Professional Documents
Culture Documents
BY
LANNEKE TRISTANTO
INSTITURE OF ROAD ENGINEERING
..).._....,
~• r4 .r-")~ T)1'1'l'~
_,_$
)I 4 ~ r..,~.r
--·
"- ••"\. • .Ld. k . .!....JJ.. .'1.
·~-
-.' ~\
J-~.J ••••••
··, r•
'>...L
f'"'t "' Aj.:·;. ·r-. ~t'
r ' Arr. ..j '- J._.
~u· ·r.'. jf.J
~ I.
T lJJ,' . '_i
,j
v
• ~
THE USE OF SOFTWARE FOR STRUCTURAL ANALYSIS
OF PRESTRESSED CONCRETE BRIDGES
B A U I iL\ ~ ~ FU
BY:
LAA'NEKE TRIST AL'l"TO
INSTITUTE OF ROAD ENGINEERING
The aspect to upgrade design knowledge and skill through software application training
has influenced the growth and the use of micro computers. Research studies need to be
executed by involvement and intensive use of computers while the users have to take care
for not becoming a computer addict. Some designers could become dazzled by the display
of the computer and could forget that they are engineers. Equilibrium between civil
engineering and computers should be enhanced to expect a good understanding and
interpretation of the computer output analysis. The criterion of good results in science is
'good means close to the true solution'. Exact solutions can not be achieved by any
method of calculation.
The main span range for segmental bridge types using balanced cantilever construction
method is 60 - 150m with a maximum of 200m for which heavy equipment is required
during construction. The segments can be prefabricated or cast in place by using traveling
formwork. The connection between segments is made by shear keys and epoxy resin for
prefab segments or by reinforcing steel dowels in case of segments that are cast in place.
Stability during construction is achieved by using temporary formwork near the pier and
by post tensioned tendons that are anchored in the top slab along the cantilever span.
Crossing of longitudinal cables in narrow webs should be avoided. The segments near the
pier need a thicker bottom slab to countermeasure the high compressive stresses that are
caused by the maximum negative moment at the pier. After closure of the center cantilever
spans, the static system \will change from statically determinate girder to statically
indeterminate girder, causing positive moments at center of main span and in side spans.
1.
In the positive moment area, tendons are required in the bottom slab or webs of the box
girder to counteract the positive moment. Tendon anchoring into the slab or web is usually
in 25 degree slope to minimize the required thickness of the anchor block.
At the pier and abutment segments, a diaphragm is required to strengthen the webs of the
box girder in transferring the high shear force to the bearings. The diaphragm is
sufficiently reinforced and sometimes strengthened by vertical and transverse tendons that
are calculated against the shear in the webs of the box. The diaphragm is frequently a
hollow section to allow equipment and labour passage during construction.
r .. , , ' ' ttpJ ' ....•. ·, ..• , .. ' tq:tL1 ' . . . . ':I
y
X
e 8
D
The width of the top slab W is selected according to the width and number of traffic lanes
and when necessary a multi box section is used. Structural height D is usually among 1/18
- 1/20 to main span 1 . In general the structural height is variable that is 1/18 - 1/20 at pier
location and 1/40 - 1/50 at center of main span and at abutment location. In case of
vertical webs, the width ofthe bottom slab B is determined by the width of the top slab W.
Inclined webs will not offer problems in case of constant structural height. But in case of
variable structural height some re-assembling and adjustment of formwork are required as
the width of the bottom slab changes. The reduction in the bottom slab width is beneficial
to reduce the segment weight that will reduce the force and moment in the girder. The
segment length L depends on the required efficiency by minimizing the number of
segments and considering the available equipment capacity. The web axis spacing s is
determined to fulfill the criteria of normal beam theory for moments in longitudinal
direction. This requires a structural height of more or equal to 1/30 L In addition, the ratio
between the width ofthe top slab W to the number of webs may not be more than 7.5%
of the span length.
2.
The cantilever slab width C is approximately 114 of the total width W. In case of more
than two webs, C is selected to achieve equilibrium of transverse moments in cantilever
and center of box.
