You are on page 1of 12

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/319486398

Critical Factors Affecting No-dispute Performance: A Case of Ethiopian Public


Construction Projects

Article · December 2016


DOI: 10.6106/JCEPM.2016.12.4.024

CITATIONS READS

0 391

3 authors:

Ephrem Girma Sinesilassie S. Z. S. Tabish

4 PUBLICATIONS   27 CITATIONS   
Office of the Comptroller and Auditor General of India
12 PUBLICATIONS   259 CITATIONS   
SEE PROFILE
SEE PROFILE

Kumar Neeraj Jha


Indian Institute of Technology Delhi
113 PUBLICATIONS   2,004 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

I am working with construction department of Govt. of India View project

IT INDIAN HERITAGE PLATFORM View project

All content following this page was uploaded by Kumar Neeraj Jha on 24 December 2017.

The user has requested enhancement of the downloaded file.


KICEM Journal of Construction Engineering and Project Management www.jcepm.org
Online ISSN 2233-9582 http://dx.doi.org/10.6106/JCEPM.2016.12.4.024

Critical Factors Affecting No-dispute Performance:


A Case of Ethiopian Public Construction Projects

Ephrem Girma Sinesilassie1, Syed Zafar Shahid Tabish2, Kumar Neeraj Jha3

Abstract: Disputes seem to be synonymous with large-scale construction projects in Ethiopia. The purpose of this study is to
determine the factors responsible for impacting the performance of Ethiopian public construction projects. To this end, 35 success
and failure attributes responsible for impacting the performance of the projects were identified and presented to Ethiopian
construction professionals in the form of a structured questionnaire, and responses were collected. The factor analysis conducted
on the success and failure attributes influencing no-dispute performance separately resulted in six success factors and five failure
factors. Further analysis using stepwise multiple regression indicates that owner competence and interaction among project
participants have a positive impact on no-dispute performance. However, conflict among project participants has a negative impact
on the no-dispute performance of Ethiopian public construction projects. Although Ethiopia-specific, the results reflect
construction management problems common to both developed and developing countries. The findings are expected to help
researchers and practitioners gain a better understanding of critical success and failure factors and to help them take proactive
measures to avoid disputes in public construction projects.

Keywords: Public projects, No-dispute performance, Factor analysis, Ethiopia

I. INTRODUCTION detrimental to this performance. Therefore, it is


important to identify and understand the impact of both
The problem of disputes in the construction industry
the critical success and critical failure factors
is a global phenomenon, and the costs associated with
contributing to a construction project’s no-dispute
resolving disputes are significant. According to [1], the
performance. Consequently, maximizing the results of
direct costs associated with disputes range from 0.5 to 5
the critical success factors and minimizing the negative
percent of project’s contract value. Claims in large scale
impact of failure factors may result in the desired no-
construction projects in Ethiopia ranging in millions of
dispute performance of construction projects.
Ethiopian Birr and sometimes even in excess of 100% of
Earlier research on success and failure factors
the project costs [2], if not resolved, can lead to
includes the perceptions of respondents from either the
costly disputes. Public construction projects have tight private sector or both the private and public sector.
deadlines and risks related to conflict, which tends to However, the existence of differences in perceptions
breed costly and time-consuming disputes. Disputes arise about the relative importance of success factors between
when the behavior adopted by one party to fulfill the private and the public sector has been reported ([4],
interests, meet needs, or protect values adversely impacts [5]). Hence, only public sector employees were
the interests, needs, or values of the other party [3]. considered as respondents for the present study.
When a major construction project goes into dispute, the Our literature review revealed that not enough
impact is far reaching, manifesting itself in cost overruns research has been conducted with regard to the
and late delivery and compromising the quality and performance of Ethiopian public construction projects.
scope of the project itself. There are many attributes that affect no-dispute
No-dispute performance implies that the project is performance either positively or negatively. Hence,
completed with a minimum number of litigations or identification of these attributes and evaluation of their
preferably no dispute resulting from disagreements impact on project performance is the aim of this
among participants. Though there are success factors research. The objectives for the study are given below:
contributing to no-dispute performance in construction
projects, there are also various failure factors that are

‫ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ‬
1
Research Scholar, Dept. of Civil Engineering, Indian Institute of Technology Delhi, Hauz Khas, New Delhi 110016, India (corresponding author).
E-mail: ephremg41@gmail.com
2
PhD, Director (Works), Office of CAG of India, 9-DDU Marg, 3 New Delhi-110124. Email: szstabish@yahoo.co.uk
3
Associate Professor, Dept. of Civil Engineering, Indian Institute of Technology Delhi, Hauz Khas, New Delhi 110016, India. E-mail:
knjha@civil.iitd.ac.in
24
Critical Factors Affecting No-dispute Performance: A Case of Ethiopian Public Construction Projects

 To identify the relative importance of success II. LITERATURE REVIEW


and failure attributes affecting no-dispute
In the literature, several researchers identified,
performance in Ethiopian construction projects;
explained, and discussed the factors that are critical to
and
the success of a project. Rockart used the term ‘critical
 To understand the latent properties of the success factors (CSFs)’ for the few key areas of activity
success and failure attributes by studying the in which favorable results are absolutely necessary for a
critical success and failure factors for particular manager to reach his or her goals [5]. Further,
improving no-dispute performance. [6] defined critical success factors (CSFs) as those few
things that must go well to ensure success for a manager
Because the study required a large data set of or an organization, and therefore, they represent those
completed projects in Ethiopia, which was difficult to managerial or enterprise areas that must be given special
obtain, we decided to collect the data using a and continual attention to bring about high performance.
questionnaire survey approach. The responses received A summary of critical factors used by different
were statistically analyzed. researchers is presented in Table 1.

