Professional Documents
Culture Documents
Name
Designation
Date
Signature
Amendment Sheet
The purpose of this procedure is to establish the precautions and conditions considered
necessary for safety of the personnel involved in excavation & trenching work as well as
integrity of above / underground services &/or facilities where such excavation work shall be
carried out.
Scope
The procedure is applicable to all activities & facilities where excavation is carried out for
maintenance, construction or inspection need.
Abbreviations
ft - Feet
H - Horizontal
HSE - Health, Safety and Environment
HSEMS - Health, Safety and Environment Management System
Kpa - Kilo Pascal
LTHE - Larsen and Toubro Hydrocarbon Engineering Limited
m - Meter
mm - Millimetre
PPE - Personnel Protective Equipment
tsf - Tonnes per Square Foot
Definitions
Benching
A method of protecting personnel from sidewall cave-in by excavating the sides of an
excavation to form one or more of a series of horizontal steps, with a vertical rise between
each step.
Backfilling
It is an activity to fill-in (with soil) a trench that is no longer needed and returning the area
around its original condition.
Cave - ins
It is collapse of the trench side walls due to weight of the adjacent soil. A cave - in can drop
several cubic meters of soils on trench worker.
Competent Person
One who is capable of identifying existing and predictable hazards by way of training and/or
experience in the surroundings or working conditions which are unsanitary, hazardous, or
dangerous to employees, and has authorization to take prompt corrective measures to
eliminate them.
Excavation
An excavation as any man-made cut, cavity, trench, or depression in the earth’s surface
formed by earth removal.
Manual Excavation
The excavation without using any powered equipment or excavating machinery such as
backhoe, loader, Jack Hammer etc.
Mechanical Excavation
The excavation work using powered equipment or excavating machinery such backhoe,
loader, Jack Hammer etc.
Metal Detector
It is a device to screen the excavation area to mitigate the risk of damaging unknown
pipelines, cables and utilities.
Protective Systems
Methods used to protect personnel from sidewall cave-in, materials that could fall or roll
into the excavation, or collapse of adjacent structures. Protective systems include sloping,
benching, and shoring.
Shoring
Hydraulic, timber, or mechanical systems that support the sides of an excavation, which is
designed to prevent sidewall cave-ins.
Sloping
A method of protecting personnel from sidewall cave-in by forming sides of an excavation
that are inclined away from the excavation. The safe angle of slope required varies with
different types of soil, exposure to the elements, and superimposed loads.
Soil Classification
A method of categorizing soil and rock deposits as Types A, B, and C in decreasing order of
stability. Soil type is determined by an analysis of the soil's properties and how it performs
under exposure to the elements and superimposed loads. If the type of soil cannot be
accurately determined, then Type C soil is to be assumed for design of protective systems.
Stable Rock
Natural solid mineral matter that can be excavated with vertical sides and remain intact
while exposed.
Trench
A trench is defined as a narrow underground excavation that is deeper than it is wide, and is
no wider than 15 feet (4.5 meters).
Trench Shield
A structure that protects personnel inside it by withstanding the forces imposed by sidewall
cave-in on two (2) sides.
Type A Soil
Cohesive soils with an unconfined compressive strength of 1.5 ton per square foot (tsf) (144
kPa) or greater are classified as Type A. Examples of cohesive soils are: clay, silty clay, sandy
clay, clay loam, and, in some cases, silty clay loam and sandy clay loam. Cemented soils,
such as marl, are also considered Type A. However, no soil is Type A if one or more of the
following conditions are true:
• The soil is fissured.
• The soil is subject to vibration from heavy traffic, pile driving, or similar effects.
• The soil has been previously disturbed.
• The soil is part of a sloped, layered system where the layers dip into the excavation on a
slope of four horizontal to one vertical (4H:1V) or greater.
• The material is subject to other factors that would require it to be classified as a less
stable material.
