You are on page 1of 1

Contract For The Construction And Completion For Cadangan Membina 64 Unit Rumah Berkembar 2

Tingkat Dan 3 Tingkat Yang Mengandungi: − (A) 17 Unit 2 Tingkat Jenis A Di No 2, 6, 10, 11, 14, 15,
18, 19, 22, 26 Jalan U17/18E, Di No 2, 6, 10, 14, 18, 22, 26 Jalan U17/18F; (B) 17 Unit 2 Tingkat
Jenis A (M) Di No 4, 8, 9, 12, 13, 16, 17, 20, 24, 28 Jalan U17/18E, Di No 4, 8, 12, 16, 20, 24, 28
Jalan U17/18F; (C) 15 Unit 3 Tingkat Jenis B Di No 3, 7, 11, 15, 19, 23, 27, 31 Jalan U17/18F, Di No
3, 7, 11, 15, 19, 23, 27 Jalan U17/18G; (D) 15 Unit 3 Tingkat Jenis B (M) Di No 1, 5, 9, 13, 17, 21,
25, 29 Jalan U17/18f, Di No 1, 5, 9, 13, 17, 21, 25 Jalan U17/18G Di Atas Lot PT 50681-50686 Dan
Lot PT 50689-50746 (Di Atas Sebahagian Lot 85632), Seksyen U17, 40160 Shah Alam, Selangor Darul
Ehsan Untuk Tetuan Unik Sejati Sdn. Bhd.

Method Statement for RC Wall Waterproofing Surface Protection

1st floor slab

RC Wall
Waterproofing

PE Sheet

Ground Slab

▪ After the surface of R.C wall that is facing outside has been applied with waterproofing and
before the backfilling works, PE sheet is used to protect the waterproofing from damaged during
backfiling works.

▪ The PE Sheet is laid on all areas of the wall that has been applied waterproofing which will
ensure that no direct contact between waterproofing and soil.