20


TOTAL 1775.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 177.50
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 1952.50
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter 0.50 Nos: 450.00 P.day 225.00

Coolies. Skilled. 0.25 Nos P.day


250.00 62.50
Rs: 287.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 28.75
______________________________ ______ ______ ______ ________ _________
TOTAL 316.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 31.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 28.99 347.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 2300.38
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 12 Sft. Rs: 2300.38
Total material & labour for 1 Sft. Rs: 191.70
____ Total material & labour per Sft. say Rs: 191.70
S/N ______________________________ ______ ______ ______ ________ _________

63 ______________________________ ______ ______ ______ ________ _________


(B) D I S C R I P T I O N.

Nlylon wire gauge 144 mesh per square inch fised to chowkats

Chapter No. 9 800/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

without deodar patti


____
(A)
(Unit of rate per Sft.)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Wire gauge i/c 5% wastage of 12.6 p.sft 50 p.sft 630


3.0 x 4.0

Screws for all sorts LS 20.00


______________________________ ______ ______ ______ ________ _________
TOTAL 650.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 65.00
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 715.00
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter 0.25 Nos: 450.00 P.day 112.50

Coolies. Skilled. 0.10 Nos 250.00 P.day 25.00

______________________________ ______ ______ ______ ________ _________


Rs: 137.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 13.75
______________________________ ______ ______ ______ ________ _________
TOTAL 151.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 15.13
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 13.86 166.38
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 881.38
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 12 Sft. Rs: 881.38
Total material & labour for 1 Sft. Rs: 73.45
____ Total material & labour per Sft. say Rs: 73.45
______________________________ ______ ______ ______ ________ _________

64 ______________________________ ______ ______ ______ ________ _________


(A) D I S C R I P T I O N.

Aluminum wire gauge 144 mesh P.Square fixed to chowkats with 3/4" deodar strips
and screws.

____
(A)

Chapter No. 9 801/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(Unit of rate per Sft.)


______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Deodar wood for 3.0 x 4.0 window 0.25 Cft 4500 P.Cft 1125

Wire gauge i/c 5% wastage of 12.60 Sft 75.00 P.Sft 945.00


3.0 x 4.0

Nails /Screws. L.S 20

______________________________ ______ ______ ______ ________ _________


TOTAL 2090.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 209.00
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 2299.00
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter 0.50 Nos: 450.00 P.day 225.00

Coolies. Skilled. 0.25 Nos 250.00 P.day 62.50

Rs: 287.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 28.75
______________________________ ______ ______ ______ ________ _________
TOTAL 316.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 31.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 28.99 347.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 2646.88
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 12 Sft. Rs: 2646.88
Total material & labour for 1 Sft. Rs: 220.57
____ Total material & labour per sft. say Rs: 220.57
S/N ______________________________ ______ ______ ______ ________ _________

64 ______________________________ ______ ______ ______ ________ _________


(B) D I S C R I P T I O N.

Aluminum wire gauge 144 mesh P. Square fixed to chowkats.


(A)
(Unit of rate per Sft.)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:

Chapter No. 9 802/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________

Aluminum wire gauge 12.6 Sft 75 P.Sft 945

Nalis /Screws. L.S 20.00

______________________________ ______ ______ ______ ________ _________


TOTAL 965.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 96.50
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 1061.50
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter 0.25 Nos: 450.00 P.day 112.50

Coolies. Skilled. 0.10 Nos P.day


250.00 25.00
Rs: 137.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 13.75
______________________________ ______ ______ ______ ________ _________
TOTAL 151.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 15.13
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 13.86 166.38
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 1227.88
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 12 Sft. Rs: 1227.88
Total material & labour for 1 Sft. Rs: 102.32
____ Total material & labour per Sft. say Rs: 44.05
______________________________ ______ ______ ______ ________ _________

______________________________ ______ ______ ______ ________ _________


D I S C R I P T I O N.
S/N G I expend actual 1/2" to 3/4" mesh 16 gauge fixed to chowkats without deodar patti.

65
____
(A)
(Unit of rate per Sft.)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Expamded Metal 12 Sft 39 P.Sft 468

Chapter No. 9 803/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Nalis /Screws. L.S 20.00

______________________________ ______ ______ ______ ________ _________


TOTAL 488.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 48.80
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 536.80
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter 0.25 Nos: 450.00 P.day 112.50

Coolies. Skilled. 0.10 Nos 250.00 P.day 25.00

______________________________ ______ ______ ______ ________ _________


Rs: 137.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 13.75
______________________________ ______ ______ ______ ________ _________
TOTAL 151.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 15.13
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 13.86 166.38
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 703.18
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 12 Sft. Rs: 703.18
Total material & labour for 1 Sft. Rs: 58.60
____ Total material & labour per sft. say Rs: 58.60
______________________________ ______ ______ ______ ________ _________
66 ______________________________ ______ ______ ______ ________ _________
(A) D I S C R I P T I O N.

P/F G I expanded metal 1/8 -20 gauge fixed to chowkats with 3/4 " deodar strips
and screws.s

____
(A)
(Unit of rate per Sft.)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Deodar wood 3.0 x 4 .0 window. 0.25 Cft 4500 P.Cft 1125

Chapter No. 9 804/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

G I expanded metal 1/8 -20 gauge. 12 Sft 39 P.Sft 468

Nalis /Screws. L.S 20.00

______________________________ ______ ______ ______ ________ _________


TOTAL 1613.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 161.30
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 1774.30
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter 0.50 Nos: 450.00 P.day 225.00

Coolies. Skilled. 0.25 Nos P.day


250.00 62.50
Rs: 287.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 28.75
______________________________ ______ ______ ______ ________ _________
TOTAL 316.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 31.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 28.99 347.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 2122.18
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 12 Sft. Rs: 2122.18
Total material & labour for 1 Sft Rs: 176.85
____ Total material & labour per Sft. say Rs: 176.85
S/N ______________________________ ______ ______ ______ ________ _________

66 ______________________________ ______ ______ ______ ________ _________


(B) D I S C R I P T I O N.

P/F G I expanded metal 1/8 -20 gauge fixed to chowkats

____
(A)
(Unit of rate per Sft.)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Expanded metal 1/8 -20 gauge.s 12 Sft 46 P.Sft 552

Chapter No. 9 805/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Nalis /Screws. LS 20.00


TOTAL 572.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 57.20
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 629.20
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter 0.25 Nos: 450.00 P.day 112.50

Coolies. Skilled. 0.10 Nos 250.00 P.day 25.00

Rs: 137.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 13.75
______________________________ ______ ______ ______ ________ _________
TOTAL 151.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 15.13
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 13.86 166.38
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 795.58
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 12 Sft. Rs: 795.58
Total material & labour for 1 Sft. Rs: 66.30
____ Total material & labour per Sft. say Rs: 66.30

S/N ______________________________ ______ ______ ______ ________ _________

67 ______________________________ ______ ______ ______ ________ _________


(A) D I S C R I P T I O N.

P/F G I expanded metal 3/32 (20-gauge) fixed to chowkats with 3/4" deodar strips
and screws.

____
(A)
(Unit of rate per Sft.)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Deodar wood 3.0 x 4 .0 window. 0.25 Cft 4500 P.Cft 1125

expanded metal 3/32 -20 gauge. 12 Sft 39 P.Sft 468

Chapter No. 9 806/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Nalis /Screws. LS 20.00

TOTAL 1613.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 161.30
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 1774.30
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter 0.50 Nos: 450.00 P.day 225.00

Coolies. Skilled. 0.25 Nos 250.00 P.day 62.50


______________________________ ______ ______ ______ ________ _________
Rs: 287.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 28.75
______________________________ ______ ______ ______ ________ _________
TOTAL 316.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 31.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 28.99 347.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 2122.18
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 12 Sft. Rs: 2122.18
Total material & labour for 1 Sft. Rs: 176.85
____ Total material & labour per Sft. say Rs: 176.85
S/N ______________________________ ______ ______ ______ ________ _________

67 ______________________________ ______ ______ ______ ________ _________


(B) D I S C R I P T I O N.

P/F G I expanded metal 3/32 (20 -gauge) fixed to chowkats


Without deodar strips.

____
(A)
(Unit of rate per Sft.)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Expanded metal 3/32 -20 gauge.s 12 Sft 39 P.Sft 468

Nalis /Screws. LS 20.00

Chapter No. 9 807/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


TOTAL 488.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 48.80
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 536.80
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter 0.25 Nos: 450.00 P.day 112.50

Coolies. Skilled. 0.10 Nos 250.00 P.day 25.00


______________________________ ______ ______ ______ ________ _________
Rs: 137.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 13.75
______________________________ ______ ______ ______ ________ _________
TOTAL 151.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 15.13
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 13.86 166.38
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 703.18
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 12 Sft. Rs: 703.18
Total material & labour for 1 Sft. Rs: 58.60
____ Total material & labour per Sft. say Rs: 58.60
______________________________ ______ ______ ______ ________ _________

68 ______________________________ ______ ______ ______ ________ _________


(A) D I S C R I P T I O N.

Providing & fixing wilded wire mesh square shape (1/2 -18 gauge) with coating
fixing to chowkats with 3/4" deodar strips & screws.

____
(A)
(Unit of rate per Sft.)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Deodar wood 3.0 x 4 .0 window. 0.25 Cft 4500 P.Cft 1125

Welded wire (1/2" -18 gauge.) 12 Sft 18 P.Sft 216

Nalis /Screws. LS 20.00

TOTAL 1361.00

Chapter No. 9 808/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


Contractor's profit 10.00 % 136.10
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 1497.10
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter 0.50 Nos: 450 P.day 225.00

Coolies. Skilled. 0.25 Nos 250 P.day 62.50

Rs: 287.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 28.75
______________________________ ______ ______ ______ ________ _________
TOTAL 316.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 31.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 28.99 347.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 1844.98
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 12 Sft. Rs: 1844.98
Total material & labour for 1 Sft. Rs: 153.75
____ Total material & labour per Sft. say Rs: 58.45
______________________________ ______ ______ ______ ________ _________

68 ______________________________ ______ ______ ______ ________ _________


(B) D I S C R I P T I O N.

Providing & fixing welded wire mesh square shape (1/2 -18 gauge ) with coating
fixed to chowkats.

____
(A)
(Unit of rate per Sft.)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Welded wire (1/2"- 18 gauge.) 12 Sft 18 P.Sft 216

Welding rods 2.00 No 35.00 Each 70.00

TOTAL 286.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 28.60
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 314.60

Chapter No. 9 809/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ________ _________


LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter 0.33 Nos: 450.00 P.day 148.50

Coolies. 0.10 Nos 250.00 P.day 25.00

Hire charges of welding machines LS 30

Rs: 203.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 20.35
______________________________ ______ ______ ______ ________ _________
TOTAL 223.85
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 22.39
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 20.52 246.24
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 560.84
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 12 Sft. Rs: 560.84
Total material & labour for 1 Sft. Rs: 46.74
____ Total material & labour per Sft. say Rs: 46.74
______________________________ ______ ______ ______ ________ _________

69 ______________________________ ______ ______ ______ ________ _________


(A) D I S C R I P T I O N.

Providing & fixing crimped G I mesh square shape with 1" opening 12- gauge i/c
fixed in chowkats with screws by 3/4 " deodar strips.

____
(A)
(Unit of rate per Sft.)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Deodar wood 3.0 x 4 .0 window. 0.25 Cft 4500 P.Cft 1125

Crimped G I mesh 1" -12 gauge. 12 Sft 75 P.Sft 900

Nalis /Screws. LS 20.00


TOTAL 2045.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 204.50
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 2249.50
______________________________ ______ ______ ______ ________ _________

Chapter No. 9 810/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter 0.50 Nos: 450.00 P.day 225.00

Coolies. Skilled. 0.25 Nos 250.00 P.day 62.50

Rs: 287.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 28.75
______________________________ ______ ______ ______ ________ _________
TOTAL 316.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 31.63
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 28.99 347.88
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 2597.38
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 12 Sft. Rs: 2597.38
Total material & labour for 1 Sft. Rs: 216.45
____ Total material & labour per Sft. say Rs: 216.45
______________________________ ______ ______ ______ ________ _________

69 ______________________________ ______ ______ ______ ________ _________


(B) D I S C R I P T I O N.

Providing & fixing welded wire mesh square shape (1/2 -18 gauge ) with coating
fixed to chowkats.

____
(A)
(Unit of rate per Sft.)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Crimped wire Mesh (1"-12 gauge.) 12 Sft 63 P.Sft 756

Welding rods 2.00 No 35.00 Each 70.00


______________________________ ______ ______ ______ ________ _________
TOTAL 826.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 82.60
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 908.60
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter 0.33 Nos: 450.00 P.day 148.50

Chapter No. 9 811/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Coolies. 0.10 Nos 250.00 P.day 25.00

Hire charges of welding machines LS 30

Rs: 203.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 20.35
______________________________ ______ ______ ______ ________ _________
TOTAL 223.85
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 22.39
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 20.52 246.24
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 1154.84
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 12 Sft. Rs: 1154.84
Total material & labour for 1 Sft. Rs: 96.24
____ Total material & labour per Sft. say Rs: 96.24
______________________________ ______ ______ ______ ________ _________

70 ______________________________ ______ ______ ______ ________ _________


D I S C R I P T I O N.

Supplying & fixing window blinds (Horizontal / vertical ) with plain design and of
approved colour i/c fixing in windows with necessary accessories.

____
(A)
(Unit of rate per Sft.)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Window blinds i/c 10% wastage 17.6 Sft 60 P.Sft 1056

Nails /Screws. LS 15.00

______________________________ ______ ______ ______ ________ _________


TOTAL 1071.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 107.10
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 1178.10
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter 0.25 Nos: 450.00 P.day 112.50

Chapter No. 9 812/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Coolies. 0.10 Nos P.day 201.00


20.10
Rs: 132.60
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 13.26
______________________________ ______ ______ ______ ________ _________
TOTAL 145.86
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 14.59
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 10.03 160.45
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 1338.55
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 16 Sft. Rs: 1338.55
Total material & labour for 1 Sft. Rs: 83.66
____ Total material & labour per Sft. say Rs: 83.66
______________________________ ______ ______ ______ ________ _________

______________________________ ______ ______ ______ ________ _________


D I S C R I P T I O N.
S/N
Supplying & fixing window printed blinds (Horizontal / Vertical ) with plain design and
71 of approved colour i/c fixing in windows with necessary axxessories.

____ without Printrf blinds.


(A)
(Unit of rate per Sft.)
______________________________ ______ ______ ______ ________ _________
MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ________ _________

Window blinds printed i/c 17.6 Sft 65 P.Sft 1144


10 % wastage.

Nails /Screws. LS 15.00

______________________________ ______ ______ ______ ________ _________


TOTAL 1159.00
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 115.90
(B) ______________________________ ______ ______ ______ ________ _________
TOTAL PART " A " 1274.90
______________________________ ______ ______ ______ ________ _________
LABOUR
______________________________ ______ ______ ______ ________ _________
Carpenter 0.25 Nos: 450.00 P.day 112.50

Chapter No. 9 813/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Coolies. 0.10 Nos 250.00 P.day 25.00


______________________________ ______ ______ ______ ________ _________
Rs: 137.50
______________________________ ______ ______ ______ ________ _________
Sundries. 10.00 % 13.75
______________________________ ______ ______ ______ ________ _________
TOTAL 151.25
______________________________ ______ ______ ______ ________ _________
Contractor's profit 10.00 % 15.13
______________________________ ______ ______ ______ ________ _________
TOTAL PART " B " 10.40 166.38
______________________________ ______ ______ ______ ________ _________
TOTAL (MATERIAL + LABOUR) 1441.28
______________________________ ______ ______ ______ ________ _________
____ Total material & labour for 16 Sft. Rs: 1441.28
Total material & labour for 1 Sft. Rs: 90.08
Total material & labour per Sft. say Rs: 90.08

______________________________ ______ ______ ______ ________ _________

Chapter No. 9 814/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

FIRST FILL THIS SHEET

PAINTING AND VARNISHING

MATERIAL RATE UNIT

1 Oil Lin seed 1300 P.gal

2 Paint , Black and White Paint 1600 P.gal

3 Coaltar , Bitumen 86213.00 P.Ton

4 Mineral Pitch 25 Lbs

5 Lime Slaked 375 P.Mand

6 Herosine Oil 110 P.Lt

7 Fuel wood 900 P.Mand

8 French Polish 1800 P.gal

9 Varnish (1st quality) 1750 P.gal

10 Soligunm Paint 1525 P.gal

11 Creosote wood Pre servatine) 1450 P.gal

12 Caustic Soda 45 P.Lb

13 Black Jaman 1475 P.gal

14 Enamel paint 1850 P.gal

Chapter No. 10 815/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

LABOUR RATE UNIT

1 Skilled cooly 250 P.day

Painter , Polisher. 450 P.day

cooly 250 P.day

S/N P A I N T I N G A N D V A R N I S H I N G.
=================================================
NOTERates for all finishing works include the removal of surplus
debris, un-used material and by-products.

For handling of all types of materials for short leads including


carriage upto 3 chains nothing is to be paid as extra. Where
handling and carriage involves an extra lead beyond three chains,
carriage for whole of the distance should be provided in the
estimate.

The rate include the cost of scaffolding and its removal.


_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 816/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

D E S C R I P T I O N.

1. Cleaning painted wood work with oil and water.


(a)

____ _______________________________ ________ _____ ______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Oil linseed. 0.50 Lbs. 1300.00 Gallon. 65.00

Brushes and sand papers. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 77.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 7.70
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 84.70
_______________________________ ________ _____ ______ ______ ________
(B) LABOUR
_______________________________ ________ _____ ______ ______ ________
Cooly skilled. 0.20 Nos: 250.00 P.day. 50.00

_______________________________ ________ _____ ______ ______ ________


Rs: 50.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 5.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 55.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 5.50
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 60.50
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 145.20
Total material & labour for 100 Sft. Rs: 145.00

Chapter No. 10 817/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

1. Oiling wood work with boiled linseed oil.


(b)

____ _______________________________ ________ _____ ______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Oil linseed. 1.00 Lbs. 1300.00 Gallon. 130.00

Brushes and sand papers. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 142.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 14.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 156.20
_______________________________ ________ _____ ______ ______ ________
(B) LABOUR
_______________________________ ________ _____ ______ ______ ________
Cooly skilled. 0.20 Nos: 250.00 P.day. 50.00

_______________________________ ________ _____ ______ ______ ________


Rs: 50.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 5.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 55.00

Chapter No. 10 818/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


Contractor's profit 10.00 % 5.50
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 60.50
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 216.70
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 271.00
S/N D E S C R I P T I O N.

2. Brushing and scraping blisters of old paints from wood work.

____ _______________________________ ________ _____ ______ ______ ________


(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Skilled Cooly. 0.50 Nos: 250.00 P.day. 125.00

_______________________________ ________ _____ ______ ______ ________


Rs: 125.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 12.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 137.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 13.75
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 151.25
_______________________________ ________ _____ ______ ______ ________
Labour rate for 100 Sft. Rs: 151.25
____ _______________________________ ________ _____ ______ ______ ________

____ _______________________________ ________ _____ ______ ______ ________

Chapter No. 10 819/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

3. Scraping, brushing and removing old paint from metal surface.

____ _______________________________ ________ _____ ______ ______ ________


(A) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Skilled Cooly 2.00 Nos: 250.00 P.day. 500.00

_______________________________ ________ _____ ______ ______ ________


Rs: 500.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 50.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 550.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 55.00
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 605.00
_______________________________ ________ _____ ______ ______ ________
Labour rate for 100 Sft. Rs: 605.00

Chapter No. 10 820/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4. Painting old surfaces.


(a) Painting corrugated surfaces, patent roofing, etc, with oil
paint.

(i) First coat.

____ _______________________________ ________ _____ ______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 2.00 Lbs. 1600.00 P.Gallon 320.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 332.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 33.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 365.20
_______________________________ ________ _____ ______ ______ ________
(B) LABOUR
_______________________________ ________ _____ ______ ______ ________
Painter 0.33 Nos: 450.00 P.day. 148.50

Skilled'Cooly. 0.33 Nos: 250.00 P.day. 82.50

Chapter No. 10 821/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Rs: 231.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 23.10
_______________________________ ________ _____ ______ ______ ________
TOTAL 254.10
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 25.41
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 279.51
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 644.71
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 644.71
S/N D E S C R I P T I O N.

4. Painting old surfaces.


(a) Painting corrugated surfaces,patent roofing,etc,with oil paint.

(ii) Each susequent coat.

____ _______________________________ ________ _____ ______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 1.00 Lbs. 1600.00 P.Gallon 160.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 172.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 17.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 189.20
_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 822/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(B) LABOUR
_______________________________ ________ _____ ______ ______ ________
Painter 0.25 Nos: 450.00 P.day. 112.50

Cooly. 0.25 Nos: 250.00 P.day. 62.50

_______________________________ ________ _____ ______ ______ ________


Rs: 175.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 17.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 192.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 19.25
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 211.75
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 400.95
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 401.00
S/N D E S C R I P T I O N.

4. Painting old surfaces.


(b) Painting sashes, fan lights glazed or gauzed, doors and windows.

(i) First coat.

____ _______________________________ ________ _____ ______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 1.00 Lbs. 1600.00 P.Gallon 160.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 172.00

Chapter No. 10 823/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


Contractor's profit 10.00 % 17.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 189.20
_______________________________ ________ _____ ______ ______ ________
(B) LABOUR
_______________________________ ________ _____ ______ ______ ________
Painter 0.20 Nos: 450.00 P.day. 90.00

Skilled Cooly 0.20 Nos: 250.00 P.day. 50.00

_______________________________ ________ _____ ______ ______ ________


Rs: 140.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 14.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 154.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 15.40
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 169.40
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 358.60
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 359.00
____ _______________________________ ________ _____ ______ ______ ________

____ _______________________________ ________ _____ ______ ______ ________

S/N D E S C R I P T I O N.

4. Painting old surfaces.


(b) Painting sashes, fan lights glazed or gauzed, doors and windows.

(ii) Each subsequent coat.

____ _______________________________ ________ _____ ______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:

Chapter No. 10 824/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


Paint. 0.75 Lbs. 1600.00 P.Gallon 120.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 132.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 13.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 145.20
_______________________________ ________ _____ ______ ______ ________
(B) LABOUR
_______________________________ ________ _____ ______ ______ ________
Painter 0.17 Nos: 450.00 P.day. 76.50

Skilled 'Cooly. 0.17 Nos: 250.00 P.day. 42.50

_______________________________ ________ _____ ______ ______ ________


Rs: 119.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 11.90
_______________________________ ________ _____ ______ ______ ________
TOTAL 130.90
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 13.09
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 143.99
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 289.19
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 289.00
____ _______________________________ ________ _____ ______ ______ ________

S/N D E S C R I P T I O N.

Chapter No. 10 825/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

4. Painting old surfaces.


(c) Painting doors and windows any type.

(i) First coat.

____ _______________________________ ________ _____ ______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 2.00 Lbs. 1600.00 P.Gallon 320.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 332.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 33.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 365.20
_______________________________ ________ _____ ______ ______ ________
(B) LABOUR
_______________________________ ________ _____ ______ ______ ________
Painter 0.33 Nos: 450.00 P.day. 148.50

Cooly. 0.33 Nos: 250.00 P.day. 82.50

_______________________________ ________ _____ ______ ______ ________


Rs: 231.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 23.10
_______________________________ ________ _____ ______ ______ ________
TOTAL 254.10
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 25.41

Chapter No. 10 826/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


TOTAL PART " B " 279.51
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 644.71
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 644.71
____ _______________________________ ________ _____ ______ ______ ________
____ _______________________________ ________ _____ ______ ______ ________
S/N D E S C R I P T I O N.

4. Painting old surfaces.


(c) Painting doors and windows any type.

(ii) Each subsequent coat.

____ _______________________________ ________ _____ ______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 1.50 Lbs. 1600.00 P.Gallon 240.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 252.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 25.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 277.20
_______________________________ ________ _____ ______ ______ ________
(B) LABOUR
_______________________________ ________ _____ ______ ______ ________
Painter 0.25 Nos: 450.00 P.day. 112.50

Cooly. 0.25 Nos: 250.00 P.day. 62.50

Chapter No. 10 827/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


Rs: 175.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 17.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 192.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 19.25
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 211.75
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 488.95
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 489.00
____ _______________________________ ________ _____ ______ ______ ________
____ _______________________________ ________ _____ ______ ______ ________
S/N D E S C R I P T I O N.

4. Painting old surfaces.


(d) Painting gaurd bars gates, iron bars, gratting, railings
(including standard braces etc) and similar open work.

(a) First coat.

____ _______________________________ ________ _____ ______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 1.00 Lbs. 1600.00 P.Gallon 160.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 172.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 17.20
_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 828/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL PART " A " 189.20


_______________________________ ________ _____ ______ ______ ________
(B) LABOUR
_______________________________ ________ _____ ______ ______ ________
Painter 0.20 Nos: 450.00 P.day. 90.00

Cooly. 0.20 Nos: 250.00 P.day. 50.00

_______________________________ ________ _____ ______ ______ ________


Rs: 140.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 14.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 154.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 15.40
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 169.40
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 358.60
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 359.00
S/N D E S C R I P T I O N.

4. Painting old surfaces.


(d) Painting gaurd bars gates, iron bars, gratting, railings
(including standard braces etc) and similar open work.

(ii) Each subsequent coat.

____ _______________________________ ________ _____ ______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 0.75 Lbs. 1600.00 P.Gallon 120.00

Brushes. L.S. 12.00

Chapter No. 10 829/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


TOTAL 132.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 13.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 145.20
_______________________________ ________ _____ ______ ______ ________
(B) LABOUR
_______________________________ ________ _____ ______ ______ ________
Painter 0.17 Nos: 450.00 P.day. 76.50

Cooly. 0.17 Nos: 250.00 P.day. 42.50

_______________________________ ________ _____ ______ ______ ________


Rs: 119.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 11.90
_______________________________ ________ _____ ______ ______ ________
TOTAL 130.90
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 13.09
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 143.99
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 289.19
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 289.00
____ _______________________________ ________ _____ ______ ______ ________

S/N D E S C R I P T I O N.

4. Painting old surfaces.


(e) Painting fillets, framings, skirtings, pipes, gutters and
similar, linear work not exceeding 6" inches in grith.

(i) First coat.

____ _______________________________ ________ _____ ______ ______ ________

Chapter No. 10 830/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 1.00 Lbs. 1600.00 P.Gallon 160.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 172.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 17.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 189.20
_______________________________ ________ _____ ______ ______ ________
(B) LABOUR
_______________________________ ________ _____ ______ ______ ________
Painter 0.17 Nos: 450.00 P.day. 76.50

Cooly. 0.17 Nos: 250.00 P.day. 42.50

_______________________________ ________ _____ ______ ______ ________


Rs: 119.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 11.90
_______________________________ ________ _____ ______ ______ ________
TOTAL 130.90
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 13.09
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 143.99
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 333.19
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 333.00
____ _______________________________ ________ _____ ______ ______ ________

Chapter No. 10 831/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ _______________________________ ________ _____ ______ ______ ________


S/N D E S C R I P T I O N.

4. Painting old surfaces.


(e) Painting fillets, framings, skirtings, pipes, gutters and
similar, linear work not exceeding 6" inches in grith.

(ii) Each subsequent coat.

____ _______________________________ ________ _____ ______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 0.75 Lbs. 1600.00 P.Gallon 120.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 132.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 13.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 145.20
_______________________________ ________ _____ ______ ______ ________
(B) LABOUR
_______________________________ ________ _____ ______ ______ ________
Painter 0.12 Nos: 450.00 P.day. 54.00

Cooly. 0.12 Nos: 250.00 P.day. 30.00

_______________________________ ________ _____ ______ ______ ________


Rs: 84.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 8.40
_______________________________ ________ _____ ______ ______ ________
TOTAL 92.40

Chapter No. 10 832/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


Contractor's profit 10.00 % 9.24
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 101.64
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 246.84
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 247.00
____ _______________________________ ________ _____ ______ ______ ________

____ _______________________________ ________ _____ ______ ______ ________


S/N D E S C R I P T I O N.

4. Painting old surfaces.


(f) Painting small detached surface not exceeding one square foot of
painted surface.

(i) First coat.

____ _______________________________ ________ _____ ______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 2.00 Lbs. 1600.00 P.Gallon 320.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 332.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 33.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 365.20
_______________________________ ________ _____ ______ ______ ________
(B) LABOUR
_______________________________ ________ _____ ______ ______ ________
Painter 1.00 Nos: 450.00 P.day. 450.00

Cooly. 0.25 Nos: 250.00 P.day. 62.50

Chapter No. 10 833/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


Rs: 512.50
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 51.25
_______________________________ ________ _____ ______ ______ ________
TOTAL 563.75
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 56.38
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 620.13
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 985.33
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 985.00
S/N D E S C R I P T I O N.

4. Painting old surfaces.


(f) Painting small detached surface not exceeding one square foot of
painted surface.

(ii) Each subsequent coat.

____ _______________________________ ________ _____ ______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 1.00 Lbs. 1600.00 P.Gallon 160.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 172.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 17.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 189.20

Chapter No. 10 834/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


(B) LABOUR
_______________________________ ________ _____ ______ ______ ________
Painter 0.75 Nos: 450.00 P.day. 337.50

Cooly. 0.25 Nos: 250.00 P.day. 62.50

_______________________________ ________ _____ ______ ______ ________


Rs: 400.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 40.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 440.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 44.00
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 484.00
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 673.20
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 673.00
____ _______________________________ ________ _____ ______ ______ ________

____ _______________________________ ________ _____ ______ ______ ________


S/N D E S C R I P T I O N.

4. Painting old surfaces.


(g) Painting small detached articles exceeding one square foot and
not exceding three square foot of painted surface.

(i) First coat.

____ _______________________________ ________ _____ ______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 6.00 Lbs. 1600.00 P.Gallon 960.00

Chapter No. 10 835/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 972.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 97.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 1069.20
_______________________________ ________ _____ ______ ______ ________
(B) LABOUR
_______________________________ ________ _____ ______ ______ ________
Painter 2.00 Nos: 450.00 P.day. 900.00

Cooly. 0.50 Nos: 250.00 P.day. 125.00

_______________________________ ________ _____ ______ ______ ________


Rs: 1025.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 102.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 1127.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 112.75
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 1240.25
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 2309.45
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 2309.00
____ _______________________________ ________ _____ ______ ______ ________
S/N D E S C R I P T I O N.

4. Painting old surfaces.


(g) Painting small detached articles exceeding one square foot and
not exceding three square foot of painted surface.

(ii) Each subsequent coat.

Chapter No. 10 836/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ _______________________________ ________ _____ ______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 3.00 Lbs. 1600.00 P.Gallon 480.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 492.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 49.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 541.20
_______________________________ ________ _____ ______ ______ ________
(B) LABOUR
_______________________________ ________ _____ ______ ______ ________
Painter 1.00 Nos: 450.00 P.day. 450.00

Cooly. 0.50 Nos: 250.00 P.day. 125.00

_______________________________ ________ _____ ______ ______ ________


Rs: 575.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 57.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 632.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 63.25
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 695.75
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 1236.95
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 1237.00

Chapter No. 10 837/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ _______________________________ ________ _____ ______ ______ ________

____ D E S C R I P T I O N.
S/N
Painting new surfaces.
5. Preparing surface painting corrugated surfaces,patent roofing,etc
(a)

Priming coat.
(i)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 3.00 Lbs. 1600.00 P.Gallon 480.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 492.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 49.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 541.20
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.50 Nos: 450.00 P.day. 225.00

Cooly. 0.12 Nos: 250.00 P.day. 30.00

_______________________________ ________ _____ ______ ______ ________


Rs: 255.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 25.50

Chapter No. 10 838/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


TOTAL 280.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 28.05
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 308.55
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 849.75
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 849.75
_______________________________ ________ _____ ______ ______ ________
____ D E S C R I P T I O N.
S/N
Painting new surfaces.
5. Preparing surface painting corrugated surfaces, patent roofing,
(b) etc.

Each subsequent coat of paint.


(ii)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 2.50 Lbs. 1600.00 P.Gallon 400.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 412.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 41.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 453.20
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.25 Nos: 450.00 P.day. 112.50

Cooly. 0.08 Nos: 250.00 P.day. 20.00

Chapter No. 10 839/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


Rs: 132.50
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 13.25
_______________________________ ________ _____ ______ ______ ________
TOTAL 145.75
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 14.58
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 160.33
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 613.53
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. 614.00
_______________________________ ________ _____ ______ ______ ________
____
_______________________________ ________ _____ ______ ______ ________

____ D E S C R I P T I O N.
S/N
Painting new surfaces.
5. Preparing surface & painting sashes, fan lights glazed or
(b) gauzed, doors and windows etc, any type. (including edges)

Priming coat.
(i)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 1.75 Lbs. 1600.00 P.Gallon 280.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 292.00

Chapter No. 10 840/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


Contractor's profit 10.00 % 29.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 321.20
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.25 Nos: 450.00 P.day. 112.50

Cooly. 0.17 Nos: 250.00 P.day. 42.50

_______________________________ ________ _____ ______ ______ ________


Rs: 155.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 15.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 170.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 17.05
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 187.55
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 508.75
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 508.75
_______________________________ ________ _____ ______ ______ ________
____ D E S C R I P T I O N.
S/N
Painting new surfaces.
5. Preparing surface & painting sashes, fan lights glazed or
(b) gauzed, doors and windows etc, any type. (including edges)

Each subsequent coat.


(ii)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 1.40 Lbs. 1600.00 P.Gallon 224.00

Chapter No. 10 841/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 236.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 23.60
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 259.60
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.12 Nos: 450.00 P.day. 54.00

Cooly. 0.12 Nos: 250.00 P.day. 30.00

_______________________________ ________ _____ ______ ______ ________


Rs: 84.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 8.40
_______________________________ ________ _____ ______ ______ ________
TOTAL 92.40
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 9.24
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 101.64
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 361.24
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 95.00
_______________________________ ________ _____ ______ ______ ________
____
_______________________________ ________ _____ ______ ______ ________

____ D E S C R I P T I O N.
S/N
Painting new surfaces.
5. Preparing surface and painting doors and windows any type.

Chapter No. 10 842/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(c) (including edges)

Priming coat.
(i)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 3.00 Lbs. 1600.00 P.Gallon 480.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 492.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 49.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 541.20
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.50 Nos: 450.00 P.day. 225.00

Cooly. 0.12 Nos: 250.00 P.day. 30.00

_______________________________ ________ _____ ______ ______ ________


Rs: 255.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 25.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 280.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 28.05
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 308.55

Chapter No. 10 843/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


TOTAL (MATERIAL + LABOUR) 849.75
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 849.75
____ D E S C R I P T I O N.
S/N
Painting new surfaces.
5. Preparing surface and painting doors and windows any type.
(c) (including edges)

Each subsequent coat.


(ii)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 2.50 Lbs. 1600.00 P.Gallon 400.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 412.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 41.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 453.20
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.25 Nos: 450.00 P.day. 112.50

Cooly. 0.08 Nos: 250.00 P.day. 20.00

_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 844/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Rs: 132.50
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 13.25
_______________________________ ________ _____ ______ ______ ________
TOTAL 145.75
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 14.58
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 160.33
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 613.53
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 614.00
____ D E S C R I P T I O N.
S/N
Painting new surfaces.
5. Preparing surface and painting gaurd bars gates, iron bars,
(d) gratting, railings (including standard braces etc) and similar
open work.
Priming coat.
(a)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 1.75 Lbs. 1600.00 P.Gallon 280.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 292.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 29.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 321.20
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.25 Nos: 450.00 P.day. 112.50

Cooly. 0.17 Nos: 250.00 P.day. 42.50

Chapter No. 10 845/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


Rs: 155.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 15.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 170.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 17.05
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 187.55
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 508.75
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 508.75
_______________________________ ________ _____ ______ ______ ________
____
_______________________________ ________ _____ ______ ______ ________

____ D E S C R I P T I O N.
S/N
Painting new surfaces.
5. Preparing surface and painting gaurd bars gates, iron bars,
(d) gratting, railings (including standard braces etc) and similar
open work.
Each subsequent coat.
(ii)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 1.40 Lbs. 1600.00 P.Gallon 224.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 236.00
_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 846/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 23.60


_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 259.60
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.12 Nos: 450.00 P.day. 54.00

Cooly. 0.12 Nos: 250.00 P.day. 30.00

_______________________________ ________ _____ ______ ______ ________


Rs: 84.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 8.40
_______________________________ ________ _____ ______ ______ ________
TOTAL 92.40
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 9.24
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 101.64
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 361.24
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 361.00
_______________________________ ________ _____ ______ ______ ________
____
_______________________________ ________ _____ ______ ______ ________

____ D E S C R I P T I O N.
S/N
Painting new surfaces.
5. Preparing surface and painting fillets, framings, skirtings,
(e) pipes, gutters and similar, linear work not exceeding 6" inches
in grith.
Priming coat.
(i)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 847/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Paint. 1.30 Lbs. 1600.00 P.Gallon 208.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 220.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 22.00
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 242.00
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.17 Nos: 450.00 P.day. 76.50

Cooly. 0.17 Nos: 250.00 P.day. 42.50

_______________________________ ________ _____ ______ ______ ________


Rs: 119.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 11.90
_______________________________ ________ _____ ______ ______ ________
TOTAL 130.90
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 13.09
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 143.99
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 385.99
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 386.00
_______________________________ ________ _____ ______ ______ ________
____
_______________________________ ________ _____ ______ ______ ________

____ D E S C R I P T I O N.
S/N

Chapter No. 10 848/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Painting new surfaces.


5. Preparing surface and painting fillets, framings, skirtings,
(e) pipes, gutters and similar, linear work not exceeding 6" inches
in grith.
Each subsequent coat.
(ii)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 1.10 Lbs. 1600.00 P.Gallon 176.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 188.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 18.80
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 206.80
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.08 Nos: 450.00 P.day. 36.00

Cooly. 0.08 Nos: 250.00 P.day. 20.00

_______________________________ ________ _____ ______ ______ ________


Rs: 56.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 5.60
_______________________________ ________ _____ ______ ______ ________
TOTAL 61.60
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 6.16

Chapter No. 10 849/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


TOTAL PART " B " 67.76
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 274.56
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 275.00
____ D E S C R I P T I O N.
S/N
Painting new surfaces.
5. Preparing surface and painting small detached surface not
(f) exceeding one square foot of painted surface.

Priming coat.
(i)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 6.25 Lbs. 1600.00 P.Gallon 1000.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 1012.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 101.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 1113.20
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.75 Nos: 450.00 P.day. 337.50

Cooly. 0.75 Nos: 250.00 P.day. 187.50

_______________________________ ________ _____ ______ ______ ________


Rs: 525.00
_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 850/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Sundries. 10.00 % 52.50


_______________________________ ________ _____ ______ ______ ________
TOTAL 577.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 57.75
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 635.25
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 1748.45
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 1748.00
_______________________________ ________ _____ ______ ______ ________
____

_______________________________ ________ _____ ______ ______ ________


____ D E S C R I P T I O N.
S/N
Painting new surfaces.
5. Preparing surface and painting small detached surface not
(f) exceeding one square foot of painted surface.

Each subsequent coat.


(ii)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 5.00 Lbs. 1600.00 P.Gallon 800.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 812.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 81.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 893.20
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________

Chapter No. 10 851/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Painter 0.40 Nos: 450.00 P.day. 180.00

Cooly. 0.33 Nos: 250.00 P.day. 82.50

_______________________________ ________ _____ ______ ______ ________


Rs: 262.50
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 26.25
_______________________________ ________ _____ ______ ______ ________
TOTAL 288.75
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 28.88
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 317.63
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 1210.83
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 1210.83
_______________________________ ________ _____ ______ ______ ________
____

_______________________________ ________ _____ ______ ______ ________


____ D E S C R I P T I O N.
S/N
Painting new surfaces.
5. Preparing surface and painting of small detached articles
(g) exceeding one square foot and not exceding three square foot of
painted surface.
Priming coat.
(i)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 12.00 Lbs. 1600.00 P.Gallon 1920.00

Brushes. L.S. 12.00

Chapter No. 10 852/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


TOTAL 1932.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 193.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 2125.20
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 1.75 Nos: 450.00 P.day. 787.50

Cooly. 1.00 Nos: 250.00 P.day. 250.00

_______________________________ ________ _____ ______ ______ ________


Rs: 1037.50
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 103.75
_______________________________ ________ _____ ______ ______ ________
TOTAL 1141.25
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 114.13
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 1255.38
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 3380.58
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 3381.00
_______________________________ ________ _____ ______ ______ ________
____

_______________________________ ________ _____ ______ ______ ________


____ D E S C R I P T I O N.
S/N
Painting new surfaces.
5. Preparing surface and painting of small detached articles
(g) exceeding one square foot and not exceding three square foot of
painted surface.
Each subsequent coat.
(ii)

Chapter No. 10 853/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. 9.00 Lbs. 1600.00 P.Gallon 1440.00

Brushes. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 1452.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 145.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 1597.20
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.75 Nos: 450.00 P.day. 337.50

Cooly. 0.50 Nos: 250.00 P.day. 125.00

_______________________________ ________ _____ ______ ______ ________


Rs: 462.50
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 46.25
_______________________________ ________ _____ ______ ______ ________
TOTAL 508.75
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 50.88
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 559.63
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 2156.83
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 2157.00
_______________________________ ________ _____ ______ ______ ________
____ D E S C R I P T I O N.

Chapter No. 10 854/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N
Painting new surfaces.
5. Extra for knotting and stopping to priming coat on new surface
(h) of wood.

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Paint. L.S 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 12.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 1.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 13.20
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.06 Nos: 450.00 P.day. 27.00

_______________________________ ________ _____ ______ ______ ________


Rs: 27.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 2.70
_______________________________ ________ _____ ______ ______ ________
TOTAL 29.70
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 2.97
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 32.67
_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 855/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (MATERIAL + LABOUR) 45.87


_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 46.00

_______________________________ ________ _____ ______ ______ ________


____
_______________________________ ________ _____ ______ ______ ________
____ D E S C R I P T I O N.
S/N
Applying khanki mixture hot to barrage gates:-
6.
First coat.
(a)

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Coaltar. 0.04 Cwt. 86213.0 P.Ton 161.65

Mineral pitch. 0.50 Lbs. 25.00 P.Lb. 12.50

Slaked lime. 0.15 Lbs. 375.00 P.Mand. 0.69

Kerosine oil. 0.05 Galn 110.00 P.Litre 24.75

Fuel wood. 0.08 Mand 900.00 P.Mand. 67.50

Brushes etc. L.S 12.00


_______________________________ ________ _____ ______ ______ ________
TOTAL 279.09
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 27.91
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 306.99
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.25 Nos: 450.00 P.day. 112.50

Cooly. 0.25 Nos: 250.00 P.day. 62.50

Chapter No. 10 856/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


Rs: 175.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 17.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 192.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 19.25
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 211.75
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 518.74
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 518.74
____ D E S C R I P T I O N.
S/N
Applying khanki mixture hot to barrage gates:-
6.
Second coat.
(b)

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Coaltar. 0.023 Cwt. 86213.0 P.Ton 100.22

Mineral pitch. 0.310 Lbs. 25.00 P.Lb. 7.75

Slaked lime. 0.093 Lbs. 375.00 P.Mand. 0.43

Kerosine oil. 0.031 Galn 110.00 P.Litre 15.35

Fuel wood. 0.047 Mand 900.00 P.Mand. 41.85

Brushes etc. L.S 12.00


_______________________________ ________ _____ ______ ______ ________
TOTAL 177.59
_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 857/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 17.76


_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 195.35
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.16 Nos: 450.00 P.day. 72.00

Cooly. 0.25 Nos: 250.00 P.day. 62.50

_______________________________ ________ _____ ______ ______ ________


Rs: 134.50
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 13.45
_______________________________ ________ _____ ______ ______ ________
TOTAL 147.95
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 14.80
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 162.75
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 358.10
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 358.10
____ D E S C R I P T I O N.
S/N
French polishing complete.
7.
On new work.
(a)

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
French polish. 0.50 Galn 1800.00 P.Gallon 900.00

Brushes etc. L.S 45.00

Chapter No. 10 858/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


TOTAL 945.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 94.50
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 1039.50
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Polisher. 4.50 Nos: 450.00 P.day. 2025.00

Cooly. 1.00 Nos: 250.00 P.day. 250.00

_______________________________ ________ _____ ______ ______ ________


Rs: 2275.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 227.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 2502.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 250.25
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 2752.75
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 3792.25
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 3792.25

_______________________________ ________ _____ ______ ______ ________


____ D E S C R I P T I O N.
S/N
French polishing complete.
7.
On old work.
(b)

Chapter No. 10 859/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
French polish. 0.25 Galn 1800.00 P.Gallon 450.00

Brushes etc. L.S 30.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 480.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 48.00
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 528.00
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Polisher. 2.00 Nos: 450.00 P.day. 900.00

Cooly. 1.00 Nos: 250.00 P.day. 250.00

_______________________________ ________ _____ ______ ______ ________


Rs: 1150.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 115.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 1265.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 126.50
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 1391.50
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 1919.50
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 1919.50

Chapter No. 10 860/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ D E S C R I P T I O N.
S/N
Varnishing wood work including cleaning and preparing surface.
8.
First coat.
(a)

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Varnish. (Ist: quality) 0.33 Galn 1750.00 P.Gallon 577.50

Brushes etc. L.S 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 589.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 58.95
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 648.45
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter. 0.20 Nos: 450.00 P.day. 90.00

Cooly. 0.20 Nos: 250.00 P.day. 50.00

_______________________________ ________ _____ ______ ______ ________


Rs: 140.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 14.00
_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 861/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 154.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 15.40
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 169.40
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 817.85
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 817.85
_______________________________ ________ _____ ______ ______ ________
_______________________________ ________ _____ ______ ______ ________
____ D E S C R I P T I O N.
S/N
Varnishing wood work including cleaning and preparing surface.
8.
Second coat.
(b)

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Varnish. (Ist: quality) 0.25 Galn 1750.00 P.Gallon 437.50

Brushes etc. L.S 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 449.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 44.95
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 494.45
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter. 0.10 Nos: 450.00 P.day. 45.00

Chapter No. 10 862/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Cooly. 0.10 Nos: 250.00 P.day. 25.00

_______________________________ ________ _____ ______ ______ ________


Rs: 70.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 7.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 77.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 7.70
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 84.70
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 579.15
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 579.15
_______________________________ ________ _____ ______ ______ ________
____ D E S C R I P T I O N.
S/N
Varnishing wood work including cleaning and preparing surface.
8.
Third coat.
(c)

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Varnish. (Ist: quality) 0.20 Galn 1750.00 P.Gallon 350.00

Brushes etc. L.S 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 362.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 36.20

Chapter No. 10 863/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


TOTAL PART " A " 398.20
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter. 0.10 Nos: 450.00 P.day. 45.00

Cooly. 0.10 Nos: 250.00 P.day. 25.00

_______________________________ ________ _____ ______ ______ ________


Rs: 70.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 7.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 77.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 7.70
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 84.70
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 482.90
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 482.90

____ D E S C R I P T I O N.
S/N
Bitumen coating to plastered or cement concrete surface.
9.

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Bitumen. 12.00 Lbs. 86213.0 P.Ton 461.86

Fuel wood. 0.120 Mand 900.00 P.Mand. 108.00

Chapter No. 10 864/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


TOTAL 569.86
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 56.99
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 626.84
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________

Cooly. 0.50 Nos: 250.00 P.day. 125.00

_______________________________ ________ _____ ______ ______ ________


Rs: 125.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 12.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 137.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 13.75
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 151.25
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 778.09
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 778.09

____ D E S C R I P T I O N.
S/N
Writing letters or figures per letter per inch hieght.
10.

Chapter No. 10 865/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Assume for 100 Nos:
Paint. 0.60 Lbs. 1600.00 P.Gallon 96.00

Brushes etc. L.S 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 108.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 10.80
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 118.80
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 1.00 Nos: 450.00 P.day. 450.00

Cooly. 1.00 Nos: 250.00 P.day. 250.00

_______________________________ ________ _____ ______ ______ ________


Rs: 700.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 70.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 770.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 77.00
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 8.47 847.00
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 965.80
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Nos: Rs: 965.80
Total material & labour for 1 No: Rs: 9.66

Chapter No. 10 866/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for each No: Rs: 9.66


_______________________________ ________ _____ ______ ______ ________
____
_______________________________ ________ _____ ______ ______ ________
____ D E S C R I P T I O N.
S/N
Coaltar painting.
11.
First coat laid hot.
(a)

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Coaltar. 16.00 Lbs. 86213.0 P.Ton 615.81

Fuel wood. L.S 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 627.81
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 62.78
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 690.59
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________

Cooly skilled. 0.33 Nos: 250.00 P.day. 82.50

_______________________________ ________ _____ ______ ______ ________


Rs: 82.50
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 8.25

Chapter No. 10 867/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


TOTAL 90.75
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 9.08
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 99.83
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 790.41
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 790.41

_______________________________ ________ _____ ______ ______ ________


____ D E S C R I P T I O N.
S/N
Coaltar painting.
11.
Second coat laid hot.
(b)

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Coaltar. 10.00 Lbs. 86213.0 P.Ton 384.88

Fuel wood. L.S 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 396.88
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 39.69
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 436.57
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________

Chapter No. 10 868/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Cooly skilled. 0.20 Nos: 250.00 P.day. 50.00

_______________________________ ________ _____ ______ ______ ________


Rs: 50.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 5.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 55.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 5.50
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 60.50
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 497.07
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 497.07

____ D E S C R I P T I O N.
S/N
Solignum painting:-
12.
One coat applied hot.
(a)

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Solignum paint. 0.20 Galn 1525.0 P.Gallon 305.00

Brushes. L.S 12.00

_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 869/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 317.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 31.70
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 348.70
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________

Painter 0.33 Nos: 450.00 P.day. 148.50

_______________________________ ________ _____ ______ ______ ________


Rs: 148.50
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 14.85
_______________________________ ________ _____ ______ ______ ________
TOTAL 163.35
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 16.34
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 179.69
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 528.39
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 528.39

_______________________________ ________ _____ ______ ______ ________


____ D E S C R I P T I O N.
S/N
Solignum painting:-
12.
Two coat applied hot.
(b)

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 870/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Solignum paint. 0.34 Galn 1525.0 P.Gallon 518.50

Brushes. L.S 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 530.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 53.05
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 583.55
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________

Painter 0.50 Nos: 450.00 P.day. 225.00

_______________________________ ________ _____ ______ ______ ________


Rs: 225.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 22.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 247.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 24.75
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 272.25
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 855.80
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 855.80

____ D E S C R I P T I O N.
S/N
Creosote painting:-
13.

Chapter No. 10 871/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

One coat applied hot.


(a)

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Creosote. 0.20 Galn 1450.0 P.Gallon 290.00
(Wood preservative)
Brushes. L.S 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 302.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 30.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 332.20
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________

Painter 0.33 Nos: 450.00 P.day. 148.50

_______________________________ ________ _____ ______ ______ ________


Rs: 148.50
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 14.85
_______________________________ ________ _____ ______ ______ ________
TOTAL 163.35
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 16.34
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 179.69
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 511.89

Chapter No. 10 872/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


Total material & labour for 100 Sft. Rs: 511.89

_______________________________ ________ _____ ______ ______ ________


____ D E S C R I P T I O N.
S/N
Creosote painting:-
13.
Two coat applied hot.
(b)

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Creosote. 0.34 Galn 1450.0 P.Gallon 493.00
(Wood preservative)
Brushes. L.S 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 505.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 50.50
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 555.50
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________

Painter 0.50 Nos: 450.00 P.day. 225.00

_______________________________ ________ _____ ______ ______ ________


Rs: 225.00

Chapter No. 10 873/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


Sundries. 10.00 % 22.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 247.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 24.75
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 272.25
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 827.75
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 827.75

_______________________________ ________ _____ ______ ______ ________


____ D E S C R I P T I O N.
S/N
Burning off or rubbing down with pumice stone old paint from
14. wood work.

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______
Burner charges., Kerosine L.S 48.00
oil, scraper.

_______________________________ ________ _____ ______ ______ ________


TOTAL 48.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 4.80
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 52.80
_______________________________ ________ _____ ______ ______ ________
LABOUR

Chapter No. 10 874/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(B) _______________________________ ________ _____ ______ ______ ________

Cooly. 0.25 Nos: 250.00 P.day. 62.50

Cooly skilled.. 1.00 Nos: 250.00 P.day. 250.00

_______________________________ ________ _____ ______ ______ ________


Rs: 312.50
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 31.25
_______________________________ ________ _____ ______ ______ ________
TOTAL 343.75
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 34.38
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 378.13
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 430.93
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 430.93

_______________________________ ________ _____ ______ ______ ________


____ D E S C R I P T I O N.
S/N
Removing with caustic soda old paint from wood work.
15.

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Caustic soda. 2.00 P.Lb 45.00 P.Lb 90.00

Chapter No. 10 875/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


TOTAL 90.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 9.00
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 99.00
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________

Cooly. 0.50 Nos: 250.00 P.day. 125.00

_______________________________ ________ _____ ______ ______ ________


Rs: 125.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 12.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 137.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 13.75
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 151.25
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 250.25
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 250.25

____ D E S C R I P T I O N.
S/N
Painting distance marks for white ground and black lettering on
16. both sides.

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:

Chapter No. 10 876/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


Assume for 10 Nos:
White paint. 0.50 Lbs. 1600.00 P.Gallon 80.00

Black Jaman. 0.20 Lbs. 1475.00 P.Gallon 29.50

Brushes etc. L.S 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 121.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 12.15
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 133.65
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.50 Nos: 450.00 P.day. 225.00
Cooly. 0.50 Nos: 250.00 P.day. 125.00

_______________________________ ________ _____ ______ ______ ________


Rs: 350.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 35.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 385.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 38.50
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 42.35 423.50
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 557.15
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 10 Nos: Rs: 557.15
Total material & labour for 1 No: Rs: 55.72
Total material & labour for each No: Rs: 55.72

____ D E S C R I P T I O N.
S/N

Chapter No. 10 877/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Painting two feet wide gauges reading to 10th of a foot.


