You are on page 1of 304

QUANTITY SURVEY NOTES

INDEX:
SUB – STRUCTURE (CONCRETE PART)
1. INTRODUCTION
2. THE BASICS
3. FOOTING
4. FOOTING PCC
5. NECK COLUMN
6. TIE BEAM
7. TIE BEAM PCC
8. PLINTH BEAM
9. PLINTH BEAM PCC
10. GRADE SLAB
11. RETAINING WALL
12. RECTANGULAR SUMP
13. EXCAVATION & BACKFILL
14. SUB – STRUCTURE ABSTRACT
15. BOQ OF SUB – STRUCTURE

SUPER – STRUCTURE (CONCRETE PART)


16. FLOOR COLUMN
17. FLOOR BEAM
18. SLAB
19. STAIRCASE
20. BRICKWORK
21. PLASTERING
22. WALL PUTTY
23. PAINT
24. FLOORING
25. FALSE CEILING
26. DOORS & WINDOWS
27. LINTELS
28. SUPER – STRUCTURE ABSTRACT - 1
29. SUPER – STRUCTURE ABSTRACT - 2
30. BOQ OF SUPER – STRUCTURE

31. BAR BENDING SCHEDULE

SHAZEB NOMAN 1
QUANTITY SURVEY NOTES

SUB – STRUCTURE (REINFORCEMENT PART)


32. FOOTING
33. NECK COLUMN
34. TIE BEAM
35. PLINTH BEAM
36. GRADE SLAB
37. RETAINING WALL
38. RECTANGULAR SUMP
39. SUB – STRUCTURE ABSTRACT
40. BOQ OF SUB – STRUCTURE

SUPER – STRUCTURE (REINFORCEMENT PART)


41. FLOOR COLUMN
42. FLOOR BEAM
43. SLAB
44. STAIRCASE
45. SUPER – STRUCTURE REINFORCEMENT ABSTRACT
46. BOQ OF SUPER – STRUCTURE REINFORCEMENT
47. COMPLETE BILL OF QUANTITY OF SAMPLE PROJECT

SHAZEB NOMAN 2
QUANTITY SURVEY NOTES

1. QUANTITY SURVEY: IT IS A PROCESS IN WHICH, QUANTITIES OF ALL THE CONSTRUCTION


MATERIALS ARE ESTIMATED AND COST OF THE PROJECT IS DERIVED.

100 BAGS OF CEMENT

GRADE 43 CEMENT AMBUJA BRAND

450 RS MARKET VALUE

COSTING

SHAZEB NOMAN 3
QUANTITY SURVEY NOTES

2.BASIC EXECUTION PROCESS:

SHAZEB NOMAN 4
QUANTITY SURVEY NOTES

SHAZEB NOMAN 5
QUANTITY SURVEY NOTES

TYPES OF FOOTINGS :
1. PLAIN FOOTING:

2. STEP FOOTING :

3. ISOLATED/STRIP/TAPERED FOOTING :

SHAZEB NOMAN 6
QUANTITY SURVEY NOTES

4. PLAIN COMBINED FOOTING:

5. ISOLATED COMBINED FOOTING :

6.STRAP FOOTING OR NEIGHBOR FOOTING OR SHOE FOOTING:

SHAZEB NOMAN 7
QUANTITY SURVEY NOTES

7. RAFT FOOTING :

8. PILE FOOTING :

SHAZEB NOMAN 8
QUANTITY SURVEY NOTES

TYPES OF COLUMNS:
1. SQUARE COLUMN OR RECTANGULAR COLUMN
2. CIRCULAR COLUMN
3. “L” TYPE COLUMN
4. “T” TYPE COLUMN
5.”V” TYPE COLUMN
6. HEXAGON TYPE COLUMN
7. ARCH TYPE COLUMN
8.”Y” TYPE COLUMN:
9. “Y” TYPE COLUMN WITH ARCH

TYPES OF FLOORS :
1. BASEMENT FLOOR: the floor which is constructed below ground level for store rooms or mechanical room or
parking is called as basement floor.

2. PODIUM FLOOR: the floor which is constructed either below ground level or above ground level, especially for car
parking is called as podium floor.

3. GROUND FLOOR: the floor which is constructed on ground level is called as ground floor.

4. MEZZANINE FLOOR: the floor which is constructed between ground and first floor is called as mezzanine floor. this
type of floor is constructed for services of building, shops & offices, to provide facilities for the occupants who are
living in high-rise buildings. For proper ventilation the ceiling height of floor is increase 1metre more than the normal
ceiling height.

5. FIRST FLOOR: the floor which is constructed above ground floor or above mezzanine floor is called as first floor.

6. TYPICAL FLOOR: typical floor is nothing but repeated floor. The plan which is design for ground floor and want to
have the same plan for other floors, then these floors are called as typical floor-1 or typical floor-2, etc.

7. HELIPAD: the floor which is constructed above roof floor and which is used for landing of helicopter or taking off of
helicopter is called as helipad.

SHAZEB NOMAN 9
QUANTITY SURVEY NOTES

TYPES OF BEAMS:
1. TIE BEAM
2. STRAP BEAM
3. PLINTH BEAM
4. DROP BEAM ORO INVERTED BEAM
5. CONCEALED BEAM
6. CANTILEVER BEAM

TYPES OF SLABS:
1. CONVENTIONAL SLAB
(I)ONE-WAY SLAB
(II)TWO WAYS SLAB

SHAZEB NOMAN 10
QUANTITY SURVEY NOTES

2. HARDY OR HORDY SLAB

3. WAFFLE SLAB

4. DOME SLAB

SHAZEB NOMAN 11
QUANTITY SURVEY NOTES

5. PITCH ROOF

6. PROJECTED SLAB OR PORTICO SLAB

7. PRE-STRESSED SLAB

SHAZEB NOMAN 12
QUANTITY SURVEY NOTES

8. CABLE SUSPENSION SLAB

9. SLAB WITH ARCHES

10. GRADE SLAB

SHAZEB NOMAN 13
QUANTITY SURVEY NOTES

11. HOLLOW-CORE RIBBED SLAB

12. SUNKEN-SLAB OR DEPRESSED SLAB

SHAZEB NOMAN 14
QUANTITY SURVEY NOTES

TYPES OF WALLS :
1. BRICK MASONRY WALL

2. COURSE RUBBLE STONE MASONRY WALL OR C.R.S WALL

3. RANDOM RUBBLE STONE MASONRY WALL OR R.R.S WALL.

SHAZEB NOMAN 15
QUANTITY SURVEY NOTES

4. RETAINING WALL

5. SHEAR WALL

6. CURTAIN WALL

SHAZEB NOMAN 16
QUANTITY SURVEY NOTES

7. PRE-CAST WALL

8. PARAPET WALL

9. COMPOUND OR BOUNDARY WALL

SHAZEB NOMAN 17
QUANTITY SURVEY NOTES

10. DROP WALL

11. PARTITION WALL

12. LOAD BEARING WALL

SHAZEB NOMAN 18
QUANTITY SURVEY NOTES

TYPES OF STAIR CASES : stairs can be broadly classified into three types

1. STRAIGHT STAIRS
2. TURNING STAIRS
3. CONTINUOUS STAIRS

1. STRAIGHT STAIRS: generally for small houses, available width is very retractable. So, this type of straight stairs are
used in such conditions which runs straight between two floors. This stair may consists of either one single flight or
more than one flight with a landing.

STRAIGHT STAIRS

2. TURNING STAIRS: turning stairs are sub classified as:

A) QUARTER TURN STAIRS


B) HALF TURN STAIRS ( DOG LEGGED STAIRS)
C) THREE – QUARTER TURN STAIRS
D) BIFURCATED STAIRS

A) QUARTER TURN STAIRS: a quarter turn stair is the one which changes its direction either to the right or to the left
but where the turn being affected either by introducing a quarter space landing or by providing winders. In these
type of stairs the flight of stair turns 90 degrees art landing as it rises to connect two different levels. So it is also
called as l-stair.

QUARTER TURN STAIRS

SHAZEB NOMAN 19
QUANTITY SURVEY NOTES

B) HALF TURN STAIRS:

In case of half turn stairs its direction reversed, or changed for 180o. Such stairs are quite common.

GEOMETRICAL HALF TURN STAIRS

C) THREE QUARTER TURN STAIRS:

The direction of stairs changed three times with its upper flight crossing the bottom one in the case of three quarter
turn stairs. These stairs are may either be newel or open newel type. This type stairs are generally used when the
vertical distance between two floors is more and as well as length of the stair room is limited.

THREE QUARTER TURN STAIRS

D) BIFURCATED STAIRS:

Bifurcated stairs are commonly used in public building at their entrance hall. This has a wider flight at the bottom,
which bifurcates into two narrower flights, one turning to the left and other to the right, at landing. it may be either
of newel type with a newel post or of geometrical type with continuous stringer and hand rails.

BIFURCATED STAIRS

SHAZEB NOMAN 20
QUANTITY SURVEY NOTES

3. CONTINUOUS STAIRS:
This type of stairs neither have any landing nor any intermediate newel post. They are geometric in shape. These are
may be of following types.

CIRCULAR STAIRS
SPIRAL STAIRS
HELICAL STAIRS

CIRCULAR STAIRS OR SPIRAL STAIRS: are usually made either of r.c.c or metal, and is placed at a location
where there are space limitations. Sometimes these are also used as emergency stairs, and are provided at
the back side of a building. These are not comfortable because of all the steps are winders and provides
discomfort.

SPIRAL STAIRS: a helical stair looks very fine but its structural design and construction is very complicated. It
is made of r.c.c in which a large portion of steel is required to resist bending, shear and torsion.

HELICAL STAIRS: looks very fine but its structural design and construction is very complicated. It is made of
r.c.c in which a large portion of steel is required to resist bending, shear and torsion.

CONTINOUS STAIRS

SHAZEB NOMAN 21
QUANTITY SURVEY NOTES

UNIT CONVERSION:

UNIT CONVERSIONS
1 METER = 1000 MM
1 METER = 100 CM
1 CM = 10 MM
1 METER = 1.0936 YD
1 METER = 3.28 FT
1 METER = 39.37 INCH”
1 FEET = 12 INCH”
1 INCH” = 2.542 CM
1 INCH” = 25.42 MM
1 YARD = 36 INCH”
1 YARD = 3 FEET
1YD 2
= 9 SQF
1 ACRE = 4840 YD2
1 HECTARE = 2.47 ACRE

SHAZEB NOMAN 22
QUANTITY SURVEY NOTES

EXAMPLE PROBLEMS:

1. 10m =? fts
1m = 3.28 ft
So 10 * 3.28 = 32.8 ft

2. 10m2 =? fts2
1m = 3.28 ft
So 10 * 3.282 = 107.639 ft2

3. 10m3 =? fts3
1m = 3.28 ft
So 10 * 3.283 = 353.146 ft3

4. 10ft =? m
1m = 3.28 ft
So 10 / 3.28 = 3.048 m

5. 10ft2 =? m2
1m = 3.28 ft
So 10 / 3.282 = 0.929 m2

6. 10m3 =? fts3
1m = 3.28 ft
So 10 / 3.283 = 0.283 m3

SHAZEB NOMAN 23
QUANTITY SURVEY NOTES

FORMULAS :

SHAZEB NOMAN 24
QUANTITY SURVEY NOTES

3. FOOTING CALCULATIONS: FOOTING - 1

LENGTH= 1.2m
WIDTH= 1.4m
DEPTH= 0.45m

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 1.2 * 1.4 * 0.45 m3
= 0.756 m3
FOUR SIDE AREA = (LENGTH * DEPTH) + (WIDTH * DEPTH) + (LENGTH * DEPTH) + (WIDTH * DEPTH) m2
= (LENGTH * DEPTH) * 2 + (WIDTH * DEPTH) * 2 m2
= (LENGTH + WIDTH) * 2 * DEPTH m2

2. SHUTTERING AREA = (LENGTH +WIDTH) * 2 * DEPTH m2


= ( PERIPHERAL AREA OF FOOTING) m2
= (1.2 +1.4) * 2 * 0.45 m2
= 2.34 m2

3. BITUMEN PAINT AREA ={ (LENGTH +WIDTH) * 2 * DEPTH + ( LENGTH * WIDTH ) M2


= (PERIPHERAL AREA OF FOOTING) +(TOP AREA OF FOOTING) m2
= {(2.34) + (1.2 * 1.4) m2
= 4.02 m2

SHAZEB NOMAN 25
QUANTITY SURVEY NOTES

1.1.FOOTING CALCULATIONS: FOOTING - 2

LENGTH= 1.2m
WIDTH= 1.5m
DEPTH= 0.45m

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 1.2 * 1.5 * 0.45 m3
= 0.81 m3

