Professional Documents
Culture Documents
OMMP19-3 - Sessions 03&04
OMMP19-3 - Sessions 03&04
◼ Teaching
◼ Session 03 to Session 04
◼ Evaluation
◼ Quiz 01 – 15 marks (45 minutes)
◼ Date → On March 14, 2020
◼ Quiz 02 – 15 marks (45 minutes)
◼ Date → After April 12, 2020
◼ Part of End-term – 5 Marks
◼ Product A
◼ Profit = Rs. 80/unit
◼ Demand = 100/week
◼ Production = 0.4 hours/unit
◼ Product B
◼ Profit = Rs. 50/unit
◼ Demand = 200/week
◼ Production = 0.2 hours/unit
C
80
Supplier Customer
A B D E
80 90 60 75
C
80
Supplier Customer
A B D E
80 90 60 75
Constraint
(Drum)
Dipankar Bose - XLRI
Drum-Buffer-Rope (DBR)
C
80
60
Supplier Customer
A B D E
80 90 60 75
60 60 60
Constraint
(Drum)
Dipankar Bose - XLRI
Drum-Buffer-Rope (DBR)
C
80
60
Constraint Buffer
Supplier Customer
A B D E
80 90 60 75
60 60 60
Constraint
(Drum)
Dipankar Bose - XLRI
Drum-Buffer-Rope (DBR)
C
80
60
Constraint Buffer Shipping Buffer
Supplier Customer
A B D E
80 90 60 75
60 60 60
Constraint
(Drum)
Dipankar Bose - XLRI
Drum-Buffer-Rope (DBR)
C
80
60
RM Buffer Constraint Buffer Shipping Buffer
Supplier Customer
A B D E
80 90 60 75
60 60 60
Constraint
(Drum)
Dipankar Bose - XLRI
Drum-Buffer-Rope (DBR)
C
80
60
RM Buffer Constraint Buffer Shipping Buffer
Supplier Customer
A B D E
80 90 60 75
60 60 60
Rope
Constraint
(Drum)
Dipankar Bose - XLRI
Drum-Buffer-Rope (DBR)
Assembly Buffer
C
80
60
RM Buffer Constraint Buffer Shipping Buffer
Supplier Customer
A B D E
80 90 60 75
60 60 60
Rope
Constraint
(Drum)
Dipankar Bose - XLRI
Drum-Buffer-Rope (DBR)
Assembly Buffer
C
80
60
RM Buffer Constraint Buffer Shipping Buffer
Supplier Customer
A B D E
80 90 60 75
60 60 60
Rope
Constraint
(Drum)
Dipankar Bose - XLRI
Capacity Constrained Resource (CCR)
Assembly Buffer
C
80
60
RM Buffer Constraint Buffer Shipping Buffer
Supplier Customer
A B D E
80 90 60 75
60 60 60
Rope
Constraint
(Drum)
CCR Dipankar Bose - XLRI
Capacity Constrained Resource (CCR)
Assembly Buffer
C
80
60
RM Buffer Constraint Buffer Shipping Buffer
Supplier Customer
A B D E 55
80 90 60 75
60 60 60
Changeover Time
=10 minutes
Rope
Constraint
Rope
(Drum)
CCR Dipankar Bose - XLRI
Theory of Constraints – Some
Principles
◼ Balance flow, not capacity
◼ An hour lost at a bottleneck is an hour lost forever
◼ An hour saved at a non-bottleneck has no value
◼ Bottlenecks govern both throughput and inventory in the
system
◼ Set the schedule by examining capacity and priority
simultaneously and sequentially
◼ The level of utilization of a non-bottleneck is determined
not by its own potential
◼ But by some other constraint in the system
◼ Utilization (for entire system) and activation (doing
independently) of a resource are not synonymous
Dipankar Bose - XLRI
Example 1
Product A Product B Product C
Price = 50 Price = 75 Price = 60
Worker 2
RM 20 minutes/part RM
=5 =5
RM
= 10
◼ Max prod: Min prod = 10:1; Weekly 5 days3 shifts
◼ Weekly operating expenses = 3000
◼ Maximize Sales revenue/Gross profit per unit/ Total gross
profit Dipankar Bose - XLRI
Topic: Project Management
◼ Project
◼ A unique set of activities meant to produce a defined
outcome within an established time frame using
specific allocation of resources.
◼ A project is a temporary endeavor undertaken to
provide a unique product or service or result – PMBOK
Guide
◼ Project management
◼ Project management is a process of developing
substantive, systematic data about each parameter in
order to maximize the effectiveness of tradeoff decision.
◼ Parameters → Time/ Resource/ Result
Dipankar Bose - XLRI
Project Management – Steps
◼ Input → WBS
◼ Identify all the dependencies
◼ Finish – Start (FS)/ Start – Start (SS)
◼ If required → Add new tasks or identify redundant tasks
◼ Go back to WBS step to include/exclude task
◼ Create Network diagram
◼ Assign duration for each task
◼ May be expressed with range
◼ Critically examine if time requirement is long or can
not be identified
◼ Identify ‘Milestones’
◼ Create “Gantt Chart”
Dipankar Bose - XLRI
Network Diagramming Method –
Example
Activity Duration Predecessor
A 2 --
B 2 --
C 1 --
D 4 A
E 5 B
F 8 B
G 3 C
H 1 D
I 4 E
J 5 F, G
K 3 H, I
Duration, Resource
Predecessor Successor
2 5
D, 4
H, 1
A, 2
I, 4 8 9
1 B, 2 3 E, 5 6 K, 3
F, 8
C, 1
J, 5
4 G, 3 7
2 5
D, 4
2 6
H, 1
A, 2
I, 4 8 9
1 B, 2 3 E, 5 6 K, 3
11 15
0 2 7
F, 8
C, 1
J, 5
4 G, 3 7
1 10
2 5
D, 4
2 7 6 11
H, 1
A, 2
I, 4 8 9
1 B, 2 3 E, 5 6 K, 3
11 12 15 15
0 0 2 2 7 8
F, 8
C, 1
J, 5
4 G, 3 7
1 7 10 10
Act 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
A
B
C
D
E
F
G
H
I
J
K
◼ Risk avoidance
◼ The project manager says, “I will not accept this option
because of the potentially unfavourable results. I will
either change the design to preclude the issue or
change the requirements that lead to the issue.”
◼ Risk transfer
◼ The project manager says, “I will share this risk with
others through insurance or a warranty, or transfer the
entire risk to them. I may also consider partitioning the
risk across hardware and/or software interfaces.”
◼ Mainly 4 Types
◼ Cost-plus fixed fee
◼ Cost-plus incentive fee
◼ Fixed price or lump sum
◼ Fixed price incentive fee
◼ Contract Agreement:
Cost estimate = Rs. 100,000
◼ All allowable costs will be reimbursed
Target Fee = Rs. 10,000
Minimum Fee = Rs. 5,000
Maximum Fee = Rs. 15,000
Target Price = 110,000
Gain Sharing Ratio = 70/30