Project Planner

MATERIALS
PERIODS
Quantity Units 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60

Sand 110 cubic

Gravel 220 cubic

16mm Dia. Rebars 80 length

Cement 1980 bagS


Item 200(Base
Course) 22 cubic
January
Equipment Quantity Units
9 10 11 12 13 14 15 16 17 18
Backhoe 1 unit 1 1 1 1 1 1 1

Road Roller 1 unit 1 1 1 1 1

Water Pump 1 unit


Concrete Vibrator 1 unit
Transit Mixer 1 unit
January
19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
February
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Total
1 1 1 1 1 1 1 1 1 35
1 1 1 1 1 1 1 1 1 33
1 1 1 1 1 1 1 1 1 25
1 1 1 1 1 1 1 1 1 25
1 1 1 1 1 1 1 1 1 25
462000
158400
January
MATERIALS Quantity Units
9 10 11 12 13 14 15 16 17 18
Sand 110 cubic 10 10 10

Gravel 220 cubic 20 20 20

16mm Dia. Rebars 80 length 80

Steel Form 0.20m*3m 15 in/out 15

Solar Lights 5 pcs 5

Steel Form 0.20m*6m 10 in/out 10

Shovel 6 pcs 6

Cement 1980 bagS 300 300 300

Item 200(Base Course) 22 cubic 11 11


January
19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6
10 10 10 10 10
20 20 20 20 20

300 300 480


February
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Total
80
160
80
15
5
10
6
1980
22