Professional Documents
Culture Documents
Notes:
1. Arch/Engg Design firm estimate is complete, rough-in, finishing and provisions for building equipment (pumps etc)
2. Construction firm estimate only up to rough-in
3. Soil/Earthworks/Slope protection included in both estimates
4. Microbored Piles included incontrusction firm estimate
Action Plan:
Reconcile estimates
a. Construction firm to submit a more detailed description of work to be performed
b. Meet with Arch/Design Firm representative for evaluation of Consturction firm estimates
2,450,000.00
13,880,000.00
49,815,280.00
14,670,400.00
80,796,717.00
11,079,720.00
0.00
0.00
0.00
0.00
0.00
0.00
4,180,000.00
0.00
25,000,000.00
2,500,000.00
0.00
17,595,000.00
0.00
221,967,117.00
221,967,117.00
108,583,499.96
uction Firm Estimate is lower)