RE-ENGINEERING & RLA
PT. Mitra Patra Borneo
DAFTAR ISI
DAFTAR ISI .................................................................................................................................................................. 1
DAFTAR TABEL ........................................................................................................................................................... 4
EXECUTIVE SUMMARY .............................................................................................................................................. 5
1 PENDAHULUAN DAN LATAR BELAKANG ......................................................................................................... 6
1.1 Umum .......................................................................................................................................................... 6
1.2 Tujuan.......................................................................................................................................................... 7
1.3 Lingkup Pekerjaan ....................................................................................................................................... 7
2 Standar dan Regulasi ........................................................................................................................................... 8
2.1 Regulasi....................................................................................................................................................... 8
2.2 Standar / Code dan Recommended practice............................................................................................... 8
2.3 Dokumen Refrensi ....................................................................................................................................... 9
3 METODOLOGI ................................................................................................................................................... 10
3.1 Pengumpulan Data .................................................................................................................................... 11
3.2 Data Teknis ............................................................................................................................................... 12
3.1 Parameter Teknis ...................................................................................................................................... 13
3.2 Perhitungan Engineering ........................................................................................................................... 14
3.2.1 Piping system ............................................................................................................................... 14
3.3 Mekanisme Kegagalan .............................................................................................................................. 17
3.4 Mekanisme Kerusakan .............................................................................................................................. 18
3.5 Penentuan Mekanisme Kerusakan ............................................................................................................ 21
3.6 Analisa Resiko ........................................................................................................................................... 23
3.6.1 Kemungkinan Kegagalan (PoF) ................................................................................................... 23
3.6.2 Kosekuensi Kegagalan (CoF) ...................................................................................................... 24
3.6.3 Laju Kebocoran ............................................................................................................................ 25
3.6.4 Luas Kebocoran ........................................................................................................................... 26
3.6.5 Risk Level .................................................................................................................................... 27
3.7 Metode Inspeksi dan Interval Inspeksi....................................................................................................... 27
3.8 Health, Safety and Environment ................................................................................................................ 28
3.8.1 Tata Letak dan Proses keselamatan............................................................................................ 28
3.8.2 Sistem Perlindungan Anti Kebakaran .......................................................................................... 28
3.8.3 Emergency Respon Plan ............................................................................................................. 29
DAFTAR TABEL
DAFTAR GAMBAR
EXECUTIVE SUMMARY
Secara garis besar Re-Engineering Instalasi dilakukan melalui tahap sebagai berikut:
a. Melakukan peninjauan terhadap peralatan instalasi
b. Melakukan analisis teknis untuk mengetahui kondisi dan integritas peralatan.
c. Melakukan perhitungan sisa umur layan.
d. Menyediakan strategi mitigasi risiko melalui berbagai rencana inspeksi dan pemeliharaan.
Berdasarkan evaluasi terhadap fasilitas Floating Storage TK. Kapuas-118 milik PT. Mitra Patra Borneo
untuk memenuhi Persyaratan Peraturan Menteri Energi dan Sumber Daya Mineral Republik Indonesia
No. 32 tahun 2021, diperoleh kesimpulan sebagai berikut:
1. Pemilik fasilitas Instalasi adalah PT. Mitra Patra Borneo, yang beralokasi di JL.Khatulistiwa Km 4
Batu Layang, Kec.Pontianak Utara, Kota Pontianak, Kalimantan Barat (0.002775°,109.314336°).
2. Instalasi Floating Storage TK. Kapuas-118 dibangun pada tahun 1992 dengan kapasitas desain
3000 kL.
3. Floating Storage TK. Kapuas-118 masih layak beroperasi, dengan nilai sisa umur layan terendah
adalah 180 bulan (15 tahun) yaitu pada peralatan pompa (P-02).
RLA
No Equipment
Bulan Tahun
1 Piping System 312 26
2 Rotating Equipment 180 15
3 Generator Set 192 16
4. Berdasarkan hasil penilaian analisis risiko, didapat tingkat risiko Instalasi Floating Storage
TK.Kapuas-118 berada pada tingkat “Medium” dan “Medium High”.
5. Maximum Allowable Working Pressure (MAOP) instalasi perpipaan floating storage TK. Kapuas-118
tidak boleh melebihi 921 Psi atau 64,76 Kg/Cm2.