17.

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Assume for 10 Rft.

Paint. 1.00 Lbs. 1600.00 P.Gallon 160.00

LS 12

_______________________________ ________ _____ ______ ______ ________


TOTAL 172.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 17.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 189.20
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 1.00 Nos: 450.00 P.day. 450.00
Cooly. 1.00 Nos: 250.00 P.day. 250.00

_______________________________ ________ _____ ______ ______ ________


Rs: 700.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 70.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 770.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 77.00
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 84.7 847.00
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 1036.20

Chapter No. 10 878/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


Total material & labour for 10 Rft. Rs: 1036.20
Total material & labour for 1 foot. Rs: 103.62
Total material & labour per Rft. say Rs: 103.62

_______________________________ ________ _____ ______ ______ ________


____ D E S C R I P T I O N.
S/N
Painting sounding rods and other gauges, reading to 10th of a
18. foot.

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Assume for 10 Lft.

Brushes etc. L.S 12.00

Paint black and white. 0.25 Lbs. 1600.00 P.Gallon 40.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 52.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 5.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 57.20
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.50 Nos: 450.00 P.day. 225.00
Cooly. 0.50 Nos: 250.00 P.day. 125.00

_______________________________ ________ _____ ______ ______ ________


Rs: 350.00

Chapter No. 10 879/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


Sundries. 10.00 % 35.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 385.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 38.50
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 42.35 423.50
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 480.70
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 10 Lft. Rs: 480.70
Total material & labour for 1 foot. Rs: 48.07
Total material & labour per Lft. say Rs: 48.07

_______________________________ ________ _____ ______ ______ ________


____ D E S C R I P T I O N.
S/N
Painting levelling staves:-
19.

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Assume for 10 Lft.

Brushes etc. L.S 12.00

Paint black and white. 0.50 Lbs. 1600.00 P.Gallon 80.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 92.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 9.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 101.20

Chapter No. 10 880/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 2.00 Nos: 450.00 P.day. 900.00
Cooly. 1.00 Nos: 250.00 P.day. 250.00

_______________________________ ________ _____ ______ ______ ________


Rs: 1150.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 115.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 1265.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 126.50
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 139.15 1391.50
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 1492.70
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 10 Lft. Rs: 1492.70
Total material & labour for 1 foot. Rs: 149.27
Total material & labour per Lft. say Rs: 149.27

____ D E S C R I P T I O N.
S/N

20. Painting and lettering furlong stones two coats of both sides.
(a)

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Assume for 8 Nos:

Brushes etc. L.S 12.00

Paint black and white. 0.60 Lbs. 1600.00 P.Gallon 96.00

Chapter No. 10 881/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


TOTAL 108.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 10.80
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 118.80
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.25 Nos: 450.00 P.day. 112.50
Cooly. 0.25 Nos: 250.00 P.day. 62.50

_______________________________ ________ _____ ______ ______ ________


Rs: 175.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 17.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 192.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 19.25
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 21.18 211.75
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 330.55
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 8 Nos: Rs: 330.55
Total material & labour for 1 No: Rs: 41.32
Total material & labour for each No: say say Rs: 41.32

_______________________________ ________ _____ ______ ______ ________


____ D E S C R I P T I O N.
S/N

20. Painting and lettering mile stones two coats of both sides.
(b)

Chapter No. 10 882/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Assume for 1 No:

Brushes etc. L.S 12.00

Paint black and white. 0.60 Lbs. 1600.00 P.Gallon 96.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 108.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 10.80
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 118.80
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.25 Nos: 450.00 P.day. 112.50
Cooly. 0.25 Nos: 250.00 P.day. 62.50

_______________________________ ________ _____ ______ ______ ________


Rs: 175.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 17.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 192.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 19.25
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 211.75
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 330.55
_______________________________ ________ _____ ______ ______ ________
Total material & labour for each No: say say Rs: 330.55

Chapter No. 10 883/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ D E S C R I P T I O N.
S/N

20. Painting and lettering sign posts two coats of both sides.
(c)

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Assume for 1 No:

Brushes etc. L.S 120.00

Paint black and white. 0.60 Lbs. 1600.00 P.Gallon 96.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 216.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 21.60
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 237.60
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.33 Nos: 450.00 P.day. 150.00
Cooly. 0.33 Nos: 250.00 P.day. 83.33

_______________________________ ________ _____ ______ ______ ________


Rs: 233.33
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 23.33
_______________________________ ________ _____ ______ ______ ________
TOTAL 256.67
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 25.67
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 282.33

Chapter No. 10 884/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


TOTAL (MATERIAL + LABOUR) 519.93
_______________________________ ________ _____ ______ ______ ________
Total material & labour for each No: say say Rs: 519.93

_______________________________ ________ _____ ______ ______ ________


____ D E S C R I P T I O N.
S/N Removing paint or varnish from wall.
21. _______________________________ ________ _____ ______ ______ ________
____ LABOUR QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Cooly. 1.00 Nos: 250.00 P.day. 250.00
_______________________________ ________ _____ ______ ______ ________
TOTAL Rs: 250.00
Sundries. 10.00 % 25.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 275.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 27.50
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 302.50
_______________________________ ________ _____ ______ ______ ________
Labour rate for 100 Sft. say say Rs: 302.50
_______________________________ ________ _____ ______ ______ ________
____ D E S C R I P T I O N.
S/N Scraping from hydraulic gates:-
22. Khanki paint.
(a) _______________________________ ________ _____ ______ ______ ________
____ LABOUR QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Cooly. 2.00 Nos: 250.00 P.day. 500.00
_______________________________ ________ _____ ______ ______ ________
TOTAL Rs: 500.00
Sundries. 10.00 % 50.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 550.00
_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 885/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 55.00


_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 605.00
_______________________________ ________ _____ ______ ______ ________
Labour rate for 100 Sft. say say Rs: 605.00

_______________________________ ________ _____ ______ ______ ________


____ D E S C R I P T I O N.
S/N Scraping from hydraulic gates:-
22. Aluminium paint.
(b) _______________________________ ________ _____ ______ ______ ________
____ LABOUR QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Cooly. 2.00 Nos: 250.00 P.day. 500.00
_______________________________ ________ _____ ______ ______ ________
TOTAL Rs: 500.00
Sundries. 10.00 % 50.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 550.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 55.00
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 605.00
_______________________________ ________ _____ ______ ______ ________
Labour rate for 100 Sft. say say Rs: 605.00

Chapter No. 10 886/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


____
_______________________________ ________ _____ ______ ______ ________
____ D E S C R I P T I O N.
S/N
Painting letters with shade.
23.

(Unit of rate per letter per inch hieght)

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Assume for 100 Letters.

Brushes etc. L.S 12.00

Chapter No. 10 887/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Paint black and white. 0.50 Lbs. 1600.00 P.Gallon 80.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 92.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 9.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 101.20
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 1.60 Nos: 450.00 P.day. 720.00
Cooly. 1.60 Nos: 250.00 P.day. 400.00

_______________________________ ________ _____ ______ ______ ________


Rs: 1120.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 112.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 1232.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 123.20
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 13.55 1355.20
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 1456.40
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 letters 1" hieght. Rs: 1456.40
Total material & labour for 1 letter 1" hieght. Rs: 14.56
Total material & labour for one letter 1" hieght say Rs: 14.56

____ D E S C R I P T I O N.
S/N Scraping rust from old rail or girders. (Unit of rate per % Sft.)
24. _______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
Scraping material. L.S 10.00
_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 888/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Cooly. 1.50 Nos: 250.00 P.day. 375.00
Sundries. 10.00 % 37.50
TOTAL 412.50
Contractor's profit 10.00 % 41.25
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 453.75
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 463.75
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. say say Rs: 463.75

Chapter No. 10 889/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


Chieselling old paint from brick work. (Unit of rate per % Sft.)
25. _______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
E.T.C L.S 30.00
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Cooly. 2.00 Nos: 250.00 P.day. 500.00
Sundries. 10.00 % 50.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 550.00
Contractor's profit 10.00 % 55.00
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 605.00
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 635.00
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. say say Rs: 635.00
_______________________________ ________ _____ ______ ______ ________
____ Cleaning glasses with chalk and spirt,etc.
26. _______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
E.T.C L.S 13.33
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Cooly. 1.667 Nos: 250.00 P.day. 416.67
Sundries. 10.00 % 41.67
_______________________________ ________ _____ ______ ______ ________
TOTAL 458.33
Contractor's profit 10.00 % 45.83
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 504.17
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 517.50
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. say say Rs: 517.50
_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 890/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____
_______________________________ ________ _____ ______ ______ ________
____

____ D E S C R I P T I O N.
S/N
Cleaning and oiling rafter or rolled steel beams.
27.

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Oil linseed. 0.50 Lbs. 1300.00 Gallon. 65.00

Brushes, etc. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 77.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 7.70
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 84.70
_______________________________ ________ _____ ______ ______ ________
LABOUR

Chapter No. 10 891/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(B) _______________________________ ________ _____ ______ ______ ________


Cooly. 0.50 Nos: 250.00 P.day. 125.00

_______________________________ ________ _____ ______ ______ ________


Rs: 125.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 12.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 137.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 13.75
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 151.25
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 235.95
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 235.95
_______________________________ ________ _____ ______ ______ ________
____
_______________________________ ________ _____ ______ ______ ________
____ D E S C R I P T I O N.
S/N

Cleaning and painting punkha poles including fixing hooks.


28.

_______________________________ ________ _____ ______ ______ ________


____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________
Assume for 3 Nos:
Paint. 0.25 Lbs. 1600.00 P.Gallon 40.00

Brushes, etc. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 52.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 5.20

Chapter No. 10 892/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


TOTAL PART " A " 57.20
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00

_______________________________ ________ _____ ______ ______ ________


Rs: 250.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 25.00
_______________________________ ________ _____ ______ ______ ________
TOTAL 275.00
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 27.50
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 100.83 302.50
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 359.70
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 3 Nos: Rs: 359.70
Total material & labour for each No: Rs: 119.90
Total material & labour for each No: say Rs: 119.90
_______________________________ ________ _____ ______ ______ ________
____ D E S C R I P T I O N.
S/N

Preparing surface and painting with emulsion paint.


29.
First coat.
(a) (Unit of rate per 100 Sft.)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________

Linseed Oil. 0.34 Galn: 1300.00 P.Gallon 44.20

Chapter No. 10 893/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Brushes, sand paper, etc. L.S. 60.00

Emulsion Paint. 1.57 Lbs. 1850.00 P.Gallon 290.45

_______________________________ ________ _____ ______ ______ ________


TOTAL 394.65
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 39.47
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 434.12
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.50 Nos: 450.00 P.day. 225.00

Cooly. 0.25 Nos: 250.00 P.day. 62.50

_______________________________ ________ _____ ______ ______ ________


Rs: 287.50
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 28.75
_______________________________ ________ _____ ______ ______ ________
TOTAL 316.25
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 31.63
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 347.88
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 781.99
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 781.99

_______________________________ ________ _____ ______ ______ ________


____ D E S C R I P T I O N.
S/N

Chapter No. 10 894/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Preparing surface and painting with emulsion paint.


29.
Second coat and each subsequent coat.
(b) (Unit of rate per 100 Sft.)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________

Emulsion Paint. 1.18 Lbs. 1850.00 P.Gallon 218.30

Brushes, sand paper, etc. L.S. 30.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 248.30
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 24.83
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 273.13
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.25 Nos: 450.00 P.day. 112.50

Cooly. 0.05 Nos: 250.00 P.day. 12.50

_______________________________ ________ _____ ______ ______ ________


Rs: 125.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 12.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 137.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 13.75
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 151.25
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 424.38

Chapter No. 10 895/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_______________________________ ________ _____ ______ ______ ________


Total material & labour for 100 Sft. Rs: 424.38

____ D E S C R I P T I O N.
S/N

Painting with enamel paint on Masonry walls.


30
First coat
(a) (Unit of rate per 100 Sft.)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________

Emulsion Paint. 0.25 Lbs. 1850.00 P.Gallon 46.25

Brushes etc L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 58.25
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 5.83
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 64.08
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.25 Nos: 450.00 P.day. 112.50

Cooly. 0.05 Nos: 250.00 P.day. 12.50

_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 896/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Rs: 125.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 12.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 137.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 13.75
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 151.25
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 215.33
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 215.33
____ D E S C R I P T I O N.
S/N

Painting with enamel paint Masonry walls.


30
Second coat and each subsequent coat.
(b) (Unit of rate per 100 Sft.)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________

Emulsion Paint. 1.18 Lbs. 1850.00 P.Gallon 218.30

Brushes etc L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 230.30
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 23.03
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 253.33
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.25 Nos: 450.00 P.day. 112.50

Chapter No. 10 897/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Cooly. 0.05 Nos: 250.00 P.day. 12.50

_______________________________ ________ _____ ______ ______ ________


Rs: 125.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 12.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 137.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 13.75
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 151.25
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 404.58
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 404.58

____ D E S C R I P T I O N.
S/N

Preparing the surface and painting with enamel paint on masonry walls.
31
First coat and each subsequent coat.
(a) (Unit of rate per 100 Sft.)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________

Emulsion Paint. 1.18 Lbs. 1850.00 P.Gallon 218.30

Brushes etc L.S. 12.00

_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 898/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 230.30
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 23.03
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 253.33
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.25 Nos: 450.00 P.day. 112.50

Cooly. 0.05 Nos: 250.00 P.day. 12.50

_______________________________ ________ _____ ______ ______ ________


Rs: 125.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 12.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 137.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 13.75
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 151.25
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 404.58
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 404.58

____ D E S C R I P T I O N.
S/N

Preparing the surface and painting with ceamel paint on masonry walls.
31
Second coat and each subsequent coat.
(b) (Unit of rate per 100 Sft.)
_______________________________ ________ _____ ______ ______ ________
____ MATERIAL QUANTITY RATE UNIT AMOUNT
(A) Rs: Rs:
_______________________________ ________ _____ ______ ______ ________

Chapter No. 10 899/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Emulsion Paint. 1.18 Lbs. 1850.00 P.Gallon 218.30

Brushes etc. L.S. 12.00

_______________________________ ________ _____ ______ ______ ________


TOTAL 230.30
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 23.03
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " A " 253.33
_______________________________ ________ _____ ______ ______ ________
LABOUR
(B) _______________________________ ________ _____ ______ ______ ________
Painter 0.25 Nos: 450.00 P.day. 112.50

Cooly. 0.05 Nos: 250.00 P.day. 12.50

_______________________________ ________ _____ ______ ______ ________


Rs: 125.00
_______________________________ ________ _____ ______ ______ ________
Sundries. 10.00 % 12.50
_______________________________ ________ _____ ______ ______ ________
TOTAL 137.50
_______________________________ ________ _____ ______ ______ ________
Contractor's profit 10.00 % 13.75
_______________________________ ________ _____ ______ ______ ________
TOTAL PART " B " 151.25
_______________________________ ________ _____ ______ ______ ________
TOTAL (MATERIAL + LABOUR) 404.58
_______________________________ ________ _____ ______ ______ ________
Total material & labour for 100 Sft. Rs: 404.58
_______________________________ ________ _____ ______ ______ ________
____

Chapter No. 10 900/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

LINING OF CANALS

FIRST FILL THIS SHEET


MATERIAL

CEMENT 400 P.CWT

SAND 2425 %CFT

BRICK TILE 12"*6"*2" 5650 %0 NOS

BRICK 9"*4.5"*3" 5000 %0 NOS

STONE AGGREGATE 2000 %CFT

LABOUR

DRESSER , BAHISHTI 250 P. DAY

COOLIES 250 P. DAY

MASSON 450 P. DAY

Chapter No. 11 901/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
1. Formation, dressing and preparing sub-grade.
(a) In Bed.

(B) LABOUR QUANTITY


RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Dresser. 0.33 Nos: 250.00 P.day. 82.50

Coolies. 0.75 Nos: 250.00 P.day. 187.50

Rs: 270.00
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 27.00
_________________________________ ______ _____ _______ ______ ________
TOTAL 297.00
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 29.70
_________________________________ ______ _____ _______ ______ ________
TOTAL (LABOUR) 326.70
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Cft. Rs: 326.70
S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.

1. Formation, dressing and preparing sub-grade.


(b) On slope.

____ _________________________________ ______ _____ _______ ______ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Dresser. 0.50 Nos: 250.00 P.day. 125.00

Coolies. 1.00 Nos: 250.00 P.day. 250.00


Rs: 375.00
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 37.50
_________________________________ ______ _____ _______ ______ ________
TOTAL 412.50
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 41.25
_________________________________ ______ _____ _______ ______ ________

Chapter No. 11 902/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (LABOUR) 453.75


Total material & labour for 100 Cft. Rs: 453.75

Chapter No. 11 903/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
2. Stablizing layer of cement sand ratio (1:30) 2" thick on slope.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Cement. 0.50 Cwt. 400.00 P.Cwt. 200.00

Sand. 18.00 Cft. 2425.00 % Cft. 436.50

_________________________________ ______ _____ _______ ______ ________


TOTAL 636.50
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 63.65
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 700.15
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________
Mason. 0.50 Nos: 450.00 P.day. 225.00

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

_________________________________ ______ _____ _______ ______ ________


Rs: 725.00
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 72.50
_________________________________ ______ _____ _______ ______ ________
TOTAL 797.50
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 79.75
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " 877.25
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) 1577.40

Chapter No. 11 904/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_________________________________ ______ _____ _______ ______ ________


Total material & labour for 100 Sft. Rs: 1577.40
S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
3. Cement plaster 1/2" thick ratio 1:10.

(a) In bed.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Cement. 0.34 Cwt. 400.00 P.Cwt. 136.00

Sand. 4.20 Cft. 2425.00 % Cft. 101.85

_________________________________ ______ _____ _______ ______ ________


TOTAL 237.85
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 23.79
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 261.64
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________
Mason. 0.33 Nos: 450.00 P.day. 148.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

Rs: 523.50
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 52.35
_________________________________ ______ _____ _______ ______ ________
TOTAL 575.85
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 57.59
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " 633.44
_________________________________ ______ _____ _______ ______ ________

Chapter No. 11 905/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (MATERIAL + LABOUR) 895.07


_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Sft. Rs: 895.07
____ _________________________________ ______ _____ _______ ______ ________
S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
3. Cement plaster 1/2" thick ratio 1:10.

(b) On slope.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Cement. 0.34 Cwt. 400.00 P.Cwt. 136.00

Sand. 4.20 Cft. 2425.00 % Cft. 101.85

_________________________________ ______ _____ _______ ______ ________


TOTAL 237.85
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 23.79
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 261.64
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________
Mason. 0.50 Nos: 450.00 P.day. 225.00

Coolies. 1.25 Nos: 250.00 P.day. 312.50

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

_________________________________ ______ _____ _______ ______ ________


Rs: 662.50
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 66.25
_________________________________ ______ _____ _______ ______ ________
TOTAL 728.75
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 72.88

Chapter No. 11 906/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_________________________________ ______ _____ _______ ______ ________


TOTAL PART " B " 801.63
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) 1063.26
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Sft. Rs: 1063.26
S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
4. Cement plaster 3/8" thick ratio 1:3.

(a) In bed.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Cement. 0.70 Cwt. 400.00 P.Cwt. 280.00

Sand. 2.50 Cft. 2425.00 % Cft. 60.63

_________________________________ ______ _____ _______ ______ ________


TOTAL 340.63
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 34.06
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 374.69
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________
Mason. 0.33 Nos: 450.00 P.day. 148.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

Rs: 523.50
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 52.35
_________________________________ ______ _____ _______ ______ ________
TOTAL 575.85
_________________________________ ______ _____ _______ ______ ________

Chapter No. 11 907/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 57.59


_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " 633.44
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) 1008.12
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Sft. Rs: 1008.12
____ _________________________________ ______ _____ _______ ______ ________
S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
4. Cement plaster 3/8" thick ratio 1:3.

(b) On slope.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Cement. 0.70 Cwt. 400.00 P.Cwt. 280.00

Sand. 2.50 Cft. 2425.00 % Cft. 60.63

_________________________________ ______ _____ _______ ______ ________


TOTAL 340.63
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 34.06
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 374.69
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________
Mason. 0.50 Nos: 450.00 P.day. 225.00

Coolies. 1.25 Nos: 250.00 P.day. 312.50

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

_________________________________ ______ _____ _______ ______ ________


Rs: 662.50
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 66.25
_________________________________ ______ _____ _______ ______ ________

Chapter No. 11 908/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 728.75
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 72.88
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " 801.63
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) 1176.31
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Sft. Rs: 1176.31

S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
5. Cement plaster 1-1/2" thick ratio 1:6.

(a) In bed.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Cement. 1.56 Cwt. 400.00 P.Cwt. 624.00

Sand. 11.70 Cft. 2425.00 % Cft. 283.73

_________________________________ ______ _____ _______ ______ ________


TOTAL 907.73
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 90.77
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 998.50
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________
Mason. 0.50 Nos: 450.00 P.day. 225.00

Coolies. 1.25 Nos: 250.00 P.day. 312.50

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

Rs: 662.50
_________________________________ ______ _____ _______ ______ ________

Chapter No. 11 909/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Sundries. 10.00 % 66.25


_________________________________ ______ _____ _______ ______ ________
TOTAL 728.75
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 72.88
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " 801.63
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) 1800.12
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Sft. Rs: 1800.12

S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
5. Cement plaster 1-1/2" thick ratio 1:6.

(b) On slope.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Cement. 1.56 Cwt. 400.00 P.Cwt. 624.00

Sand. 11.70 Cft. 2425.00 % Cft. 283.73

_________________________________ ______ _____ _______ ______ ________


TOTAL 907.73
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 90.77
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 998.50
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

Rs: 837.50

Chapter No. 11 910/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_________________________________ ______ _____ _______ ______ ________


Sundries. 10.00 % 83.75
_________________________________ ______ _____ _______ ______ ________
TOTAL 921.25
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 92.13
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " 1013.38
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) 2011.87
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Sft. Rs: 2011.87

____ _________________________________ ______ _____ _______ ______ ________

____ _________________________________ ______ _____ _______ ______ ________


S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
6. Tile lining (12" * 6" * 2") in 1:6 cement sand morter.

(a) In bed.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Brick Tiles 12"*6"*2" 1200 Nos. 5650.0 P.%0 6780.00

Cement. 3.44 Cwt. 400.00 P.Cwt. 1376.00

Sand. 25.70 Cft. 2425.00 % Cft. 623.23

_________________________________ ______ _____ _______ ______ ________


TOTAL 8779.23
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 877.92
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 9657.15
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________
Mason. 2.50 Nos: 450.00 P.day. 1125.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Chapter No. 11 911/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Bahishti. 0.75 Nos: 250.00 P.day. 187.50

Rs: 2562.50
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 256.25
_________________________________ ______ _____ _______ ______ ________
TOTAL 2818.75
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 281.88
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " 3100.63
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) 12757.77
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Cft. Rs: 12757.77
S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
6. Tile lining (12" * 6" * 2") in 1:6 cement sand morter.

(b) On slope.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Brick Tiles 12"*6"*2" 1200 Nos. 5650.0 P.%0 6780.00

Cement. 3.44 Cwt. 400.00 P.Cwt. 1376.00

Sand. 25.70 Cft. 2425.00 % Cft. 623.23

_________________________________ ______ _____ _______ ______ ________


TOTAL 8779.23
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 877.92
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 9657.15
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________
Mason. 2.75 Nos: 450.00 P.day. 1237.50

Coolies. 6.00 Nos: 250.00 P.day. 1500.00

Chapter No. 11 912/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Bahishti. 0.75 Nos: 250.00 P.day. 187.50

Rs: 2925.00
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 292.50
_________________________________ ______ _____ _______ ______ ________
TOTAL 3217.50
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 321.75
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " 3539.25
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) 13196.40
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Cft. Rs: 13196.40
____ _________________________________ ______ _____ _______ ______ ________

____ _________________________________ ______ _____ _______ ______ ________


S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
7. Tile lining (12" * 6" * 2") in 1:3 cement sand morter.

(a) In bed.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Brick Tiles 12"*6"*2" 1200 Nos. 5650.0 P.%0 6780.00

Cement. 6.00 Cwt. 400.00 P.Cwt. 2400.00

Sand. 22.50 Cft. 2425.00 % Cft. 545.63

_________________________________ ______ _____ _______ ______ ________


TOTAL 9725.63
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 972.56
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 10698.19
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________

Chapter No. 11 913/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Mason. 2.50 Nos: 450.00 P.day. 1125.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50

Rs: 2562.50
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 256.25
_________________________________ ______ _____ _______ ______ ________
TOTAL 2818.75
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 281.88
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " 3100.63
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) 13798.81
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Cft. Rs: 13798.81
S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
7. Tile lining (12" * 6" * 2") in 1:3 cement sand morter.

(b) On slope.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Brick Tiles 12"*6"*2" 1200 Nos. 5650.0 P.%0 6780.00

Cement. 6.00 Cwt. 400.00 P.Cwt. 2400.00

Sand. 22.50 Cft. 2425.00 % Cft. 545.63

_________________________________ ______ _____ _______ ______ ________


TOTAL 9725.63
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 972.56
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 10698.19
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR

Chapter No. 11 914/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_________________________________ ______ _____ _______ ______ ________


Mason. 2.75 Nos: 450.00 P.day. 1237.50

Coolies. 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50

Rs: 2925.00
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 292.50
_________________________________ ______ _____ _______ ______ ________
TOTAL 3217.50
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 321.75
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " 3539.25
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) 14237.44
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Cft. Rs: 14237.44
____ _________________________________ ______ _____ _______ ______ ________

____ _________________________________ ______ _____ _______ ______ ________


S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
8. Brick lining (9" * 4-1/2" * 3") in 1:6 cement sand morter.

(a) In bed.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Brick 9"*4-1/2"*3" 1350 Nos. 5000.0 P.%0 6750.00

Cement. 3.44 Cwt. 400.00 P.Cwt. 1376.00

Sand. 25.70 Cft. 2425.00 % Cft. 623.23

_________________________________ ______ _____ _______ ______ ________


TOTAL 8749.23
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 874.92

Chapter No. 11 915/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_________________________________ ______ _____ _______ ______ ________


TOTAL PART " A " 9624.15
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________
Mason. 2.50 Nos: 450.00 P.day. 1125.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50

_________________________________ ______ _____ _______ ______ ________


_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % #REF!
_________________________________ ______ _____ _______ ______ ________
TOTAL #REF!
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % #REF!
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " #REF!
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) #REF!
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Cft. Rs: #REF!
S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
8. Brick lining (9" * 4-1/2" * 3") in 1:6 cement sand morter.

(b) On slope.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Brick 9"*4-1/2"*3" 1350 Nos. 5000.0 P.%0 6750.00

Cement. 3.44 Cwt. 400.00 P.Cwt. 1376.00

Sand. 25.70 Cft. 2425.00 % Cft. 623.23

_________________________________ ______ _____ _______ ______ ________


TOTAL 8749.23
_________________________________ ______ _____ _______ ______ ________

Chapter No. 11 916/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 874.92


_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 9624.15
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________
Mason. 2.75 Nos: 450.00 P.day. 1237.50

Coolies. 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50

_________________________________ ______ _____ _______ ______ ________


Rs: 2925.00
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 292.50
_________________________________ ______ _____ _______ ______ ________
TOTAL 3217.50
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 321.75
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " 3539.25
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) 13163.40
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Cft. Rs: 13163.40
____ _________________________________ ______ _____ _______ ______ ________
S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
9. Brick lining (9" * 4-1/2" * 3") in 1:3 cement sand morter.

(a) In bed.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Brick 9"*4-1/2"*3" 1350 Nos. 5000.0 P.%0 6750.00

Cement. 6.00 Cwt. 400.00 P.Cwt. 2400.00

Sand. 22.50 Cft. 2425.00 % Cft. 545.63

_________________________________ ______ _____ _______ ______ ________

Chapter No. 11 917/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 9695.63
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 969.56
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 10665.19
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________
Mason. 2.50 Nos: 450.00 P.day. 1125.00

Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50

_________________________________ ______ _____ _______ ______ ________


Rs: 2562.50
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 256.25
_________________________________ ______ _____ _______ ______ ________
TOTAL 2818.75
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 281.88
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " 3100.63
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) 13765.81
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Cft. Rs: 13765.81
S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
9. Brick lining (9" * 4-1/2" * 3") in 1:6 cement sand morter.

(b) On slope.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Brick 9"*4-1/2"*3" 1350 Nos. 5000.0 P.%0 6750.00

Cement. 6.00 Cwt. 400.00 P.Cwt. 2400.00

Sand. 22.50 Cft. 2425.00 % Cft. 545.63

Chapter No. 11 918/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_________________________________ ______ _____ _______ ______ ________


TOTAL 9695.63
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 969.56
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 10665.19
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________
Mason. 2.75 Nos: 450.00 P.day. 1237.50

Coolies. 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 0.75 Nos: 250.00 P.day. 187.50

_________________________________ ______ _____ _______ ______ ________


Rs: 2925.00
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 292.50
_________________________________ ______ _____ _______ ______ ________
TOTAL 3217.50
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 321.75
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " 3539.25
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) 14204.44
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Cft. Rs: 14204.44
S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
10. Cement concrete lining 4" thick ratio 1:3:6.

(a) In bed.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Stone aggregates. 92.00 Cft. 2000.00 % Cft. 1840.00

Cement. 13.00 Cwt. 400.00 P.Cwt. 5200.00

Sand. 46.00 Cft. 2425.00 % Cft. 1115.50

Chapter No. 11 919/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_________________________________ ______ _____ _______ ______ ________


TOTAL 8155.50
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 815.55
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 8971.05
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 6.00 Nos: 250.00 P.day. 1500.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

_________________________________ ______ _____ _______ ______ ________


Rs: 2075.00
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 207.50
_________________________________ ______ _____ _______ ______ ________
TOTAL 2282.50
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 228.25
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " 2510.75
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) 11481.80
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Cft. Rs: 11481.80
____ _________________________________ ______ _____ _______ ______ ________

____ _________________________________ ______ _____ _______ ______ ________


S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
10. Cement concrete lining 4" thick ratio 1:3:6.

(b) On slope.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Stone aggregates. 92.00 Cft. 2000.00 % Cft. 1840.00

Chapter No. 11 920/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Cement. 13.00 Cwt. 400.00 P.Cwt. 5200.00

Sand. 46.00 Cft. 2425.00 % Cft. 1115.50

_________________________________ ______ _____ _______ ______ ________


TOTAL 8155.50
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 815.55
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 8971.05
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 7.00 Nos: 250.00 P.day. 1750.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

_________________________________ ______ _____ _______ ______ ________


Rs: 2437.50
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 243.75
_________________________________ ______ _____ _______ ______ ________
TOTAL 2681.25
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 268.13
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " 2949.38
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) 11920.43
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Cft. Rs: 11920.43
S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
11 Cement concrete lining 4" thick ratio 1:2:4.

(a) In bed.

____ _________________________________ ______ _____ _______ ______ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Stone aggregates. 88.00 Cft. 2000.00 % Cft. 1760.00

Chapter No. 11 921/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Cement. 17.50 Cwt. 400.00 P.Cwt. 7000.00

Sand. 44.00 Cft. 2425.00 % Cft. 1067.00

_________________________________ ______ _____ _______ ______ ________


TOTAL 9827.00
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 982.70
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 10809.70
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________
Mason. 1.25 Nos: 450.00 P.day. 562.50

Coolies. 7.00 Nos: 250.00 P.day. 1750.00

Bahishti. 0.60 Nos: 250.00 P.day. 150.00

_________________________________ ______ _____ _______ ______ ________


Rs: 2462.50
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 246.25
_________________________________ ______ _____ _______ ______ ________
TOTAL 2708.75
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 270.87
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " 2979.62
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) 13789.32
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Cft. Rs: 13789.32
____ _________________________________ ______ _____ _______ ______ ________

____ _________________________________ ______ _____ _______ ______ ________


S/N L I N I N G O F C A N A L S -12
===================================
D E S C R I P T I O N.
11 Cement concrete lining 4" thick ratio 1:2:4.

(b) On slope.

____ _________________________________ ______ _____ _______ ______ ________

Chapter No. 11 922/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_________________________________ ______ _____ _______ ______ ________
Stone aggregates. 88.00 Cft. 2000.00 % Cft. 1760.00

Cement. 17.50 Cwt. 400.00 P.Cwt. 7000.00

Sand. 44.00 Cft. 2425.00 % Cft. 1067.00

_________________________________ ______ _____ _______ ______ ________


TOTAL 9827.00
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 982.70
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " A " 10809.70
_________________________________ ______ _____ _______ ______ ________
(B) LABOUR
_________________________________ ______ _____ _______ ______ ________
Mason. 1.50 Nos: 450.00 P.day. 675.00

Coolies. 8.00 Nos: 250.00 P.day. 2000.00

Bahishti. 0.60 Nos: 250.00 P.day. 150.00

_________________________________ ______ _____ _______ ______ ________


Rs: 2825.00
_________________________________ ______ _____ _______ ______ ________
Sundries. 10.00 % 282.50
_________________________________ ______ _____ _______ ______ ________
TOTAL 3107.50
_________________________________ ______ _____ _______ ______ ________
Contractor's profit 10.00 % 310.75
_________________________________ ______ _____ _______ ______ ________
TOTAL PART " B " 3418.25
_________________________________ ______ _____ _______ ______ ________
TOTAL (MATERIAL + LABOUR) 14227.95
_________________________________ ______ _____ _______ ______ ________
Total material & labour for 100 Cft. Rs: 14227.95

12a. Installation of P.V.C GEO-Membrane.

(A) 0.25 mm THICK MEMBRANE


Cost of 0.25 Mm thick GEO -Membrane Per Sft 360
I/c sales tax
Cost of installation Per Sft 1.75

Chapter No. 11 923/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Transportation charges Per Sft 0.05


Total 5.40
Add 10% contractor's profit 0.54
Total 5.94

b Installation of P.V.C GEO-Membrane.

(b) 0.50 mm THICK MEMBRANE


Cost of 0.50 mm thick GEO -Membrane Per Sft 7.2
I/c sales tax
Cost of installation Per Sft 1.75
Transportation charges Per Sft 0.05
Total 9.0
Add 10% contractor's profit 0.9
Total 9.90

c Installation of P.V.C GEO-Membrane.

(c) 0.75 mm THICK MEMBRANE


Cost of 0.75 mm thick GEO -Membrane Per Sft 10.8
I/c sales tax
Cost of installation Per Sft 1.75
Transportation charges Per Sft 0.1
Total 12.65
Add 10% contractor's profit 1.26
Total 13.91

Chapter No. 11 924/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

SHEET PILLING
FIRST FILL THIS SHEET

LABOUR
BLACK SMITH , FOREMAN 450 P.DAY

SKILLED COLLY 250 P.DAY

COOLIES 250 P.DAY

FITTER , MECHNICAL LAB TECH 400 P.DAY

Chapter No. 12 925/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N S H E E T P I L I N G-13
==========================
NOTE Unless otherwise stated the rate includes handling of material
within 3 chains.
D E S C R I P T I O N.

1. Cutting Ransom and Laison piles.

______ ______________________________ ______ _____ ______ ______ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ______ ________
Blacksmith. 0.25 Nos: 450.00 P.day. 112.50

______________________________ ______ _____ ______ ______ ________


Rs: 112.50
______________________________ ______ _____ ______ ______ ________
Sundries. 10.00 % 11.25
______________________________ ______ _____ ______ ______ ________
TOTAL 123.75
______________________________ ______ _____ ______ ______ ________
Contractor's profit 10.00 % 12.38
______________________________ ______ _____ ______ ______ ________
TOTAL (LABOUR) 136.13
______________________________ ______ _____ ______ ______ ________
Total labour rate per Cut. Rs: 136.13

______ ______________________________ ______ _____ ______ ______ ________


______ ______________________________ ______ _____ ______ ______ ________
S/N S H E E T P I L I N G-13
==========================
D E S C R I P T I O N.

2. Cutting Universal piles.

______ ______________________________ ______ _____ ______ ______ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ______ ________
Blacksmith. 0.37 Nos: 450.00 P.day. 166.50

______________________________ ______ _____ ______ ______ ________


Rs: 166.50
______________________________ ______ _____ ______ ______ ________
Sundries. 10.00 % 16.65
______________________________ ______ _____ ______ ______ ________
TOTAL 183.15
______________________________ ______ _____ ______ ______ ________
Contractor's profit 10.00 % 18.32
______________________________ ______ _____ ______ ______ ________
TOTAL (LABOUR) 201.47

Chapter No. 12 926/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
______________________________ ______ _____ ______ ______ ________
Total labour rate per Cut. Rs: 201.47

S/N S H E E T P I L I N G-13
==========================
D E S C R I P T I O N.

3. Driving steel piles 25' to 30'.

______ ______________________________ ______ _____ ______ ______ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ______ ________
Skilled Coolies. 4.25 Nos: 250.00 P.day. 1062.50

Coolies. 2.00 Nos: 250.00 P.day. 500.00

______________________________ ______ _____ ______ ______ ________


Rs: 1562.50
______________________________ ______ _____ ______ ______ ________
Sundries. 10.00 % 156.25
______________________________ ______ _____ ______ ______ ________
TOTAL 1718.75
______________________________ ______ _____ ______ ______ ________
Contractor's profit 10.00 % 171.88
______________________________ ______ _____ ______ ______ ________
TOTAL (LABOUR) 1890.63
______________________________ ______ _____ ______ ______ ________
Total labour rate per 100 Sft. Rs: 1890.63

______ ______________________________ ______ _____ ______ ______ ________


S/N S H E E T P I L I N G-13
==========================
D E S C R I P T I O N.

4. Driving steel piles more than 15' and less than 25'.

______ ______________________________ ______ _____ ______ ______ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ______ ________
Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Coolies. 2.00 Nos: 250.00 P.day. 500.00

______________________________ ______ _____ ______ ______ ________


Rs: 1500.00
______________________________ ______ _____ ______ ______ ________
Sundries. 10.00 % 150.00
______________________________ ______ _____ ______ ______ ________
TOTAL 1650.00
______________________________ ______ _____ ______ ______ ________
Contractor's profit 10.00 % 165.00

Chapter No. 12 927/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
______________________________ ______ _____ ______ ______ ________
TOTAL (LABOUR) 1815.00
______________________________ ______ _____ ______ ______ ________
Total labour rate per 100 Sft. Rs: 1815.00
S/N S H E E T P I L I N G-13
==========================
D E S C R I P T I O N.

5. Driving steel piles more than 14' and under.

______ ______________________________ ______ _____ ______ ______ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ______ ________
Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Coolies. 2.00 Nos: 250.00 P.day. 500.00

______________________________ ______ _____ ______ ______ ________


Rs: 1125.00
______________________________ ______ _____ ______ ______ ________
Sundries. 10.00 % 112.50
______________________________ ______ _____ ______ ______ ________
TOTAL 1237.50
______________________________ ______ _____ ______ ______ ________
Contractor's profit 10.00 % 123.75
______________________________ ______ _____ ______ ______ ________
TOTAL (LABOUR) 1361.25
______________________________ ______ _____ ______ ______ ________
Total labour rate per 100 Sft. Rs: 1361.25

______ ______________________________ ______ _____ ______ ______ ________


______ ______________________________ ______ _____ ______ ______ ________

S/N S H E E T P I L I N G-13
==========================
D E S C R I P T I O N.

6. Dolleying piles.

(B) LABOUR QUANTITY


RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ______ ________
Skilled Coolies. 0.20 Nos: 250.00 P.day. 50.00

Coolies. 0.20 Nos: 250.00 P.day. 50.00

______________________________ ______ _____ ______ ______ ________


Rs: 100.00
______________________________ ______ _____ ______ ______ ________
Sundries. 10.00 % 10.00
______________________________ ______ _____ ______ ______ ________
TOTAL 110.00
______________________________ ______ _____ ______ ______ ________

Chapter No. 12 928/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
Contractor's profit 10.00 % 11.00
______________________________ ______ _____ ______ ______ ________
TOTAL (LABOUR) 121.00
______________________________ ______ _____ ______ ______ ________
Total labour rate per each No. Rs: 121.00

S/N S H E E T P I L I N G-13
==========================
D E S C R I P T I O N.

7. Drilling holes in piles.

Assume for 10 Holes.


______ ______________________________ ______ _____ ______ ______ ________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ______ ________
Blackksmith. 0.33 Nos: 450.00 P.day. 148.50

______________________________ ______ _____ ______ ______ ________


Rs: 148.50
______________________________ ______ _____ ______ ______ ________
Sundries. 10.00 % 14.85
______________________________ ______ _____ ______ ______ ________
TOTAL 163.35
______________________________ ______ _____ ______ ______ ________
Contractor's profit 10.00 % 16.34
______________________________ ______ _____ ______ ______ ________
TOTAL (LABOUR) 179.69
______________________________ ______ _____ ______ ______ ________
Total labour rate per each No. Rs: 17.97
Total labour rate per each No. say Rs: 17.97
______ ______________________________ ______ _____ ______ ______ ________
______ ______________________________ ______ _____ ______ ______ ________
S/N S H E E T P I L I N G-13
==========================
D E S C R I P T I O N.

8. Raising and lowering machine.

______ ______________________________ ______ _____ ______ ______ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ______ ________
Labour Mechanical. 1.00 Nos: 400.00 P.day. 400.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00


Coolies. 2.00 Nos: 250.00 P.day. 500.00
______________________________ ______ _____ ______ ______ ________
Rs: 1900.00
______________________________ ______ _____ ______ ______ ________
Sundries. 10.00 % 190.00
______________________________ ______ _____ ______ ______ ________
TOTAL 2090.00

Chapter No. 12 929/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
______________________________ ______ _____ ______ ______ ________
Contractor's profit 10.00 % 209.00
______________________________ ______ _____ ______ ______ ________
TOTAL (LABOUR) 2299.00
______________________________ ______ _____ ______ ______ ________
Total labour rate per foot. Rs: 2299.00

S/N S H E E T P I L I N G-13
==========================
D E S C R I P T I O N.

9. Turning machine 90 degrees.

______ ______________________________ ______ _____ ______ ______ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ______ ________
Fitter. 1.00 Nos: 400.00 P.day. 400.00

Skilled Coolies. 5.00 Nos: 250.00 P.day. 1250.00


Coolies. 3.00 Nos: 250.00 P.day. 750.00
______________________________ ______ _____ ______ ______ ________
Rs: 2400.00
______________________________ ______ _____ ______ ______ ________
Sundries. 10.00 % 240.00
______________________________ ______ _____ ______ ______ ________
TOTAL 2640.00
______________________________ ______ _____ ______ ______ ________
Contractor's profit 10.00 % 264.00
______________________________ ______ _____ ______ ______ ________
TOTAL (LABOUR) 2904.00
______________________________ ______ _____ ______ ______ ________
Total labour rate per foot. Rs: 2904.00

______ ______________________________ ______ _____ ______ ______ ________


______ ______________________________ ______ _____ ______ ______ ________
S/N S H E E T P I L I N G-13
==========================
D E S C R I P T I O N.

10. Turning machine 135 degrees.

______ ______________________________ ______ _____ ______ ______ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ______ ________
Fitter. 1.00 Nos: 400.00 P.day. 400.00

Skilled Coolies. 5.50 Nos: 250.00 P.day. 1375.00


Coolies. 5.00 Nos: 250.00 P.day. 1250.00
______________________________ ______ _____ ______ ______ ________
Rs: 3025.00
______________________________ ______ _____ ______ ______ ________
Sundries. 10.00 % 302.50

Chapter No. 12 930/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
______________________________ ______ _____ ______ ______ ________
TOTAL 3327.50
______________________________ ______ _____ ______ ______ ________
Contractor's profit 10.00 % 332.75
______________________________ ______ _____ ______ ______ ________
TOTAL (LABOUR) 3660.25
______________________________ ______ _____ ______ ______ ________
Total labour rate per foot. Rs: 3660.25

Chapter No. 12 931/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N S H E E T P I L I N G-13
==========================
D E S C R I P T I O N.

11. Turning machine 180 degrees.

______ ______________________________ ______ _____ ______ ______ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ______ ________
Fitter. 1.00 Nos: 400.00 P.day. 400.00

Skilled Coolies. 7.00 Nos: 250.00 P.day. 1750.00


Coolies. 7.00 Nos: 250.00 P.day. 1750.00
______________________________ ______ _____ ______ ______ ________
Rs: 3900.00
______________________________ ______ _____ ______ ______ ________
Sundries. 10.00 % 390.00
______________________________ ______ _____ ______ ______ ________
TOTAL 4290.00
______________________________ ______ _____ ______ ______ ________
Contractor's profit 10.00 % 429.00
______________________________ ______ _____ ______ ______ ________
TOTAL (LABOUR) 4719.00
______________________________ ______ _____ ______ ______ ________
Total labour rate per foot. Rs: 4719.00

______ ______________________________ ______ _____ ______ ______ ________


S/N S H E E T P I L I N G-13
==========================
D E S C R I P T I O N.

12. Travelling machine (Light)

______ ______________________________ ______ _____ ______ ______ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ______ ________
Fitter. 1.25 Nos: 400.00 P.day. 500.00

Skilled Coolies. 8.00 Nos: 250.00 P.day. 2000.00


Coolies. 8.50 Nos: 250.00 P.day. 2125.00
______________________________ ______ _____ ______ ______ ________
Rs: 4625.00
______________________________ ______ _____ ______ ______ ________
Sundries. 10.00 % 462.50
______________________________ ______ _____ ______ ______ ________
TOTAL 5087.50
______________________________ ______ _____ ______ ______ ________
Contractor's profit 10.00 % 508.75
______________________________ ______ _____ ______ ______ ________
TOTAL (LABOUR) 5596.25
______________________________ ______ _____ ______ ______ ________
Total labour rate per chain. Rs: 5596.25

Chapter No. 12 932/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N S H E E T P I L I N G-13
==========================
D E S C R I P T I O N.

13. Loading un-loading piles.

______ ______________________________ ______ _____ ______ ______ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ______ ________

Coolies. 0.37 Nos: 250.00 P.day. 92.50


______________________________ ______ _____ ______ ______ ________
Rs: 92.50
______________________________ ______ _____ ______ ______ ________
Sundries. 10.00 % 9.25
______________________________ ______ _____ ______ ______ ________
TOTAL 101.75
______________________________ ______ _____ ______ ______ ________
Contractor's profit 10.00 % 10.18
______________________________ ______ _____ ______ ______ ________
TOTAL (LABOUR) 111.93
______________________________ ______ _____ ______ ______ ________
Total labour rate per Ton. Rs: 111.93

______ ______________________________ ______ _____ ______ ______ ________


S/N S H E E T P I L I N G-13
==========================
D E S C R I P T I O N.

14. Dismentling pilling machine.

______ ______________________________ ______ _____ ______ ______ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ______ ________
Foreman. 3.00 Nos: 450.00 P.day. 1350.00
Fitter. 18.00 Nos: 400.00 P.day. 7200.00
Skilled Coolies. 12.00 Nos: 250.00 P.day. 3000.00
Coolies. 9.50 Nos: 250.00 P.day. 2375.00
______________________________ ______ _____ ______ ______ ________
Rs: 13925.00
______________________________ ______ _____ ______ ______ ________
Sundries. 10.00 % 1392.50
______________________________ ______ _____ ______ ______ ________
TOTAL 15317.50
______________________________ ______ _____ ______ ______ ________
Contractor's profit 10.00 % 1531.75

Chapter No. 12 933/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
______________________________ ______ _____ ______ ______ ________
TOTAL (LABOUR) 16849.25
______________________________ ______ _____ ______ ______ ________
Total labour rate per each No. Rs: 16849.25
S/N S H E E T P I L I N G-13
==========================
D E S C R I P T I O N.

15. Erecting piling machine.

______ ______________________________ ______ _____ ______ ______ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ______ ________
Foreman. 3.00 Nos: 450.00 P.day. 1350.00
Fitter. 18.00 Nos: 400.00 P.day. 7200.00
Skilled Coolies. 12.00 Nos: 250.00 P.day. 3000.00
Coolies. 9.50 Nos: 250.00 P.day. 2375.00
______________________________ ______ _____ ______ ______ ________
Rs: 13925.00
______________________________ ______ _____ ______ ______ ________
Sundries. 10.00 % 1392.50
______________________________ ______ _____ ______ ______ ________
TOTAL 15317.50
______________________________ ______ _____ ______ ______ ________
Contractor's profit 10.00 % 1531.75
______________________________ ______ _____ ______ ______ ________
TOTAL (LABOUR) 16849.25
______________________________ ______ _____ ______ ______ ________
Total labour rate per each No. Rs: 16849.25
SAY 16849.25
______ ______________________________ ______ _____ ______ ______ ________
S/N S H E E T P I L I N G-13
==========================
D E S C R I P T I O N.

16. Carriage of pile machine under different condition.

______ ______________________________ ______ _____ ______ ______ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ______ ________
Fitter. 1.00 Nos: 400.00 P.day. 400.00
Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Coolies. 3.75 Nos: 250.00 P.day. 937.50


______________________________ ______ _____ ______ ______ ________
Rs: 1962.50
______________________________ ______ _____ ______ ______ ________
Sundries. 10.00 % 196.25
______________________________ ______ _____ ______ ______ ________
TOTAL 2158.75
______________________________ ______ _____ ______ ______ ________
Contractor's profit 10.00 % 215.88

Chapter No. 12 934/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
______________________________ ______ _____ ______ ______ 2374.63
TOTAL (LABOUR)
______________________________ ______ _____ ______ ______ ________
Total labour rate per each No. Rs: 2374.63

______ ______________________________ ______ _____ ______ ________

Chapter No. 12 935/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

RIVER TRAINING & DIVERSION WORKS


FIRST FILL THIS SHEET

MATERIAL
EMPTY CEMENT JUTE BAG 125 EACH

SUTLI 135 P.KG

MUNJBAN 150 P.KG

G.I WIRE #15 4250 P.CWT

PILCHI 475 %CFT

PEGS 2" DIA 1.5 FT LONG 900 % NOS

STAKES 7 " - 12" THICK 3550 % NOS

STAKES 9 " - 12" THICK 4325 % NOS

LABOUR
SKILLED COLLY , BOATMAN 250 P.DAY

COLLIES 250 P.DAY

SMALL BOAT WITH BOAT MAN 450 P.DAY

BLACK SMITH 450 P.DAY

BOAT MAN WITH BOAT 500 P.DAY

Chapter No. 13 936/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N RIVER TRAINING AND DIVERSION WORKS
==================================
D E S C R I P T I O N.

1. Cutting pilchi farash or sarkanda including carriage within one


mile.

_____________________________ ______ ______ ______ ______ __________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Skilled Coolies. 1.90 Nos: 250.00 P.day. 475.00
_____________________________ ______ ______ ______ ______ __________
Rs: 475.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 47.50
_____________________________ ______ ______ ______ ______ __________
TOTAL 522.50
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 52.25
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 574.75
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 574.75
_____ _____________________________ ______ ______ ______ ______ __________
S/N RIVER TRAINING AND DIVERSION WORKS
==================================
D E S C R I P T I O N.

2. Weaving matresses.

_____________________________ ______ ______ ______ ______ __________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Coolies. 3.60 Nos: 250.00 P.day. 900.00

Rs: 900.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 90.00
_____________________________ ______ ______ ______ ______ __________
TOTAL 990.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 99.00
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 1089.00
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Sft. Rs: 1089.00

Chapter No. 13 937/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

3. (a) Supplying and filling new Jute bags 4 to 5 Cft capacity


with sand or earth sewing and stacking in dry.

Assume fo 50 Nos.
_____ _____________________________ ______ ______ ______ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Empty Cement Jute Bags. 50.00 Nos. 125.00 Each. 6250.00

Sutli. 1.50 Seer. 135.00 Seer. 202.50

_____________________________ ______ ______ ______ ______ __________


TOTAL 6452.50
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 645.25
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " A " 7097.75
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR
_____________________________ ______ ______ ______ ______ __________

Coolies. 7.00 Nos: 250.00 P.day. 1750.00

_____________________________ ______ ______ ______ ______ __________


Rs: 1750.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 175.00
_____________________________ ______ ______ ______ ______ __________
TOTAL 1925.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 192.50
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " B " 42.35 2117.50
_____________________________ ______ ______ ______ ______ __________
TOTAL (MATERIAL + LABOUR) 9215.25
_____________________________ ______ ______ ______ ______ __________
Total material & labour for 50 Nos. Rs: 9215.25
Total material & labour for 1 No. Rs: 184.31
Total material & labour for each No. say Rs: 184.31
_____ _____________________________ ______ ______ ______ ______ __________

Chapter No. 13 938/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

3. (b) Supplying and filling new Jute bags 4 to 5 Cft capacity


with sand or earth sewing and laying in position under water.