Type B Soil
Soils classified as Type B are:
• Cohesive soils with an unconfined compressive strength greater than 0.5 tsf (48 kPa)
but less than 1.5 tsf (144 kPa).
• Granular cohesionless soils including angular gravel (similar to crushed rock), silt, silt
loam, sandy loam, and, in some cases, silty clay loam and sandy loam clay.
• Soil that meets the unconfined compressive strength or cementation requirements
for Type A - but is fissured or subject to vibration.
• Dry rock that is not stable.
• Material that is part of a sloped, layered system where the layers dip into the
excavation on a slope less steep than four horizontal to one vertical (4H:1V) but only if
the material would otherwise be classified as Type B.
Type C Soil
Soils classified as Type C are:
• Cohesive soils with an unconfined compressive strength of 0.5 tsf (48 kPa) or less.
• Previously disturbed soil (e.g., fill) is to be considered as Type C soil.
• Granular soils, including gravel, sweet sand, desert sand, and loamy sand.
• Submerged soil or soil from which water is freely seeping.
• Submerged rock that is not stable.
• Material in a sloped layered system where the layers dip into the excavation or a slope
of four horizontal to one vertical (4H:1V) or greater.
The Civil Engineer / Maintenance Engineer will carry out the following activities:
• prior to any excavation being dug, carry out a prior survey of the area to establish the
presence of any underground utilities;
• evaluate the effects of the excavation on buildings or constructions nearby;
• establish ground conditions, e.g. the type of ground involved, clay, sand etc. and
compaction qualities and water table;
• identify the presence of any overhead-underground lines and other obstructions;
• identify the need for any permits that are required in the area and arrange for them;
• brief the personnel carrying out the work of any adjacent operations that may impact
on the work, the presence of overhead and underground utilities;
• identifying all underground facilities;
• In case digging will uncover material that have the potential to be hazardous to
health, excavation will be immediately stopped up to the nature of material will be
clarified and required safety measures applied.
Supervisor
Supervisor will be responsible for the following:
• briefing personnel doing the work on the safe working practices required;
• application of any work permits that are provided;
• provision of equipment that is capable of carrying out the work safely, has been
maintained and is certified for use on the project;
• provision of adequate barriers, flashing lights and signs for the work;
• programme the work to ensure that any trenches that go across roads are done so in a
manner that maintains access;
• notify the engineer of any unmarked utilities found.
HSE Team
Procedure
7
All benched excavations made in Type A soil that are 6 m (20 ft) or less in depth are to
have a
maximum allowable slope of 3/4 horizontal to 1 vertical and maximum bench dimensions
as
follows
SIMPLE BENCH
MULTIPLE BENCH
• All excavations made in Type A soil that are 6 m (20 ft) or less in depth, which have
vertically sided lower portions that are supported or shielded, are to have a maximum
allowable slope of 3/4 to 1. The support or shield system must extend at least 0.45 m (18
in) above the top of the vertical side.
Excavation in Type “B” Soil
• All simple slope excavations made in Type B soil that are 6 m (20 ft) or less in depth
are to have a slope of not greater than 1 horizontal to 1 vertical
SIMPLE SLOPE
• All benched excavations made in Type B soil that are 6 m (20 ft) or less in depth are to
have a
maximum allowable slope of 1 horizontal to 1 vertical and maximum bench
dimensions as
shown below. Benched excavations that are unsupported or unshielded are permitted
only in cohesive soils.
SIMPLE BENCH
MULTIPLE BENCH
• All excavations made in Type B soil that are 6 m (20 ft) or less in depth that have
vertically
sided lower portions are to be shielded or supported to a height at least 0.45 m (18 in)
above
the top of the vertical side. All such excavations are to have a maximum allowable
slope of
1:1.
Excavation in Type “C” Soil
• All simple slope excavations made in Type C soil that are 6 m (20 ft) or less in depth
are to
have a slope of not greater than 1-1/2 horizontal to 1 vertical.
