You are on page 1of 5

What Went Wrong?

BY W. NORM SHADE
CASE N
What caused the carbon buildup
o
28
No company, product, or individual is immune from on the compressor bearings?
experiencing failures or shortcomings. The solution to
these problems can often result in new “best practices.”
By relating some of these real case histories, it is hoped
that the lessons learned will be educational to the read- highest thrust pad temperature had been 217°F (103°C), but af-
ers. In each case, a failure or incident is described and the ter about 13,000 hours of problem-free operation, the position
question is asked, “What went wrong?” In each case, the monitor showed the rotor was gradually moving away from the
answer (or at least the best speculation) and the solution
inboard thrust bearing and the thrust pad temperature had ex-
that was applied to the problem will be explained.
cursions as high as 248°F (120°C) over a period of about two
weeks. The compressor thrust bearing was inspected and found
to have a 0.007-in. (0.18-mm) thick black carbonaceous deposit
on the inboard bearing thrust pads. The thrust disc had simi-
lar deposits on its inboard face. The outboard thrust bearing
pads and disc face were free of deposits. The axial clearance of
the thrust bearing had decreased from 0.021 in. (0.53 mm) to
0.007 in. The carbonaceous material was water-soluble and after
washing, both the pads and disc were reusable.
A review of maintenance records showed that the total acid
number (TAN) of the tertiary-butylphenyl diphenyl SPEL had in-
creased to 0.89 about three months before the problems began
and was even higher when the carbonaceous deposits were dis-
covered. The lubricant had received occasional activated alumina
½PXVEXMSR)\GIWWMZIEQSYRXWSJERXMJSEQEKIRXLEHFIIREHHIH
in the preceding six months to combat a foaming problem. Also,
some problems with lubricant cooling had occurred prior to the
Figure 1. Pipeline centrifugal compressor with overhung rotor as unit’s shutdown.
in Compressors 1 and 2 and similar to Compressors 4 and 5.1 8LIPYFVMGEXMSRW]WXIQ[EWXLSVSYKLP]¾YWLIHERHXLIPYFVM-
cant was replaced with new SPEL of the same type. The cleaned
thrust pads and disc were reinstalled. With the new lubricant,

A bout 40 years ago, a major gas transmission pipe-


line operator was experiencing problems with car-
bon deposits on bearings and seals in several of its large
the inboard thrust pad temperature was under 199°F (93°C) at
the design condition. After two months, the unit continued to
VYR[MXLSYXTVSFPIQWERHXLI¾YMH8%2[EWFIMRKQEMRXEMRIHMR
centrifugal compressors. In some cases, bearing and seal XLIXSVERKI[MXLGSRXMRYSYWEGXMZEXIHEPYQMRE½PXVEXMSR
failures were resulting from the deposits. Oddly, in each and it was still operating without problems after accumulating an
case, the machinery had run successfully for long periods additional 18,000 operating hours.
of time prior to encountering problems, and operating Compressor 2 was similar to Compressor 1, but was direct-
conditions were essentially unchanged from past experi- driven by a 5900-rpm, 16,360-hp (12.2-MW) gas turbine. The
ences. Mechanical inspection revealed no misassembled unit used an isopropyl phenyl SPEL, with occasional Fuller’s earth
or deviated components. This left the pipeline operator ½PXVEXMSRERHRSETTEVIRXTVSFPIQWJSVQSVIXLERLSYVW
asking the question, “What went wrong?”! The compressor had no thrust pad temperature instrumenta-
Five of the compressors were investigated in detail and tion, but some erratic axial rotor position and outer seal drain
smoking guns were discovered with the care and mainte- temperature indications had been observed in the last few weeks
nance of the lubricant in each case. All the gas turbine-driv- of the operating period. When the compressor was disassem-
en compressors were lubricated with synthetic phosphate bled to add bearing pad temperature instrumentation, the out-
ester lubricants (SPELs). Several types of SPELs had been FSEVHXLVYWXTEHW[IVIJSYRHXSLEZILIEZ][MTMRKERHWMKRM½-
widely used in gas turbines and centrifugal compressors cant Babbitt loss as shown in Figure 2.1 The inboard thrust pads
JSVHIGEHIWQEMRP]FIGEYWISJMXWWYTIVMSV½VIVIWMWXERGI had 0.040 in. (1.02 mm) of heavy black carbonaceous deposits.
Compressor 1 was a large 29,100-hp (21.7-MW), Similar deposits and some resulting Babbitt loss were found on
4950-rpm centrifugal compressor with an overhung ro- XLISMP½PQFYWLMRKWIEPWERHSRXLIMRFSEVHJEGISJXLIXLVYWX
tor design as shown in Figure 1.1 Under normal operating disc. The compressor journal bearings and all turbine bearings
conditions, the axial position monitor showed the rotor were discolored, but free of deposits. After the black deposits
thrust toward the inboard direction, carried by a 15-in. were washed off the inboard pads, pitting and corrosion damage
(381-mm) direct-lubricated tilting pad thrust bearing. The was evident on four of the eight pads, as shown in Figure 3.1