The slab, web and voute thickness are determined by the requirements of construction and
fabrication of segments. The slab thickness of 17.5 - 25 em accommodates four layers of
normal reinforcement in transverse and longitudinal directions, transverse and longitudinal
tendons, and a concrete cover of 5 em at top and 2.5 em at bottom. The voute dimension
is determined by the transverse moment and space required by anchorage of longitudinal
tendons. In general a concrete thickness of 3 5 em is sufficient to place two longitudinal
tendon layers and anchorages. As the top slab is the heaviest part of the box, it is
recommended to minimize top slab thickness and voute.
The bottom slab thickness in positive moment region only adds to the section properties
and ,is minimal 18 em to carry own weight, placement of normal reinforcement and
concrete cover. Along the negative moment region near the piers, the bottom slab
thickness is governed by the high compressive stresses. Its thickness has to be increased
along a short as possible distance to minimize complication in fabrication of the segments.
The voute dimension in the bottom slab has two functions, that are transfer of force
change between bottom slab and webs, and transfer of flexural moments in transverse
direction between bottom slab and webs.
3.
3. ANALYSIS IN LONGITIJDINAL DIRECTION BY I'fL~IERlCAL LX...\...~LE
The compressive stress ~b in bottom fiber of the pier segments in particular, is calculated
as follows:
/a,= ME + P _ P(e)
zb A zb
where Zb =section modulus of bottom fiber (mm3)
By using this first method, the cantilever construction weight is carried by stop tendons
that are anchored at the surface of each pair of segments. At closure of the main span,
continuous tendons are required to carry the total dead and live load as the bridge changes
from simple supported system to continuous span.
The required tensioning for total dead and live load can be placed as stop tendons during
the cantilever construction. In this case, the compressive stress in top fiber and tensile
stress in bottom fiber are within allowable limits during construction - Figure 3 - where
tensile stress at bottom fiber is 0. 7 :MPa and compressive stress at top fiber is 10.4 :MPa
for concrete grade ~, = 30 Mpa. This method can be applied for relatively small spans
where the number of tendons is limited. For larger spans the first mentioned method is
recommended.
The dead and live end configurations of anchorages are chosen to restrict loss of
prestressing by slippage ~t live end, in particular for short tendons. The tendon profile is
chosen to minimize losses due to friction and wobble- Figure 4 and 5.
At finishing of the cantilever construction, the tensile stress at bottom fiber decrease to 4.5
MPa and the top fibre compressive stress is 105 :MPa at 82 da.J'S- Figure 6.
4.
.l' •• ' ' ! '
-
tl]JJJ ' ' '
..A.
I ! ' " I I I I ' ' ' t1pJ
-
I ' ' ' ! I '1.
-
~.88 days
Seale: 1---i = 171.29
Date:
89/ltVJ&
"! ••
....... ! ' ' ' '
-
t:t1ll
....... T ' ' ' ' ! ' " I ' ' '
-
' ' t ttll1
....... T ' ' ' I ' ':I
-
Figure 3i. Moment and stress diagram due to selfweight ofbox girder during cantilever
construction - the construction time for left and right cantilevers is 79 days
4a_
l~~t.t£S~'"i~Yi! :OUt.:'i:ifa'~arFtJ :Ot,feiC£i[c~ ~~'~i-'z~:~·1 :~~·:c;£it :serur;gs.":
-~~ -.:; ~~.,.~~-; ·:
.+
r- ......
,...
r--
...,....( r--1-......
A rr-,.__
~ v
y ~ )V
,..v ' ' ~,..-v
/
v
' ...... ~.--'-'"
Figure 3ii. Moment and stress diagram due to selfweight ofbox girder after cantilever
construction and closure of main span at 85 days
4b.
'I Iff'! f lUJj:f f! I I I!,. I I I I~ I I I l : t
5 22
-Y
18.481 18.481
Tendon group 8 (2 tendons )
span
cara kantilcuer bcbas
5.
_--~·- --- ';.-. "":.~-
2 24
,·~lr.<,~·;.:d .. z
.•. o~<;·~=:i;?T:
~-----
rmuwrwn11J
-Y'
~:::: xliTlllT!T[l--!TT!TrJ_[_] z
Force in kN
JG27
2822
2617
2455
~--------------------------------------~z
I• 18.524 •I
Tendon group 10 (2 tendons )
span 38+68+38tl Date:
cara nta l kant i lcucr be bas 88/83/'36
6.
