Professional Documents
Culture Documents
The purpose of this method statement is to outline the general requirements and precautionary description of
the foundation works for signboard.
SCOPE OF WORK
The scope of work covers the procedures for carrying out all the civil works such as survey works, excavation,
base-preparation, compaction, blinding, shuttering works, re-bar works, concreting, application of weather
proof coating for the casting of signboard foundation
1.4 FOUNDATION
Shuttering & rebar work for the footing will be carried out on top of blinding.
Installed rebar and shutter will be inspected and after approval concrete will be poured.
Concrete must be an approved mix design.
Concrete will be delivered to site in trucks from Ready mix plant approved and concrete pump will be
used for pouring of concrete at site.
Concrete temperature shall not exceed 30C whilst slump as per the approved mix design
Cube samples shall be tested for compressive strength at independent third party laboratory, 1 for 7
days, 2 for 28 days and 1 for w/c.
After concrete protection, the area will be backfilled in layers with proper compaction using jumping
compactor and 3-ton roller. Compaction test will be carried out as required.
2. HOURS OF WORK
The work will be executed during day light only, six days a week as per approval and instruction from
ALBA.
Work will extend beyond above-mentioned time and on holidays only in special circumstances with
the approval of ALBA.
3. PERSONNEL
S.No Designation No.
1 PROJECT MANAGER
2 PROJECT ENGINEER
3 HSE MANAGER
4 SAFETY OFFICER
5 QUALITY CONTROL ENGINEER
6 SITE SUPERVISOR
7 FOREMAN
8 SURVEYOR
9 CARPENTER
10 STEEL FIXER
11 MASON
12 HELPER
13 FLAG MAN
14 PERMIT HOLDER/RECEIVER
15 EQUIPMENT OPERATORS
16 FIRE WATCHER
4. EQUIPMENT
S.No Equipment QTY
1 JCB
2 Dump Truck
3 3 Ton Roller
4 Jumping Compactor
5 Concrete Vibrator
6 Hand Tools
7 Concrete Truck
8 Concrete Pump
9 Jackhammer
10 Power Generator
11 Survey Instrument
12 Water Tanker