40 gascompressionmagazine.com | APRIL 2023


Figure 2. Outboard thrust bearing was found Figure 3. Inboard thrust bearing from Com- Figure 4. Inboard thrust bearing from Compres-
in Compressor 2 with heavy wiping and sig- TVIWWSVEJXIV[EWLMRKE[E]XLIXLMGOFPEGO WSVEJXIVPIWWXLERLSYVWSJSTIVEXMRK[MXL
RM½GERX&EFFMXXPSWWEWEVIWYPXSJXLMGOHITSW- HITSWMXWVIZIEPIHTMXXMRKERHGSVVSWMSRHEQ- W]RXLIXMGTLSWTLEXIIWXIVPYFVMGERXLEHEXSXEP
its on the inboard pads that reduced running age on four of eight pads.1 EGMH RYQFIV SJ  4MXXIH ERH GVEGOIH &EF-
GPIEVERGI1 bitt was discovered after washing away 0.004 in.
QQ SJFPEGOGEVFSREGISYWQEXIVMEP1

A new thrust disc, thrust bearing pads, and pad tem- ½PXIVIHXLVSYKLEGXMZEXIHEPYQMRE3TIVEXMRK[MXLGSRXMRYSYWEG-
perature instrumentation were installed. After startup, the XMZEXIHEPYQMRE½PXVEXMSRXLIYRMXVER[MXLSYXER]JYVXLIVFIEVMRK
thrust pad temperatures increased with time at comparable TVSFPIQWEJXIVEGGYQYPEXMRKEREHHMXMSREPSTIVEXMRKLSYVW
WTIIHW ERH XLVYWX PSEHW ;MXLMR ½ZI HE]W XLI XLVYWX TEH 'SQTVIWWSV[EWETMTIPMRIGSQTVIWWSV[MXLEFIEQWX]PIVS-
temperatures were limiting both the compressor speed XSV HVMZIR EX  VTQ F] E LT 1;  KEW XYVFMRI
ERHPSEHXSFIPS[VEXIHGSRHMXMSRWIZIR[MXLVIHYGIHPY- %JXIVEFSYX½ZI]IEVWSJVIPMEFPISTIVEXMSRHYVMRKEVITEMVSJE
FVMGERXWYTTP]XIQTIVEXYVI-RWTIGXMSRSJXLIGSQTVIWWSV Continued on page 42
XLVYWX FIEVMRK VIZIEPIH XLEX XLI MRFSEVH TEHW LEH EPVIEH]
accumulated a 0.004-in.- (0.1-mm)-thick black deposit near
the outer diameter of the bearing pads. The deposits were
washed off the undamaged pads, which were reinstalled.
2MRIX] LSYVW EJXIV VIWXEVXMRK XLI YRMX I\TIVMIRGIH XLI
same temperature problems that limited speed and load.
-RWTIGXMSREKEMRJSYRHEHITSWMXSJEFSYXMRSRXLI
inboard thrust pads, as shown in Figure 4.1 After washing the
TEHWWYFWYVJEGITMXXMRKERHEGVEGOIH&EFFMXX[IVIHMWGSZ- One source for precision, quality,
IVIHYRHIVXLIEVIESJLIEZMIWXHITSWMXW*MKYVIWLS[WSRI
SJXLITEHW[MXLXLIHITSWMX[EWLIHE[E]SRLEPJXLITEH and capability.
surface.1 Under a microscope, the Babbitt cracks had the
appearance of a stress corrosion attack. At this time, high
8%2[EWHMWGSZIVIHERHXLI¾YMH[EWGMVGYPEXIHXLVSYKL
EGXMZEXIHEPYQMREJSVX[SHE]WVIHYGMRKXLI8%2JVSQ
XS3XLIVPYFVMGERXTVSTIVXMIWWYGLEWZMWGSWMX][EXIV
content, foaming characteristics, metal content, etc. did not
MRHMGEXI ER] SXLIV TVSFPIQW [MXL XLI ¾YMH % RI[ XLVYWX
bearing was installed and, after the unit was restarted, some
initial foaming was controlled through the addition of an
ERXMJSEQ EKIRX %X EFSYX  LSYVW EJXIV VIWXEVXMRK XLI
YRMXI\TIVMIRGIHWYGGIWWMZIWLYXHS[RWHYIXSLMKLMRFSEVH
XLVYWXFIEVMRKXIQTIVEXYVIERHI\GIWWMZIE\MEPVSXSVQSZI-
www.hfwindustries.com
QIRX;LIRXLISTIVEXSVF]TEWWIHXLIXVMTWERHVIWXEVXIH
to keep the unit online during a critical pumping period, the HFW Industries, Inc.
MRFSEVHXLVYWXFIEVMRKERHXLVYWXHMWG[IVIHIWXVS]IH8LI 196 Philadelphia St.
outboard thrust bearing was in perfect condition as were all Buffalo, NY 14207-0008
the compressor and turbine journal bearings. Compressor
bushing seals had thin deposits of black carbonaceous ma- sales@hfwindustries.com
XIVMEP(YVMRKXLIGSQTVIWWSVVITEMVXLI¾YMHW]WXIQ[EW Ph: 716-875-3380 / Fax: 716-875-3385
¾YWLIH RI[¾YMH[EWEHHIHERHXLIVIQEMRMRK¾YMH