3.2. Final Moments
After the static system is converted with dead and live load on the continuous bridge, the
negative moment at the pier increases while positive moments at center of main span and
side spans berome significant. The tensile stress at bottom fiber becomes 3.3 MPa -
Figure 7 - which is modified by trial and error inside the program.
With the addition of prestressing at bottom fiber of the side spans - Figure 8 - and center
span - Figure 9 and 10 - a stress diagram is obtained at 85 days. Stresses at minimum
load or self weight fulfill - Figure 11 - and stresses at maximum dead and live load after
opening ofthe bridge to traffic at 115 days fulfill allowable stress- Figure 12.
After the bridge is in service at 115 days, the tensile stress becomes 6.4 MPa with a
compressive stress of 119 MPa. The influence of creep and shrinkage in long term (up to
9000 days) reduce the tensile stress to 3.2 Mpa and increase the compressive stress to 123
MPa - Figure 13. The program does the checking of each construction stage. In this way
the stresses are controlled during the whole construction progress.
The final moments due to the total loads and prestressing - Figure 14 - v.-ith normal forces
- Figure 15 - and shear forces - Figure 16 - can be calculated in short period or when the
bridge is opened to traffic. The long term influence of creep and shrinkage is limited for
relatively short spans up to 1OOm.
The deflection and camber are controlled by adjusting the formwork during the
construction sequence. The designer determines the day at which the bridge alignment is
expected to be horizontal - for example 115 days in this case. The program calculates the
required camber - Figure 17. After 9000 days this camber will cause a 3cm camber at
center of span - Figure 18 - while at 10000 days the bridge is theoretically horizontal -
regardless of any method of deflection and camber control. The camber of the main span
needs to be controlled (2.3 em) - Figure 17a - while the camber for side spans can be
neglected or made horizontal.
The program allows for a curved bridge alignment where the segments and tendon profiles
will follow this curve. The final alignment is in this case not a horizontal line, and is
obtained by adding the difference between the curve and the horizontal axis to the
previous correction.
A differential settlement of 2.5 em will not influence the stress increase - Figure 19a. The
calculation has to be repeated and additional reinforcement is required when the
differential settlement becomes 5 em - Figure 19b. The differential settlement can increase
during a certain period - 5 em at 115 days and 10 em at 9000 days - Figure 20 - where
creep and shrinkage will distribute and reduce the stresses.
7.
span 38+6B•3811
cara seg~~enta 1 kant i leuer be bas
l lk1te:
17/Si/96
Figure 7i. Moments and stresses caused by total dead weight including wearing surface
and side curbs at 115 days (opening of the bridge) where the influence of tendons is
excluded. This diagram is used to calculate the required number of tendons due to final
dead loads
7a.
1' '''I. '::tt:I11' ~!.'I' I I. '!. t::t1UJ:T 'T '.I '1.
f
span 38+6B+3811
cara Seq~~Cnta I kant i leuer be bas 1 Date:
89/8i.r.:J6
- -*- ...._ -
Figure 7ii. Moments and stresses caused by total dead weight and live load at 115 days
(opening of the bridge) where the influence of tendons is excluded. This diagram is used to
calculate the required number of tendons due to final dead and live loads
7b.
1.1 1 1 , , 1 ~ u::n:r , , 1 I •• 1 , I • , • r ~ t t:nt , 1 , 1• 1 1.1
- ...... ...... -
sendi rol
+ tegangan tarik serat bawah
- tegangan tekan
Catatan:
'-'~J~··
·, -~~~te'\~·- i · dibuat tie (0-1 0000 hari) antara garis sistem dan perletakan
c '"R~~ffile -:~:,:
___ ·'·. ·---. -:
· dengan EA 1000.000 mN dan EI 1000.000 mNm2 ,
/
._.. •. ..:.