6. Floating Storage dilengkapi dengan Fire Fighting Installation, alat pemadam api ringan (APAR), alat
pemadam api besar (APAB) dengan tipe dry powder, selain itu terdapat, ball valve, check valve, dan
pressure indicator sebagai safety device pada piping system dan Venting pada setiap storage.
Instalasi Floating Storge TK. Kapuas-118 merupakan Floating Storage yang dimiliki oleh PT Mitra
Patra Borneo, yang berfungsi sebagai penampungan/penyimpanan Bahan Bakar Minyak (BBM)
Solar. Instalasi Floating Storge TK. Kapuas-118 tersebut dibangun pada tahun 1992 dengan
kapasitas tanki 3000 kL. Instalasi tersebut terdiri dari proses loading, unloading, serta penyimpanan
pada Floating Storage. Oleh karena itu, perlu dipastikan bahwa semua instalasi peralatan berfungsi
sesuai desain untuk mencapai reliability dan efisiensi.
TK.KAPUAS-118
Berdasarkan Peraturan Menteri Energi dan Sumber Daya Mineral Republik Indonesia No.32 Tahun
2021, tentang Pemeriksaan Keselamatan Instalasi dan Peralatan pada Kegiatan Usaha Minyak dan
Gas Bumi, bahwa Instalasi dan/atau peralatan yang telah melewati batas umur layan desain dapat
tetap digunakan setelah dilakukan penilaian sisa umur layan dan dinyatakan
1.2 Tujuan
▪ Tujuan dari dibuatnya dokumen ini untuk Memenuhi Persyaratan Peraturan Menteri Energi
dan Sumber Daya Mineral Republik Indonesia No. 32 tahun 2021.
▪ Sebagai bentuk tanggung jawab Pemilik Usaha dalam rangka memenuhi Prosedur
Keselamatan Usaha MIGAS
2.1 Regulasi
Peraturan Menteri Energi dan Inspeksi Teknis dan Pemeriksaan Keselamatan Instalasi dan
Sumber Daya Mineral No 32 Peralatan Pada Kegiatan Usaha Minyak dan Gas Bumi”,
1
Tahun 2021
Referensi
No Equipment
Dokumen No. Dokumen
01/ENG/3.1/P-01/FTSI-MPB/II/23
1 Rotating Equipment Re-Engineering & RLA
02/ENG/3.1/P-01/FTSI-MPB/II/23
2 Generator Set Re-Engineering & RLA 01/ENG/4.1/G-01/FTSI-MPB/II/23
3 METODOLOGI
Langkah pertama dalam memastikan integritas suatu peralatan adalah dengan mengidentifikasikan dan
memahami potensi potensi kerusakan yang dapat mengganggu fungsi dari masing – masing peralatan
itu sendiri atau bahkan dapat mengganggu fungsi dari peralatan yang ada disekitarnya. Secara garis
besar Re-Engineering Instalasi dilakukan melalui tahap sebagai berikut:
Start
Pengumpulan Data
Mekasisme Kegagalan
Analisa Resiko
Re-Engineering
Pengumpulan data dilakukan dengan site visit dengan inspeksi secara langsung pada peralatan,
inspeksi peralatan yang dilakukan antara lain adalah :
Selain pengumpulan data tersebut diatas, juga dilakukan pengamatan dan koordinasi pada pemilik
terkait lingkup fasilitas yang dimiliki. Dalam melakukan studi Re-Engineering Instalasi dengan
bantuan piranti lunak, membutuhkan data mengenai parameter design dari instalasi, yaitu
diantaranya:
1. Process Flow Diagram (PFD) Instalasi
2. Process and Instrumentation Diagram (P&ID) Instalasi
3. Datasheet peralatan (piping, pompa, Electrical, Safety Device).
4. History record atau Maintenance data record peralatan.
Apabila kebutuhan data diatas tidak terpenuhi atau tidak terlengkapi, maka akan digunakan data
asumsi yang sesuai dengan kaidah keteknikan.