gascompressionmagazine.com | APRIL 2023 41


speeds on mineral oil. After problem-free operation for about six months, the
non-drive-end journal bearing temperature began to increase. Fluid quality was
RSXGLIGOIHFYXJSYVXS½ZILSYVWSJEGXMZEXIHEPYQMRE½PXVEXMSRGSRXVSPPIHXLI
TVSFPIQ;MXLTIVMSHMGEGXMZEXIHEPYQMRE½PXVEXMSRXLIYRMX[EWWXMPPSTIVEXMRK
with minimal deposits 30 months later.
Compressor 4 was another single-stage, overhung pipeline booster driven by
a 12,300-hp (9.2-MW), 4950-rpm gas turbine. The compressor encountered in-
board bearing and seal problems after more than 50,000 hours of operation. The
synthetic lubricant had never been replaced during that time, although makeup
¾YMH LEH FIIR EHHIH 8LI XIVXMEV]FYX]PTLIR]P HMTLIR]P 74)0 LEH SGGEWMSREP
*YPPIV´WIEVXL½PXVEXMSRERHSYXIVFYWLMRKWIEPPMJILEHI\GIIHIHSRI]IEV,S[-
ever, major problems were encountered following a six-month idle period during
[LMGLXLIVIWIVZSMVLIEXIVW[IVIWSQIXMQIWIRIVKM^IH[MXLSYX¾YMHGMVGYPEXMSR
About 1000 hours of operation after this idle period, the compressor seal drain
Figure 5. One of the pads from the bearing in Figure
XIQTIVEXYVIFIKERXSMRGVIEWIERHXLIWIEPHVEMR¾S[VEXIHIGVIEWIH[MXLXMQI
4 after washing away the deposits on half the pad
surface. Under a microscope, the Babbitt cracks had
Inspection revealed black carbonaceous deposits on the inboard journal bearing
the appearance of stress corrosion attack.1 TEHWERHSRFSXLFYWLMRKWIEPW8LI¾YMH8%2SJ[EWVIHYGIHXSF]
*YPPIV´WIEVXL½PXVEXMSR%JXIVXLIFIEVMRKWERHWIEPW[IVIVITPEGIHMRERSXLIV
1000 hours of operation, the inboard journal bearing failed, scoring the shaft. The
HEQEKIH FEPERGI WIEP WMKRM½GERX GSEXMRKW SJ bushing seal bores and shaft area under each seal were coated with black deposits.
black carbonaceous material were discovered 8LI¾YMH8%2LEHMRGVIEWIHXSERHXLIRLEHFIIRVIHYGIHXSPIWWXLER
on the non-drive-end journal bearing, the F]½PXVEXMSREXXLIXMQISJXLIJEMPYVI8LIVIFYMPXYRMX[MXLXLIPYFVMGEXMSRW]WXIQ
bushing seals on both ends, and the outboard ¾YWLIHERHVI½PPIH[MXLRI[XIVXMEV]FYX]PTLIR]PHMTLIR]P74)0VER½RIEKEMR
TEHWERHXLVYWXHMWGSJXLIMR QQ  Compressor 5, with almost 73,000 operating hours, was virtually identical to
XLVYWXFIEVMRKWLS[RMR*MKYVI8LIVI[EW Compressor 4. It experienced similar behavior at about the same time following
RS &EFFMXX PSWW JVSQ ER] SJ XLI FIEVMRKW SV EWMQMPEVMHPITIVMSH8LIQENSVHMJJIVIRGI[EWXLEXXLI¾YMH8%2[EWSRP]EX
seals. The damaged balance seal caused the XLIXMQISJXLITVSFPIQ,S[IZIVJSVXLITVMSVX[S]IEVWTIVMSHMG¾YMHEREP]WMW
seal differential pressure to increase, causing VIGSVHWWLS[IHE8%2EWLMKLEW*YPPIV´WIEVXL½PXVEXMSRLEHFIIRYWIHSGGE-
some lubricant ingestion into the gas stream WMSREPP]JSVQER]]IEVWFIJSVIW[MXGLMRKXSEGXMZEXIHEPYQMRE½PXVEXMSR3RXLVII
on the non-drive end. There, the lubricant had SGGEWMSRW[MXLMR½ZIQSRXLWFPEGOHITSWMXW[IVIJSYRHSRXLISYXIVFYWLMRKWIEP
migrated along the rotor shaft, leaving black FSVIJSPPS[MRKSFWIVZEXMSRWSJHIGVIEWMRKSYXIVWIEPSMP¾S[ERHMRGVIEWMRKSMP