TABLE I
SUMMARY OF CRITICAL FACTORS

No. of
Types of Methods of
No. Authors variables Critical Factors
respondent analysis
considered

Project manager competence, project management team members’


Mixed type competence, project manager coordinating skills, client clear and
Gudiene et Relative
respondent precise goals/objectives, project value, project management team
1 al.(2013) importance index, 71
(Public & members’ relevant past experience, project manager organizing
[7] ranking
Private) skills, project manager effective and timely conflict resolution, client
ability to make timely decision, and project manager experience.
Factor analysis
Chan et al. Public- Project team commitment, client's competencies, and contractor's
2 and multiple 31
(2001) [8] sector. competencies
regression analysis
Adequacy of plans and specifications, constructability, realistic
Kog and Mixed type
An analytical obligations/clear objectives, economic risks, project manager
Loh (2013) respondent
3 hierarchy process 67 competency, project manager commitment and involvement,
[9] (Public &
(AHP) contractual motivation/incentive, technical approval authorities,
Private)
construction control meetings, pioneering status.
Mixed type Factor analysis
Iyer and
respondent and multinomial Commitment of the project participants, owner’s competence, and
4 Jha (2005) 55
(Public & logistic conflict among project participants
[10]
Private) regressions
Mixed type Establishment and communication of a conflict resolution strategy,
factor analysis and
Chan et al. respondent the willingness to share resources among project participants, a clear
5 multiple 41
(2004) [11] (Public & definition of responsibilities, a commitment to win-win attitudes, and
regression
Private) regular monitoring of the partnering process.
Thorough understanding of scope on the part of project manager and
contractor, comprehensive pretender site investigation, regular
Tabish and analysis of
Public- monitoring and feedback by owner, no bureaucratic interference, no
6 Jha (2011) variance
sector. 36 social and political interference, clearly articulated scope of work,
[12] (ANOVA)
quality control and quality assurance activities, and adequate
communication among all project participants.
Poor communication, poor contract documentation, suspension of
Mixed type
Agumba work, failure to understand and correctly bid or price the work, bad
respondent
7 and Baloyi Content analysis 14 weather, non-circulation of information, incomplete tracing
(Public &
(2014) [13] mechanisms for request of information and delays in extensions of
Private)
time
Mixed type
El-razek et Variations initiated by the owner/consultant; inferior quality of
respondent Frequencies and
8 al. (2007) 17 design, drawings and/or specifications; and delays in the approval of
(Public & pareto Analysis
[14] shop drawings, instructions and decision making.
Private)
Mixed type
Sambasivan Ranking and Delay in payments for completed work, frequent owner interference,
respondent
9 and Soon relative 28 changing requirements, lack of communication between the various
(Public &
(2007) [17] importance index parties, problems with neighbors, and unforeseen site conditions
Private)
Mixed type
Nguyen et Ranking, Competent project manager, adequate funding until project
respondent
10 al. (2004) Spearman’s rho, 20 completion, multidisciplinary/competent project team, commitment
(Public &
[43] factor analysis to project, and availability of resources.
Private)

25

Vol. 6, No. 4 / Dec 2016


Ephrem Girma Sinesilassie, Syed Zafar Shahid Tabish, Kumar Neeraj Jha

Decision making effectiveness, Project Manager’s experience ,


Mixed type
Saqib, et al. Contractor’s cash flow, Contractor experience, Timely decision by
respondent
11 (2008) Criticality index 77 owner/ owner’s, representative , Site management, Supervision,
(Public &
[44] Planning effort, Prior project management experience, Client’s
Private)
ability to make decision.
Mixed type Poor risk management, budget overruns, poor communication
Ikediashi et Ranking and
respondent management, schedule delays, poor estimation practices, cash flow
12 al. (2014) relative 30
(Public & difficulties, design discrepancies, lack of efficient change
[45] importance index
Private) management, inadequate project structure and lack of teamwork.
Anderson Mixed type Strong project commitment, early stakeholder influence, stakeholder
Factor analysis
et al. respondent endorsement of project plans and rich project communications, a
13 and regression 60
(2006) (Public & well-structured and formal project approach and well understood and
analysis
[46] Private) accepted project purpose.
Schaufelber Interview based Well defined, that there was a mutual understanding of the scope of
Private
14 ger (2004) approach from 7 work between the owner and the contractor, and that the owner had
sector.
[47] seven contractors sufficient experience with the design-build project delivery method.
Well organized facility team, contract that allows and encourages the
Mixed type team chemistry without conflict of interest and differing goals,
Sanvido et Ranking,
respondent experience in project management, planning, design, construction
15 al., 1992 Spearman’s rho, 35
(Public & and operation of similar facilities, and timely valuable optimization
[48] pairwise analysis
Private) information from the owner, user, designer, contractor and operator
in the planning and design phase of the facility.

III. RESEARCH METHOD


[15] described that the inclusion of special conditions
The focus of this research is to identify and evaluate
in contracts, changes in construction plans and
the success and failure attributes for the no-dispute
specifications, and the resulting contradictory and
performance of public sector construction projects. This
erroneous information in the mass of documents all
involves a literature review to capture the existing body
contribute to the germination and manifestation of
of knowledge about project performance attributes.
construction disputes.
Then, a questionnaire-based survey was conducted to
A study by [16] is a good reference for the root
elicit the views of experienced public sector
causes of construction disputes. These causes included
professionals on these attributes. Finally, univariate and
unfair risk allocation, unrealistic time/cost/quality targets
multivariate data analyses such as ANOVA, factor
by the client, an adversarial industry culture,
analysis and regression analysis were applied. Through
inappropriate contract type, and unrealistic information
ANOVA, significant attributes were identified. Then,
expectations. In another study, [17] found that factors
these attributes were grouped into several factors through
such as delay in payments for completed work, frequent
factor analysis. Finally, regression analysis was
owner interference, changing requirements, lack of
conducted to identify the critical factors. The steps
communication between the various parties, problems
involved are briefly explained below.
with neighbors, and unforeseen site conditions could
cause disputes among project participants. A. Step 1-identification of attributes affecting project
Later, a survey by [1] reported that the most common performance
causes of construction disputes are the nature of the task An initial list of project performance attributes was
being performed (failure to detect and correct errors), prepared from the literature, including leading journals
people’s deliberate practices (failure to abide by and project management textbooks. Because the
contractual requirements) and circumstances arising attributes selected were from the literature, which
from the situation or environment the project was primarily includes studies in the context of developed
operating in (unforeseen scope changes). nations, it was decided to present these attributes to key
From our literature review, it was found that most of construction professionals in Ethiopia to obtain feedback
the studies on construction project performance have on them. Based on the feedback, necessary modifications
been conducted in the context of the developed world, were made to the list of attributes, and a list of 35 project
and only a few studies have been conducted pertaining to performance attributes was prepared. The fragmented
public construction projects of African countries. Hence, nature of the construction industry makes these attributes
their findings may not be relevant to developing non-exhaustive, but they still cover many types of
countries. Ethiopia is not yet a developed country, and construction projects.
the performance of projects has also not been B. Step 2-questionnaire development.
encouraging. Therefore, it will be beneficial to compare The questionnaire was designed to assess the impact
and discuss the results by assessing similar attributes as of the above-mentioned 35 project performance
those studied in other countries. Accordingly, for this attributes on the no-dispute performance of public
study, 35 attributes were selected from the literature and construction projects. The respondents were requested to
project management textbooks. rate these attributes for the project in which they were
involved.