2. SHUTTERING AREA = (LENGTH +WIDTH) * 2 * DEPTH m2


= ( PERIPHERAL AREA OF FOOTING) m2
= (1.2 +1.5) * 2 * 0.45 m2
= 2.43 m2

3 BITUMEN PAINT AREA ={ (LENGTH +WIDTH) * 2 * DEPTH + ( LENGTH * WIDTH ) m2


= (PERIPHERAL AREA OF FOOTING) +(TOP AREA OF FOOTING ) m2
= {(2.43) + (1.2 * 1.5) m2
= 4.23 m2

SHAZEB NOMAN 26
QUANTITY SURVEY NOTES

4. FOOTING PCC CALCULATIONS: FOOTING - 1

NOTE:
LENGTH = FOOTING LENGTH + 0.1.+ 0.1m
WIDTH = FOOTING WIDTH + 0.1.+ 0.1m
DEPTH = 0.1

LENGTH= 1.2 + 0.1 + 0.1 = 1.4m


WIDTH= 1.4 + 0.1+ 0.1 = 1.6m
DEPTH= 0.1m

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH M3


= 1.4 * 1.6 * 0.1 m3
= 0.224 m3

2. SHUTTERING AREA = (LENGTH +WIDTH) * 2 * DEPTH m2


= ( PERIPHERAL AREA OF FOOTING) m2S
= (1.4 +1.6) * 2 * 0.1 m2
= 0.6 m2

SHAZEB NOMAN 27
QUANTITY SURVEY NOTES

3. BITUMEN PAINT AREA ={ (LENGTH +WIDTH) * 2 * DEPTH + ( LENGTH * WIDTH ) m2


= (PERIPHERAL AREA OF FOOTING PCC) +(TOP AREA OF FOOTING PCC) m2
= {(0.6) + (1.4 * 1.6) m2
= 2.84 m2

4. POLYTHENE SHEET = LENGTH * WIDTH m2


= 1.4 * 1.6 m2
= 2.24 m2

5. TERMITE CONTROL= LENGTH * WIDTH m2


= 1.4 * 1.6 m2
= 2.24 m2

SHAZEB NOMAN 28
QUANTITY SURVEY NOTES

5. NECK COLUMN CALCULATIONS:

LENGTH= 0.3 M,

WIDTH= 0.3 M

DEPTH= 1.65 M

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 0.3 * 0.3 * 1.65 m3
= 0.149 m3

2. SHUTTERING AREA = (LENGTH +WIDTH) * 2 * DEPTH m2


= (PERIPHERAL AREA OF NECK COLUMN) m2
= (0.3 +0.3) * 2 * 1.65 m2
= 1.98 m2

3. BITUMEN PAINT AREA = (LENGTH +WIDTH) * 2 * DEPTH m2


= (PERIPHERAL AREA OF NECK COLUMN) m2
= 1.98 m2

SHAZEB NOMAN 29
QUANTITY SURVEY NOTES

6. TIE BEAM CALCULATIONS:

SHAZEB NOMAN 30
QUANTITY SURVEY NOTES

LENGTH= 3.45m

WIDTH= 0.3m

DEPTH= 0.3m

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 3.45 * 0.3 * 0.3 m3
= 0.31 m3

2. SHUTTERING AREA = (LENGTH * DEPTH) * 2 m2


= (3.45 * 0.3) * 2 m2
= 2.07 m2

3. BITUMEN PAINT AREA = (LENGTH * DEPTH) * 2 + (LENGTH * WIDTH) m2


= (3.45 * 0.3) * 2 + (3.45 * 0.3) m2
= 3.11 m2

SHAZEB NOMAN 31
QUANTITY SURVEY NOTES

7. TIE BEAM PCC CALCULATIONS:

SHAZEB NOMAN 32
QUANTITY SURVEY NOTES

NOTE:

LENGTH = TIE BEAM LENGTH - 0.1 - 0.1

WIDTH = TIE BEAM WIDTH + 0.1 + 0.1

DEPTH = 0.1

LENGTH= 3.45-0.1-0.1=3.25 M,

WIDTH= 0.3+0.1+0.1=0.5 M

DEPTH= 0.1 M

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 3.25 * 0.5 * 0.1 m3
= 0.16 m3

2. SHUTTERING AREA = (LENGTH * DEPTH) * 2 m2


= (3.25 * 0.1) * 2 m2
= 0.65 m2

3. BITUMEN PAINT AREA = (LENGTH * DEPTH) * 2 + (LENGTH * WIDTH) m2


= (3.25 * 0.1) * 2 + (3.25 * 0.5) m2
= 2.28 m2

4. POLYTHENE SHEET AREA = (LENGTH * WIDTH) m2


= (3.25 * 0.45) m2
= 1.63 m2

5. TERMITE CONTROL AREA = (LENGTH * WIDTH) m2


= (3.25 * 0.5) m2
= 1.63 m2

SHAZEB NOMAN 33
QUANTITY SURVEY NOTES

8. PLINTH BEAM CALCULATIONS:

LENGTH= 4.35 M,

WIDTH= 0.3 M

DEPTH= 0.3 M

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 4.35 * 0.3 * 0.3m3
= 0.39 m3

2. SHUTTERING AREA = (LENGTH * DEPTH) * 2 m2


= (4.35 * 0.3) * 2 m2
= 2.61 m2

3. BITUMEN PAINT AREA = (LENGTH * DEPTH) * 2 + (LENGTH * WIDTH) m2


= (4.35 * 0.3) * 2 + (4.35 * 0.3) m2
= 3.92 m2

SHAZEB NOMAN 34
QUANTITY SURVEY NOTES

9. PLINTH BEAM PCC CALCULATIONS:

SHAZEB NOMAN 35
QUANTITY SURVEY NOTES

NOTE:

LENGTH = PLINTH BEAM LENGTH

WIDTH = PLINTH BEAM WIDTH + 0.1 + 0.1

DEPTH = 0.1

LENGTH= 4.35 M,

WIDTH= 0.3+0.1+0.1=0.5 M

DEPTH= 0.1 M

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 4.35 * 0.5 * 0.1 m3
= 0.22 m3

2. SHUTTERING AREA = (LENGTH * DEPTH) * 2 m2


= (4.35 * 0.1) * 2 m2
= 0.87 m2

3. BITUMEN PAINT AREA = (LENGTH * DEPTH) * 2 + (LENGTH * WIDTH) m2


= (4.35 * 0.1) * 2 + (4.35 * 0.5) m2
= 3.05 m2

4. POLYTHENE SHEET AREA = (LENGTH * WIDTH) m2


= (4.35 * 0.5) m2
= 2.18 m2
5. TERMITE CONTROL AREA = (LENGTH * WIDTH) m2
= (4.35 * 0.5) m2
= 2.18 m2

SHAZEB NOMAN 36
QUANTITY SURVEY NOTES

10. GRADE SLAB CALCULATIONS:

LENGTH= 4.45 M,

WIDTH= 3.4 M

DEPTH= 0.1 M

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 4.45 * 3.4 * 0.1 m3
= 1.51 m3

2. POLYTHENE SHEET AREA = (LENGTH * WIDTH) m2


= (4.45 * 3.4) m2
= 15.13 m2

3. TERMITE CONTROL AREA = (LENGTH * WIDTH) m2


= (4.45 * 3.4) m2
= 15.13 m2

SHAZEB NOMAN 37
QUANTITY SURVEY NOTES

11. RETAINING WALL CALCULATIONS:

SHAZEB NOMAN 38
QUANTITY SURVEY NOTES

PART-1

LENGTH= 4.35 M,

WIDTH= 1.25M

WALL THICKNESS= 0.2 M

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 4.35 * 1.25 * 0.2 m3
= 1.09 m3

2. SHUTTERING AREA = (LENGTH * WIDTH) * 2 m2


= (4.35 * 1.25) * 2 m2
= 10.88 m2

3. BITUMEN PAINT AREA = (LENGTH * WIDTH) m2


= (4.35 * 1.25) m2
= 5.44 m2

PART-2

LENGTH= 3.45 M,

WIDTH= 0.15M

WALL THICKNESS= 0.2 M

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 3.45 * 0.15 * 0.2 m3
= 0.1 m3

2. SHUTTERING AREA = (LENGTH * WIDTH) * 2 m2


= (3.45 * 0.15) * 2 m2
= 1.04 m2

3. BITUMEN PAINT AREA = (LENGTH * WIDTH) m2


= (3.45 * 0.15) m2
= 0.52 m2

SHAZEB NOMAN 39
QUANTITY SURVEY NOTES

12. RECTANGULAR SUMP CALCULATIONS:

SHAZEB NOMAN 40
QUANTITY SURVEY NOTES

1. TOP SLAB:

LENGTH= 4 M,
WIDTH= 3 M
DEPTH= 0.2 M

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 4 * 3 * 0.2 m3
= 2.4 m3

2. SHUTTERING AREA ={ ((LENGTH + WIDTH)*2*DEPTH) + (LENGTH * WIDTH) +


((LENGTH + WIDTH)*2*DEPTH) }m2
= {((4 + 3) * 2 * 0.2) + (3.6 * 2.6) + ((0.5 + 0.5) * 2 * 0.2)} m2
= 12.56 m2

3. BITUMEN PAINT AREA = ((LENGTH + WIDTH) * 2 * DEPTH) m2


= ((4 + 3) * 2 * 0.2) m2
= 2.8 m2

SHAZEB NOMAN 41
QUANTITY SURVEY NOTES

2. DEDUCTION OF MANHOLE:
LENGTH = 0.5
WIDTH = 0.5
DEPTH = 0.2

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 0.5 * 0.5 * 0.2 m3
= - 0.05 m3

2. SHUTTERING AREA = (LENGTH * WIDTH) m2


= (0.5 * 0.5) m2
= - 0.25 m2

SHAZEB NOMAN 42
QUANTITY SURVEY NOTES

3. WALLS:
HORIZONTAL SHEAR WALL:
LENGTH= 4 M,
WIDTH= 2 M
DEPTH OR WALL THICKNESS= 0.2 M
NO.S = 2

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH * NO.S m3


= 4 * 2 * 0.2 * 2 m3
= 3.2 m3

2. SHUTTERING AREA = ((LENGTH * WIDTH)*2) * 2 m2


= ((4 * 2) * 2) * 2 m2
= 32 m2

3. BITUMEN PAINT AREA = (LENGTH * WIDTH) * NO.S m2


= (4 * 2) * 2 m2
= 16 m2

VERTICAL SHEAR WALL:


LENGTH= 2.6 M,
WIDTH= 2 M
DEPTH OR WALL THICKNESS= 0.2 M
NO.S = 2

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH * NO.S m3


= 2.6 * 2 * 0.2 * 2 m3
= 2.08 m3

2. SHUTTERING AREA = ((LENGTH * WIDTH)*2) * 2 m2


= ((2.6 * 2) * 2) * 2 m2
= 20.8 m2

3. BITUMEN PAINT AREA = (LENGTH * WIDTH) * NO.S m2


= (2.6 * 2) * 2 m2
= 10.4 m2

SHAZEB NOMAN 43
QUANTITY SURVEY NOTES

4. BOTTOM SLAB:
LENGTH= 4 M,
WIDTH= 3 M
DEPTH= 0.2 M

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 4 * 3 * 0.2 m3
= 2.4 m3

2. SHUTTERING AREA = ((LENGTH + WIDTH)*2*DEPTH) m2


= ((4 + 3) * 2 * 0.2) m2
= 2.8 m2

3. BITUMEN PAINT AREA = ((LENGTH + WIDTH) * 2 * DEPTH) m2


= ((4 + 3) * 2 * 0.2) m2
= 2.8 m2

5. PCC BED:
LENGTH= 4+0.1+0.1=4.2 M,
WIDTH= 3+0.1+0.1=3.2 M,
DEPTH= 0.1 M.

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 4.2 * 3.2 * 0.1 m3
= 1.34 m3

2. SHUTTERING AREA = ((LENGTH + WIDTH)*2*DEPTH) m2


= ((4.2 + 3.2) * 2 * 0.1) m2
= 1.48 m2

3. BITUMEN PAINT AREA = {((LENGTH + WIDTH) * 2 * DEPTH) + (LENGTH * WIDTH) –


(LENGTH * WIDTH)} m2
= {((4.2 + 3.2) * 2 * 0.1) + (4.2 * 3.2) – (4 * 3)}m2
= 2.92 m2

SHAZEB NOMAN 44
QUANTITY SURVEY NOTES

4. POLYTHENE SHEET AREA = (LENGTH * WIDTH) m2


= (4.2 * 3.2) m2
= 13.44 m2

5. TERMITE CONTROL AREA = (LENGTH * WIDTH) m2


= (4.2 * 3.2) m2
= 13.44 m2

SHAZEB NOMAN 45
QUANTITY SURVEY NOTES

13. EXCAVATION & BACKFILL CALCULATIONS:

SHAZEB NOMAN 46
QUANTITY SURVEY NOTES

SHAZEB NOMAN 47
QUANTITY SURVEY NOTES

VOLUME OF EXCAVATION = LENGTH * WIDTH * DEPTH m3


1. FOOTING-1 PIT:

LENGTH=FOOTING PCC LENGTH = 1.4 M,


WIDTH=FOOTING PCC WIDTH = 1.6 M
DEPTH= NECK COLUMN HEIGHT + FOOTING DEPTH + FOOTING PCC DEPTH M = 1.65 + 0.45 + 0.1 M = 2.2 M

1. VOLUME OF EXCAVATION = LENGTH * WIDTH * DEPTH m3


= 1.4 * 1.6 * 2.2 m3
= 4.92 m3
2. TIE BEAM PIT:

LENGTH = TIE BEAM PCC LENGTH = 3.25 M,


WIDTH = TIE BEAM PCC WIDTH = 0.5 M
DEPTH = NECK COLUMN HEIGHT + FOOTING DEPTH + FOOTING PCC DEPTH M = 1.65 + 0.45 + 0.1 M = 2.2 M