carbonaceous deposits and some evidence of HVEMRXIQTIVEXYVI3RSRISGGYVVIRGIHITSWMXW[IVIJSYRHEPWSSRXLIMRFSEVH
chemical attack on the labyrinth seals. The thrust bearing pads and the mating thrust disc face. Following reassembly after the
XIVXMEV]FYX]PTLIR]P HMTLIR]P 74)0 LEH SG- third occurrence, the inboard journal bearing and seals failed in only 30 hours of
GEWMSREP½PXVEXMSRXLVSYKL*YPPIV´WIEVXLERH operation, preceded by an increasing outer seal drain temperature. The bearing
generous doses of silicone antifoam agent failure also damaged the shaft. After rebuilding, another failure occurred in only
LEH FIIR EHHIH SZIV WIZIVEP ]IEVW 3RP] seven hours of operation. After this failure, the compressor was rebuilt with 20%
310 hours after the compressor rebuild, the increased inboard journal bearing clearance, although original design clearance
compressor non-drive-end bearings and seals had run successfully for more than a decade on this unit and on many other units.
were reinspected following an increase in 8LISPH¾YMH[EWVITPEGIH[MXLRI[XIVXMEV]FYX]PTLIR]PHMTLIR]P74)08LIVIEJ-
the journal bearing pad temperature. The in- XIVXLIYRMXVERWYGGIWWJYPP][MXLGSRXMRYSYWEGXMZEXIHEPYQMRE½PXVEXMSR
ner bushing seal had accumulated a buildup
of deposits in the bore, causing a diametral 8,)713/-2++927
clearance reduction of 0.002 in. (0.05 mm), As a result of extensive investigations of the compressor problems, sev-
which was 40% of the design running clear- eral smoking guns were discovered that answered the question, “What went
ance. Analysis of the lubricant indicated that wrong?”! All were related to the maintenance procedures and condition of
XLI 8%2 [EW  XLI ZMWGSWMX] [EW   XLI74)0¾YMHWMRXLIGSQTVIWWSVW4VMSVXSXLMWWIVMIWSJIZIRXWSXLIVYWIVW
LMKLIV XLER WTIGM½GEXMSR ERH JSEQMRK XIR- ERHETTPMGEXMSRWLEHVITSVXIHTVSFPIQW[MXL74)0W)EVP]YWIVWHMWGSZIVIH
dency was high. Waxy deposits were found XLEXXLI¾YMHWEVII\GIPPIRXTEMRXVIQSZIVWERHEVIMRGSQTEXMFPI[MXLQER]
MRXLI½PXIVWERHXLIVIWIVZSMVLIEXIVWLEHE common elastomers such as polychloroprene or acrylonitrile polymer.2,3 As
thick black deposit of carbonaceous material. IEVP]EWMX[EWVITSVXIHXLEXI\XIRHIHI\TSWYVIXSQSMWXYVISVLMKL
The lubrication system was cleaned, XIQTIVEXYVI PIH XS WMKRM½GERX ZMWGSWMX] ERH EGMHMX] MRGVIEWIW GSPSV GLERKI
¾YWLIH ERH VI½PPIH [MXL RI[ 74)0 SJ XLI from yellow to black, and formation of black brittle deposits.4 For example, at
same type. The inner seal bore geometry „* „' XLI¾YMHHIXIVMSVEXIHEXEWPS[VEXI&YXEX„* „' XLI
[EWQSHM½IHXSTIVQMXQSVI¾S[JSVGSSP- YWIJYPPMJI[EWEJI[[IIOWERHEX„* „' MX[EWEJI[LSYVW
ing; however, the original seal design had 8LII\MWXIRGISJELMKL8%2GEYWIWEREYXSGEXEP]XMGVIEGXMSRXLEXWTIIHWYT
been successfully used for many years on well the oxidation of the lubricant at relatively low temperatures.5 For quite some
over 100 units operating at up to 10% higher Continued on page 44