26
KICEM Journal of Construction Engineering and Project Management
Critical Factors Affecting No-dispute Performance: A Case of Ethiopian Public Construction Projects

A five-point scale was used to measure the and on the expected line with or without the outliers. At
attributes’ influence on no-dispute performance: “1” the end, these outliers were excluded from further
refers to “Adversely increasing project disputes,” “2” analysis.
refers to “significantly increasing project disputes,” “3” The effectiveness of attributes was calculated for the
refers to “marginally increasing project disputes,” “4” projects based upon no-dispute performance criteria for
refers to “no effect on project disputes,” and “5” refers to successful and failed projects. These are ranked: ‘high’
“helps in decreasing project disputes”. The target and ‘very high’ for the successful projects, while for
respondents were engineers involved in public sector failed projects these are ranked ‘low’ and ‘very low’.
projects. The mean responses of the attributes can be considered
the indicators of the effectiveness of the attributes.
C. Step 3-selection of respondents.
Depending upon the mean scores of the responses for
A list of completed public construction projects
various attributes, the attributes were then segregated in
(Railways, highways, buildings, and water works) was
three groups: if the mean score of the responses for any
developed on the basis of information obtained from
attribute is significantly >4.5, that attribute contributes
different government offices responsible for public
positively to reducing project disputes and is thus a
construction works. A total of 407 questionnaires were
“success attribute” (Group-1). If the mean score is
distributed to respondents selected randomly from the
significantly < 3.5, then it causes negative impacts and is
list made available by these offices. A total of 200
called a “failure attribute” (Group-3). However, an
responses were received. The average response rate was
attribute with a mean score falling between 3.5 and 4.5
49.1%. As is shown in Table II the respondents had a
can be considered neutral (Group-2) because it would
wide range of experience, and the average experience of
have neither a positive nor negative impact. It was
the respondents was 17 years.
decided to drop the project attributes of the second group
TABLE II
(with 4.5 <µ<3.5).
SUMMARY OF RESPONDENT’S PROFILE. Analysts that adopt a relative importance index (RII)
Experience
Percentage Contract Amount Percentage
assert that the mean values and standard deviations of
in years each variable, assessed individually, are not statistically
Less than10 Less than Birr 100
20 36.0 suitable to compute relative importance across variables.
year Million
Between 10- Between 100- 300 They argue that magnitudes computed based on such
51.5 20.5 values would not reflect any relative relationships among
20 year Million
Between 20-
21
Between 300-600
33.0 variables of interest to justify comparison [18].
30 year Million Therefore, this group of analysts advocated for the use of
More than 30 Between 600-900
year
7.5
Million
7.0 a RII that yields values that are comparable in relative
Above 900 Million 3.5 terms. The RII (Relative Importance Index) was
Note: 1 USD = 20.99 Ethiopian Birr. computed using the following equation
∑W
D. Step 4-analysis method. RII = ⁄(A ∗ N) -------------------------------- (1)
All the responses were stored and analyzed using
where w is the weight given to each attribute by the
Statistical Package for the Social Sciences (SPSS)
respondents and ranges from 1 to 5, A is the highest
Version 20. The statistical tests used in this study
weight (i.e., 5 in this case), and N is the total number of
included both univariate and multivariate analysis
respondents.
techniques. Mahalanobis D² (d-squared) was used to find
The attributes of the first group (with µ>4.5) were
the outliers from the data. ANOVA, mean, median,
arranged on their descending order of RII values and
standard deviation and frequency were used to determine
ranked. The highest RII indicates the most critical
the summary statistics of the responses. Reliability
success attributes with rank 1 and the next indicating the
assessment (internal consistency through Cronbach's
next most critical success attribute with rank 2 and so on.
alpha coefficient) and factor analysis (Bartlett test of
On the other hand, attributes of the third group (with
sphericity, KMO test, PCA with Varimax rotation) were
µ<3.5) were arranged in the ascending order of the RII
carried out to determine the success and failure factors.
and ranked. The lowest RII indicates the most critical
Multiple regression analysis was conducted on the
failure attribute with rank 1, the next indicating the next
factors obtained by factor analysis to determine the most
most critical failure factor 2 and so on.
important factors.
As is shown in Table III &IV, a total of 13 attributes
emerged as success attributes (µ>4.5) and 12 attributes
IV. DATA ANALYSIS
as failure attributes (µ<3.5) respectively, while ten
Using Mahalanobis D² (d-squared) the authors found
attributes remained neutral (3.5<µ<4.5). Neutral
eleven outliers in the data samples with probability value
attributes falling in the group 3.5<µ<4.5 were discarded.
below 0.001. Analyses were performed with and without
these outliers, and the results obtained were compared to
determine whether the results are more representative