1. VOLUME OF EXCAVATION = LENGTH * WIDTH * DEPTH m3


= 3.25 * 0.5 * 2.2 m3
= 3.57 m3

SHAZEB NOMAN 48
QUANTITY SURVEY NOTES

3. RECTANGULAR SUMP PIT:

LENGTH = RECTANGULAR SUMP PCC LENGTH = 4.2 M,


WIDTH = RECTANGULAR SUMP PCC WIDTH = 3.2 M
DEPTH = TOP SLAB THICKNESS + SHEAR WALL HEIGHT + BOTTOM SLAB THICKNESS + PCC BED THICKNESS M
= 0.2 + 2 + 0.2 + 0.1 M = 2.5 M

1. VOLUME OF EXCAVATION = LENGTH * WIDTH * DEPTH m3


= 4.2 * 3.2 * 2.5 m3
= 33.6 m3

VOLUME OF BACKFILL = VOLUME OF EXCAVTION – VOLUME OF CONCRETE


VOLUME OF CONCRETE:
FOOTING = 14.04
FOOTING PCC = 4.14
NECK COLUMN = 2.67
TIE BEAM = 5.42
TIE BEAM PCC = 2.81
RETAINING WALL = 12.19
RECTANGULAR SUMP = 28.8
NOTE:
RECTANGULAR SUMP = VOLUME OF EXCAVATION – VOLUME OCCUPIED
VOLUME OCCUPIED:
LENGTH = 4M
WIDTH = 3M
DEPTH = TOP SLAB THICKNESS + SHEAR WALL HEIGHT + BOTTOM SLAB THICKNESS M = 0.2 + 2 + 0.2 M = 2.4 M

VOLUME OCCUPIED = 4 * 3 * 2.4 M3 = 28.8 M3


RECTANGULAR SUMP = VOLUME OF EXCAVATION – VOLUME OCCUPIED
RECTANGULAR SUMP = 33.6 – 28.8 M3 = 4.8 M3

SHAZEB NOMAN 49
QUANTITY SURVEY NOTES

14. SUB – STRUCTURE ABSTRACT CALCULATIONS:

 STANDARD WEIGHTS N DENSITIES :

1. WEIGHT OF CEMENT IN KGS/M 3= 1440 KGS.


2. WEIGHT OF EACH CEMENT BAG= 50 KGS.
3. NO. OF CEMENT BAGS /M 3 = 1440/50 = 28.80 OR APPROXIMATELY EQUAL TO 29 BAGS.
4. WEIGHT OF SAND /M 3 = 1600KGS TO 1750 KGS i.e., DRY OR MOISTURIZING.
5. WEIGHT OF AGGREGATE /M 3 = 2400 KGS.
6. WEIGHT OF WATER / M 3 = 1000 KGS.
7. WEIGHT OF WATER /LITRE. = 1 KG.
8. DENSITY OF CONCRETE /M 3 = 2400 KGS.
9. DENSITY OF STEEL /M 3= 7850 KGS.
10. DENSITY OF BRICK = 1.92 GRMS/CM 3 (NORMAL CLAY) OR 2.42 GRMS/CM 3 (FINE CLAY).
11. WEIGHT OF CONCRETE /M 3 = 2500 KGS TO 2800 KGS (R.C.C).
12. M15 = 1:2:4.
WHERE M15 = GRADE OF CONCRETE
M= MIX‐DESIGN
15 = COMPRESSIVE STRENGTH OF CONCRETE
1= 1 BAG OF CEMENT
2 = 2 BAGS OF SAND
4 = 4 BAGS OF AGGREGATE
13. CEMENT: MORTAR = 1:3.
1 = CEMENT,
3 = 3 BAGS OF SAND.

SHAZEB NOMAN 50
QUANTITY SURVEY NOTES

 RATIOS ‘’ MIX DESIGNS “GRADES

GRADE OF CONCRETES N RATIOS: Cement, Sand & Aggregate required for different Grades of Concrete /m3

CONCRETE GRADES N RATIOS


GRADE OF RATIO OF
SL.NO. CONCRETE CONCRETE
1 M7.5 1:4:8
2 M10 1:3:6
3 M15 1:2:4
4 M20 1:1.5:3
5 M25 1:1:2
6 M30 1:0.75:1.5
7 M35 1:0.5:1
8 M40 1:0.25:0.5

BRICKWORK CEMENT:MORTAR PROPORTIONS


SL.NO. PROPORTION OR RATIO
1 1:3
2 1:4
3 1:5
4 1:6
5 1:7
6 1:8

PLASTERING CEMENT:MORTAR PROPORTIONS


SL.NO. PROPORTION OR RATIO
1 1:3
2 1:4
3 1:5
4 1:6
5 1:7
6 1:8

SHAZEB NOMAN 51
QUANTITY SURVEY NOTES


TOTAL QUANTITY OF CONCRETE FOR PCC = 13 m3
GRADE OF CONCRETE USED FOR PCC = M 7.5
RATION = 1: 4: 8,

ACCORDING TO STANDARDS: FOR 1m3 OF CONCRETE


1. SAND FOR 1 m3 OF CONCRETE = 0.46 m3
THEN FOR 13 m3 = 13 * 0.46 m3
= 5.98 m3

2. AGGREGATE OF SIZE 40mm FOR 1m3 = 0.92 m3


THEN FOR 13 m3 = 13 * 0.92 m3
= 11.96 m3

3. CEMENT FOR 1 m3 OF CONCRETE = (1440*0.92)/8 = 165.6 kgs


THEN FOR 13 m3 = 13 * 165.6 kgs
= 2152.8 kgs
1 BAG OF CEMENT = 50kgs
NO. OF CEMENT BAGS REQUIRED = 2152.8 / 50
= 43.05
APPROXIMATELY = 43 BAGS

SHAZEB NOMAN 52
QUANTITY SURVEY NOTES

TOTOAL QUANTITY OF CONCRETE FOR RCC = 63 m3
GRADE OF CONCRETE USED FOR RCC = M 15
RATION = 1: 2: 4,

ACCORDING TO STANDARDS: FOR 1m3 OF CONCRETE


1. SAND FOR 1 m3 OF CONCRETE = 0.46 m3
THEN FOR 63 m3 = 63 * 0.46 m3
= 28.98 m3

2. AGGREGATE OF SIZE 20mm FOR 1m3 = 0.92 m3


THEN FOR 63 m3 = 63 * 0.92 m3
= 57.96 m3

3. CEMENT FOR 1 m3 OF CONCRETE = (1440*0.92)/4 = 331.2 kgs


THEN FOR 63 m3 = 63 * 331.2 kgs
= 20865.6 kgs
1 BAG OF CEMENT = 50kgs
NO. OF CEMENT BAGS REQUIRED = 20865.6 / 50
= 417.31
APPROXIMATELY = 418 BAGS

TOTAL CEMENT BAGS REQUIRED = 43 + 418 = 461 Bags

TOTAL QUANTITY OF SAND = 5.98 + 28.98 m3 = 34.96 m3


LET SAY IF WE ARE ORDERING THROUGH TRUCK,
NO. OF TRUCKS REQUIRED =?
VOLUME OF SAND IN 1 TRUCK = LENGTH * WIDTH * DEPTH m3
= 18’ * 9’ * 3’
= 486 CFT
486 CFT =? m3
= 486 / 3.283
VOLUME OF SAND IN 1 TRUCK = 13.77 m3
NO. OF SAND TRUCK REQUIRED = VOLUME OF SAND REQUIRED / VOLUME OF SAND IN 1 TRUCK
= 34.96 / 13.77
= 2.54
APPROXIMATELY 3 TRUCKS

SHAZEB NOMAN 53
QUANTITY SURVEY NOTES

TOTAL QUANTITY OF AGGREGATE OF 40mm = 11.96 m3


LET SAY IF WE ARE ORDERING THROUGH TIPPERS,
NO. OF TIPPERS REQUIRED =?
VOLUME OF AGGREGATE IN 1 TIPPER = 8.5 m3
NO. OF AGGREGATE TIPPER REQUIRED = VOLUME OF AGGREGATE REQUIRED / VOLUME
OF AGGREGATE IN 1 TIPPER
= 11.96 / 8.5 m3
= 1.41
APPROXIMATELY 2 TIPPER

TOTAL QUANTITY OF AGGREGATE OF 20mm = 57.96 m3


LET SAY IF WE ARE ORDERING THROUGH TIPPERS,
NO. OF TIPPERS REQUIRED =?
VOLUME OF AGGREGATE IN 1 TIPPER = 8.5 m3
NO. OF AGGREGATE TIPPER REQUIRED = VOLUME OF AGGREGATE REQUIRED / VOLUME
OF AGGREGATE IN 1 TIPPER
= 57.96 / 8.5 m3
= 6.82
APPROXIMATELY 7 TIPPER

SHAZEB NOMAN 54
QUANTITY SURVEY NOTES

HOW TO CALCULATE CEMENT, SAND, AGGREGATE FROM CONCRETE?

FOR EXAMPLE WE WILL TAKE M20 = 1:1.5:3


CONCRETE WHICH WE USE DURING CONCRETING IS WET CONCRETE,
IT WILL INITIAL SETTING TIME (30 MIN)
FINAL SETTING TIME (10 HOURS)
SHRINKAGE OR SAFETY FACTOR =1.54 TO 1.57.
MEANS VOLUME OF DRY CONCRETE = 1.54 TO 1.57 TIMES OF WET CONCRETE
NOW THE CALCULATION PART: FOR 1 M3 OF CONCRETE
RATIO SUM = 1+1.5+3 =5.5,
SHRINKAGE OR SAFETY FACTOR =1.57 (IF U WANT U CAN TAKE 1.54 ALSO)
NOW VOLUME OF DRY CONCRETE = 1 *1.57 M3 = 1.57 M3
 VOLUME OF CEMENT REQUIRED = (CEMENT VALUE IN RATIO / SUM OF RATIO) * 1.57
VOLUME OF CEMENT = (1/5.5)*1.57
VOLUME OF CEMENT = 0.285 M3
IN KGS, = 0.285 * 1440 KGS (WHERE 1440 KGS/ M3 IS WEIGHT OF CEMENT PER M3)
=411 KGS.
NOW IN BAGS, =411 / 50 BAGS (WEIGHT OF CEMENT BAG IS 50 KGS)
CEMENT=8.22 BAGS.
NOW VOLUME OF CEMENT IN CUBIC FEET (CFT) = 8.22 * 1.224 CFT
VOLUME OF 1 BAG OF CEMENT = 50 /1440 =0.034722 M3
WHERE 50 IS WEIGHT PER CEMENT BAG,
AND 1440 IS WEIGHT OF CEMENT PER M3
SO VOLUME OF CEMENT BAG IN CFT = 0.034722 *35.287 CFT (BCOZ 1 M3 = 35.287 CFT.)
1 M3 = 35.287 CFT, 0.034722 M3 =? CFT
= 0.034722 *35.287 CFT
SO VOLUME OF CEMENT BAG IN CFT = 1.224 CFT
 COMING BACK TO
 VOLUME OF CEMENT IN CUBIC FEET (CFT) = 8.22 * 1.224 CFT
VOLUME OF CEMENT IN CUBIC FEET (CFT) = 10.06 CFT

 VOLUME OF SAND REQUIRED = (SAND VALUE IN RATIO / SUM OF RATIO) * 1.57


VOLUME OF SAND REQUIRED = (1.5/5.5)*1.57
VOLUME OF SAND REQUIRED = 0.428 M3

NOW WEIGHT OF SAND PER M3 = 1600 TO 1750 KGS DRY TO MOIST (OR 1400 KGS OR 1450)
FOR 1 M3 = 1600KGS,
THEN FOR 0.428 M3 = 0.428 * 1600
= 684.8 KGS OR =0.684 TONNES

NOW IN VOLUME OF SAND IN CUBIC FEET = 0.428 * 35.287 (BCOZ 1 M3 = 35.287 CFT.)
1 M3 = 35.287 CFT, 0.428 M3 =? CFT
= 0.428 * 35.287
 VOLUME OF SAND IN CUBIC FEET = 15.10 CFT

SHAZEB NOMAN 55
QUANTITY SURVEY NOTES

AGGREGATE = BROKEN STONE OR COARSE AGGREGATE

 VOLUME OF AGGREGATE REQUIRED = (AGGREGATE VALUE IN RATIO / SUM OF RATIO) * 1.57


VOLUME OF AGGREGATE REQUIRED = (3/5.5)*1.57
VOLUME OF AGGREGATE REQUIRED = 0.856 M3

NOW WEIGHT OF AGGREGATE PER M3 = 2240 TO 2400 KGS


FOR 1 M3 = 2400KGS,
THEN FOR 0.856 M3 = 0.856 * 2400
= 2054.4 KGS OR = 2.054 TONNES

NOW IN VOLUME OF AGGREGATE IN CUBIC FEET = 0.856 * 35.287 (BCOZ 1 M3 = 35.287 CFT.)
1 M3 = 35.287 CFT, 0.856 M3 = ? CFT
= 0.856 * 35.287
 VOLUME OF AGGREGATE IN CUBIC FEET = 30.205 CFT