Using excavation Machinery
The use of excavating machinery (such as backhoe, hack hammer, loader etc) near
above / underground services will require Excavation Permit. The following precautions are
to be taken while using mechanical means of excavation:
• Extreme care shall be taken to prevent any damage to above / underground services or
power
lines while using mechanical excavators.
• A mechanical excavator shall not be used until all underground obstructions have
been
uncovered through manual excavation.
• The machinery operator shall take extra care and follow banksman instruction while
reversing
or turning the excavator to prevent any accidental strike to the workers or
equipment at
location.
• The bucket must always be lowered to the ground if the loader or backhoe is not in operation.
• The machinery operator shall take necessary care to prevent exhaust gases
entering the
nearby trench or pit in case personnel are working inside it.
Dewatering
• Employees are not to work in excavations where there is pooled water, or in
excavations in
which water is accumulating, unless adequate precautions have been taken to
protect
employees. The necessary precautions vary with each situation, but are to include
water
removal to control the level of accumulating water (e.g., by pumping) and may also
include special support or shield systems to protect from cave-ins.
• If water is controlled or prevented from accumulating by the use of water removal equipment,
the water removal equipment and operations needs to be monitored.
• If excavation work interrupts the natural drainage of surface water (such as streams),
diversion ditches, dikes, or other suitable means need to be used to prevent surface
water
from entering the excavation and to provide adequate drainage of the area adjacent
to the
excavation.
• Excavations that have been subject to runoff (e.g., from a rain storm) need to be inspected
before use.
5.8 Completion
• Adequate fencing, barriers and warning notices are to be provided around any excavated area
to alert and prevent accidental fall into it. Posting flaggers and / or watchman will be
required
if the trench is in a heavy traffic area. It is also recommended to illuminate the
excavated area
in the night and provide flashing hazard light. Any person entering the barricaded
area must
follow safety procedures to eliminate fall from height hazard in line with
requirements of
“Working at Height Procedure”. Where equipment, workers or public are
required or
permitted to cross over a trench; then it is essential to provide a close - planked
bridge or
walkway with standard guard rail.
• Stairways, ladders, ramps and/or other safe means of egress are to be located in excavations
that are 1.2 m (4 ft) or more in depth so as to require no more than 7.5 m (25 ft) of
lateral
travel distance for personnel (i.e., ladders need to be spaced at least every 15 m [50 ft]
along
a trench).
• Ladders are to rest on the bottom of the excavation and extend at least 1 m (3 ft) above the
top landing point
• Gas tests are to be performed when there is reason to suspect oxygen deficiency or the
presence of a flammable/toxic atmosphere in an excavation. Where necessary,
mechanical ventilation or other appropriate precautions are to be taken before
personnel entry
• Walkways a minimum of 600 mm wide will be placed across trenches where access is
required and shall be fitted with handrails and will be separated from roadways
• When the access to the excavation is made by a stairway in soil, there will be enough
effort and support table to prevent erosion and landslides
• Uncovered services and utilities will be adequately supported by propping/slinging or any
other method identified as appropriate
5.10 Inspections
Excavations greater than 300 mm shall be inspected on daily basis by a competent person
using the Daily Excavation Checklist
• Before the start of the work
• After a rainfall or any water seeps in.
5.11 Training
All employees who are to be engaged in excavation works shall be instructed by a
competent person on safe methods of working. Instruction will cover as a minimum the
following subjects:
• Requirements for excavation permit.
• Shoring, Benching, Sloping
• Removal of spoil.
• Exclusion zones for machines & equipment alongside excavations.
• Unstable soil.
• Leaching of water through excavation walls.
• Access and egress
• Placement of Material into excavation by cranes or other machinery.
5.12 Records
SL.NO Description Format No
1 Excavation Checklist LTHE/HSE/PR03/F01
2 Gas Test Record LTHE/ HSE/PR03/F02