Professional Documents
Culture Documents
SISTEM KEPUTUSAN
KELOMPOK 1
AHMAD RIFQI ANDA : (6032222137)
1 0 3 0 3 0 CRITICAL
2 0 7 2 9 2
3 3 5 3 5 0 CRITICAL
Project Completion Time :
15 Weeks
4 7 12 9 14 2
5 5 11 5 11 0 CRITICAL
6 12 13 14 15 2
7 11 15 11 15 0 CRITICAL
ANSWER 2
Gantt Chart
QUESTION 3
Construct a Gantt chart and
Project Network
ANSWER 3
Activities ES EF LS LF Slack
1 0 4 0 4 0 CRITICAL
2 0 7 1 8 1
3 4 12 4 12 0 CRITICAL
4 4 7 14 17 10
5 7 16 8 17 1
6 12 17 12 17 0 CRITICAL
7 12 14 21 23 9
8 17 23 17 23 0 CRITICAL
9 7 12 18 23 11
Gantt Chart
QUESTION 10
A farm owner is going to erect a maintenance building with a connecting
electrical generator and water tank. The activities, activity descriptions,
and estimated durations are given in the following table :
(Notice that the activities are defined not by node numbers by activity
description. This alternative form expressing activities and precedence
relationship is often used in CPM/PERT). Construct the network for this
project, identify the critical path, and determine the project duration time.
ANSWER 10
Project Network
ANSWER 10
Activities ES EF LS LF Slack
a 0 2 0 2 0 CRITICAL
b 2 8 2 8 0 CRITICAL
c 2 6 4 8 2
d 2 4 6 8 4
e 8 12 9 13 1
f 8 13 8 13 0 CRITICAL
g 8 11 12 15 4
h 13 15 13 15 0 CRITICAL
ANSWER 10
Gantt Chart
4 weeks 2 weeks
d g
2 weeks
1 week
c e
a b f h
0 2 8 10 13 15 weeks
QUESTION 12
The Farmer's American Bank of Leesburg is planning to
install a new computerized accounts system. Bank
management has determined the activities required to
complete the project, the precedence relationships of the
activities, and activity time estimates, as shown in the
following table :
Determine the expected
project completion time
and variance and
determine the probality
that the project will be
completed in 40 weeks or
less.
ANSWER 12
Project Network
ANSWER 12
Time Estimates
Activity Expected Time Varians Schedule
Activities Activity Description (Weeks) Slack
Predecessor
a m b t = (a+4m+b)/6 σ2 = ((b-a)/6)2 ES EF LS LF
b System Development - 3 12 15 11 4 0 11 7 18 7
c System Training a 4 7 10 7 1 9 16 11 18 2
Preliminary System
f b, c 1 4 13 5 4 16 21 26 31 10
Changeover
Computer-Personnel
g d, e 3 6 9 6 1 19 25 19 25 0 CRITICAL
Interface
Equipment
h d, e 1 2,5 7 3 1 19 22 21 24 2
Modification
i Equipment Testing h 1 1 1 1 0 22 23 24 25 2
System Debugging
j f, g 2 2 2 2 0 25 27 31 33 6
and Isolation
Equipment
k g, i 5 8 11 8 1 25 33 25 33 0 CRITICAL
Changeover
ANSWER 12
Probability
Jane and Jim Smith are going to give a dinner party on Friday evening at 7:00 P.M. Their two children, Jerry
and Judy, are going to help them get ready. The Smiths will all get home from work and school at 4:00 P.M.
Jane and Jim have developed a project network to help them schedule their dinner preparations. Following is
a list of the activities, the precedence relationships, and the activity times involved in the project:
Develop a project network and determine the earliest and latest start and finish times, activity slack, and
critical path. Compute the probability that they will be ready by 7:00 P.M
ANSWER 19
Project Network
Critical Path : c - d - f - g -j - k - o - r
ANSWER 19
Time Estimates
Activity Expected Time Varians Schedule
Activities Activity Description (Minutes) Slack
Predecessor
a m b t = (a+4m+b)/6 σ2 = ((b-a)/6)2 ES EF LS LF
f Set Table d 10 17 25 17,17 6,25 71,00 88,17 71,00 88,17 0,00 CRITICAL
g Get Ice from Market f 5 12 18 11,83 4,69 88,17 100,00 88,17 100,00 0,00 CRITICAL
j Jim Shower and Dress g 8 10 15 10,50 1,36 100,00 110,50 100,00 110,50 0,00 CRITICAL
k Jane Shower and Dress h, i, j 20 27 40 28,00 11,11 110,50 138,50 110,50 138,50 0,00 CRITICAL
Uncork Wine/Water
l h, i, j 6 10 15 10,17 2,25 110,50 120,67 128,33 138,50 17,83
Carafes
o Cut Meat k, l 7 15 20 14,50 4,69 138,50 153,00 138,50 153,00 0,00 CRITICAL
p Heat Vegetable Dish k, l 3 4 6 4,17 0,25 138,50 142,67 156,67 160,83 18,17
q Put Out Appetaizers m 4 6 7 5,83 0,25 145,50 151,33 155,00 160,83 9,50
r Pour Champagne o 5 8 10 7,83 0,69 153,00 160,83 153,00 160,83 0,00 CRITICAL
ANSWER 19
Probability
Develop a project network and determine the critical path, the expected project duration, and
the variance. What is the probability that the project will be completed within 8 years?
ANSWER 26
Project Network
Critical Path
2 - 5 - 9 - 11 - 14 - 16
ANSWER 26
Time Estimates
Activity Expected Time Varians Schedule
Activities Activity Description (Months) Slack
Predecessor
a m b t = (a+4m+b)/6 σ2 = ((b-a)/6)2 ES EF LS LF
1 General Design - 5 10 22 11,17 8,03 0,00 11,17 4,00 15,17 4,00
2 Engine Design - 20 33 57 34,83 38,03 0,00 34,83 0,00 34,83 0,00 CRITICAL
3 Airfram Design 1 6 17 33 17,83 20,25 11,17 29,00 15,17 33,00 4,00
4 Avionic Design 1 2 8 20 9,00 9,00 11,17 20,17 19,83 28,83 8,67
5 Develop Test Engine 2 7 10 12 9,83 0,69 34,83 44,67 34,83 44,67 0,00 CRITICAL
6 Develop Test Airframe 3 8 11 18 11,67 2,78 29,00 40,67 33,00 44,67 4,00
7 Develop Interim Avionics 4 7 15 28 15,83 12,25 20,17 36,00 28,83 44,67 8,67