27

Vol. 6, No. 4 / Dec 2016


Ephrem Girma Sinesilassie, Syed Zafar Shahid Tabish, Kumar Neeraj Jha

participants (RII=0.918) emerged as the top five success


attributes when no-dispute criteria is of prime
TABLE III
importance in gauging project performance. Rankings
TABLE III are shown in Table III. Public sector projects require the
RANK OF SUCCESS ATTRIBUTES (µ>4.5) BASED ON management of all stakeholders, but this can also be used
PERFORMANCE CRITERIA.
as an opportunity and a source of resources and support
Sl. No. Project Success Attributes RII Rank
No major changes in the scope of work
for dispute resolution [19].
1 0.949 1 The studies by [38] and [20] revealed that changes in
during construction.
2 Regular schedule and budget updates. 0.928 2 the scope of work during construction cause disputes in
Adequate communication among all the construction industry. Project scope changes could be
3 0.927 3
project participants. as a result of incorrect initial scope definition. Hence, a
4 Top management support. 0.921 4
Understanding responsibilities by drawing and design brief with minimal subsequent
5 0.918 5 changes should be presented and approved by the
various project participants.
Project Manager’s with similar project client/owner at the highest level.
6 0.918 6
experience. Updating the project schedule and budget on a
Availability of resources (fund,
regular basis while keeping a close watch on the timeline
7 machinery, materials etc.) as planned 0.917 7
throughout the project and cost may help the project manager to avoid time and
Clearly articulated scope and nature of cost overruns, which are the main causes of dispute in
8 0.915 8
work in the tender. construction projects ([39], [40]).
Thorough pre-qualification for potential Adequate communication and understanding
9 0.912 9
bidders.
Regular monitoring and feedback by top
responsibility helps in building trust, which helps in
10 0.912 10 resolving conflicts among the project participants and
management.
11
Thorough understanding of scope of
0.904 11
delivering the project with the least number of disputes.
work by project manager. Further, if project managers and the top management are
Regular design and construction control supportive of each other, even major disputes can be
12 0.900 12
meetings.
Coordinating ability and rapport of resolved strategically.
13 project manager with his team members 0.871 13 B. Failure attributes
and sub-contractors. The rank order of the failure attributes in the no-
TABLE IV
dispute performance criteria (Table IV) suggests that the
RANK OF FAILURE ATTRIBUTES (µ<3.5) BASED ON failure of top management to make timely decisions
PERFORMANCE CRITERIA. (RII=0.379), conflicts between project managers and top
Sl. No. Project Failure Attributes RII Rank management (RII=0.404), conflicts among team
Reluctance in timely decision by top 0.379 1 members (RII=0.414), conflicts between project
1
management.
Conflicts between project manager and top 0.404 2
managers and sub-contractors (RII=0.438), and holding
2 key decisions in abeyance (RII=0.440) emerged as the
management.
3 Conflict among team members. 0.414 3 top five failure attributes when no-dispute criteria is of
Conflict between project manager and sub- 0.438 4 prime importance in gauging the project performance.
4
contractor. Disputes arise from a process involving conflict [21].
5 Holding key decisions in abeyance. 0.440 5
6 Hostile social and economic environment. 0.441 6
The prior presence of conflict between parties may
Ignorance of appropriate planning tools 0.456 7 initiate an unnecessary dispute [16]. In addition, the
7
and techniques by project manager. failure of top management to make timely decisions can
Lack of understanding of operating 0.464 8 lead to serious disagreements among the construction
8
procedure by the project manager.
team. Therefore, valuable timely decisions by top
9 Unfavorable climatic condition at the site. 0.479 9
Inadequate project formulation in the 0.493 10 management can help in taking timely measures to avoid
10 disputes. If any conflict during construction is not
beginning.
11
Reluctance in timely decision by project 0.496 11 resolved and timely decisions are not given, disputes
manager. become complicated and difficult to resolve.
12 Size and value of the project being large. 0.497 12
C. Factor analysis
In the following sections, the factor analysis
A. Success attributes performed to identify success and failure factors and the
No-dispute performance can be achieved if a project description of these factors will be presented.
is completed with the least number of litigations In the present study, factor analysis is performed
resulting from disagreement among project participants. separately on a group of 13 success attributes and 12
The success attributes no major changes in the scope of failure attributes. Factor analysis is a method of
work during construction (RII= 0.949), regular schedule quantitative multivariate analysis with the main aim of
and budget updates (RII=0.928), adequate identifying the interrelationships between a set of
communication among all project participants continuously measured variables (usually represented by
(RII=0.927), top management support (RII=0.921), and their interrelationships) using a number of underlying
the understanding of responsibilities by various project

28
KICEM Journal of Construction Engineering and Project Management
Critical Factors Affecting No-dispute Performance: A Case of Ethiopian Public Construction Projects

linearly independent reference variables called factors  degrees of freedom (df) 66 66


[22].  Sig. 0.000 0.000
Many researchers from other fields, including
politics, sociology, economics, human –machine To facilitate interpretation of factor loadings, an
systems, accident research, taxonomy, biology, medicine oblique rotation of the reference axes, called varimax
and geology have also applied this technique [23]. In the rotation, was performed, and the derived factors and their
construction industry, for instance,[24] used the factor corresponding loadings were obtained [32].
analysis technique to explore key stressors leading to In this study, a total of six success factors and five
construction professionals’ stress in the Gaza Strip. [25] failure factors with Eigen values greater than 1 were
employed the factor analysis technique to identify five extracted. Names were assigned to these factors. The
principal components that influence the market factors with their names representing their common and
environment for artisanal dimension stone in Nairobi, latent properties, the variance explained by each of them,
and [26] also applied this technique to identify a set of and the factor loadings of various attributes appearing in
eight key factors associated with construction industry each factor are summarized in Tables VI and VII
development. respectively. Factor loadings < 0.5 are suppressed in the
To ensure the suitability and reliability of the data for analysis, and only those having loading values > 0.5 are
factor analysis, an adequate sample size is needed. used for the interpretations. The reliability of the factor
According to [27], the sample size should not be less model was also evaluated with the communalities of
than 100, even if the number of variables is less than 20, each variable. The communalities of all variables are
and the subjects-to-variables ratio should be no lower found to be much greater than 0.5, which signifies that
than 5 [41]. In this research, the ratio of respondents to the factor model is reliable.
variables for success and failure attributes was found to a) Success factors
be 12 and 15, respectively, which is greater than 5 and
exceeds the threshold for the minimum number of The description of success factors is given in the
respondents (100). Cronbach’s alpha (α) tests were following sections.
performed to evaluate sample reliability (internal
consistencies). The Cronbach’s alphas of 0.766 for TABLE VI
success attributes and 0.735 for failure attributes suggest FACTOR PROFILE OF PROJECT SUCCESS ATTRIBUTES FOR
NO-DISPUTE AS PERFORMANCE CRITERIA.
that the overall sample reliability (internal consistency) Variance
was acceptable for factor analysis ([28],[29]). The data Factor structure Loading
Explained
were also assessed for suitability for factor analysis using Availability of resources and pre-
13.10%
the Kaiser–Meyer–Olkin measure of sampling adequacy qualification
(KMO) and Bartlett's test of sphericity. The Meyer-Olkin Thorough pre-qualification for potential
0.845
bidders.
(KMO) measure of sampling adequacy, a popular Availability of resources (fund,
diagnostic measure, tests whether the partial correlations 0.797
machinery, materials etc.)as planned
among variables are small. It is a measure of throughout the project
homogeneity of variables [30]. A higher value of KMO Project manager's competence 12.23%
Thorough understanding of scope of
is desired. Bartlett’s test of sphericity tests whether the work by project manager.
0.828
correlation matrix is an identity matrix, which would Understanding responsibilities by various
0.649
indicate that the factor model is inappropriate. It is project participants.
generally recommended that the KMO value should be Project manager’s with similar project
0.540
greater than 0.5 if the sample size is adequate [41],[31]). experience.
Top management support 11.76%
As shown in Table V, the KMO values for success and Top management support. 0.763
failure attributes were 0.723 and 0.685, respectively, and Regular monitoring and feedback by top
0.732
were considered appropriate for use in factor analysis. management.
The results of the Bartlett's tests for success and failure Owner's competence 11.58%
attributes were 302.063 and 628.781, respectively, and Clearly articulated scope and nature of
0.704
work in the tender.
the associated significance levels (sig. value) were < No major changes in the scope of work
0.001, indicating that the population correlation matrix 0.652
during construction.
was not an identity matrix. Interaction among project participants 11.16%
Coordinating ability and rapport of
TABLE V project manager with his team members 0.838
KMO AND BARTLETT'S TEST OF SUCCESS AND FAILURE and sub-contractors.
ATTRIBUTES Adequate communication among all
0.771
For success For failure project participants.
Parameter description Construction meetings, and schedule and
attributes attributes 10.31%
KMO-measure of sampling budget updates
0.723 0.685 Regular schedule and budget updates. 0.871
adequacy.
Bartlett's Test of Sphericity Regular design and construction control
0.600
 Approx. Chi-Square 302.063 628.781 meetings.
Cumulative variance explained 70.14%

