Unit Price
Installation / Erection
Unit Price Total Cost
Quantity Unit
No. Description Direct Direct (Rp) (Rp)
Raw Material Consumable
Equipment Manpower
1 PREPARATORY WORK
2. ARCHITECT WORK
- Brick Masonry 1.242,60 m2 284.527,16 103.464,42 25.866,11 103.464,42 517.322,10 642.824.441,46
- Door and window 1.242,60 m2 569.054,31 206.928,84 51.732,21 206.928,84 1.034.644,20 1.285.648.882,92
- Roof 1.242,60 m2 426.790,73 155.196,63 38.799,16 155.196,63 775.983,15 964.236.662,19
- Interior 1.242,60 m2 711.317,89 258.661,05 64.665,26 258.661,05 1.293.305,25 1.607.061.103,65
- Exterior 1.242,60 m2 398.338,02 144.850,19 36.212,55 144.850,19 724.250,94 899.954.218,04
- Multi Function Courts 1.242,60 m2 455.243,45 165.543,07 41.385,77 165.543,07 827.715,36 1.028.519.106,34
3. MEP WORK
- Electrical work 1.242,60 m2 1.190.779,88 476.311,95 238.155,98 476.311,95 2.381.559,75 2.959.326.145,35
- Hydrant 1.242,60 m2 1.455.397,63 582.159,05 291.079,53 582.159,05 2.910.795,25 3.616.954.177,65