VOLUME OF CEMENT = 0.285 M3 = 411 KGS = 8.22 BAGS = 10.06 CFT


VOLUME OF SAND REQUIRED = 0.428 M3 = 684.8 KGS = 15.10 CFT
VOLUME OF AGGREGATE REQUIRED = 0.856 M3 = 2054.4 KGS = 30.205 CFT

SHAZEB NOMAN 56
QUANTITY SURVEY NOTES

15. SUB – STRUCTURE BOQ CALCULATIONS:


BILL OF QUANTITIES SUB STRUCTURE
TOTAL
S.NO DESCRIPTON UNIT RATE/UNIT TOTAL QUANTITY AMOUNT REMARK
1 CEMENT BAGS 280 461 129080
2 SAND TRUCK 10000 3 30000
3 AGGREGATE OF SIZE 20 MM TIPPER 5000 7 35000
4 AGGREGATE OF SIZE 40 MM TIPPER 4500 2 9000
5 SHUTTERING AREA M2 194 393 76242
6 BITUMEN PAINT LITRE 150 95 14250
7 POLYTHENE SHEET M3 22 235 5170
8 TERMITE CONTROLE M3 12 235 2820
3
9 EXCAVATION M 350 187 65450
10 BACK FILL M3 177 117 20709

387721

ADD 5%WASTAGE 19386


ADD 5%
CONTENGENCIES 19386
TOTAL 426493

SHAZEB NOMAN 57
QUANTITY SURVEY NOTES

SUPER – STRUCTURE (CONCRETE PART)

16. FLOOR COLUMN CALCULATIONS:

LENGTH= 0.3m
WIDTH= 0.3m
HEIGHT= 1.8m

1. VOLUME OF CONCRETE = LENGTH * WIDTH * HEIGHT m3


= 0.3 * 0.3 * 1.8 m3
= 0.162 m3

2. SHUTTERING AREA = (LENGTH +WIDTH) * 2 * HEIGHT m2


= (0.3 + 0.3) * 2 * 1.8 m2
= 2.16 m2

SHAZEB NOMAN 58
QUANTITY SURVEY NOTES

LENGTH= 0.3m
WIDTH= 0.3m
HEIGHT= 3.15m

1. VOLUME OF CONCRETE = LENGTH * WIDTH * HEIGHT m3


= 0.3 * 0.3 * 3.15 m3
= 0.28 m3

2. SHUTTERING AREA = (LENGTH +WIDTH) * 2 * HEIGHT m2


= (0.3 + 0.3) * 2 * 3.15 m2
= 3.78 m2

SHAZEB NOMAN 59
QUANTITY SURVEY NOTES

17. FLOOR BEAM CALCULATIONS:

NOTE:
FOR EXTERNAL BEAM
SHUTTERING AREA = (L * D) + (L * W) + (L * (D – SLAB THICKNESS)) m2
FOR INTERNAL BEAM
SHUTTERING AREA = (L * (D – SLAB THICKNESS)) + (L * W) + (L * (D – SLAB THICKNESS)) m2

1. EXTERNAL FLOOR BEAM ON AXIS 2 B/W B – D:


LENGTH= 3.4m
WIDTH= 0.3m
DEPTH= 0.3m

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 3.4 * 0.3 * 0.3 m3
= 0.306 m3

2. SHUTTERING AREA = (LENGTH * DEPTH) + (LENGTH * WIDTH) + (LENGTH * (DEPTH –


SLAB THICKNESS)) m2
= (3.4 * 0.3) + (3.4 * 0.3) + (3.4 * (0.3 – 0.15)) m2
= 2.55 m2
SHAZEB NOMAN 60
QUANTITY SURVEY NOTES

2. INTERNAL FLOOR BEAM ON AXIS 4 B/W B – D:


LENGTH= 3.4m
WIDTH= 0.3m
DEPTH= 0.3m

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 3.4 * 0.3 * 0.3 m3
= 0.306 m3

2. SHUTTERING AREA = (LENGTH * (DEPTH – SLAB THICKNESS)) + (LENGTH * WIDTH) +


(LENGTH * (DEPTH – SLAB THICKNESS)) m2
= (3.4 * (0.3 – 0.15)) + (3.4 * 0.3) + (3.4 * (0.3 – 0.15)) m2
= 2.04 m2

SHAZEB NOMAN 61
QUANTITY SURVEY NOTES

18. SLAB CALCULATIONS:

LENGTH= 4.45m
WIDTH= 3.4m
SLAB THICKNESS OR DEPTH= 0.15m

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 4.45 * 3.4 * 0.15 m3
= 2.269 m3

2. SHUTTERING AREA = (LENGTH * WIDTH) m2


= (4.45 * 3.4) m2
= 15.13 m2

SHAZEB NOMAN 62
QUANTITY SURVEY NOTES

19. STAIRCASE CALCULATIONS:

SHAZEB NOMAN 63
QUANTITY SURVEY NOTES

SHAZEB NOMAN 64
QUANTITY SURVEY NOTES

1. WAIST SLAB – 1:
LENGTH= 4.082m
WIDTH= 1m
DEPTH= 0.15m

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 4.082 * 1 * 0.15 m3
= 0.61 m3

2. SHUTTERING AREA = (TWO SIDE AREA) + (FRONT AREA) + (BOTTOM AREA) m2


= (LENGTH *DEPTH * 2) + (WIDTH * DEPTH) + (LENGTH * WIDTH) m2
= (4.082 * 0.15 * 2) + (1 * 0.15) + (4.082 * 1) m2
= 5.46 m2
2. WAIST SLAB – 2:
LENGTH= 2.33m
WIDTH= 1m
DEPTH= 0.15m

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 2.33 * 1 * 0.15 m3
= 0.35 m3

2. SHUTTERING AREA = (TWO SIDE AREA) + (BOTTOM AREA) m2


= (LENGTH *DEPTH * 2) + (LENGTH * WIDTH) m2
= (2.33 * 0.15 * 2) + (2.33 * 1) m2
= 3.03 m2

3. STEPS:
LENGTH OF STEP (L) = 1.0m
WIDTH OF STEP (TREAD) = 0.3m
DEPH OR HEIGHT OF RISER (H) = 0.158m
NO. OF STEPS = 20

1. VOLUME OF CONCRETE = AREA * LENGTH m3


= (½ * WIDTH * HEIGHT)* LENGTH * NO.S m3
= (0.5 * 0.3 * 0.158) * 1.0 * 20 m3
= 0.47 m3

SHAZEB NOMAN 65
QUANTITY SURVEY NOTES

2. SHUTTERING AREA = (FRONT AREA) +(RIGHT SIDE AREA)+(LEFT SIDE AREA)*NO.S m2


= (LENGTH * HEIGHT) + ((½ * WIDTH * HEIGHT) + ((½ * WIDTH * HEIGHT) * NO.S m2
= (1.0 * 0.158) + (0.5 * 0.3 * 0.158) + (0.5 * 0.3 * 0.158) * 20 m2
= 4.11 m2
4. LANDING:
LENGTH= 1m
WIDTH= 1.4m
DEPTH= 0.15m

1. VOLUME OF CONCRETE = LENGTH * WIDTH * DEPTH m3


= 1 * 1.4* 0.15 m3
= 0.21 m3

2. SHUTTERING AREA = (FRONT AREA) + (TWO SIDE AREA) + (BOTTOM AREA) m2


= (LENGTH *DEPTH) + (WIDTH * DEPTH * 2) + (LENGTH * WIDTH) m2
= (1 * 0.15) + (1.4 * 0.15 * 2) + (1 * 1.4) m2
= 1.97 m2

4. HANDRAIL: COST WILL BE ADDED TO BOQ

SHAZEB NOMAN 66
QUANTITY SURVEY NOTES

20. BRICKWORK:

BRICK SIZE: 0.2m x 0.1m x 0.1m

DOOR SIZE: 1m X 2.1m

DOOR LINTEL SIZE: 1.2m X 0.1m

WALL THICKNESS: 0.2m

BRICKWORK CALCULATION:

BRICKWORK AREA:

1. WALL: length = 4.45m, depth = 2.85m.

Area = 4.45 x 2.85 = 12.68m2

BRICKWORK AREA = 12.68m2


DEDUCTIONS:

1. DOOR: length=1m, depth=2.1m.

Area=1 x 2.1 = 2.1m2

2. DOOR LINTEL: length=1.2m, depth=0.1m.

Area=1.2 x 0.1 = 0.12m2

TOTAL DEDUCTION AREA = 2.1 + 0.12 = 2.22m2

SHAZEB NOMAN 67
QUANTITY SURVEY NOTES

BRICKWORK:

1. VOLUME OF BRICKWORK FOR 20CM WALL = AREA OF 20CM WALL * WALL THICKNESS

= 165.94 * 0.2 m3

= 33.188 m3

2. VOLUME OF BRICKWORK FOR 10CM WALL = AREA OF 10CM WALL * WALL THICKNESS

= 37.2 * 0.1 m3

= 3.72 m3

 VOLUME OF BRICK WORK = 33.188 + 3.72 m3 = 36.908 m3

 VOLUME OF SINGLE BRICK = LENGTH X WIDTH X DEPTH


= 0.2 X 0.1 X 0.1
=0.002m3

 NUMBER OF BRICKS = VOLUME OF BRICKWORK / VOLUME OF SINGLE BRICK


= 36.908 / 0.002
= 18454 BRICKS

 CEMENT:MORTAR REQUIRED FOR BRICKWORK: RATIO = 1 : 3

VOLUME OF BRICKWORK = 36.908 m3

FOR 1m3 OF CEMENT: MORTAR, SAND=0.2m3

SAND = 36.908 X 0.2 = 7.381m3

FOR 1m3 OF CEMENT: MORTAR, CEMENT = (0.2 X 1440)/LAST DIGIT OF RATIO IN KGS

= (0.2 X 1440)/3

= 96 KGS

THEN FOR 37.868 m3 =?

= 36.908 X 96

= 3543.168 KGS

NUMBER OF CEMENT BAGS = 3543.168 / 50

= 70.86 BAGS

APPROX = 71 BAGS

SHAZEB NOMAN 68
QUANTITY SURVEY NOTES

21. PLASTERING:

SHAZEB NOMAN 69
QUANTITY SURVEY NOTES

DOOR SIZE: 1m X 2.1m

WINDOW SIZE: 1.2m X 1.5m

PLASTERING THICKNESS: 0.02m

PLASTERING CALCULATION:

 PLASTERING AREA: INTERNAL AREA

INTERNAL DIMENSIONS BEDROOM – 1: LENGTH = 4.6m, BREADTH = 3.6m, DEPTH = 3m.

INTERNAL AREA OF BEDROOM - 1 = (LENGTH + BREADTH) X 2 X DEPTH m2

= (4.6 + 3.6) x 2 x3 m2

= 49.2 m2
 INTERNAL DEDUCTIONS:
DOOR - 1: LENGTH = 1m, DEPTH = 2.1m

Door area = 1 x 2.1 =2.1m2

DOOR - 2: LENGTH = 0.9m, DEPTH = 2.1m

Door area = 0.9 x 2.1 =1.89m2

WINDOW: LENGTH = 1.2m, DEPTH = 1.5m

Window area = 1.2 x 1.5 = 1.8m2

Total internal area = internal area – door & window area

= 49.2 – 2.1 – 1.89 – 1.8 – 1.8 m2

= 41.61m2

 EXTERNAL AREA:

EXTERNAL DIMENSIONS: LENGTH = 12.2m, BREADTH = 4m, DEPTH = 3.15m.

EXTERNAL AREA = (LENGTH + BREADTH) X 2 X DEPTH m2

= (12.2 + 4) x 2 x3.15

= 102.06m2

 EXTERNAL DEDUCTIONS:

DOOR: LENGTH = 1m, DEPTH = 2.1m.

Door area = 1 x 2.1=2.1m2

WINDOW: LENGTH = 1.2m, DEPTH = 1.5m.

Window area = 1.2 x 1.5 = 1.8m2

SHAZEB NOMAN 70
QUANTITY SURVEY NOTES

VENTILATER: LENGTH = 0.9m, DEPTH = 0.4m.