Assume for 50 Nos.


_____ _____________________________ ______ ______ ______ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Empty Cement Jute Bags. 50.00 Nos. 125.00 Each. 6250.00

Sutli. 1.50 Seer. 135.00 Seer. 202.50

_____________________________ ______ ______ ______ ______ __________


TOTAL 6452.50
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 645.25
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " A " 7097.75
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR
_____________________________ ______ ______ ______ ______ __________

Coolies. 10.00 Nos: 250.00 P.day. 2500.00

_____________________________ ______ ______ ______ ______ __________


Rs: 2500.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 250.00
_____________________________ ______ ______ ______ ______ __________
TOTAL 2750.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 275.00
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " B " 60.50 3025.00
_____________________________ ______ ______ ______ ______ __________
TOTAL (MATERIAL + LABOUR) 10122.75
_____________________________ ______ ______ ______ ______ __________
Total material & labour for 50 Nos. Rs: 10122.75
Total material & labour for 1 No. Rs: 202.46
Total material & labour for each No. say Rs: 202.46
S/N D E S C R I P T I O N.

4. Carriage of new Jute bags 4 to 5 Cft capacity filled with sand


or earth.

(a) First chain. (Unit of rate 100 Nos. per chain.)


_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Skilled Coolies. 2.00 Nos: 250.00 P.day. 500.00

Rs: 500.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 50.00
_____________________________ ______ ______ ______ ______ __________
TOTAL 550.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 55.00
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 605.00
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Nos. per chain. Rs: 605.00

_____ _____________________________ ______ ______ ______ ______ __________

Chapter No. 13 939/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
_____ _____________________________ ______ ______ ______ ______ __________
S/N D E S C R I P T I O N.

4. Carriage of new Jute bags 4 to 5 Cft capacity filled with sand


or earth.

(b) 2nd to 4th chain. (Unit of rate 100 Nos. per chain.)
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Skilled Coolies. 0.70 Nos: 250.00 P.day. 175.00
Rs: 175.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 17.50
_____________________________ ______ ______ ______ ______ __________
TOTAL 192.50
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 19.25
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 211.75
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Nos. per chain. Rs: 211.75

S/N D E S C R I P T I O N.

4. Carriage of new Jute bags 4 to 5 Cft capacity filled with sand


or earth.

(c) 5th and subsequent chains. (Unit of rate 100 Nos. per chain.)
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Skilled Coolies. 0.27 Nos: 250.00 P.day. 67.50

Rs: 67.50
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 6.75
_____________________________ ______ ______ ______ ______ __________
TOTAL 74.25
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 7.43
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 81.68
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Nos. per chain. Rs: 81.68

S/N D E S C R I P T I O N.

5. Rolling matresses to river edge and floating after un-rolling.


(a) Area of matress upto 2000 Sft.

(Unit of rate per 100 Sft.)


_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Coolies. 1.10 Nos: 250.00 P.day. 275.00

Rs: 275.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 27.50
_____________________________ ______ ______ ______ ______ __________
TOTAL 302.50
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 30.25
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 332.75
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Sft. Rs: 332.75

S/N D E S C R I P T I O N.

5. Rolling matresses to river edge and floating after un-rolling.


(b) Area of matress 2000 Sft to 2500 Sft.

Chapter No. 13 940/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
(Unit of rate per 100 Sft.)
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Coolies. 2.10 Nos: 250.00 P.day. 525.00

Rs: 525.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 52.50
_____________________________ ______ ______ ______ ______ __________
TOTAL 577.50
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 57.75
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 635.25
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Sft. Rs: 635.25

S/N D E S C R I P T I O N.

5. Rolling matresses to river edge and floating after un-rolling.


(c) Area of matress over 2500 Sft.

(Unit of rate per 100 Sft.)


_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Coolies. 1.32 Nos: 250.00 P.day. 330.00

Rs: 330.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 33.00
_____________________________ ______ ______ ______ ______ __________
TOTAL 363.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 36.30
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 399.30
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Sft. Rs: 399.30
S/N D E S C R I P T I O N.

6. Sewing empty cement bags in sheets.

_____ _____________________________ ______ ______ ______ ______ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Sutli. 1.00 Seer. 135.00 Seer. 135.00

_____________________________ ______ ______ ______ ______ __________


TOTAL 135.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 13.50
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " A " 148.50
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR
_____________________________ ______ ______ ______ ______ __________

Coolies. 1.45 Nos: 250.00 P.day. 362.50

_____________________________ ______ ______ ______ ______ __________


Rs: 362.50
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 36.25

Chapter No. 13 941/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
_____________________________ ______ ______ ______ ______ __________
TOTAL 398.75
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 39.88
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " B " 438.63
_____________________________ ______ ______ ______ ______ __________
TOTAL (MATERIAL + LABOUR) 587.13
_____________________________ ______ ______ ______ ______ __________
Total material & labour for 100 Nos. Rs: 587.13

Total material & labour for 100 Nos. say Rs: 587.13
_____ _____________________________ ______ ______ ______ ______ __________
S/N D E S C R I P T I O N.
7. Carriage of pilchi sarkanda of frash or brush wood by boat or
road.
(a) Ist: chain. (Unit of rate 100 Cft.)
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Small boat with boatman. 0.03 Nos: 450.00 P.day. 13.50

Skilled Coolies. 0.03 Nos: 250.00 P.day. 7.50


Rs: 21.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 2.10
_____________________________ ______ ______ ______ ______ __________
TOTAL 23.10
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 2.31
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 25.41
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 25.41

S/N D E S C R I P T I O N.

7. Carriage of pilchi sarkanda of frash or brush wood by boat or


road.

(b) 2nd chain. (Unit of rate 100 Cft.)


_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Small boat with boatman. 0.02 Nos: 450.00 P.day. 9.00

Skilled Coolies. 0.02 Nos: 250.00 P.day. 5.00

Rs: 14.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 1.40
_____________________________ ______ ______ ______ ______ __________
TOTAL 15.40
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 1.54
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 16.94
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 16.94

S/N D E S C R I P T I O N.
7. Carriage of pilchi sarkanda of frash or brush wood by boat or
road.

(c) 3rd to 10th chain. (Unit of rate 100 Cft.)


_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Small boat with boatman. 0.007 Nos: 450.00 P.day. 3.15

Skilled Coolies. 0.007 Nos: 250.00 P.day. 1.75


Rs: 4.90
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 0.49

Chapter No. 13 942/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
_____________________________ ______ ______ ______ ______ __________
TOTAL 5.39
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 0.54
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 5.93
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 5.93
S/N D E S C R I P T I O N.

7. Carriage of pilchi sarkanda of frash or brush wood by boat or


road.

(d) 1001 ft. to 5000 ft. (Unit of rate 100 Cft.)


_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Small boat with boatman. 0.040 Nos: 450.00 P.day. 18.00

Skilled Coolies. 0.040 Nos: 250.00 P.day. 10.00

Rs: 28.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 2.80
_____________________________ ______ ______ ______ ______ __________
TOTAL 30.80
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 3.08
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 33.88
Total labour rate for 100 Cft. Rs: 33.88
S/N D E S C R I P T I O N.

7. Carriage of pilchi sarkanda of frash or brush wood by boat or


road.

(e) Ist: mile. (Unit of rate 100 Cft.)


_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Small boat with boatman. 0.250 Nos: 450.00 P.day. 112.50

Skilled Coolies. 0.250 Nos: 250.00 P.day. 62.50


Rs: 175.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 17.50
_____________________________ ______ ______ ______ ______ __________
TOTAL 192.50
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 19.25
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 211.75
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 211.75

Chapter No. 13 943/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
S/N D E S C R I P T I O N.

7. Carriage of pilchi sarkanda of frash or brush wood by boat or


road.

(f) 2nd mile. (Unit of rate 100 Cft.)


_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Small boat with boatman. 0.200 Nos: 450.00 P.day. 90.00

Skilled Coolies. 0.200 Nos: 250.00 P.day. 50.00


Rs: 140.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 14.00
_____________________________ ______ ______ ______ ______ __________
TOTAL 154.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 15.40
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 169.40
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 169.40
S/N D E S C R I P T I O N.

7. Carriage of pilchi sarkanda of frash or brush wood by boat or


road.

(g) 3rd mile. (Unit of rate 100 Cft.)


_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Small boat with boatman. 0.150 Nos: 450.00 P.day. 67.50

Skilled Coolies. 0.150 Nos: 250.00 P.day. 37.50

_____________________________ ______ ______ ______ ______ __________


Rs: 105.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 10.50
_____________________________ ______ ______ ______ ______ __________
TOTAL 115.50
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 11.55
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 127.05
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 127.05
S/N D E S C R I P T I O N.

7. Carriage of pilchi sarkanda of frash or brush wood by boat or


road.

(h) 4th mile. (Unit of rate 100 Cft.)


_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Small boat with boatman. 0.120 Nos: 450.00 P.day. 54.00

Skilled Coolies. 0.120 Nos: 250.00 P.day. 30.00


Rs: 84.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 8.40
_____________________________ ______ ______ ______ ______ __________
TOTAL 92.40
Contractor's profit 10.00 % 9.24
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 101.64
Total labour rate for 100 Cft. Rs: 101.64
S/N D E S C R I P T I O N.
7. Carriage of pilchi sarkanda of frash or brush wood by boat or
road.
(i) 5th and subsequent mile. (Unit of rate 100 Cft.)
_____________________________ ______ ______ ______ ______ __________

Chapter No. 13 944/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Small boat with boatman. 0.100 Nos: 450.00 P.day. 45.00

Skilled Coolies. 0.100 Nos: 250.00 P.day. 25.00


Rs: 70.00
Sundries. 10.00 % 7.00
TOTAL 77.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 7.70
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 84.70
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 84.70
S/N D E S C R I P T I O N.

8. Making compact round pilchi farash or sarkanda round bundles of


specified size for the work.
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Munj ban as per item 2.31 Seer 150.00 P.Kg 346.50
no:23 of this chapter =
TOTAL 346.50
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 34.65
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " A " 381.15
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR
Coolies. 1.95 Nos: 250.00 P.day. 487.50
Rs: 487.50
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 48.75
TOTAL 536.25
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 53.63
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " B " 589.88
_____________________________ ______ ______ ______ ______ __________
TOTAL (MATERIAL + LABOUR) 971.03
_____________________________ ______ ______ ______ ______ __________
Total material & labour for 100 Cft. say Rs: 971.03
S/N D E S C R I P T I O N.

9. Launching the above and placing in position.

(Unit of rate 100 Cft.)


_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Coolies. 1.200 Nos: 250.00 P.day. 300.00

_____________________________ ______ ______ ______ ______ __________


Rs: 300.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 30.00
_____________________________ ______ ______ ______ ______ __________
TOTAL 330.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 33.00
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 363.00
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 363.00
_____ _____________________________ ______ ______ ______ ______ __________
S/N D E S C R I P T I O N.

10. Supplying within 5 chains.

(a) Boulders 9" and above.


(Unit of rate 100 Cft.)
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT

Coolies. 3.620 Nos: 250.00 P.day. 905.00

Chapter No. 13 945/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ ______ ______ ______ ______ __________


Rs: 905.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 90.50
_____________________________ ______ ______ ______ ______ __________
TOTAL 995.50
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 99.55
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 1095.05
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 1095.05

S/N D E S C R I P T I O N.

10. Supplying within 5 chains.

(b) Over size shingle 3" to 9".


(Unit of rate 100 Cft.)
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Coolies. 2.420 Nos: 250.00 P.day. 605.00

_____________________________ ______ ______ ______ ______ __________


Rs: 605.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 60.50
_____________________________ ______ ______ ______ ______ __________
TOTAL 665.50
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 66.55
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 732.05
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 732.05

S/N D E S C R I P T I O N.

10. Supplying within 5 chains.

(c) Mixed graded shingle.


(Unit of rate 100 Cft.)
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT

Coolies. 2.870 Nos: 250.00 P.day. 717.50

_____________________________ ______ ______ ______ ______ __________


Rs: 717.50
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 71.75
_____________________________ ______ ______ ______ ______ __________
TOTAL 789.25
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 78.93
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 868.18
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 868.18

S/N D E S C R I P T I O N.

11. Supplying Munj or patha trungers (6" mesh to hold 3 Cft.)

Assume for 2 Nos.


_____ _____________________________ ______ ______ ______ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Munjwan. 4.00 Seer. 150.00 P.Kg. 600.00
TOTAL 600.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 60.00
_____________________________ ______ ______ ______ ______ __________

Chapter No. 13 946/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
TOTAL PART " A " 660.00
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR
_____________________________ ______ ______ ______ ______ __________

Coolies. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ ______ ______ ______ ______ __________


Rs: 62.50
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 6.25
_____________________________ ______ ______ ______ ______ __________
TOTAL 68.75
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 6.88
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " B " 37.81 75.63
_____________________________ ______ ______ ______ ______ __________
TOTAL (MATERIAL + LABOUR) 735.63
_____________________________ ______ ______ ______ ______ __________
Total material & labour for 2 Nos. Rs: 735.63
Total material & labour for 1 Nos. Rs: 367.81

_____ _____________________________ ______ ______ ______ ______ __________

_____ _____________________________ ______ ______ ______ ______ __________


S/N D E S C R I P T I O N.

12. Weaving wire netting for wire crates with G.I. wire No:15.

(a) 6" mesh.


_____ _____________________________ ______ ______ ______ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
No:15 wire 500' weighs 8 lbs.
_____________________________ ______ ______ ______ ______ __________
No:15 Wire. (G.I) 8.00 Lbs. 4250.00 P.Cwt. 303.57

_____________________________ ______ ______ ______ ______ __________


TOTAL 303.57
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 30.36
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " A " 333.93
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR
_____________________________ ______ ______ ______ ______ __________
Blacksmith. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 0.75 Nos: 250.00 P.day. 187.50

_____________________________ ______ ______ ______ ______ __________


Rs: 525.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 52.50
_____________________________ ______ ______ ______ ______ __________
TOTAL 577.50
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 57.75
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " B " 635.25
_____________________________ ______ ______ ______ ______ __________
TOTAL (MATERIAL + LABOUR) 969.18

Chapter No. 13 947/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
_____________________________ ______ ______ ______ ______ __________
Total material & labour for 100 Sft. Rs: 969.18

Total material & labour for 100 Sft. say Rs: 969.18
S/N D E S C R I P T I O N.

12. Weaving wire netting for wire crates with G.I. wire No:15.

(b) 4" mesh.


_____ _____________________________ ______ ______ ______ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
No:15 wire 750' weighs 12 lbs.
_____________________________ ______ ______ ______ ______ __________
No:15 Wire. 12.00 Lbs. 4250.00 P.Cwt. 455.36
_____________________________ ______ ______ ______ ______ __________
TOTAL 455.36
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 45.54
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " A " 500.89
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR
_____________________________ ______ ______ ______ ______ __________
Blacksmith. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 1.00 Nos: 250.00 P.day. 250.00

_____________________________ ______ ______ ______ ______ __________


Rs: 700.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 70.00
_____________________________ ______ ______ ______ ______ __________
TOTAL 770.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 77.00
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " B " 847.00
_____________________________ ______ ______ ______ ______ __________
TOTAL (MATERIAL + LABOUR) 1347.89
_____________________________ ______ ______ ______ ______ __________
Total material & labour for 100 Sft. Rs: 1347.89

Total material & labour for 100 Sft. say Rs: 1347.89
_____ _____________________________ ______ ______ ______ ______ __________

S/N D E S C R I P T I O N.

13. Filling brick bats in crates.


(Unit of rate 100 Cft.)
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________

Coolies. 1.070 Nos: 250.00 P.day. 267.50

_____________________________ ______ ______ ______ ______ __________


Rs: 267.50
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 26.75
_____________________________ ______ ______ ______ ______ __________
TOTAL 294.25
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 29.43
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 323.68
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 323.68

_____ _____________________________ ______ ______ ______ ______ __________

Chapter No. 13 948/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
_____ _____________________________ ______ ______ ______ ______ __________
S/N D E S C R I P T I O N.

14. Filling brick bats in crates and hand packing.

(Unit of rate 100 Cft.)


_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________

Coolies. 2.160 Nos: 250.00 P.day. 540.00

Rs: 540.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 54.00
_____________________________ ______ ______ ______ ______ __________
TOTAL 594.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 59.40
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 653.40
Total labour rate for 100 Cft. Rs: 653.40
S/N D E S C R I P T I O N.

15. Filling stone in wire crates and sewing.

(Unit of rate 100 Cft.)


_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________

Coolies. 3.000 Nos: 250.00 P.day. 750.00

_____________________________ ______ ______ ______ ______ __________


Rs: 750.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 75.00
_____________________________ ______ ______ ______ ______ __________
TOTAL 825.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 82.50
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 907.50
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 907.50
S/N D E S C R I P T I O N.

16. Laying shingle on top of bund including carriage of material


within 3 chains.
(Unit of rate 100 Cft.)
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________

Coolies. 1.000 Nos: 250.00 P.day. 250.00

_____________________________ ______ ______ ______ ______ __________


Rs: 250.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 25.00
_____________________________ ______ ______ ______ ______ __________
TOTAL 275.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 27.50
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 302.50
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 302.50
S/N D E S C R I P T I O N.

17. Dumping shingle spawls and boulders including carriage of


material within 3 chains.
(Unit of rate 100 Cft.)
_____________________________ ______ ______ ______ ______ __________

Chapter No. 13 949/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________

Coolies. 1.750 Nos: 250.00 P.day. 437.50

_____________________________ ______ ______ ______ ______ __________


Rs: 437.50
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 43.75
_____________________________ ______ ______ ______ ______ __________
TOTAL 481.25
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 48.13
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 529.38
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 529.38
S/N D E S C R I P T I O N.

18. Tipping wire crates.

(Unit of rate 100 Cft.)


_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________

Coolies. 2.000 Nos: 250.00 P.day. 500.00

_____________________________ ______ ______ ______ ______ __________


Rs: 500.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 50.00
_____________________________ ______ ______ ______ ______ __________
TOTAL 550.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 55.00
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 605.00
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 605.00
S/N D E S C R I P T I O N.

19. Dumping stone by boat including loading in to boat lead within


3 chains.
(Unit of rate 100 Cft.)
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Boatman with boat. 1.000 Nos: 500.00 P.day. 500.00
Coolies. 2.000 Nos: 250.00 P.day. 500.00

_____________________________ ______ ______ ______ ______ __________


Rs: 1000.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 100.00
_____________________________ ______ ______ ______ ______ __________
TOTAL 1100.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 110.00
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 1210.00
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 1210.00
S/N D E S C R I P T I O N.

20. Extra for anchoring boat.

(Unit of rate 100 Cft.)


_____________________________ ______ ______ ______ ______ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Boatman. 0.200 Nos: 250.00 P.day. 50.00

Chapter No. 13 950/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ ______ ______ ______ ______ __________


Rs: 50.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 5.00
_____________________________ ______ ______ ______ ______ __________
TOTAL 55.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 5.50
_____________________________ ______ ______ ______ ______ __________
TOTAL (LABOUR) 60.50
_____________________________ ______ ______ ______ ______ __________
Total labour rate for 100 Cft. Rs: 60.50
S/N D E S C R I P T I O N.

21. Pilchi revtment including carriage upto one mile.

_____ _____________________________ ______ ______ ______ ______ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Supplying Pilchi with in 200.00 Cft. 475.00 P.% Cft. 950.00
one mile.

_____________________________ ______ ______ ______ ______ __________


TOTAL 950.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 95.00
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " A " 1045.00
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR
_____________________________ ______ ______ ______ ______ __________

Coolies. 1.00 Nos: 250.00 P.day. 250.00

_____________________________ ______ ______ ______ ______ __________


Rs: 250.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 25.00
_____________________________ ______ ______ ______ ______ __________
TOTAL 275.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 27.50
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " B " 302.50
_____________________________ ______ ______ ______ ______ __________
TOTAL (MATERIAL + LABOUR) 1347.50
_____________________________ ______ ______ ______ ______ __________
Total material & labour for 100 Sft. Rs: 1347.50

_____ _____________________________ ______ ______ ______ ______ __________

_____ _____________________________ ______ ______ ______ ______ __________


S/N D E S C R I P T I O N.

22. Surface protection with pilchi matresses carriage upto one mile.

_____ _____________________________ ______ ______ ______ ______ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Supplying Pilchi with in 20.00 Cft. 475.00 P.% Cft. 95.00
one mile.

Chapter No. 13 951/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
_____________________________ ______ ______ ______ ______ __________
TOTAL 95.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 9.50
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " A " 104.50
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR
_____________________________ ______ ______ ______ ______ __________

Coolies. 2.90 Nos: 250.00 P.day. 725.00

_____________________________ ______ ______ ______ ______ __________


Rs: 725.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 72.50
_____________________________ ______ ______ ______ ______ __________
TOTAL 797.50
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 79.75
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " B " 877.25
_____________________________ ______ ______ ______ ______ __________
TOTAL (MATERIAL + LABOUR) 981.75
_____________________________ ______ ______ ______ ______ __________
Total material & labour for 100 Sft. Rs: 981.75

Total material & labour for 100 Sft. say Rs: 981.75
S/N D E S C R I P T I O N.
23. Palchi sarkanda or farash pitching on slope, including supply of
pilchi, sarkanda or farash.
Cutting Pilchi and carriage to river bank lead upto one mile.
Pilchi rolls 6" dia 10' long =
= 10 * 10' * 22/7 * 1'/2 * 1'/2 * 1/4 = 20 Cft.
Pilchi rolls 6" dia 5' long =
cross wise = 10 * 20 * 5' * 22/7 * 1'/2 * 1'/2 * 1/4 = 196 Cft.
------------------------------------------------ ----------- ----------- ----------- ----------- ----------------
i TOTAL =
------------------------------------------------ ----------- ----------- ----------- ----------- ----------------
ii Pegs 1'-1'/2 long 2" dia sharpened at one end 2' apart = 50 Nos.
_____ _____________________________ ______ ______ ______ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Supplying Pilchi with in 216.00 Cft. 475.00 % Cft. 1026.00
one mile.

Pegs 1'-1'/2 long 2" dia. 50.00 Nos. 900.00 % Nos. 450.00

Munj ban. 5.00 Seer. 150.00 P.Kg 750.00


_____________________________ ______ ______ ______ ______ __________
TOTAL 2226.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 222.60
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " A " 2448.60
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR
_____________________________ ______ ______ ______ ______ __________
Coolies for making 1.95 Nos: 250.00 P.day. 487.50
pilchi rolls.
Coolies for laying pilchi 2.00 Nos: 250.00 P.day. 500.00
rolls in position and
driving pegs.
Dreeser for dressing. 0.20 Nos: 250.00 P.day. 50.00
Cooly for dressing. 0.12 250.00 P.day. 30.00
_____________________________ ______ ______ ______ ______ __________
Rs: 1067.50
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 106.75
_____________________________ ______ ______ ______ ______ __________
TOTAL 1174.25
_____________________________ ______ ______ ______ ______ __________

Chapter No. 13 952/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52
Contractor's profit 10.00 % 117.43
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " B " 1291.68
_____________________________ ______ ______ ______ ______ __________
TOTAL (MATERIAL + LABOUR) 3740.28
_____________________________ ______ ______ ______ ______ __________
Total material & labour for 100 Sft. Rs: 3740.28

Total material & labour for 100 Sft. say Rs: 3740.28
S/N D E S C R I P T I O N.

24. Constructing groynes single upto 5 feet hieght average lead one
mile.
Length of grones = 100/5 =20 Ft.
_____ _____________________________ ______ ______ ______ ______ __________
Vertical stakes 7" - 12" thick 5' apart = 21 Nos.
Supports = 4 Nos.
Wastage = 3 Nos.
------------------------------------------------ ----------- ----------- ----------- ----------- ----------------
i Total = 28 Nos.
_____ _____________________________ ______ ______ ______ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Stakes 7" - 12" thick. 28.00 Nos. 3550.00 % Nos. 994.00

Munj ban. 0.35 Seer. 150.00 P.Kg 52.50


_____________________________ ______ ______ ______ ______ __________
TOTAL 1046.50
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 104.65
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " A " 1151.15
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR
_____________________________ ______ ______ ______ ______ __________
Skilled coolies. 1.00 Nos: 250.00 P.day. 250.00

Coolies. 1.00 Nos: 250.00 P.day. 250.00

Rs: 500.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 50.00
_____________________________ ______ ______ ______ ______ __________
TOTAL 550.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 55.00
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " B " 605.00
_____________________________ ______ ______ ______ ______ __________
TOTAL (MATERIAL + LABOUR) 1756.15
_____________________________ ______ ______ ______ ______ __________
Total material & labour for 100 Sft. Rs: 1756.15
Total material & labour for 100 Sft. say Rs: 1756.15
S/N D E S C R I P T I O N.

Chapter No. 13 953/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

25. Constructing groynes double upto 10 feet hieght average lead one
mile.
Length of grones = 100/10 =10 Ft.
_____ _____________________________ ______ ______ ______ ______ __________
Vertical stakes 9" - 12" thick 5' apart = 22 Nos.
Supports = 4 Nos.
Cross patties. = 3 Nos.
Wastage = 3 Nos.
------------------------------------------------ ----------- ----------- ----------- ----------- ----------------
i Total = 32 Nos.
_____ _____________________________ ______ ______ ______ ______ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ ______ ______ ______ __________
Stakes 9" - 12" thick. 32.00 Nos. 4325.00 % Nos. 1384.00

Munj ban. 0.50 Seer. 150.00 P.Kg 75.00


_____________________________ ______ ______ ______ ______ __________
TOTAL 1459.00
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 145.90
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " A " 1604.90
_____________________________ ______ ______ ______ ______ __________
(B) LABOUR
_____________________________ ______ ______ ______ ______ __________
Skilled coolies. 1.50 Nos: 250.00 P.day. 375.00

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Rs: 875.00
_____________________________ ______ ______ ______ ______ __________
Sundries. 10.00 % 87.50
_____________________________ ______ ______ ______ ______ __________
TOTAL 962.50
_____________________________ ______ ______ ______ ______ __________
Contractor's profit 10.00 % 96.25
_____________________________ ______ ______ ______ ______ __________
TOTAL PART " B " 1058.75
_____________________________ ______ ______ ______ ______ __________
TOTAL (MATERIAL + LABOUR) 2663.65
_____________________________ ______ ______ ______ ______ __________
Total material & labour for 100 Sft. Rs: 2663.65
26 Synthetic Bags

Synthetic Bags new / Ist bharti 4 to 5


capacity with sand or earth sewing
lying in posiotion under water.
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
New / Ist bharti bags 50 Nos. @ Rs . 8.00 50 P.bag 8.00 400.00
Cost of cotton rope @ Rs. 50.00 P/kg (2 kg) 2kg 50.00 100.00
TOTAL 500.00
Contractor's profit 10 % 50.00
TOTAL PART " A " 550.00

(B) LABOUR
Coolies 7 Nos @ Rs. 100/- 7.0 Nos. 100 700.00
Add for sundries (S.D) 10 % 70.00
Total 770.00
Contractor's profit 10 % 77.00
TOTAL PART " B " 8.47 847.00
TOTAL (MATERIAL + LABOUR) 1397.00
27.94

Chapter No. 13 954/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

FIRST FILL THIS SHEET

OUT LETS
MATERIAL RATE UNIT

1 Bricks 5000 % 0Nos

2 Cement 400 P.Bag

3 Sand 2425 % Cft

4 Shingle graded 3/4" 3075 % Cft

LABOUR RATE UNIT

250 P.day
1 Coolies
450 P.day
2 Mason

Chapter No. 14 955/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N O U T L E T-15
--------------
NOTE Rate for all finished work include the removal of the surplus
debris un-used material and by-products.

D E S C R I P T I O N.
======================
1. Earth work for outlets excavation refilling ramming and puddling.
(a) Channels discharge upto 50 cusecs.
______________________________ ______ _____ ______ ________ ________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Coolies. 2.50 Nos: 250.00 P.day. 625.00
Rs: 625.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 62.50
______________________________ ______ _____ ______ ________ ________
TOTAL 687.50
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 68.75
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 756.25
______________________________ ______ _____ ______ ________ ________
Total labour rate per job. Rs: 756.25
S/N D E S C R I P T I O N.
======================
1. Earth work for outlets excavation refilling ramming and puddling.

(b) Channels discharge from 51 to 100 cusecs.

______________________________ ______ _____ ______ ________ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Coolies. 3.30 Nos: 250.00 P.day. 825.00

Rs: 825.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 82.50
______________________________ ______ _____ ______ ________ ________
TOTAL 907.50
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 90.75
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 998.25
______________________________ ______ _____ ______ ________ ________

Chapter No. 14 956/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total labour rate per job. Rs: 998.25


S/N D E S C R I P T I O N.
======================
1. Earth work for outlets excavation refilling ramming and puddling.

(c) Channels discharge from 101 to 200 cusecs.

______________________________ ______ _____ ______ ________ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Coolies. 5.00 Nos: 250.00 P.day. 1250.00

______________________________ ______ _____ ______ ________ ________


Rs: 1250.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 125.00
______________________________ ______ _____ ______ ________ ________
TOTAL 1375.00
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 137.50
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 1512.50
______________________________ ______ _____ ______ ________ ________
Total labour rate per job. Rs: 1512.50
S/N D E S C R I P T I O N.
======================
1. Earth work for outlets excavation refilling ramming and puddling.

(d) Channels discharge from 201 to 350 cusecs.

______________________________ ______ _____ ______ ________ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Coolies. 6.75 Nos: 250.00 P.day. 1687.50

Rs: 1687.50
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 168.75
______________________________ ______ _____ ______ ________ ________
TOTAL 1856.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 185.63
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 2041.88

Chapter No. 14 957/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ ________


Total labour rate per job. Rs: 2041.88
S/N D E S C R I P T I O N.
======================
1. Earth work for outlets excavation refilling ramming and puddling.

(e) Channels discharge over to 350 cusecs.

______________________________ ______ _____ ______ ________ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Coolies. 10.00 Nos: 250.00 P.day. 2500.00

Rs: 2500.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 250.00
______________________________ ______ _____ ______ ________ ________
TOTAL 2750.00
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 275.00
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 3025.00
______________________________ ______ _____ ______ ________ ________
Total labour rate per job. Rs: 3025.00
_____ ______________________________ ______ _____ ______ ________ ________
_____ ______________________________ ______ _____ ______ ________ ________
S/N D E S C R I P T I O N.
======================
2. These rates are for total dismentlement and removal of material.
The rates do not include earth work for which rates are given in
item No:1 above.
(a) Old types such as K.G.O's orisie, etc.

______________________________ ______ _____ ______ ________ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Coolies. 2.50 Nos: 250.00 P.day. 625.00
______________________________ ______ _____ ______ ________ ________
Rs: 625.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 62.50
______________________________ ______ _____ ______ ________ ________
TOTAL 687.50
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 68.75

Chapter No. 14 958/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (LABOUR) 756.25


______________________________ ______ _____ ______ ________ ________
Total labour rate per Each No. Rs: 756.25
S/N D E S C R I P T I O N.
======================
2. These rates are for total dismentlement and removal of material.
The rates do not include earth work for which rates are given in
item No:1 above.
(b) A.P.M. or O.F. 'H'upto 2.0 ft.

______________________________ ______ _____ ______ ________ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Coolies. 3.75 Nos: 250.00 P.day. 937.50

Rs: 937.50
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 93.75
______________________________ ______ _____ ______ ________ ________
TOTAL 1031.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 103.13
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 1134.38
______________________________ ______ _____ ______ ________ ________
Total labour rate per Each No. Rs: 1134.38
_____ ______________________________ ______ _____ ______ ________ ________
_____ ______________________________ ______ _____ ______ ________ ________
S/N D E S C R I P T I O N.
======================
2. These rates are for total dismentlement and removal of material.
The rates do not include earth work for which rates are given in
item No:1 above.
(c) A.P.M. or O.F. 'H'upto 2.1 ft. to 3.0 ft.

______________________________ ______ _____ ______ ________ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Coolies. 5.00 Nos: 250.00 P.day. 1250.00
Rs: 1250.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 125.00
______________________________ ______ _____ ______ ________ ________
TOTAL 1375.00
______________________________ ______ _____ ______ ________ ________

Chapter No. 14 959/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 137.50


______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 1512.50
Total labour rate per Each No. Rs: 1512.50
S/N D E S C R I P T I O N.
======================
2. These rates are for total dismentlement and removal of material.
The rates do not include earth work for which rates are given in
item No:1 above.
(d) A.P.M. or O.F. 'H' above 3.0 ft.

______________________________ ______ _____ ______ ________ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Coolies. 6.25 Nos: 250.00 P.day. 1562.50

______________________________ ______ _____ ______ ________ ________


Rs: 1562.50
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 156.25
______________________________ ______ _____ ______ ________ ________
TOTAL 1718.75
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 171.88
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 1890.63
______________________________ ______ _____ ______ ________ ________
Total labour rate per Each No. Rs: 1890.63
S/N D E S C R I P T I O N.
======================
2. These rates are for total dismentlement and removal of material.
The rates do not include earth work for which rates are given in
item No:1 above.
(e) Tail Cluster bifurcation.

______________________________ ______ _____ ______ ________ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Coolies. 3.75 Nos: 250.00 P.day. 937.50
______________________________ ______ _____ ______ ________ ________
Rs: 937.50
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 93.75
______________________________ ______ _____ ______ ________ ________

Chapter No. 14 960/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 1031.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 103.13
TOTAL (LABOUR) 1134.38
Total labour rate per Each No. Rs: 1134.38
S/N D E S C R I P T I O N.
======================
2. These rates are for total dismentlement and removal of material.
The rates do not include earth work for which rates are given in
item No:1 above.
(f) Tail Cluster trifurcation.

______________________________ ______ _____ ______ ________ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Coolies. 5.00 Nos: 250.00 P.day. 1250.00

______________________________ ______ _____ ______ ________ ________


Rs: 1250.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 125.00
______________________________ ______ _____ ______ ________ ________
TOTAL 1375.00
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 137.50
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 1512.50
______________________________ ______ _____ ______ ________ ________
Total labour rate per Each No. Rs: 1512.50
_____ ______________________________ ______ _____ ______ ________ ________
_____ ______________________________ ______ _____ ______ ________ ________
S/N D E S C R I P T I O N.
======================
2. These rates are for total dismentlement and removal of material.
The rates do not include earth work for which rates are given in
item No:1 above.
(g) Tail Cluster quadrifurcation.

(B) LABOUR QUANTITY RATE UNIT AMOUNT


Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Coolies. 6.25 Nos: 250.00 P.day. 1562.50
Rs: 1562.50
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 156.25

Chapter No. 14 961/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ ________


TOTAL 1718.75
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 171.88
TOTAL (LABOUR) 1890.63
Total labour rate per Each No. Rs: 1890.63
S/N D E S C R I P T I O N.

3. Making temporary A.P.M. brick block and fixing at site.

_____ ______________________________ ______ _____ ______ ________ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Bricks. 20.00 Nos. 5000.00 %0 Nos: 100.00

Cement. 0.25 Cwt. 400.00 P.Cwt. 100.00

Sand. 1.00 Cft. 2425.00 % Cft. 24.25

TOTAL 224.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 22.43
______________________________ ______ _____ ______ ________ ________
TOTAL PART " A " 246.68
______________________________ ______ _____ ______ ________ ________
(B) LABOUR
______________________________ ______ _____ ______ ________ ________
Mason. 0.33 Nos: 450.00 P.day. 148.50

Coolies. 0.33 Nos: 250.00 P.day. 82.50

______________________________ ______ _____ ______ ________ ________


Rs: 231.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 23.10
______________________________ ______ _____ ______ ________ ________
TOTAL 254.10
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 25.41
______________________________ ______ _____ ______ ________ ________
TOTAL PART " B " 279.51

Chapter No. 14 962/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ ________


TOTAL (MATERIAL + LABOUR) 526.19
______________________________ ______ _____ ______ ________ ________
Total material & labour for each No. Rs: 526.19

_____ ______________________________ ______ _____ ______ ________ ________

_____ ______________________________ ______ _____ ______ ________ ________


S/N D E S C R I P T I O N.
======================
4. Dismentling walls, taking out tempprary A.P.M. bricks block and
fixing iron block and rebuilding dismentled walls.
______________________________ ______ _____ ______ ________ ________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Masons. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00


______________________________ ______ _____ ______ ________ ________
Rs: 587.50
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 58.75
______________________________ ______ _____ ______ ________ ________
TOTAL 646.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 64.63
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 710.88
______________________________ ______ _____ ______ ________ ________
Total labour rate per Job. Rs: 710.88
_____ ______________________________ ______ _____ ______ ________ ________
_____ ______________________________ ______ _____ ______ ________ ________
S/N D E S C R I P T I O N.
======================
5. Dismentling walls, and fitting iron block of O.F. outlet.

(B) LABOUR QUANTITY RATE UNIT AMOUNT


Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Masons. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.00 Nos: 250.00 P.day. 250.00


______________________________ ______ _____ ______ ________ ________
Rs: 587.50
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 58.75

Chapter No. 14 963/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ ________


TOTAL 646.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 64.63
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 710.88
______________________________ ______ _____ ______ ________ ________
Total labour rate per each No. Rs: 710.88
S/N D E S C R I P T I O N.
======================
6. Constructing watching and removing bund for outlet built in
runing water.
(a) Upto 3.0 ft. depth.
______________________________ ______ _____ ______ ________ ________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________

Coolies. 5.00 Nos: 250.00 P.day. 1250.00


______________________________ ______ _____ ______ ________ ________
Rs: 1250.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 125.00
______________________________ ______ _____ ______ ________ ________
TOTAL 1375.00
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 137.50
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 1512.50
______________________________ ______ _____ ______ ________ ________
Total labour rate per each No. Rs: 1512.50
_____ ______________________________ ______ _____ ______ ________ ________
_____ ______________________________ ______ _____ ______ ________ ________
S/N D E S C R I P T I O N.
======================
6. Constructing watching and removing bund for outlet built in
runing water.
(b) Above 3.0 ft. depth.
______________________________ ______ _____ ______ ________ ________
(B) LABOUR QUANTITY RATE UNIT AMOUNT

Coolies. 6.75 Nos: 250.00 P.day. 1687.50


______________________________ ______ _____ ______ ________ ________
Rs: 1687.50
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 168.75

Chapter No. 14 964/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ ________


TOTAL 1856.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 185.63
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 2041.88
______________________________ ______ _____ ______ ________ ________
Total labour rate per each No. Rs: 2041.88
_____ ______________________________ ______ _____ ______ ________ ________

_____ ______________________________ ______ _____ ______ ________ ________


S/N D E S C R I P T I O N.

7. Adjusting 'B' of tail cluster by dismentling and re-building


throat walls.

_____ ______________________________ ______ _____ ______ ________ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Bricks. 30.00 Nos. 5000.00 %0 Nos: 150.00

Cement. 0.30 Cwt. 400.00 P.Cwt. 120.00

Sand. 2.00 Cft. 2425.00 % Cft. 48.50

______________________________ ______ _____ ______ ________ ________


TOTAL 318.50
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 31.85
______________________________ ______ _____ ______ ________ ________
TOTAL PART " A " 350.35
______________________________ ______ _____ ______ ________ ________
(B) LABOUR
______________________________ ______ _____ ______ ________ ________
Mason. 0.40 Nos: 450.00 P.day. 180.00

Coolies. 0.75 Nos: 250.00 P.day. 187.50

______________________________ ______ _____ ______ ________ ________


Rs: 367.50
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 36.75

Chapter No. 14 965/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ ________


TOTAL 404.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 40.43
______________________________ ______ _____ ______ ________ ________
TOTAL PART " B " 444.68
______________________________ ______ _____ ______ ________ ________
TOTAL (MATERIAL + LABOUR) 795.03
______________________________ ______ _____ ______ ________ ________
Total material & labour for each No. Rs: 795.03
S/N D E S C R I P T I O N.

8. Adjusting 'Y' of an A.P.M. outlet including dismentling and


re-building.

_____ ______________________________ ______ _____ ______ ________ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Bricks. 50.00 Nos. 5000.00 %0 Nos: 250.00

Cement. 0.50 Cwt. 400.00 P.Cwt. 200.00

Sand. 2.00 Cft. 2425.00 % Cft. 48.50

______________________________ ______ _____ ______ ________ ________


TOTAL 498.50
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 49.85
______________________________ ______ _____ ______ ________ ________
TOTAL PART " A " 548.35
______________________________ ______ _____ ______ ________ ________
(B) LABOUR
______________________________ ______ _____ ______ ________ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 1.50 Nos: 250.00 P.day. 375.00

______________________________ ______ _____ ______ ________ ________


Rs: 712.50
______________________________ ______ _____ ______ ________ ________

Chapter No. 14 966/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Sundries. %10.00 71.25


______________________________ ______ _____ ______ ________ ________
TOTAL 783.75
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 78.38
______________________________ ______ _____ ______ ________ ________
TOTAL PART " B " 862.13
______________________________ ______ _____ ______ ________ ________
TOTAL (MATERIAL + LABOUR) 1410.48
______________________________ ______ _____ ______ ________ ________
Total material & labour for each No. Rs: 1410.48
S/N D E S C R I P T I O N.

9. Extra in fixing an A.P.M. and O.F. outlets block including


dressing of bricks.
(a) For channel depth of 5.0 ft.

_____ ______________________________ ______ _____ ______ ________ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________

Cement. 0.20 Cwt. 400.00 P.Cwt. 80.00

Sand. 1.00 Cft. 2425.00 % Cft. 24.25

______________________________ ______ _____ ______ ________ ________


TOTAL 104.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 10.43
______________________________ ______ _____ ______ ________ ________
TOTAL PART " A " 114.68
______________________________ ______ _____ ______ ________ ________
(B) LABOUR
______________________________ ______ _____ ______ ________ ________
Mason. 1.00 Nos: 450.00 P.day. 450.00

Coolies. 1.00 Nos: 250.00 P.day. 250.00

______________________________ ______ _____ ______ ________ ________


Rs: 700.00

Chapter No. 14 967/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ ________


Sundries. 10.00 % 70.00
______________________________ ______ _____ ______ ________ ________
TOTAL 770.00
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 77.00
______________________________ ______ _____ ______ ________ ________
TOTAL PART " B " 847.00
______________________________ ______ _____ ______ ________ ________
TOTAL (MATERIAL + LABOUR) 961.68
______________________________ ______ _____ ______ ________ ________
Total material & labour for each No. Rs: 961.68
S/N D E S C R I P T I O N.

9. Extra in fixing an A.P.M. and O.F. outlets block including


dressing of bricks.
(b) For channel depth of 4.0 ft.

_____ ______________________________ ______ _____ ______ ________ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________

Cement. 0.20 Cwt. 400.00 P.Cwt. 80.00

Sand. 1.00 Cft. 2425.00 % Cft. 24.25

______________________________ ______ _____ ______ ________ ________


TOTAL 104.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 10.43
______________________________ ______ _____ ______ ________ ________
TOTAL PART " A " 114.68
______________________________ ______ _____ ______ ________ ________
(B) LABOUR
______________________________ ______ _____ ______ ________ ________
Mason. 0.75 Nos: 450.00 P.day. 337.50

Coolies. 0.75 Nos: 250.00 P.day. 187.50

______________________________ ______ _____ ______ ________ ________


Rs: 525.00

Chapter No. 14 968/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ ________


Sundries. 10.00 % 52.50
______________________________ ______ _____ ______ ________ ________
TOTAL 577.50
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 57.75
______________________________ ______ _____ ______ ________ ________
TOTAL PART " B " 635.25
______________________________ ______ _____ ______ ________ ________
TOTAL (MATERIAL + LABOUR) 749.93
______________________________ ______ _____ ______ ________ ________
Total material & labour for each No. Rs: 749.93
_____ ______________________________ ______ _____ ______ ________ ________
S/N D E S C R I P T I O N.

9. Extra in fixing an A.P.M. and O.F. outlets block including


dressing of bricks.
(c) For channel depth of 3.0 ft.

_____ ______________________________ ______ _____ ______ ________ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________

Cement. 0.20 Cwt. 400.00 P.Cwt. 80.00

Sand. 1.00 Cft. 2425.00 % Cft. 24.25

______________________________ ______ _____ ______ ________ ________


TOTAL 104.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 10.43
______________________________ ______ _____ ______ ________ ________
TOTAL PART " A " 114.68
______________________________ ______ _____ ______ ________ ________
(B) LABOUR
______________________________ ______ _____ ______ ________ ________
Mason. 0.60 Nos: 450.00 P.day. 270.00

Coolies. 0.60 Nos: 250.00 P.day. 150.00

______________________________ ______ _____ ______ ________ ________

Chapter No. 14 969/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Rs: 420.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 42.00
______________________________ ______ _____ ______ ________ ________
TOTAL 462.00
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 46.20
______________________________ ______ _____ ______ ________ ________
TOTAL PART " B " 508.20
______________________________ ______ _____ ______ ________ ________
TOTAL (MATERIAL + LABOUR) 622.88
______________________________ ______ _____ ______ ________ ________
Total material & labour for each No. Rs: 622.88
_____ ______________________________ ______ _____ ______ ________ ________
S/N D E S C R I P T I O N.

9. Extra in fixing an A.P.M. and O.F. outlets block including


dressing of bricks.
(d) For channel depth of 2.0 ft.

_____ ______________________________ ______ _____ ______ ________ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________

Cement. 0.15 Cwt. 400.00 P.Cwt. 60.00

Sand. 1.00 Cft. 2425.00 % Cft. 24.25

______________________________ ______ _____ ______ ________ ________


TOTAL 84.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 8.43
______________________________ ______ _____ ______ ________ ________
TOTAL PART " A " 92.68
______________________________ ______ _____ ______ ________ ________
(B) LABOUR
______________________________ ______ _____ ______ ________ ________
Mason. 0.50 Nos: 450.00 P.day. 225.00

Coolies. 0.50 Nos: 250.00 P.day. 125.00

Chapter No. 14 970/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ ________


Rs: 350.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 35.00
______________________________ ______ _____ ______ ________ ________
TOTAL 385.00
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 38.50
______________________________ ______ _____ ______ ________ ________
TOTAL PART " B " 423.50
______________________________ ______ _____ ______ ________ ________
TOTAL (MATERIAL + LABOUR) 516.18
______________________________ ______ _____ ______ ________ ________
Total material & labour for each No. Rs: 516.18
_____ ______________________________ ______ _____ ______ ________ ________
S/N D E S C R I P T I O N.

9. Extra in fixing an A.P.M. and O.F. outlets block including


dressing of bricks.
(e) For channel depth of less than 2.0 ft.

_____ ______________________________ ______ _____ ______ ________ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________

Cement. 0.10 Cwt. 400.00 P.Cwt. 40.00

Sand. 1.00 Cft. 2425.00 % Cft. 24.25

______________________________ ______ _____ ______ ________ ________


TOTAL 64.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 6.43
______________________________ ______ _____ ______ ________ ________
TOTAL PART " A " 70.68
______________________________ ______ _____ ______ ________ ________
(B) LABOUR
______________________________ ______ _____ ______ ________ ________
Mason. 0.40 Nos: 450.00 P.day. 180.00

Coolies. 0.40 Nos: 250.00 P.day. 100.00

Chapter No. 14 971/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ ________


Rs: 280.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 28.00
______________________________ ______ _____ ______ ________ ________
TOTAL 308.00
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 30.80
______________________________ ______ _____ ______ ________ ________
TOTAL PART " B " 338.80
______________________________ ______ _____ ______ ________ ________
TOTAL (MATERIAL + LABOUR) 409.48
______________________________ ______ _____ ______ ________ ________
Total material & labour for each No. Rs: 409.48
_____ ______________________________ ______ _____ ______ ________ ________
S/N D E S C R I P T I O N.

10. Repairing damaged reducing collar of Hume pipe outlets.

_____ ______________________________ ______ _____ ______ ________ ________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________

Cement. 0.25 Cwt. 400.00 P.Cwt. 100.00

Sand. 1.00 Cft. 2425.00 % Cft. 24.25

Shingle. 1.00 Cft. 3075.00 % Cft. 30.75

______________________________ ______ _____ ______ ________ ________


TOTAL 155.00
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 15.50
______________________________ ______ _____ ______ ________ ________
TOTAL PART " A " 170.50
______________________________ ______ _____ ______ ________ ________
(B) LABOUR
______________________________ ______ _____ ______ ________ ________
Mason. 0.33 Nos: 450.00 P.day. 148.50

Coolies. 0.33 Nos: 250.00 P.day. 82.50

Chapter No. 14 972/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ______ ________ ________


Rs: 231.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 23.10
______________________________ ______ _____ ______ ________ ________
TOTAL 254.10
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 25.41
______________________________ ______ _____ ______ ________ ________
TOTAL PART " B " 279.51
______________________________ ______ _____ ______ ________ ________
TOTAL (MATERIAL + LABOUR) 450.01
______________________________ ______ _____ ______ ________ ________
Total material & labour for each No. Rs: 450.01
_____ ______________________________ ______ _____ ______ ________ ________
S/N D E S C R I P T I O N.
======================
11. Laying iron pipes of outlets.
Assume 100 Nos:
______________________________ ______ _____ ______ ________ ________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Masons. 2.00 Nos: 450.00 P.day. 900.00
Coolies. 2.00 Nos: 250.00 P.day. 500.00
______________________________ ______ _____ ______ ________ ________
Rs: 1400.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 140.00
______________________________ ______ _____ ______ ________ ________
TOTAL 1540.00
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 154.00
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 1694.00
______________________________ ______ _____ ______ ________ ________
Total labour rate per each No. Rs: 16.94
Total labour rate per each No. SAY Rs: 16.94
_____ ______________________________ ______ _____ ______ ________ ________
_____ ______________________________ ______ _____ ______ ________ ________
S/N D E S C R I P T I O N.
======================
12. Water allowance for costructing outlets or culverts when canal
(i) water is not flowing.
NOTE At the discretion of Engineer Incharge depending upon the

Chapter No. 14 973/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

distance and source of supply.


______________________________ ______ _____ ______ ________ ________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________

Coolies. 1.22 Nos: 250.00 P.day. 305.00


______________________________ ______ _____ ______ ________ ________
Rs: 305.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 30.50
______________________________ ______ _____ ______ ________ ________
TOTAL 335.50
Contractor's profit 10.00 % 33.55
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 369.05
______________________________ ______ _____ ______ ________ ________
Total labour rate per each No. Rs: 369.05
S/N D E S C R I P T I O N.
======================
12. Water allowance for costructing outlets or culverts when canal
(ii) water is not flowing.

NOTE At the discretion of Engineer Incharge depending upon the


distance and source of supply.
______________________________ ______ _____ ______ ________ ________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:

Coolies. 2.50 Nos: 250.00 P.day. 625.00


______________________________ ______ _____ ______ ________ ________
Rs: 625.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 62.50
______________________________ ______ _____ ______ ________ ________
TOTAL 687.50
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 68.75
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 756.25
______________________________ ______ _____ ______ ________ ________
Total labour rate per each No. Rs: 756.25
_____ ______________________________ ______ _____ ______ ________ ________
_____ ______________________________ ______ _____ ______ ________ ________
S/N D E S C R I P T I O N.
======================
13. Hosing and placing R.C.C. slab or stone in position on outlets

Chapter No. 14 974/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

or W.C. culverts.

______________________________ ______ _____ ______ ________ ________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________
Masons. 0.20 Nos: 450.00 P.day. 90.00
Coolies. 0.65 Nos: 250.00 P.day. 162.50
______________________________ ______ _____ ______ ________ ________
Rs: 252.50
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 25.25
TOTAL 277.75
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 27.78
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 305.53
______________________________ ______ _____ ______ ________ ________
Total labour rate per each No. Rs: 305.53
S/N D E S C R I P T I O N.

14. Fixing pipe outlet including back filling of earth and puddling.

(a) Portion under bank.


Assume for 12 Rft.
_____ ______________________________ ______ _____ ______ ________ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________

Cement for joining callar. 0.20 Cwt. 400.00 P.Cwt. 80.00

Sand. 1.00 Cft. 2425.00 % Cft. 24.25

______________________________ ______ _____ ______ ________ ________


TOTAL 104.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 10.43
______________________________ ______ _____ ______ ________ ________
TOTAL PART " A " 114.68
______________________________ ______ _____ ______ ________ ________
(B) LABOUR
______________________________ ______ _____ ______ ________ ________
Mason. 0.25 Nos: 450.00 P.day. 112.50

Chapter No. 14 975/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Coolies. 2.00 Nos: 250.00 P.day. 500.00

Rs: 612.50
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 61.25
______________________________ ______ _____ ______ ________ ________
TOTAL 673.75
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 67.38
______________________________ ______ _____ ______ ________ ________
TOTAL PART " B " 61.76 741.13
______________________________ ______ _____ ______ ________ ________
TOTAL (MATERIAL + LABOUR) 855.80
______________________________ ______ _____ ______ ________ ________
Total material & labour for 12 Rft. Rs: 855.80
Total material & labour for 1 Rft. Rs: 71.32
Total material & labour per Rft. say Rs: 71.32
_____ ______________________________ ______ _____ ______ ________ ________

_____ ______________________________ ______ _____ ______ ________ ________


S/N D E S C R I P T I O N.

14. Fixing pipe outlet including back filling of earth and puddling.

(b) Portion under road beyond bank.