29

Vol. 6, No. 4 / Dec 2016


Ephrem Girma Sinesilassie, Syed Zafar Shahid Tabish, Kumar Neeraj Jha

manager for project success has a positive impact on no-


dispute performance. In addition, it is difficult to
minimize dispute without regular monitoring and
1) Availability of resources and pre-qualification
feedback by top management.
4) Owner competency
The attributes emerging under the first factor account
for a variance of 13.10%, the highest of all factors, and Two attributes have emerged under this factor
they explain availability of resources and pre- accounting for a variance of 11.58%: a clearly articulated
qualification. This comprises the thorough pre- scope and nature of the work in the tender and no major
qualification of potential bidders and the availability of changes in the scope of the work during construction.
resources (fund, machinery, materials etc.) throughout One of the priority issues in enhancing no-dispute
the project. performance in construction projects is to clearly
Resources should be made available and, if needed, articulate the scope and nature of the work in the tender
shared resources could also be utilized for fulfilling the so that there are no major changes in the scope during
objectives. The availability of resources throughout the construction. Therefore, experience and a sufficient level
project will help in reducing the potential for disputes. of competence of the owner are required in preparing
The study by [33] noted that the shortage of resources in scope documents.
construction projects has been the cause of disputes.
5) Interaction among project participants
Another study by [34] also revealed that the non-
availability of resources as planned has been one of the This factor has two attributes: the coordinating ability
top ten causes of disputes in construction projects. and rapport of the project manager with his team
Further, the thorough pre-qualification of potential members and sub-contractors and adequate
bidders is a yardstick to allow or disallow the firms to communication among all project participants. It
participate in the bids. It helps the owner to select accounts for a variance of 11.16%. Continuous
reputed and capable firms with proven track-records so coordination by the project manager and relationships
that disputes during construction may be reduced. among project participants are required through the
project life cycle for solving problems and achieving no-
2) Project manager's competence
dispute performance.
This factor has three attributes accounting for 12.23%
6) Construction meetings, and schedule and
of the variance. This comprises thorough understanding
budget updates
of the scope of work by the project manager, various
project participants’ understanding of their This factor has two attributes accounting for 10.31%
responsibilities and project managers with similar project of variance: regular schedule and budget updates and
experience. The project manager is the key person in a regular design and construction control meetings.
project and should understand his or her role. He or she A thorough, detailed review of the contractor's
should have interpersonal, technical and administrative schedule and budget baseline and all schedule and
skills. budget updates is necessary to ensure that schedules and
A clear understanding of the scope of work by the budgets comply with the specification requirements. This
project manager may minimize construction disputes. In may help in reducing the potential for disputes.
cases in which the project manager does not understand Furthermore, to ensure that the project meets the targets
the scope of work, he or she cannot apply the proper without disputes, the entire process should be closely
basics of managerial principles to the project; hence, the scrutinized by the project manager and his team
project progress may be delayed and disputes may arise. members using regular design and construction control
Moreover, he or she must take the lead by establishing meetings for any design delays.
clear responsibilities and making each project participant b) Failure factors
understand what he or she is responsible for to minimize The description of failure factors is given in the
dispute. In this regard, the previous experience of a following sections.
project manager on similar projects makes him or her TABLE VII
competent. FACTOR PROFILE OF PROJECT FAILURE ATTRIBUTES FOR
NO-DISPUTE AS PERFORMANCE CRITERIA
3) Top management support Variance
Factor Structure Loading
Explained
This factor has two attributes accounting for 11.76% Conflict among project participants 18.05%
of the variance. This factor comprises top management
support and regular monitoring and feedback by top Conflict among team members. 0.819
management. Conflict between project manager
0.721
and top management.
Top management support/commitment is an essential Conflict between project manager
element for ensuring no-dispute performance. For 0.550
and sub-contractor.
instance, the willingness of top management to provide Indecisiveness of project participant 14.64%
the necessary resources and authority/power to project

30
KICEM Journal of Construction Engineering and Project Management
Critical Factors Affecting No-dispute Performance: A Case of Ethiopian Public Construction Projects

