Professional Documents
Culture Documents
March 15-22, 2023
March 15-22, 2023
Date :
AGENDA:
A. LAST WEEK PROGRESS MONITORING
B. LTI TO DATE MONITORING
C. LAST WEEK ACTIVITIES
D. SITE PHOTOS
E. 1-WEEK LOOK AHEAD ACTIVITY
F. OTHERS
A. PROGRESS C. LAST WEEK ACTIVITIES (MARCH 15 – MARCH 22, 2023)
STRUCTURAL
LAST WEEK PROGRESS CONRETE POURING DONE AT 3RD FLOOR SLAB,COLUMN, ELEVATOR
(GRIDLINE 9-16/E-C) - 167 CUBIC.
ACTUAL = 61.00 % CONRETE POURING DONE FOR FIRE EXIT STAIR 03 (MEZZANINE TO 3 RD
FLOOR AND FIRE EXIT STAIR 02 (GROUND TO MEZZANINE)
PLAN = 70.16 % ARCHITECTURAL
DONE CONCRETE TOPPING AT MEZZANINE STORAGE AREA.
VARIANCE = 9.168 %
DONE TILES INSTALLATION AT MEZZANINE CLINIC.
ON GOING TILES INSTALLATION AT MEZZANINE HALLWAY GRIDLINE
(9-16/C).
ON GOING CEILING INSTALLATION SUPPORT AT AREA MEZZANINE HALLWAY
DONE TILES INSTALLATION AT MEZZANINE CLINIC.
START TILES INSTALLATION OF TILES AT MEZZANINE RESTAURANT AREA.
B. LTI TO DATE = 87,055 Safe PLASTERING INTERIOR WALL AT MEZZANINE CCTV AREA PRIOR TO
PAINTING AND CONCRETE TOPPING.
ManHour FILLING CHB INTERIOR WALL AT GROUND FLOOR GRIDLINE 3/E-B.
DONE PAINTING AT MEZZANINE STORAGE AND CLINIC 1ST COATING.
ON GOING PLASTERING ON EXTERIOR WALL.
PILING OF CHB FOR GROUND FLOOR AT GRIDLINE 9-16/E-C, 1-7/E-B,
9/B-A
PILING OF CHB FOR 2ND FLOOR AT GRIDLINE 11-16/E-C
PLASTERING OF 2ND FLOOR WALLS
INSTALLATION OF SHORING SYSTEM AT GRIDLINE 11-16/E-C
INSTALLATION OF STIRRUPS FOR 3RD FLOOR BEAMS (GRIDLINE 11-
16/E-C)
INSTALLATION OF COLUMNS FOR 2ND FLOOR COLUMNS
INSTALLATION OF STIRRUPS FOR 2ND FLOOR BEAMS
STRIPPING OF FORMWORKS
INSTALLATION OF FORMWORKS FOR MAIN STAIR
INSTALLATION OF FORMWORKS FOR 3RD FLOOR SLAB
1- WEEK LOOK AHEAD