Assume for 12 Rft.
_____ ______________________________ ______ _____ ______ ________ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________

Cement for joining callar. 0.20 Cwt. 400.00 P.Cwt. 80.00

Sand. 1.00 Cft. 2425.00 % Cft. 24.25

______________________________ ______ _____ ______ ________ ________


TOTAL 104.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 10.43
______________________________ ______ _____ ______ ________ ________
TOTAL PART " A " 114.68
______________________________ ______ _____ ______ ________ ________
(B) LABOUR
______________________________ ______ _____ ______ ________ ________
Mason. 0.20 Nos: 450.00 P.day. 90.00

Chapter No. 14 976/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Coolies. 0.75 Nos: 250.00 P.day. 187.50

Rs: 277.50
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 27.75
______________________________ ______ _____ ______ ________ ________
TOTAL 305.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 30.53
______________________________ ______ _____ ______ ________ ________
TOTAL PART " B " 27.98 335.78
______________________________ ______ _____ ______ ________ ________
TOTAL (MATERIAL + LABOUR) 450.45
______________________________ ______ _____ ______ ________ ________
Total material & labour for 12 Rft. Rs: 450.45
Total material & labour for 1 Rft. Rs: 37.54
Total material & labour per Rft. say Rs: 37.54
_____ ______________________________ ______ _____ ______ ________ ________

_____ ______________________________ ______ _____ ______ ________ ________


S/N D E S C R I P T I O N.
======================
15. Removing pipe outlet refilling earth and pudling.
Assume 12 RFT.
(a) Portion under bank.
______________________________ ______ _____ ______ ________ ________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________

Coolies. 2.00 Nos: 250.00 P.day. 500.00


______________________________ ______ _____ ______ ________ ________
Rs: 500.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 50.00
______________________________ ______ _____ ______ ________ ________
TOTAL 550.00
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 55.00
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 605.00
______________________________ ______ _____ ______ ________ ________
Total labour rate per each No. Rs: 50.42
Total labour rate per each No. SAY Rs: 50.42
S/N D E S C R I P T I O N.
======================

Chapter No. 14 977/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

15. Removing pipe outlet refilling earth and pudling.


Assume 12 RFT.
(b) Portion under road beyond bank.
______________________________ ______ _____ ______ ________ ________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________

Coolies. 0.75 Nos: 250.00 P.day. 187.50


______________________________ ______ _____ ______ ________ ________
Rs: 187.50
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 18.75
______________________________ ______ _____ ______ ________ ________
TOTAL 206.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 20.63
______________________________ ______ _____ ______ ________ ________
TOTAL (LABOUR) 226.88
______________________________ ______ _____ ______ ________ ________
Total labour rate per each No. Rs: 18.91
Total labour rate per each No. SAY Rs: 18.91
S/N D E S C R I P T I O N.

16. Changing pipe outlet removing one pipe and replacing it at the
same site with another pipe complete with earth and puddling.

(a) Portion under bank.


Assume for 12 Rft.
_____ ______________________________ ______ _____ ______ ________ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________

Cement for joining callar. 0.20 Cwt. 400.00 P.Cwt. 80.00

Sand. 1.00 Cft. 2425.00 % Cft. 24.25

______________________________ ______ _____ ______ ________ ________


TOTAL 104.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 10.43
______________________________ ______ _____ ______ ________ ________
TOTAL PART " A " 114.68
______________________________ ______ _____ ______ ________ ________

Chapter No. 14 978/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(B) LABOUR
______________________________ ______ _____ ______ ________ ________
Mason. 0.20 Nos: 450.00 P.day. 90.00

Coolies. 2.50 Nos: 250.00 P.day. 625.00

Rs: 715.00
______________________________ ______ _____ ______ ________ ________
Sundries. 10.00 % 71.50
______________________________ ______ _____ ______ ________ ________
TOTAL 786.50
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 78.65
______________________________ ______ _____ ______ ________ ________
TOTAL PART " B " 72.10 865.15
______________________________ ______ _____ ______ ________ ________
TOTAL (MATERIAL + LABOUR) 979.83
______________________________ ______ _____ ______ ________ ________
Total material & labour for 12 Rft. Rs: 979.83
Total material & labour for 1 Rft. Rs: 81.65
Total material & labour per Rft. say Rs: 81.65
_____ ______________________________ ______ _____ ______ ________ ________

_____ ______________________________ ______ _____ ______ ________ ________


S/N D E S C R I P T I O N.

16. Changing pipe outlet removing one pipe and replacing it at the
same site with another pipe complete with earth and puddling.

(b) Portion under road beyond bank.


Assume for 12 Rft.
_____ ______________________________ ______ _____ ______ ________ ________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ______ ________ ________

Cement for joining callar. 0.20 Cwt. 400.00 P.Cwt. 80.00

Sand. 1.00 Cft. 2425.00 % Cft. 24.25

______________________________ ______ _____ ______ ________ ________


TOTAL 104.25
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % 10.43
______________________________ ______ _____ ______ ________ ________

Chapter No. 14 979/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL PART " A " 114.68


______________________________ ______ _____ ______ ________ ________
(B) LABOUR
______________________________ ______ _____ ______ ________ ________
Mason. 0.10 Nos: 450.00 P.day. 45.00

Coolies. 1.25 Nos: 250.00 P.day. 312.50

______________________________ ______ _____ ______ ________ ________


Sundries. 10.00 % #REF!
______________________________ ______ _____ ______ ________ ________
TOTAL #REF!
______________________________ ______ _____ ______ ________ ________
Contractor's profit 10.00 % #REF!
______________________________ ______ _____ ______ ________ ________
TOTAL PART " B " #REF! #REF!
______________________________ ______ _____ ______ ________ ________
TOTAL (MATERIAL + LABOUR) #REF!
______________________________ ______ _____ ______ ________ ________
Total material & labour for 12 Rft. Rs: #REF!
Total material & labour for 1 Rft. Rs: #REF!
Total material & labour per Rft. say Rs: #REF!
_____ ______________________________ ______ _____ ______ ________ ________

Chapter No. 14 980/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

FIRST FILL THIS SHEET

SINKING OF WELLS.

MATERIAL RATE UNIT

1 Steam Coal 4000 P.Ton

2 Scrap wood 900 P.mand

3 Waste Cotton 60 P.Lb

4 Kiker wood 1400 P.cft

5 M.S bar 3/4" dia. 3550 P.Cwt

6 Angle Iron 6" x^' x 1/2" 3575 P.Cwt

7 Cement 400 P.Cwt

8 Sand 2425 % cft

9 Shingle 2500 % Cft

10 Bolt and Nuts 200 P.doz

11 Char Coal 675 P.Mand

12 Form wane (Partal) 1700 P. Cft

LABOUR RATE UNIT

1 Coolies 250 P.day

2 Skilled Coolies, Divers, 250 P.day


Hammer Man

3 Fireman, Carpenter , 450 P.day


BlackSmith.

Chapter No. 15 982/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

1. Excavation of well in dry upto 20' below ground level and


disposal of soil within one chain.
(a) In ordinary soil or sand.
(i) From 0' to 5' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 3.00 Nos: 250.00 P.day. 750.00
Coolies for lifting. 4.43 Nos: 250.00 P.day. 1107.50
______________________________ ______ ______ ______ ______ _________
Rs: 1857.50
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 185.75
______________________________ ______ ______ ______ ______ _________
TOTAL 2043.25
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 204.33
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2247.58
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 2247.58

____ ______________________________ ______ ______ ______ ______ _________

Chapter No. 15 983/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ______________________________ ______ ______ ______ ______ _________


S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

1. Excavation of well in dry upto 20' below ground level and


disposal of soil within one chain.
(a) In ordinary soil or sand.
(ii) From 5.1' to 10' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 3.00 Nos: 250.00 P.day. 750.00
Coolies for lifting. 4.76 Nos: 250.00 P.day. 1190.00
______________________________ ______ ______ ______ ______ _________
Rs: 1940.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 194.00
______________________________ ______ ______ ______ ______ _________
TOTAL 2134.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 213.40
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2347.40
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 2347.40

____ ______________________________ ______ ______ ______ ______ _________

____ ______________________________ ______ ______ ______ ______ _________

Chapter No. 15 984/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

1. Excavation of well in dry upto 20' below ground level and


disposal of soil within one chain.
(a) In ordinary soil or sand.
(iii) From 10.1' to 15' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 3.00 Nos: 250.00 P.day. 750.00
Coolies for lifting. 5.73 Nos: 250.00 P.day. 1432.50
______________________________ ______ ______ ______ ______ _________
Rs: 2182.50
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 218.25
______________________________ ______ ______ ______ ______ _________
TOTAL 2400.75
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 240.08
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2640.83
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 2641.00

Chapter No. 15 985/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

1. Excavation of well in dry upto 20' below ground level and


disposal of soil within one chain.
(a) In ordinary soil or sand.
(iv) From 15.1' to 20' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 3.00 Nos: 250.00 P.day. 750.00
Coolies for lifting. 7.02 Nos: 250.00 P.day. 1755.00
______________________________ ______ ______ ______ ______ _________
Rs: 2505.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 250.50
______________________________ ______ ______ ______ ______ _________
TOTAL 2755.50
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 275.55
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 3031.05
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 3031.05

____ ______________________________ ______ ______ ______ ______ _________

Chapter No. 15 986/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ______________________________ ______ ______ ______ ______ _________

S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

1. Excavation of well in dry upto 20' below ground level and


disposal of soil within one chain.
(b) In hard soil.
(i) From 0' to 5' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 4.00 Nos: 250.00 P.day. 1000.00
Coolies for lifting. 5.05 Nos: 250.00 P.day. 1262.50
______________________________ ______ ______ ______ ______ _________
Rs: 2262.50
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 226.25
______________________________ ______ ______ ______ ______ _________
TOTAL 2488.75
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 248.88
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2737.63
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 2738.00

Chapter No. 15 987/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

1. Excavation of well in dry upto 20' below ground level and


disposal of soil within one chain.
(b) In hard soil.
(ii) From 5.1' to 10' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 4.00 Nos: 250.00 P.day. 1000.00
Coolies for lifting. 5.46 Nos: 250.00 P.day. 1365.00
______________________________ ______ ______ ______ ______ _________
Rs: 2365.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 236.50
______________________________ ______ ______ ______ ______ _________
TOTAL 2601.50
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 260.15
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2861.65
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 2861.65

____ ______________________________ ______ ______ ______ ______ _________

Chapter No. 15 988/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ______________________________ ______ ______ ______ ______ _________

S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

1. Excavation of well in dry upto 20' below ground level and


disposal of soil within one chain.
(b) In hard soil.
(iii) From 10.1' to 15' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 4.00 Nos: 250.00 P.day. 1000.00
Coolies for lifting. 6.34 Nos: 250.00 P.day. 1585.00
______________________________ ______ ______ ______ ______ _________
Rs: 2585.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 258.50
______________________________ ______ ______ ______ ______ _________
TOTAL 2843.50
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 284.35
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 3127.85
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 3127.85

Chapter No. 15 989/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

1. Excavation of well in dry upto 20' below ground level and


disposal of soil within one chain.
(b) In hard soil.
(iv) From 15.1' to 20' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 4.00 Nos: 250.00 P.day. 1000.00
Coolies for lifting. 7.63 Nos: 250.00 P.day. 1907.50
______________________________ ______ ______ ______ ______ _________
Rs: 2907.50
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 290.75
______________________________ ______ ______ ______ ______ _________
TOTAL 3198.25
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 319.83
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 3518.08
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 3518.08
____ ______________________________ ______ ______ ______ ______ _________

Chapter No. 15 990/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.
1. Excavation of well in dry upto 20' below ground level and
disposal of soil within one chain.
(c) In hard strata such as shingle or gravel etc.
(i) From 0' to 5' depth.
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 4.00 Nos: 250.00 P.day. 1000.00
Coolies for lifting. 15.52 Nos: 250.00 P.day. 3880.00
______________________________ ______ ______ ______ ______ _________
Rs: 4880.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 488.00
______________________________ ______ ______ ______ ______ _________
TOTAL 5368.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 536.80
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 5904.80
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 5904.80
____ ______________________________ ______ ______ ______ ______ _________
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

1. Excavation of well in dry upto 20' below ground level and


disposal of soil within one chain.
(c) In hard strata such as shingle or gravel etc.
(ii) From 5.1' to 10' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 4.00 Nos: 250.00 P.day. 1000.00
Coolies for lifting. 16.22 Nos: 250.00 P.day. 4055.00
______________________________ ______ ______ ______ ______ _________
Rs: 5055.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 505.50
______________________________ ______ ______ ______ ______ _________
TOTAL 5560.50
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 556.05
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 6116.55
______________________________ ______ ______ ______ ______ _________

Chapter No. 15 991/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total labour rate per %0 Cft. Rs: 6116.55

Chapter No. 15 992/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

1. Excavation of well in dry upto 20' below ground level and


disposal of soil within one chain.
(c) In hard strata such as shingle or gravel etc.
(iii) From 10.1' to 15' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 4.00 Nos: 250.00 P.day. 1000.00
Coolies for lifting. 17.08 Nos: 250.00 P.day. 4270.00
______________________________ ______ ______ ______ ______ _________
Rs: 5270.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 527.00
______________________________ ______ ______ ______ ______ _________
TOTAL 5797.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 579.70
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 6376.70
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 6376.70

Chapter No. 15 993/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

1. Excavation of well in dry upto 20' below ground level and


disposal of soil within one chain.
(c) In hard strata such as shingle or gravel etc.
(iv) From 15.1' to 20' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 4.00 Nos: 250.00 P.day. 1000.00
Coolies for lifting. 18.63 Nos: 250.00 P.day. 4657.50
______________________________ ______ ______ ______ ______ _________
Rs: 5657.50
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 565.75
______________________________ ______ ______ ______ ______ _________
TOTAL 6223.25
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 622.33
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 6845.58
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 6845.58

Chapter No. 15 994/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ______________________________ ______ ______ ______ ______ _________


S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.
2. Dry sinking of well including loading and removing excavated
material.
(a) In ordinary soil.
(i) From 10' to 15' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 10.00 Nos: 250.00 P.day. 2500.00
Coolies for lifting. 30.00 Nos: 250.00 P.day. 7500.00
______________________________ ______ ______ ______ ______ _________
Rs: 10000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 1000.00
______________________________ ______ ______ ______ ______ _________
TOTAL 11000.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 1100.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 12100.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 12100.00
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

2. Dry sinking of well including loading and removing excavated


material.
(a) In ordinary soil.
(ii) From 15.1' to 20' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 10.00 Nos: 250.00 P.day. 2500.00
Coolies for lifting. 40.00 Nos: 250.00 P.day. 10000.00
______________________________ ______ ______ ______ ______ _________
Rs: 12500.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 1250.00
______________________________ ______ ______ ______ ______ _________
TOTAL 13750.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 1375.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 15125.00

Chapter No. 15 995/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ______ _________


Total labour rate per %0 Cft. Rs: 15125.00
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

2. Dry sinking of well including loading and removing excavated


material.
(a) In ordinary soil.
(iii) From 20.1' to 25' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 10.00 Nos: 250.00 P.day. 2500.00
Coolies for lifting. 50.00 Nos: 250.00 P.day. 12500.00
______________________________ ______ ______ ______ ______ _________
Rs: 15000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 1500.00
______________________________ ______ ______ ______ ______ _________
TOTAL 16500.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 1650.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 18150.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 18150.00
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.
2. Dry sinking of well including loading and removing excavated
material.
(a) In ordinary soil.
(iv) From 25.1' to 30' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 10.00 Nos: 250.00 P.day. 2500.00
Coolies for lifting. 60.00 Nos: 250.00 P.day. 15000.00
______________________________ ______ ______ ______ ______ _________
Rs: 17500.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 1750.00
______________________________ ______ ______ ______ ______ _________
TOTAL 19250.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 1925.00
______________________________ ______ ______ ______ ______ _________

Chapter No. 15 996/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (LABOUR) 21175.00


______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 21175.00
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.
2. Dry sinking of well including loading and removing excavated
material.
(a) In ordinary soil.
(v) From 30.1' to 35' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 10.00 Nos: 250.00 P.day. 2500.00
Coolies for lifting. 70.00 Nos: 250.00 P.day. 17500.00
______________________________ ______ ______ ______ ______ _________
Rs: 20000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 2000.00
______________________________ ______ ______ ______ ______ _________
TOTAL 22000.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 2200.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 24200.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 24200.00
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

2. Dry sinking of well including loading and removing excavated


material.
(a) In ordinary soil.
(vi) From 35.1' to 40' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 10.00 Nos: 250.00 P.day. 2500.00
Coolies for lifting. 80.00 Nos: 250.00 P.day. 20000.00
______________________________ ______ ______ ______ ______ _________
Rs: 22500.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 2250.00
______________________________ ______ ______ ______ ______ _________
TOTAL 24750.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 2475.00

Chapter No. 15 997/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ______ _________


TOTAL (LABOUR) 27225.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 27225.00
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

2. Dry sinking of well including loading and removing excavated


material.
(a) In ordinary soil.
(vii) From 40.1' to 45' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 10.00 Nos: 250.00 P.day. 2500.00
Coolies for lifting. 90.00 Nos: 250.00 P.day. 22500.00
______________________________ ______ ______ ______ ______ _________
Rs: 25000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 2500.00
______________________________ ______ ______ ______ ______ _________
TOTAL 27500.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 2750.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 30250.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 30250.00
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

2. Dry sinking of well including loading and removing excavated


material.
(a) In ordinary soil.
(viii) From 45.1' to any depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 10.00 Nos: 250.00 P.day. 2500.00
Coolies for lifting. 100.00 Nos: 250.00 P.day. 25000.00
______________________________ ______ ______ ______ ______ _________
Rs: 27500.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 2750.00
______________________________ ______ ______ ______ ______ _________
TOTAL 30250.00

Chapter No. 15 998/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ______ _________


Contractor's profit 10.00 % 3025.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 33275.00
Total labour rate per %0 Cft. Rs: 33275.00
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.
2. Dry sinking of well including loading and removing excavated
material.
(b) In hard soil.
(i) From 10' to 15' depth.
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 25.00 Nos: 250.00 P.day. 6250.00
Coolies for lifting. 30.00 Nos: 250.00 P.day. 7500.00
______________________________ ______ ______ ______ ______ _________
Rs: 13750.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 1375.00
______________________________ ______ ______ ______ ______ _________
TOTAL 15125.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 1512.50
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 16637.50
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 16637.50
____ ______________________________ ______ ______ ______ ______ _________
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

2. Dry sinking of well including loading and removing excavated


material.
(b) In hard soil.
(ii) From 15.1' to 20' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 25.00 Nos: 250.00 P.day. 6250.00
Coolies for lifting. 40.00 Nos: 250.00 P.day. 10000.00
______________________________ ______ ______ ______ ______ _________
Rs: 16250.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 1625.00
______________________________ ______ ______ ______ ______ _________
TOTAL 17875.00

Chapter No. 15 999/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ______ _________


Contractor's profit 10.00 % 1787.50
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 19662.50
Total labour rate per %0 Cft. Rs: 19662.50
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.
2. Dry sinking of well including loading and removing excavated
material.
(b) In hard soil.
(iii) From 20.1' to 25' depth.
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 25.00 Nos: 250.00 P.day. 6250.00
Coolies for lifting. 50.00 Nos: 250.00 P.day. 12500.00
______________________________ ______ ______ ______ ______ _________
Rs: 18750.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 1875.00
______________________________ ______ ______ ______ ______ _________
TOTAL 20625.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 2062.50
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 22687.50
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 22687.50
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.
2. Dry sinking of well including loading and removing excavated
material.
(b) In hard soil.
(iv) From 25.1' to 30' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 25.00 Nos: 250.00 P.day. 6250.00
Coolies for lifting. 60.00 Nos: 250.00 P.day. 15000.00
______________________________ ______ ______ ______ ______ _________
Rs: 21250.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 2125.00
______________________________ ______ ______ ______ ______ _________
TOTAL 23375.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 2337.50

Chapter No. 15 1000/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ______ _________


TOTAL (LABOUR) 25712.50
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 25712.50
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.
2. Dry sinking of well including loading and removing excavated
material.
(b) In hard soil.
(v) From 30.1' to 35' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 25.00 Nos: 250.00 P.day. 6250.00
Coolies for lifting. 70.00 Nos: 250.00 P.day. 17500.00
______________________________ ______ ______ ______ ______ _________
Rs: 23750.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 2375.00
______________________________ ______ ______ ______ ______ _________
TOTAL 26125.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 2612.50
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 28737.50
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 28737.50
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

2. Dry sinking of well including loading and removing excavated


material.
(b) In hard soil.
(vi) From 35.1' to 40' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 25.00 Nos: 250.00 P.day. 6250.00
Coolies for lifting. 80.00 Nos: 250.00 P.day. 20000.00
______________________________ ______ ______ ______ ______ _________
Rs: 26250.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 2625.00
______________________________ ______ ______ ______ ______ _________
TOTAL 28875.00
______________________________ ______ ______ ______ ______ _________

Chapter No. 15 1001/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 2887.50


______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 31762.50
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 31762.50
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.
2. Dry sinking of well including loading and removing excavated
material.
(b) In hard soil.
(vii) From 40.1' to 45' depth.
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 25.00 Nos: 250.00 P.day. 6250.00
Coolies for lifting. 90.00 Nos: 250.00 P.day. 22500.00
______________________________ ______ ______ ______ ______ _________
Rs: 28750.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 2875.00
______________________________ ______ ______ ______ ______ _________
TOTAL 31625.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 3162.50
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 34787.50
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 34787.50
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

2. Dry sinking of well including loading and removing excavated


material.
(b) In hard soil.
(viii) From 45.1' to any depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 25.00 Nos: 250.00 P.day. 6250.00
Coolies for lifting. 100.00 Nos: 250.00 P.day. 25000.00
______________________________ ______ ______ ______ ______ _________
Rs: 31250.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 3125.00
______________________________ ______ ______ ______ ______ _________
TOTAL 34375.00
______________________________ ______ ______ ______ ______ _________

Chapter No. 15 1002/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 3437.50


______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 37812.50
Total labour rate per %0 Cft. Rs: 37812.50
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.
2. Dry sinking of well including loading and removing excavated
material.
(c) In hard strata such as shingle gravel etc.
(i) From 10' to 15' depth.
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 40.00 Nos: 250.00 P.day. 10000.00
Coolies for lifting. 35.00 Nos: 250.00 P.day. 8750.00
______________________________ ______ ______ ______ ______ _________
Rs: 18750.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 1875.00
______________________________ ______ ______ ______ ______ _________
TOTAL 20625.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 2062.50
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 22687.50
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 22687.50
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

2. Dry sinking of well including loading and removing excavated


material.
(c) In hard strata such as shingle gravel etc.
(ii) From 15.1' to 20' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 40.00 Nos: 250.00 P.day. 10000.00
Coolies for lifting. 45.00 Nos: 250.00 P.day. 11250.00
______________________________ ______ ______ ______ ______ _________
Rs: 21250.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 2125.00
______________________________ ______ ______ ______ ______ _________
TOTAL 23375.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 2337.50

Chapter No. 15 1003/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ______ _________


TOTAL (LABOUR) 25712.50
Total labour rate per %0 Cft. Rs: 25712.50
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

2. Dry sinking of well including loading and removing excavated


material.
(c) In hard strata such as shingle gravel etc.
(iii) From 20.1' to 25' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 40.00 Nos: 250.00 P.day. 10000.00
Coolies for lifting. 55.00 Nos: 250.00 P.day. 13750.00
______________________________ ______ ______ ______ ______ _________
Rs: 23750.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 2375.00
______________________________ ______ ______ ______ ______ _________
TOTAL 26125.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 2612.50
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 28737.50
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 28737.50
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

2. Dry sinking of well including loading and removing excavated


material.
(c) In hard strata such as shingle gravel etc.
(iv) From 25.1' to 30' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 40.00 Nos: 250.00 P.day. 10000.00
Coolies for lifting. 65.00 Nos: 250.00 P.day. 16250.00
______________________________ ______ ______ ______ ______ _________
Rs: 26250.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 2625.00
______________________________ ______ ______ ______ ______ _________
TOTAL 28875.00
______________________________ ______ ______ ______ ______ _________

Chapter No. 15 1004/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 2887.50


______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 31762.50
Total labour rate per %0 Cft. Rs: 31762.50
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.
2. Dry sinking of well including loading and removing excavated
material.
(c) In hard strata such as shingle gravel etc.
(v) From 30.1' to 35' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 40.00 Nos: 250.00 P.day. 10000.00
Coolies for lifting. 75.00 Nos: 250.00 P.day. 18750.00
______________________________ ______ ______ ______ ______ _________
Rs: 28750.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 2875.00
______________________________ ______ ______ ______ ______ _________
TOTAL 31625.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 3162.50
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 34787.50
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 34787.50
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.

2. Dry sinking of well including loading and removing excavated


material.
(c) In hard strata such as shingle gravel etc.
(vi) From 35.1' to 40' depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 40.00 Nos: 250.00 P.day. 10000.00
Coolies for lifting. 85.00 Nos: 250.00 P.day. 21250.00
______________________________ ______ ______ ______ ______ _________
Rs: 31250.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 3125.00
______________________________ ______ ______ ______ ______ _________
TOTAL 34375.00
______________________________ ______ ______ ______ ______ _________

Chapter No. 15 1005/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 3437.50


______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 37812.50
Total labour rate per %0 Cft. Rs: 37812.50
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.
2. Dry sinking of well including loading and removing excavated
material.
(c) In hard strata such as shingle gravel etc.
(vii) From 40.1' to 45' depth.
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 40.00 Nos: 250.00 P.day. 10000.00
Coolies for lifting. 95.00 Nos: 250.00 P.day. 23750.00
______________________________ ______ ______ ______ ______ _________
Rs: 33750.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 3375.00
______________________________ ______ ______ ______ ______ _________
TOTAL 37125.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 3712.50
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 40837.50
______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 40837.50
S/N S I N K I N G O F W E L L S-16
===================================
D E S C R I P T I O N.
2. Dry sinking of well including loading and removing excavated
material.
(c) In hard strata such as shingle gravel etc.
(viii) From 45.1' to any depth.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Coolies for digging. 40.00 Nos: 250.00 P.day. 10000.00
Coolies for lifting. 105.00 Nos: 250.00 P.day. 26250.00
______________________________ ______ ______ ______ ______ _________
Rs: 36250.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 3625.00
______________________________ ______ ______ ______ ______ _________
TOTAL 39875.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 3987.50
______________________________ ______ ______ ______ ______ _________

Chapter No. 15 1006/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (LABOUR) 43862.50


______________________________ ______ ______ ______ ______ _________
Total labour rate per %0 Cft. Rs: 43862.50

S/N D E S C R I P T I O N.
3. Wet sinking of wells for depth below spring level by means of
divers including all charges for shoring loading and removing
excavated material with in one chain.
(a) In ordinary soil or sand.
(i) From 0' to 5' depth.
Assume for 180 Cft.
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 5.00 Nos: 250.00 P.day. 1250.00
Rs: 1750.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 175.00
______________________________ ______ ______ ______ ______ _________
TOTAL 1925.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 192.50
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2117.50
______________________________ ______ ______ ______ ______ _________
Total labour rate per 180 Cft. Rs: 2117.50
Total labour rate per 1000 Cft. Rs: 11763.89
Total labour rate per %0 Cft. say Rs: 11763.89
S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(a) In ordinary soil or sand.
(ii) From 5.1' to 10' depth.
Assume for 100 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________
Rs: 2000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 200.00
______________________________ ______ ______ ______ ______ _________
TOTAL 2200.00
______________________________ ______ ______ ______ ______ _________

Chapter No. 15 1007/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 220.00


______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2420.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 100 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 24200.00
Total labour rate per %0 Cft. say Rs: 24200.00
____ ______________________________ ______ ______ ______ ______ _________
S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(a) In ordinary soil or sand.
(iii) From 10.1' to 15' depth.
Assume for 65 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________
Rs: 2000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 200.00
______________________________ ______ ______ ______ ______ _________
TOTAL 2200.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 220.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2420.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 65 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 37230.77
Total labour rate per %0 Cft. say Rs: 37230.77

Chapter No. 15 1008/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ______________________________ ______ ______ ______ ______ _________

____ ______________________________ ______ ______ ______ ______ _________


S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(a) In ordinary soil or sand.
(iv) From 15.1' to 20' depth.
Assume for 48 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________
Rs: 2000.00
Sundries. 10.00 % 200.00
______________________________ ______ ______ ______ ______ _________
TOTAL 2200.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 220.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2420.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 48 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 50416.67
Total labour rate per %0 Cft. say Rs: 50416.67

Chapter No. 15 1009/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ______________________________ ______ ______ ______ ______ _________


S/N D E S C R I P T I O N.
3. Wet sinking of wells for depth below spring level by means of
divers including all charges for shoring loading and removing
excavated material with in one chain.
(a) In ordinary soil or sand.
(v) From 20.1' to 25' depth.
Assume for 36.50 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________
Rs: 2000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 200.00
______________________________ ______ ______ ______ ______ _________
TOTAL 2200.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 220.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2420.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 36.50 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 66301.37
Total labour rate per %0 Cft. say Rs: 66301.37

____ ______________________________ ______ ______ ______ ______ _________


____ ______________________________ ______ ______ ______ ______ _________
S/N D E S C R I P T I O N.

Chapter No. 15 1010/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(a) In ordinary soil or sand.
(vi) From 25.1' to 30' depth.
Assume for 28.50 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________
Rs: 2000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 200.00
TOTAL 2200.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 220.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2420.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 28.50 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 84912.28
Total labour rate per %0 Cft. say Rs: 84912.28

____ ______________________________ ______ ______ ______ ______ _________


S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.

Chapter No. 15 1011/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(a) In ordinary soil or sand.


(vii) From 30.1' to 35' depth.
Assume for 23.50 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________
Rs: 2000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 200.00
______________________________ ______ ______ ______ ______ _________
TOTAL 2200.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 220.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2420.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 23.50 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 102978.72
Total labour rate per %0 Cft. say Rs: 102978.72

____ ______________________________ ______ ______ ______ ______ _________


____ ______________________________ ______ ______ ______ ______ _________
S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(a) In ordinary soil or sand.
(viii) From 35.1' to 40' depth.

Chapter No. 15 1012/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Assume for 19.0 Cft.


______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________
Rs: 2000.00
Sundries. 10.00 % 200.00
______________________________ ______ ______ ______ ______ _________
TOTAL 2200.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 220.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2420.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 19.0 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 127368.42
Total labour rate per %0 Cft. say Rs: 127368.42

____ ______________________________ ______ ______ ______ ______ _________


S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(a) In ordinary soil or sand.
(ix) From 40.1' to 45' depth.
Assume for 16.0 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:

Chapter No. 15 1013/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ ______ _________


Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________
Rs: 2000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 200.00
______________________________ ______ ______ ______ ______ _________
TOTAL 2200.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 220.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2420.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 16.0 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 151250.00
Total labour rate per %0 Cft. say Rs: 151250.00

____ ______________________________ ______ ______ ______ ______ _________

____ ______________________________ ______ ______ ______ ______ _________


S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(a) In ordinary soil or sand.
(x) From 45.1' to any depth.
Assume for 13.30 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________

Chapter No. 15 1014/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Rs: 2000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 200.00
______________________________ ______ ______ ______ ______ _________
TOTAL 2200.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 220.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2420.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 13.30 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 181954.89
Total labour rate per %0 Cft. say Rs: 181954.89

S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(b) In hard soil.
(i) From 0' to 5' depth.
Assume for 140 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 5.00 Nos: 250.00 P.day. 1250.00
______________________________ ______ ______ ______ ______ _________
Rs: 1750.00
______________________________ ______ ______ ______ ______ _________

Chapter No. 15 1015/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Sundries. %
10.00 175.00
______________________________ ______ ______ ______ ______ _________
TOTAL 1925.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 192.50
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2117.50
______________________________ ______ ______ ______ ______ _________
Total labour rate per 140 Cft. Rs: 2117.50
Total labour rate per 1000 Cft. Rs: 15125.00
Total labour rate per %0 Cft. say Rs: 15125.00

____ ______________________________ ______ ______ ______ ______ _________


____ ______________________________ ______ ______ ______ ______ _________
S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(b) In hard soil.
(ii) From 5.1' to 10' depth.
Assume for 80 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________
Rs: 2000.00
Sundries. 10.00 % 200.00
______________________________ ______ ______ ______ ______ _________
TOTAL 2200.00
______________________________ ______ ______ ______ ______ _________

Chapter No. 15 1016/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 220.00


______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2420.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 80 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 30250.00
Total labour rate per %0 Cft. say Rs: 30250.00

S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(b) In hard soil.
(iii) From 10.1' to 15' depth.
Assume for 53 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________
Rs: 2000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 200.00
______________________________ ______ ______ ______ ______ _________
TOTAL 2200.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 220.00
______________________________ ______ ______ ______ ______ _________

Chapter No. 15 1017/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (LABOUR) 2420.00


______________________________ ______ ______ ______ ______ _________
Total labour rate per 53 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 45660.38
Total labour rate per %0 Cft. say Rs: 45660.38

____ ______________________________ ______ ______ ______ ______ _________

____ ______________________________ ______ ______ ______ ______ _________


S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(b) In hard soil.
(iv) From 15.1' to 20' depth.
Assume for 40 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________
Rs: 2000.00
Sundries. 10.00 % 200.00
______________________________ ______ ______ ______ ______ _________
TOTAL 2200.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 220.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2420.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 40 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 60500.00

Chapter No. 15 1018/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total labour rate per %0 Cft. say Rs: 60500.00

____ ______________________________ ______ ______ ______ ______ _________


S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(b) In hard soil.
(v) From 20.1' to 25' depth.
Assume for 29.0 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________
Rs: 2000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 200.00
______________________________ ______ ______ ______ ______ _________
TOTAL 2200.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 220.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2420.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 29.0 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 83448.28
Total labour rate per %0 Cft. say Rs: 83448.28

Chapter No. 15 1019/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ______________________________ ______ ______ ______ ______ _________


____ ______________________________ ______ ______ ______ ______ _________
S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(b) In hard soil.
(vi) From 25.1' to 30' depth.
Assume for 25.0 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________
Rs: 2000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 200.00
TOTAL 2200.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 220.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2420.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 25.0 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 96800.00
Total labour rate per %0 Cft. say Rs: 96800.00

Chapter No. 15 1020/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ______________________________ ______ ______ ______ ______ _________


S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(b) In hard soil.
(vii) From 30.1' to 35' depth.
Assume for 18.75 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________
Rs: 2000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 200.00
______________________________ ______ ______ ______ ______ _________
TOTAL 2200.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 220.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2420.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 18.75 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 129066.67
Total labour rate per %0 Cft. say Rs: 129066.67

Chapter No. 15 1021/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(b) In hard soil.
(viii) From 35.1' to 40' depth.
Assume for 15.20 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________
Rs: 2000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 200.00
______________________________ ______ ______ ______ ______ _________
TOTAL 2200.00
Contractor's profit 10.00 % 220.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2420.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 15.50 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 156129.03
Total labour rate per %0 Cft. say Rs: 156129.03

Chapter No. 15 1022/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(b) In hard soil.
(ix) From 40.1' to 45' depth.
Assume for 12.80 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________
Rs: 2000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 200.00
______________________________ ______ ______ ______ ______ _________
TOTAL 2200.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 220.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2420.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 12.80 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 189062.50
Total labour rate per %0 Cft. say Rs: 189062.50

Chapter No. 15 1023/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(b) In hard soil.
(x) From 45.1' to any depth.
Assume for 10.70 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 2.00 Nos: 250.00 P.day. 500.00
Coolies for lifting. 6.00 Nos: 250.00 P.day. 1500.00
______________________________ ______ ______ ______ ______ _________
Rs: 2000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 200.00
______________________________ ______ ______ ______ ______ _________
TOTAL 2200.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 220.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 2420.00
Total labour rate per 10.70 Cft. Rs: 2420.00
Total labour rate per 1000 Cft. Rs: 226168.22
Total labour rate per %0 Cft. say Rs: 226168.22

Chapter No. 15 1024/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(c) In hard strata such as shingle or gravel etc.
(i) From 0' to 5' depth.
Assume for 125 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 4.00 Nos: 250.00 P.day. 1000.00
Coolies for lifting. 8.00 Nos: 250.00 P.day. 2000.00
______________________________ ______ ______ ______ ______ _________
Rs: 3000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 300.00
______________________________ ______ ______ ______ ______ _________
TOTAL 3300.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 330.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 3630.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 125 Cft. Rs: 3630.00
Total labour rate per 1000 Cft. Rs: 29040.00
Total labour rate per %0 Cft. say Rs: 29040.00

____ ______________________________ ______ ______ ______ ______ _________

____ ______________________________ ______ ______ ______ ______ _________

Chapter No. 15 1025/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
3. Wet sinking of wells for depth below spring level by means of
divers including all charges for shoring loading and removing
excavated material with in one chain.
(c) In hard strata such as shingle or gravel etc.
(ii) From 5.1' to 10' depth.
Assume for 52.50 Cft.
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 4.00 Nos: 250.00 P.day. 1000.00
Coolies for lifting. 8.00 Nos: 250.00 P.day. 2000.00
______________________________ ______ ______ ______ ______ _________
Rs: 3000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 300.00
______________________________ ______ ______ ______ ______ _________
TOTAL 3300.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 330.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 3630.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 52.50 Cft. Rs: 3630.00
Total labour rate per 1000 Cft. Rs: 69142.86
Total labour rate per %0 Cft. say Rs: 69142.86

____ ______________________________ ______ ______ ______ ______ _________


S/N D E S C R I P T I O N.

Chapter No. 15 1026/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(c) In hard strata such as shingle or gravel etc.
(iii) From 10.1' to 15' depth.
Assume for 38.50 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 4.00 Nos: 250.00 P.day. 1000.00
Coolies for lifting. 8.00 Nos: 250.00 P.day. 2000.00
______________________________ ______ ______ ______ ______ _________
Rs: 3000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 300.00
______________________________ ______ ______ ______ ______ _________
TOTAL 3300.00
______________________________ ______ ______ ______ ______ _________
Contractor's profit 10.00 % 330.00
______________________________ ______ ______ ______ ______ _________
TOTAL (LABOUR) 3630.00
______________________________ ______ ______ ______ ______ _________
Total labour rate per 38.50 Cft. Rs: 3630.00
Total labour rate per 1000 Cft. Rs: 94285.71
Total labour rate per %0 Cft. say Rs: 94285.71

S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(c) In hard strata such as shingle or gravel etc.

Chapter No. 15 1027/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(iv) From 15.1' to 20' depth.


Assume for 27.80 Cft.
______________________________ ______ ______ ______ ______ _________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ______ ______ ______ _________
Divers.(Skilled Cooly) 4.00 Nos: 250.00 P.day. 1000.00
Coolies for lifting. 8.00 Nos: 250.00 P.day. 2000.00
______________________________ ______ ______ ______ ______ _________
Rs: 3000.00
______________________________ ______ ______ ______ ______ _________
Sundries. 10.00 % 300.00
TOTAL 3300.00
______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 330.00
______________________________ ______ ______ ______ _________
TOTAL (LABOUR) ______ 3630.00
______________________________ ______ ______ ______ _________
Total labour rate per 27.80 Cft. Rs: 3630.00
Total labour rate per 1000 Cft. Rs: 130575.54
Total labour rate per %0 Cft. ______ say Rs: 130575.54

S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(c) In hard strata such as shingle or gravel etc.
(v) From 20.1' to 25' depth.
Assume for18.50 Cft. ______
______________________________ QUANTI______ ______ ______ _________

Chapter No. 15 1028/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(B) LABOUR RATE UNIT AMOUNT


______ Rs: Rs:
______________________________ 4.00 ______ ______ ______ _________
Divers.(Skilled Cooly) 8.00 Nos: 250.00 P.day. 1000.00
Coolies for lifting. ______ Nos: 250.00 P.day. 2000.00
______________________________ ______ ______ ______ _________
______ Rs: 3000.00
______________________________ ______ ______ ______ _________
Sundries. ______ 10.00 % 300.00
______________________________ ______ ______ ______ _________
TOTAL ______ 3300.00
______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 330.00
______________________________ ______ ______ ______ _________
TOTAL (LABOUR) ______ 3630.00
______________________________ ______ ______ ______ _________
Total labour rate per 18.50 Cft. Rs: 3630.00
Total labour rate per 1000 Cft. Rs: 196216.22
Total labour rate per %0 Cft. ______ say Rs: 196216.22

S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(c) In hard strata such as shingle or gravel etc.
(vi) From 25.1' to 30' depth.
Assume for 14.30 Cft. ______
______________________________ QUANTI______ ______ ______ _________
(B) LABOUR RATE UNIT AMOUNT
______ Rs: Rs:
______________________________ 4.00 ______ ______ ______ _________

Chapter No. 15 1029/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Divers.(Skilled Cooly) 8.00 Nos: 250.00 P.day. 1000.00


Coolies for lifting. ______ Nos: 250.00 P.day. 2000.00
______________________________ ______ ______ ______ _________
______ Rs: 3000.00
Sundries. ______ 10.00 % 300.00
______________________________ ______ ______ ______ _________
TOTAL ______ 3300.00
______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 330.00
______________________________ ______ ______ ______ _________
TOTAL (LABOUR) ______ 3630.00
______________________________ ______ ______ ______ _________
Total labour rate per 14.30 Cft. Rs: 3630.00
Total labour rate per 1000 Cft. Rs: 253846.15
Total labour rate per %0 Cft. ______ say Rs: 253846.15

____ ______________________________ ______ ______ ______ _________


S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(c) In hard strata such as shingle or gravel etc.
(vii) From 30.1' to 35' depth.
Assume for 11.40 Cft. ______
______________________________ QUANTI______ ______ ______ _________
(B) LABOUR RATE UNIT AMOUNT
______ Rs: Rs:
______________________________ 4.00 ______ ______ ______ _________
Divers.(Skilled Cooly) 8.00 Nos: 250.00 P.day. 1000.00
Coolies for lifting. ______ Nos: 250.00 P.day. 2000.00
______________________________ ______ ______ ______ _________

Chapter No. 15 1030/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______ Rs: 3000.00


______________________________ ______ ______ ______ _________
Sundries. ______ 10.00 % 300.00
______________________________ ______ ______ ______ _________
TOTAL ______ 3300.00
______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 330.00
______________________________ ______ ______ ______ _________
TOTAL (LABOUR) ______ 3630.00
______________________________ ______ ______ ______ _________
Total labour rate per 11.40 Cft. Rs: 3630.00
Total labour rate per 1000 Cft. Rs: 318421.05
Total labour rate per %0 Cft. ______ say Rs: 318421.05

____ ______________________________ ______ ______ ______ ______ _________


____ ______________________________ ______ ______ ______ _________
S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(c) In hard strata such as shingle or gravel etc.
(viii) From 35.1' to 40' depth.
Assume for 8.80 Cft. ______
(B) LABOUR RATE UNIT AMOUNT
______ Rs: Rs:
______________________________ 4.00 ______ ______ ______ _________
Divers.(Skilled Cooly) 8.00 Nos: 250.00 P.day. 1000.00
Coolies for lifting. ______ Nos: 250.00 P.day. 2000.00
______________________________ ______ ______ ______ _________
______ Rs: 3000.00
______________________________ ______ ______ ______ _________
Sundries. ______ 10.00 % 300.00
______________________________ ______ ______ ______ _________

Chapter No. 15 1031/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL ______ 3300.00


______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 330.00
______________________________ ______ ______ ______ _________
TOTAL (LABOUR) ______ 3630.00
______________________________ ______ ______ ______ _________
Total labour rate per 8.80 Cft. Rs: 3630.00
Total labour rate per 1000 Cft. Rs: 412500.0
Total labour rate per %0 Cft. ______ say Rs: 412500.0

S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(c) In hard strata such as shingle or gravel etc.
(ix) From 40.1' to 45' depth.
Assume for 7.0 Cft. ______
______________________________ QUANTI______ ______ ______ _________
(B) LABOUR RATE UNIT AMOUNT
______ Rs: Rs:
______________________________ 4.00 ______ ______ ______ _________
Divers.(Skilled Cooly) 8.00 Nos: 250.00 P.day. 1000.00
Coolies for lifting. ______ Nos: 250.00 P.day. 2000.00
______________________________ ______ ______ ______ _________
______ Rs: 3000.00
______________________________ ______ ______ ______ _________
Sundries. ______ 10.00 % 300.00
______________________________ ______ ______ ______ _________
TOTAL ______ 3300.00
______________________________ ______ ______ ______ _________

Chapter No. 15 1032/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit ______ 10.00 % 330.00


______________________________ ______ ______ ______ _________
TOTAL (LABOUR) ______ 3630.00
______________________________ ______ ______ ______ _________
Total labour rate per 7.0 Cft. Rs: 3630.00
Total labour rate per 1000 Cft. Rs: 518571.4
Total labour rate per %0 Cft. ______ say Rs: 518571.4

____ ______________________________ ______ ______ ______ ______ _________


S/N D E S C R I P T I O N.

3. Wet sinking of wells for depth below spring level by means of


divers including all charges for shoring loading and removing
excavated material with in one chain.
(c) In hard strata such as shingle or gravel etc.
(x) From 45.1' to any depth.
Assume for 5.50 Cft. ______
(B) LABOUR RATE UNIT AMOUNT
______ Rs: Rs:
______________________________ 4.00 ______ ______ ______ _________
Divers.(Skilled Cooly) 8.00 Nos: 250.00 P.day. 1000.00
Coolies for lifting. ______ Nos: 250.00 P.day. 2000.00
______________________________ ______ ______ ______ _________
______ Rs: 3000.00
______________________________ ______ ______ ______ _________
Sundries. ______ 10.00 % 300.00
______________________________ ______ ______ ______ _________
TOTAL ______ 3300.00
______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 330.00
______________________________ ______ ______ ______ _________
TOTAL (LABOUR) ______ 3630.00
______________________________ ______ ______ ______ _________

Chapter No. 15 1033/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total labour rate per 5.50 Cft. Rs: 3630.00


Total labour rate per 1000 Cft. Rs: 660000.0
Total labour rate per %0 Cft. ______ say Rs: 660000.0

S/N D E S C R I P T I O N.

4. Wet sinking of well for depth below spring level by means of


mechanical devices including all charges for operation of
machinery pumping, shoring loading and removing spil with in one
chain.
(a) In ordinary soil.
(i) From 0.0' ft. to 5.0' ft.
Assume for 350 Cft. ______
____ ______________________________ QUANTI______ ______ ______ _________
(A) MATERIAL RATE UNIT AMOUNT
______ Rs: Rs:
______________________________ L.S. ______ ______ ______ _________
Maintenance charges. 48.00
3.00
Steam coal. Cwt. 4000.00 P.Ton. 600.00
0.50
Scrap wood. 0.33 Mds: 900.00 P.Maund 450.00
Waste cotton. Lbs. 60.00 P.lb. 20.00
L.S.
Lubericating oil. ______ 42.00
______________________________ ______ ______ ______ _________
TOTAL ______ 1160.00
______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 116.00
______________________________ ______ ______ ______ _________
TOTAL PART " A " ______ 1276.00

Chapter No. 15 1034/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ _________


(B) LABOUR ______
______________________________ 1.00 ______ ______ ______ _________
Fireman. Nos: 450.00 P.day. 450.00
2.00
Divers. Nos: 250.00 P.day. 500.00
4.00
Coolies. Nos: 250.00 P.day. 1000.00

______
______________________________ ______ ______ ______ _________
______ Rs: 1950.00
______________________________ ______ ______ ______ _________
Sundries. ______ 10.00 % 195.00
______________________________ ______ ______ ______ _________
TOTAL ______ 2145.00
______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 214.50
______________________________ ______ ______ ______ _________
TOTAL PART " B " ______ 6741.43 2359.50
______________________________ ______ ______ ______ _________
TOTAL (MATERIAL + LABOUR) ______ 3635.50
______________________________ ______ ______ ______ _________
Total material & labour for 350 Cft. Rs: 3635.50
Total material & labour for 1000 Cft. Rs: 10387.14
Total material & labour for %0 Cft. ______ Rs: 10387.14
(ii) From 5.1' ft. to 10' ft.
Assume for 186 Cft. ______

______________________________ ______ ______ ______ _________


Total material & labour for 186 Cft. Rs: 3635.50
Total material & labour for 1000 Cft. Rs: 19545.70
Total material & labour for %0 Cft. ______ Rs: 19545.70
____ ______________________________ ______ ______ ______ _________
(iii) From 10.1' ft. to 15' ft.
Assume for 127 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 127 Cft. Rs: 3635.50
Total material & labour for 1000 Cft. Rs: 28625.98
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(iv) From 15.1' ft. to 20' ft.
Assume for 96 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 96 Cft. Rs: 3635.50
Total material & labour for 1000 Cft. Rs: 37869.79
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(v) From 20.1' ft. to 25' ft.
Assume for 78 Cft. ______

Chapter No. 15 1035/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ _________


Total material & labour for 78 Cft. Rs: 3635.50
Total material & labour for 1000 Cft. Rs: 46608.97
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(vi) From 25.1' ft. to 30' ft.
Assume for 64 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 64 Cft. Rs: 3635.50
Total material & labour for 1000 Cft. Rs: 56804.69
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(vii) From 30.1' ft. to 35' ft.
Assume for 53 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 53 Cft. Rs: 3635.50
Total material & labour for 1000 Cft. Rs: 68594.34
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(viii) From 35.1' ft. to 40' ft.
Assume for 44.50 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 44.50 Cft. Rs: 3635.50
Total material & labour for 1000 Cft. Rs: 81696.63
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(ix) From 40.1' ft. to 45' ft.
Assume for 37.50 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 37.50 Cft. Rs: 3635.50
Total material & labour for 1000 Cft. Rs: 96946.67
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(x) From 45' ft. to any depth.
Assume for 31 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 31 Cft. Rs: 3635.50
Total material & labour for 1000 Cft. Rs: 117274.19
Total material & labour for %0 Cft. Rs:

Chapter No. 15 1036/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4. Wet sinking of well for depth below spring level by means of


mechanical devices including all charges for operation of
machinery pumping, shoring loading and removing spil with in one
chain.
b In ordinary soil.
(i) From 0.0' ft. to 5.0' ft.
Assume for 350 Cft. ______
____ ______________________________ QUANTI______ ______ ______ _________
(B) LABOUR RATE UNIT AMOUNT
______ Rs: Rs:
______________________________ 1.00 ______ ______ ______ _________
Fireman. Nos: 450.00 P.day. 450.00
2.00
Divers. Nos: 250.00 P.day. 500.00
4.00
Coolies. Nos: 250.00 P.day. 1000.00

______
______________________________ ______ ______ ______ _________
______ Rs: 1950.00
______________________________ ______ ______ ______ _________
Sundries. ______ 10.00 % 195.00
______________________________ ______ ______ ______ _________
TOTAL ______ 2145.00
______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 214.50
______________________________ ______ ______ ______ _________
TOTAL PART " B " ______ 2359.50
______________________________ ______ ______ ______ _________
TOTAL (LABOUR) ______ 2359.50
______________________________ ______ ______ ______ _________
Total labour rate for 350 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 6741.43

Chapter No. 15 1037/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total labour rate for %0 Cft. ______ Rs:


____ ______________________________ ______ ______ ______ _________
____ ______________________________ ______ ______ ______ _________
(ii) From 5.1' ft. to 10' ft.
Assume for 186 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 186 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 12685.48
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(iii) From 10.1' ft. to 15' ft.
Assume for 127 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 127 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 18578.74
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(iv) From 15.1' ft. to 20' ft.
Assume for 96 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 96 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 24578.13
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(v) From 20.1' ft. to 25' ft.
Assume for 78 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 78 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 30250.00
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(vi) From 25.1' ft. to 30' ft.
Assume for 64 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 64 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 36867.19
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(vii) From 30.1' ft. to 35' ft.
Assume for 53 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 53 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 44518.87
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(viii) From 35.1' ft. to 40' ft.
Assume for 44.50 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 44.5 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 53022.47

Chapter No. 15 1038/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total labour rate for %0 Cft. ______ Rs:


____ ______________________________ ______ ______ ______ _________
(ix) From 40.1' ft. to 45' ft.
Assume for 37.50 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 37.5 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 62920.00
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(x) From 45' ft. to any depth.
Assume for 31 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 31.0 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 76112.90
Total labour rate for %0 Cft. Rs:

Chapter No. 15 1039/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4. Wet sinking of well for depth below spring level by means of


mechanical devices including all charges for operation of
machinery pumping, shoring loading and removing spil with in one
chain.
(b) In hard soil.
(i) From 0.0' ft. to 5.0' ft.
Assume for 280 Cft. ______
____ ______________________________ QUANTI______ ______ ______ _________
(A) MATERIAL RATE UNIT AMOUNT
______ Rs: Rs:
______________________________ L.S. ______ ______ ______ _________
Maintenance charges. 48.00
3.00
Steam coal. Cwt. 4000.00 P.Ton. 600.00
0.50
Scrap wood. 0.33 Mds: 900.00 P.Maund 450.00
Waste cotton. Seer 60.00 P.Lb. 1.65
L.S.
Lubericating oil. ______ 48.00
______________________________ ______ ______ ______ _________
TOTAL ______ 1147.65
______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 114.77
______________________________ ______ ______ ______ _________
TOTAL PART " A " ______ 1262.42
______________________________ ______ ______ ______ _________
(B) LABOUR ______
______________________________ 1.00 ______ ______ ______ _________
Fireman. Nos: 450.00 P.day. 450.00
2.00
Divers. Nos: 250.00 P.day. 500.00
4.00
Coolies. Nos: 250.00 P.day. 1000.00

______
______________________________ ______ ______ ______ _________
______ Rs: 1950.00
______________________________ ______ ______ ______ _________
Sundries. ______ 10.00 % 195.00
______________________________ ______ ______ ______ _________
TOTAL ______ 2145.00
______________________________ ______ ______ ______ _________

Chapter No. 15 1040/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit ______ 10.00 % 214.50


______________________________ ______ ______ ______ _________
TOTAL PART " B " ______ 2359.50
______________________________ ______ ______ ______ _________
TOTAL (MATERIAL + LABOUR) ______ 3621.92
______________________________ ______ ______ ______ _________
Total material & labour for 280 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 12935.41
Total material & labour for %0 Cft. ______ Rs: 12935.41
____ ______________________________ ______ ______ ______ _________
(ii) From 5.1' ft. to 10' ft.
Assume for 140 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 140 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 25870.82
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(iii) From 10.1' ft. to 15' ft.
Assume for 93 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 93 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 38945.32
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(iv) From 15.1' ft. to 20' ft.
Assume for 70 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 70 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 51741.64
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(v) From 20.1' ft. to 25' ft.
Assume for 56 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 56 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 64677.05
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(vi) From 25.1' ft. to 30' ft.
Assume for 46.50 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 46.50 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 77890.65
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(vii) From 30.1' ft. to 35' ft.
Assume for 40 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 40 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 90547.88

Chapter No. 15 1041/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for %0 Cft. ______ Rs:


____ ______________________________ ______ ______ ______ _________
(viii) From 35.1' ft. to 40' ft.
Assume for 35.0 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 35.0 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 103483.29
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(ix) From 40.1' ft. to 45' ft.
Assume for 31.0 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 31.0 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 116835.97
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(x) From 45' ft. to any depth.
Assume for 28 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 28 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 129354.11
Total material & labour for %0 Cft. Rs:

Chapter No. 15 1042/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

4. Wet sinking of well for depth below spring level by means of


mechanical devices including all charges for operation of
machinery pumping, shoring loading and removing spil with in one
chain.
(b) In hard soil.
(i) From 0.0' ft. to 5.0' ft.
Assume for 280 Cft. ______
____ ______________________________ QUANTI______ ______ ______ _________
(B) LABOUR RATE UNIT AMOUNT
______ Rs: Rs:
______________________________ 1.00 ______ ______ ______ _________
Fireman. Nos: 450.00 P.day. 450.00
2.00
Divers. Nos: 250.00 P.day. 500.00
4.00
Coolies. Nos: 250.00 P.day. 1000.00

______
______________________________ ______ ______ ______ _________
______ Rs: 1950.00
______________________________ ______ ______ ______ _________
Sundries. ______ 10.00 % 195.00
______________________________ ______ ______ ______ _________
TOTAL ______ 2145.00
______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 214.50
______________________________ ______ ______ ______ _________
TOTAL PART " B " ______ 2359.50
______________________________ ______ ______ ______ _________
TOTAL (MATERIAL + LABOUR) ______ 2359.50
______________________________ ______ ______ ______ _________
Total labour rate for 280 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 8426.79
Total labour rate for %0 Cft. ______ Rs: 8426.79
____ ______________________________ ______ ______ ______ _________
______
____ ______________________________ ______ ______ ______ _________
(ii) From 5.1' ft. to 10' ft.
Assume for 140 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 140 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 16853.57
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(iii) From 10.1' ft. to 15' ft.
Assume for 93 Cft. ______
______________________________ ______ ______ ______ _________

Chapter No. 15 1043/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total labour rate for 93 Cft. Rs: 2359.50


Total labour rate for 1000 Cft. Rs: 25370.97
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(iv) From 15.1' ft. to 20' ft.
Assume for 70 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 70 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 33707.14
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(v) From 20.1' ft. to 25' ft.
Assume for 56 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 56 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 42133.93
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(vi) From 25.1' ft. to 30' ft.
Assume for 46.50 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 46.5 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 50741.94
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(vii) From 30.1' ft. to 35' ft.
Assume for 40 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 40.0 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 58987.50
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(viii) From 35.1' ft. to 40' ft.
Assume for 35.0 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 35.0 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 67414.29
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(ix) From 40.1' ft. to 45' ft.
Assume for 31.0 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 31.0 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 76112.90
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(x) From 45' ft. to any depth.
Assume for 28 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 28.0 Cft. Rs: 2359.50

Chapter No. 15 1044/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total labour rate for 1000 Cft. Rs: 84267.86


Total labour rate for %0 Cft. Rs:

S/N D E S C R I P T I O N.