Berikut data umum pada Floating Storage TK. Kapuas-118 sebagai berikut:
Adpun peralatan yang dimiliki TK. Kapuas-118 dirangkum pada tabel berikut :
PERALATAN JUMLAH
Piping System 8 Line
Rotating Equipment 2 unit
Generator Set 1 unit
Untuk mempermudah dalam proses Re-Engineering maka perlu dilakukan klasifikasi peralatan,
secara umum jenis-jenis peralatan diklasifikasikan sebagai berikut:
• Piping system
• Rotating equipment
• Generator equipment
𝑡𝑟𝑒𝑞 = 𝑡 + 𝐶𝐴
𝑃𝐷
𝑡𝑚𝑖𝑛 =
2(𝑆𝐸𝑊 + 𝑃𝑌)
Dimana:
P : Pressure design
D : outside diameter
S : stress value for material
E : quality factor
W : weld joint strength reduction factor (see ASME B31.3, Equation 3a)
Y : coefficient
t : Nilai Thickness minimum
CA : Corrosion Allowance
Setelah didaptkan nila required akan di perkirakan laju korosi dari 2 (dua) metode beriku
dibandingkan dan dipilih salah satu yang akan menghasilkan corrosion rate terbesar.
Dimana:
Tinitial : ketebalan pipa, pada lokasi yang sama dengan tactual, pada saat awal
instalasi atau pada saat dianggap adanya kondisi yang memicu
ditentukannya lingkungan korosi yang baru
Tactual : ketebalan aktual yang diukur pada saat inspeksi terakhir (terkini)
Dimana:
Tinitial : ketebalan aktual pada lokasi yang sama dengan tactual yang diukur pada
saat (satu atau lebih) periode inspeksi sebelumnya
Tactual : ketebalan aktual yang diukur pada saat inspeksi terakhir (terkini)
Berikut perhitungan laju korosi metode ke 2 (dua) menggunakan standar API 581
• Laju Korosi Terpublikasi (Published Corrosion Rate)
Laju korosi diperhitungkan dengan menggunakan metode ke-1 dan metode ke-2 dengan
pendekatan worst case scenario.
Dimana:
Tactual : ketebalan aktual yang diukur pada saat inspeksi terakhir (terkini)
Treq : ketebalan minimum yang disyaratkan, dihitung tanpa menambahkan
alokasi korosi (corrosion allowance) dan toleransi manufaktur
a. Kebocoran fluida,
b. Kerusakan lingkungan,
c. Kebakaran,
d. Ledakan,
e. Sistem mati,
f. Malfungsi,
g. Korban jiwa.
Penentuan mekanisme kerusakan mempertimbangkan beberapa faktor yaitu affected material, critical
factor dan affected unit, seperti terlihat pada gambar di bawah ini:
Damage
Mechanism
Untuk mempermudah identifikasi mekanisme kerusakan maka dapat menggunkan table screening
mekanisme kerusakan sebagai berikut:
Mekanisme kerusakan pada piping ditinjau berdasarkan tingkat corrosion pada pipa. Erosion
corrosion disebabkan oleh material abrasive dan tingkat keparahan ditentukan oleh laju alir
fluida, dan tekanan. Atmospheric corrosion disebabkan oleh kelembaban udara yang dapat
membentuk lapisan tipis liquid dipermukaan pipa. Peluang kegagalan yang dapat terjadi akibat
korosi pada piping, yaitu retak, penipisan ketebalan dan kebocoran.
Electrical equipment yang terpasang pada Floating Storage TK. Kapuas-118 yaitu Generator.
Generator rentan terhadap berbagai jenis kerusakan, beberapa hal yang perlu diperhatikan saat
pengoperasian dan perawatan seperti tekanan kerja generator, vibrasi, peningkatan temperatur,
allowable speed, grounding.
Usually
Usually
Usually
Usually
Poorly
Highly
Poorly
Highly
Poorly
Highly
Poorly
Highly
Usually
Usually
Fairly
Fairly
Fairly
Fairly
Poorly
Highly
Poorly
Highly
Fairly
Fairly
ar/t
0.02 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0.04 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0.06 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0.08 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0.10 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0.12 6 5 3 2 1 4 2 1 1 3 1 1 1 2 1 1 1 2 1 1 1 1 1 1 1
0.14 20 17 10 6 1 13 6 1 1 10 3 1 1 7 2 1 1 5 1 1 1 4 1 1 1
0.16 90 70 50 20 3 50 20 4 1 40 10 1 1 30 5 1 1 20 2 1 1 14 1 1 1
0.18 250 200 130 70 7 170 70 10 1 130 35 3 1 100 15 1 1 70 7 1 1 50 3 1 1
0.20 400 300 210 11 15 290 120 20 1 160 60 5 1 180 20 2 1 120 10 1 1 100 6 1 1
0.25 520 450 290 150 20 350 170 30 2 240 80 6 1 200 30 2 1 150 15 2 1 120 7 1 1
0.30 650 550 400 200 30 400 200 40 4 320 110 9 2 240 50 4 2 180 25 3 2 150 10 2 2
0.35 750 650 550 300 80 600 300 80 10 540 150 20 5 440 90 10 4 350 70 6 4 280 40 5 4
0.40 900 800 700 400 130 700 400 120 30 600 200 50 10 500 140 20 8 400 110 10 8 350 90 9 8
0.45 1050 900 810 500 200 800 500 160 40 700 270 60 20 600 200 30 15 500 160 20 15 400 130 20 15
Dari nilai TMFS diatas diperlukan penyesuaian dengan melihat factor Overdesign, kemudian
pengalian antara nilai TMFS dengan faktor overdesign akan menghasilkan nilai TMFS Adjust.