42 gascompressionmagazine.com | APRIL 2023


LS[IZIV XSS QYGL ERXMJSEQ EKIRX [MPP TVSQSXI XLI
JSVQEXMSR SJ KIPW JSEQMRK ERH EIVEXMSR EW SGGYVVIH
MR'SQTVIWWSV%PWSGSOMRKGERFIJSVQIHF]¾YMH
EIVEXMSR TVSFEFP] F] XLI EWWSGMEXIH S\MHEXMSR XLEX
SGGYVW8)\GIWWMZI8%2PIZIPWERHXLIEHHMXMSRSJWMK-
RM½GERXEQSYRXWSJERXMJSEQEKIRXW[IVIWQSOMRKKYRW
MRWIZIVEPSJXLIGEWIW1EMRXIRERGISJPS[8%2ERH
GEYXMSYWEHHMXMSRSJERXMJSEQEKIRXW[MPPLIPTGSRXVSP
JSEQMRKERHEIVEXMSR
74)0 QERYJEGXYVIVW LEZI TIVMSHMGEPP] VIJSVQYPEXIH
XLIMV TVSHYGXW XS VIHYGI S\MHEXMSR JSEQMRK ERH HI-
TSWMXJSVQEXMSR81ER]YWIVWLEZIIRNS]IHWYGGIWW[MXL
74)0WFYXPSRKXIVQ¾YMHHIKVEHEXMSRGERGVIEXIXLI
Figure 6. Pipeline centrifugal compressor with beam-type rotor as in Compressor 3.1
TVSFPIQWQIRXMSRIHWMRGIXLIHIKVEHIH¾YMHEGGIPIV-
EXIW JYVXLIV HIKVEHEXMSR =IX ERSXLIV WQSOMRK KYR
XMQIFIJSVIXLI½ZIMRGMHIRXWHMWGYWWIHLIVI[EWXLIQE\MQYQ8%2 [EWEPPS[MRKXLI8%2SJXLI¾YMHXSFIGSQII\GIWWMZI
VIGSQQIRHIHJSVXYVFMRIPYFVMGERXW-JEPPS[IHXSMRGVIEWIWMKRM½GERXP] [LMGLJYVXLIVEGGIPIVEXIHXLIHIKVEHEXMSRVEXI
XLIVEXISJ8%2MRGVIEWIKVI[IZIRXLSYKLEGXMZI½PXVEXMSR[SYPHKMZI
EXIQTSVEV]HIGVIEWI1ER]TVSFPIQW[MXL74)0WEVIEWWSGMEXIH[MXL 0)773270)%62)(%2(6)'311)2(%8-327
XLIHIZIPSTQIRXSJEGMHMX]HYIXSL]HVSP]WMWSVS\MHEXMSR7]WXIQW[MXL 6IGSQQIRHEXMSRW[IVIFEWIHSRWYGGIWWJYPI\TIVM-
JI[TVSFPIQWEVIYWYEPP]JSYRHXSLEZIPS[PIZIPWSJEGMHMX]68LIVIJSVI IRGI[MXLRIEVP]KEWXYVFMRIGIRXVMJYKEPGSQTVIWWSV
EWMKRM½GERXWQSOMRKKYRMREPPXLIGEWIWHMWGYWWIH[EWXLEXXLI8%2[EW MRWXEPPEXMSRW STIVEXMRK [MXL 74)0 1ER] SJ XLIWI YRMXW
EXPIEWXEXWSQITSMRX[MXLXLI[SVWX¾YMHETTVSEGLMRKE8%2SJ LEHEGGYQYPEXIHQSVIXLERLSYVWSJSTIVEXMSR
74)0WEVIWYFNIGXXSEYXSGEXEP]XMGL]HVSP]XMGHIKVEHEXMSR7MRGITVI- EX XLI XMQI  [MXL RS WMKRM½GERX TVSFPIQW %PXLSYKL
ZIRXMRKQSMWXYVIJVSQIRXIVMRKQSWXPYFVMGERXWMWHMJ½GYPXTEVXMGYPEVP] FIEVMRK ERH WIEP TVSFPIQW [IVI ZMVXYEPP] RSRI\MWXIRX
[LIRXLIYRMXWEVIRSXSTIVEXMRKQIXLSHWQYWXFIHITPS]IHXSWPS[¾Y- [MXLGSQTVIWWSVWSTIVEXMRKSRQMRIVEPSMPWIZIVEPLEH
MHQSMWXYVIEFWSVTXMSRSVVIQSZIVIWYPXMRKEGMHMX]1SMWXYVIQE]EJJIGX TVSFPIQW[LIRSTIVEXMRK[MXL74)0W8LI[MHIZEVME-
XLIEGXMZMX]SJXLIWSPMHWGSRXEMRIHMRXLIEGXMZI½PXIVW67SQIVIWIEVGL XMSRMRXLI[E]74)0W[IVIXVIEXIHERHQEMRXEMRIHI\-
MRHMGEXIHXLEXS\MHEXMSRSJXLIPYFVMGERXSGGYVWEXLMKLXIQTIVEXYVIWERH EGIVFEXIH F] E TIVMSH [LIVI PS[ REXYVEP KEW HIQERH
PIEHWXSHITSWMXWSRFIEVMRKTEHW-RXLIGEWIWSJ'SQTVIWWSVWERH VIWYPXIHMRQER]YRMXWMHPMRKJSVQSRXLWEXEXMQIPIHXS
XLIYRMXWLEHFIIRMHPIFIJSVIXLITVSFPIQWFIGEQIETTEVIRX(YVMRK TVSFPIQW[MXLYRMXWSTIVEXMRKSR74)0W
WSQISJXLMWMHPIXMQIXLIVIWIVZSMVLIEXIVW[IVIFIMRKYWIH[MXLRS 8LI WSPYXMSR SJ XLI GSQTVIWWSV PYFVMGERX TVSFPIQW
GMVGYPEXMSR 0EVKI HITSWMXW SJ GEVFSR SR VIWIVZSMV LIEXIVW TSMRXIH XS HMWGYWWIHMRXLIWIGEWIW[EWXLIVIWYPXSJGSPPEFSVEXMSR