'\
prategang pada serat bawah
::::.<:-
f~j~l~~--~-pa-n---=38"""..{,8~-=.38.=-l-ka_nt_il-c-ue_r_be_ba_s_ _ _ _ _ _ _ _ _r.~;:--8-;-~-::--6-----l
Figure 8. Tendons to counteract the positive moments in side spans
8
Catatan:
tendon tambahan mungk:in diperlukan
dalam lantai atas tengah bentang untuk
menjamin kontinuitas pada kabel momen negatif
segmen penutup
~
span 38+68+38.
caN. nt.al kanti lcuer bcbas
Figure 9. Tendons to counteract positive moments in main span, stressed after closure of
main span
~; ,'~k~;,~;-;=t~: ~ 19 32
z
~l~;;i:·
~....-- ......... ---..__ ..____
I--
-Y •
,.O<J<l
O.O<J<l
xl--rrrrr-rTTTTT1
. ,
z
Force i
-liiiiiiiii;;;d2 7 , 2
,~----------------------------------------~z
19.070 19.070
I• I•:
Tendon group 22 (2 tendons )
sp4n 38+68+3811 Date:
t.a 1 kant i lcuer bcb4s 88/83/96
_ro 0 • =t r T! t:tn1 T T ' ' 0 ' ' "......,._%-!=tttt:J:1:!1 ! t ' ' • 'l_
- ...... ...... -
\
Co.putcd Stresses in tv•..Z at: 115.88 days
y +4 z
tap Hax: 8.&46 nin: -11.918 Scale: 1------1;: 3.978
Botto. Kax: 8.637 nin: -11.372
Spilll 38+68+3811
~ .:nta l kant i leuer be bas
10.
_ro 0 ' ' ! !! t::tp::J t • I • 0 ! I I ' •••• T t:t:ttJ:! T • ! ·~
- ..A.. -
Figure 13. The influence of creep and shrinkage at effective prestressing, dead load and
,maximum live load, at 9000 days v.ith average 80% humidity at 25 degree Celsius
115.88 days
Seale: 1----i = 31875
Date:
BS/83/96
11
.r· .... , I ~ , ::t:qtu • , , I , •••• I , •• tr:qtu , , , I I I~ .
~~: :S~!!i:i9~~":+~ .
·,: .:~!~~~,.0~~~,,
+
~ y
~llllllliJIIIImriilW
\
to.putcd ttort~al Farces in lett at: 115.88 days
YLZ
nax: 8.487 ltin: -51535 Scale: ~ = 17178
12.
'-==:='\...~.
i~~~ _tttl ''! Ltl}!!T ! T ' ' !! P' • • 'r tt tt11J T T tt • • '1_
~~~4
- ..... -
11: -~:
0 ' ' ' '' '' .. ~-
13.
I' •.,,, '::tttlJ ~.,,,,,,,,, .. 1 '::t:tiJJ:~,,,., ·~
- ...... ...... -
1 T
a)
b)
Figure 19. Pier 1 settles 2.5 em (a) where stresses fulfill, pier 2 settles 5 em where stresses
are exceeded (b)
y'f' z
to.pu~ Stresses in IV•.Z at: ~~99.95 days 4
Top ~: 8.&16 11in: -18.&38 Scale: 1----1 = 1.719
Botto. ~: 1.121 11in: -11.Zi8
Figure 20. Pier 2 settles 5-1 0 em during 115-9000 days where creep reduces the
settlement and stresses in the box girder - compare to 19(b)
14
3.5. Shear Analysis
Tne tendons in the top slab of the box girder produce a stress concentration in the
negative moment region. This effect will counteract the shear influence of dead and live
loads. The shear transfer has significant influence in a relatively short distance near the
pier. A nominal residual compressive stress in the pier segments for maximum negative
moment condition can reduce the required shear reinforcement.
The shear stress in normal concrete is equal to the principal stress. In prestressed concrete
, the shear capacity and required stirrup reinforcements are based on the principal tensile
stress fp as follows :
where:
fx = total longitudinal stress, tension is positive and compression is negative
~ = shear stress
The maximum principal tensile stress has to be checked at several sections along the girder
height as the maximum value is not always at the neutral axis.
The pier and abutment segments need to be reinforced as the shear is transferred from
diaphragms to the bearing reactions - Figure 21.
In this example, the residual compressive stress in the girder section is 0. 7 - 5 Mpa. The
principal stress is within allowable tensile limit + 0.92 .MPa for diaphragms and span
segments - Table 1. The required stirrup reinforcement consists of grade BJ30 diam.16mm
at 20 @ 30 em spacing in both girder webs - Figure 21. The shear analysis has to be
assisted by some hand calculation for the critical sections near the supporting points. The
shear stress is calculated by using the following formula :
t = (QS)I(bl)
where:
Q= shear force - Figure 15
S= static moment against the sectional axis
b=width of both webs of the box girder
I = inertia moment against neutral axis
In this example, the shear is 1analyzed against the neutral axis for the diaphragms and the
axis below the thickened webs for the span segments - Figure 21.