Dimana :
QL : Liquid discharge rute (lbs/sec)
Cd : discharge coefficient,
A : Hole cross
gc : Coefficient factor from lbf to lbm
Dimana :
Wg(sonic) : Gas discharge rate,(lbs/sec)
Cd : Discarge coefficient
A : Cross section area (in2)
Ps : Upstream pressure (psia)
M : Molecular weigh (lb/lb-mol)
R : Gas constan
Ts : Upstream temperature(oR)
Tabel 10. Persamaan luas daerah kerusakan untuk tipe liquid (API 581)
Dimana :
x : Laju kebocoran yang telah direduksi, lbs/sec.
Hidran digunakan sebagai alat penyembur fire water secara manual, hidrant telah
ditempatkan di sekitar area proses, dan terletak di sepanjang jalan raya, berjarak tidak
lebih dari 45meter dari satu sama lain. Kotak penyimpanan selang kebakaran (fire hose
box) dengan selang, nozzle, percabangan pipa, dan sambungan akan dipasang di dekat
setiap hidran atau di lokasi-lokasi strategis.
d) Alat Pemadam Api
Alat pemadam api portable dan beroda harus disediakan di lokasi-lokasi strategis di
sekitar fasilitas. Jenis alat pemadam api portable berikut harus digunakan sesuai dengan
jenis risiko:
- Untuk area di mana ada bahan mudah terbakar biasa, seperti kayu, kain, kertas,
plastik, dll. Alat pemadam harus sesuai untuk Kebakaran Kelas A dan harus berupa
bahan kimia kering.
- Untuk area di mana terdapat cairan yang mudah terbakar, minyak, gemuk, cat, dll.,
alat pemadam harus sesuai untuk kebakaran Kelas B. Ini bisa berupa bahan kimia
kering atau karbon dioksida.
- Untuk area di mana ada peralatan bertenaga listrik, alat pemadam harus memenuhi
syarat untuk kebakaran Kelas C. Ini harus karbon dioksida, dengan bahan kimia
kering sebagai pilihan kedua.
Alat pemadam harus tipe portabel atau beroda tergantung pada ukuran yang dibutuhkan. Alat pemadam
api portabel harus disediakan di dalam bangunan, sedangkan jenis roda harus disediakan di area di mana
kemungkinan kebakaran lebih besar diantisipasi.
4 HASIL INSPEKSI
4.1 Deskripsi Proses
Instalasi Floating Storage TK. Kapuas-118 merupakan Floating Storge yang dimiliki oleh PT Mitra
Patra Borneo, yang berfungsi sebagai penampungan/penyimpanan Bahan Bakar Minyak (BBM)
solar dengan kapasitas desain tangki 3000 KL Floating Storage TK. KAPUAS-118 berlokasi di
JL.Khatulistiwa Km 4 Batu Layang, Kec.Pontianak Utara, Kota Pontianak, Kalimantan Barat.
Berikut gambarat singkat proses distribusi TBBM Khatulistiwa milik PT. Mitra Patra Borneo.
TK.KAPUAS-118
Feed Floating Tank Unloading To Customer
No Dokumentasi Catatan
1. - Piping sistem Floating Storage
TK.Kapuas-118 PT. Mitra Patra Borneo
InletOutlet
Header
No Dokumentasi Catatan
3. - Kondisi pipa inlet Floating Storage
dalam kondisi baik dengan perlindungan
Inlet Floating permukaan berupa painting.
- Valve dalam kondisi baik.