Reluctance in timely decision by top know what operating procedures should be carried out to
0.751
management. avoid those factors causing disputes. However, lack of
Holding key decisions in abeyance. 0.731
these knowledge and operating procedures by a project
Reluctance in timely decision by
project manager.
0.726 manager may have a negative impact on no-dispute
Project manager's ignorance and lack performance.
14.00%
of knowledge
Lack of understanding of operating 4) Hostile socioeconomic and climatic conditions
0.901
procedure by the project manager.
Attributes of this factor include a hostile social and
Ignorance of appropriate planning
tools and techniques by project 0.886 economic environment and unfavorable climatic
manager. conditions at the site. Hostile socioeconomic and
Socio Economic and climatic climatic conditions create difficult working conditions
13.17%
condition for workers on site. This factor affects construction
Hostile social and economic
environment.
0.849 projects adversely in the form of difficulties in timely
Unfavorable climatic condition at the mobilization of the resources, frequent stoppage of work,
0.681
site. labor unrest, and reduced productivity, which may lead
Project specific factors 12.28% to construction disputes. Further, a study by [16]
Inadequate project formulation in the identified unfavorable climatic conditions at the site as
0.808
beginning.
Size and value of the project being one of the causes of disputes. Both attributes under this
0.738 factor have negative impacts on the efficiency and
large.
Cumulative variance explained 72.14% productivity of the workforce and thus impact no-dispute
performance. This factor explains 13.17% of the
variance.
1) Conflict among project participants
5) Project specific factor
Three attributes have emerged under this factor
accounting for a variance of 18.05%, the highest of all The attributes with high loading in this factor are
factors. This is comprised of conflict among team inadequate project formulation in the beginning and the
members, conflicts between project managers and top size and value of the project being large. It accounts for a
management, and conflict between project managers and variance of 12.28%.
sub-contractors. Inadequate project formulation in the beginning may
The top management must devise a suitable means to result in design changes, changes in project scope,
avoid conflict among project participants that could lead schedule acceleration, and failure to supply sufficient
to disputes. resources, which can lead to construction disputes [35].
Moreover, as the size and cost of the project increases,
2) Indecisiveness of project participants
the complexity and risk of the project may increase [42].
Two attributes have emerged under this factor This could be because larger projects are typically more
accounting for a variance of 14.64%: the failure of top complex, require multi-disciplinary inputs, are non-
management to make timely decisions and holding key integrative, are more time consuming, etc., and hence
decisions in abeyance. there could be a greater likelihood of disputes.
The reluctance of top management and project D. Critical success and failure factors
managers to make day-to-day decisions and holding key As mentioned above, factor analysis was used to
decisions in abeyance has a negative impact on no- transform the 25 significant success and failure attributes
dispute performance. Therefore, top management and into a few success and failure factors. To explore the
project managers need to make effective and timely relative importance of these factors in impacting no-
decisions regarding any issue that might arise during the dispute performance, multiple regression analysis was
course of the project. applied. The factors found significant using multiple
3) Project manager ignorance and lack of regression analysis are referred to as ‘critical
knowledge success/failure factors’.
The general purpose of a multiple regression is to
This factor accounts for 14% of variance explained. learn about the relationship among several factors
The attributes with high loading in this factor are: (known as independent variables or explanatory
ignorance of appropriate planning tools and techniques variables) and another factor (known as the dependent
by the project manager and lack of understanding of variable or response variable). The regression model
operating procedures by the project manager. takes the form of the following equation
Project management tools and techniques help a
project manager in the development of a realistic Y = a 0 + a1 X1 + a 2 X2 + a 3 X3 + ⋯ + a n Xn + e ----- (2)
approach to achieve no-dispute performance. Therefore, where Y is the dependent variable, Xi (i =1, 2 … n) are
the project manager should have the required knowledge the independent variables, ai (i= 0, 1 … n) are the
about these tools and techniques and their application in parameters to be estimated, and e is the error term.
construction projects and also the project manager has to
31

Vol. 6, No. 4 / Dec 2016


Ephrem Girma Sinesilassie, Syed Zafar Shahid Tabish, Kumar Neeraj Jha

This study uses the responses on no-dispute significantly contribute to no-dispute performance of
performance of the project as the dependent variable and Ethiopian public construction projects while the factor of
factors found from factor analysis as independent conflict among project participants is found to be
variables. detrimental to no-dispute performance of Ethiopian
a) Critical success factor public construction projects.
Table VIII shows the stepwise multiple regression The importance of the owner’s role in minimizing
results, when ‘no-dispute performance’ is treated as the disputes begins at the start of the project, as plans are
dependent variable and the six success factors discussed formulated; this is when the owner has the most
above as independent variables. influence over the construction process. The owner
should be competent enough to prepare a clearly
articulated scope and unambiguous nature of work in the
TABLE VIII tender. By doing so, major changes in the scope of work
STEPWISE MULTIPLE REGRESSION RESULTS FOR SUCCESS during construction, which is the cause of construction
FACTORS. disputes ( [38], [20]), could be avoided. Moreover,
Independent variables B σ β t-value p-value
Dependent variable: No-dispute; R2= 0.34, Adjusted R2= 0.10 project managers and their teams must develop effective
Constant 4.58 0.04 NA 121.617 0.00 communication channels to avoid or reduce the potential
Factor 4. owner's for disputes. They must learn to create an atmosphere
0.15 0.04 0.29 3.88 0.00
competence that encourages open communication. Communication
Factor 5. interaction needs to be established from the start to prevent the
among project 0.10 0.04 0.16 2.07 0.04
participants problems from escalating into disputes. Poor
communication and misunderstandings among project
In this case ‘owner's competence’ (Factor 4), and members are some of the most common reasons for
‘interaction among project participants’ (Factor 5), were disputes [36]. Moreover, as the construction process
found to be significant at p< 0.05 for no-dispute requires a great amount of manpower with diverse skill
performance for public projects. These factors are the sets, coordination is required in almost every stage of a
most important when the objective is no-dispute project. Considerable time is consumed in coordination.
performance. Project managers must realize that time spent on
coordination is an investment, which bears fruit through
b) Critical failure factor
no-dispute performance. Further, according to [37], if
Table IX shows the stepwise multiple regression
conflicts are not properly managed, they may cause
results, when ‘no-dispute performance’ is treated as the
project delays and increase project costs, which leads to
dependent variable and the five failure factors as
dispute. Therefore, top management must devise a means
independent variables.
to avoid conflict by creating a suitable environment to
TABLE IX build up a team spirit among project participants. This is
STEPWISE MULTIPLE REGRESSION RESULTS FOR FAILURE because the achievement of success in no-dispute
FACTORS. performance is a team effort and if the team members are
Independent variables B σ β t-value p-value not working in unison it leads to adverse effects on the
Dependent variable: No-dispute; R2= 0.05, Adjusted R2= 0.04
Constant 1.85 0.03 NA 70.783 0.00
performance of a construction project.
Factor 1. conflict among As with any other opinion -based study, the present
-0.10 0.03 -0.22 -2.94 0.00 study also has some limitations. The majority of
project participants
respondents have evaluated the projects in their
The ‘conflict among project participants’ (Factor 1), execution stage only and very few have evaluated the
is found to be significant at p<0.05 for no-dispute performance of projects in the planning and operation
performance of public construction projects. stages. The study was also carried out only in the
Ethiopian context. Hence the study has a limitation in
V. DISCUSSION this regard.
Disputes between the parties to construction projects In this study the importance of understanding the
are of great concern to the industry. It can be damaging impact of various factors on project performance was
and expensive, thus it should be studied more to be emphasized. Further research is needed to investigate
minimized or prevented. There are certain factors that potential improvement in the implementation of no-
affect no-dispute performance in construction projects. dispute performance in the Ethiopian public construction
Identifying these factors and taking appropriate measures industry.
could be an important step towards improving no-dispute
performance. VI. CONCLUSION
This study identified the critical factors affecting no- Completing public construction projects without
dispute performance of public construction projects in disputes is still a challenge for construction
Ethiopia. The stepwise multiple regression analysis professionals. If disputes are avoided, it can result in the
indicated that Factor 4 (owner's competence), and Factor successful delivery of public construction projects.
5 (interaction among project participants) can