VENTILATER area = 0.9 x 0.4 = 0.36m2

Total External area = External area – door & window area

= 102.06 – 2.1 – 2.1 – 1.8 – 1.8 – 1.8 – 1.8 – 0.36 – 0.36

= 89.94 m2

 TOTAL PLASTERING AREA: INTERNAL + EXTERNAL PLASTERING AREA


= 241.323 m2 + 210.663 m2
= 451.986 m2

TOTAL THICKNESS OF PLASTER = 20 MM

1. 1ST COAT (ROUGH CAOT) OF PLASTER WITH C : M RATIO 1:6


THICKNESS OF PLASTER FOR 1ST COAT =12MM OR 0.012M
VOLUME OF PLASTER = TOTAL AREA OF PLASTER*THICKNESS OF PLASTER
VOLUME OF 12 MM = 451.986 *0.012
= 5.423 M3

ACCORDING TO STANDARDS
FOR 1 M3 OF C:M WITH RATIO 1:6
SAND = 1.25 m3
CEMENT = 300 Kgs
A. SAND FOR 5.423 m3 =?
SAND = 5.423 * 1.25
SAND = 6.779 m3

B. CEMENT FOR 5.46 m3 =?


CEMENT = 5.46 * 300
= 1626.9 KGS

CEMENT= 1638 KGS


NO. OF BAGS = 1638/50
= 32.538
APPROX = 33 BAGS

SHAZEB NOMAN 71
QUANTITY SURVEY NOTES

2. 2ND COAT (FINE CAOT) OF PLASTER WITH C : M RATIO 1:3


THICKNESS OF PLASTER FOR FINE COAT =8MM OR 0.008M
VOLUME OF PLASTER = TOTAL AREA OF PLASTER*THICKNESS OF PLASTER
VOLUME OF 8 MM = 451.986 *0.008
= 3.615 m3

ACCORDING TO STANDARDS
FOR 1 M3 OF C:M WITH RATIO 1:3
SAND = 1.25 m3
CEMENT = 600 Kgs
A. SAND FOR 3.615 m3=?
SAND = 3.615 * 1.25
SAND = 4.519 m3

B. CEMENT FOR 3.64 m3 =?


CEMENT = 3.615 *600
CEMENT = 2169.532 Kgs
NO. OF BAGS = 2184.22/50
= 43.39
APPROX = 44 BAGS

TOTAL SAND = 6.779 + 4.519


= 11.29 m3

TOTAL CEMENT IN BAGS =33 + 44


= 77 BAGS

SHAZEB NOMAN 72
QUANTITY SURVEY NOTES

22. WALL PUTTY CALCULATIONS:


THICKNESS OF WALL PUTTY LAYER ON WALL = 3mm OR 0.003m
AREA OF WALL PUTTY = LENGTH * DEPTH m2
WHERE LENGTH = LENGTH OF WALL,

DEPTH = HEIGHT OF WALL

BEDROOM – 1 = (LENGTH + BREADTH) X 2 X DEPTH m2

= (4.6 + 3.6) x 2 x 3 m2

= 49.2 m2

BEDROOM – 2 = (LENGTH + BREADTH) X 2 X DEPTH m2

= (4.7 + 3.6) x 2 x 3 m2

= 49.8 m2

TOTAL WALL PUTTY AREA = 49.2 + 49.8 = 99 m2

DEDUCTIONS:

DOOR-1: LENGTH = 1m, DEPTH = 2.1m

Door area = 1 x 2.1 =2.1m2

DOOR-2: LENGTH = 0.9m, DEPTH = 2.1m

Door area = 0.9 x 2.1 =1.89m2

WINDOW: LENGTH = 1.2m, DEPTH = 1.5m

Window area = 1.2 x 1.5 = 1.8m2

Total internal area = internal area – door & window area

= 99 – 2.1 – 1.89 – 1.8 – 1.8 – 2.1 – 1.89 – 1.8 – 1.8 m2

= 83.82m2

VOLUME OF WALL PUTTY = TOTAL AREA * THICKNESS OF LAYER

= 83.82 * 0.003 m3 = 0.251 m3

 WEIGHT OF WALLPUTTY / m3 = 849 Kgs


1 m3 = 849 Kgs
0.251 m3 =?
0.251 * 849 = 213.489 Kgs
AVAILABLE WALL PUTTY BAGS = 5Kgs, 10Kgs, 20Kgs, AND 40Kgs
NO. OF WALL PUTTY BAGS = 213.489 / 40
= 5.33 = 6 Bags

SHAZEB NOMAN 73
QUANTITY SURVEY NOTES

23. PAINT CALCULATIONS:


 PAINT AREA: INTERNAL AREA

INTERNAL DIMENSIONS BEDROOM – 1: LENGTH = 4.6m, BREADTH = 3.6m, DEPTH = 3m.

INTERNAL AREA OF BEDROOM - 1 = (LENGTH + BREADTH) X 2 X DEPTH m2

= (4.6 + 3.6) x 2 x3 m2

= 49.2 m2
 INTERNAL DEDUCTIONS:
DOOR - 1: LENGTH = 1m, DEPTH = 2.1m

Door area = 1 x 2.1 =2.1m2

DOOR - 2: LENGTH = 0.9m, DEPTH = 2.1m

Door area = 0.9 x 2.1 =1.89m2

WINDOW: LENGTH = 1.2m, DEPTH = 1.5m

Window area = 1.2 x 1.5 = 1.8m2

Total internal area = internal area – door & window area

= 49.2 – 2.1 – 1.89 – 1.8 – 1.8 m2

= 41.61m2

 EXTERNAL AREA:

EXTERNAL DIMENSIONS: LENGTH = 12.2m, BREADTH = 4m, DEPTH = 3.15m.

EXTERNAL AREA = (LENGTH + BREADTH) X 2 X DEPTH m2

= (12.2 + 4) x 2 x3.15

= 102.06m2

 EXTERNAL DEDUCTIONS:

DOOR: LENGTH = 1m, DEPTH = 2.1m.

Door area = 1 x 2.1=2.1m2

WINDOW: LENGTH = 1.2m, DEPTH = 1.5m.

Window area = 1.2 x 1.5 = 1.8m2

VENTILATER: LENGTH = 0.9m, DEPTH = 0.4m.

VENTILATER area = 0.9 x 0.4 = 0.36m2

SHAZEB NOMAN 74
QUANTITY SURVEY NOTES

Total External area = External area – door & window area

= 102.06 – 2.1 – 2.1 – 1.8 – 1.8 – 1.8 – 1.8 – 0.36 – 0.36

= 89.94m2

ACCORDING TO STANDARDS:
1 Litre OF PAINT WILL COVER 4.2 m2 AREA
1. INTERNAL PAINT:
4.2m2 = 1 Litre
124.44 m2 =?
124.44 / 4.2 = 29.62 = 30 Litres
2. EXTERNAL PAINT:
4.2m2 = 1 Litre
327.546 m2 =?
327.546 / 4.2 = 77.98 = 78 Litres

SHAZEB NOMAN 75
QUANTITY SURVEY NOTES

24. FLOORING CALCULATIONS:

1. MARBLE FLOORING:
BEDROOM – 1
BEDROOM – 2

2. WALL SKIRTING:
BEDROOM – 1
BEDROOM – 2

3. VERTIFIED TILES:
TOILET – 1
TOILET – 2

4. CERAMIC TILES ON TOILET WALLS:


TOILET – 1
TOILET – 2

5. INTER-LOCK TILES:
PARKING AREA

SHAZEB NOMAN 76
QUANTITY SURVEY NOTES

1. MARBLE FLOORING AREA CALCULATION:


BEDROOM -1
LENGTH = 4.6m,
WIDTH = 3.6m.
BEDROOM -1 FLOORING AREA = LENGTH * WIDTH m2
= 4.6 * 3.6 m2
= 16.56 m2
BEDROOM -2
LENGTH = 4.7m,
WIDTH = 3.6m.
BEDROOM -2 FLOORING AREA = LENGTH * WIDTH m2
= 4.7 * 3.6 m2
= 16.92 m2
2. WALL SKIRTING AREA CALCULATION:
BEDROOM -1
LENGTH = 4.6m,
WIDTH = 3.6m.
WALL SKIRTING HEIGHT = 0.15m.
BEDROOM -1 WALL SKIRTING AREA = (LENGTH + WIDTH) * 2 * HEIGHT m2
= (4.6 + 3.6) * 2 * 0.15 m2
= 2.46 m2
BEDROOM -2
LENGTH = 4.7m,
WIDTH = 3.6m.
WALL SKIRTING HEIGHT = 0.15m.
BEDROOM -2 WALL SKIRTING AREA = (LENGTH + WIDTH) * 2 * HEIGHT m2
= (4.7 + 3.6) * 2 * 0.15 m2
= 2.49 m2

SHAZEB NOMAN 77
QUANTITY SURVEY NOTES

2. VERTIFIED TILES AREA CALCULATION:


TOILET - 1
LENGTH = 2.1m,
WIDTH = 1.7m.
TOILET -1 TILE AREA = LENGTH * WIDTH m2
= 2.1 * 1.7 m2
= 3.57 m2
TOILET - 2
LENGTH = 2.1m,
WIDTH = 1.7m.
TOILET -2 TILE AREA = LENGTH * WIDTH m2
= 2.1 * 1.7 m2
= 3.57 m2
3. CERAMIC TILES AREA CALCULATION:
TOILET - 1
LENGTH = 2.1m,
WIDTH = 1.7m,
DEPTH = 3m.
TOILET -1 WALL TILE AREA = (LENGTH + WIDTH) * 2 * DEPTH m2
= (2.1 + 1.7) * 2 * 3 m2
= 22.8 m2
TOILET - 2
LENGTH = 2.1m,
WIDTH = 1.7m,
DEPTH = 3m.
TOILET -2 WALL TILE AREA = (LENGTH + WIDTH) * 2 * DEPTH m2
= (2.1 + 1.7) * 2 * 3 m2
= 22.8 m2

SHAZEB NOMAN 78
QUANTITY SURVEY NOTES

4. INTERLOCK TILES AREA CALCULATION: PARKING AREA


PARKING AREA IS DIVIDED INTO 4 PARTS
AREA – 1:
LENGTH = 15.2m,
WIDTH = 3.2m.
AREA - 1 = LENGTH * WIDTH m2
= 15.2 * 3.2 m2
= 48.64 m2
AREA – 2:
LENGTH = 15.2m,
WIDTH = 1.3m.
AREA – 2= LENGTH * WIDTH m2
= 15.2 * 1.3 m2
= 19.76 m2
AREA – 3:
LENGTH = 1.5m,
WIDTH = 4m.
AREA – 3= LENGTH * WIDTH m2
= 1.5 * 4 m2
= 6 m2
AREA – 4:
LENGTH = 1.5m,
WIDTH = 4m.
AREA – 4= LENGTH * WIDTH m2
= 1.5 * 4 m2
= 6 m2

TOTAL PARKING AREA = 48.64 + 19.76 + 6 + 6 = 80.4m2

DEDUCTIONS:

SHAZEB NOMAN 79
QUANTITY SURVEY NOTES

WALL SKIRTING AREA:

BEDROOM – 1 = 2 DOORS TO BE DEDUCTED

DOOR -1:
LENGTH = 1m
DEPTH = 0.15m

AREA = LENGTH * DEPTH m2


= 1 * 0.15m2
= 0.15m2

DOOR -2:
LENGTH = 0.9m
DEPTH = 0.15m

AREA = LENGTH * DEPTH m2


= 0.9 * 0.15m2
= 0.135m2
BEDROOM – 2 = 2 DOORS TO BE DEDUCTED

SHAZEB NOMAN 80
QUANTITY SURVEY NOTES

DOOR -1:
LENGTH = 1m
DEPTH = 0.15m

AREA = LENGTH * DEPTH m2


= 1 * 0.15m2
= 0.15m2

DOOR -2:
LENGTH = 0.9m
DEPTH = 0.15m

AREA = LENGTH * DEPTH m2


= 0.9 * 0.15m2
= 0.135m2

WALL TILES IN TOILETS:


TOILET -1 = 1 DOOR & 1 VENTILATOR

DOOR:
LENGTH = 0.9m
HEIGHT = 2.1m

AREA = LENGTH * HEIGHT m2


= 0.9 * 2.1 m2
= 1.89 m2

VENTILATOR:
LENGTH = 0.9m
HEIGHT = 0.4m

AREA = LENGTH * HEIGHT m2


= 0.9 * 0.4 m2
= 0.36 m2

NO. OF MARBLES OR TILES = TOTAL AREA / SINGLE MARBLE OR TILE AREA

SHAZEB NOMAN 81
QUANTITY SURVEY NOTES

CALCULATIONS FOR THE QUANTITIES OF CEMENT MORTAR FOR FLOORING


TOTAL AREA OF FLOORING
1. MARBLE = 33.48m2
2. VERTIFIED TILE = 7.14m2
3. INTERLOCK TILES = 80.4m2
TOTAL = 121.02m2

CEMENT MORTAR REQUIRED FOR FLOORING WITH C : M RATIO 1:8


THICKNESS OF CEMENT MORTAR LAYER = 2’’ OR 0.05m
VOLUME OF CEMENT MORTAR FOR FLOORING = TOTAL AREA OF FLOORING * THICKNESS OF C : M
=121.02 * 0.05m3
=6.051m3
ACCORDING TO STANDARDS: FOR 1m3 OF CEMENT MORTAR
1. SAND FOR 1 m3 OF C:M = 1.25 m3
THEN FOR 6.051 m3 = 6.051 * 1.25 m3
= 7.563 m3

2. CEMENT FOR 1 m3 OF C:M = 225 kgs


THEN FOR 6.051 m3 = 6.051 * 225 kgs
= 1361.475 kgs
1 BAG OF CEMENT = 50kgs
NO. OF CEMENT BAGS REQUIRED = 1361.475 / 50
= 27.22
APPROXIMATELY = 28 BAGS

CALCULATIONS FOR CEMENT BAGS REQUIRED FOR SKIRTING AND WALL TILES

THICKNESS OF CEMENT LAYER FOR SKIRTING AND WALL TILES = 10mm OR 0.01m

AREA OF MARBLE SKIRTING = 4.95m2


AREA OF WALL TILES = 41.1m2
TOTAL AREA = 4.95 + 41.1 = 46.05m2
VOLUME OF CEMENT = TOTAL AREA * THICKNESS OF CEMENT LAYER
= 46.05 * 0.01
= 0.46m3

