CARPENTRY WORK DEMOLITION

NO WORK DESCRIPTION BLOCK STATUS REMARKS

MAIN DECK
1 Existing Lab Room
Dismantle existing :
- furniture (Testing machine, standing AC, stainless steel table)
- paneling (4 M²)
- ceiling (4 M²) This area will be use for New Locker Room
- door (1 unit)
- insualtion (11 M²)
- Flooring (4 M²)

2 Existing Laundry Room


Dismantle existing :
- Accessoriess existing toilet.
This area will be use for New Shower Room
- Cubilac wall, wash basin.
- Flooring (6.8 M²)

3 Hospital Room
Dismantle existing :
This area will be use for New Hospital
- Furniture (table and rack)

4 Emergency Generator Room


Dismantle existing :
For work access joining AHU Room
- Insulation Partial (2.5 M²)

5 Engine Room (below AHU Room)


Dismantle existing :
Need Staging for works access
- Deckhead insulation Partial (18 M²)

A - DECK
1 Existing Officer Main Messroom
Dismantle existing :
- furniture (Round table, chair, , stainless steel table for food and waste)
- Door B15 (1 unit)
- paneling (18.9 M²) This area will be use for New Main Mess Room
- ceiling (35 M²)
- insualtion (11 M²)
- Flooring (35 M²)

2 Crew Messroom
Dismantle existing :
- furniture (long table, chair, sofa, table existing duct line. Refrigerator, TV)
- Door B15 (1 unit)
- paneling (2 M²) This area will be use for New Recreation Room
- ceiling (35 M²)
- insualtion (11 M²)
- Flooring (39 M²)

B - DECK
1 2 Man Cabin (front side) - 4 unit
Dismantle existing :
Need to change become double bunk c/w curtain
- Single bunk

2 Chief Cook Room


Dismantle existing :
- furniture (Desk, sofa, bunk, wardrobe)
This area will be use for Cabin 4 men.
- paneling (6.2 M²)
Need to dismantle for hotwork access to extend
- ceiling (2.4M²)
bulkhead.
- insualtion (6.2 M²)
- Flooring (2.4²)

3 Spare Room Stbd


Dismantle existing :
- furniture (Desk, sofa, bunk, wardrobe)
- Door B15 (1 unit)
This area will be use for New Crew’s Shower and
- paneling (30 M²)
W.C
- ceiling (10.5 M²)
- insualtion (8.7 M²)
- Flooring (10.5 M²)

4 Shower Room (Port)


- Still become toilet and shower room
- Tiles need to renew because most existing tiles
are damagend.

Dismantle existing :
- Tiles floor and wall
- existing toilet partition.

b. Finishing and cleaning

5 Client Room (Port)


Dismantle existing :
This area will be use for Cabin 4 men (Port)
- Sofa (1 unit)

C - DECK
1 Captain Room
Dismantle existing cabin: :
This area will be use for Medco office No 2
- furniture all (Desk, sofa, bunk, wardrobe, book rack, refrigerator) and door (1 unit)
2 Captain Room
Dismantle existing :
- furniture all (Desk, sofa, bunk, wardrobe)
- toilet module (1 unit)
- paneling (14 M²) This area will be use for Medco office No 1
- ceiling (14M²)
- insualtion (14 M²)
- Flooring (9M²)

3 Client Room
Dismantle existing :
- furniture all (Desk, sofa, bunk, wardrobe)
- toilet module (1 unit) This area will be use for Medco office No 1
- ceiling (12.4M²)
- Flooring (12.4M²)
4 C/E Room
Dismantle existing : : This area will be use for Conference Meeting
- furniture all (Desk, sofa, bunk, wardrobe, book rack, refrigerator) and door (1 unit) Room
5 C/E Room
Dismantle existing :
- furniture all (Desk, sofa, bunk, wardrobe)
- toilet module (1 unit)
- paneling (14 M²) This area will be use for Filling Room
- ceiling (14M²)
- insualtion (14 M²)
- Flooring (9M²)

6 C/O Room
Dismantle existing :
- furniture all(Desk, sofa, bunk, wardrobe)
- paneling (5.5 M²) This area will be use for Medco Room 2 Man stbd
- Ceiling (2.5 M²)
- Flooring (12.8M²)
7 Client Room Stbd
Dismantle existing :
- furniture all (Desk, sofa, bunk, wardrobe)
- Toilet module (1 unit)
This area will be use for Owner Office
- paneling (5.5 M²)
- Ceiling (2.5 M²)
- Flooring (12.8M²)

Nav. Bridge Deck


1 Bridge Deck Control
a. Dismantle existing furniture on front Bridge Deck all
- Locker steel
This area will be use for Gym Room and Mushola
- Table
- Gym equipment.
b. Dismantle existing (Cabin Stbd) :
- furniture all (Desk, sofa, bunk, wardrobe)
- toilet module (1 unit)
- paneling (22 M²) This area will be use for Helicopter Briefing Room
- ceiling (8.4M²)
- insualtion (22 M²)
- Flooring (8.4M²)
c. Dismantle existing (Cabin Midle) :
This area will be use for Telecom Equipment
- furniture (Desk, sofa, bunk, wardrobe)
Room
- toilet module (1 unit)
d. Dismantle existing (Cabin Port) :
- Gym Equipment and furniture. This area will be use for HLO Office
- toilet module (1 unit)

Prepared By :
CHARLIE / MISKODIR

Note: The green block is revision after comment from client and check onboard.