LMKLXIQTIVEXYVIWKIRIVEXIHF]XLIWILIEXIVWXSKIXLIV[MXLQSMWXYVI FIX[IIR XLI GSQTVIWWSV QERYJEGXYVIV XLI STIVEXSV
GSRHIRWEXMSREWGEYWIWSJ¾YMHHIKVEHEXMSRERHERSXLIVWQSOMRKKYR ERH¾YMHQERYJEGXYVIVW74)0WLEZIZMVXYEPP]YRPMQMXIH
;LIVI[EXIVGSRXEQMREXMSR[EWTSWWMFPI½PXVEXMSRXLVSYKLEGXMZEXIH PMJI[LIREGMHMX]ERHGSRXEQMREXMSREVIGSRXVSPPIHTVST-
GPE]W *YPPIV´WIEVXL SVEGXMZEXIHEPYQMRE[EWYWIHXSGSRXVSPEGMHMX]SJ IVP];LMPIPYFVMGERXQERYJEGXYVIVWLEHMQTVSZIHXLIMV
74)0WVIWYPXMRKJVSQL]HVSP]WMWERHXSI\XIRHXLIMVYWIJYPPMJI9RXMPXLI ¾YMHWSZIVXLI]IEVWMRVIWTSRWIXS½IPHTVSFPIQWXLI]
PEXIW*YPPIV´WIEVXL[EW[MHIP]YWIHLS[IZIVQER]TVSFPIQWLEH LEHRSXFIIREWIJJIGXMZIMRGSQQYRMGEXMRK¾YMHQEMR-
FIIRIRGSYRXIVIH66IEGXMSRSJL]HVSP]WMWTVSHYGXW[MXLQEKRIWMYQL]- XIRERGI KYMHIPMRIW XS XLIMV GYWXSQIVW *SPPS[MRK EVI
HVS\MHIERHWSHMYQEPYQMRYQWMPMGEXIWGEYWIHKIPJSVQEXMSRMR½PXIVWERH WSQI VIGSQQIRHEXMSRW XLEX VIWYPXIH EX XLI XMQI %W
VIWIVZSMVW,MKLP]EGMHMG¾YMHWXIRHIHXSJSEQERHWMPMGSRIERXMJSEQEH- EP[E]WGYVVIRXGSQTVIWWSVERHPYFVMGERXQERYJEGXYVIV
HMXMZIW[IVIWXVMTTIHSYXF]XLIGPE]%QSVIWMKRM½GERXTVSFPIQ[EWXLI KYMHIPMRIWWLSYPHFIJSPPS[IHMJHMJJIVIRXJVSQXLIVIG-
XIRHIRG]SJEGMHMG74)0WXLEX[IVIXVIEXIH[MXL*YPPIV´WIEVXLXSTPEXI SQQIRHEXMSRWTVSZMHIHLIVI
SYXFPEGOFVMXXPIWSPMHHITSWMXWSRLSXWYVJEGIWMRGPYHMRKFIEVMRKW Acid Control:74)0EGMHPIZIPWLSYPHFIGSRXVSPPIHXSE
-RXLIPEXIWEGXMZEXIHEPYQMREKEMRIHEGGITXERGIEWEQSVIGSRWMW- 8%2SJRSQSVIXLERXS;LIRHIKVEHIH¾YMHMW
XIRXERHGSWXIJJIGXMZIEFWSVFIRXQEXIVMEPJSVXLIXVIEXQIRXSJ74)0W GLERKIHSYXXLIW]WXIQWLSYPHFIGPIERIHERH¾YWLIHXS
IZIRXLSYKLMX[EWWIZIVEPXMQIWQSVII\TIRWMZI6%GXMZEXIHEPYQMRE VIQSZIEPPKIPERHWPYHKIERH½PXIVWWLSYPHFIVITPEGIH
QSVIGSRWMWXIRXERHPEGOMRKGEPGMYQERHQEKRIWMYQMSRWLEWPIWWXIR- 8SQEMRXEMREPS[8%2XLIRI[¾YMHWLSYPHFISRGSR-
HIRG]XSJSVQHITSWMXW,S[IZIVMXGSRXEMRWWSQIWSHMYQ[LMGLGER XMRYSYWEGXMZEXIHEPYQMRE½PXVEXMSREWWSSREWMRWXEPPIH
JSVQHITSWMXWERHLEWGEYWIHWSQITVSFPIQWEW[IPP&IGEYWIPS[8%2 Active Filtration: 'SRXMRYSYW EGXMZEXIH EPYQMRE ½PXVE-
¾YMHWLEZIPS[IVVIEGXMSRVEXIWQEMRXIRERGISJPS[8%2F]GSRXMRYSYW XMSR YWMRK E TEVXMEP F]TEWW W]WXIQ MW VIGSQQIRHIH
½PXVEXMSR[EWJSYRHXSEGXYEPP]YWIPIWW½PXVEXMSRQIHMEXLERMRXIVQMXXIRX 1EMRXIRERGISJPS[8%2MWGVMXMGEPXSEZSMHMRKXLIJSV-
½PXVEXMSR ERH VIWYPXIH MR PS[IV WSHMYQ WEPX GSRGIRXVEXMSR MR XLI ¾YMH QEXMSRSJKIPWERHHITSWMXW*MPXIVWWLSYPHFIGLERKIH
9WMRKEGXMZI½PXVEXMSRXSVIHYGIXLI8%2EJXIVMXLEHVIEGLIHELMKLPIZIP TIVMSHMGEPP] TVIJIVEFP] [LIR XLI 8%2 VIEGLIW 
[EWERSXLIVWQSOMRKKYRMRWSQISJXLIGEWIW FYX HI½RMXIP] FIJSVI  MW I\GIIHIH *MPXIVW WLSYPH
7IZIVIJSEQMRKERHEMVIRXVEMRQIRXGERVIWYPX[LIR8%2VIEGLIWI\- FIWLMTTIHERHWXSVIHMRWIEPIHGSRXEMRIVWXSTVIZIRX
GIWWMZIPIZIPW6%GXMZI½PXVEXMSRGERVIQSZIWMPMGSRIERXMJSEQMRKEKIRXW QSMWXYVIEFWSVTXMSR8LIYWISJ*YPPIV´WIEVXLWLSYPHFI