FOR 1m3 CEMENT = 1440 Kgs


FOR 0.46m3 = 0.46 * 1440 = 662.4 Kgs
NO. OF CEMENT BAGS = 662.4 / 50 = 13.24 = 14 Bags

SHAZEB NOMAN 82
QUANTITY SURVEY NOTES

25. FALSE CELING CALCULATIONS:

FALSE CEILING AREA:

BEDROOM – 1:
LENGTH = 4.6m
WIDTH = 3.6m

AREA = LENGTH * WIDTH m2


= 4.6 * 3.6 m2
= 16.56m2

SHAZEB NOMAN 83
QUANTITY SURVEY NOTES

26. DOOR & WINDOWS CALCULATIONS:

DOOR PANEL DOOR FRAME

WINDOW FRAME & PANEL AL-DROP

DOOR EYE DOOR HANDLE

SHAZEB NOMAN 84
QUANTITY SURVEY NOTES

DOOR LOCK RUBBER STOPPER

DOOR STOPPER HINGES

TOWER BOLT WINDOW GRILL METAL GATE

SHAZEB NOMAN 85
QUANTITY SURVEY NOTES

27. CALCULATION OF QUANTITIES OF LINTELS:

DOOR -1:
LENGTH = 1m,
WALL THICKNESS = 0.2m

LENGTH= DOOR LENGTH + 0.1 + 0.1 = 1 + 0.1 + 0.1 = 1.2m


WIDTH= WALL THICKNESS = 0.2m
HEIGHT= 0.1m

1. VOLUME OF CONCRETE = LENGTH * WIDTH * HEIGHT m3


= 1.2 * 0.2 * 0.1 m3
= 0.024m3

2. SHUTTERING AREA = (LENGTH +WIDTH) * 2 * HEIGHT m2


= (1.2 + 0.2) * 2 * 0.1 m2
= 0.28m2

SHAZEB NOMAN 86
QUANTITY SURVEY NOTES

28. SUPER – STRUCTURE ABSTRACT 1 CALCULATIONS:



TOTOAL QUANTITY OF CONCRETE FOR RCC = 14.55 m3
GRADE OF CONCRETE USED FOR RCC = M 15
RATIO = 1: 2: 4,

ACCORDING TO STANDARDS: FOR 1m3 OF CONCRETE


4. SAND FOR 1 m3 OF CONCRETE = 0.46 m3
THEN FOR 14.55 m3 = 14.55 * 0.46 m3
= 6.693 m3

5. AGGREGATE OF SIZE 20mm FOR 1m3 = 0.92 m3


THEN FOR 14.55 m3 = 14.55 * 0.92 m3
= 13.386 m3

6. CEMENT FOR 1 m3 OF CONCRETE = (1440*0.92)/4 = 331.2 kgs


THEN FOR 14.55 m3 = 14.55 * 331.2 kgs
= 4818.96 kgs
1 BAG OF CEMENT = 50kgs
NO. OF CEMENT BAGS REQUIRED = 4818.96 / 50
= 96.37
APPROXIMATELY = 97 BAGS
TOTAL CEMENT BAGS REQUIRED = 97 Bags

SHAZEB NOMAN 87
QUANTITY SURVEY NOTES

TOTAL QUANTITY OF SAND = 6.693 m3


LET SAY IF WE ARE ORDERING THROUGH TRUCK,
NO. OF TRUCKS REQUIRED =?
VOLUME OF SAND IN 1 TRUCK = LENGTH * WIDTH * DEPTH m3
= 18’ * 9’ * 3’
= 486 CFT
486 CFT =? m3
= 486 / 3.283
VOLUME OF SAND IN 1 TRUCK = 13.77 m3
NO. OF SAND TRUCK REQUIRED = VOLUME OF SAND REQUIRED / VOLUME OF SAND IN 1 TRUCK
= / 13.77
= 2.54
APPROXIMATELY 3 TRUCKS

TOTAL QUANTITY OF AGGREGATE OF 20mm = 57.96 m3


LET SAY IF WE ARE ORDERING THROUGH TIPPERS,
NO. OF TIPPERS REQUIRED =?
VOLUME OF AGGREGATE IN 1 TIPPER = 8.5 m3
NO. OF AGGREGATE TIPPER REQUIRED = VOLUME OF AGGREGATE REQUIRED / VOLUME
OF AGGREGATE IN 1 TIPPER
= 57.96 / 8.5 m3
= 6.82
APPROXIMATELY 7 TIPPER

SHAZEB NOMAN 88
QUANTITY SURVEY NOTES

29. SUPER – STRUCTURE ABSTRACT 2 CALCULATIONS:


TOTAL QUANTITY OF SAND = 32.927 m3
LET SAY IF WE ARE ORDERING THROUGH TRUCK,
NO. OF TRUCKS REQUIRED =?
VOLUME OF SAND IN 1 TRUCK = LENGTH * WIDTH * DEPTH m3
= 18’ * 9’ * 3’
= 486 CFT
486 CFT =? m3
= 486 / 3.283
VOLUME OF SAND IN 1 TRUCK = 13.77 m3
NO. OF SAND TRUCK REQUIRED = VOLUME OF SAND REQUIRED / VOLUME OF SAND IN 1 TRUCK
= 32.927 / 13.77
= 2.39
APPROXIMATELY 3 TRUCKS

TOTAL QUANTITY OF AGGREGATE OF 20mm = 13.386 m3


LET SAY IF WE ARE ORDERING THROUGH TIPPERS,
NO. OF TIPPERS REQUIRED =?
VOLUME OF AGGREGATE IN 1 TIPPER = 8.5 m3
NO. OF AGGREGATE TIPPER REQUIRED = VOLUME OF AGGREGATE REQUIRED / VOLUME
OF AGGREGATE IN 1 TIPPER
= 13.386 / 8.5 m3
= 1.57
APPROXIMATELY 2 TIPPER

NO. OF CEMENT BAGS = 289 BAGS

SHUTTERING AREA = 131.84 m2

NO. OF BRICKS = 18934

NO. OF WALL PUTTY BAGS = 6 (PER BAG 40Kg)

FALSE CEILING AREA = 33.48 m2

INTERNAL PAINT = 30 Litre

SHAZEB NOMAN 89
QUANTITY SURVEY NOTES

EXTERNAL PAINT = 78 Litre

NO. OF MARBLE = 339

NO. OF VERTIFIED TILES = 179


PER BOX = 10
NO. OF BOXES = 179/10 = 18

NO. OF INTER LOCK TILES = 2010

NO OF CERAMIC TILES = 1028


PER BOX = 10
NO. OF BOXES = 1028/10 = 103

WINDOW GRILL AND GATE AREA = 11.874

SHAZEB NOMAN 90
QUANTITY SURVEY NOTES

30. SUPER – STRUCTURE BOQ CALCULATIONS: PLZ CHECK EXCEL

SHAZEB NOMAN 91
QUANTITY SURVEY NOTES

31. BAR BENDING SCHEDULE BASICS:


1. DIAMETERS:
6mm
8mm
10mm
12mm
16mm
20mm
25mm
28mm
32mm
36mm
40mm

2. STANDARD LENGTH OF BAR = 12m.

3. WEIGHT PER METER = D2/162 kg/m. D=DIAMETER


FOR EXAMPLE SAY 8mm BAR.
WEIGHT PER METER = 82/162 = 0.39 kg/m.

4. WEIGHT PER BAR = (D2/162)*12 KGS/BAR.


FOR EXAMPLE SAY 8mm BAR.
WEIGHT PER BA = (82/162)*12 = 4.74 KGS/BAR

5. HOOK :

9d

LENGTH OF HOOK =9d, d = diameter.

LENGTH OF BAR = L + 9d +9d m

SHAZEB NOMAN 92
QUANTITY SURVEY NOTES

6. BEND:

LENGTH OF BEND =10d – 16d, d = diameter.

LENGTH OF BAR = L + 12d +12d m. (BEND = 12d).

SHAZEB NOMAN 93
QUANTITY SURVEY NOTES

7. OVERLAPPING:

JOGGLE LAP

REINFORCEMENT
OVERLAP

SHAZEB NOMAN 94
QUANTITY SURVEY NOTES

MECHANICAL COUPLER OR COUPLER

 FOR COMPRESSION MEMBERS (COLUMNS) OVERLAPPING SHOULD BE TAKEN AS 40D


 FOR TENSILE MEMBERS (BEAMS) OVERLAPPING SHOULD BE TAKEN AS 50D
 BUT FOR BOTH WE CAN TAKE 50D.
 NECK COLUMN TO FOOTING OVERLAPPING = 16D
 COLUMN TO COLUMN = 50d,
 GENERAL OVERLAPPING WHEN 12m BAR FINISHES = 50d. D=DIAMETER

SHAZEB NOMAN 95
QUANTITY SURVEY NOTES

CHAIR IN REINFORCEMENT

8. CRANK BAR:

CRANK = 0.42d,

LENGTH OF THE CRANK BAR = L + 0.42d + 0.42d,

D= SLAB OR BEAM THICKNESS – TOP N BOTTOM COVER.

LENGTH OF EXTRA BAR = L/4.

9. COVER: SPACE BETWEEN REINFORCEMENT AND SHUTTERING. COVERING


BLOCKS ARE USED FOR PROVIDING COVER.
FOOTING = 50mm
COLUMN = 25mm - 50mm
BEAM = 25mm - 50mm
SLAB = 25mm

SHAZEB NOMAN 96
QUANTITY SURVEY NOTES

CLEAR COVER COVERING BLOCKS

COVERING BLOCKS IN BEAM

COVERING BLOCKS IN SLAB

SHAZEB NOMAN 97
QUANTITY SURVEY NOTES

10. SPACING: DISTANCE BETWEEN TWO REINFORCEMENT BARS.

11. NUMBER OF BARS = (OPPOSITE LENGTH /SPACING) + 1.

12. NUMBER OF STIRRUPS = (ACTUAL LENGTH OF COLUMN OR BEAM /SPACING) + 1.

STEPS IN REINFORCEMENT CALCULATION:


1. LENGTH OF BAR =
2. NUMBER OF BAR = (OPPOSITE LENGTH / SPACING) + 1
3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M
4. DIAMETER OF BAR = 12 MM (GIVEN IN DRAWING)
5. WEIGHT PER METER OF BAR = D2/162 GS/M
6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS

SHAZEB NOMAN 98
QUANTITY SURVEY NOTES

32. FOOTING REINFORCEMENT CALCULATIONS: FOOTING - 1

SHAZEB NOMAN 99
QUANTITY SURVEY NOTES

FOOTING REINFORCEMENT CALCULATIONS: BEND = 12D, D=DIAMETER.


X - BARS:
1. LENGTH OF X - BAR = L - 0.1 – 0.1 + 12D + 12D M
LENGTH OF X - BAR = 1.2 – 0. 1 – 0.1 + 12(0.012) + 12(0.012) M
LENGTH OF X - BAR = 1.288 M

2. NUMBER OF X - BAR = (OPPOSITE LENGTH / SPACING) + 1


NUMBER OF X - BAR = {(1.4 – 0.1 – 0.1)/0.1} + 1
NUMBER OF X - BAR = {1.2/0.1} + 1
NUMBER OF X - BAR = 13 BARS

3. TOTAL LENGTH OF X - BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X - BARS = 1.288 *13 M
TOTAL LENGTH OF X - BARS = 16.744 M

4. DIAMETER OF X - BAR = 12 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X - BAR = D2/162 KGS/M


WEIGHT PER METER OF X - BAR = 12*12/162 KGS/M
WEIGHT PER METER OF X - BAR = 0.889 KGS/M

6. TOTAL WEIGHT OF X - BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X - BARS = 16.744 * 0.889 KGS
TOTAL WEIGHT OF X - BARS = 14.884 KGS

SHAZEB NOMAN 100


QUANTITY SURVEY NOTES

Y - BARS:
1. LENGTH OF Y - BAR = L - 0.1 – 0.1 +12D + 12D M
LENGTH OF Y - BAR = 1.4 – 0. 1 – 0.1 + 12(0.016) + 12(0.016) M
LENGTH OF Y - BAR = 1.584 M

2. NUMBER OF Y - BAR = (OPPOSITE LENGTH / SPACING) + 1


NUMBER OF Y - BAR = {(1.2 – 0.1 – 0.1)/0.1} + 1
NUMBER OF Y - BAR = {1/0.1} + 1
NUMBER OF Y - BAR = 11 BARS

3. TOTAL LENGTH OF Y - BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y - BARS = 1.584 *11 M
TOTAL LENGTH OF Y - BARS = 17.424 M

4. DIAMETER OF Y - BAR = 16 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF Y - BAR = D2/162 KGS/M


WEIGHT PER METER OF Y - BAR = 16*16/162 KGS/M
WEIGHT PER METER OF Y - BAR = 1.58 KGS/M

6. TOTAL WEIGHT OF Y - BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y - BARS = 17.424 * 1.58 KGS
TOTAL WEIGHT OF Y - BARS = 27.534 KGS

SHAZEB NOMAN 101


QUANTITY SURVEY NOTES

FOOTING – 2:

SHAZEB NOMAN 102


QUANTITY SURVEY NOTES

FOOTING REINFORCEMENT CALCULATIONS: BEND = 12D, D=DIAMETER.