4. Wet sinking of well for depth below spring level by means of


mechanical devices including all charges for operation of
machinery pumping, shoring loading and removing spil with in one
chain.
(c) In hard strata such as shingle or gravel etc.
(i) From 0.0' ft. to 5.0' ft.
Assume for 140 Cft. ______
____ ______________________________ QUANTI______ ______ ______ _________
(A) MATERIAL RATE UNIT AMOUNT
______ Rs: Rs:
______________________________ L.S. ______ ______ ______ _________
Maintenance charges. 48.00
3.00
Steam coal. Cwt. 4000.00 P.Ton. 600.00
0.50
Scrap wood. 0.33 Mds: 900.00 P.Maund 450.00
Waste cotton. Lbs. 60.00 P.lb. 1.65
L.S.
Lubericating oil. ______ 48.00
______________________________ ______ ______ ______ _________
TOTAL ______ 1147.65
______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 114.77
______________________________ ______ ______ ______ _________
TOTAL PART " A " ______ 1262.42
______________________________ ______ ______ ______ _________
(B) LABOUR ______
______________________________ 1.00 ______ ______ ______ _________
Fireman. Nos: 450.00 P.day. 450.00
2.00
Divers. Nos: 250.00 P.day. 500.00
4.00
Coolies. Nos: 250.00 P.day. 1000.00

______
______________________________ ______ ______ ______ _________
______ Rs: 1950.00
______________________________ ______ ______ ______ _________
Sundries. ______ 10.00 % 195.00
______________________________ ______ ______ ______ _________
TOTAL ______ 2145.00
______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 214.50
______________________________ ______ ______ ______ _________
TOTAL PART " B " ______ 2359.50

Chapter No. 15 1045/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ ______ ______ _________


TOTAL (MATERIAL + LABOUR) ______ 3621.92
______________________________ ______ ______ ______ _________
Total material & labour for 140 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 25870.82
Total material & labour for %0 Cft. ______ Rs: 25870.82
____ ______________________________ ______ ______ ______ _________
______
____ ______________________________ ______ ______ ______ _________
(ii) From 5.1' ft. to 10' ft.
Assume for 70 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 70 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 51741.64
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(iii) From 10.1' ft. to 15' ft.
Assume for 46.5 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 46.5 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 77890.65
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(iv) From 15.1' ft. to 20' ft.
Assume for 35 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 35 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 103483.29
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(v) From 20.1' ft. to 25' ft.
Assume for 25.50 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 25.50 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 142035.88
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(vi) From 25.1' ft. to 30' ft.
Assume for 20.0 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 20.0 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 181095.75
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(vii) From 30.1' ft. to 35' ft.
Assume for 16 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 16 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 226369.69
Total material & labour for %0 Cft. ______ Rs:

Chapter No. 15 1046/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ______________________________ ______ ______ ______ _________


(viii) From 35.1' ft. to 40' ft.
Assume for 13.4 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 35.0 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 270292.16
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(ix) From 40.1' ft. to 45' ft.
Assume for 11.20 Cft. ______
______________________________ ______ ______ ______ _________
Total material & labour for 11.20 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 323385.27
Total material & labour for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(x) From 45' ft. to any depth.
Assume for 9.35 Cft. ______

______________________________ ______ ______ ______ _________


Total material & labour for 9.35 Cft. Rs: 3621.92
Total material & labour for 1000 Cft. Rs: 387370.59
Total material & labour for %0 Cft. Rs:

S/N D E S C R I P T I O N.

Chapter No. 15 1047/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

4. Wet sinking of well for depth below spring level by means of


mechanical devices including all charges for operation of
machinery pumping, shoring loading and removing spil with in one
chain.
(c) In hard strata such as shingle or gravel etc.
(i) From 0.0' ft. to 5.0' ft.
Assume for 140 Cft. ______
____ ______________________________ QUANTI______ ______ ______ _________
(B) LABOUR RATE UNIT AMOUNT
______ Rs: Rs:
______________________________ 1.00 ______ ______ ______ _________
Fireman. Nos: 450.00 P.day. 450.00
2.00
Divers. Nos: 250.00 P.day. 500.00
4.00
Coolies. Nos: 250.00 P.day. 1000.00

______
______________________________ ______ ______ ______ _________
______ Rs: 1950.00
______________________________ ______ ______ ______ _________
Sundries. ______ 10.00 % 195.00
______________________________ ______ ______ ______ _________
TOTAL ______ 2145.00
______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 214.50
______________________________ ______ ______ ______ _________
TOTAL PART " B " ______ 2359.50
______________________________ ______ ______ ______ _________
TOTAL (LABOUR) ______ 2359.50
______________________________ ______ ______ ______ _________
Total labour rate for 140 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 16853.57
Total labour rate for %0 Cft. ______ Rs: 16853.57
____ ______________________________ ______ ______ ______ _________
______
____ ______________________________ ______ ______ ______ _________
(ii) From 5.1' ft. to 10' ft.
Assume for 70 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 70 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 33707.14
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(iii) From 10.1' ft. to 15' ft.
Assume for 46.5 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 46.5 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 50741.94
Total labour rate for %0 Cft. ______ Rs:

Chapter No. 15 1048/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ______________________________ ______ ______ ______ _________


(iv) From 15.1' ft. to 20' ft.
Assume for 35 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 35.0 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 67414.29
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(v) From 20.1' ft. to 25' ft.
Assume for 25.50 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 25.5 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 92529.41
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(vi) From 25.1' ft. to 30' ft.
Assume for 20.0 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 20.0 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 117975.00
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(vii) From 30.1' ft. to 35' ft.
Assume for 16 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 20.0 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 147468.75
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(viii) From 35.1' ft. to 40' ft.
Assume for 13.4 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 13.4 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 176082.09
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(ix) From 40.1' ft. to 45' ft.
Assume for 11.20 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 11.2 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 210669.64
Total labour rate for %0 Cft. ______ Rs:
____ ______________________________ ______ ______ ______ _________
(x) From 45' ft. to any depth.
Assume for 9.35 Cft. ______
______________________________ ______ ______ ______ _________
Total labour rate for 9.35 Cft. Rs: 2359.50
Total labour rate for 1000 Cft. Rs: 252352.94
Total labour rate for %0 Cft. ______ Rs:

Chapter No. 15 1049/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
5. Making and fixing in position Kikar wood well curb.

Assume for 2.36 Cft. ______


____ ______________________________ QUANTI______ ______ ______ _________
(A) MATERIAL RATE UNIT AMOUNT
______ Rs: Rs:
______________________________ ______ ______ ______ _________
Kikar wood = (1* 1-2/3 * 1/3) + [1*(1-2.3 + 1/2)*1-2/3]=2.36 Cft.
M.S. Round bars 3/4" dia = 7*2/112 = 0.125 Cwt.
Angle Iron 6" * 6" *1/2" =1'*10 lbs/ft /1 ______
______________________________ 2.36 ______ ______ ______ _________
Kikar Wood. Cft. 1400.00 P.Cft. 3304.00
0.125
M.S. bars 3/4" dia. Cwt. 3550.00 P.Cwt. 443.75
0.09
Angle iron 6"*6"*1/2" Cwt. 3575.00 P.Cwt. 321.75

TOTAL ______ 4069.50


______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 406.95
______________________________ ______ ______ ______ _________
TOTAL PART " A " ______ 4476.45
______________________________ ______ ______ ______ _________
(B) LABOUR ______
______________________________ 1.00 ______ ______ ______ _________
Carpenter. Nos: 450.00 P.day. 450.00
1.00
Coolies. Nos: 250.00 P.day. 250.00
0.50
Blacksmith Nos: 250.00 P.day. 125.00
0.50
Hammerman. ______ Nos: 450.00 P.day. 225.00
______________________________ ______ ______ ______ _________
______ Rs: 1050.00
______________________________ ______ ______ ______ _________
Sundries. ______ 10.00 % 105.00
______________________________ ______ ______ ______ _________
TOTAL ______ 1155.00
______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 115.50
______________________________ ______ ______ ______ _________
TOTAL PART " B " ______ 538.35 1270.50
______________________________ ______ ______ ______ _________
TOTAL (MATERIAL + LABOUR) ______ 5746.95
______________________________ ______ ______ ______ _________
Total material & labour for 2.36 Cft. Rs: 5746.95
Total material & labour for 1 Cft. Rs: 2435.15
Total material & labour per Cft. ______ say Rs: 2435.15

Chapter No. 15 1050/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

6. Laying well curb in position only.

Assume for 2 well curbs. ______


____ ______________________________ QUANTI______ ______ ______ _________
(B) LABOUR RATE UNIT AMOUNT
______ Rs: Rs:
______________________________ 1.00 ______ ______ ______ _________
Carpenter. Nos: 450.00 P.day. 450.00
______
______________________________ ______ ______ ______ _________
______ Rs: 450.00
______________________________ ______ ______ ______ _________
Sundries. ______ 10.00 % 45.00
______________________________ ______ ______ ______ _________
TOTAL ______ 495.00
______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 49.50
______________________________ ______ ______ ______ _________
TOTAL PART " B " ______ 544.50
______________________________ ______ ______ ______ _________
TOTAL (LABOUR) ______ 544.50
______________________________ ______ ______ ______ _________
Total labour rate for 2 Nos. Rs: 544.50
Total labour rate for 1 No. Rs: 272.25
Total labour rate for each No. ______ say Rs: 272.25

S/N D E S C R I P T I O N.

7. Making R.C.C. Well Curb.

Chapter No. 15 1051/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Assume for 12'*13'*7-1/4' = 94 Cft.


______
____ ______________________________ QUANTI______ ______ ______ _________
(A) MATERIAL RATE UNIT AMOUNT
______ Rs: Rs:
______________________________ 21.15 ______ ______ ______ _________
Cement. 39.50 Cwt. 400.00 P.Cwt. 8460.00
sand. 79.000 Cft. 2425.00 % Cft. 957.88
Shingle. 7.00 Cft. 2500.00 % Cft. 1975.00
Steel. 6.62 Cwt. 1500.00 P.Cwt. 10500.00
Angle iron 6"*6"*1/2" 20.00 Cwt. 3575.00 P.Cwt. 23666.50
Bolts & Nuts. 10.00 Nos. 200.00 P.doz: 333.33
Charcoal. 3.00 Seer. 675.00 P.Maund 168.75
Form work. ______ Cft. 1700.00 P.Cft. 5100.00
______________________________ ______ ______ ______ _________
TOTAL ______ 51161.46
______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 5116.15
______________________________ ______ ______ ______ _________
TOTAL PART " A " ______ 56277.60
______________________________ ______ ______ ______ _________
(B) LABOUR ______
______________________________ 4.00 ______ ______ ______ _________
Mason. 3.00 Nos: 450.00 P.day. 1800.00
Coolies for mixing. 4.00 Nos: 250.00 P.day. 750.00
Coolies for carrying, Nos: 250.00 P.day. 1000.00
placing and ramming. 1.00
Bahishti. 1.00 Nos: 250.00 P.day. 250.00
Carpenter. 1.00 Nos: 450.00 P.day. 450.00
Coolies for carpenter. 6.00 Nos: 250.00 P.day. 250.00
Blacksmith. 4.00 Nos: 450.00 P.day. 2700.00
Coolies for blacksmith. ______ Nos: 250.00 P.day. 1000.00
______________________________ ______ ______ ______ _________
______ Rs: 8200.00
______________________________ ______ ______ ______ _________
Sundries. ______ 10.00 % 820.00
______________________________ ______ ______ ______ _________
TOTAL ______ 9020.00
______________________________ ______ ______ ______ _________
Contractor's profit ______ 10.00 % 902.00
______________________________ ______ ______ ______ _________
TOTAL PART " B " ______ 105.55 9922.00
______________________________ ______ ______ ______ _________
TOTAL (MATERIAL + LABOUR) ______ 66199.60
______________________________ ______ ______ ______ _________
Total material & labour for 94 Cft. Rs: 66199.60
Total material & labour for 1 Cft. Rs: 704.25
Total material & labour per Cft. ______ say Rs: 704.25

Chapter No. 15 1052/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

FIRST FILL THIS SHEET

IRON WORK

MATERIAL RATE UNIT

1 Flate iron Section and Frame, 3375 P.Cwt


Angle Iron

2 Mild Steel , Gratings 3550 P.cwt

3 Char Coal 675 P.Mand

4 Steam Coal 4000 P.Ton

5 Hold fasts Complete 85 Each

6 Rivets and Bolts 110 P.Lb

7 Locking arrangments 200 Each

8 Welding rods 10 each

9 Deodar wood (2nd quality) 4000 P.Cft

10 Stone Bollast 2" gauge 2350 % Cft

11 M.S Sttel Sheet 10 SWG 5000 P.Cwt.

12 Hinges 3" length 150 P.doz

13 Cement 400 P.Cwt

14 Sand 2425 %Cft

15 Flat Iron 71 Kg

16 Square Rod 1/2" x 1/2" 71 Kg

17 Ruvetes 1- 1/2" x 1/4" dia 15.0 Each

18 Pins 5/16" x 1/4" dia 8.0 Each

19 M.S Rollers 8.0 Each

20 G.I Pipe 2" dia 195.00 Rft

21 Side Channal 3"x1-1/2" 3375 P.Cwt

22 Bracket 20 gauge 350 Each

Chapter No. 16 1053/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

23 Spring 1-1/2" 450 Each

24 Pully 150 Each

25 Iron Sheet Cover 3 gauge 4600 P.Cwt

26 Deodar wood (1st quality) 4500 P.Cft

27 Aluminum Expand Matel3/32-20 Gug 43 P.Sft

LABOUR RATE UNIT

1 Black Smith , Fitter, Carpenter, 450 P.day


Riveters , Painter, Welder.

2 Coolies , Below Man 250 P.day

3 Skilled Coolies , Hammerman 250 P.day

S/N D E S C R I P T I O N.
IRON WORK.
1 Small iron work such as gusset plate knees bends, stirrups,
straps, rings, etc, including cutting drilling rivetting,
handling, assembling and fixing but excluding erection in
position.

____ ______________________________ ______ _____ ________ ______ ___________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Iron including 10% wastage. 1.10 Cwt. 3375.00 P.Cwt. 3712.50

Chapter No. 16 1054/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Mild Steel. 1.50 Lbs. 3550.00 P.Cwt. 47.54

Charcoal. 9.00 Seer 675 P.Mand. 151.88

______________________________ ______ _____ ________ ______ ___________


TOTAL 3911.92
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 391.19
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " A " 4303.11
______________________________ ______ _____ ________ ______ ___________
(B) LABOUR
______________________________ ______ _____ ________ ______ ___________
Black-smith. 2.50 Nos: 450.00 P.day. 1125.00

Coolies. 2.50 Nos: 250.00 P.day. 625.00

______________________________ ______ _____ ________ ______ ___________


Rs: 1750.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 175.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 1925.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 192.50
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " B " 2117.50
______________________________ ______ _____ ________ ______ ___________
TOTAL (MATERIAL + LABOUR) 6420.61
______________________________ ______ _____ ________ ______ ___________
Total material & labour for 1 Cwt. Rs: 6420.61

Total material & labour per Cwt. say Rs: 6420.61

____ ______________________________ ______ _____ ________ ______ ___________


S/N D E S C R I P T I O N.
IRON WORK.
2 Fabrication of heavy steel work with angles, tees, flat iron,
round iron and sheet iron for making trusses girders, tanks, etc,
including cutting, drilling riveting, handling assembling and
fixing but excluding erection in position.

____ ______________________________ ______ _____ ________ ______ ___________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Iron including 5% wastage. 1.05 Cwt. 3375.00 P.Cwt. 3543.75

Mild Steel. 1.00 Lbs. 3550.00 P.Cwt. 31.70

Chapter No. 16 1055/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Charcoal. 8.00 Seer 675 P.Mand. 135.00


______________________________ ______ _____ ________ ______ ___________
TOTAL 3710.45
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 371.04
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " A " 4081.49
______________________________ ______ _____ ________ ______ ___________
(B) LABOUR
______________________________ ______ _____ ________ ______ ___________
Black-smith. 1.00 Nos: 450.00 P.day. 450.00

Hammerman. 1.00 Nos: 250.00 P.day. 250.00


______________________________ ______ _____ ________ ______ ___________
Rs: 700.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 70.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 770.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 77.00
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " B " 847.00
______________________________ ______ _____ ________ ______ ___________
TOTAL (MATERIAL + LABOUR) 4928.49
______________________________ ______ _____ ________ ______ ___________
Total material & labour for 1 Cwt. Rs: 4928.49

Total material & labour per Cwt. say Rs: 4928.49

S/N D E S C R I P T I O N.
IRON WORK.
3 Erection and fitting in position of iron trusses, staging of
water tanks etc.
Assume for 6.25 Cwt.
____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Fitters. 2.00 Nos: 450.00 P.day. 900.00

Coolies. 2.00 Nos: 250.00 P.day. 500.00


Rs: 1400.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 140.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 1540.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 154.00
______________________________ ______ _____ ________ ______ ___________
TOTAL (LABOUR) 1694.00

Chapter No. 16 1056/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ________ ______ ___________


Total labour rate for 6.25 Cwt. Rs: 1694.00
Total labour per Cwt. Rs: 271.04
Total labour per Cwt. say Rs: 271.04
____ ______________________________ ______ _____ ________ ______ ___________
S/N D E S C R I P T I O N.
IRON WORK.
4 Fixing G.I. sheets including riveting etc.
Assume for 125 Sft.
____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Black smith. 1.00 Nos: 450.00 P.day. 450.00
Coolies. 1.00 Nos: 250.00 P.day. 250.00
Charcoal. 5.00 Seer 675 P.Mand. 84.38
Rs: 784.38
Sundries. 10.00 % 78.44
TOTAL 862.81
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 86.28
TOTAL (LABOUR) 949.09
______________________________ ______ _____ ________ ______ ___________
Total labour rate for 125 Sft. Rs: 949.09
Total labour rate for 100 Sft. Rs: 759.28
Total labour rate per 100 Sft. say Rs: 759.28
S/N D E S C R I P T I O N.
IRON WORK.
5 Erecting C.I tanks upto 20 feet hieght.
Assume for 12.5 Cwt.
____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Blacksmith. 2.00 Nos: 450.00 P.day. 900.00
Coolies. 9.50 Nos: 250.00 P.day. 2375.00
______________________________ ______ _____ ________ ______ ___________
Rs: 3275.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 327.50
______________________________ ______ _____ ________ ______ ___________
TOTAL 3602.50
Contractor's profit 10.00 % 360.25
______________________________ ______ _____ ________ ______ ___________
TOTAL (LABOUR) 3962.75
______________________________ ______ _____ ________ ______ ___________
Total labour rate for 12.5 Cwt. Rs: 3962.75
Total labour rate for 1 Cwt. Rs: 317.02
Total labour per Cwt. say Rs: 317.02
____ ______________________________ ______ _____ ________ ______ ___________
S/N D E S C R I P T I O N.
IRON WORK.
6 Erecting rolled steel beams or old rails for posts etc.
Erection and fixing in position.
Assume 25 Cwt.
____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:

Chapter No. 16 1057/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Blacksmith. 0.50 Nos: 450.00 P.day. 225.00


Coolies. 14.50 Nos: 250.00 P.day. 3625.00
______________________________ ______ _____ ________ ______ ___________
Rs: 3850.00
Sundries. 10.00 % 385.00
TOTAL 4235.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 423.50
TOTAL (LABOUR) 4658.50
______________________________ ______ _____ ________ ______ ___________
Total labour rate for 25 Cwt. Rs: 4658.50
Total labour rate for 1 Cwt. Rs: 186.34
Total labour rate per Cwt. say Rs: 186.34
____ ______________________________ ______ _____ ________ ______ ___________

S/N D E S C R I P T I O N.
IRON WORK.
7 Erecting rolled steel beams or rails erection for posts etc.
(Other than in roof)
Assume 25 Cwt.
____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Blacksmith. 0.50 Nos: 450.00 P.day. 225.00

Coolies. 6.75 Nos: 250.00 P.day. 1687.50


______________________________ ______ _____ ________ ______ ___________
Rs: 1912.50
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 191.25
______________________________ ______ _____ ________ ______ ___________
TOTAL 2103.75
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 210.38
______________________________ ______ _____ ________ ______ ___________
TOTAL (LABOUR) 2314.13
______________________________ ______ _____ ________ ______ ___________
Total labour rate for 25 Cwt. Rs: 2314.13
Total labour rate for 1 Cwt. Rs: 92.57
Total labour rate per Cwt. say Rs: 92.57

Chapter No. 16 1058/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
IRON WORK.

8 Making bolts and nuts of iron rods.

____ ______________________________ ______ _____ ________ ______ ___________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Mild Steel i/c 10% wastage. 1.10 Cwt. 3550.00 P.Cwt. 3905.00

Mild Steel. 1.50 Lbs. 3550.00 P.Cwt. 47.54

Steam Coal. 1.25 Mds: 4000.00 P.Ton. 178.57


TOTAL 4131.12
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 413.11
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " A " 4544.23
______________________________ ______ _____ ________ ______ ___________
(B) LABOUR
______________________________ ______ _____ ________ ______ ___________
Black-smith. 2.00 Nos: 450.00 P.day. 900.00

Hammerman. 1.00 Nos: 250.00 P.day. 250.00

Rs: 1150.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 115.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 1265.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 126.50
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " B " 1391.50
______________________________ ______ _____ ________ ______ ___________
TOTAL (MATERIAL + LABOUR) 5935.73
______________________________ ______ _____ ________ ______ ___________
Total material & labour for 1 Cwt. Rs: 5935.73

Total material & labour per Cwt. say Rs: 5935.73

Chapter No. 16 1059/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
IRON WORK.
9 Cutting rails and rolled steel joists and beams with back saw.
(a) Upto 6" size.
Assume for 6 Cuts.
____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Fitter. 1.25 Nos: 450.00 P.day. 562.50
Coolies. 1.25 Nos: 250.00 P.day. 312.50
Rs: 875.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 87.50
______________________________ ______ _____ ________ ______ ___________
TOTAL 962.50
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 96.25
______________________________ ______ _____ ________ ______ ___________
TOTAL (LABOUR) 1058.75
______________________________ ______ _____ ________ ______ ___________
Total labour rate for 6 Cut. Rs: 1058.75
Total labour rate for 1 Cut. Rs: 176.46
Total labour rate per Cut. say Rs: 176.46
____ ______________________________ ______ _____ ________ ______ ___________
S/N D E S C R I P T I O N.
IRON WORK.
9 Cutting rails and rolled steel joists and beams with back saw.
(b) Above 6" size.
Assume for 4 Cuts.
____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Fitter. 1.20 Nos: 450.00 P.day. 540.00
Coolies. 1.20 Nos: 250.00 P.day. 300.00
______________________________ ______ _____ ________ ______ ___________
Rs: 840.00
Sundries. 10.00 % 84.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 924.00
Contractor's profit 10.00 % 92.40
TOTAL (LABOUR) 1016.40
Total labour rate for 4 Cut. Rs: 1016.40
Total labour rate for 1 Cut. Rs: 254.10
Total labour rate per Cut. say Rs: 254.10

Chapter No. 16 1060/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
IRON WORK.
10 Cutting rails and rolled steel beams of size below 6" with jim.
Assume for 12 Cuts.
____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Fitter. 1.00 Nos: 450.00 P.day. 450.00
Coolies. 1.00 Nos: 250.00 P.day. 250.00
______________________________ ______ _____ ________ ______ ___________
Rs: 700.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 70.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 770.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 77.00
______________________________ ______ _____ ________ ______ ___________
TOTAL (LABOUR) 847.00
______________________________ ______ _____ ________ ______ ___________
Total labour rate for 12 Cut. Rs: 847.00
Total labour rate for 1 Cut. Rs: 70.58
Total labour rate per Cut. say Rs: 70.58
____ ______________________________ ______ _____ ________ ______ ___________
S/N D E S C R I P T I O N.
IRON WORK.
11 Bending rolled steel beams or rails.
Assume for 7 bends.
____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Blacksmith 0.75 Nos: 450.00 P.day. 337.50
Coolies. 0.75 Nos: 250.00 P.day. 187.50
Steam Coal. 3.75 Mds: 4000.00 P.Ton. 535.71
______________________________ ______ _____ ________ ______ ___________
Rs: 1060.71
Sundries. 10.00 % 106.07
______________________________ ______ _____ ________ ______ ___________
TOTAL 1166.79
Contractor's profit 10.00 % 116.68
TOTAL (LABOUR) 1283.46
Total labour rate for 7 bends. Rs: 1283.46
Total labour rate for 1 bend. Rs: 183.35
Total labour rate per bend. say Rs: 183.35

Chapter No. 16 1061/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
IRON WORK.
12 Fixing handles to iron hammers.
Assume for 10 Nos.
____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Carpenter. 1.25 Nos: 450.00 P.day. 562.50
Rs: 562.50
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 56.25
______________________________ ______ _____ ________ ______ ___________
TOTAL 618.75
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 61.88
______________________________ ______ _____ ________ ______ ___________
TOTAL (LABOUR) 680.63
Total labour rate for 10 Nos. Rs: 680.63
Total labour rate for 1 No. Rs: 68.06
Total labour rate per each No. say Rs: 68.06
____ ______________________________ ______ _____ ________ ______ ___________
S/N D E S C R I P T I O N.
IRON WORK.
13 Drilling holes in plates upto 1/2" thick per inch dia or part
thereof.
Assume for 30 holes.
____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Fitters. 0.50 Nos: 450.00 P.day. 225.00
Coolies. 2.00 Nos: 250.00 P.day. 500.00
______________________________ ______ _____ ________ ______ ___________
Rs: 725.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 72.50
______________________________ ______ _____ ________ ______ ___________
TOTAL 797.50
Contractor's profit 10.00 % 79.75
______________________________ ______ _____ ________ ______ ___________
TOTAL (LABOUR) 877.25
Total labour rate for 30 holes. Rs: 877.25
Total labour rate for 1 hole. Rs: 29.24
Total labour rate per hole. say Rs: 29.24
____ ______________________________ ______ _____ ________ ______ ___________

Chapter No. 16 1062/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
IRON WORK.
14 Extra for drilling holes in plates over 1/2" thick per inch dia
or part thereof.
Assume for 100 holes.
____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Fitters. 0.25 Nos: 450.00 P.day. 112.50
Coolies. 4.00 Nos: 250.00 P.day. 1000.00
______________________________ ______ _____ ________ ______ ___________
Rs: 1112.50
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 111.25
______________________________ ______ _____ ________ ______ ___________
TOTAL 1223.75
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 122.38
______________________________ ______ _____ ________ ______ ___________
TOTAL (LABOUR) 1346.13
Total labour rate for 100 holes. Rs: 1346.13
Total labour rate for 1 hole. Rs: 13.46
Total labour rate per hole. say Rs: 13.46

Chapter No. 16 1063/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
IRON WORK.
15 (a) Riveting 1/8" dia.
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Riveters. 0.50 Nos: 450.00 P.day 225.00
Coolies. 0.50 Nos: 250.00 P.day. 125.00
______________________________ ______ _____ ________ ______ ___________
Rs: 350.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 35.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 385.00
Contractor's profit 10.00 % 38.50
______________________________ ______ _____ ________ ______ ___________
TOTAL (LABOUR) 423.50
______________________________ ______ _____ ________ ______ ___________
Total labour rate for 100 Nos. Rs: 423.50
Total labour rate per % Nos. say Rs: 423.50
____ ______________________________ ______ _____ ________ ______ ___________
____ ______________________________ ______ _____ ________ ______ ___________
S/N D E S C R I P T I O N.
IRON WORK.
15 (b) Extra for every 1/8" dia.
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Rivetters. 0.50 Nos: 450.00 P.day. 225.00

Coolies. 0.50 Nos: 250.00 P.day. 125.00


______________________________ ______ _____ ________ ______ ___________
Rs: 350.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 35.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 385.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 38.50
______________________________ ______ _____ ________ ______ ___________
TOTAL (LABOUR) 423.50
______________________________ ______ _____ ________ ______ ___________
Total labour rate for 100 Nos. Rs: 423.50

Total labour rate per % Nos. say Rs: 423.50

Chapter No. 16 1064/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
IRON WORK.
16 Cutting out rivets.

Assume 144 Nos.


____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Fitters. 2.00 Nos: 450.00 P.day. 900.00

Hammerman. 2.00 Nos: 250.00 P.day. 500.00


______________________________ ______ _____ ________ ______ ___________
Rs: 1400.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 140.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 1540.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 154.00
______________________________ ______ _____ ________ ______ ___________
TOTAL (LABOUR) 1694.00
______________________________ ______ _____ ________ ______ ___________
Total labour rate for 144 Nos. Rs: 1694.00
Total labour rate for 100 Nos. Rs: 1176.39
Total labour rate per % Nos. say Rs: 1176.39
____ ______________________________ ______ _____ ________ ______ ___________

____ ______________________________ ______ _____ ________ ______ ___________


S/N D E S C R I P T I O N.
IRON WORK.
17 Fitting and erection of gutters of sheet iron.

Assume for 100 Lft.


____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Fitters. 1.00 Nos: 450.00 P.day. 450.00
Mason. 1.00 Nos: 450.00 P.day. 450.00
Coolies. 10.00 Nos: 250.00 P.day. 2500.00
______________________________ ______ _____ ________ ______ ___________
Rs: 3400.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 340.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 3740.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 374.00
______________________________ ______ _____ ________ ______ ___________
TOTAL (LABOUR) 4114.00
______________________________ ______ _____ ________ ______ ___________
Total labour rate for 100 Lft. Rs: 4114.00
Total labour rate for 1 Lft. Rs: 41.14
Total labour rate per Lft. say Rs: 41.14
____ ______________________________ ______ _____ ________ ______ ___________

Chapter No. 16 1065/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
IRON WORK.
18 Cutting and fixing iron bars for barred windows.

Assume for 30 Bars.


____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Fitters. 0.50 Nos: 450.00 P.day. 225.00
Carpenter. 0.50 Nos: 450.00 P.day. 225.00
Coolies. 1.00 Nos: 250.00 P.day. 250.00
______________________________ ______ _____ ________ ______ ___________
Rs: 700.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 70.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 770.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 77.00
______________________________ ______ _____ ________ ______ ___________
TOTAL (LABOUR) 847.00
______________________________ ______ _____ ________ ______ ___________
Total labour rate for 30 Bars. Rs: 847.00
Total labour rate for 1 Bar. Rs: 28.23
Total labour rate per bar. say Rs: 28.23
____ ______________________________ ______ _____ ________ ______ ___________

____ ______________________________ ______ _____ ________ ______ ___________


S/N D E S C R I P T I O N.
IRON WORK.
19 Cutting G.I. sheets.(2"-8")

Assume for 60 cuts.


____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Fitters. 1.00 Nos: 450.00 P.day. 450.00
Hammerman. 1.00 Nos: 250.00 P.day. 250.00

______________________________ ______ _____ ________ ______ ___________


Rs: 700.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 70.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 770.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 77.00
______________________________ ______ _____ ________ ______ ___________
TOTAL (LABOUR) 847.00
______________________________ ______ _____ ________ ______ ___________
Total labour rate for 60 cuts. Rs: 847.00
Total labour rate for 1 cut. Rs: 14.12
Total labour rate per cut. say Rs: 14.12

Chapter No. 16 1066/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
IRON WORK.
20 Notching web or foot or rail posts for housing rail beams.

Assume for 3 notches.


____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Blacksmith. 1.00 Nos: 450.00 P.day. 450.00
Hammerman. 1.00 Nos: 250.00 P.day. 250.00
Steam Coal. 0.75 Mds: 4000.00 P.Ton. 107.14
______________________________ ______ _____ ________ ______ ___________
Rs: 807.14
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 80.71
______________________________ ______ _____ ________ ______ ___________
TOTAL 887.86
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 88.79
______________________________ ______ _____ ________ ______ ___________
TOTAL (LABOUR) 976.64
______________________________ ______ _____ ________ ______ ___________
Total labour rate for 3 notches. Rs: 976.64
Total labour rate for 1 notch. Rs: 325.55
Total labour rate per notch. say Rs: 325.55
____ ______________________________ ______ _____ ________ ______ ___________

____ ______________________________ ______ _____ ________ ______ ___________


S/N D E S C R I P T I O N.
IRON WORK.
21 Hoop iron netted trellis work fixing with nails.

Assume for 36 Sft.


____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Fitter. 1.00 Nos: 450.00 P.day. 450.00
Coolies. 1.00 Nos: 250.00 P.day. 250.00

______________________________ ______ _____ ________ ______ ___________


Rs: 700.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 70.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 770.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 77.00
______________________________ ______ _____ ________ ______ ___________
TOTAL (LABOUR) 847.00
______________________________ ______ _____ ________ ______ ___________
Total labour rate for 36 Sft. Rs: 847.00
Total labour rate for 1 Sft. Rs: 23.53
Total labour rate per Sft. say Rs: 23.53
____ ______________________________ ______ _____ ________ ______ ___________

Chapter No. 16 1067/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ______________________________ ______ _____ ________ ______ ___________


S/N D E S C R I P T I O N.
IRON WORK.
22 Fixing zinc iron or G.I. sheet on table tops.

Assume for 75 Sft.


____ ______________________________ ______ _____ ________ ______ ___________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Carpenter. 1.00 Nos: 450.00 P.day. 450.00
Coolies. 1.00 Nos: 250.00 P.day. 250.00

______________________________ ______ _____ ________ ______ ___________


Rs: 700.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 70.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 770.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 77.00
______________________________ ______ _____ ________ ______ ___________
TOTAL (LABOUR) 847.00
______________________________ ______ _____ ________ ______ ___________
Total labour rate for 75 Sft. Rs: 847.00
Total labour rate for 1 Sft. Rs: 11.29
Total labour rate per Sft. say Rs: 11.29

Chapter No. 16 1068/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
IRON WORK.
23 Making and fixing steel grated doors complete with locking
arrangement angle iron frame 2"*2"*3/8" and 3/4" square bars at
4" center to center.

Assume door size 4' * 7' =28 sft.


____ ______________________________ ______ _____ ________ ______ ___________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Mild Steel. (Iron work) 3.00 Cwt. 3550.00 P.Cwt. 10650.00

Hold fasts with pivot & 6.00 Nos. 85.00 Each. 510.00
clamps.
Locking arrangements. 1.00 No. 200.00 Each. 200.00

Rivets and bolts. 5 Lbs. 110.00 P.lb. 550.00

Steam Coal. 0.500 Mds: 4000.00 P.Ton. 71.43

Steel. 2.50 Lbs. 5000.00 P.Cwt. 18.15

______________________________ ______ _____ ________ ______ ___________


TOTAL 11999.58
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 1199.96
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " A " 13199.54
______________________________ ______ _____ ________ ______ ___________
(B) LABOUR
______________________________ ______ _____ ________ ______ ___________
Black-smith. 3.00 Nos: 450.00 P.day. 1350.00

Hammerman. 3.00 Nos: 250.00 P.day. 750.00

Belowman. 3.00 Nos: 250.00 P.day. 750.00

______________________________ ______ _____ ________ ______ ___________


Rs: 2850.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 285.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 3135.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 313.50
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " B " 123.16 3448.50
______________________________ ______ _____ ________ ______ ___________
TOTAL (MATERIAL + LABOUR) 16648.04
______________________________ ______ _____ ________ ______ ___________
Total material & labour for 28 Sft. Rs: 16648.04
Total material & labour for 1 Sft. 594.57

Chapter No. 16 1069/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour per sft. say Rs: 594.57


S/N D E S C R I P T I O N.
IRON WORK.
24 Making and fixing steel door with 1/16" thick sheeting including
angle iron frame 2"*2"*3/8" and 3/4" square bars at 4" center to
center with locking arrangement.

Assume door size 4' * 7' =28 sft.


____ ______________________________ ______ _____ ________ ______ ___________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Mild Steel. 3.00 Cwt. 3550.00 P.Cwt. 10650.00

Hold fasts with pivots & 6.00 Nos. 85.00 Each. 510.00
clamps.
Locking arrangements. 1.00 No. 200.00 Each. 200.00
(1-1/2 Rft.)
Rivets and bolts. 5 Lbs. 110.00 P.lb. 550.00

Steam Coal. 0.625 Mds: 85.00 P.Ton. 1.90

M.S.Sheet. (1/16") 73.00 Lbs. 5000.00 P.Cwt. 3258.93

______________________________ ______ _____ ________ ______ ___________


TOTAL 15170.83
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 1517.08
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " A " 16687.91
______________________________ ______ _____ ________ ______ ___________
(B) LABOUR
______________________________ ______ _____ ________ ______ ___________
Black-smith. 3.25 Nos: 450.00 P.day. 1462.50

Hammerman. 3.25 Nos: 250.00 P.day. 812.50

Belowman. 3.00 Nos: 250.00 P.day. 750.00

______________________________ ______ _____ ________ ______ ___________


Rs: 3025.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 302.50
______________________________ ______ _____ ________ ______ ___________
TOTAL 3327.50
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 332.75
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " B " 130.72 3660.25
______________________________ ______ _____ ________ ______ ___________
TOTAL (MATERIAL + LABOUR) 20348.16
______________________________ ______ _____ ________ ______ ___________
Total material & labour for 28 Sft. Rs: 20348.16
Total material & labour for 1 Sft. 726.72
Total material & labour per sft. say Rs: 726.72

Chapter No. 16 1070/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

____ ______________________________ ______ _____ ________ ______ ___________

Chapter No. 16 1071/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
IRON WORK.
25 Making and fixing grating in opening including fixing at site
with flat iron 2"*3/8" and 3/4" square bars at 4" center to
center.

Assume door size 5' * 8' = 40 sft.


____ ______________________________ ______ _____ ________ ______ ___________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Frame 2"*3/8"=386'=18 Rft* 47.25 Lbs. 3375.00 P.Cwt. 1423.83
2.50 lbs/ft=45 lbs+5% Wast:

Gratings 3/4" * 3/4" =112 221.1 Lbs. 3550.00 P.Cwt. 7007.70


Rft * 1.88 lbs/ft +5% wat:

Steel. 1.5 Lbs. 5000.00 P.Cwt. 66.96

Steam Coal. 0.500 Mds: 4000.00 P.Ton. 71.43

______________________________ ______ _____ ________ ______ ___________


TOTAL 8569.92
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 856.99
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " A " 9426.91
______________________________ ______ _____ ________ ______ ___________
(B) LABOUR
______________________________ ______ _____ ________ ______ ___________
Black-smith. 2.00 Nos: 450.00 P.day. 900.00

Hammerman. 2.00 Nos: 250.00 P.day. 500.00

Belowman. 2.00 Nos: 250.00 P.day. 500.00

______________________________ ______ _____ ________ ______ ___________


Rs: 1900.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 190.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 2090.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 209.00
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " B " 57.48 2299.00
______________________________ ______ _____ ________ ______ ___________
TOTAL (MATERIAL + LABOUR) 11725.91
______________________________ ______ _____ ________ ______ ___________
Total material & labour for 40 Sft. Rs: 11725.91
Total material & labour for 1 Sft. 293.15
Total material & labour per sft. say Rs: 293.15

Chapter No. 16 1072/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
IRON WORK.
26 Supplying and fixing in position iron/steel grill of 3/4" * 1/4"
flat iron of approved design including painting 3-coats etc,
ccomplete (weight not less than 3.70 lbs per sq-ft of finished
grill.
Assume door size 6' * 6' = 36 sft.
____ ______________________________ ______ _____ ________ ______ ___________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Flat iron =36 * 3.7 lbs/sft 139.9 Lbs. 3375.00 P.Cwt. 4214.53
=1332.2 lbs + 5% wastage.

Welding rods. 4.0 Nos. 10.00 Each 40.00

Hire charges of welding L.S 107.00


machine i/c all T&P.

Painting material, etc. L.S 48.00


Screws and Nails. L.S 32.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 4441.53
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 444.15
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " A " 4885.68
______________________________ ______ _____ ________ ______ ___________
(B) LABOUR
______________________________ ______ _____ ________ ______ ___________
Black-smith. 0.50 Nos: 450.00 P.day. 225.00

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Painter. 0.25 Nos: 450.00 P.day. 112.50

Welder. 0.50 Nos: 450.00 P.day. 225.00


Carpenter for fixing. 0.50 Nos: 450.00 P.day. 225.00
______________________________ ______ _____ ________ ______ ___________
Rs: 1162.50
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 116.25
______________________________ ______ _____ ________ ______ ___________
TOTAL 1278.75
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 127.88
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " B " 39.07 1406.63
______________________________ ______ _____ ________ ______ ___________
TOTAL (MATERIAL + LABOUR) 6292.31
______________________________ ______ _____ ________ ______ ___________
Total material & labour for 36 Sft. Rs: 6292.31
Total material & labour for 1 Sft. 174.79
Total material & labour per sft. say Rs: 174.79
____ ______________________________ ______ _____ ________ ______ ___________

Chapter No. 16 1073/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
27 Supplying and fixing special heavy type steel doors for lockups with angle iron frame of
2-1/2" * 2-1/2" * 3/8" size and shutter of 2" * 2" * 3/8" with 1" diameter M.S bars Placed @
4" center to center with a seperate locking box having size of 12" * 12" of M.Steel
sheet embeded in masonry with proper locking arrangement as per approved design
including cost of erection of steel eork, fixing in masonry wall in cement concrete 1: 2: 4
etc, complete as per instructions of Engineer Incharge.
______________________________ ______ _____ ________ ______ ___________
Assume Door size 3'-6" * 7'-0"
Angle iron 2-1/2" * 2-1/2" * 3/8" for frame =2*(7'+3'-6")=21 Rft
Angle iron 2-1/2" * 2-1/2" * 3/8" for Hold fasts = 2* 4' * 1' =8 Rft
Angle iron 2" * 2" * 3/8" for Shutter = 2* (6'11" + 3'-5") =20.68 Rft
MS.flat iron 2" * 3/8" size for dividing D.opening = 2*3'-5"=6.84 Rft
Angle iron 2" * 2" *3/8" for locking box = 2 * 4' =8 Rft
M.S. Sheet SWG-10 for locking box =4 Rft
MS Bars 1" diameter for shutter = 9* 6' -11" =62.28 Rft
MS Bars 1" diameter for Aldrop = 1 * 2' -0" = 2.00 Rft.
____ ______________________________ ______ _____ ________ ______ ___________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Angle iron = 21 Rft * 5.90Angle iron = 21 Rft * 5.90Angle iron = 21 Rft * 5.90
Lb / Ft = 123 .90 Lbs + 2% wastage 126.40 Lbs 3375.00 P.Cwt. 3808.93
Angle iron =8 Rft * 5.90
Lbs/ Ft = 47 .20 Lbs + 2% wastage 48.10 Lbs 3375.00 P.Cwt. 1449.44
Angle iron =20 .68 Rft* 4.62
Lbs/Ft =95.54 Lbs + 2% wastage 97.5 Lbs 3375.00 P.Cwt. 2938.06
M.S flat = 6.84 Rft * 2. 55
Lbs/ Ft= 17.44 Lbs +2% wastage 17.8 Lbs 3375.00 P.Cwt. 536.38
M.S sheet 10 SWG=4 sft * 5.10
Lbs/ Sft =20 .1 Lbs +2% wastage 20.5 Lbs 5000.00 P.Cwt. 915.18
M.S bar =64 .28 Rft * 2.67
Lb/ Rft = 171 .63 Lbs + 2% wastage 175.1 Lbs 3550.00 P.Cwt. 5550.04
Welding rods. 6 Nos 10.00 Each 60.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 15258.04
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 1525.80
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " A " 16783.84
______________________________ ______ _____ ________ ______ ___________
(B) LABOUR
______________________________ ______ _____ ________ ______ ___________
Black-smith. 5.50 Nos: 450.00 P.day. 2475.00

Hammerman . 5.50 Nos: 250.00 P.day. 1375.00

Belowman 4.50 Nos: 250.00 P.day. 1125.00


______________________________ ______ _____ ________ ______ ___________
Rs: 4975.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 497.50
______________________________ ______ _____ ________ ______ ___________
TOTAL 5472.50
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 547.25

Chapter No. 16 1074/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ________ ______ ___________


TOTAL PART " B " 245.70 6019.75
______________________________ ______ _____ ________ ______ ___________
TOTAL (MATERIAL + LABOUR) 22803.59
______________________________ ______ _____ ________ ______ ___________
Total material & labour for 24.50 Sft. Rs: 22803.59
Total material & labour for 1 Sft. 930.76
Total material & labour per sft. say Rs: 930.76
____ ______________________________ ______ _____ ________ ______ ___________

NEW ITEMS 2001-2002

____ ______________________________ ______ _____ ________ ______ ___________


S/N D E S C R I P T I O N.

28 Providing and Fixing GI Fixed /Choukhats of size7" x 2" or 4 1/2 " x 3" for windows using
20 gauge GI Sheet i/c welded hinges and fixing at site with necessaryu hold fasts, filling
with cement sand slurry of ratio 1:6 and repairing the jambs .The cost also i/c all carriage
tools andplants used in making and fixing.
window 4*4 or 22.68rft
____ ______________________________ ______ _____ ________ ______ ___________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
GI sheet 20 gauge i/c 5% wastage. 72.95 ibs 5000.00 pcwt 3256.70

Hold fasts 4 nos 85 each 340

Hinges 3" length. 6 nos 150 p.doz 75

Cement. 0.5 bag 400.00 p.bag 200.00

Hill Sand. 4 cft 2425.00 %cft 97.00

______________________________ ______ _____ ________ ______ ___________


TOTAL 3968.70
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 396.87
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " A " 4365.57
______________________________ ______ _____ ________ ______ ___________
(B) LABOUR
______________________________ ______ _____ ________ ______ ___________
Black-smithskilled. 1.00 No 450.00 P.day. 450.00

Mason Skilled 0.50 No 450.00 P.day. 225.00

Coolie/ Bhisti 0.50 No 250.00 P.day. 125.00

Cartage L.S P.day. 50.00


P.day. 0.00
______________________________ ______ _____ ________ ______ ___________
Rs: 850.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 85.00
______________________________ ______ _____ ________ ______ ___________

Chapter No. 16 1075/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 935.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 93.50
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " B " 45.35 1028.50
______________________________ ______ _____ ________ ______ ___________
TOTAL (MATERIAL + LABOUR) 5394.07
______________________________ ______ _____ ________ ______ ___________
Total material & labour for 22.68rft. Rs: 5394.07
Total material & labour for 1 Sft. 237.83
Total material & labour per sft. say Rs: 237.83
S/N D E S C R I P T I O N.

29 Providing and Fixing GI Fixed /Choukhats of size7" x 2" or 4 1/2 " x 3" for Doors using
20 gauge GI Sheet i/c welded hinges and fixing at site with necessary hold fasts, filling
with cement sand slurry of ratio 1:6 and repairing the jambs .The cost also i/c all carriage
tools and plants used in making and fixing.
door 3*7 or 17 rft
____ ______________________________ ______ _____ ________ ______ ___________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
GI sheet 20 gauge i/c 5% wastage. 38.75 ibs 5000.00 cwt 1729.91
17*.92*1.05*2.36
Hold fasts 6 nos 85 each 510

Hinges 3" length. 6 nos 150 p.doz 75

Cement. 0.4 bag 400.00 bag 160.00

Hill Sand. 3 cft 2425.00 %cft 72.75

______________________________ ______ _____ ________ ______ ___________


TOTAL 2547.66
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 254.77
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " A " 2802.43
______________________________ ______ _____ ________ ______ ___________
(B) LABOUR
______________________________ ______ _____ ________ ______ ___________
Black-smithskilled. 1.00 No 450.00 P.day. 450.00

Mason Skilled 0.50 No 450.00 P.day. 225.00

Coolie/ Bhisti 0.50 No 250.00 P.day. 125.00

Cartage L.S P.day. 50.00


P.day. 0.00
______________________________ ______ _____ ________ ______ ___________
Rs: 850.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 85.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 935.00
______________________________ ______ _____ ________ ______ ___________

Chapter No. 16 1076/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit %
10.00 93.50
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " B " 60.50 1028.50
______________________________ ______ _____ ________ ______ ___________
TOTAL (MATERIAL + LABOUR) 3830.93
______________________________ ______ _____ ________ ______ ___________
Total material & labour for 17 Sft. Rs: 3830.93
Total material & labour for 1 Sft. 225.35
Total material & labour per sft. say Rs: 225.35
____ ______________________________ ______ _____ ________ ______ ___________

S/N D E S C R I P T I O N.

30 Providing and fixing iron steel grill using solid square bars of size 1/2 "x 1/2" placed at
4" i/c and frame of flat iron patti of 3/4" x 3/4" i/c circle shape at 1-0 apart equivalent fitted
with screws are pins i/c painting 3 coats with Ist coat of red oxide paint etc.
____ ______________________________ ______ _____ ________ ______ ___________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ ________ ______ ___________
Flat Iron patti i/c 5% wastage. 9.4 Lbs. 71.00 P.kg 297.00

Flat patti 12.48 Lbs. 71.00 P.kg 395.57

Sq.roads 1/2" x 1/2" 28.59 Lbs. 71.00 P.kg 906.20

Welding roads 4 No. 10.00 Each 40.00

Nails /screws. LS 30.00

Hire charges of welding Machine i/c LS 125.00


all T&P.