44 gascompressionmagazine.com | APRIL 2023


EZSMHIHJSV74)0½PXVEXMSRFIGEYWI WLSYPH FI HSRI SRP] EJXIV GSRWYPXMRK XLI QERYJEGXYVIVW *PYMHW EVI WSQIXMQIW VIJSV-
SJ XLI XIRHIRG] XS GEYWI HITSWMX QYPEXIH[MXLSYXEGLERKIMRFVERHREQISVKVEHIERHXLI]QE]VIUYMVIGLERKIWMRXLI
JSVQEXMSR *YPPIV´W IEVXL VIQSZIW XVIEXQIRXTVSGIHYVI
EGMHFYXMX[MPPVIEGX[MXLXLI¾YMH System Compatibility:9WISJTYVIGSTTIVERHPIEH&EFFMXXMRQEGLMRIV]YWMRK74)0WMW
VIWYPXMRKMRLEVHWEPXWERHWSETHI- HMWGSYVEKIH-REHHMXMSR74)0WEVIMRGSQTEXMFPI[MXLQSWXTEMRXWERHGIVXEMRIPEWXSQIVW
TSWMXWXLEXGSEXMRXIVREPWYVJEGIW-X 7]WXIQWYWMRK74)0WJSVXLI½VWXXMQIQYWXFIGEVIJYPP]VIZMI[IHJSVGSQTEXMFMPMX]
EPWSEHHWQEKRIWMYQMVSRERHGEP-
GMYQGSRXEQMREXMSRXSXLISMP 6)*)6)2')7
Frequent Testing: 6ITVIWIRXEXMZI 
7LEHI;2±*MIPH)\TIVMIRGI[MXL(IKVEHIH7]RXLIXMG4LSWTLEXI)WXIV0YFVMGERXW²
WEQTPIWSJXLI¾YMHXEOIRJVSQXLI 1EVGL
VIWIVZSMVTVIJIVEFP]IZIV]SRIXS 2
.EQIW60±8LI,MWXSV]ERH9WISJ*MVI6IWMWXERX*PYMHWMR+EW8YVFMRIW²%71)4E-
XLVII [IIOW WLSYPH FI GLIGOIH TIV+8 2I[=SVO2=%71) LXXTWHSMSVK+8
JSV EGMHMX] ERH GSRXEQMREXMSR YW- 3
±)ZEPYEXMSR ERH 8IWX SJ -QTVSZIH *MVI6IWMWXERX *PYMH 0YFVMGERXW JSV ;EXIV 6IEGXSV
MRKOMXQIXLSHW/MXXIWXMRKSJJIVW 'SSPERX4YQT1SXSVW²;46-24.YP]
UYMGOIV VIWYPXW [MXL PS[IV GSWXW 
'LMERXIPPE%.%JJIRW;%ERH.SLRWSR.)±)JJIGXSJ,MKL8IQTIVEXYVIWSR7XE-
XLERPEFSVEXSV]QIXLSHW0EFSVE- FMPMX] ERH -KRMXMSR 4VSTIVXMIW SJ 'SQQIVGMEP 8VMEV]P 4LSWTLEXI *PYMHW² I&EC Product
XSV]XIWXWWLSYPHFIGSRHYGXIHIZ- Research and Development  T
IV]X[SXSXLVIIQSRXLWEWEGLIGO 
6MXGI](6±8LI7IPIGXMSRERH4IVJSVQERGISJE7]RXLIXMG0YFVMGERX;LIR9WIHMR
SJXLIOMXQIXLSHVIWYPXW6IWYPXW ER-RHYWXVMEP+EW8YVFMRI²%71)4ETIV;%+84 2I[=SVO2=%71) 
SJ XLI XIWXW WLSYPH FI VIGSVHIH 
4LMPPMTW;(±8LI'SRHMXMSRMRKSJ4LSWTLEXI)WXIV*PYMHWMR8YVFMRI%TTPMGEXMSRW²
ERH EREP]^IH JSV XVIRHW MRHMGEXMRK Lubrication Engineering  T