X - BARS:
1. LENGTH OF X - BAR = L - 0.1 – 0.1 + 12D + 12D M
LENGTH OF X - BAR = 1.2 – 0. 1 – 0.1 + 12(0.012) + 12(0.012) M
LENGTH OF X - BAR = 1.288 M

2. NUMBER OF X - BAR = (OPPOSITE LENGTH / SPACING) + 1


NUMBER OF X - BAR = {(1.5 – 0.1 – 0.1)/0.1} + 1
NUMBER OF X - BAR = {1.3/0.1} + 1
NUMBER OF X - BAR = 14 BARS

3. TOTAL LENGTH OF X - BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X - BARS = 1.288 *14 M
TOTAL LENGTH OF X - BARS = 18.032 M

4. DIAMETER OF X - BAR = 12 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X - BAR = D2/162 KGS/M


WEIGHT PER METER OF X - BAR = 12*12/162 KGS/M
WEIGHT PER METER OF X - BAR = 0.889 KGS/M

6. TOTAL WEIGHT OF X - BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X - BARS = 18.032 * 0.889 KGS
TOTAL WEIGHT OF X - BARS = 16.028 KGS

SHAZEB NOMAN 103


QUANTITY SURVEY NOTES

Y - BARS:
1. LENGTH OF Y - BAR = L - 0.1 – 0.1 +12D + 12D M
LENGTH OF Y - BAR = 1.5 – 0. 1 – 0.1 + 12(0.016) + 12(0.016) M
LENGTH OF Y - BAR = 1.684 M

2. NUMBER OF Y - BAR = (OPPOSITE LENGTH / SPACING) + 1


NUMBER OF Y - BAR = {(1.2 – 0.1 – 0.1)/0.1} + 1
NUMBER OF Y - BAR = {1/0.1} + 1
NUMBER OF Y - BAR = 11 BARS

3. TOTAL LENGTH OF Y - BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y - BARS = 1.684 *11 M
TOTAL LENGTH OF Y - BARS = 18.524 M

4. DIAMETER OF Y - BAR = 16 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF Y - BAR = D2/162 KGS/M


WEIGHT PER METER OF Y - BAR = 16*16/162 KGS/M
WEIGHT PER METER OF Y - BAR = 1.58 KGS/M

6. TOTAL WEIGHT OF Y - BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y - BARS = 18.524 * 1.58 KGS
TOTAL WEIGHT OF Y - BARS = 29.272 KGS

SHAZEB NOMAN 104


QUANTITY SURVEY NOTES

FOOTING REINFORCEMENT ABSTRACT:


DIA OF BAR = 12mm,
WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (122)/162 Kg/m = 0.889 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.889 = 10.667 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 12mm = 277.063 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 277.063 / 10.667
= 25.97 BARS APPROXIMATELY EQUAL TO 26 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER INCREASING BARS FROM 25.97 TO 26 NO.S
ACTUAL WEIGHT = 26 X 10.667
= 277.333 Kgs

DIA OF BAR = 16mm,


WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (162)/162 Kg/m = 1.58 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 1.58 = 18.963 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 16mm = 509.522 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 509.522 / 18.963
= 26.87 BARS APPROXIMATELY EQUAL TO 27 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER INCREASING BARS FROM 26.87 TO 27 NO.S
ACTUAL WEIGHT = 17 X 18.963
= 512 Kgs

SHAZEB NOMAN 105


QUANTITY SURVEY NOTES

33. NECK COLUMN REINFORCEMENT CALCULATION:

SHAZEB NOMAN 106


QUANTITY SURVEY NOTES

COVER = 30 MM
STIRRUP BAR SPACING = 100mm = 0.1m
STIRRUP BAR LENGTH = 0.3 – 0.03 – 0.03 = 0.24m
STIRRUP BAR WIDTH = 0.3 – 0.03 – 0.03 = 0.24m

SHAZEB NOMAN 107


QUANTITY SURVEY NOTES

NECK COLUMN REINFORCEMENT CALCULATIONS:


GENERAL OVERLAP = 50D,
NECK COLUMN TO FOOTING OVERLAP = 16D.
MAIN BARS:
1. LENGTH OF MAIN BAR = L + 0.4 + 16D + 50D M
LENGTH OF MAIN BAR = 1.65 + 0.4 + 16(0.012) + 50(0.012) M
LENGTH OF MAIN BAR = 2.842 M

2. NUMBER OF MAIN BARS = 4 (GIVEN)

3. TOTAL LENGTH OF MAIN BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF MAIN BARS = 2.842 *4 M
TOTAL LENGTH OF MAIN BARS = 11.368 M

4. DIAMETER OF MAIN BAR = 12 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF MAIN BAR = D2/162 KGS/M


WEIGHT PER METER OF MAIN BAR = 12*12/162 KGS/M
WEIGHT PER METER OF MAIN BAR = 0.889 KGS/M

6. TOTAL WEIGHT OF MAIN BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF MAIN BARS = 11.368 * 0.889 KGS
TOTAL WEIGHT OF MAIN BARS = 10.105 KGS

SHAZEB NOMAN 108


QUANTITY SURVEY NOTES

STIRRUP BARS:
1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (HEIGHT OF NECK COLUMN / SPACING) + 1


NUMBER OF STIRRUPS BAR = (1.65 + 0.4 / 0.1) + 1
NUMBER OF STIRRUPS BAR = {1.95/0.1} + 1
NUMBER OF STIRRUPS BAR = 21 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *21 M
TOTAL LENGTH OF STIRRUP BARS = 23.184 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 23.184 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 9.159 KGS

SHAZEB NOMAN 109


QUANTITY SURVEY NOTES

NECK COLUMN REINFORCEMENT ABSTRACT:


DIA OF BAR = 12mm,
WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (122)/162 Kg/m = 0.889 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.889 = 10.667 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 12mm = 181.888 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 181.888 / 10.667
= 17.05 BARS APPROXIMATELY EQUAL TO 18 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER INCREASING BARS FROM 17.05 TO 18 NO.S
ACTUAL WEIGHT = 18 X 10.667
= 192.00 Kgs

DIA OF BAR = 8mm,


WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (82)/162 Kg/m = 0.395 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.395 = 4.741 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 8mm = 164.864 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 164.864 / 4.741
= 34.78 BARS APPROXIMATELY EQUAL TO 35 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER INCREASING BARS FROM 34.78 TO 35 NO.S
ACTUAL WEIGHT = 35 X 4.741
= 165.926 Kgs

SHAZEB NOMAN 110


QUANTITY SURVEY NOTES

34. TIE BEAM REINFORCEMENT CALCULATIONS : ON AXIS A BETWEEN 1 - 3

SHAZEB NOMAN 111


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS A BETWEEN 1 - 3


MAIN BARS:
1. LENGTH OF TOP BAR = 4.7 M
LENGTH OF BOTTOM BAR = 4.7 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.7 * 2 M = 9.4 M
TOTAL LENGTH OF BOTTOM BARS = 4.7 * 2 M = 9.4 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 9.4 * 0.617 KGS = 5.802 KGS
TOTAL WEIGHT OF BOTTOM BARS = 9.4 * 0.617 KGS = 5.802 KGS

SHAZEB NOMAN 112


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS:


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.45/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 35.5 = 36 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *36 M
TOTAL LENGTH OF STIRRUP BARS = 39.744 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 39.744 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 15.701 KGS

SHAZEB NOMAN 113


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS A BETWEEN 3 - 6


MAIN BARS:
1. LENGTH OF TOP BAR = 6.35 M
LENGTH OF BOTTOM BAR = 6.35 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 6.35 * 2 M = 12.7 M
TOTAL LENGTH OF BOTTOM BARS = 6.35 * 2 M = 12.7 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 12.7 * 0.617 KGS = 7.84 KGS
TOTAL WEIGHT OF BOTTOM BARS = 12.7 * 0.617 KGS = 7.84 KGS

SHAZEB NOMAN 114


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS:


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (5.15/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 53 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *53 M
TOTAL LENGTH OF STIRRUP BARS = 58.512 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 58.512 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 23.116 KGS

SHAZEB NOMAN 115


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS A BETWEEN 6 - 8


MAIN BARS:
1. LENGTH OF TOP BAR = 4.35 M
LENGTH OF BOTTOM BAR = 4.35 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.35 * 2 M = 8.7 M
TOTAL LENGTH OF BOTTOM BARS = 4.35 * 2 M = 8.7 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 8.7 * 0.617 KGS = 5.37 KGS
TOTAL WEIGHT OF BOTTOM BARS = 8.7 * 0.617 KGS = 5.37 KGS

SHAZEB NOMAN 116


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS:


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.1/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 32 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *32 M
TOTAL LENGTH OF STIRRUP BARS = 35.328 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 41.54 * 0.39 KGS
TOTAL WEIGHT OF STIRRUP BARS = 13.957 KGS

SHAZEB NOMAN 117


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS B BETWEEN 2 - 4


MAIN BARS:
1. LENGTH OF TOP BAR = 4.8 M
LENGTH OF BOTTOM BAR = 4.8 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.8 * 2 M = 9.6 M
TOTAL LENGTH OF BOTTOM BARS = 4.8 * 2 M = 9.6 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 9.6 * 0.617 KGS = 5.926 KGS
TOTAL WEIGHT OF BOTTOM BARS = 9.6 * 0.617 KGS = 5.926 KGS

SHAZEB NOMAN 118


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS:


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.34) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.55/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 37 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *37 M
TOTAL LENGTH OF STIRRUP BARS = 40.848 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 40.848 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 16.137 KGS

SHAZEB NOMAN 119


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS B BETWEEN 4 - 5


MAIN BARS:
1. LENGTH OF TOP BAR = 2.3 M
LENGTH OF BOTTOM BAR = 2.3

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 2.3 * 2 M = 4.6 M
TOTAL LENGTH OF BOTTOM BARS = 2.3 * 2 M = 4.6 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 4.6 * 0.617 KGS = 2.84 KGS
TOTAL WEIGHT OF BOTTOM BARS = 4.6 * 0.617 KGS = 2.84 KGS

SHAZEB NOMAN 120


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS:


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (1.1/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 12 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *12 M
TOTAL LENGTH OF STIRRUP BARS = 13.248 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 13.248 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 5.234 KGS

SHAZEB NOMAN 121


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS B BETWEEN 5 - 7


MAIN BARS:
1. LENGTH OF TOP BAR = 4.85 M
LENGTH OF BOTTOM BAR = 4.85 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.85 * 2 M = 9.7 M
TOTAL LENGTH OF BOTTOM BARS = 4.85 * 2 M = 9.7 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 9.7 * 0.617 KGS = 5.988 KGS
TOTAL WEIGHT OF BOTTOM BARS = 9.7 * 0.617 KGS = 5.988 KGS

SHAZEB NOMAN 122


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS:


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.65/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 38 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *38 M
TOTAL LENGTH OF STIRRUP BARS = 41.952 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 41.952 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 16.574 KGS

SHAZEB NOMAN 123


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS D BETWEEN 2 - 4


MAIN BARS:
1. LENGTH OF TOP BAR = 4.8 M
LENGTH OF BOTTOM BAR = 4.8 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.8 * 2 M = 9.6 M
TOTAL LENGTH OF BOTTOM BARS = 4.8 * 2 M = 9.6 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 9.6 * 0.617 KGS = 5.926 KGS
TOTAL WEIGHT OF BOTTOM BARS = 9.6 * 0.617 KGS = 5.926 KGS

SHAZEB NOMAN 124


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS:


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.34) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.55/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 37 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *37 M
TOTAL LENGTH OF STIRRUP BARS = 40.848 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 40.848 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 16.137 KGS

SHAZEB NOMAN 125


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS D BETWEEN 4 - 5


MAIN BARS:
1. LENGTH OF TOP BAR = 2.3 M
LENGTH OF BOTTOM BAR = 2.3

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 2.3 * 2 M = 4.6 M
TOTAL LENGTH OF BOTTOM BARS = 2.3 * 2 M = 4.6 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 4.6 * 0.617 KGS = 2.84 KGS
TOTAL WEIGHT OF BOTTOM BARS = 4.6 * 0.617 KGS = 2.84 KGS

SHAZEB NOMAN 126


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS:


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (1.1/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 12 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *12 M
TOTAL LENGTH OF STIRRUP BARS = 13.248 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 13.248 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 5.234 KGS

SHAZEB NOMAN 127


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS D BETWEEN 5 - 7


MAIN BARS:
1. LENGTH OF TOP BAR = 4.85 M
LENGTH OF BOTTOM BAR = 4.85 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.85 * 2 M = 9.7 M
TOTAL LENGTH OF BOTTOM BARS = 4.85 * 2 M = 9.7 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 9.7 * 0.617 KGS = 5.988 KGS
TOTAL WEIGHT OF BOTTOM BARS = 9.7 * 0.617 KGS = 5.988 KGS

SHAZEB NOMAN 128


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS:


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.65/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 38 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *38 M
TOTAL LENGTH OF STIRRUP BARS = 41.952 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 41.952 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 16.574 KGS

SHAZEB NOMAN 129


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS E BETWEEN 1 - 3


MAIN BARS:
1. LENGTH OF TOP BAR = 4.7 M
LENGTH OF BOTTOM BAR = 4.7 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.7 * 2 M = 9.4 M
TOTAL LENGTH OF BOTTOM BARS = 4.7 * 2 M = 9.4 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 9.4 * 0.617 KGS = 5.802 KGS
TOTAL WEIGHT OF BOTTOM BARS = 9.4 * 0.617 KGS = 5.802 KGS