15.
-. ... ,
ll
___
1 o:are~l !rutile..--
lert.... len: lJ lert... Plpt: lJ
I~
span 38+&8+3811
cara q~~enta 1 kant i lcuer bcbas
IDate:
12AIV9&
span 38+&8+3811
cara seq~~ental kantilcuer bcbas !Date:
12.1'81/'36
16.
Table 1. Principle tensile stresses of the prestressed box girder cross section
If there is no provision made for residual compressive stress, the required number of
tendons is reduced but the amount of shear reinforcement \Viii increase. The stresses of the
girder cross section due to differential settlement of the foundation are checked through
this program. The number of tendons is adjusted according to the concrete stress
limitation and the expected settlement of the bridge foundations.
Additional tendons may be required at center of the main span - Figure 9 - to obtain
continuity of the negative moment tendon profile in enhancing the ultimate moment
capacity along the whole bridge span.
17.
11!-"tSses in tv•.Z
8.8
·15'·.35
'1.35 '1.00 ,.~ 1.30 i f.cc
I Uc Ill 2.35
.~
lil
T
I
........ I y
~~~~~~~~--~~~~~1!~-------
j_
i
I
I
I
I
;
: 6 ...q5
! I
oT 1 o.1o ~n o. 40
-,
T T
:1. 2>5
·18.8
EP = -8.2358E-83 H = 8.8888E•88 kH
KX = 8.9161E-83 1/M HX = 8.1541E+86 kHH
MY = -8.3237E-19 1/M HY = 8.8888E•88 kHH
t!ure 22. Ultimate moment capacity of girder segment at the pier
1T
" IV
18.
3.7. Thermal Load Analysis
The influence of thermal load on the longitudinal stresses is analyzed due to the
temperature gradient profile along the girder height. In case of higher temperature at top
fiber compared to bottom fiber, the top of the girder expands while the bottom fiber
becomes shorter. This causes secondary moments and shear forces in the structure. A
difference of 10 degree Celsius between top and bottom of the girder increases the tensile
stress in the bottom slab and the· compressive stress in the top slab - figure 23. The
combined thermal, dead and live load stresses may exceed 25-40 % of the normal stress.
The temperature difference within the girder is in general minimized by the asphalt
isolating layer. It is also recommended to place ventilation holes in the box section to
remove entrapped water and provide fresh air.
In this example, the bridge width is 9.3m (2 lanes @ 3.5m + 2 sidewalks @ 1m) where
each cantilever span consists of 10 segments @ 3m length. In this case, minimal 10
tendons are required to stress each segment to the previous segment - Table 2. This
tendon configuration causes greater tensile and compressive stresses at a concrete age of
15 days - Figure 3. A better stress configuration could be obtained when the number of
tendons is increased and some tendons are stressed after the cantilever construction is
finished.
Thickening of the bottom slab of the pier segments is necessary to maintain the allowable
compressive stress. The bottom slab thickness of the left pier segments (nr 9-10, 14-16)
and right pier segments (nr 33-35, 38-40) are 40cm at the pier location and gradually
decrease to 20cm in the dlrection of the span.
With the input data of the cable profile, the program calculates the tendon elongation and
prestress losses in short period until infinite 9000 days - Table 3 - which is the output
result. Any change in construction time, tendon type and system, or cable profile can be
programmed to perform a re-analysis.
19.
Table 2. Concreting and stressing stages of segments as input data
i\
/
:~ 1-12 ; 1>- ~·) 25-3· ;f 37-48
<length- elevation of
tendon to side to
horizontal - vertical
7 .. · 0.22
7 .· ·· - ··
0.22
.
•.... ...
... .0.22
. ..... . .....
.. . .......
49 <......
·-···
- . 0.10 ·• .
. .
< 55 < . ..
. . . 0.10 >
•:,;.:,··············· ) 61 .5 ~ 0.10
>35,)8
. . .
. •.
. ~ ........
.. .. . ~ ... FT
• ...11 >•
.. ......•
-
... 0 .22
. .
..... . . ..
34,3.9: •· . •·······. 44/ 47F 47/ ... ... •··• 12 < IF' . .0.22 .