Inlet Floating
Outlet Floating
Outlet Floating
Inlet Floating
Inlet Floating
Suction Starboard
Discharge
Discharge Pump
Pump
Suction Pump
No Dokumentasi Catatan
5.
Stipping Line
- line Stripping dalam kondisi baik dengan
perlindungan permukaan berupa
Hydrant Line painting
- valve dalam kondisi baik.
Stipping Line
Stipping Line
Outlet Stipping
Venting Portside
No Dokumentasi Catatan
7. - Berikut beberapa dokumentasi
pengambilan data pada Instalasi
perpipaan TK.Kapuas-118
No Dokumentasi Catatan
1. - Kondisi P-01 dengan tipe (Gear pump)
menggunakan motor diesel dengan
gear box sebagai reduce putaran.
- Kondisi Name Plate Unit pompa
masih dalam keadaan baik.
- Kondisi painting mulai memudar.
- Perlu dilakukan cleaning unit pompa dan
area R.Pump.
No Dokumentasi Catatan
2. - Kondisi P-02 dengan tipe (Centrifugal
pump) menggunakan motor diesel.
- Kondisi Name Plate Unit pompa
masih dalam keadaan baik.
- Tidak terdapat name plate motor
diesel.
- Kondisi painting mulai memudar.
- Perlu dilakukan cleaning unit pompa
dan area R.Pump.
No Dokumentasi Catatan
8. - Kondisi Generator (G-01) dalam
keadaan baik.
- Kondisi Name Plate Unit Generator
masih dalam keadaan baik.
- Filter Oli berfungsi dengan normal.
- Perlu dilakukan cleaning unit Generator
dan area R.R.Generator.
No Dokumentasi Catatan
9. - Berikut beberapa dokomentasi inspeksi
yang dilakukan pada peralatan
Generator (G-01) dan Proteksi
generator.
No Dokumentasi Catatan
1. - Berikut merupakan beberapa alat
pemadam api ringan (APAR) dan alat
Pemadam Api besar (APAB), Floating
Storage TK.Kapuas-118.
No Dokumentasi Catatan
9. - Berikut merupakan beberapa alat
pemadam api berupa Hydrant, dan
beberapa titik box pasir.
Dari hasil Analisa dan perhitungan system perpipaan Floating Storage TK.Kapuas-118 sebagai berikut:
Dariri hasil tersebut maka instalasi perpipaan Floating Storage TK.Kapuas-118 milik PT. Mitra Patra Borneo masih layak digunakan beroperasi.
INSTALASI PIPING
System Loading / Unloading
Line No. FD.05 HD.01 HD.02 VT
Dimension 3" 2" 8" 6" 6" 4"
Konstanta reduksi (a.r/t) 0,337 0,310 0,386 0,368 0,236 0,317
TMSF 2 2 4 4 1 2
Tact/Tact-CA 1,5405405 1,8 1,5128205 1,625 1,5128205 1,4444444
pof
Over Design tabel 0,5 0,5 0,5 0,5 0,5 0,5
TSMF Adjust 1 1 2 2 1 1
Kategori Kemungkinan Kegagalan PoF 2 2 2 2 2 2
1/4 inch 0,000028 0,000028 0,000008 0,000008 0,000008 0,000008
1 - - 0,00002 0,00002 0,00002 0,00002
gff
4 - - 0,000002 - - -
Repture 3E-06 3E-06 6E-07 3E-06 3E-06 3E-06
total Gff 3,1E-05 3,1E-05 3,1E-05 3,1E-05 3,1E-05 3,1E-05
1/4 inch 0,000028 0,000028 0,000008 0,000008 0,000008 0,000008
Frekuensi kegagalan 1 - - 0,00002 0,00002 0,00002 0,00002
umum 4 - - 0,000002 - - -
Repture 0,0000026 0,0000026 6E-07 2,6E-06 2,6E-06 2,6E-06
1/4 inch 0,38 0,38 0,38 0,38 0,38 0,38
cof 1 6,02 6,02 6,02 6,02 6,02 6,02
Laju kebocoran
4 - - 96,32 - - -
Repture 6,02 6,02 96,32 6,02 6,02 6,02
1/4 inch 53,94 53,94 53,94 53,94 53,94 4,60
1 654,01 654,01 654,01 654,01 654,01 69,69
Luasan Kerusakan
4 - - 7930,32 - - -
Repture 654,0 654,0 7930,3 654,0 654,0 69,7
1/4 inch 156,27 156,27 156,27 156,27 156,27 129,5
1 1843,11 1843,11 1843,11 1843,11 1843,11 1856,6
Luasan Berbahaya
4 21738,0
Repture 1843,11 1843,11 21737,97 1843,11 2166,29 168,4245
Kategori Konsekuensi Nilai Luasan 1843,11 1843,11 21737,97 1843,11 2166,29 1856,62
Kegagalan CoF Kategori D D E D D D
RISK M M MH M M M
1. Pemilik fasilitas Instalasi Floating Storage adalah PT. Mitra Patra Borneo, yang beralokasi di
JL.Khatulistiwa Km 4 Batu Layang, Kec.Pontianak Utara, Kota Pontianak, Kalimantan Barat
2. Instalasi Floating Storage TK. Kapuas-118 dibangun pada tahun 1992 dengan kapasitas desain
3000 kL.