32
KICEM Journal of Construction Engineering and Project Management
Critical Factors Affecting No-dispute Performance: A Case of Ethiopian Public Construction Projects

In this paper, the critical success and failure factors Engineering, Construction and Architectural Management, vol. 17,
no. 4, pp. 404–423, 2010
for no-dispute performance in the construction industry
[2] A. Dinku and G. Kahssay, “Claims in international construction
were analyzed. First, 35 attributes for no-dispute projects in Ethiopia and a case studies on selected projects,”
performance were identified with a comprehensive Journal of EEA, vol. 20, pp. 1–14, 2003.
literature review. Through ANOVA, significant success [3] J. M. Keating and M. L. Shaw, “Compared to what?’: Defining
terms in court-related ADR programs,” Negotiations Journal, vol. 6,
and failure attributes were identified. Then, factor
no. 3, pp. 217–220, 1990.
analysis was conducted to transform the significant [4] J. Yang, G. Q. Shen, D. S. Drew, and M. Ho, “Critical success
success and failure attributes into several success and factors for stakeholder management: Construction practitioners’
failure factors. After determining the success and failure perspectives,” Journal of Construction Engineering and
Management, vol. 136, no. 7, pp. 778–786, 2010.
factors, multiple regression analysis was conducted on
[5] J. F. Rockart, “The changing role of the information systems
these factors to determine the critical factors for no- executive: A critical success factors perspective,” Sloan School of
dispute performance. The analysis reveals that the Management, pp. 3–13, 1982.
critical factors found in this study are related to people [6] A. C. Boynton and R. W. Zmud, “An Assessment of Critical
Success Factors,” Sloan Management Review, vol. 25, pp. 17–27,
competency. This also shows that people competency
1986.
issues in Ethiopian public construction projects are given [7] N. Gudiene, A. Banaitis, and N. Banaitiene, “Evaluation of critical
inadequate attention. Competency is the underlying success factors for construction projects - an empirical study in
characteristic of a person that enables that person to Lithuania,” International Journal of Strategic Property
Management, vol. 17, no. 1, pp. 21–31, 2013.
demonstrate superior performance on a job. Hence, a
[8] A. P. C. Chan, D. C. K. Ho, and C. M. Tam, “Design and Build
lack of competent people in the sector lowers the Project Success Factors: Multivariate Analysis,” Journal of
possibility of the successful achievement of no-dispute Construction Engineering and Management, vol. 127, no. 2, pp.
performance. 93–100, 2001.
[9] Y. C. Kog and P. K. Loh, “Critical success factors for different
It is common for developing countries such as
components of construction projects,” Journal of Construction
Ethiopia to use foreign consultancy firms to develop Engineering and Management, vol. 138, no. 4, pp. 520–528, 2012.
their physical infrastructures. These foreign firms, in [10] K. C. Iyer and K. N. Jha, “Factors affecting cost
addition to executing different projects across the performance: Evidence from Indian construction projects,”
International Journal of Project Management, vol. 23, no. 4, pp.
country, should make an effort to work on technology
283–295, 2005.
transfer and training to produce competent people in the [11] A. P. C. Chan, D. W. M. Chan, Y. H. Chiang, B. S. Tang, E.
sector, which enhances domestic capabilities. This H. W. Chan, and K. S. K. Ho, “Exploring critical success factors
research has emphasized the role of people in the for partnering in construction projects,” Journal of Construction
Engineering and Management, vol. 130, no. 2, pp. 188–198, 2004.
construction industry.
[12] S. Z. S. Tabish and K. N. Jha, “Important factors for success
This study provides new and significant information of public construction projects.,” International Conference on
regarding the determinants affecting construction Construction and Project Management, vol. 15, pp. 64–68, 2011.
projects in Ethiopia. It will play a vital role in the [13] M. Agumba and J. N. Baloyi, “Causes of dispute in
construction projects in South Africa- A case of Gauteng province.,”
construction industry to identify critical success factors
in Proceedings 8th Construction Industry Development Board
and consider them in new projects. Further, it helps in (CIDB) Postgraduate Conference, pp. 179–187, 2014.
eliminating or solving failure factors that affect a [14] M. E. A. El-razek, H. Bassioni, and W. A. El-Salam,
construction project. This will help in reducing time and “Investigation Into the Causes of Claims in Egyptian Building
Construction,” ARCOM Conference, no. September, pp. 147–156,
cost issues that arise due to disputes, and new projects
2007.
may be completed within the stipulated time and budget. [15] S. O. Cheung, T. W. Yiu, and S. F. Yeung, “A Study of
The implications of this study are not limited to Styles and Outcomes in Construction Dispute Negotiation,”
researchers and construction industry practitioners. The Journal of Construction Engineering and Management, vol. 132,
no. 8, pp. 805–814, 2006.
Ethiopian government could adopt the results of this
[16] M. M. Kumarasswamy, “Conflicts, claims and disputes in
study to reduce/avoid additional costs incurred due to the construction,” Engineering, Construction and Architectural
poor no-dispute performance of public construction Management, vol. 4, no. 2, pp. 95–111, 1997.
projects, which results in poor utilization and an [17] M. Sambasivan and Y. W. Soon, “Causes and effects of
delays in Malaysian construction industry,” International Journal
increased social and economic cost. Furthermore, the
of Project Management, vol. 25, no. 5, pp. 517–526, 2007.
study may also help government efforts to enhance the [18] N. A. A. Bari, R. Yusuff, N. Ismail, A. Jaapar, and R.
efficient and effective use of public funds on Ahmad, “Factors influencing the construction cost of industrialised
construction projects, which is an on-going concern of building system (IBS) Projects,” Procedia - Social and Behavioral
Sciences, vol. 35, no. 2012, pp. 689–696, 2012.
the government and of the international development
[19] D. W. Wirick, Public-Sector Project Management: Meeting
community. the Challenges and Achieving Results. 2009.
It would be interesting to carry out further research to [20] A. Ashworth, Contractual procedures, Edition, F. Pearson
investigate potential improvement in the implementation Longman, New York., 2005.
[21] P. Fenn, D. Lowe, and C. Speck, “Conflict and dispute in
of no-dispute performance by evaluating the projects in
construction,” Construction Management and Economics, vol. 15,
their planning, execution and operation stages. no. 6, pp. 513–518, 1997.
[22] L. Bing, A. Akintoye, P. J. Edwards, and C. Hardcastle,
REFERENCES “Critical success factors for PPP/PFI projects in the UK
[1] P. Love, P. Davis, J. Ellis, and S. O. Cheung, “Dispute causation: construction industry,” Construction Management and Economics,
identification of pathogenic influences in construction,” vol. 23, no. 5, pp. 459–471, 2005.

