Project DSUEP(W1)

SN Description Progress time line


1 Survey 100%
2 Soil Investigation 100%
3 Civil(Design & Approval) 60%
4 Electrical(Design & Approval) 60%
5 Installation 0%
6 over all 15% 85%

Legend
Complete
Process
Yet to start
Progress time line
100%
100%
40%
40%
0%
85%
Project time line
Distribution system upgrade and expansion project(W1)

2022 2023 2024 2025


S.N Description AUG SEPT OCT NOV DEC JAN FEB MAC APR MAY JUN JULY AUG SEP OCT NOV DEC JAN FEB MAC APR MAY JUN JULY AUG SEP OCT NOV DEC JAN FEB MAC
1 Effective date for contract
2 Establishment of office
3 Mobilisation of site team
4 finalisation of survey
5 finalisation of civil sub contractor
6 finalisation of Elc sub contractor
7 Soil investigation
8 11 kv route survey approval
9 Civil Design
9.1 CRB,SQ,Office building,Guard house
9.2 Boundary
9.2 Equipment foundation drawing
9.4 Ganitary tower and beam
10 Electrical design
10.1 SLD
10.2 Electrical layout,plan
10.3 Earthing details
10.4 EKD
10.5 Cable schedule
11 Supply of equipment
12 Excecution of works
13 Precommisioning & testing
14 Handover to NEA