Painting Material. LS 50.00


____ ______________________________ ______ _____ ________ ______ ___________
TOTAL 1843.77
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 184.38
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " A " 2028.14
______________________________ ______ _____ ________ ______ ___________
(B) LABOUR
______________________________ ______ _____ ________ ______ ___________
Black-smith. 0.50 No 450.00 P.day. 225.00

Coolies 0.75 No 250.00 P.day. 187.50

Painter 0.15 No 450.00 P.day. 67.50

Welder 0.25 No. 450.00 P.day. 112.50

carpenter for fixing 0.25 No. 450.00 P.day. 112.50


______________________________ ______ _____ ________ ______ ___________
Rs: 705.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 70.50

Chapter No. 16 1077/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ________ ______ ___________


TOTAL 775.50
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 77.55
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " B " 53.32 853.05
______________________________ ______ _____ ________ ______ ___________
TOTAL (MATERIAL + LABOUR) 2881.19
______________________________ ______ _____ ________ ______ ___________
Total material & labour for 16 Sft. Rs: 2881.19
Total material & labour for 1 Sft. 180.07
Total material & labour per sft. say Rs: 180.07
____ ______________________________ ______ _____ ________ ______ ___________
S/N D E S C R I P T I O N.

31 Providing and fixing iron steel grill door with angle iron frome of 1 1/2" x 1 1/2" x 1/4 " and
flat iron of 3/4" x 1/4" with approved design and locking arrangement embedded in
Masonry as per instruction of Engineer in charge.

____ ______________________________ ______ _____ ________ ______ ___________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Angle frome 1 1/2" 1 1/2" x 1/4" 77.2 Lbs 3375.00 P.Cwt 2326.94
for frame i/c 10% wastage .

Flat patti for two frames of 4.0 x 7.0 207.2 Lbs 3375.00 P .Cwt 6243.75
@ 3.70 Lbs /Sft.

Hold fast withj pivot & Clamp. 6 No. 85.00 .Each 510.00

Welding roads. 8 No. 10.00 Each 80.00

Hire charges of welding Machine i/c LS 50.00


all T&P.

____ ______________________________ ______ _____ ________ ______ ___________


TOTAL 9210.69
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 921.07
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " A " 10131.76
______________________________ ______ _____ ________ ______ ___________
(B) LABOUR
______________________________ ______ _____ ________ ______ ___________
Black-smith. 2.00 No 450.00 P.day. 900.00

Coolies 2.00 No 250.00 P.day. 500.00

Welder 1.00 No. 450.00 P.day. 450.00

Carpenter for fixing 1.00 No. 450.00 P.day. 450.00


______________________________ ______ _____ ________ ______ ___________
Rs: 2300.00

Chapter No. 16 1078/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ________ ______ ___________


Sundries. 10.00 % 230.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 2530.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 253.00
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " B " 49.70 2783.00
______________________________ ______ _____ ________ ______ ___________
TOTAL (MATERIAL + LABOUR) 12914.76
______________________________ ______ _____ ________ ______ ___________
Total material & labour for 56 Sft. Rs: 12914.76
Total material & labour for 1 Sft. 230.62
Total material & labour per sft. say Rs: 230.62
____ ______________________________ ______ _____ ________ ______ ___________
S/N D E S C R I P T I O N.

32 Providing and fixing iron collapsoble gate with channel framing of section 3/4" x 5/16" at
4" i/c revitted with 3/4" "x 1/8 " flat iron patti placed diagonally and provided with top &
bottom T- section 1 " x1" 1/8" along with rollers also i/c locking arrangement and fixing
in floor /ceiling or wall etc: completed.

____ ______________________________ ______ _____ ________ ______ ___________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Channel section i/c 10% wastage. 66.3 Kg. 3375.00 P.Cwt 4475.25

Flat iron 3/4" x 1/8 " cross patti i/c 9.27 Kg. 3375 P.Cwt. 625.725
10% wastage.

Ruvets 1 1/2" x 1/4" dia. 42 No. 15.00 Each. 630.00

Railing patti T-section 1" x 1" x 1/8" 4.5 Lbs. 3375.00 P.Cwt. 303.75

Pins 5/16" x 1/4" dia 156 No. 8 Each. 1248.00

M.S.rollers. 6 No. 8 Each. 48.00

Hooks for locking arrangement LS. 100.00


Expins @ fixed end.
____ ______________________________ ______ _____ ________ ______ ___________
TOTAL 7430.73
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 743.07
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " A " 8173.80
______________________________ ______ _____ ________ ______ ___________
(B) LABOUR
______________________________ ______ _____ ________ ______ ___________
Black-smith. 3.00 No 450.00 P.day. 1350.00

Hammer man 2.00 No 250.00 P.day. 500.00

Mason for fixing 1.00 No. 450.00 P.day. 450.00

Chapter No. 16 1079/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Coolies 1.00 No. 450.00 P.day. 450.00


______________________________ ______ _____ ________ ______ ___________
Rs: 2750.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 275.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 3025.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 302.50
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " B " 110.92 3327.50
______________________________ ______ _____ ________ ______ ___________
TOTAL (MATERIAL + LABOUR) 11501.30
______________________________ ______ _____ ________ ______ ___________
Total material & labour for 30 Sft. Rs: 11501.30
Total material & labour for 1 Sft. 383.38
Total material & labour per sft. say Rs: 383.38
S/N D E S C R I P T I O N.

33 Providing & fixing GI sheet rolling shutter using 2 gauge GI sheet for shutter, side iron
channed of 12 gauge for rolling on 2" dia CI pipe i/c brackert of 20 gauge, springs of
requisite size and rolling pulley, necessary hold fasts, nuts bolts, welding, greasing,
all carriage, T&P required for making and fixing in masonry.
____ ______________________________ ______ _____ ________ ______ ___________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
GI sheet 22 gauge i/c 10% wastage. 394.2 Lbs 5000.00 P.Cwt. 17596.88

Angle urth landle 1 1/2" x 1 1/4 x 3/6" 21.48 Lbs. 3375 P.Cwt. 647.28

GI pipe 2 " dia 12 Rft. 195 P.Rft. 2340

Side channel 3" x1 1/2" 82.8 Lbs. 3375.00 P.Cwt. 2495.09

Bracket 20 Gauge . 1 No. 350.00 Each. 350.00

Spring 1 1/2" kg 4 No. 450 Each 1800.00

Pully. 4 No. 150 Each 600.00

Iron sheet cover 3 .0 Gauge 21.7 L.bs 4600 P.Cwt. 891.25

Nut bolt L.S 50.00

Grease. L.S 25.00


____ ______________________________ ______ _____ ________ ______ ___________
TOTAL 26795.49
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 2679.55
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " A " 29475.04
______________________________ ______ _____ ________ ______ ___________
(B) LABOUR
______________________________ ______ _____ ________ ______ ___________
Black Smith Skilled 2.00 No 450.00 P.day. 900.00

Chapter No. 16 1080/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Mason Skilled 1.00 No 450.00 P.day. 450.00

Coolies. 2.00 No. 250.00 P.day. 500.00


______________________________ ______ _____ ________ ______ ___________
Rs: 1850.00
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 185.00
______________________________ ______ _____ ________ ______ ___________
TOTAL 2035.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 203.50
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " B " 18.65 2238.50
______________________________ ______ _____ ________ ______ ___________
TOTAL (MATERIAL + LABOUR) 31713.54
______________________________ ______ _____ ________ ______ ___________
Total material & labour for 120 Sft. Rs: 31713.54
Total material & labour for 1 Sft. 264.28
Total material & labour per sft. say Rs: 264.28
S/N D E S C R I P T I O N.

34 Providing & fixing Aluminum expaned metal 3/32 -20 Gauge fixed to chowkats with 3/4"
(a) deodar strips and screws.

____ ______________________________ ______ _____ ________ ______ ___________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________
Deodar wood for 3.0 x4.0 window 0.3 Cft. 4500.00 P.Cft 1125.00

Alum expend Metal 3/32 -20 Gauge. 12 Sft. 43 P.Sft 516

Nails/screws. LS 15

____ ______________________________ ______ _____ ________ ______ ___________


TOTAL 1656.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 165.60
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " A " 1821.60
______________________________ ______ _____ ________ ______ ___________
(B) LABOUR
______________________________ ______ _____ ________ ______ ___________
Carpenter. 0.50 No 450.00 P.day. 225.00

CooliesSkilled 0.25 No 250.00 P.day. 62.50

Chapter No. 16 1081/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ________ ______ ___________


Rs: 287.50
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 28.75
______________________________ ______ _____ ________ ______ ___________
TOTAL 316.25
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 31.63
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " B " 28.99 347.88
______________________________ ______ _____ ________ ______ ___________
TOTAL (MATERIAL + LABOUR) 2169.48
______________________________ ______ _____ ________ ______ ___________
Total material & labour for 12 Sft. Rs: 2169.48
Total material & labour for 1 Sft. 180.79
Total material & labour per sft. say Rs: 180.79
____ ______________________________ ______ _____ ________ ______ ___________

____ ______________________________ ______ _____ ________ ______ ___________


S/N D E S C R I P T I O N.

34 Providing & fixing Aluminum expaned metal 3/32 -20 Gauge fixed to chowkats with 3/4"
(b) deodar strips and screws.

____ ______________________________ ______ _____ ________ ______ ___________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
______________________________ ______ _____ ________ ______ ___________

Alum expend Metal 3/32 -20 Gauge. 12 Sft. 43 P.Sft 516

Nails/screws. LS 15

____ ______________________________ ______ _____ ________ ______ ___________


TOTAL 531.00
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 53.10
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " A " 584.10
______________________________ ______ _____ ________ ______ ___________
(B) LABOUR
______________________________ ______ _____ ________ ______ ___________
Carpenter. 0.25 No 450.00 P.day. 112.50

CooliesSkilled 0.10 No 250.00 P.day. 25.00

Chapter No. 16 1082/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

______________________________ ______ _____ ________ ______ ___________


Rs: 137.50
______________________________ ______ _____ ________ ______ ___________
Sundries. 10.00 % 13.75
______________________________ ______ _____ ________ ______ ___________
TOTAL 151.25
______________________________ ______ _____ ________ ______ ___________
Contractor's profit 10.00 % 15.13
______________________________ ______ _____ ________ ______ ___________
TOTAL PART " B " 13.86 166.38
______________________________ ______ _____ ________ ______ ___________
TOTAL (MATERIAL + LABOUR) 750.48
______________________________ ______ _____ ________ ______ ___________
Total material & labour for 12 Sft. Rs: 750.48
Total material & labour for 1 Sft. 62.54
Total material & labour per sft. say Rs: 62.54
____ ______________________________ ______ _____ ________ ______ ___________

Chapter No. 16 1083/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

MISCELLANEOUS

FIRST FILL THIS SHEET

LABOUR
MASSON ,CARPENTOR ,FITTER 450 P.DAY
BLACK SMITH , PAINTER

COOLIES 250 P.DAY

MATE , SKILLED COOLI , DIVERS 250 P.DAY


WASHER MAN

BULLOCK MAN WITH ONE PAIR 450 P.DAY


OF BULOCK

CART WITH CART MAN 425 P.DAY

GLAZIER 400 P.DAY

MATERIAL
CEMENT 400 P.CWT

SAND 2425 %CFT

DEODAR WOOD 2ND QUALITY 4000 P.CFT

STONE BALLAST 2" RING 2350 %CFT

BARBED WIRE 5000 P.CWT

EYE BOLT 390 P.DOZ

WASHER 3/16 56 P.DOZ

BAMBOOS 10-12' &1-1/2" DIA 160 EACH

IRON SHOE 50 EACH

CLOTH 45 P.METER

WOODEN PEGS 1-1/2" DIA & 6" LG 900 %NOS

ROYALTY OF BUSH WOOD 1000 %NOS

SAWING OF WOOD 80 P.CFT

BAN 150 P.KG

Chapter No. 17 1084/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

BAMBOOS 8-10' &2-1/2"TO 5" DIA 200 EACH

BAMBOOS 10-12' &2-1/2"TO 5" DIA 225 EACH

B.S W.G 10 WIRE 5000 P.CFT Cwt

BAMBOOS 12-14' &2-1/2"TO 5" DIA 225 EACH

BAMBOOS 14-16' &2-1/2"TO 5" DIA 285 EACH

BAMBOOS 16-20' &2-1/2"TO 5" DIA 340 EACH

HOOKS 140

CANE 5 P.DOZ

CANE 250 P.KG

SHEESHAM WOOD 2300 P.CFT

PAINT 1600 P.GAL

NAILS 110 P.KG

GRATTINGS 2100 P.CWT

BRICKS 5000 %0 NOS

DAMPO 125 P.KG

STEAM COAL 4000 P.TON

ALUMINUM FRAMING HINGED 1050 P.SFT


DOOR ALCOP

ALPHA DOOR LOCK (JAPAN) BRO 1500 EACH

5 M.M TINTED GLASS 230 P.SFT

FLY SCREAN (FORIGN) 180 P.SFT

ALMUNUM FRAME FOR HINGED 1000 P.SFT


DOOR ALCOPE WHITE

ORGANO CHLORO SOLUTION 5500 P.GAL

CHIP BOARD 39 P.SFT

ANGLE IRON 3575 P.CWT

BITUMEN 86213.00 P.TON

A.C FRAMES 1500 EACH

PICTURE RAILING / DEODAR RAI 150 P.RFT

G.I FRAME 5500 P.CWT

Chapter No. 17 1085/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

HOLD FAST 65 EACH

ALUMINUM FRAMING FOR HING 150 PRFT


DOOR ALCOP

5 M.M TINTED GLASS 40 EACH

RAILING PATTI 150 PRFT

POTASIUM PER MAGNETE 55 P.LBS

WHITE LIME 6 P.KG

BROKEN GLASS 450 P.MAND

HIRE CHARGES OF TRACTOR 6000 P.DAY

Chapter No. 17 1086/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

C H A P T E R - 17
MISCELLANEOUS
=========================
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.

1. Notice board made with cement .


(The board is to be of cement plaster 1/2" thick with 2" wide
and 1" thick heading)

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Assume size of board = 4' * 5' = 20 Sft.
_____________________________ __________ ________ ________ __________
Cement. 0.3 Cwt 400.00 P.Cwt. 120.00

Sand. 1.20 Cft 2425.00 % Cft. 29.10

TOTAL 149.10
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 14.91
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 164.01
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00

Coolies. 1.50 Nos. 250.00 P.day. 375.00

Rs: 825.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 82.50
_____________________________ __________ ________ ________ __________
TOTAL 907.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 90.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 49.91 998.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 1162.26
_____________________________ __________ ________ ________ __________
Total material & labour for 20 Sft. Rs: 1162.26
Total material & labour for 1 Sft. Rs: 58.11
Total material & labour per Sft. say Rs: 58.11
___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1087/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
JUNGLE CLEARANCE.

2. Cutting and removing trees within a distance of 100 feet.


(a) Upto 2.50 feet girth.
(Unit of rate per No.)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Carpenter. 0.15 Nos. 450.00 P.day. 67.50
Coolies. 1.50 Nos. 250.00 P.day. 375.00
_____________________________ __________ ________ ________ __________
Rs: 442.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 44.25
_____________________________ __________ ________ ________ __________
TOTAL 486.75
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 48.68
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 535.43
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 535.43
_____________________________ __________ ________ ________ __________
Total labour rate for Each No. Rs: 535.43
Total labour rate for Each No. Say Rs: 535.43
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
JUNGLE CLEARANCE.
2. Cutting and removing trees within a distance of 100 feet.
(b) From 2.50 to 6.0 feet girth.
(Unit of rate per No.)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Carpenter. 0.25 Nos. 450.00 P.day. 112.50
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 862.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 86.25
_____________________________ __________ ________ ________ __________
TOTAL 948.75
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 94.88
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1043.63
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1043.63
Total labour rate for Each No. Rs: 1043.63
Total labour rate for Each No. Say Rs: 1043.63

Chapter No. 17 1088/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
JUNGLE CLEARANCE.

3. Up-rooting stumps and removing within 100 ft.


From 2'-0" to 6'-0" girth.
(Unit of rate per No.)
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________

Coolies. 2.00 Nos. 250.00 P.day. 500.00


_____________________________ __________ ________ ________ __________
Rs: 500.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 50.00
_____________________________ __________ ________ ________ __________
TOTAL 550.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 55.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 605.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 605.00
_____________________________ __________ ________ ________ __________
Total labour rate for Each No. Rs: 605.00
Total labour rate for Each No. Say Rs: 605.00
S/N D E S C R I P T I O N.
JUNGLE CLEARANCE.

4. Jungle clearance and removing within 100'.


From 2'-0" to 6'-0" girth.
(a) Light.
(Unit of rate one thousand Sft.)
___ _____________________________ __________ _____ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
___ _____________________________ __________ _____ Rs: Rs:
Coolies. 0.25 Nos. 250.00 P.day. 62.50
_____________________________ __________ ________ ________ __________
Rs: 62.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 6.25
TOTAL 68.75
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 6.88
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 75.63
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 75.63
_____________________________ __________ ________ ________ __________
Total labour rate per 1000 Sft. Rs: 75.63
Total labour rate per 1000 Sft. Say Rs: 75.63

Chapter No. 17 1089/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
JUNGLE CLEARANCE.
4. Jungle clearance and removing within 100'.
From 2'-0" to 6'-0" girth.
(b) Thick.
(Unit of rate one thousand Sft.)
(B) LABOUR QUANTITY RATE UNIT AMOUNT

Coolies. 0.50 Nos. 250.00 P.day. 125.00


Rs: 125.00
Sundries. 10.00 % 12.50
TOTAL 137.50
Contractor's profit 10.00 % 13.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 151.25
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 151.25
_____________________________ __________ ________ ________ __________
Total labour rate per 1000 Sft. Rs: 151.25
Total labour rate per 1000 Sft. Say Rs: 151.25
S/N D E S C R I P T I O N.
FENCING.

5 Making and fixing second class deodar palisade fencing complete.


Assume for 6 Lft.
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Deodar wood. (2nd class) 2.8 Cft 4000.00 P.Cft. 11000.00

Screws and Nails. L.S 10.00

Stone Ballast 2" gauge. 2.5 Cft 2350.00 % Cft. 58.75


TOTAL 11068.75
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 1106.88
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 12175.63
_____________________________ __________ ________ ________ __________
(B) LABOUR
Carpenter. 1.25 Nos. 450.00 P.day. 562.50

Coolies. 1.50 Nos. 250.00 P.day. 375.00


Rs: 937.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 93.75
_____________________________ __________ ________ ________ __________
TOTAL 1031.25
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 103.13
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1134.38
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 13310.00
_____________________________ __________ ________ ________ __________
Total material & labour for 6 Lft. Rs: 13310.00
Total material & labour for 100 Lft. Rs: 221833.3

Chapter No. 17 1090/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour per % Lft. say Rs: 221833.33

Chapter No. 17 1091/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
FENCING.

6 Fixing palisade fencing including erecting posts.

Assume for 6 Lft.


___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT

_____________________________ __________ ________ ________ __________


Coolies. 1.00 Nos. 250.00 P.day. 250.00

_____________________________ __________ ________ ________ __________


Rs: 250.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 25.00
_____________________________ __________ ________ ________ __________
TOTAL 275.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 27.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 302.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 302.50
_____________________________ __________ ________ ________ __________
Total labour rate for 6 Lft. Rs: 302.50
Total labour rate for 100 Lft. Rs: 5041.67
Total labour rate per % Lft. say Rs: 5041.67

Chapter No. 17 1092/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 Making and fixing barbed wire fencing including R.C.C. posts


upto 4 horizontal and a cross wires.
Assume for 48 Rft.
___ _____________________________ __________ ________ ________ __________
R.C.C. Posts (1:2:4)
Straining posts (9"*9"*6")= 1/2 * 7' * 3'/4 * 3'/4 =2.00 Cft.
Collar around Straining posts=1/2* *2*1.5'*1'/4*1'/2 =0.44 cft.
Stiffening posts (6"*6")= 1/2 * 7' * 1'/2 * 1'/2 =0.88 Cft.
Intermediate posts (5"*5") = 5 * 7' * 5'/12 * 5'/12 =6.07 Cft.
DEDUCT for portion of the posts = 1/2*3'/4*3'/4*1'/2 =-0.14 Cft.
------------------------------------------------- ----------------- ------------- ------------- -----------------
i Net R.C.C. work required for 48 Rft = 9.25
------------------------------------------------- ----------------- ------------- ------------- -----------------
Mild steel bars with binding wires.
Straining posts Vertical bars 1/2" dia = 2 * 7 = 14 Rft.
Stirrups 1/4" dia bars =1/2 * 8 * 3 = 12 Rft.
Stifening posts vertical bars 3/8" dia = 2 * 7' = 14 Rft.
Stirrups 1/4" dia bars =1/2 * 8 * 2 = 8 Rft.
Intermediate posts vert: bars 3/8" dia =5 * 4 * 7' = 140 Rft.
Stirrups 1/4" dia bars =5 * 8 * = 67 Rft.
Weight 1/2" dia = 14 * 0.67 = 9.38 Lbs.
Weight 3/8" dia = (14 + 140)*0.375 = 57.75 Lbs.
Weight 1/4" dia bars = (12 + 8 + 67)*0.167 = 14.53 Lbs.
------------------------------------------------- ----------------- ------------- ------------- -----------------
ii Net Fabrication of Mild steel reinforcement required =81.66 Lbs.
------------------------------------------------- ----------------- ------------- ------------- -----------------
Straned barbed wires.
Horizontal wires = 4 * 48 = 192 Rft. 5% wastage = 202 Lbs.
Cross wires = 12 * 9 = 108 Rft. 5% wastage = 113 Lbs.
------------------------------------------------- ----------------- ------------- ------------- -----------------
TOTAL = 300 Rft. 5% wastage = 315 Lbs.
------------------------------------------------- ----------------- ------------- ------------- -----------------
iii Weight of 315' lenth of barbed wire =315*1.25/1350=0.30 Cwt.
------------------------------------------------- ----------------- ------------- ------------- -----------------
Eye Bolts (bigger size)
For Straining Posts = 4 Nos.
For Stiffening Posts = 2 Nos.
For Intermediate Posts = 20 Nos.
------------------------------------------------- ----------------- ------------- ------------- -----------------
TOTAL Nos. of Eye Bolts = 26 Nos.
------------------------------------------------- ----------------- ------------- ------------- -----------------
iv 3"/16 washers.
For Straining Posts = 4 Nos.
For Stiffening Posts = 2 Nos.
For Intermediate Posts = 20 Nos.
------------------------------------------------- ----------------- ------------- ------------- -----------------
TOTAL Nos. of 3"/16 washers = 26 Nos.

Chapter No. 17 1093/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

7 MAKING & FIXING BARBED WIRE FENCING INCLUDING R.C.C POST


UP TO 4 HORIZONTAL AND A CROO EIRES

ASSUME FOR 48 RFT


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
R.C.C 1:2:4 CH 04 (I/6 (i) ) 9.25 CFT 309.70 P.CFT 2864.72

STEEL CH 04 (I/7(b) 81.66 LBS 5001.70 P.CWT 3646.77


BARBED WIRE 0.3 CWT 5000.00 P.CWT 1500.00
EYE BOLTS 26 Nos 390 P.DOZ 845.00
WASHER 3/10" 26 Nos 56 P.DOZ 121.33
TOTAL 8977.82
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 897.78
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 9875.60
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
LABOUR FOR R.C.C 9.25 CFT 77.80 P.CFT 719.65

LABOUR FOR FABRICATION 81.66 LBS 423.50 P.CWT 310.96

BLACK SMITH 0.75 No 450 P.day. 337.50

COOLIES 2 No 250 P.day. 500.00


Rs: 1868.11
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 186.81
_____________________________ __________ ________ ________ __________
TOTAL 2054.92
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 205.49
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 4709.19 2260.41
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 12136.02
_____________________________ __________ ________ ________ __________
Total material & labour for 48ft. Rs: 12136.02
Total material & labour for 100 Lft. Rs: 25283.36

Chapter No. 17 1094/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.
new

8 Providing & fixing angle iron vertical posts for barbed wire fencing of size 2" x 2" 1/4"
embedded in RCC / Masonry pillars i/c Making cuts / holders @ 12" i/c fixing in pillars
by chiseling and filling the with cement sand mortar, saprining & finishing the surface.

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Angle iron 2" x 2" 1/4" i/c 10% 350.9 lbs 3575.00 P.Cwt. 11200.60
wastage.

T&P for cutting. LS 50

Cement samd Mortar, for filling LS 500


& repair (25/- per pillars.

_____________________________ __________ ________ ________ __________


TOTAL 11750.60
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 1175.06
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 12925.66
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Black Smith for Cutting & Making 2.00 450.00 P.day. 900.00
holes.

Coolies for chiesling 2 250 P.day. 500.00

Masonfor fixing angle 2 450 P.day. 900.00

Bhisti for Careing etc. 2 250 P.day. 500.00

Rs: 2800.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 280.00
_____________________________ __________ ________ ________ __________
TOTAL 3080.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 308.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 33.88 3388.00
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 16313.66
_____________________________ __________ ________ ________ __________
Total material & labour for 100 Lft. Rs: 16313.66
Total material & labour for per Lft. Rs: 163.14

Chapter No. 17 1095/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
new

9 P roviding & fixing barbed wire fencing with 12 gauge -4 points @ 6" apart barbed wire i/c
straightening & fixing in angle iron vertical posts.

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________

Barbed wire i/c 10% wastage. 13.42 Lbs 5000 P.Cwt 599.107143

_____________________________ __________ ________ ________ __________


TOTAL 599.11
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 59.91
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 659.02
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________

Black Smith for straightening & 0.33 Nos. 450 P.day 148.5
fixing.

Rs: 148.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 14.85
_____________________________ __________ ________ ________ __________
TOTAL 163.35
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 16.34
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1.80 179.69
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 838.70
_____________________________ __________ ________ ________ __________

Chapter No. 17 1096/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 100 Lft. Rs: 838.70


Total material & labour for per Lft. Rs: 8.4

S/N D E S C R I P T I O N.
SURVEYING.

10 Supplying bamboo jhandies 10' to 12' with iron shoes and flags
15" square.

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cost of bamboo. 1.00 Nos. 160.00 Each. 160.00

Cost of iron shoe. 1.00 Nos. 50.00 Each. 50.00

Cost of red cloth. 0.50 Mtr: 45.00 P.Meter 22.50

_____________________________ __________ ________ ________ __________


TOTAL 232.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 23.25
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 255.75
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Carpenter. 0.04 Nos. 450.00 P.day. 18.00

Sawing charges. L.S 8.00

_____________________________ __________ ________ ________ __________


Rs: 26.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 2.60
_____________________________ __________ ________ ________ __________
TOTAL 28.60
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 2.86
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 31.46
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 287.21
_____________________________ __________ ________ ________ __________
Total material & labour for each No. Rs: 287.21

Total material & labour for each No. say Rs: 287.21
___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1097/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
SURVEYING.

11 Sypplying wooden pegs for levelling 1-1/2" dia 6" long.

Assume for 200 Nos.


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cost of wooden pegs. 200.0 Nos 900.00 % Nos. 1800.00

_____________________________ __________ ________ ________ __________


TOTAL 1800.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 180.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 1980.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Carpenter. 1.00 Nos. 450.00 P.day. 450.00

_____________________________ __________ ________ ________ __________


Rs: 450.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 45.00
_____________________________ __________ ________ ________ __________
TOTAL 495.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 49.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 272.25 544.50
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 2524.50
_____________________________ __________ ________ ________ __________
Total material & labour for 200 Nos. Rs: 2524.50
Total material & labour for 100 Nos. Rs: 1262.25
Total material & labour for % Nos. say Rs: 1262.25

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1098/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
SURVEYING.

12 Supplying wooden pegs for alignment 3" dia 6" long.

Assume for 200 Nos.


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cost of wooden pegs. 100.0 Nos 900.00 % Nos. 900.00

_____________________________ __________ ________ ________ __________


TOTAL 900.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 90.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 990.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Carpenter. 1.00 Nos. 450.00 P.day. 450.00
Rs: 450.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 45.00
_____________________________ __________ ________ ________ __________
TOTAL 495.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 49.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 272.25 544.50
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 1534.50
_____________________________ __________ ________ ________ __________
Total material & labour for 200 Nos. Rs: 1534.50
Total material & labour for 100 Nos. Rs: 767.25
Total material & labour for % Nos. say Rs: 767.25
___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1099/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.
CANAL AND ROADS.
13 Fixing floating spurs with materials from canal plantation
within one mile lead.
(a) Upto 2'-0" F.S.depth.
Assume for 200 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mate. 1.00 Nos. 250.00 P.day. 250.00
Carpenter. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 7.00 Nos. 250.00 P.day. 1750.00
_____________________________ __________ ________ ________ __________
Rs: 2450.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 245.00
_____________________________ __________ ________ ________ __________
TOTAL 2695.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 269.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 2964.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 2964.50
_____________________________ __________ ________ ________ __________
Total labour rate for 200 Nos. Rs: 2964.50
Total labour rate for 1 Nos. Rs: 14.82
Total labour rate for Each No. Say Rs: 14.82

Chapter No. 17 1100/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
CANAL AND ROADS.
13 Fixing floating spurs with materials from canal plantation
within one mile lead.
(b) 2'-0" to 3'-0" F.S.depth.
Assume for 150 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mate. 1.00 Nos. 250.00 P.day. 250.00
Carpenter. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 7.00 Nos. 250.00 P.day. 1750.00
_____________________________ __________ ________ ________ __________
Rs: 2450.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 245.00
_____________________________ __________ ________ ________ __________
TOTAL 2695.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 269.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 2964.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 2964.50
_____________________________ __________ ________ ________ __________
Total labour rate for 150 Nos. Rs: 2964.50
Total labour rate for 1 Nos. Rs: 19.76
Total labour rate for Each No. Say Rs: 19.76

Chapter No. 17 1101/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.
CANAL AND ROADS.
13 Fixing floating spurs with materials from canal plantation
within one mile lead.
(c) 3'-0" to 4'-0" F.S.depth.
Assume for 100 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mate. 1.00 Nos. 250.00 P.day. 250.00
Carpenter. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 7.00 Nos. 250.00 P.day. 1750.00
_____________________________ __________ ________ ________ __________
Rs: 2450.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 245.00
_____________________________ __________ ________ ________ __________
TOTAL 2695.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 269.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 2964.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 2964.50
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Nos. Rs: 2964.50
Total labour rate for 1 Nos. Rs: 29.65
Total labour rate for Each No. Say Rs: 29.65

Chapter No. 17 1102/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________

S/N D E S C R I P T I O N.
CANAL AND ROADS.
13 Fixing floating spurs with materials from canal plantation
within one mile lead.
(d) Abov 4'-0" F.S.depth.
Assume for 50 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mate. 1.00 Nos. 250.00 P.day. 250.00
Carpenter. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 7.00 Nos. 250.00 P.day. 1750.00
_____________________________ __________ ________ ________ __________
Rs: 2450.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 245.00
_____________________________ __________ ________ ________ __________
TOTAL 2695.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 269.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 2964.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 2964.50
_____________________________ __________ ________ ________ __________
Total labour rate for 50 Nos. Rs: 2964.50
Total labour rate for 1 Nos. Rs: 59.29
Total labour rate for Each No. Say Rs: 59.29

Chapter No. 17 1103/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(a) (i) Cutting and supplying un-sharpened pegs 3.5" long 3" - 6"
dia. Lead with in one mile.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Wood required for 100 Pegs = 100*3.5'*9'/24 *9'/24 * 1'/4 * 22/7=
= 38.70 Cft. + 20% wastage = 46.44 say 46.50 Cft.
Weight of 46.50 of green wood @ 62 lbs/cft =46.5*62/82.5 =35 Mds.
_____________________________ __________ ________ ________ __________

Royality of Brush wood. 46.5 Cft 1000.0 % Cft. 465.00


TOTAL 465.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 46.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 511.50
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Sawing of wood by machine. 46.50 Cft 80.00 P.Cft. 3720.00

_____________________________ __________ ________ ________ __________


Rs: 3720.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 372.00
_____________________________ __________ ________ ________ __________
TOTAL 4092.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 409.20
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 4501.20
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 5012.70
_____________________________ __________ ________ ________ __________
Total material & labour for 100 Nos. Rs: 5012.70

Chapter No. 17 1104/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour per % Nos. say Rs: 5012.70


___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(a) (ii) Sharpening one end of pegs 3.5' long 3" - 6" dia.

(Unit of rate per % Nos. pegs)


___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Carpenter. 0.50 Nos. 450.00 P.day. 225.00
Coolies. 0.50 Nos. 250.00 P.day. 125.00
_____________________________ __________ ________ ________ __________
Rs: 350.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 35.00
_____________________________ __________ ________ ________ __________
TOTAL 385.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 38.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 423.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 423.50
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Nos. Rs: 423.50

Total labour rate for 100 Nos. Say Rs: 423.50

Chapter No. 17 1105/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(a) (iii) Driving pegs 3.5' long 3" - 6" dia.(Driven 1.0' below the
available bed or ground)
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies skilled. 1.40 Nos. 250.00 P.day. 350.00
_____________________________ __________ ________ ________ __________
Rs: 350.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 35.00
_____________________________ __________ ________ ________ __________
TOTAL 385.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 38.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 423.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 423.50
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Nos. Rs: 423.50

Total labour rate for 100 Nos. Say Rs: 423.5

Chapter No. 17 1106/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(a) (iv) Tying pegs with Munj Patha Ban (one line, inncluding tying
around the pegs)
(Unit of rate per chain of one row.)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of Ban for one chain lenth of row of killas
including a tie around the pegs.=100' + 50 * 9/24*22/7 = 160 Lft.
Add 10% wastage. = 160' + 16' = 176 Lft. say 175 Lft.
1 Seer of ban covers 250' Length. Hence, weight of 175' ban
= 175/250 =0.70 Seer.

_____________________________ __________ ________ ________ __________


Ban. 0.7 Seer 150.00 P.Seer. 105.00
TOTAL 105.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 10.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 115.50
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Coolies. 0.10 Nos. 250.00 P.day. 25.00

_____________________________ __________ ________ ________ __________


Rs: 25.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 2.50
_____________________________ __________ ________ ________ __________
TOTAL 27.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 2.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 30.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 145.75
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 145.75

Total material & labour for one chain of row. Rs: 145.75

Chapter No. 17 1107/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(a) (v) Cutting & supplying brush wood from Canal Plantation or
Private owners, lead within one mile and wattling between stakes
and intertwining (Thickness of wattled brush wood 1.0' average)

(Unit of rate per chain of one row.)


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of brush wood=Lenth =100', Thickness=1.0',Hiegt=2.5'
= 100' * 1' * 2.5' = 250 Cft.
_____________________________ __________ ________ ________ __________

Royality of Brush wood. 250.0 Cft 1000.0 % Cft. 2500.00

_____________________________ __________ ________ ________ __________


TOTAL 2500.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 250.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 2750.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Skilled coolies for 1.00 250.00 P.day. 250.00
wattling brush wood.

_____________________________ __________ ________ ________ __________


Rs: 250.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 25.00
_____________________________ __________ ________ ________ __________
TOTAL 275.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 27.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 302.50
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 3052.50
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 3052.50

Total material & labour for one chain of row. Rs: 3052.50

Chapter No. 17 1108/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(b) (i) Cutting and supplying un-sharpened pegs 4.0' long 3" - 6"
dia. Lead with in one mile.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Wood required for 100 Pegs = 100*4.0'*9'/24 *9'/24 * 1'/4 * 22/7=
= 44.20 Cft. + 20% wastage = 53.04 say 53.0 Cft.
Weight of 53 cft of green wood @ 62 lbs/cft=53*62/82.5 =39.80 Mds.
_____________________________ __________ ________ ________ __________

Royality of Brush wood. 53.0 Cft 1000.0 % Cft. 530.00

TOTAL 530.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 53.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 583.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Sawing of wood by machine. 53.00 80.00 P.Cft. 4240.00

_____________________________ __________ ________ ________ __________


Rs: 4240.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 424.00
_____________________________ __________ ________ ________ __________
TOTAL 4664.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 466.40
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 5130.40
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 5713.40
_____________________________ __________ ________ ________ __________
Total material & labour for 100 Nos. Rs: 5713.40

Total material & labour per % Nos. say Rs: 5713.40

Chapter No. 17 1109/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(b) (ii) Sharpening one end of pegs 4.0' long 3" - 6" dia.

(Unit of rate per % Nos. pegs)


___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Carpenter. 0.50 Nos. 450.00 P.day. 225.00
Coolies. 0.50 Nos. 250.00 P.day. 125.00
_____________________________ __________ ________ ________ __________
Rs: 350.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 35.00
_____________________________ __________ ________ ________ __________
TOTAL 385.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 38.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 423.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 423.50
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Nos. Rs: 423.50

Total labour rate for 100 Nos. Say Rs: 423.50

Chapter No. 17 1110/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(b) (iii) Driving pegs 4.0' long 3" - 6" dia.(Driven 1.25' below the
available bed or ground)
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies skilled. 1.00 Nos. 250.00 P.day. 250.00
Coolies. 0.73 Nos. 250.00 P.day. 182.50
_____________________________ __________ ________ ________ __________
Rs: 432.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 43.25
_____________________________ __________ ________ ________ __________
TOTAL 475.75
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 47.58
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 523.33
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 523.33
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Nos. Rs: 523.33

Total labour rate for 100 Nos. Say Rs: 523.33

Chapter No. 17 1111/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(b) (iv) Tying pegs with Munj Patha Ban (one line, inncluding tying
around the pegs)
(Unit of rate per chain of one row.)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of Ban for one chain lenth of row of killas
including a tie around the pegs.=100' + 50 * 9/24*22/7 = 160 Lft.
Add 10% wastage. = 160' + 16' = 176 Lft. say 175 Lft.
1 Seer of ban covers 250' Length. Hence, weight of 175' ban
= 175/250 =0.70 Seer.

_____________________________ __________ ________ ________ __________


Ban. 0.7 Seer 150.00 P.Seer. 105.00

_____________________________ __________ ________ ________ __________


TOTAL 105.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 10.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 115.50
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Coolies. 0.10 Nos. 250.00 P.day. 25.00

_____________________________ __________ ________ ________ __________


Rs: 25.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 2.50
_____________________________ __________ ________ ________ __________
TOTAL 27.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 2.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 30.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 145.75
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 145.75

Total material & labour for one chain of row. Rs: 145.75
___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1112/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(b) (v) Cutting & supplying brush wood from Canal Plantation or
Private owners, lead within one mile and wattling between stakes
and intertwining (Thickness of wattled brush wood 1.0' average)

(Unit of rate per chain of one row.)


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of brush wood=Lenth =100', Thickness=1.0',Hiegt=2.75'
= 100' * 1' * 2.75' = 275 Cft.
_____________________________ __________ ________ ________ __________

Royality of Brush wood. 275.0 Cft 1000.0 % Cft. 2750.00

_____________________________ __________ ________ ________ __________


TOTAL 2750.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 275.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 3025.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Skilled coolies for 1.20 Nos. 250.00 P.day. 300.00
wattling brush wood.
_____________________________ __________ ________ ________ __________
Rs: 300.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 30.00
_____________________________ __________ ________ ________ __________
TOTAL 330.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 33.00
_____________________________ __________ ________ ________ __________
Cutting brush wood by hand. 275 Cft 650 Per %Cft. 1787.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 2150.50
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 5175.50
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 5175.50
Total material & labour for one chain of row. Rs: 5175.50
___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1113/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(c) (i) Cutting and supplying un-sharpened pegs 5.0' long 3" - 6"
dia. Lead with in one mile.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Wood required for 100 Pegs = 100*5.0'*9'/24 *9'/24 * 1'/4 * 22/7=
= 55.25 Cft. + 20% wastage = 66.3 say 63.30 Cft.
Weight of 53 cft of green wood @ 62 lbs/cft=53*62/82.5 =39.80 Mds.
_____________________________ __________ ________ ________ __________

Royality of Brush wood. 66.30 Cft 1000.0 % Cft. 663.00

_____________________________ __________ ________ ________ __________


TOTAL 663.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 66.30
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 729.30
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Sawing of wood by machine. 66.30 Cft 80.00 P.Cft. 5304.00

_____________________________ __________ ________ ________ __________


Rs: 5304.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 530.40
_____________________________ __________ ________ ________ __________
TOTAL 5834.40
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 583.44
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 6417.84
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 7147.14
_____________________________ __________ ________ ________ __________
Total material & labour for 100 Nos. Rs: 7147.14

Total material & labour per % Nos. say Rs: 7147.14


___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1114/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(c) (ii) Sharpening one end of pegs 5.0' long 3" - 6" dia.

(Unit of rate per % Nos. pegs)


___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Carpenter. 0.55 Nos. 450.00 P.day. 247.50
Coolies. 0.50 Nos. 250.00 P.day. 125.00
_____________________________ __________ ________ ________ __________
Rs: 372.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 37.25
_____________________________ __________ ________ ________ __________
TOTAL 409.75
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 40.98
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 450.73
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 450.73
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Nos. Rs: 450.73

Total labour rate for 100 Nos. Say Rs: 450.73

Chapter No. 17 1115/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(c) (iii) Driving pegs 5.0' long 3" - 6" dia.(Driven 1.5' below the
available bed or ground)
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies skilled. 1.00 Nos. 250.00 P.day. 250.00
Coolies. 1.00 Nos. 250.00 P.day. 250.00
_____________________________ __________ ________ ________ __________
Rs: 500.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 50.00
_____________________________ __________ ________ ________ __________
TOTAL 550.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 55.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 605.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 605.00
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Nos. Rs: 605.00

Total labour rate for 100 Nos. Say Rs: 605.00

Chapter No. 17 1116/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(c) (iv) Tying pegs with Munj Patha Ban (one line, inncluding tying
around the pegs)
(Unit of rate per chain of one row.)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of Ban for one chain lenth of row of killas
including a tie around the pegs.=100' + 50 * 9/24*22/7 = 160 Lft.
Add 10% wastage. = 160' + 16' = 176 Lft. say 175 Lft.
1 Seer of ban covers 250' Length. Hence, weight of 175' ban
= 175/250 =0.70 Seer.

_____________________________ __________ ________ ________ __________


Ban. 0.7 Seer 150.00 P.Seer. 105.00

_____________________________ __________ ________ ________ __________


TOTAL 105.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 10.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 115.50
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Coolies. 0.10 Nos. 250.00 P.day. 25.00

_____________________________ __________ ________ ________ __________


Rs: 25.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 2.50
_____________________________ __________ ________ ________ __________
TOTAL 27.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 2.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 30.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 145.75
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 145.75

Total material & labour for one chain of row. Rs: 145.75
___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1117/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(c) (v) Cutting & supplying brush wood from Canal Plantation or
Private owners, lead within one mile and wattling between stakes
and intertwining (Thickness of wattled brush wood 1.0' average)

(Unit of rate per chain of one row.)


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of brush wood=Lenth =100', Thickness=1.0',Hiegt=3.5'
= 100' * 1' * 3.5' = 350 Cft.
_____________________________ __________ ________ ________ __________

Royality of Brush wood. 350.0 Cft 1000.0 % Cft. 3500.00

_____________________________ __________ ________ ________ __________


TOTAL 3500.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 350.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 3850.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Skilled coolies for 1.50 Nos. 250.00 P.day. 375.00
wattling brush wood.

_____________________________ __________ ________ ________ __________


Rs: 375.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 37.50
_____________________________ __________ ________ ________ __________
TOTAL 412.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 41.25
_____________________________ __________ ________ ________ __________
Sawing cutting of wood by 350.0 Cft 650.00 Per %Cft. 2275.00
hand.
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 2728.75
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 6578.75
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 6578.75
___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1118/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(d) (i) Cutting and supplying un-sharpened pegs 6.0' long 3" - 6"
dia. Lead with in one mile.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Wood required for 100 Pegs = 100*6.0'*9'/24 *9'/24 * 1'/4 * 22/7=
= 66.30 Cft. + 20% wastage = 79.6 say 63.30 Cft.
Weight of 79.6 cft of green wood @ 62 lbs/cft=79.6*62/82.5=59.8 Mds.
_____________________________ __________ ________ ________ __________

Royality of Brush wood. 59.80 Cft 1000.0 % Cft. 598.00

_____________________________ __________ ________ ________ __________


TOTAL 598.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 59.80
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 657.80
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Sawing of wood by machine. 59.80 Cft 80.00 P.Cft. 4784.00

_____________________________ __________ ________ ________ __________


Rs: 4784.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 478.40
_____________________________ __________ ________ ________ __________
TOTAL 5262.40
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 526.24
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 5788.64
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 6446.44
_____________________________ __________ ________ ________ __________
Total material & labour for 100 Nos. Rs: 6446.44

Total material & labour per % Nos. say Rs: 6446.44


___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1119/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(d) (ii) Sharpening one end of pegs 6.0' long 3" - 6" dia.

(Unit of rate per % Nos. pegs)


___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Carpenter. 0.65 Nos. 450.00 P.day. 292.50
Coolies. 0.60 Nos. 250.00 P.day. 150.00
_____________________________ __________ ________ ________ __________
Rs: 442.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 44.25
_____________________________ __________ ________ ________ __________
TOTAL 486.75
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 48.68
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 535.43
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 535.43
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Nos. Rs: 535.43

Total labour rate for 100 Nos. Say Rs: 535.43

Chapter No. 17 1120/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(d) (iii) Driving pegs 6.0' long 3" - 6" dia.(Driven 1.75' below the
available bed or ground)
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies skilled. 1.20 Nos. 250.00 P.day. 300.00
Coolies. 1.20 Nos. 250.00 P.day. 300.00
_____________________________ __________ ________ ________ __________
Rs: 600.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 60.00
_____________________________ __________ ________ ________ __________
TOTAL 660.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 66.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 726.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 726.00
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Nos. Rs: 726.00

Total labour rate for 100 Nos. Say Rs: 726.00

___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1121/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(d) (iv) Tying pegs with Munj Patha Ban (one line, inncluding tying
around the pegs)
(Unit of rate per chain of one row.)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of Ban for one chain lenth of row of killas
including a tie around the pegs.=100' + 50 * 9/24*22/7 = 160 Lft.
Add 10% wastage. = 160' + 16' = 176 Lft. say 175 Lft.
1 Seer of ban covers 250' Length. Hence, weight of 175' ban
= 175/250 =0.70 Seer.

_____________________________ __________ ________ ________ __________


Ban. 0.7 Seer 150.00 P.Seer. 105.00
_____________________________ __________ ________ ________ __________
TOTAL 105.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 10.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 115.50
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Coolies. 0.10 Nos. 250.00 P.day. 25.00

_____________________________ __________ ________ ________ __________


Rs: 25.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 2.50
_____________________________ __________ ________ ________ __________
TOTAL 27.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 2.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 30.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 145.75
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 145.75

Total material & labour for one chain of row. Rs: 145.75
___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1122/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(d) (v) Cutting & supplying brush wood from Canal Plantation or
Private owners, lead within one mile and wattling between stakes
and intertwining (Thickness of wattled brush wood 1.0' average)

(Unit of rate per chain of one row.)


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of brush wood=Lenth =100', Thickness=1.0',Hiegt=4.25'
= 100' * 1' * 4.25' = 425 Cft.
_____________________________ __________ ________ ________ __________

Royality of Brush wood. 425.0 Cft 1000.0 % Cft. 4250.00

TOTAL 4250.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 425.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 4675.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Skilled coolies for 1.80 Nos. 250.00 P.day. 450.00
wattling brush wood.

Rs: 450.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 45.00
_____________________________ __________ ________ ________ __________
TOTAL 495.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 49.50
_____________________________ __________ ________ ________ __________
Sawing cutting of wood by 425.0 650.00 Per %Cft. 2762.50
hand.
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 3307.00
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 7982.00
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 7982.00

Total material & labour for one chain of row. Rs: 7982.00

Chapter No. 17 1123/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(e) (i) Cutting and supplying un-sharpened pegs 6'-1" to 8'-0"
long 4" - 8" dia. Lead with in one mile.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Wood required for 100 Pegs = 100*7.0'*1/2"*1/2"*1/4"*22/7=
= 137.30 Cft. + 20% wastage = 165.00 Cft.
Weight of 165 cft of green wood @ 62 lbs/cft=165*62/82.5=124 Mds.
_____________________________ __________ ________ ________ __________

Royality of Brush wood. 165.0 Cft 1000.0 % Cft. 1650.00

_____________________________ __________ ________ ________ __________


TOTAL 1650.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 165.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 1815.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Sawing of wood by machine. 165.0 Cft 80.00 P.Cft. 13200.00

_____________________________ __________ ________ ________ __________


Rs: 13200.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 1320.00
_____________________________ __________ ________ ________ __________
TOTAL 14520.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 1452.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 15972.00
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 17787.00
_____________________________ __________ ________ ________ __________
Total material & labour for 100 Nos. Rs: 17787.00

Total material & labour per % Nos. say Rs: 17787.00


___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1124/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(e) (ii) Sharpening one end of pegs 6'-1" to 8'-0" long 4" - 8" dia.

(Unit of rate per % Nos. pegs)


___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Carpenter. 0.80 Nos. 450.00 P.day. 360.00
Coolies. 0.80 Nos. 250.00 P.day. 200.00
_____________________________ __________ ________ ________ __________
Rs: 560.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 56.00
_____________________________ __________ ________ ________ __________
TOTAL 616.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 61.60
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 677.60
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 677.60
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Nos. Rs: 677.60

Total labour rate for 100 Nos. Say Rs: 677.60

Chapter No. 17 1125/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(e) (iii) Driving pegs 6'-0" to 8'-0 long 4" - 8" dia.(Driven 2.0'
below the available bed or ground)
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies skilled. 1.30 Nos. 250.00 P.day. 325.00
Coolies. 1.35 Nos. 250.00 P.day. 337.50
_____________________________ __________ ________ ________ __________
Rs: 662.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 66.25
_____________________________ __________ ________ ________ __________
TOTAL 728.75
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 72.88
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 801.63
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 801.63
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Nos. Rs: 801.63

Total labour rate for 100 Nos. Say Rs: 801.63

Chapter No. 17 1126/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(e) (iv) Tying pegs with Munj Patha Ban (one line, inncluding tying
around the pegs)
(Unit of rate per chain of one row.)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of Ban for one chain lenth of row of killas
including a tie around the pegs.=100' + 50 * 9/24*22/7 = 160 Lft.
Add 10% wastage. = 160' + 16' = 176 Lft. say 175 Lft.
1 Seer of ban covers 250' Length. Hence, weight of 175' ban
= 175/250 =0.70 Seer.

_____________________________ __________ ________ ________ __________


Ban. 0.7 Seer 150.00 P.Seer. 105.00
_____________________________ __________ ________ ________ __________
TOTAL 105.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 10.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 115.50
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Coolies. 0.10 Nos. 250.00 P.day. 25.00

_____________________________ __________ ________ ________ __________


Rs: 25.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 2.50
_____________________________ __________ ________ ________ __________
TOTAL 27.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 2.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 30.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 145.75
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 145.75

Total material & labour for one chain of row. Rs: 145.75
___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1127/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

14 Staking and bushing from canal plantation with in one mile.


Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(e) (v) Cutting & supplying brush wood from Canal Plantation or
Private owners, lead within one mile and wattling between stakes
and intertwining (Thickness of wattled brush wood 1.0' average)

(Unit of rate per chain of one row.)


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of brush wood=Lenth =100', Thickness=1.0',Hiegt=5.0'
= 100' * 1' * 5.0' = 500 Cft.
_____________________________ __________ ________ ________ __________

Royality of Brush wood. 500.0 Cft 1000.0 % Cft. 5000.00

_____________________________ __________ ________ ________ __________


TOTAL 5000.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 500.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 5500.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Skilled coolies for 2.10 Nos. 250.00 P.day. 525.00
wattling brush wood.

Rs: 525.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 52.50
_____________________________ __________ ________ ________ __________
TOTAL 577.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 57.75
_____________________________ __________ ________ ________ __________
Sawing cutting of wood by 500.0 650.00 Per %Cft. 3250.00
hand.
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 3885.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 9385.25
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 9385.25

Total material & labour for one chain of row. Rs: 9385.25

Chapter No. 17 1128/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.
15 Staking with Bamboos from marked and bushing from Canal
plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(a) (i) Supplying Bamboos 8'-0" to 10.0' long 2-1/2" to 5" dia.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Bamboos. 100.0 Nos 150.0 Each. 15000.00
TOTAL 15000.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 1500.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 16500.00
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL) 16500.00
_____________________________ __________ ________ ________ __________
Total material for 100 Nos. Rs: 16500.00

Total material for % Nos. say Rs: 16500.00


S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(a) (ii) Sharpening one end of bamboos 8'-1" to 10.0' long 2-1/2"
to 5" dia.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Carpenter. 0.70 Nos. 450.00 P.day. 315.00
Coolies. 0.70 Nos. 250.00 P.day. 175.00
_____________________________ __________ ________ ________ __________
Rs: 490.00
Sundries. 10.00 % 49.00
_____________________________ __________ ________ ________ __________
TOTAL 539.00
Contractor's profit 10.00 % 53.90
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 592.90
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 592.90
Total labour rate for 100 Nos. Rs: 592.90
Total labour rate for 100 Nos. Say Rs: 592.90

Chapter No. 17 1129/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(a) (iii) Driving bamboos 8'-1" to 10' long 2-1/2" to 5" dia (Driven 2.5'
below the available bed or ground) average.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies skilled. 1.45 Nos. 250.00 P.day. 362.50
Coolies. 1.45 Nos. 250.00 P.day. 362.50
_____________________________ __________ ________ ________ __________
Rs: 725.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 72.50
_____________________________ __________ ________ ________ __________
TOTAL 797.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 79.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 877.25
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 877.25
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Nos. Rs: 877.25

Total labour rate for 100 Nos. Say Rs: 877.25

Chapter No. 17 1130/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(a) (iv) Tying bamboos 2-1/2" to 5" dia with munj/ patha ban two
lines including tying around the bamboos.
(Unit of rate per chain of one row.)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of Ban for one chain length.
200 + 50*(15/48 *22/7) = 249 Lft + 10% wastage = 274 Lft.