3. Dari hasil evaluasi peralatan Instalasi TK.Kapuas-118 milik PT. Mitra Patra Borneo masih layak
beroperasi, adapun perhitungan engineering dan RLA yang dilakukan Pada instalasi
TK.Kapuas-118 milik PT. Mitra Patra Borneo sebagai berikut.
RLA
No Equipment
Bulan Tahun
1 Piping System 312 26
2 Rotating Equipment 180 15
3 Generator Set 192 16
Mayoritas damage mekanism yang terjadi pada di area instalasi adalah atmospheric corrosion,
dan mechanical corrosion.
4. Maximum Allowable Working Pressure (MAOP) sistem perpipaan tidak boleh melebihi 921 Psi
atau 64,76 Kg/Cm2.
5. Berdasarkan hasil penilaian analisis risiko, didapat tingkat risiko Instalasi Floating Storage
TK.Kapuas-118 berada pada tingkat “Medium” dan “Medium High”.
6. Floating Storage dilengkapi dengan Fire Fighting Installation, alat pemadam api ringan (APAR),
Alat Pemadam Api Besar (APAB) dengan tipe dry powder, selain itu terdapat, ball valve, check
valve, dan pressure indicator sebagai safety device pada piping system dan Venting pada tiap
storage.
7. Safety sign sudah terpasng dengan baik di floating storage, dan Prosedur kegatan sudah
terpasang di area Floating storage TK. Kapuas-118.
6.2 Rekomendasi
Berdasarkan analisis risiko instalasi, untuk keamanan operasi, berikut ini adalah rekomendasi yang
perlu dilakukan:
1. Melakukan perawatan secara rutin terkait peralatan dan keselamatan kerja dengan periode
inspeksi yang telah di tentukan pada masing-masing peralatan serta mendokumentasikannya
sesuai tabel 12. Metode Inspeksi
2. Melakukan pencatatan pada saat pemeliharaan peralatan dan kegagalan yang terjadi selama
peralatan beroperasi.
3. Melakukan seluruh rekomendasi yang tercantum pada RLA Peralatan (Peralatan putar,
peralatan dan Generator)
4. Lakukan pemasangan taging atau nameplate pada setiap peralatan.
LAMPIRAN 1
Piping Calculation
Risk Level
PIPING CALCULATION
Minimum Thickness
acc. ASME B31.3, Eq. (3a)
Thickness required tm = P * dext / ( 2* (s allow * E + P* Y) )
= 0,0716 inch
= 1,8196 mm
= tm + CA mm
= 3,82 mm
PIPING CALCULATION
Minimum Thickness
acc. ASME B31.3, Eq. (3a)
Thickness required tm = P * dext / ( 2* (s allow * E + P* Y) )
= 0,0545 inch
= 1,3845 mm
= tm + CA mm
= 3,38 mm
PIPING CALCULATION
Minimum Thickness
acc. ASME B31.3, Eq. (3a)
Thickness required tm = P * dext / ( 2* (s allow * E + P* Y) )
= 0,0710 inch
= 1,8025 mm
= tm + CA mm
= 3,80 mm
PIPING CALCULATION
Minimum Thickness
acc. ASME B31.3, Eq. (3a)
Thickness required tm = P * dext / ( 2* (s allow * E + P* Y) )
= 0,0545 inch
= 1,3845 mm
= tm + CA mm
= 3,38 mm
PIPING CALCULATION
Minimum Thickness
acc. ASME B31.3, Eq. (3a)
Thickness required tm = P * dext / ( 2* (s allow * E + P* Y) )
= 0,0545 inch
= 1,3845 mm
= tm + CA mm
= 3,38 mm
PIPING CALCULATION
Minimum Thickness
acc. ASME B31.3, Eq. (3a)
Thickness required tm = P * dext / ( 2* (s allow * E + P* Y) )
= 0,0545 inch
= 1,3845 mm
= tm + CA mm
= 3,38 mm
PIPING CALCULATION
Minimum Thickness
