Activity Start Date End Date Duration Status

Site selection/ Drawing development 01-Jan 05-Jan 5 Complete


Grading & Site prepration/Material procurement 06-Jan 07-Jan 2 Complete
Foundation Layout( Excavation-construction) 07-Jan 12-Jan 6 Pending
Plinth Construction 10-Jan 12-Jan 3 Complete
Wall Construction 12-Jan 20-Jan 9 Pending
Wall Curing 20-Jan 22-Jan 3 Complete
Roof Construction 23-Jan 26-Jan 4 Complete
Floor Construction 21-Jan 23-Jan 3 pending
Wall Plastering 23-Jan 27-Jan 5 Complete
Wall Painting 27-Jan 29-Jan 3 Complete