1 Seer of ban covers 250' Length. Hence, weight of 274' ban


= 274/250 =1.10 Seer.
_____________________________ __________ ________ ________ __________
Ban. 1.1 Seer 150.00 P.Seer. 165.00
TOTAL 165.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 16.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 181.50
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Coolies. 0.15 Nos. 250.00 P.day. 37.50

_____________________________ __________ ________ ________ __________


Rs: 37.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 3.75
_____________________________ __________ ________ ________ __________
TOTAL 41.25
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 4.13
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 45.38
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 226.88
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 226.88

Total material & labour for one chain of row. Rs: 226.88

Chapter No. 17 1131/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(a) (v) Cutting & supplying brush wood from Canal Plantation or
Private owners, lead within one mile and wattling between stakes
and intertwining (Thickness of wattled brush wood 1.0' average)

(Unit of rate per chain of one row.)


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of brush wood=Lenth =100', Thickness=1.0',Hiegt=6.5'
= 100' * 1' * 6.5' = 650 Cft.
_____________________________ __________ ________ ________ __________

Royality of Brush wood. 650.0 Cft 1000.0 % Cft. 6500.00

TOTAL 6500.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 650.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 7150.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Skilled coolies for 2.50 Nos. 250.00 P.day. 625.00
wattling brush wood.

_____________________________ __________ ________ ________ __________


Rs: 625.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 62.50
_____________________________ __________ ________ ________ __________
TOTAL 687.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 68.75
_____________________________ __________ ________ ________ __________
Sawing cutting of wood by 650.0 650.00 Per %Cft. 4225.00
hand.
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 4981.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 12131.25
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 12131.25

Chapter No. 17 1132/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
15 Staking with Bamboos from marked and bushing from Canal
plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(b) (i) Supplying Bamboos 10'-1" to 12.0' long 2-1/2" to 5" dia.

(Unit of rate per % Nos. pegs)


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Bamboos. 100.0 Nos 225.0 Each. 22500.00

_____________________________ __________ ________ ________ __________


TOTAL 22500.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 2250.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 24750.00
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL) 24750.00
_____________________________ __________ ________ ________ __________
Total material for 100 Nos. Rs: 24750.00

Total material for % Nos. say Rs: 24750.00


S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(b) (ii) Sharpening one end of bamboos 10'-1" to 12.0' long 2-1/2"
to 5" dia.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Carpenter. 0.80 Nos. 450.00 P.day. 360.00
Coolies. 0.80 Nos. 250.00 P.day. 200.00
_____________________________ __________ ________ ________ __________
Rs: 560.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 56.00
_____________________________ __________ ________ ________ __________
TOTAL 616.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 61.60
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 677.60
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 677.60
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Nos. Rs: 677.60

Total labour rate for 100 Nos. Say Rs: 677.60

Chapter No. 17 1133/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(b) (iii) Driving bamboos 10'-1" to 12' long 2-1/2" to 5" dia
(Driven 2.75' below the available bed or ground) average.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies skilled. 1.55 Nos. 250.00 P.day. 387.50
Coolies. 1.60 Nos. 250.00 P.day. 400.00
_____________________________ __________ ________ ________ __________
Rs: 787.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 78.75
_____________________________ __________ ________ ________ __________
TOTAL 866.25
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 86.63
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 952.88
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 952.88
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Nos. Rs: 952.88

Total labour rate for 100 Nos. Say Rs: 952.88

Chapter No. 17 1134/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________

S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(b) (iv) Tying bamboos 2-1/2" to 5" dia with BSWG No.10 (Two lines
including tying around the bamboos and third tie around the top
end only)
(Unit of rate per chain of one row.)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of BSSW No.10 for one chain length.
Two lines = 2*(100+50*(15/48 *22/7) = 298 Lft
Top end only = 50 *15/48 *22/7 = 50 Lft.
298 + 50 = 348 Lft + 5% wastage = 366 Lft.
Weight of 100 yards of BSWG No.10 = 13.12 Lbs.
Weight of 366 Lft = 366/300 * 13.12 = 16 lbs = 0.143 Cwt.
_____________________________ __________ ________ ________ __________
B.S.W.G No.10 wire. 0.143 Cwt 5000.0 P.Cwt. 715.00

TOTAL 715.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 71.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 786.50
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Coolies. 0.50 Nos. 250.00 P.day. 125.00
_____________________________ __________ ________ ________ __________
Rs: 125.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 12.50
_____________________________ __________ ________ ________ __________
TOTAL 137.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 13.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 151.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 937.75
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 937.75

Total material & labour for one chain of row. Rs: 937.75
___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1135/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(b) (v) Cutting & supplying brush wood from Canal Plantation or
Private owners, lead within one mile and wattling between stakes
and intertwining (Thickness of wattled brush wood 1.0' average)

(Unit of rate per chain of one row.)


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of brush wood=Lenth =100', Thickness=1.0',Hiegt=8.25'
= 100' * 1' * 8.25' = 825 Cft.
_____________________________ __________ ________ ________ __________

Royality of Brush wood. 825.0 Cft 1000.0 % Cft. 8250.00

TOTAL 8250.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 825.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 9075.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Skilled coolies for 3.00 Nos. 250.00 P.day. 750.00
wattling brush wood.

_____________________________ __________ ________ ________ __________


Rs: 750.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 75.00
_____________________________ __________ ________ ________ __________
TOTAL 825.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 82.50
_____________________________ __________ ________ ________ __________
Sawing cutting of wood by 825.0 Cft 650.00 Per %Cft. 5362.50
hand.
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 6270.00
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 15345.0
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 15345.00

Total material & labour for one chain of row. Rs: 15345.00

Chapter No. 17 1136/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
15 Staking with Bamboos from marked and bushing from Canal
plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(c) (i) Supplying Bamboos 12'-1" to 14.0' long 2-1/2" to 5" dia.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Bamboos. 100.0 Nos 225.0 Each. 22500.00

TOTAL 22500.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 2250.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 24750.00
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL) 24750.00
_____________________________ __________ ________ ________ __________
Total material for 100 Nos. Rs: 24750.00

Total material for % Nos. say Rs: 24750.00


___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(c) (ii) Sharpening one end of bamboos 12'-1" to 14.0' long 2-1/2"
to 5" dia.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Carpenter. 0.90 Nos. 450.00 P.day. 405.00
Coolies. 0.90 Nos. 250.00 P.day. 225.00
_____________________________ __________ ________ ________ __________
Rs: 630.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 63.00
_____________________________ __________ ________ ________ __________
TOTAL 693.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 69.30
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 762.30
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 762.30
Total labour rate for 100 Nos. Rs: 762.30
Total labour rate for 100 Nos. Say Rs: 762.30
___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1137/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(c) (iii) Driving bamboos 12'-1" to 14' long 2-1/2" to 5" dia
(Driven 3.5' below the available bed or ground) average.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies skilled. 1.80 Nos. 250.00 P.day. 450.00
Coolies. 1.80 Nos. 250.00 P.day. 450.00
_____________________________ __________ ________ ________ __________
Rs: 900.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 90.00
_____________________________ __________ ________ ________ __________
TOTAL 990.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 99.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1089.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1089.00
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Nos. Rs: 1089.00

Total labour rate for 100 Nos. Say Rs: 1089.00

___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1138/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(c) (iv) Tying bamboos 2-1/2" to 5" dia with BSWG No.10 (Two lines
including tying around the bamboos and third tie around the top
end only)
(Unit of rate per chain of one row.)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of BSSW No.10 for one chain length.
Two lines = 2*(100+50*(15/48 *22/7) = 298 Lft
Top end only = 50 *15/48 *22/7 = 50 Lft.
298 + 50 = 348 Lft + 5% wastage = 366 Lft.
Weight of 100 yards of BSWG No.10 = 13.12 Lbs.
Weight of 366 Lft = 366/300 * 13.12 = 16 lbs = 0.143 Cwt.
_____________________________ __________ ________ ________ __________
B.S.W.G No.10 wire. 0.143 Cwt 5000.0 P.Cwt. 715.00

TOTAL 715.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 71.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 786.50
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Coolies. 0.50 Nos. 250.00 P.day. 125.00

_____________________________ __________ ________ ________ __________


Rs: 125.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 12.50
_____________________________ __________ ________ ________ __________
TOTAL 137.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 13.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 151.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 937.75
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 937.75

Total material & labour for one chain of row. Rs: 937.75
___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1139/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(c) (v) Cutting & supplying brush wood from Canal Plantation or
Private owners, lead within one mile and wattling between stakes
and intertwining (Thickness of wattled brush wood 1.0' average)

(Unit of rate per chain of one row.)


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of brush wood=Lenth =100', Thickness=1.0',Hiegt=9.50'
= 100' * 1' * 9.5' = 950 Cft.
_____________________________ __________ ________ ________ __________

Royality of Brush wood. 950.0 Cft 1000.0 % Cft. 9500.00

_____________________________ __________ ________ ________ __________


TOTAL 9500.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 950.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 10450.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Skilled coolies for 3.50 Nos. 250.00 P.day. 875.00
wattling brush wood.

Rs: 875.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 87.50
_____________________________ __________ ________ ________ __________
TOTAL 962.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 96.25
_____________________________ __________ ________ ________ __________
Sawing cutting of wood by 950.0 650.00 Per %Cft. 6175.00
hand.
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 7233.8
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 17683.75
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 17683.75

Chapter No. 17 1140/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
15 Staking with Bamboos from marked and bushing from Canal
plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(d) (i) Supplying Bamboos 14'-1" to 16.0' long 2-1/2" to 5" dia.

(Unit of rate per % Nos. pegs)


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Bamboos. 100.0 Nos 285.0 Each. 28500.00

_____________________________ __________ ________ ________ __________


TOTAL 28500.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 2850.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 31350.00
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL) 31350.00
_____________________________ __________ ________ ________ __________
Total material for 100 Nos. Rs: 31350.00

Total material for % Nos. say Rs: 31350.00


S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(d) (ii) Sharpening one end of bamboos 14'-1" to 16.0' long 2-1/2"
to 5" dia.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Carpenter. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 1.00 Nos. 250.00 P.day. 250.00
_____________________________ __________ ________ ________ __________
Rs: 700.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 70.00
_____________________________ __________ ________ ________ __________
TOTAL 770.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 77.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 847.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 847.00
Total labour rate for 100 Nos. Rs: 847.00
Total labour rate for 100 Nos. Say Rs: 847.00

Chapter No. 17 1141/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(d) (iii) Driving bamboos 14'-1" to 16' long 2-1/2" to 5" dia
(Driven 4' below the available bed or ground) average.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies skilled. 2.00 Nos. 250.00 P.day. 500.00
Coolies. 2.00 Nos. 250.00 P.day. 500.00
_____________________________ __________ ________ ________ __________
Rs: 1000.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 100.00
_____________________________ __________ ________ ________ __________
TOTAL 1100.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 110.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1210.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1210.00
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Nos. Rs: 1210.00

Total labour rate for 100 Nos. Say Rs: 1210.00

Chapter No. 17 1142/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________

S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(d) (iv) Tying bamboos 2-1/2" to 5" dia with BSWG No.10 (Two lines
including tying around the bamboos and third tie around the top
end only)
(Unit of rate per chain of one row.)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of BSSW No.10 for one chain length.
Two lines = 2*(100+50*(15/48 *22/7) = 298 Lft
Top end only = 50 *15/48 *22/7 = 50 Lft.
298 + 50 = 348 Lft + 5% wastage = 366 Lft.
Weight of 100 yards of BSWG No.10 = 13.12 Lbs.
Weight of 366 Lft = 366/300 * 13.12 = 16 lbs = 0.143 Cwt.
_____________________________ __________ ________ ________ __________
B.S.W.G No.10 wire. 0.143 Cwt 5000.0 P.Cwt. 715.00

_____________________________ __________ ________ ________ __________


TOTAL 715.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 71.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 786.50
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Coolies. 0.50 Nos. 250.00 P.day. 125.00

_____________________________ __________ ________ ________ __________


Rs: 125.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 12.50
_____________________________ __________ ________ ________ __________
TOTAL 137.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 13.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 151.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 937.75
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 937.75

Chapter No. 17 1143/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for one chain of row. Rs: 937.75
___ _____________________________ __________ ________ ________ __________

S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(d) (v) Cutting & supplying brush wood from Canal Plantation or
Private owners, lead within one mile and wattling between stakes
and intertwining (Thickness of wattled brush wood 1.0' average)

(Unit of rate per chain of one row.)


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of brush wood=Lenth =100', Thickness=1.0',Hiegt=11.0'
= 100' * 1' * 11.0' = 1100 Cft.
_____________________________ __________ ________ ________ __________

Royality of Brush wood. 1100 Cft 1000.0 % Cft. 11000.00

TOTAL 11000.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 1100.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 12100.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Skilled coolies for 4.00 Nos. 250.00 P.day. 1000.00
wattling brush wood.

_____________________________ __________ ________ ________ __________


Rs: 1000.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 100.00
_____________________________ __________ ________ ________ __________
TOTAL 1100.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 110.00
_____________________________ __________ ________ ________ __________
Sawing cutting of wood by 1100 650.00 Per %Cft. 7150.00
hand.
_____________________________ __________ ________ ________ __________

Chapter No. 17 1144/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL PART " B " 8360.0


_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 20460.00
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 20460.00

___ _____________________________ __________ ________ ________ __________

S/N D E S C R I P T I O N.
15 Staking with Bamboos from marked and bushing from Canal
plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(e) (i) Supplying Bamboos 16'-1" to 20.0' long 2-1/2" to 5" dia.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Bamboos. 100.0 Nos 340.0 Each. 34000.00

_____________________________ __________ ________ ________ __________


TOTAL 34000.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 3400.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 37400.00
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL) 37400.00
_____________________________ __________ ________ ________ __________
Total material for 100 Nos. Rs: 37400.00

Total material for % Nos. say Rs: 37400.00


S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(e) (ii) Sharpening one end of bamboos 16'-1" to 20.0' long 2-1/2"
to 5" dia.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Carpenter. 1.20 Nos. 450.00 P.day. 540.00
Coolies. 1.20 Nos. 250.00 P.day. 300.00
Rs: 840.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 84.00
TOTAL 924.00

Chapter No. 17 1145/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 92.40


_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1016.40
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1016.40
Total labour rate for 100 Nos. Rs: 1016.40
Total labour rate for 100 Nos. Say Rs: 1016.40

Chapter No. 17 1146/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(e) (iii) Driving bamboos 16'-1" to 20' long 2-1/2" to 5" dia
(Driven 4' below the available bed or ground) average.
(Unit of rate per % Nos. pegs)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies skilled. 2.40 Nos. 250.00 P.day. 600.00
Coolies. 2.40 Nos. 250.00 P.day. 600.00
_____________________________ __________ ________ ________ __________
Rs: 1200.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 120.00
_____________________________ __________ ________ ________ __________
TOTAL 1320.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 132.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1452.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1452.00
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Nos. Rs: 1452.00

Total labour rate for 100 Nos. Say Rs: 1452.00

Chapter No. 17 1147/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(e) (iv) Tying bamboos 2-1/2" to 5" dia with BSWG No.10 (Two lines
including tying around the bamboos and third tie around the top
end only)
(Unit of rate per chain of one row.)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of BSSW No.10 for one chain length.
Two lines = 2*(100+50*(15/48 *22/7) = 298 Lft
Top end only = 50 *15/48 *22/7 = 50 Lft.
298 + 50 = 348 Lft + 5% wastage = 366 Lft.
Weight of 100 yards of BSWG No.10 = 13.12 Lbs.
Weight of 366 Lft = 366/300 * 13.12 = 16 lbs = 0.143 Cwt.
_____________________________ __________ ________ ________ __________
B.S.W.G No.10 wire. 0.143 Cwt 5000.0 P.Cwt. 715.00
_____________________________ __________ ________ ________ __________
TOTAL 715.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 71.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 786.50
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Coolies. 0.50 Nos. 250.00 P.day. 125.00

_____________________________ __________ ________ ________ __________


Rs: 125.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 12.50
_____________________________ __________ ________ ________ __________
TOTAL 137.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 13.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 151.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 937.75
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 937.75

Chapter No. 17 1148/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for one chain of row. Rs: 937.75
___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

15 Staking with Bamboos from marked and bushing from Canal


plantation or Private source.
Note:-Royalty to be paid to Forest Department or Private owner
if and when required.
(e) (v) Cutting & supplying brush wood from Canal Plantation or
Private owners, lead within one mile and wattling between stakes
and intertwining (Thickness of wattled brush wood 1.0' average)

(Unit of rate per chain of one row.)


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Requirement of brush wood=Lenth =100', Thickness=1.0',Hiegt=14.0'
= 100' * 1' * 14.0' = 1400 Cft.
_____________________________ __________ ________ ________ __________

Royality of Brush wood. 1400 Cft 1000.0 % Cft. 14000.00

TOTAL 14000.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 1400.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 15400.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Skilled coolies for 5.00 Nos. 250.00 P.day. 1250.00
wattling brush wood.

Rs: 1250.0
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 125.00
_____________________________ __________ ________ ________ __________
TOTAL 1375.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 137.50
_____________________________ __________ ________ ________ __________
Sawing cutting of wood by 1400 Cft 650.00 Per %Cft. 9100.00
hand.
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 10612.50
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 26012.5
_____________________________ __________ ________ ________ __________
Total material & labour for one chain of row. Rs: 26012.50

___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1149/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

16 Cutting and supplying brush wood from Canal plantation or from


any other source within one mile.
NOTE:-Royality to be paid to the Forest Department if and when
required.
Measured in thourghly compacted and packed shape before
filling.

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________

Royality of Brush wood. 100.0 Cft 1000.0 % Cft. 1000.00

_____________________________ __________ ________ ________ __________


TOTAL 1000.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 100.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 1100.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Coolies. 1.00 Nos. 250.00 P.day. 250.00

_____________________________ __________ ________ ________ __________


Rs: 250.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 25.00
_____________________________ __________ ________ ________ __________
TOTAL 275.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 27.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 302.50
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 1402.50
_____________________________ __________ ________ ________ __________
Total material & labour for 100 Cft. Rs: 1402.50

Total material & labour per % Cft. say Rs: 1402.50

Chapter No. 17 1150/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________

S/N D E S C R I P T I O N.

17 Filling brush wood only throughly packed.

(B) LABOUR QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies. 0.50 Nos. 250.00 P.day. 125.00
_____________________________ __________ ________ ________ __________
Rs: 125.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 12.50
_____________________________ __________ ________ ________ __________
TOTAL 137.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 13.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 151.25
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 151.25
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Cft. Rs: 151.25

Total labour rate for % Cft. Say Rs: 151.25

Chapter No. 17 1151/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.

18 Fixing enammelled iron gauges flush with masonary including cost


of hooks.

Assume for 12 Lft long gauge.


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Hooks. 6.0 Nos 140.0 P.doz: 70.00

_____________________________ __________ ________ ________ __________


TOTAL 70.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 7.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 77.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00

Coolies. 1.00 Nos. 250.00 P.day. 250.00

_____________________________ __________ ________ ________ __________


Rs: 700.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 70.00
_____________________________ __________ ________ ________ __________
TOTAL 770.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 77.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 70.58 847.00
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 924.00
_____________________________ __________ ________ ________ __________

Chapter No. 17 1152/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for 12 Lft. Rs: 924.00


Total material & labour for 1 Lft. Rs: 77.00
Total material & labour per Lft. say Rs: 77.00

___ _____________________________ __________ ________ ________ __________

S/N D E S C R I P T I O N.

19 Placing boundary pillars in position including digging pits.

Assume for 25 Pillars.


___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 1.00 Nos. 250.00 P.day. 250.00
_____________________________ __________ ________ ________ __________
Rs: 700.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 70.00
_____________________________ __________ ________ ________ __________
TOTAL 770.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 77.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 847.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 847.00
_____________________________ __________ ________ ________ __________
Total labour rate for 25 Nos. Rs: 847.00
Total labour rate for 1 No. Rs: 33.88
Total labour rate for each No. Say Rs: 33.88
S/N D E S C R I P T I O N.

20 Coverning road 10' - 12' wide with 3" sarkanda or jungle upto
one chain lead.

Assume for 5 chains.


___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies. 6.00 Nos. 250.00 P.day. 1500.00
_____________________________ __________ ________ ________ __________
Rs: 1500.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 150.00
_____________________________ __________ ________ ________ __________
TOTAL 1650.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 165.00
_____________________________ __________ ________ ________ __________

Chapter No. 17 1153/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL PART " B " 1815.00


_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1815.00
_____________________________ __________ ________ ________ __________
Total labour rate for 5 Chains. Rs: 1815.00
Total labour rate for 1 Chains. Rs: 363.00
Total labour rate for one Chain. Say Rs: 363.00

S/N D E S C R I P T I O N.

21 (a) Gachi pitching 1' thick.

(B) LABOUR QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies. 6.50 Nos. 250.00 P.day. 1625.00
_____________________________ __________ ________ ________ __________
Rs: 1625.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 162.50
_____________________________ __________ ________ ________ __________
TOTAL 1787.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 178.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1966.25
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1966.25
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Sft. Rs: 1966.25

Total labour rate for 100 Sft. Say Rs: 1966.25


S/N D E S C R I P T I O N.

21 (b) Gachi pitching done with silt clearance and berm dressing.

___ _____________________________ __________ ________ ________ __________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies. 5.50 Nos. 250.00 P.day. 1375.00
_____________________________ __________ ________ ________ __________
Rs: 1375.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 137.50
_____________________________ __________ ________ ________ __________
TOTAL 1512.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 151.25

Chapter No. 17 1154/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


TOTAL PART " B " 1663.75
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1663.75
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Sft. Rs: 1663.75

Total labour rate for 100 Sft. Say Rs: 1663.75

Chapter No. 17 1155/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
HAND PUMPS AND PRESSURE PIPE.
22 Cutting pipes upto 2" dia.

Assume for 25 cuts.


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Blacksmith. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 1.00 Nos. 250.00 P.day. 250.00
_____________________________ __________ ________ ________ __________
Rs: 700.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 70.00
_____________________________ __________ ________ ________ __________
TOTAL 770.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 77.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 847.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 847.00
_____________________________ __________ ________ ________ __________
Total labour rate for 25 Cuts. Rs: 847.00
Total labour rate for 1 Cuts. Rs: 33.88
Total labour rate per Cut. Say Rs: 33.88
S/N D E S C R I P T I O N.

HAND PUMPS AND PRESSURE PIPE.


23 Cutting pipes above 2" dia.

Assume for 20 cuts.


___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Blacksmith. 1.75 Nos. 450.00 P.day. 787.50
Coolies. 1.25 Nos. 250.00 P.day. 312.50
_____________________________ __________ ________ ________ __________
Rs: 1100.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 110.00
_____________________________ __________ ________ ________ __________
TOTAL 1210.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 121.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1331.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1331.00
_____________________________ __________ ________ ________ __________
Total labour rate for 20 Cuts. Rs: 1331.00
Total labour rate for 1 Cuts. Rs: 66.55
Total labour rate per Cut. Say Rs: 66.55

Chapter No. 17 1156/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
HAND PUMPS AND PRESSURE PIPE.
24 Threading pipe ends 1-1/2" to 4" dia.

Assume for 24 Nos of ends.


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Blacksmith. 1.50 Nos. 450.00 P.day. 675.00
Coolies. 1.00 Nos. 250.00 P.day. 250.00
_____________________________ __________ ________ ________ __________
Rs: 925.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 92.50
_____________________________ __________ ________ ________ __________
TOTAL 1017.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 101.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1119.25
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1119.25
_____________________________ __________ ________ ________ __________
Total labour rate for 24 Nos of ends. Rs: 1119.25
Total labour rate for 1 Nos of end. Rs: 46.64
Total labour rate per each end. Say Rs: 46.64
S/N D E S C R I P T I O N.

HAND PUMPS AND PRESSURE PIPE.


25 Assembling 1-1/2" dia pressure pipes.

Assume for 600 Lft.


___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Fitter. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 1.50 Nos. 250.00 P.day. 375.00
_____________________________ __________ ________ ________ __________
Rs: 825.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 82.50
_____________________________ __________ ________ ________ __________
TOTAL 907.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 90.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 998.25
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 998.25
_____________________________ __________ ________ ________ __________
Total labour rate for 600 Lft. Rs: 998.25
Total labour rate for 100 Lft. Rs: 166.38
Total labour rate per % Lft. Say Rs: 166.38

Chapter No. 17 1157/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
HAND PUMPS AND PRESSURE PIPE.
26 Boring and fixing 1-1/2" dia pressure pipe.
(a) In ordinary soil.
Assume for 30 Lft.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Fitter. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.50 Nos. 250.00 P.day. 875.00
_____________________________ __________ ________ ________ __________
Rs: 1325.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 132.50
_____________________________ __________ ________ ________ __________
TOTAL 1457.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 145.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1603.25
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1603.25
_____________________________ __________ ________ ________ __________
Total labour rate for 30 Lft. Rs: 1603.25
Total labour rate for 1 Lft. Rs: 53.44
Total labour rate per Lft. Say Rs: 53.44
S/N D E S C R I P T I O N.
HAND PUMPS AND PRESSURE PIPE.
26 Boring and fixing 1-1/2" dia pressure pipe.
(b) In clay.
Assume for 30 Lft.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Fitter. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 8.00 Nos. 250.00 P.day. 2000.00
_____________________________ __________ ________ ________ __________
Rs: 2450.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 245.00
_____________________________ __________ ________ ________ __________
TOTAL 2695.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 269.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 2964.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 2964.50
_____________________________ __________ ________ ________ __________
Total labour rate for 30 Lft. Rs: 2964.50
Total labour rate for 1 Lft. Rs: 98.82
Total labour rate per Lft. Say Rs: 98.82

S/N D E S C R I P T I O N.
HAND PUMPS AND PRESSURE PIPE.

Chapter No. 17 1158/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

26 Boring and fixing 1-1/2" dia pressure pipe.


(c) In shingle.
Assume for 30 Lft.
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Fitter. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 12.50 Nos. 250.00 P.day. 3125.00
_____________________________ __________ ________ ________ __________
Rs: 3575.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 357.50
_____________________________ __________ ________ ________ __________
TOTAL 3932.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 393.25
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 4325.75
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 4325.75
_____________________________ __________ ________ ________ __________
Total labour rate for 30 Lft. Rs: 4325.75
Total labour rate for 1 Lft. Rs: 144.19
Total labour rate per Lft. Say Rs: 144.19
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.

HAND PUMPS AND PRESSURE PIPE.


27 Repairs to hand pump pullingout and refitting.

Assume labour for pulling & refitting for 40 Lft.

(B) LABOUR QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_____________________________ __________ ________ ________ __________
Fitter. 0.50 Nos. 450.00 P.day. 225.00
Coolies. 2.00 Nos. 250.00 P.day. 500.00
_____________________________ __________ ________ ________ __________
Rs: 725.00
Sundries. 10.00 % 72.50
TOTAL 797.50
Contractor's profit 10.00 % 79.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 877.25
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 877.25
Total labour rate for 40 Lft. Rs: 877.25
Total labour rate for 1 Lft. Rs: 21.93
Total labour rate per Lft. Say Rs: 21.93

S/N D E S C R I P T I O N.

HAND PUMPS AND PRESSURE PIPE.


28 Fixing hand pump (machine only)
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________

Chapter No. 17 1159/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Fitter. 0.40 Nos. 450.00 P.day. 180.00

_____________________________ __________ ________ ________ __________


Rs: 180.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 18.00
_____________________________ __________ ________ ________ __________
TOTAL 198.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 19.80
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 217.80
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 217.80
_____________________________ __________ ________ ________ __________
Total labour rate for Each No. say Rs: 217.80
S/N D E S C R I P T I O N.
REST HOUSE FURNITURE AND FUEL ETC.
29 Washing Niwar of bed.
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Soap, etc. L.S 25.00
_____________________________ __________ ________ ________ __________
TOTAL 25.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 2.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 27.50
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Coolies.(Washerman) 1.00 Nos. 250.00 P.day. 250.00
_____________________________ __________ ________ ________ __________
Rs: 250.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 25.00
_____________________________ __________ ________ ________ __________
TOTAL 275.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 27.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 302.50
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 330.00
_____________________________ __________ ________ ________ __________
Total material & labour for each bed. Rs: 330.00

S/N D E S C R I P T I O N.
REST HOUSE FURNITURE AND FUEL ETC.
30 Washing Durries.
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Soap, etc. L.S 75.00
_____________________________ __________ ________ ________ __________

Chapter No. 17 1160/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 75.00
Contractor's profit 10.00 % 7.50
TOTAL PART " A " 82.50
_____________________________ __________ ________ ________ __________
_____________________________ __________ ________ ________ __________
Coolies.(Washerman) 1.00 Nos. 250.00 P.day. 250.00
_____________________________ __________ ________ ________ __________
Rs: 250.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 25.00
TOTAL 275.00
Contractor's profit 10.00 % 27.50
TOTAL PART " B " 302.50
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 385.00
_____________________________ __________ ________ ________ __________
Total material & labour for each bed. Rs: 385.00
S/N D E S C R I P T I O N.
31 Re-canning Chairs.
(a) Office chairs single plastic canning seat only.
Assume for 4 Nos. of chairs.
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cane. 12.0 Oz 5 P.Oz: 60.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 6.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 66.00
(B) LABOUR
Caners. (Skilled cooly) 2.00 Nos. 250.00 P.day. 500.00
_____________________________ __________ ________ ________ __________
Rs: 500.00
Sundries. 10.00 % 50.00
_____________________________ __________ ________ ________ __________
TOTAL 550.00
Contractor's profit 10.00 % 55.00
TOTAL PART " B " 151.25 605.00
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 671.00
Total material & labour for 4 Nos. Rs: 671.00
Total material & labour for each No. Rs: 167.75

S/N D E S C R I P T I O N.
31 Re-canning Chairs.
(b) Office chairs double canning seat only.
Assume for 3 Nos. of chairs.
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Cane. 12.0 Oz 5 P.Oz: 60.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 6.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 66.00
(B) LABOUR
_____________________________ __________ ________ ________ __________

Chapter No. 17 1161/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Caners. (Skilled cooly) 2.00 Nos. 250.00 P.day. 500.00


Rs: 500.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 50.00
TOTAL 550.00
Contractor's profit 10.00 % 55.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 201.67 605.00
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 671.00
_____________________________ __________ ________ ________ __________
Total material & labour for 3 Nos. Rs: 671.00
Total material & labour for each No. Rs: 223.67
S/N D E S C R I P T I O N.
31 Re-canning Chairs.
(c) Office chairs single plastic canning back only.
Assume for 6Nos. of chairs.
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cane. 10.5 5 P.Oz: 52.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 5.25
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 57.75
(B) LABOUR
_____________________________ __________ ________ ________ __________
Caners. (Skilled cooly) 3.00 Nos. 250.00 P.day. 750.00
Rs: 750.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 75.00
TOTAL 825.00
Contractor's profit 10.00 % 82.50
TOTAL PART " B " 151.25 907.50
TOTAL (MATERIAL + LABOUR) 965.25
Total material & labour for 6 Nos. Rs: 965.25
Total material & labour for each No. Rs: 160.88

S/N D E S C R I P T I O N.
31 Re-canning Chairs.
(d) Office chairs double canning back only.
Assume for 4 Nos. of chairs.
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cane. 8.0 Oz 5 P.Oz: 40.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 4.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 44.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Caners. (Skilled cooly) 2.50 Nos. 250.00 P.day. 625.00
_____________________________ __________ ________ ________ __________

Chapter No. 17 1162/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Rs: 625.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 62.50
_____________________________ __________ ________ ________ __________
TOTAL 687.50
Contractor's profit 10.00 % 68.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 189.06 756.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 800.25
_____________________________ __________ ________ ________ __________
Total material & labour for 4 Nos. Rs: 800.25
Total material & labour for each No. Rs: 200.06

___ _____________________________ __________ ________ ________ __________


___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
31 Re-canning Chairs.
(e) Easy chairs single plastic canning seat only.
Assume for 4 Nos. of chairs.
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cane. 16.0 Oz 5 P.Oz: 80.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 8.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 88.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Caners. (Skilled cooly) 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 750.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 75.00
_____________________________ __________ ________ ________ __________
TOTAL 825.00

Chapter No. 17 1163/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 82.50


_____________________________ __________ ________ ________ __________
TOTAL PART " B " 226.88 907.50
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 995.50
_____________________________ __________ ________ ________ __________
Total material & labour for 4 Nos. Rs: 995.50
Total material & labour for each No. Rs: 248.88

S/N D E S C R I P T I O N.
31 Re-canning Chairs.
(f) Easy chairs double canning back only.
Assume for 3 Nos. of chairs.
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cane. 18.0 Oz 5 P.Oz: 90.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 9.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 99.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Caners. (Skilled cooly) 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 750.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 75.00
_____________________________ __________ ________ ________ __________
TOTAL 825.00
Contractor's profit 10.00 % 82.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 302.50 907.50
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 1006.50
_____________________________ __________ ________ ________ __________
Total material & labour for 3 Nos. Rs: 1006.50

Chapter No. 17 1164/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour for each No. Rs: 335.50

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.
31 Re-canning Chairs.
(g) Easy chairs double canning seat only.
Assume for 3 Nos. of chairs.
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cane. 18.0 Oz 5 P.Oz: 90.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 9.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 99.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Caners. (Skilled cooly) 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 750.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 75.00
_____________________________ __________ ________ ________ __________
TOTAL 825.00
Contractor's profit 10.00 % 82.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 302.5 907.50
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 1006.50
_____________________________ __________ ________ ________ __________
Total material & labour for 3 Nos. Rs: 1006.50
Total material & labour for each No. Rs: 335.50
___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1165/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
31
(g) Easy chairs single canning seat only.
(I) back end seat in one piece
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cane Superier. 12.0 Oz 1.2 P.Oz: 14.40
__________ ________ ________ __________
Contractor's profit 10.00 % 1.44
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 15.84
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Caners. 2.00 Nos. 120.00 P.day. 240.00
_____________________________ __________ ________ ________ __________
Rs: 240.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 24.00
_____________________________ __________ ________ ________ __________
TOTAL 264.00
Contractor's profit 10.00 % 26.40
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 96.8 290.40
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 306.24
_____________________________ __________ ________ ________ __________
Total material & labour for 3 Nos. Rs: 306.24
Total material & labour for each No. Rs: 102.08
___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1166/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
31 Re-canning Chairs.
(h) Easy chairs double canning back and seat in one piece or
couches canned.
Assume area about 16 sft.
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cane. 12.0 Oz 250.00 P.Kg 63.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 6.35
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 69.85
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Caners. (Skilled cooly) 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 750.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 75.00
_____________________________ __________ ________ ________ __________
TOTAL 825.00
Contractor's profit 10.00 % 82.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 907.50
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 977.35
_____________________________ __________ ________ ________ __________
Total material & labour for each No. Rs: 977.35

Chapter No. 17 1167/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________

S/N D E S C R I P T I O N.
32 Making and fixing Hat pegs ordinary.

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_____________________________ __________ ________ ________ __________
Sheesham wood=1*2.5'*0.4'*0.1'+0.3'*0.75*0.2'*0.1'+20%WAs:=0.174
Sheesham wood. 0.174 2300 P.Cft. 400.20
Polish & nails. L.S 8.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 40.82
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 449.02
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Carpenter. 0.25 Nos. 450.00 P.day. 112.50
_____________________________ __________ ________ ________ __________
TOTAL Rs: 112.50
Sundries. 10.00 % 11.25
_____________________________ __________ ________ ________ __________
TOTAL 123.75
Contractor's profit 10.00 % 12.38
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 136.13
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 585.15
_____________________________ __________ ________ ________ __________
Total material & labour for each No. Rs: 585.15
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
33 Weaving charpoy.

___ _____________________________ __________ ________ ________ __________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies. 0.75 Nos. 250.00 P.day. 187.50
_____________________________ __________ ________ ________ __________
Rs: 187.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 18.75
TOTAL 206.25
Contractor's profit 10.00 % 20.63
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 226.88
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 226.88
_____________________________ __________ ________ ________ __________
Total labour rate for Each No. Rs: 226.88
___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

Chapter No. 17 1168/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

34 Sweeping chimneys.
Assume for 12 Nos.
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Rope, rags etc. L.S 30.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 3.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 33.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
TOTAL Rs: 750.00
Sundries. 10.00 % 75.00
_____________________________ __________ ________ ________ __________
TOTAL 825.00
Contractor's profit 10.00 % 82.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 75.63 907.50
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 940.50
_____________________________ __________ ________ ________ __________
Total material & labour for 12 Nos. Rs: 940.50
Total material & labour for each No. Rs: 78.38

S/N D E S C R I P T I O N.

35 Picture railing including making fixing and painting.


(size 0.3'*0.1'*15' + 10% wastage.)= 0.49 Cft. say 0.50 Cft.

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________

Chapter No. 17 1169/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Deodar wood. 0.50 Cft 4000.0 P.Cft. 2000.00

Paint. 0.38 Gallon 1600.00 P.Gallon. 60.80

Nails. 0.0625 KG 110.00 P.KG 6.88

_____________________________ __________ ________ ________ __________


TOTAL 2067.68
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 206.77
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 2274.44
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Carpenter. 1.00 Nos. 450.00 P.day. 450.00

Painter. 0.03 Nos. 450.00 P.day. 13.50

_____________________________ __________ ________ ________ __________


Rs: 463.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 46.35
_____________________________ __________ ________ ________ __________
TOTAL 509.85
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 50.99
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 37.39 560.84
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 2835.28
_____________________________ __________ ________ ________ __________
Total material & labour for 15 Lft. Rs: 2835.28
Total material & labour for 1 Lft. Rs: 189.02
Total material & labour per Lft. say Rs: 189.02
___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

36 Flapping G.I. pipes for bath room drains.

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________

Cost of flaps i/c higes. L.S 50.00

Chapter No. 17 1170/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


TOTAL 50.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 5.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 55.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Fitters. 1.00 Nos. 450.00 P.day. 450.00

_____________________________ __________ ________ ________ __________


Rs: 450.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 45.00
_____________________________ __________ ________ ________ __________
TOTAL 495.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 49.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 544.50
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 599.50
_____________________________ __________ ________ ________ __________
Total material & labour for each No. Rs: 599.50
___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.

37 Cutting fuel wood from plantation.

Assume for 15 Maunds.


___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies. 1.50 Nos. 250.00 P.day. 375.00

Rs: 375.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 37.50
_____________________________ __________ ________ ________ __________
TOTAL 412.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 41.25
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 453.75
_____________________________ __________ ________ ________ __________

Chapter No. 17 1171/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (LABOUR) 453.75


_____________________________ __________ ________ ________ __________
Total labour rate per Maund. Rs: 30.25
Total labour rate per Maund. say Rs: 30.25
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.

38 Splitting fuel wood.

Assume for 10 Maunds.


___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies. 2.00 Nos. 250.00 P.day. 500.00

Rs: 500.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 50.00
_____________________________ __________ ________ ________ __________
TOTAL 550.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 55.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 605.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 605.00
_____________________________ __________ ________ ________ __________
Total labour rate per Maund. Rs: 60.50
Total labour rate per Maund. say Rs: 60.50

S/N D E S C R I P T I O N.
39 Burning charcoal including loading un-loading and repairing kiln.
Assume for 100 Maunds.
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies for repairing. 3.00 Nos. 250.00 P.day. 750.00
Coolies for loading 20.00 Nos. 250.00 P.day. 5000.00
unloading.
Coolies skilled. 10.00 Nos. 250.00 P.day. 2500.00
Mason for repairing kiln. 1.00 Nos. 450.00 P.day. 450.00
Rs: 8700.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 870.00
_____________________________ __________ ________ ________ __________
TOTAL 9570.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 957.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 10527.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 10527.00
_____________________________ __________ ________ ________ __________
Total labour rate per Maund. Rs: 105.27
Total labour rate per Maund. say Rs: 105.27
___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1172/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
40 Filling cement bags with coal and sewing. (i/c cost of strings)
Assume for 400 Cft.
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
String (Sutli) L.S 25.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 2.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 27.50
(B) LABOUR
Coolies. 10.25 Nos. 250.00 P.day. 2562.50
Rs: 2562.50
Sundries. 10.00 % 256.25
_____________________________ __________ ________ ________ __________
TOTAL 2818.75
Contractor's profit 10.00 % 281.88
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 775.16 3100.63
TOTAL (MATERIAL + LABOUR) 3128.13
_____________________________ __________ ________ ________ __________
Total material & labour for 400 Cft. Rs: 3128.13
Total material & labour per 100 Cft. Rs: 782.03
Total material & labour per 100 Cft. Rs: 782.03

S/N D E S C R I P T I O N.
41 Ploughing 3 times.

___ _____________________________ __________ ________ ________ __________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Bullockman with one pair 3.25 Nos. 450.00 P.day. 1462.50
of bullock each for
ploughing 3 times.
_____________________________ __________ ________ ________ __________
Rs: 1462.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 146.25
_____________________________ __________ ________ ________ __________
TOTAL 1608.75
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 160.88
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1769.63
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1769.63
_____________________________ __________ ________ ________ __________
Total labour rate per Acre. Rs: 1769.63
___ _____________________________ __________ ________ ________ __________
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
42 Levelling dressing and making lawns.

___ _____________________________ __________ ________ ________ __________


(B) LABOUR QUANTITY RATE UNIT AMOUNT

Chapter No. 17 1173/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies. (Skilled) 0.60 Nos. 250.00 P.day. 150.00

_____________________________ __________ ________ ________ __________


Rs: 150.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 15.00
_____________________________ __________ ________ ________ __________
TOTAL 165.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 16.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 181.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 181.50
_____________________________ __________ ________ ________ __________
Total labour rate per % Sft. Rs: 181.50
___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.
43 Turfing lawns (excluding cost of turf)

(B) LABOUR QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_____________________________ __________ ________ ________ __________
Mali. 0.50 Nos. 450.00 P.day. 225.00
_____________________________ __________ ________ ________ __________
Rs: 225.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 22.50
TOTAL 247.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 24.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 272.25
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 272.25
_____________________________ __________ ________ ________ __________
Total labour rate per % Sft. Rs: 272.25
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
44 Supplying Manure.

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cost of manure. L.S 75.00

_____________________________ __________ ________ ________ __________


Contractor's profit 10.00 % 7.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 82.50
_____________________________ __________ ________ ________ __________

Chapter No. 17 1174/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(B) LABOUR
_____________________________ __________ ________ ________ __________
Cart with cartman. 0.25 Nos. 425.00 P.day. 106.25
Rs: 106.25
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 10.63
_____________________________ __________ ________ ________ __________
TOTAL 116.88
Contractor's profit 10.00 % 11.69
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 128.56
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 211.06
Total material & labour per cart. Rs: 211.06

S/N D E S C R I P T I O N.
45 Supplying and fixing iron grating for fire places.

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_____________________________ __________ ________ ________ __________
Cost of grating. 3.70 Cwt 2100.00 P.Cwt. 69.38

_____________________________ __________ ________ ________ __________


Contractor's profit 10.00 % 6.94
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 76.31
_____________________________ __________ ________ ________ __________
(B) LABOUR
Mason. 0.10 Nos. 450.00 P.day. 45.00
Coolies. 0.05 Nos. 250.00 P.day. 12.50
_____________________________ __________ ________ ________ __________
Rs: 45.00
Sundries. 10.00 % 4.50
_____________________________ __________ ________ ________ __________
TOTAL 49.50
Contractor's profit 10.00 % 4.95
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 54.45
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 130.76
_____________________________ __________ ________ ________ __________
Total material & labour per sft. Rs: 130.76
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
46 Fixing copper flashing i/c cutting of sheets, groving & riveting.
Assume for 25 Lft.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Blacksmith. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 1.00 Nos. 250.00 P.day. 250.00
_____________________________ __________ ________ ________ __________
Rs: 700.00
Sundries. 10.00 % 70.00
_____________________________ __________ ________ ________ __________

Chapter No. 17 1175/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 770.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 77.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 847.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 847.00
Total labour rate per 25 Lft. Rs: 847.00
Total labour rate per Lft. say Rs: 33.88

S/N D E S C R I P T I O N.
47 Washing punkha frills.
Assume for 4 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Washerman. (Skilled cooly) 1.00 Nos. 250.00 P.day. 250.00
_____________________________ __________ ________ ________ __________
Rs: 250.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 25.00
_____________________________ __________ ________ ________ __________
TOTAL 275.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 27.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 302.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 302.50
_____________________________ __________ ________ ________ __________
Total labour rate per 4 Nos. Rs: 302.50
Total labour rate per each No. say Rs: 75.63
___ _____________________________ __________ ________ ________ __________
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
48 Washing (a) Table cloth.
Assume for 8 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Washerman. (Skilled cooly) 0.50 Nos. 250.00 P.day. 125.00
_____________________________ __________ ________ ________ __________
Rs: 125.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 12.50
_____________________________ __________ ________ ________ __________
TOTAL 137.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 13.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 151.25
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 151.25
_____________________________ __________ ________ ________ __________
Total labour rate per 8 Nos. Rs: 151.25

Chapter No. 17 1176/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total labour rate per each No. say Rs: 18.91


___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.
48 Washing (b) MNapkins, dusters etc.
Assume for 13 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Washerman. (Skilled cooly) 0.50 Nos. 250.00 P.day. 125.00
_____________________________ __________ ________ ________ __________
Rs: 125.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 12.50
_____________________________ __________ ________ ________ __________
TOTAL 137.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 13.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 151.25
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 151.25
_____________________________ __________ ________ ________ __________
Total labour rate per 13 Nos. Rs: 151.25
Total labour rate per each No. say Rs: 11.63
___ _____________________________ __________ ________ ________ __________
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
49 Slit clearing 10' dia wells and removal of slush out side the
compound.
(a) Upto 10' depth of slush.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Divers. 4.00 Nos. 250.00 P.day. 1000.00
Coolies. 8.00 Nos. 250.00 P.day. 2000.00
_____________________________ __________ ________ ________ __________
Rs: 3000.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 300.00
_____________________________ __________ ________ ________ __________
TOTAL 3300.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 330.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 3630.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 3630.00
_____________________________ __________ ________ ________ __________
Total labour rate per each well. say Rs: 3630.00
___ _____________________________ __________ ________ ________ __________

S/N D E S C R I P T I O N.
49 Slit clearing 10' dia wells and removal of slush out side the

Chapter No. 17 1177/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

compound.
(b) Beyond 10' depth of slush.
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Divers. 8.00 Nos. 250.00 P.day. 2000.00
Coolies. 16.00 Nos. 250.00 P.day. 4000.00
_____________________________ __________ ________ ________ __________
Rs: 6000.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 600.00
_____________________________ __________ ________ ________ __________
TOTAL 6600.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 660.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 7260.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 7260.00
_____________________________ __________ ________ ________ __________
Total labour rate per each well. say Rs: 7260.00
___ _____________________________ __________ ________ ________ __________
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
MASONRY WORK.
50 Hoisting & placing sleepers for centering i/c carriage within
one chain.
assume for 36 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Masons. 0.50 Nos. 450.00 P.day. 225.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 975.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 97.50
_____________________________ __________ ________ ________ __________
TOTAL 1072.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 107.25
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1179.75
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1179.75
_____________________________ __________ ________ ________ __________
Total labour rate for 36 Nos. Rs: 1179.75
Total labour rate for each No. say Rs: 32.77
S/N D E S C R I P T I O N.
MASONRY WORK.
51 Dismentling sleepers from centering i/c stacking within one chain.
assume for 70 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________

Chapter No. 17 1178/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Coolies.(skilled) 1.00 Nos. 250.00 P.day. 250.00


Coolies. 7.50 Nos. 250.00 P.day. 1875.00
_____________________________ __________ ________ ________ __________
Rs: 2125.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 212.50
_____________________________ __________ ________ ________ __________
TOTAL 2337.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 233.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 2571.25
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 2571.25
_____________________________ __________ ________ ________ __________
Total labour rate for 70 Nos. Rs: 2571.25
Total labour rate for each No. say Rs: 36.73
___ _____________________________ __________ ________ ________ __________
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
MASONRY WORK.
52 Filling expansion joints with bitumen.
assume for 10 Lft.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies.(skilled) 0.75 Nos. 250.00 P.day. 187.50
_____________________________ __________ ________ ________ __________
Rs: 187.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 18.75
_____________________________ __________ ________ ________ __________
TOTAL 206.25
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 20.63
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 226.88
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 226.88
_____________________________ __________ ________ ________ __________
Total labour rate for 10 Lft. Rs: 226.88
Total labour rate per Lft. say Rs: 22.69

S/N D E S C R I P T I O N.
MASONRY WORK.
53 Dredging sumps.

___ _____________________________ __________ ________ ________ __________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies. 4.75 Nos. 250.00 P.day. 1187.50
_____________________________ __________ ________ ________ __________
Rs: 1187.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 118.75

Chapter No. 17 1179/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


TOTAL 1306.25
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 130.63
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1436.88
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1436.88
_____________________________ __________ ________ ________ __________
Total labour rate for each shift. Rs: 1436.88
___ _____________________________ __________ ________ ________ __________
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
MASONRY WORK.
54 Moree corners.
(in addition to masonary work)
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 0.20 Nos. 450.00 P.day. 90.00
_____________________________ __________ ________ ________ __________
Rs: 90.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 9.00
_____________________________ __________ ________ ________ __________
TOTAL 99.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 9.90
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 108.90
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 108.90
_____________________________ __________ ________ ________ __________
Total labour rate for each No. Rs: 108.90
___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.
MASONRY WORK.
55 Chamfering sides of head regulators and masonary walls to
increase width.
Assume for 25 Sft.
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 1.00 Nos. 250.00 P.day. 250.00
_____________________________ __________ ________ ________ __________
Rs: 700.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 70.00
_____________________________ __________ ________ ________ __________
TOTAL 770.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 77.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 847.00

Chapter No. 17 1180/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


TOTAL (LABOUR) 847.00
_____________________________ __________ ________ ________ __________
Total labour rate for 25 Sft. Rs: 847.00
Total labour rate per Sft. Rs: 33.88
___ _____________________________ __________ ________ ________ __________
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
MASONRY WORK.
56 Fixing 'U' bolt in masonary or concrete including levelling for
fixing angle iron post.
Assume for 10 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Blacksmith. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 1.00 Nos. 250.00 P.day. 250.00
_____________________________ __________ ________ ________ __________
Rs: 1150.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 115.00
_____________________________ __________ ________ ________ __________
TOTAL 1265.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 126.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1391.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1391.50
_____________________________ __________ ________ ________ __________
Total labour rate for 10 Nos. Rs: 1391.50
Total labour rate per each No. Rs: 139.15

S/N D E S C R I P T I O N.
57 Replacing kallar eaten bricks.
Assume 50 Bricks.
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Bricks. 50.0 5000.00 %o Nos. 250.00
cement + sand. L.S 75.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 32.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 357.50
_____________________________ __________ ________ ________ __________
(B) LABOUR
Mason. 2.00 Nos. 450.00 P.day. 900.00
Coolies. 1.00 Nos. 250.00 P.day. 250.00
Rs: 1150.00
Sundries. 10.00 % 115.00
_____________________________ __________ ________ ________ __________
TOTAL 1265.00
Contractor's profit 10.00 % 126.50
_____________________________ __________ ________ ________ __________

Chapter No. 17 1181/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL PART " B " 13.92 1391.50


_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 1749.00
_____________________________ __________ ________ ________ __________
Total material & labour for 50 Bricks. Rs: 1749.00
Total material & labour for each Bricks. Rs: 34.98
Total material & labour for each Bricks. SAY Rs: 34.98
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
MASONRY WORK.
58 Un-watering by hand.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies. 3.75 Nos. 250.00 P.day. 937.50
_____________________________ __________ ________ ________ __________
Rs: 937.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 93.75
TOTAL 1031.25
Contractor's profit 10.00 % 103.13
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1134.38
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1134.38
_____________________________ __________ ________ ________ __________
Total labour rate for 100 Cft. Rs: 1134.38
Total labour rate per %0 Cft. say Rs: 1134.38

S/N D E S C R I P T I O N.
59 Repairing carners of bridges and other hydraulic masonry works.