......... . 33,40 ···· ••• ••• •.•. 13 ..
\ 4~ S 51 ~5L FT · 0.22 .
32;41 ···· · > 52 .:.55 :.55 .... • :.··• 14 TF • •.. 0.22
·. .. 31,42 56 > 59 < 59 ·•· ·: • 15 > TT . ...•. 0.10
. ·. ·.:· 30,4) · ··· ·· ·. ~q · ~ 63 00 63 •••. . :• ·.• 16 . < TT • ··• 0.10
29 44 . . . . .
' . · .:
• 64 ;_ "67 ..._ 67 ... •·· . •·• ·• .17 -
. :·.· · : · :·:· .. ·:·: · · .. : · : · :·:-· - :· · · : - :· ·:
TT
... . ..
• • ...
0.10
28/ 45 ••••• ••· • ••• ·•·•• 6$ .. 7} ~ 11 .••••• ·• >. .• 18 .. - 1' T • .•.. 0.10
27 ' .:46 . ····: ••·• •• •·. 72
.. : :
:._ 75.:/ - 75 •· ..
...
19 · - TT .· · .
.:.:.. . . .. . . : . .. .. ... .
0.10
26, 47 . 76 ;_ 79 > 79 ·• .· 20 - · . F T •· 0.10
20.
pier 2 : continued
26,47 76 - 79 - 79 20 - F T 61.5 0.10
The design load is 100% Bina Marga -1992, that consists of a uniform distributed load 25
kL'{/m/lane and a knife load included impact of 177.5 kN/lane, applied in system line nr1 of
the program. Additional dead load from side curbs, railings and asphalt surface is -28
kL'{/m. Truck train combination is available in the program. In this example it is assumed
that the total dead and live 1oad is at 115 days in service.
Segmental bridge construction using the balanced cantilever method is not always
appropriate for provinces where prestressed concrete technique is not yet available. For
the 60m span range there are 3 economic bridge types to be considered in practice -
Figure 24 - that are competing to each other.
21.
29 500 60 {)()() :9 500'
30CWJJ 60000 30000 ,
~
I ~
I
\ __ I ;
28000 60000
sistem segmental 2!000
----~
cara kantilever ~
I
4. CONCLUSIONS
This report discusses a new design method by using the software program Bridges 2D,
where the influence of construction time and concrete properties in long term period are
considered and analyzed. The program is especially designed for prestressed concrete
bridging using internal and external tendons. Reinforced concrete design and composite
girder design are included in this program. Cable structures like cable-stay bridging and
other bridge types with temporary cables- Figure 25 - is also one of the capabilities of
program Bridges 2D.
;IIJg .
--r.r- ~
c.nrw;
s.:... Slob
of
~~ -~
(ufing of
~- (#:sting of
Bollofll Sbb ~ Top Sill>
The other modules are I{_eat 2.5 D and Buildings 2D. Heat is a program to monitor the
heat generation in mass concrete construction with and without the application of cooling
pipes inside the concrete. With this Heat program, the removal of isolation layers in
practice is monitored and cracks due to thermal shock can be prevented.
22.
Buildings is a finite element program for shear walls in buildings or bridge piers, and
concrete slabs for decks or pavement.
It is a feature of these programs that they are finite element based, but the users need no
theoretical finite element background to work with these programs.
5. REFERENCES
1. Bridges 2D, Heat 2.5D, Buildings 2D, Intron Sme Software, P.E. Roelfstra, The
Netherlands, 1995
2. Jembatan Gelagar Boks Beton Pratekan Sistem Segmen Pracetak, terjemahan Code of
Practice, Prestressed Concrete Institute, DPMTJ, 1980
3. The Penang Bridge, Tan Sri Datuk Profir. Chin Fung Kee, Malaysian Highway
Authority, 1988
BIO- DATA
The author graduated from Parahyangan University in 1969. She worked in the bridge
design office of the Directorate of Planning during 1970 - 1979. She has joined the
Institute of Road Engineering since 1979 as researcher in bridge engineering. She is a
member of the International Association of Bridge and Structural Engineering, the Road
Development Association of Indonesia, and the Road Engineering Association of Asia and
Australasia.
23.
D A L J l IL \ N G !.'
U
-
/• .
..
..
~.
h •
-
\
.,
.·