[LIR½PXIVWWLSYPHFIGLERKIHSV 
+EVHRIV 0 ERH 1SSR + ±)ZEPYEXMSR SJ *MVI6IWMWXERX 0YFVMGERXW JSV -RHYWXVMEP +EW
[LIR ¾YMH WLSYPH FI VITPEGIH SV 8YVFMRIW²2EXMSREP6IWIEVGL'SYRGMPSJ'EREHE1IGLERMGEP)RKMRIIVMRK*YIPWERH0Y-
±WTMOIH²[MXLJVIWL¾YMH FVMGERXW0EFSVEXSV]6ITSVX142SZIQFIV
Additives: %HHMXMZIW WLSYPH FI 
 4EROS[MIGOM . ±*MVI 6IXEVHERX 0YFVMGERX JSV 8YVFMRI +IRIVEXSVW² )46- 24
YWIH WTEVMRKP] ERH EGGSVHMRK XS *MREP6ITSVX.ERYEV]
XLI PYFVMGERX QERYJEGXYVIV´W VIG-
SQQIRHEXMSRW 3RI QENSV 74)0
YWIVHMWTIVWIWERXMJSEQEHHMXMZIMR
XSPYIRIERHWTVE]WXLIQM\XYVISR
XLI ¾YMH WYVJEGI MR XLI VIWIVZSMV
IPMQMREXMRKJSEQ[MXLSRP]EWQEPP
EQSYRXSJXLIEHHMXMZI A POWERFUL FUTURE
Idle Periods:1EMRXEMRMRKXLIVIW-
IVZSMVEFSZIEQFMIRXXIQTIVEXYVI THE WORLD WANTS MORE ENERGY
[MXLWSQI¾YMHGMVGYPEXMSRWLSYPH AND LOWER EMISSIONS
PMQMXQSMWXYVIGSRHIRWEXMSR(YV-
MRKTIVMSHW[LIRXLIGSQTVIWWSV WAUKESHA’S VHP SERIES FIVE DELIVERS BOTH
MWRSXSTIVEXMRKEQIERWSJWPS[
¾YMH GMVGYPEXMSR WLSYPH FI TVS-
ZMHIH MR XLI VIWIVZSMV [LIR XLI
LIEXIVW EVI IRIVKM^IH FYX [LIR
XLIQEMRTYQTWEVISJJ0S[[EXX
HIRWMX]LIEXIVW XSO;LQ2)
EVIVIGSQQIRHIHXSEZSMHSZIV-
LIEXMRKXLISMPEVSYRHXLILIEXIV
IPIQIRXW,IEXIVIPIQIRXWWLSYPH
RSXFISJVIEGXMZIQEXIVMEPWWYGL Energy demands are growing. Emissions standards
EWGSTTIVYRPIWWTPEXIH[MXLEQE- are changing. Waukesha Engine offers reliance for
XIVMEPXLEXMWRSRVIEGXMZI[MXLXLI today and compliance for tomorrow.
74)0 'ERMWXIVX]TI LIEXIVW EVI
TVIJIVVIH • 90%+ lower methane emissions
Fluid Recognition: 8LIVI EVI HMJ- • 10-20% lower CO2e emissions
JIVIRX 74)0 JSVQYPEXMSRW ERH
XLI] QE] RSX FILEZI XLI WEQI • Lower NOx and VOC emissions
[E] MR HMJJIVIRX W]WXIQW 1M\MRK
SJ74)0WJVSQHMJJIVIRXQERYJEG- ZZZLQQLRFRPHQZDXNHVKDJDVHQJLQHVYKSVHULHV¿YH
XYVIVWMWWXVSRKP]HMWGSYVEKIHERH

gascompressionmagazine.com | APRIL 2023 45

You might also like