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_____________________________ __________ ________ ________ __________
Bricks. 10.0 Nos. 5000.00 %o Nos. 50.00
Cement. 0.08 Cwt 400.00 P.Cwt. 32.00
Sand. 0.25 Cft 2425.00 % Cft. 6.06
TOTAL 88.06
Contractor's profit 10.00 % 8.81
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 96.87
(B) LABOUR
_____________________________ __________ ________ ________ __________
Mason. 0.25 Nos. 450.00 P.day. 112.50
Coolies. 0.25 Nos. 250.00 P.day. 62.50
_____________________________ __________ ________ ________ __________
Rs: 175.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 17.50
_____________________________ __________ ________ ________ __________
TOTAL 192.50
Contractor's profit 10.00 % 19.25
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 211.75
_____________________________ __________ ________ ________ __________

Chapter No. 17 1182/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (MATERIAL + LABOUR) 308.62


_____________________________ __________ ________ ________ __________
Total material & labour for each No. Rs: 308.62
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
MASONRY WORK.
60 Breaking brick ballast screening and stacking.
(a) 2" ring.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
TOTAL Rs: 750.00
Sundries. 10.00 % 75.00
_____________________________ __________ ________ ________ __________
TOTAL 825.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 82.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 907.50
TOTAL (LABOUR) 907.50
Total labour rate per % Cft. say Rs: 907.50

S/N D E S C R I P T I O N.
MASONRY WORK.
60 Breaking brick ballast screening and stacking.
(b) 1-1/2" ring.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies. 3.50 Nos. 250.00 P.day. 875.00
_____________________________ __________ ________ ________ __________
Rs: 875.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 87.50
_____________________________ __________ ________ ________ __________
TOTAL 962.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 96.25
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1058.75
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1058.75
_____________________________ __________ ________ ________ __________
Total labour rate per % Cft. say Rs: 1058.75
___ _____________________________ __________ ________ ________ __________
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
MASONRY WORK.
60 Breaking brick ballast screening and stacking.
(c) 1" ring.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:

Chapter No. 17 1183/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


Coolies. 4.00 Nos. 250.00 P.day. 1000.00
_____________________________ __________ ________ ________ __________
Rs: 1000.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 100.00
_____________________________ __________ ________ ________ __________
TOTAL 1100.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 110.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1210.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1210.00
_____________________________ __________ ________ ________ __________
Total labour rate per % Cft. say Rs: 1210.00
___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.
MASONRY WORK.
60 Breaking brick ballast screening and stacking.
(d) Jhama ballast 3/4" ring.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies. 4.50 Nos. 250.00 P.day. 1125.00
_____________________________ __________ ________ ________ __________
Rs: 1125.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 112.50
_____________________________ __________ ________ ________ __________
TOTAL 1237.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 123.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1361.25
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1361.25
_____________________________ __________ ________ ________ __________
Total labour rate per % Cft. say Rs: 1361.25
S/N D E S C R I P T I O N.
61 Supplying and fixing broken glass on court yard walls i/c cement
concrete 1:3:6.
Assume for 100 Lft.
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Assume base 13-1/2" and hieght 4-1/2" for segment-angle
subtended at the center 150 deg. Area=1/2*(8-sin8)=
= 1/2*0.56*2(5/6-1/2)=0.16*89/42 = 0.43 Sft.
_____________________________ __________ ________ ________ __________
Cement. 4.4 Cwt 400.00 P.Cwt. 1760.00
Sand. 16.0 Cft 2425.00 % Cft. 388.00
Stone aggregates. 32.0 Cft 2350.00 % Cft. 752.00
Broken glas. 2.0 Maund 450.00 P.Maund 900.00

Chapter No. 17 1184/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 3800.00


_____________________________ __________ ________ ________ __________
TOTAL PART " A " 4700.00
(B) LABOUR
Mason. 0.33 Nos. 450.00 P.day. 150.00
Coolies. 7.00 Nos. 250.00 P.day. 1750.00
Bahishti. 0.15 Nos. 250.00 P.day. 37.50
Rs: 1937.50
Sundries. 10.00 % 193.75
TOTAL 2131.25
Contractor's profit 10.00 % 213.13
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 23.44 2344.38
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 7044.38
Total material & labour for 100 Lft. Rs: 7044.38
Total material & labour for 1 Lft. Rs: 70.44
Total material & labour per Lft. say Rs: 70.44

S/N D E S C R I P T I O N.
MASONRY WORK.
62 Extra labour for drains of bath rooms etc.
Assume for 30 Lft.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
_____________________________ __________ ________ ________ __________
Rs: 450.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 45.00
_____________________________ __________ ________ ________ __________
TOTAL 495.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 49.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 544.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 544.50
_____________________________ __________ ________ ________ __________
Total labour rate per 30 Lft. Rs: 544.50
Total labour rate per Lft. Rs: 18.15
___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.
MASONRY WORK.
63 Hoisting R.S.Beams and wooden beams and placing in position.

Assume for 6 Nos.


___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00

Chapter No. 17 1185/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


Rs: 1200.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 120.00
_____________________________ __________ ________ ________ __________
TOTAL 1320.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 132.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1452.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1452.00
_____________________________ __________ ________ ________ __________
Total labour rate for 6 Nos. Rs: 1452.00
Total labour rate per each No. Rs: 242.00
Total labour rate per each No. say Rs: 242.00

S/N D E S C R I P T I O N.
MASONRY WORK.
64 Hoisting and placing in position sal ballies over roofs.

Assume for 30 Nos.


___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 1.00 Nos. 250.00 P.day. 250.00
_____________________________ __________ ________ ________ __________
Rs: 700.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 70.00
_____________________________ __________ ________ ________ __________
TOTAL 770.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 77.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 847.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 847.00
_____________________________ __________ ________ ________ __________
Total labour rate for 30 Nos. Rs: 847.00
Total labour rate per each No. say Rs: 28.23
S/N D E S C R I P T I O N.
MASONRY WORK.
65 Hoisting R.C battens and placing in position.
(a) 5' to 6' long.
Assume for 60 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 1200.00
_____________________________ __________ ________ ________ __________

Chapter No. 17 1186/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Sundries. 10.00 % 120.00


_____________________________ __________ ________ ________ __________
TOTAL 1320.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 132.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1452.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1452.00
Total labour rate for 60 Nos. Rs: 1452.00
Total labour rate per each No. say Rs: 24.20

S/N D E S C R I P T I O N.
MASONRY WORK.
65 Hoisting R.C battens and placing in position.
(b) 6' to 7' long.
Assume for 40 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 1200.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 120.00
_____________________________ __________ ________ ________ __________
TOTAL 1320.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 132.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1452.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1452.00
_____________________________ __________ ________ ________ __________
Total labour rate for 40 Nos. Rs: 1452.00
Total labour rate per each No. say Rs: 36.30
S/N D E S C R I P T I O N.
MASONRY WORK.
65 Hoisting R.C battens and placing in position.
(c) 7' to 8'' long.
Assume for 30 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 1200.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 120.00
_____________________________ __________ ________ ________ __________
TOTAL 1320.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 132.00

Chapter No. 17 1187/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


TOTAL PART " B " 1452.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1452.00
Total labour rate for 30 Nos. Rs: 1452.00
Total labour rate per each No. say Rs: 48.40

S/N D E S C R I P T I O N.
MASONRY WORK.
65 Hoisting R.C battens and placing in position.
(d) 8' to 9' long.
Assume for 25 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 1200.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 120.00
_____________________________ __________ ________ ________ __________
TOTAL 1320.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 132.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1452.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1452.00
_____________________________ __________ ________ ________ __________
Total labour rate for 25 Nos. Rs: 1452.00
Total labour rate per each No. say Rs: 58.08
S/N D E S C R I P T I O N.
MASONRY WORK.
65 Hoisting R.C battens and placing in position.
(e) Above 9' length.
Assume for 20 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 1200.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 120.00
_____________________________ __________ ________ ________ __________
TOTAL 1320.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 132.00
TOTAL PART " B " 1452.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1452.00
_____________________________ __________ ________ ________ __________
Total labour rate for 20 Nos. Rs: 1452.00

Chapter No. 17 1188/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total labour rate per each No. say Rs: 72.60

S/N D E S C R I P T I O N.
MASONRY WORK.
66 Hoisting and placing in position R.C.Trough.
(a) Upto 10' in length.
Assume for 20 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 1200.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 120.00
_____________________________ __________ ________ ________ __________
TOTAL 1320.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 132.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1452.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1452.00
_____________________________ __________ ________ ________ __________
Total labour rate for 20 Nos. Rs: 1452.00
Total labour rate per each No. say Rs: 72.60
S/N D E S C R I P T I O N.
MASONRY WORK.
66 Hoisting and placing in position R.C.Trough.
(b) 10' to 11' in length.
Assume for 15 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 1200.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 120.00
_____________________________ __________ ________ ________ __________
TOTAL 1320.00
Contractor's profit 10.00 % 132.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1452.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1452.00
_____________________________ __________ ________ ________ __________
Total labour rate for 15 Nos. Rs: 1452.00
Total labour rate per each No. say Rs: 96.80

S/N D E S C R I P T I O N.
MASONRY WORK.
66 Hoisting and placing in position R.C.Trough.

Chapter No. 17 1189/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(c) 11' to 12' in length.


Assume for 12 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 1200.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 120.00
_____________________________ __________ ________ ________ __________
TOTAL 1320.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 132.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1452.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1452.00
_____________________________ __________ ________ ________ __________
Total labour rate for 12 Nos. Rs: 1452.00
Total labour rate per each No. say Rs: 121.00
___ _____________________________ __________ ________ ________ __________
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
MASONRY WORK.
66 Hoisting and placing in position R.C.Trough.
(d) 12' to 13' in length.
Assume for 11 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00
Rs: 1200.00
Sundries. 10.00 % 120.00
_____________________________ __________ ________ ________ __________
TOTAL 1320.00
Contractor's profit 10.00 % 132.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1452.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1452.00
_____________________________ __________ ________ ________ __________
Total labour rate for 11 Nos. Rs: 1452.00
Total labour rate per each No. say Rs: 132.00

S/N D E S C R I P T I O N.
MASONRY WORK.
66 Hoisting and placing in position R.C.Trough.
(e) 13' to 14' in length.
Assume for 10 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:

Chapter No. 17 1190/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 1200.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 120.00
_____________________________ __________ ________ ________ __________
TOTAL 1320.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 132.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1452.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1452.00
_____________________________ __________ ________ ________ __________
Total labour rate for 10 Nos. Rs: 1452.00
Total labour rate per each No. say Rs: 145.20
S/N D E S C R I P T I O N.
MASONRY WORK.
66 Hoisting and placing in position R.C.Trough.
(f) 14' to 15' in length.
Assume for 9 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 1200.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 120.00
_____________________________ __________ ________ ________ __________
TOTAL 1320.00
Contractor's profit 10.00 % 132.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1452.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1452.00
_____________________________ __________ ________ ________ __________
Total labour rate for 9 Nos. Rs: 1452.00
Total labour rate per each No. say Rs: 161.33

S/N D E S C R I P T I O N.
MASONRY WORK.
66 Hoisting and placing in position R.C.Trough.
(g) 15' to 16' in length.
Assume for 8 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 1200.00

Chapter No. 17 1191/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


Sundries. 10.00 % 120.00
_____________________________ __________ ________ ________ __________
TOTAL 1320.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 132.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1452.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1452.00
_____________________________ __________ ________ ________ __________
Total labour rate for 8 Nos. Rs: 1452.00
Total labour rate per each No. say Rs: 181.50
S/N D E S C R I P T I O N.
MASONRY WORK.
66 Hoisting and placing in position R.C.Trough.
(h) 16' to 17' in length.
Assume for 7 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 1200.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 120.00
_____________________________ __________ ________ ________ __________
TOTAL 1320.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 132.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1452.00
TOTAL (LABOUR) 1452.00
_____________________________ __________ ________ ________ __________
Total labour rate for 7 Nos. Rs: 1452.00
Total labour rate per each No. say Rs: 207.43

S/N D E S C R I P T I O N.
MASONRY WORK.
66 Hoisting and placing in position R.C.Trough.
(i) 17' to 18' in length.
Assume for 6 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 1200.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 120.00
_____________________________ __________ ________ ________ __________
TOTAL 1320.00
_____________________________ __________ ________ ________ __________

Chapter No. 17 1192/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 132.00


_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1452.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1452.00
_____________________________ __________ ________ ________ __________
Total labour rate for 6 Nos. Rs: 1452.00
Total labour rate per each No. say Rs: 242.00
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
MASONRY WORK.
66 Hoisting and placing in position R.C.Trough.
(j) 18' to 19' in length.
Assume for 5.5 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00
Rs: 1200.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 120.00
_____________________________ __________ ________ ________ __________
TOTAL 1320.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 132.00
TOTAL PART " B " 1452.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1452.00
Total labour rate for 5.50 Nos. Rs: 1452.00
Total labour rate per each No. say Rs: 264.00

S/N D E S C R I P T I O N.
MASONRY WORK.
66 Hoisting and placing in position R.C.Trough.
(k) 19' to 20' in length.
Assume for 5 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 3.00 Nos. 250.00 P.day. 750.00
_____________________________ __________ ________ ________ __________
Rs: 1200.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 120.00
_____________________________ __________ ________ ________ __________
TOTAL 1320.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 132.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1452.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1452.00
_____________________________ __________ ________ ________ __________

Chapter No. 17 1193/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total labour rate for 5.0 Nos. Rs: 1452.00


Total labour rate per each No. say Rs: 290.40
S/N D E S C R I P T I O N.
MASONRY WORK.
67 Hoisting and placing in position R.C. inverted battens.
(a) Upto 10' span.
Assume for 30 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 4.00 Nos. 250.00 P.day. 1000.00
_____________________________ __________ ________ ________ __________
Rs: 1450.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 145.00
_____________________________ __________ ________ ________ __________
TOTAL 1595.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 159.50
TOTAL PART " B " 1754.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1754.50
_____________________________ __________ ________ ________ __________
Total labour rate for 30 Nos. Rs: 1754.50
Total labour rate per each No. say Rs: 58.48

S/N D E S C R I P T I O N.
MASONRY WORK.
67 Hoisting and placing in position R.C. inverted battens.
(b) From 10' - 12' span.
Assume for 15 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 4.00 Nos. 250.00 P.day. 1000.00
_____________________________ __________ ________ ________ __________
Rs: 1450.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 145.00
_____________________________ __________ ________ ________ __________
TOTAL 1595.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 159.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1754.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1754.50
_____________________________ __________ ________ ________ __________
Total labour rate for 15 Nos. Rs: 1754.50
Total labour rate per each No. say Rs: 116.97
S/N D E S C R I P T I O N.
MASONRY WORK.
67 Hoisting and placing in position R.C. inverted battens.

Chapter No. 17 1194/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(c) From 12' - 13' span.


Assume for 12 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 4.00 Nos. 250.00 P.day. 1000.00
_____________________________ __________ ________ ________ __________
Rs: 1450.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 145.00
_____________________________ __________ ________ ________ __________
TOTAL 1595.00
Contractor's profit 10.00 % 159.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1754.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1754.50
_____________________________ __________ ________ ________ __________
Total labour rate for 12 Nos. Rs: 1754.50
Total labour rate per each No. say Rs: 146.21

S/N D E S C R I P T I O N.
MASONRY WORK.
67 Hoisting and placing in position R.C. inverted battens.
(d) From 13' - 14' span.
Assume for 10 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 4.00 Nos. 250.00 P.day. 1000.00
_____________________________ __________ ________ ________ __________
Rs: 1450.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 145.00
_____________________________ __________ ________ ________ __________
TOTAL 1595.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 159.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1754.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1754.50
_____________________________ __________ ________ ________ __________
Total labour rate for 10 Nos. Rs: 1754.50
Total labour rate per each No. say Rs: 175.45
S/N D E S C R I P T I O N.
MASONRY WORK.
67 Hoisting and placing in position R.C. inverted battens.
(e) From 14' - 15' span.
Assume for 9 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:

Chapter No. 17 1195/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 4.00 Nos. 250.00 P.day. 1000.00
_____________________________ __________ ________ ________ __________
Rs: 1450.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 145.00
_____________________________ __________ ________ ________ __________
TOTAL 1595.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 159.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1754.50
TOTAL (LABOUR) 1754.50
_____________________________ __________ ________ ________ __________
Total labour rate for 9 Nos. Rs: 1754.50
Total labour rate per each No. say Rs: 194.94

S/N D E S C R I P T I O N.
MASONRY WORK.
67 Hoisting and placing in position R.C. inverted battens.
(f) From 15' - 16' span.
Assume for 8 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 4.00 Nos. 250.00 P.day. 1000.00
_____________________________ __________ ________ ________ __________
Rs: 1450.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 145.00
_____________________________ __________ ________ ________ __________
TOTAL 1595.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 159.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1754.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1754.50
_____________________________ __________ ________ ________ __________
Total labour rate for 8 Nos. Rs: 1754.50
Total labour rate per each No. say Rs: 219.31
S/N D E S C R I P T I O N.
MASONRY WORK.
67 Hoisting and placing in position R.C. inverted battens.
(g) From 16' - 18' span.
Assume for 6 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 4.00 Nos. 250.00 P.day. 1000.00
_____________________________ __________ ________ ________ __________
Rs: 1450.00

Chapter No. 17 1196/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


Sundries. 10.00 % 145.00
_____________________________ __________ ________ ________ __________
TOTAL 1595.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 159.50
TOTAL PART " B " 1754.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1754.50
_____________________________ __________ ________ ________ __________
Total labour rate for 6 Nos. Rs: 1754.50
Total labour rate per each No. say Rs: 292.42

S/N D E S C R I P T I O N.
MASONRY WORK.
67 Hoisting and placing in position R.C. inverted battens.
(h) From 18' - 20' span.
Assume for 4 Nos.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 4.00 Nos. 250.00 P.day. 1000.00
_____________________________ __________ ________ ________ __________
Rs: 1450.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 145.00
_____________________________ __________ ________ ________ __________
TOTAL 1595.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 159.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1754.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1754.50
_____________________________ __________ ________ ________ __________
Total labour rate for 4 Nos. Rs: 1754.50
Total labour rate per each No. say Rs: 438.63
S/N D E S C R I P T I O N.
68 Laying asphaltic mixture in expansion joints.

___ _____________________________ __________ ________ ________ __________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies. 0.083 Nos. 250.00 P.day. 20.75

_____________________________ __________ ________ ________ __________


Rs: 20.75
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 2.08
_____________________________ __________ ________ ________ __________
TOTAL 22.83
_____________________________ __________ ________ ________ __________

Chapter No. 17 1197/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 2.28


_____________________________ __________ ________ ________ __________
TOTAL PART " B " 25.11
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 25.11
_____________________________ __________ ________ ________ __________
Total labour rate per Lft. Rs: 25.11

S/N #REF!
68 Re infereed cement concrete spout
i/c fixing in position with top and
bottom khuros
(b) unit of rate for each No.
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cement. 0.25 Cwt 195.00 P.Cwt. 48.75
Sand. 1.00 Cft 350.00 % Cft. 3.50
stone aggregate 2.00 Cft 550.00 % Cft. 11.00

_____________________________ __________ ________ ________ __________


TOTAL. 63.25
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 6.33
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 69.58
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Mason. 0.40 No. 270.00 P.day. 108.00
Coolies. 0.40 No 100.00 P.day. 40.00

_____________________________ __________ ________ ________ __________


TOTAL Rs: 148.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 14.80
_____________________________ __________ ________ ________ __________
TOTAL 162.80
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 16.28
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 179.08
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 248.66
_____________________________ __________ ________ ________ __________
Total material & labour for 100 Sft. Rs: 248.66
Total material & labour for 100 Sft. say Rs: 248.66
___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1198/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

S/N D E S C R I P T I O N.
69 Damp proof course with cement sand ratio (1:2) mixed with dampo.

(a) 1/2" thick.

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cement. 1.20 Cwt 400.00 P.Cwt. 480.00
Sand. 3.10 Cft 2425.00 % Cft. 75.18
Dampo. 2.70 lbs 125.00 P.Lb 337.50

_____________________________ __________ ________ ________ __________


TOTAL. 892.68
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 89.27
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 981.94
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Mason. 0.50 Nos. 450.00 P.day. 225.00
Coolies. 2.00 Nos. 250.00 P.day. 500.00
Bahishti. 0.25 Nos. 250.00 P.day. 62.50
_____________________________ __________ ________ ________ __________
TOTAL Rs: 787.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 78.75
_____________________________ __________ ________ ________ __________
TOTAL 866.25
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 86.63
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 952.88
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 1934.82
_____________________________ __________ ________ ________ __________
Total material & labour for 100 Sft. Rs: 1934.82
Total material & labour for 100 Sft. say Rs: 1934.82

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.
69 Damp proof course with cement sand ratio (1:2) mixed with dampo.

(b) 3/4" thick.

Chapter No. 17 1199/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cement. 1.80 Cwt 400.00 P.Cwt. 720.00
Sand. 4.00 Cft 2425.00 % Cft. 97.00
Dampo. 4.00 lbs 125.00 P.Lb 500.00

_____________________________ __________ ________ ________ __________


TOTAL. 1317.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 131.70
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 1448.70
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Mason. 0.50 Nos. 450.00 P.day. 225.00
Coolies. 2.00 Nos. 250.00 P.day. 500.00
Bahishti. 0.25 Nos. 250.00 P.day. 62.50
_____________________________ __________ ________ ________ __________
TOTAL Rs: 787.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 78.75
_____________________________ __________ ________ ________ __________
TOTAL 866.25
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 86.63
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 952.88
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 2401.58
_____________________________ __________ ________ ________ __________
Total material & labour for 100 Sft. Rs: 2401.58
Total material & labour for 100 Sft. say Rs: 2401.58

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.
70 Vertical damp proof course of 3/4 thick cement plaster ratio
(1:2) with bitumen @ 20 lbs per % sft.

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cement. 1.80 Cwt 400.00 P.Cwt. 720.00

Chapter No. 17 1200/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Sand. 4.70 Cft 2425.00 % Cft. 113.98


Bitumen. 20.00 lbs 86213.0 P.Ton. 769.76
Fuel and Brush. L.S. 20.00

_____________________________ __________ ________ ________ __________


TOTAL. 1623.73
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 162.37
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 1786.11
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Mason. 0.50 Nos. 450.00 P.day. 225.00
Coolies. 2.00 Nos. 250.00 P.day. 500.00
Bahishti. 0.25 Nos. 250.00 P.day. 62.50
_____________________________ __________ ________ ________ __________
TOTAL Rs: 787.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 78.75
_____________________________ __________ ________ ________ __________
TOTAL 866.25
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 86.63
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 952.88
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 2738.98
_____________________________ __________ ________ ________ __________
Total material & labour for 100 Sft. Rs: 2738.98
Total material & labour for 100 Sft. say Rs: 2738.98

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________

S/N D E S C R I P T I O N.
71 Laying 2" thick sand and bitumen carpet on top of foundation of
oil tanks.

Assume for 2464 Sft.


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Sand. 621.0 Cft 2425.00 % Cft. 15059.25
Bitumen. 1.83 Ton 86213.0 P.Ton. 157769.8
Fuel and Brush. L.S. 75.00
Coal. 1.00 Ton 4000.00 P.Ton. 4000.00

Chapter No. 17 1201/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


TOTAL. 176904.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 17690.40
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 194594.4
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Mason. 15.00 Nos. 450.00 P.day. 6750.00
Coolies. 41.00 Nos. 250.00 P.day. 10250.00
_____________________________ __________ ________ ________ __________
TOTAL Rs: 17000.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 1700.00
_____________________________ __________ ________ ________ __________
TOTAL 18700.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 1870.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 834.82 20570.00
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 215164.4
_____________________________ __________ ________ ________ __________
Total material & labour for 2464 Sft. Rs: 215164.4
Total material & labour for 100 Sft. Rs: 8732.32
Total material & labour for 100 Sft. say Rs: 8732.32

___ _____________________________ __________ ________ ________ __________

S/N D E S C R I P T I O N.
72 Cutting hole 4" * 6" in stone masonary or brick wall with
chiesel, repairing masonry and removing debris within one chain
lead.(NOTE:same rate to be paid for other type of masonry and
RCC work.)
Assume for 5 holes.
___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 1.00 Nos. 450.00 P.day. 450.00
Coolies. 1.00 Nos. 250.00 P.day. 250.00
_____________________________ __________ ________ ________ __________
TOTAL Rs: 700.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 70.00
_____________________________ __________ ________ ________ __________
TOTAL 770.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 77.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 847.00

Chapter No. 17 1202/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


TOTAL (LABOUR) 847.0
_____________________________ __________ ________ ________ __________
Total labour rate for 5 Nos. of holes. Rs: 847.0
Total labour rate for 1 Nos. of holes. Rs: 169.40
Total labour rate per hole. say Rs: 169.40
S/N D E S C R I P T I O N.
73 Cutting grooves in stone masonry, brick masonry or cement
concrete wall and removing debris within one chain lead.

(B) LABOUR QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 0.25 Nos. 450.00 P.day. 112.50
Coolies. 0.25 Nos. 250.00 P.day. 62.50
TOTAL Rs: 175.00
Sundries. 10.00 % 17.50
_____________________________ __________ ________ ________ __________
TOTAL 192.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 19.25
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 211.75
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 211.8
_____________________________ __________ ________ ________ __________
Total labour rate per groove. Rs: 211.75

S/N D E S C R I P T I O N.
74 Making 1-1/2" * 1-1/2" groove in stone masonry,brick masonry in
cement for fixing planks upto 9" deep.

Assume for 3 planks.


___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Mason. 0.50 Nos. 450.00 P.day. 225.00
Coolies. 0.50 Nos. 250.00 P.day. 125.00
_____________________________ __________ ________ ________ __________
TOTAL Rs: 350.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 35.00
_____________________________ __________ ________ ________ __________
TOTAL 385.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 38.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 423.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 423.50
_____________________________ __________ ________ ________ __________
Total labour rate per Plank. Rs: 141.17
___ _____________________________ __________ ________ ________ __________
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.

Chapter No. 17 1203/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

75 Drilling holes in stones or brick masonry upto 2" dia per inch
depth.

Assume for 8 holes.


___ _____________________________ __________ ________ ________ __________
(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies. 1.00 Nos. 250.00 P.day. 250.00
_____________________________ __________ ________ ________ __________
TOTAL Rs: 250.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 25.00
_____________________________ __________ ________ ________ __________
TOTAL 275.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 27.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 302.50
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 302.50
_____________________________ __________ ________ ________ __________
Total labour rate per hole per inch. Rs: 37.81

S/N D E S C R I P T I O N.
76 Grouting concrete between the grooves of gates including
shuttering.

___ _____________________________ __________ ________ ________ __________


(B) LABOUR QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Masons. 2.50 Nos. 450.00 P.day. 1125.00
Carpenters. 0.50 Nos. 450.00 P.day. 225.00
Coolies. 6.00 Nos. 250.00 P.day. 1500.00
Bahishti. 1.00 Nos. 250.00 P.day. 250.00
_____________________________ __________ ________ ________ __________
TOTAL Rs: 3100.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 310.00
_____________________________ __________ ________ ________ __________
TOTAL 3410.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 341.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 3751.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 3751.00
_____________________________ __________ ________ ________ __________
Total labour rate per 100 Cft. Rs: 3751.00
___ _____________________________ __________ ________ ________ __________
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
77 Chiesel dressing concrete surface on sides of grooves.

___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1204/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(B) LABOUR QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_____________________________ __________ ________ ________ __________
Masons. 0.25 Nos. 450.00 P.day. 112.50

_____________________________ __________ ________ ________ __________


TOTAL Rs: 112.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 11.25
_____________________________ __________ ________ ________ __________
TOTAL 123.75
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 12.38
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 136.13
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 136.13
Total labour rate per 100 sft. Rs: 136.13

S/N D E S C R I P T I O N.
78 Ramming and laying dry ballast or kankar.

(B) LABOUR QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_____________________________ __________ ________ ________ __________
Coolies. 4.00 Nos. 250.00 P.day. 1000.00
TOTAL Rs: 1000.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 100.00
_____________________________ __________ ________ ________ __________
TOTAL 1100.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 110.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1210.00
_____________________________ __________ ________ ________ __________
TOTAL (LABOUR) 1210.00
_____________________________ __________ ________ ________ __________
Total labour rate per 100 Cft. Rs: 1210.00
___ _____________________________ __________ ________ ________ __________
___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
79 Petty repairs to fire place.
(a)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cement,sand,bricks, etc. L.S 60.00

TOTAL. 60.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 6.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 66.0
(B) LABOUR
_____________________________ __________ ________ ________ __________

Chapter No. 17 1205/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Mason. 0.14 Nos. 450.00 P.day. 64.29


Coolies. 0.14 Nos. 250.00 P.day. 35.71
_____________________________ __________ ________ ________ __________
TOTAL Rs: 100.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 10.00
_____________________________ __________ ________ ________ __________
TOTAL 110.00
Contractor's profit 10.00 % 11.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 121.00
TOTAL (MATERIAL + LABOUR) 187.00
Total material & labour for each No. Rs: 187.00

S/N D E S C R I P T I O N.
79 Petty repairs to fire place. (Large fire place)
(b)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cement,sand,bricks, etc. L.S 75.00

_____________________________ __________ ________ ________ __________


TOTAL. 75.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 7.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 82.5
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Mason. 0.29 Nos. 450.00 P.day. 128.57
Coolies. 0.29 Nos. 250.00 P.day. 71.43
_____________________________ __________ ________ ________ __________
TOTAL Rs: 200.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 20.00
_____________________________ __________ ________ ________ __________
TOTAL 220.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 22.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 242.00
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 324.50
_____________________________ __________ ________ ________ __________
Total material & labour for each No. Rs: 324.50

Chapter No. 17 1206/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
80 Petty repairs to main rooms.

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cement,sand,bricks, etc. L.S 100.00

_____________________________ __________ ________ ________ __________


TOTAL. 100.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 10.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 110.0
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Mason. 0.25 Nos. 450.00 P.day. 112.50
Coolies. 0.33 Nos. 250.00 P.day. 83.33
_____________________________ __________ ________ ________ __________
TOTAL Rs: 195.83
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 19.58
_____________________________ __________ ________ ________ __________
TOTAL 215.42
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 21.54
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 236.96
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 346.96
_____________________________ __________ ________ ________ __________
Total material & labour for each No. Rs: 346.96

Chapter No. 17 1207/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.
81 Petty repairs to small rooms.

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Cement,sand,bricks, etc. L.S 50.00

_____________________________ __________ ________ ________ __________


TOTAL. 50.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 5.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 55.0
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Mason. 0.13 Nos. 450.00 P.day. 56.25
Coolies. 0.17 Nos. 250.00 P.day. 41.67
_____________________________ __________ ________ ________ __________
TOTAL Rs: 97.92
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 9.79
_____________________________ __________ ________ ________ __________
TOTAL 107.71
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 10.77
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 118.48
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 173.48
_____________________________ __________ ________ ________ __________
Total material & labour for each No. Rs: 173.48

___ _____________________________ __________ ________ ________ __________


___ _____________________________ __________ ________ ________ __________
S/N D E S C R I P T I O N.
82 Petty repairs to verandah.

___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1208/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

(A) MATERIAL QUANTITY RATE UNIT AMOUNT


Rs: Rs:
_____________________________ __________ ________ ________ __________
Cement,sand,bricks, etc. L.S 100.00

_____________________________ __________ ________ ________ __________


TOTAL. 100.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 10.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 110.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Mason. 0.25 Nos. 450.00 P.day. 112.50
Coolies. 0.33 Nos. 250.00 P.day. 83.33
_____________________________ __________ ________ ________ __________
TOTAL Rs: 195.83
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 19.58
_____________________________ __________ ________ ________ __________
TOTAL 215.42
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 21.54
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 236.96
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 346.96
_____________________________ __________ ________ ________ __________
Total material & labour for each No. Rs: 346.96

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.
83 Supplying and fixing in position Aluminium Channels framing for
hinged doors of Alcop made with 5 m.m thick tinted glass glazing
(BELGIUM) and ALPHA (Japan) locks i/c handles stoppers etc,
complete.
(a) DELUXE MODEL. (WHITE)
Assume for 28 Sft.
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:

Chapter No. 17 1209/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


Aluminium framing for 28.00 Sft 1050.00 P.Sft. 29400.00
hinged doors ALCOP.
Door Lock ALPHA (Japan) 1.00 Each 1500.00 Each. 1500.00

5 m.m tinted glass i/c 10% 30.80 Sft 230.00 P.Sft. 7084.00
wastage.
_____________________________ __________ ________ ________ __________
TOTAL. 37984.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 3798.40
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 41782.40
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Glazier. 0.33 Nos. 250.00 P.day. 82.50

Mason. 0.50 Nos. 450.00 P.day. 225.00


_____________________________ __________ ________ ________ __________
TOTAL Rs: 307.50
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 30.75
_____________________________ __________ ________ ________ __________
TOTAL 338.25
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 33.83
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 13.29 372.08
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 42154.48
_____________________________ __________ ________ ________ __________
Total material & labour for 28 Sft. Rs: 42154.48
Total material & labour for 1 Sft. Rs: 1505.52
Total material & labour per Sft. Rs: 1505.52

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.
83 Supplying and fixing in position Aluminium Channels framing for
hinged doors of Alcop made with 5 m.m thick tinted glass glazing
(BELGIUM) and ALPHA (Japan) locks i/c handles stoppers etc,
complete.
(b) DELUXE MODEL. (BRONZE)
Assume for 28 Sft.
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Aluminium framing for 28.00 Sft 1050.00 P.Sft. 29400.00
hinged doors ALCOP.
Door Lock ALPHA (Japan) 1.00 Nos 1500.00 Each. 1500.00

5 m.m tinted glass i/c 10% 30.80 Sft 230.00 P.Sft. 7084.00

Chapter No. 17 1210/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

wastage.
_____________________________ __________ ________ ________ __________
TOTAL. 37984.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 3798.40
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 41782.40
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Glazier. 0.33 Nos. 400.00 P.day. 132.00

Mason. 0.50 Nos. 450.00 P.day. 225.00


_____________________________ __________ ________ ________ __________
TOTAL Rs: 357.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 35.70
_____________________________ __________ ________ ________ __________
TOTAL 392.70
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 39.27
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 15.43 431.97
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 42214.37
_____________________________ __________ ________ ________ __________
Total material & labour for 28 Sft. Rs: 42214.37
Total material & labour for 1 Sft. Rs: 1507.66
Total material & labour per Sft. Rs: 1507.66

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.
84 Supplying and fixing in position Aluminium Channels framing for
sliding windows & ventilators of Alcop made with 5 m.m thick
tinted glass glazing (BELGIUM) and Aluminium fly screen handles
stoppers and locking arrangements etc, complete.

(a) DELUXE MODEL. (WHITE)


Assume for 24 Sft.
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Aluminium framing for 24.00 Sft 1000.00 P.Sft. 24000.00
hinged doors ALCOP.
Fly screen.(Foreign) 24.00 Sft 180.00 P.Sft. 4320.00

5 m.m tinted glass i/c 10% 26.40 Sft 230.00 P.Sft. 6072.00
wastage.
_____________________________ __________ ________ ________ __________
TOTAL. 34392.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 3439.20

Chapter No. 17 1211/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


TOTAL PART " A " 37831.20
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Glazier. 0.25 Nos. 400.00 P.day. 100.00

Mason. 0.50 Nos. 450.00 P.day. 225.00


_____________________________ __________ ________ ________ __________
TOTAL Rs: 325.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 32.50
_____________________________ __________ ________ ________ __________
TOTAL 357.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 35.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 16.39 393.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 38224.45
_____________________________ __________ ________ ________ __________
Total material & labour for 24 Sft. Rs: 38224.45
Total material & labour for 1 Sft. Rs: 1592.69
Total material & labour per Sft. Rs: 1592.69

___ _____________________________ __________ ________ ________ __________

S/N D E S C R I P T I O N.
84 Supplying and fixing in position Aluminium Channels framing for
sliding windows & ventilators of Alcop made with 5 m.m thick
tinted glass glazing (BELGIUM) and Aluminium fly screen handles
stoppers and locking arrangements etc, complete.

(b) DELUXE MODEL. (BRONZE)


Assume for 24 Sft.
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Aluminium framing for 24.00 Sft 1050.00 P.Sft. 25200.00
hinged doors ALCOP.
Fly screen.(Foreign) 24.00 Sft 180.00 P.Sft. 4320.00

5 m.m tinted glass i/c 10% 26.40 Sft 230.00 P.Sft. 6072.00
wastage.
_____________________________ __________ ________ ________ __________
TOTAL. 35592.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 3559.20
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 39151.20
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Glazier. 0.25 Nos. 400.00 P.day. 100.00

Chapter No. 17 1212/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Mason. 0.50 Nos. 450.00 P.day. 225.00


_____________________________ __________ ________ ________ __________
TOTAL Rs: 325.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 32.50
_____________________________ __________ ________ ________ __________
TOTAL 357.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 35.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 16.39 393.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 39544.45
_____________________________ __________ ________ ________ __________
Total material & labour for 24 Sft. Rs: 39544.45
Total material & labour for 1 Sft. Rs: 1647.69
Total material & labour per Sft. Rs: 1647.69

___ _____________________________ __________ ________ ________ __________

S/N D E S C R I P T I O N.
85 Supplying and fixing in position Aluminium Channels framing for
fixing glass glazing of Alcop made with 5 m.m thick tinted
glass glazing (BELGIUM) etc, complete.

(a) DELUXE MODEL. (WHITE)


Assume 24 Sft.
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Aluminium framing for 24.00 Sft 1000.00 P.Sft. 24000.00
hinged doors ALCOP.

5 m.m tinted glass i/c 10% 26.40 Sft 230.00 P.Sft. 6072.00
wastage.
_____________________________ __________ ________ ________ __________
TOTAL. 30072.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 3007.20
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 33079.20
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Glazier. 0.25 Nos. 400.00 P.day. 100.00

Mason. 0.50 Nos. 450.00 P.day. 225.00


_____________________________ __________ ________ ________ __________
TOTAL Rs: 325.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 32.50
_____________________________ __________ ________ ________ __________

Chapter No. 17 1213/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL 357.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 35.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 16.39 393.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 33472.45
_____________________________ __________ ________ ________ __________
Total material & labour for 24 Sft. Rs: 33472.45
Total material & labour for 1 Sft. Rs: 1394.69
Total material & labour per Sft. Rs: 1394.69

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D E S C R I P T I O N.
85 Supplying and fixing in position Aluminium Channels framing for
fixing glass glazing of Alcop made with 5 m.m thick tinted
glass glazing (BELGIUM) etc, complete.

(b) DELUXE MODEL. (BRONZE)


Assume 24 Sft.
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Aluminium framing for 24.00 Sft 1050.00 P.Sft. 25200.00
hinged doors ALCOP.

5 m.m tinted glass i/c 10% 26.40 Sft 230.00 P.Sft. 6072.00
wastage.
_____________________________ __________ ________ ________ __________
TOTAL. 31272.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 3127.20
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 34399.20
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Glazier. 0.25 Nos. 400.00 P.day. 100.00

Mason. 0.50 Nos. 450.00 P.day. 225.00


_____________________________ __________ ________ ________ __________
TOTAL Rs: 325.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 32.50
_____________________________ __________ ________ ________ __________
TOTAL 357.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 35.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 16.39 393.25
_____________________________ __________ ________ ________ __________

Chapter No. 17 1214/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

TOTAL (MATERIAL + LABOUR) 34792.45


_____________________________ __________ ________ ________ __________
Total material & labour for 24 Sft. Rs: 34792.45
Total material & labour for 1 Sft. Rs: 1449.69
Total material & labour per Sft. Rs: 1449.69

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N NEW
86 Providing & fixing wooden frame of partal wood for Air Condition of 1.5 Tons i/c cutting
the wall 6" -9" and fixing the frame .The cost also includes cost of prcture railling / of 2"-
3" width and repairing the surface with cement plaster & making good etc: complete.

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
A.C frame 1.00 Nos 1500.00 Each 1500.00
Picture Railing 8.00 RFT 150.00 P.Rft 1200.00
Cement Mortar LS 50.00
Steel/Iron Nails LS 15.00

_____________________________ __________ ________ ________ __________


TOTAL. 2765.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 276.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 3041.50
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Cooolies for cutting wall 1.50 Nos. 250.00 P.day. 375.00

Mason for fixing 0.50 Nos. 450.00 P.day. 225.00


_____________________________ __________ ________ ________ __________
TOTAL Rs: 600.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 60.00
_____________________________ __________ ________ ________ __________
TOTAL 660.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 66.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 726.00
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 3767.50
_____________________________ __________ ________ ________ __________
Total material & labour per Sft. Rs: 3767.50
Total material & labour for 1 Sft. Rs: 3767.50
Total material & labour per Sft. Rs: 3767.50

Chapter No. 17 1215/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N _
87 Proivding & fixing GI frame for Air condition of 1.50 Tons i/c cutting the wall 6" -9" and
fixing the frame .The cost also includes cost of Picture railing , beading of 2" -3" width &
repairing the surface with cement plaster & making good etc: complete.

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
GI frame i/c 5% wastage 19.82 Cwt 5500.00 P.CWT 973.30

Hold fasts 4.00 Nos 65.00 P.Each 260.00

Picture Railing 8.00 RFT 150.00 P.Rft 1200.00

Cement 0.50 Cwt 400.00 P.bag 200.00

Hill Sand 4.00 Cft 2425.00 P.% Cft 97.00

Nails /Screws. LS 15.00


_____________________________ __________ ________ ________ __________
TOTAL. 2745.3
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 274.53
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 3019.83
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Black smith for cutting frame 0.50 Nos. 450.00 P.day. 225.00

Mason for fixing 0.50 Nos. 450.00 P.day. 225.00

Coolies for cutting wall 1.50 Nos. 250.00 P.day 375.00


_____________________________ __________ ________ ________ __________
TOTAL Rs: 825.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 82.50
_____________________________ __________ ________ ________ __________
TOTAL 907.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 90.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 998.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 4018.08
_____________________________ __________ ________ ________ __________
Total material & labour EACH Rs: 4018.08
Total material & labour for EACH Rs: 4018.08
Total material & labour EACH Rs: 4018.08
___ _____________________________ __________ ________ ________ __________
S/N

Chapter No. 17 1216/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

88 Providing and fixing Aluminum sheet 6" to 9" with V-Notch for expansion joints i/c fixing
with nails/ screws.

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
Aluminium framing for 10.00 RFT 150.00 RFT 1500.00
hinged doors ALCOP.
5 m.m tinted glass i/c 10% 6.00 Nos. 40.00 P.EACH 240.00
wastage.
NAILS /SCREW /GITTIES L.S 10
_____________________________ __________ ________ ________ __________
TOTAL. 1750.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 175.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 1925.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Mason. 0.20 Nos. 450.00 P.day. 90.00

COLLIES 0.10 Nos. 250.00 P.day. 25.00


_____________________________ __________ ________ ________ __________
TOTAL Rs: 115.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 11.50
_____________________________ __________ ________ ________ __________
TOTAL 126.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 12.65
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 139.15
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 2064.15
_____________________________ __________ ________ ________ __________
Total material & labour for 10 RFT Rs: 2064.15
Total material & labour for RFT Rs: 206.42
Total material & labour per RFT Rs: 206.42

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N
89 P/Fixing railing for curtains i.c fixed in wall with clips screwed in gitties etc complete.

Chapter No. 17 1217/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
RAILING PATTI 10.00 RFT 150.00 RFT 1500.00

CLIPS / GITTIES /ROLLERS L.S 20.00

_____________________________ __________ ________ ________ __________


TOTAL. 1520.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 152.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 1672.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
CARPENTER 0.10 Nos. 450.00 P.day. 45.00

_____________________________ __________ ________ ________ __________


TOTAL Rs: 45.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 4.50
_____________________________ __________ ________ ________ __________
TOTAL 49.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 4.95
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 54.45
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 1726.45
_____________________________ __________ ________ ________ __________
Total material & labour for 10 RFT. Rs: 1726.45
Total material & labour for PRFT Rs: 172.65
Total material & labour per P.RFT Rs: 172.65

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N
90 Providing & fixing railing flor curtains with deodar wooden patti i/c fixed in wall with
screws etc: complete.

___ _____________________________ __________ ________ ________ __________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
DEODAR PATTI 10.00 RFT 150.00 RFT 1500.00

Chapter No. 17 1218/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

RAILING 10.00 RFT 150.00 RFT 1500.00

CLIP , SCREWS , NAILS , ROLLERS L.S 30.00


_____________________________ __________ ________ ________ __________
TOTAL. 3030.0
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 303.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 3333.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
CARPENTER 0.20 Nos. 450.00 P.day. 90.00

_____________________________ __________ ________ ________ __________


TOTAL Rs: 90.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 9.00
_____________________________ __________ ________ ________ __________
TOTAL 99.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 9.90
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 108.90
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 3441.90
_____________________________ __________ ________ ________ __________
Total material & labour for 10 R FT Rs: 3441.90
Total material & labour for P RFT Rs: 344.19
Total material & labour per RFT Rs: 344.19

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D I S C R I P T I O N.

91 Providing Anti-termmite treatment by spraying/ sprinkling/spreading Neptachlar 0.5% Emulsion as an overall preconstr

(Unit of rate per Rft.)


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
1 gallon of Heptachlar with 72 gallons of water (0.5% Emulsion)
will cover 180 Running feet @ rate of 5 gallons per 5 Rft.
_____________________________ __________ ________ ________ __________
Organo chloro solution 1.00 Gallon 5500.00 P.Gallon 5500.00

Cartage of material, rent L.S 50.00


of T & P, etc.

Chapter No. 17 1219/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


TOTAL 5550.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 555.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 6105.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Skilled Coolies. 2.00 Nos. 250.00 P.day 500.00

Cooly. 1.50 Nos. 250.00 P.day 375.00

_____________________________ __________ ________ ________ __________


Rs: 875.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 87.50
_____________________________ __________ ________ ________ __________
TOTAL 962.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 96.25
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 5.88 1058.75
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 7163.75
_____________________________ __________ ________ ________ __________
Total material & labour for 180 Rft. Rs: 7163.75
Total material & labour for 1 Rft. Rs: 39.80
Total material & labour per Rft. say Rs: 39.80
___ _____________________________ __________ ________ ________ __________

S/N D I S C R I P T I O N.

92 Providing Anti-termmite treatment by spraying/ sprinkling/


spreading Neptachlar 0.5% Emulsion as an overall preconstruction
treatment in slab type construction under the slab and along
attached perches or entrances etc, complete as per directions of
Engineer Incharge.
(Unit of rate per Sft.)
___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
1 gallon of Heptachlar with 72 gallons of water (0.5% Emulsion)
will cover 720 Sft.
_____________________________ __________ ________ ________ __________
Organo chloro solution 1.00 Gallon 5500.00 P.Gallon 5500.00

Cartage of material, rent L.S 50.00


of T & P, etc.

_____________________________ __________ ________ ________ __________


TOTAL 5550.00
_____________________________ __________ ________ ________ __________

Chapter No. 17 1220/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Contractor's profit 10.00 % 555.00


_____________________________ __________ ________ ________ __________
TOTAL PART " A " 6105.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Skilled Coolies. 2.00 Nos. 250.00 P.day 500.00

Cooly. 1.00 Nos. 250.00 P.day 250.00

_____________________________ __________ ________ ________ __________


Rs: 750.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 75.00
_____________________________ __________ ________ ________ __________
TOTAL 825.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 82.50
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 1.26 907.50
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 7012.50
_____________________________ __________ ________ ________ __________
Total material & labour for 720 Sft. Rs: 7012.50
Total material & labour for 1 Sft. Rs: 9.74
Total material & labour per Sft. say Rs: 9.74

S/N D I S C R I P T I O N.

93 Providing and placing in position Chip Board 3/4" thick for


filling space between expansion joints of buildings.

(Unit of rate per Sft.)


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
For 100 Sft.

Chip Board. 100.0 Sft 39.00 P.Sft. 3900.00

_____________________________ __________ ________ ________ __________


TOTAL 3900.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 390.00
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 4290.00
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Skilled Cooly. 0.12 Nos. 250.00 P.day 30.00

Chapter No. 17 1221/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


Rs: 30.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 3.00
_____________________________ __________ ________ ________ __________
TOTAL 33.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 3.30
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 0.36 36.30
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 4326.30
_____________________________ __________ ________ ________ __________
Total material & labour for 100 Sft. Rs: 4326.30
Total material & labour for 1 Sft. Rs: 43.26
Total material & labour per sft. say Rs: 43.26

S/N D I S C R I P T I O N.
94 Cleaning & decontamination of under ground / over head water tand with chemical i/c
dewatering and cleaning the walls with hand bruxh, applying potassium per magnate
coat to eliminate all bacteria's germs and removing the algae and vegetal growth and
white washing two coats.

SIZE OF TANK 10x5x4


walls2(10+5)x5=120sft (Unit of rate per Sft.)
___ top & bott 2*10*5=100 __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
POTASIUM PER MAGNATE 4 lbs 55 P.LBS 220

WHITE LIME 10.0 KG 6.00 P.KG 60

WHIRE BRUSH L.S 25

POTCH FOR WHITE WASH L.S 10

TOTAL 315.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 31.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 346.50
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Skilled Cooly. FOR DEWATERING 4.00 Nos. 250.00 P.day 1000.00
AND BRUSHING

COLLIES FOR WHITE WASH 0.5 Nos. 250 P.day 125.00

Rs: 1125.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 112.50

Chapter No. 17 1222/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

_____________________________ __________ ________ ________ __________


TOTAL 1237.50
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 123.75
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 5.67 1361.25
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 1707.75
_____________________________ __________ ________ ________ __________
Total material & labour for 240 Sft. Rs: 1707.75
Total material & labour for 1 Sft. Rs: 7.12
Total material & labour per sft. say Rs: 7.12
___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D I S C R I P T I O N.

95 Cleaning of septic tank/ soak pit i/c dewatering, remocing the sewage and solid wastes
and throwing outside the municipal, limits and cleaning the walls ceilings and bottom of
thank.

TANK SIZE 10*20*5 =1000CFT


(Unit of rate per Sft.)
___ _____________________________ __________ ________ ________ __________

(B) LABOUR
_____________________________ __________ ________ ________ __________
Skilled Cooly.FOR DEWATERING 12.00 Nos. 250.00 P.day 3000.00
TAKING OUT SEWAGE FROM
TANK AND CLEANING WALLS
BY BRUSHES

COOLIES FOR LOADING UNLOAD 8 Nos. 250.00 P.day 2000.00


SEWAGE ON TRUCK

HIRE CHARGES OF TRACTOR 1 Nos. 6000.00 P.day 6000.00

_____________________________ __________ ________ ________ __________


Rs: 11000.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 1100.00
_____________________________ __________ ________ ________ __________
TOTAL 12100.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 1210.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 13310.00
_____________________________ __________ ________ ________ __________
TOTAL LABOUR) 13310.00
_____________________________ __________ ________ ________ __________
Total material & labour for 100 0Cft. Rs: 13310.00
Total material & labour for 1 Cft. Rs: 13.31
Total material & labour per Cft. say Rs: 13.31

Chapter No. 17 1223/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

___ _____________________________ __________ ________ ________ __________

___ _____________________________ __________ ________ ________ __________


S/N D I S C R I P T I O N.

96 Cleaning/ desillting of manhole / inspection chambers i/c cleaning and rodding of


connected sewers (Average 50'-0 per m-hole ) Remocing sewage and solid wastes and
throwing outside KMC Limits.

(Unit of rate per M.HOLE.)


___ _____________________________ __________ ________ ________ __________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ __________ ________ ________ __________
BAMBOOS 2-1/2" dia 16 to 20 ' long 0.25 Nos 340 each 85

_____________________________ __________ ________ ________ __________


TOTAL 85.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 8.50
_____________________________ __________ ________ ________ __________
TOTAL PART " A " 93.50
_____________________________ __________ ________ ________ __________
(B) LABOUR
_____________________________ __________ ________ ________ __________
Skilled Cooly.FOR DEWATERING 1.00 Nos. 250.00 P.day 250.00
TAKING OUT SEWAGE FROM
TANK AND CLEANING WALLS
BY BRUSHES

COOLIES FOR LOADING UNLOAD 1 Nos. 250.00 P.day 250.00


SEWAGE ON TRUCK

HIRE CHARGES OF TRACTOR 0.1 Nos. 6000.00 P.day 600.00

_____________________________ __________ ________ ________ __________


Rs: 1100.00
_____________________________ __________ ________ ________ __________
Sundries. 10.00 % 110.00
_____________________________ __________ ________ ________ __________
TOTAL 1210.00
_____________________________ __________ ________ ________ __________
Contractor's profit 10.00 % 121.00
_____________________________ __________ ________ ________ __________
TOTAL PART " B " 443.67 1331.00
_____________________________ __________ ________ ________ __________
TOTAL (MATERIAL + LABOUR) 1424.50
_____________________________ __________ ________ ________ __________
Total material & labour for 3 m.hole Rs: 1424.50
Total material & labour for 1 hole Rs: 474.83

Chapter No. 17 1224/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Total material & labour per hole say Rs: 474.83


___ _____________________________ __________ ________ ________ __________

Chapter No. 17 1225/1226


GENERAL RATE ANALYSIS VOLUME – III
FOR FINISHED ITEMS OF WORK PART - III
PUBLICATION NO.52

Emulsion as an overall preconstruction treatment in slab type construction along external

Chapter No. 17 1226/1226

You might also like