TACKLING EROSION AND INCREASING SAFETY DISTANCE IN TOWERS AT RIVERS CROSSING ON EDM T&D LINES
Construction of River crossing towers by replacing exisitng 33 kV poles for various distribution line across the country for Average river crossing spans of 400 m for Mulberry AAAC
150mm2 at Various Distribution line river crossings across Mozambique.
SUPPLY
A
(Including Transportation, Insurance Charges, other Incidental to Delivery Charges)
Design Fabrication and Supply of of 33 kV Single Circuit Galvanised Steel Lattice Tension Towers for River
1 crossings with average span 400 m for Single circuit Mulberry AAAC 150mm2 condcutor Extensions complete Nos. 82 7020 575640
with nuts, bolts & washers, hanger/D-schackles etc. as per specifications.
Fabrication and Supply of all Type of Stub & Stub setting templates for all Type of Towers including bolts &
2 Set of 4 82 716 58712
nuts complete as per specifications
Design & Destruction tests including the cost of materials after allowing rebate for scrap value of steel of
3
destroyed tower with 9m extension.
4 Number Plates with Bolts, Nuts and Washers complete as per specifications Nos. 82 20 1640
5 Danger Plates with Bolts, Nuts and Washers complete as per specifications Nos. 82 20 1640
6 Phase Plates with Bolts, Nuts and Washers (Set of 3 Plates) complete as per specifications Nos. 82 20 1640
7 Circuit Plates with Bolts, Nuts and Washers (Set of 2 Plates) complete as per specifications Nos. 82 20 1640
Anti - Climbing Devices for Towers including Bolts, Nuts and Washers for all Types of Towers including
8 Nos. 82 160 13120
Barbed Wire complete as per specifications
10 Earthing Material for Towers
a Pipe Type Earthing Material complete with necessary Bolts, Nuts and Washers complete as per specifications Nos. 41 100 4100
b Counterpoise Earthing Set complete with necessary Bolts, Nuts and Washers complete as per specifications
Any other Item specifically not mentioned above but required for completion and successful
19 Commissioning of River crossing towers by replacing exisitng 33 kV poles for various distribution line
across the country for Average river crossing spans of 400 m for Mulberry AAAC 150mm2.
i
ii
iii
iv
v
vi
vii
viii
Total Price 1727687.74
NOTE:
1
3
Unit
Total Total Unit Price Total Price
No. Description Unit Guaranted
Quantity Volume (USD) (USD)
Volume
Conducting Detailed Survey along the route by taking levels at every 15m intervals, details of crossings, steep
km 18 300 5412
increse in contour, trees and bushes etc.
2 SOIL INVESTIGATION
Running
Detailed Soil Investigation for Tower Locations for Open Shallow foundation as per specification 574 50 28700
Metre
3 BENCHING WORK
Benching of Tower Footings in all kind of Soil Cum 20
DESIGN AND EXECUTION OF FULLY SUBMERGED TYPE FOUNDATION INCLUDING
EXCAVATION, STUB SETTING & STUB SETTING TEMPLATE, PROVIDING SHORING,
4 SHUTTERING, DEWATERING & PROCURING, PLACING OF REINFORCEMENT AND Nos. 82 249517.472
CONCRETING INCLUDING FORM WORK & BACKFILLING TOWER FOUNDATION IN ALL
KINDS OF SOIL
Excavation Cum 90.16 5.6 504.896
Reinforcement kg 500 1.5 750
Concreting M10 Cum 1.875 160 300
Concreting M20 Cum 7.44 200 1488
5 ERECTION WORK
Removal of Exisiting 33 kV poles and Erection of new Towers ( Super Structures alongwith Body Extension of
a) Nos. 82 140.4 11512.8
all Towers) with Bolts and Nuts including Tack Welding, complete in all respects
b) Installation of Earthing of Towers
i) Pipe Earthing Nos. 41 70 2870
ii) 30metres Counterpoise Type Earthing complete with Excavation and Backfilling Nos. 21 70 1470
iii) 50 metres Counterpoise Type Earthing complete with Excavation and Backfilling Nos. 20 70 1400
c) Installation of following Tower Accessories
i) Danger Plate Nos. 82 10 820
ii) Number Plate Nos. 82 10 820
iii) Phase Plate (Set of Three) Nos. 82 10 820
iv) Circuit Plate (Set of Two) Nos. 82 10 820
v) Anticlimbing Device Set 82 10 820
6 REVETMENT WORK
i) Stone Masonary Work including Cement Mortar Work complete including exacavation(1:5 cement mortar) cum 20 5 100
ii) Stone bound in galvanizing wire netting including excavation cum 6 5 30
iii) PCC 1:2:4 as per specification for top seal cover of revetment cum 3.6 5 18
iv) Back filling & gap levelling of volumes enclosed by revetment cum 24 5 120
7 STRINGING WORK
Removal of Exisitng Hardware fittings from Exisitng Poles, De-stringing of Exisitng conductors and
Installation of Insulator Strings complete with Arcing Horns and necessary Hardware, Installing and Stringing
i) Spans 41 1000 41000
of Mulberry AAAC 150mm2 conductor (3 Phases) including fixing of Conductor Accessories complete in all
respects
ii) Installation and Stringing of Earth wire including Accessories complete in all respects Spans 41 500 20500
NOTE:
1