acc. ASME B31.3, Eq. (3a)
Thickness required tm = P * dext / ( 2* (s allow * E + P* Y) )
= 0,0288 inch
= 0,7314 mm
= tm + CA mm
= 2,73 mm
PIPING CALCULATION
Minimum Thickness
acc. ASME B31.3, Eq. (3a)
Thickness required tm = P * dext / ( 2* (s allow * E + P* Y) )
= 0,0195 inch
= 0,4963 mm
= tm + CA mm
= 2,50 mm
PIPING CALCULATION
Minimum Thickness
acc. ASME B31.3, Eq. (3a)
Thickness required tm = P * dext / ( 2* (s allow * E + P* Y) )
= 0,0710 inch
= 1,8025 mm
= tm + CA mm
= 3,80 mm
PIPING CALCULATION
Minimum Thickness
acc. ASME B31.3, Eq. (3a)
Thickness required tm = P * dext / ( 2* (s allow * E + P* Y) )
= 0,0545 inch
= 1,3845 mm
= tm + CA mm
= 3,38 mm
PIPING CALCULATION
Minimum Thickness
acc. ASME B31.3, Eq. (3a)
Thickness required tm = P * dext / ( 2* (s allow * E + P* Y) )
= 0,0545 inch
= 1,3845 mm
= tm + CA mm
= 3,38 mm
PIPING CALCULATION
Minimum Thickness
acc. ASME B31.3, Eq. (3a)
Thickness required tm = P * dext / ( 2* (s allow * E + P* Y) )
= 0,0370 inch
= 0,9404 mm
= tm + CA mm
= 2,94 mm
LAMPIRAN 2
Drawing General Arrangement
Safety Layout
Escape Plan
Process Flow Diagram (PFD)
Piping & Instrumentation Diagram (PID)
A A
B B
C C
D D
E E
F F
G G
H H
TK.KAPUAS-118 I
J J
K K
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A A
B B
C C
D D
E E
F F
G G
H H
TK.KAPUAS-118 I
J J
K K
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A A
B B
C C
D D
E E
F F
G G
H H
TK.KAPUAS-118 I
J J
K K
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A A
B B
C C
0
0
D D
E E
F F
G G
H H
TK.KAPUAS-118 I
J J
K K
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A A
B B
C C
D D
E E
F F
G G
H H
TK.KAPUAS-118 I
J J
K K
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A A
B B
C C
D D
E E
F F
G G
H H
TK.KAPUAS-118 I
J J
K K
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A A
B B
C C
D D
E E
F F
G G
H H
TK.KAPUAS-118 I
J J
K K
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A A
B B
C C
D D
E E
F F
G G
H H
TK.KAPUAS-118 I
J J
K K
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A A
B B
C C
D D
E E
F F
G G
H H
TK.KAPUAS-118 I
J J
K K
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A A
B B
C C
D D
E E
F F
G G
H H
TK.KAPUAS-118 I
J J
K K
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A A
B B
C C
D D
E E
F F
G G
H H
TK.KAPUAS-118 I
J J
K K
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A A
B B
C C
D D
E E
F F
G G
H H
TK.KAPUAS-118 I
J J
K K
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A A
B B
C C
D D
E E
F F
G G
H H
TK.KAPUAS-118 I
J J
K K
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
RE-ENGINEERING & RLA
FLOATING STORAGE TBBM KHATULISTIWA
SIANTAN KALBAR
INSTALLATION Date : 25 Februari 2022 Rev. : 0
TK.KAPUAS-118 No. Report : 01/ENG/7/INST-01/FTSI-MPB/II/23 Page 64 of 65
LAMPIRAN 3
Report Re-Engineering & RLA Pompa
(01/RLA/3.1/P-01/FTSI-MPB/II/23 dan 02/RLA/3.1/P-02/FTSI-MPB/II/23)
LAMPIRAN 4
Report Re-Engineering & RLA Generator
(01/ENG/4.1/G-01/FTSI-MPB/II/23).