33

Vol. 6, No. 4 / Dec 2016


Ephrem Girma Sinesilassie, Syed Zafar Shahid Tabish, Kumar Neeraj Jha

[23] J. S. Williams and D. Child, The Essentials of Factor [37] S.-O. Cheung and H. C. H. Suen, “A multi-attribute utility
Analysis., vol. viii. 2003. model for dispute resolution strategy selection,” Construction
[24] A. Enshassi and E. Al.Swaity, “Key Stressors Leading to Management and Economics, vol. 20, no. 7, pp. 557–568, 2002.
Construction Professionals ’ Stress in the Gaza Strip , Palestine,” [38] Hewitt, R., Winning construction disputes: strategic
Journal of Construction in Developing Countries, vol. 20, no. 2, pp. planning for major litigation, Ernst and Young, London, 1991.
53–79, 2015. [39] Heath, B., Hills, B., & Berry, M., The Origin of Conflict
[25] O. A. K’Akumu, B. Jones, and Y. Junli, “Factor Analysis of within the Construction Process, CIB Publication 171, First Plenary
the Market Environment for Artisanal Dimension Stone in Nairobi, Meeting of TG-15, The Netherlands, 35-48, 1994.
Kenya,” Journal of Construction in Developing Countries, vol. 18, [40] Adriaanse, J., Construction contract law: The essentials,
no. 2, pp. 15–32, 2013. Palgrave-Mac Millan, New York, 2005.
[26] P. Fox and M. Skitmore, “Factors facilitating construction [41] Gorsuch, R.L., Factor analysis (2nd ed.). Hillsdale,NJ:
industry development.,” Building Research and Information, vol. Erlbaum, 1983.
35, no. 2, pp. 178–188, 2007. [42] Carmichael, D.G., Dispute and international projects, The
[27] W. a. Arrindell and J. van der Ende, “An Empirical Test of University of New South Wales, Sydney, Australia, 2002.
the Utility of the Observations-To-Variables Ratio in Factor and [43] L. D. Nguyen, S. O. Ogunlana, and D. T. X. Lan, “A study
Components Analysis,” Applied Psychological Measurement, vol. on project success factors in large construction projects in Vietnam,”
9, no. 2, pp. 165–178, 1985. Eng. Constr. Archit. Manag., vol. 11, no. 6, pp. 404–413, 2004.
[28] J. Pallent, Spss survival manual. Crows Nest, Australia: [44] M. Saqib, R. U. Farooqui, and S. H. Lodi, “Assessment of
Allen and Unwin., 2001. Critical Success Factors for Construction Projects in Pakistan,”
[29] R. F. Fellows, A. M. M. Liu, and A. M. M. Liu, Research First Int. Conf. Constr. Dev. Ctries. “Advancing Integr. Constr.
Methods for Construction, 4th Ed. Oxford: Blackwell publishing Educ. Res. Pract., pp. 392–404, 2008.
Ltd., 2008. [45] D. I. Ikediashi, S. O. Ogunlana, and A. Alotaibi, “Analysis
[30] S. Sharma, Applied Multivariate Techniques Subhash of project failure factors for infrastructure projects in Saudi Arabia:
Sharma. John Wiley and Sons, Inc., New York, 1996. A multivariate approach,” J. Constr. Dev. Ctries., vol. 19, no. 1, pp.
[31] A. Field, Andy field. London Sage Publications, London. 35–52, 2014.
[32] J. Hair, R. Anderson, B. J. Babin, and W. Black, [46] E. S. Andersen, David Birchall, S. A. Jessen, and A. H.
Multivariate Data Analysis, 7th ed. Pearson Education, London, Money, “Exploring project success,” Balt. J. Manag., vol. 1, no. 2,
2014. pp. 127–147, 2006.
[33] K. M. J. Harmon, “Conflicts between Owner and [47] J. E. Schaufelberger, “Success Factors for Design-Build
Contractors: Proposed Intervention Process,” Journal of Contracting,” Constr. Res., pp. 1–7, 2004.
Management. Engineering, vol. 19, no. 3, pp. 121–125, 2003. [48] V. Sanvido, F. Grobler, K. Parfitt, M. Guvenis, and M.
[34] Blake Dawson Waldron, A survey of pressure points in Coyle, “Critical Success Factors for Construction Projects,” J.
Australian construction and infrastructure projects. 2006. Constr. Eng. Manag., vol. 118, no. 1, pp. 94–111, 1992.
[35] G. F. Jergeas, “Claims and disputes in construction,”
Construction Law Journal, vol. 12, no. 1, pp. 3–13, 1996.
[36] E. Cakmak and P. I. Cakmak, “An Analysis of Causes of
Disputes in the Construction Industry Using Analytical Network
Process,” Procedia - Social and Behavioral Sciences, vol. 109, pp.
183–187, 2014.

34
KICEM Journal of Construction Engineering and Project Management

View publication stats

You might also like