SHAZEB NOMAN 130


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS:


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.34) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.45/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 35.5 = 36 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *36 M
TOTAL LENGTH OF STIRRUP BARS = 39.744 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 39.744 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 15.701 KGS

SHAZEB NOMAN 131


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS E BETWEEN 3 - 6


MAIN BARS:
1. LENGTH OF TOP BAR = 6.35 M
LENGTH OF BOTTOM BAR = 6.35 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 6.35 * 2 M = 12.7 M
TOTAL LENGTH OF BOTTOM BARS = 6.35 * 2 M = 12.7 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 12.7 * 0.617 KGS = 7.84 KGS
TOTAL WEIGHT OF BOTTOM BARS = 12.7 * 0.617 KGS = 7.84 KGS

SHAZEB NOMAN 132


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS:


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (5.15/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 53 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *53 M
TOTAL LENGTH OF STIRRUP BARS = 58.512 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 58.512 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 23.116 KGS

SHAZEB NOMAN 133


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS E BETWEEN 6 - 8


MAIN BARS:
1. LENGTH OF TOP BAR = 4.35 M
LENGTH OF BOTTOM BAR = 4.35 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.35 * 2 M = 8.7 M
TOTAL LENGTH OF BOTTOM BARS = 4.35 * 2 M = 8.7 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 8.7 * 0.617 KGS = 5.37 KGS
TOTAL WEIGHT OF BOTTOM BARS = 8.7 * 0.617 KGS = 5.37 KGS

SHAZEB NOMAN 134


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS:


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.1/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 32 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *32 M
TOTAL LENGTH OF STIRRUP BARS = 35.328 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 41.54 * 0.39 KGS
TOTAL WEIGHT OF STIRRUP BARS = 13.957 KGS

SHAZEB NOMAN 135


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS 1 BETWEEN A - C


LENGTH OF MAIN BARS = 3.4m
MAIN BARS:
1. LENGTH OF TOP BAR = 3.4 M
LENGTH OF BOTTOM BAR = 3.4 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 3.4 * 2 M = 6.8 M
TOTAL LENGTH OF BOTTOM BARS = 3.4 * 2 M = 6.8 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 6.8 * 0.617 KGS = 4.198 KGS
TOTAL WEIGHT OF BOTTOM BARS = 6.8 * 0.617 KGS = 4.198 KGS

SHAZEB NOMAN 136


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS: ACTUAL LENGTH OF TIE BEAM = 1.95m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (1.95/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 21 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *21 M
TOTAL LENGTH OF STIRRUP BARS = 23.184 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 23.184 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 9.159 KGS

SHAZEB NOMAN 137


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS 1 BETWEEN C - E


LENGTH OF MAIN BARS = 5.2m
MAIN BARS:
1. LENGTH OF TOP BAR = 5.2 M
LENGTH OF BOTTOM BAR = 5.2 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 5.2 * 2 M = 10.4 M
TOTAL LENGTH OF BOTTOM BARS = 5.2 * 2 M = 10.4 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 10.4 * 0.617 KGS = 6.42 KGS
TOTAL WEIGHT OF BOTTOM BARS = 10.4 * 0.617 KGS = 6.42 KGS

SHAZEB NOMAN 138


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS: ACTUAL LENGTH OF TIE BEAM = 3.75m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.75/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 39 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *39 M
TOTAL LENGTH OF STIRRUP BARS = 43.056 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 43.056 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 17.01 KGS

SHAZEB NOMAN 139


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS 2 BETWEEN B - D


LENGTH OF MAIN BARS = 3.8m
MAIN BARS:
1. LENGTH OF TOP BAR = 3.8 M
LENGTH OF BOTTOM BAR = 3.8 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 3.8 * 2 M = 7.6 M
TOTAL LENGTH OF BOTTOM BARS = 3.8 * 2 M = 7.6 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 7.6 * 0.617 KGS = 4.691 KGS
TOTAL WEIGHT OF BOTTOM BARS = 7.6 * 0.617 KGS = 4.691 KGS

SHAZEB NOMAN 140


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS: ACTUAL LENGTH OF TIE BEAM = 2.2m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (2.2/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 23 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *23 M
TOTAL LENGTH OF STIRRUP BARS = 25.392 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 25.392 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 10.031 KGS

SHAZEB NOMAN 141


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS 4 BETWEEN B - D


LENGTH OF MAIN BARS = 3.8m
MAIN BARS:
1. LENGTH OF TOP BAR = 3.8 M
LENGTH OF BOTTOM BAR = 3.8 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 3.8 * 2 M = 7.6 M
TOTAL LENGTH OF BOTTOM BARS = 3.8 * 2 M = 7.6 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 7.6 * 0.617 KGS = 4.691 KGS
TOTAL WEIGHT OF BOTTOM BARS = 7.6 * 0.617 KGS = 4.691 KGS

SHAZEB NOMAN 142


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS: ACTUAL LENGTH OF TIE BEAM = 2.2m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (2.2/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 23 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *23 M
TOTAL LENGTH OF STIRRUP BARS = 25.392 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 25.392 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 10.031 KGS

SHAZEB NOMAN 143


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS 5 BETWEEN B - D


LENGTH OF MAIN BARS = 3.8m
MAIN BARS:
1. LENGTH OF TOP BAR = 3.8 M
LENGTH OF BOTTOM BAR = 3.8 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 3.8 * 2 M = 7.6 M
TOTAL LENGTH OF BOTTOM BARS = 3.8 * 2 M = 7.6 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 7.6 * 0.617 KGS = 4.691 KGS
TOTAL WEIGHT OF BOTTOM BARS = 7.6 * 0.617 KGS = 4.691 KGS

SHAZEB NOMAN 144


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS: ACTUAL LENGTH OF TIE BEAM = 2.2m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (2.2/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 23 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *23 M
TOTAL LENGTH OF STIRRUP BARS = 25.392 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 25.392 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 10.031 KGS

SHAZEB NOMAN 145


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS 7 BETWEEN B - D


LENGTH OF MAIN BARS = 3.8m
MAIN BARS:
1. LENGTH OF TOP BAR = 3.8 M
LENGTH OF BOTTOM BAR = 3.8 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 3.8 * 2 M = 7.6 M
TOTAL LENGTH OF BOTTOM BARS = 3.8 * 2 M = 7.6 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 7.6 * 0.617 KGS = 4.691 KGS
TOTAL WEIGHT OF BOTTOM BARS = 7.6 * 0.617 KGS = 4.691 KGS

SHAZEB NOMAN 146


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS: ACTUAL LENGTH OF TIE BEAM = 2.2m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (2.2/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 23 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *23 M
TOTAL LENGTH OF STIRRUP BARS = 25.392 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 25.392 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 10.031 KGS

SHAZEB NOMAN 147


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS 8 BETWEEN A - C


LENGTH OF MAIN BARS = 3.4m
MAIN BARS:
1. LENGTH OF TOP BAR = 3.4 M
LENGTH OF BOTTOM BAR = 3.4 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 3.4 * 2 M = 6.8 M
TOTAL LENGTH OF BOTTOM BARS = 3.4 * 2 M = 6.8 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 6.8 * 0.617 KGS = 4.198 KGS
TOTAL WEIGHT OF BOTTOM BARS = 6.8 * 0.617 KGS = 4.198 KGS

SHAZEB NOMAN 148


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS: ACTUAL LENGTH OF TIE BEAM = 1.95m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (1.95/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 21 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *21 M
TOTAL LENGTH OF STIRRUP BARS = 23.184 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 23.184 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 9.159 KGS

SHAZEB NOMAN 149


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT CALCULATIONS: ON AXIS 8 BETWEEN C - E


LENGTH OF MAIN BARS = 5.2m
MAIN BARS:
1. LENGTH OF TOP BAR = 5.2 M
LENGTH OF BOTTOM BAR = 5.2 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 5.2 * 2 M = 10.4 M
TOTAL LENGTH OF BOTTOM BARS = 5.2 * 2 M = 10.4 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 10.4 * 0.617 KGS = 6.42 KGS
TOTAL WEIGHT OF BOTTOM BARS = 10.4 * 0.617 KGS = 6.42 KGS

SHAZEB NOMAN 150


QUANTITY SURVEY NOTES

TIE BEAM STIRRUP BARS: ACTUAL LENGTH OF TIE BEAM = 3.75m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH TIE BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.75/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 39 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *39 M
TOTAL LENGTH OF STIRRUP BARS = 43.056 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 43.056 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 17.01 KGS

SHAZEB NOMAN 151


QUANTITY SURVEY NOTES

TIE BEAM REINFORCEMENT ABSTRACT:


DIA OF BAR = 10mm,
WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (102)/162 Kg/m = 0.617 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.617 = 7.407 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 10mm = 215.062 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 215.062 / 7.407
= 29.03 BARS APPROXIMATELY EQUAL TO 29 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER DECREASING BARS FROM 29.03 TO 29 NO.S
ACTUAL WEIGHT = 29 X 7.407
= 214.815 Kgs

DIA OF BAR = 8mm,


WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (82)/162 Kg/m = 0.395 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.395 = 4.741 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 8mm = 273.901 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 273.901 / 4.741
= 57.78 BARS APPROXIMATELY EQUAL TO 58 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER INCREASING BARS FROM 57.78 TO 58 NO.S
ACTUAL WEIGHT = 58 X 4.741
= 274.963 Kgs

SHAZEB NOMAN 152


QUANTITY SURVEY NOTES

35. PLINTH BEAM REINFORCEMENT CALCULATIONS : ON AXIS A BETWEEN 1 - 3

SHAZEB NOMAN 153


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS A BETWEEN 1 - 3


LENGTH OF MAIN BARS = 4.65m
MAIN BARS:
1. LENGTH OF TOP BAR = 4.65 M
LENGTH OF BOTTOM BAR = 4.65 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.65 * 2 M = 9.3 M
TOTAL LENGTH OF BOTTOM BARS = 4.65 * 2 M = 9.3 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 9.3 * 0.617 KGS = 5.741 KGS
TOTAL WEIGHT OF BOTTOM BARS = 9.3 * 0.617 KGS = 5.741 KGS

SHAZEB NOMAN 154


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 4.35m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (4.35/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 44.5 = 45 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *45 M
TOTAL LENGTH OF STIRRUP BARS = 49.68 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 49.68 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 19.627 KGS

SHAZEB NOMAN 155


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS A BETWEEN 3 - 6


MAIN BARS: LENGTH OF MAIN BARS = 6.35
1. LENGTH OF TOP BAR = 6.35 M
LENGTH OF BOTTOM BAR = 6.35 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 6.35 * 2 M = 12.7 M
TOTAL LENGTH OF BOTTOM BARS = 6.35 * 2 M = 12.7 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 12.7 * 0.617 KGS = 7.84 KGS
TOTAL WEIGHT OF BOTTOM BARS = 12.7 * 0.617 KGS = 7.84 KGS

SHAZEB NOMAN 156


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 6.05m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (6.05/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 62 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *62 M
TOTAL LENGTH OF STIRRUP BARS = 68.448 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 68.448 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 27.041 KGS

SHAZEB NOMAN 157


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS A BETWEEN 6 - 8


MAIN BARS: LENGTH OF MAIN BARS = 4.3
1. LENGTH OF TOP BAR = 4.3 M
LENGTH OF BOTTOM BAR = 4.3 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.3 * 2 M = 8.6 M
TOTAL LENGTH OF BOTTOM BARS = 4.3 * 2 M = 8.6 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 8.6 * 0.617 KGS = 5.309 KGS
TOTAL WEIGHT OF BOTTOM BARS = 8.6 * 0.617 KGS = 5.309 KGS

SHAZEB NOMAN 158


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTAUL LENGTH OF PLINTH BEAM = 4.0m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (4/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 41 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *41 M
TOTAL LENGTH OF STIRRUP BARS = 45.264 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 45.264 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 17.882 KGS

SHAZEB NOMAN 159


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS B BETWEEN 2 - 4


MAIN BARS: LENGTH OF MAIN BARS = 4.75m
1. LENGTH OF TOP BAR = 4.75 M
LENGTH OF BOTTOM BAR = 4.75 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.75 * 2 M = 9.5 M
TOTAL LENGTH OF BOTTOM BARS = 4.75 * 2 M = 9.5 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 9.5 * 0.617 KGS = 5.864 KGS
TOTAL WEIGHT OF BOTTOM BARS = 9.5 * 0.617 KGS = 5.864 KGS

SHAZEB NOMAN 160


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 4.45m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.34) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (4.45/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 46 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *46 M
TOTAL LENGTH OF STIRRUP BARS = 50.784 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 50.784 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 20.063 KGS

SHAZEB NOMAN 161


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS B BETWEEN 4 - 5


MAIN BARS: LENGTH OF MAIN BARS = 2.3m
1. LENGTH OF TOP BAR = 2.3 M
LENGTH OF BOTTOM BAR = 2.3

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 2.3 * 2 M = 4.6 M
TOTAL LENGTH OF BOTTOM BARS = 2.3 * 2 M = 4.6 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 4.6 * 0.617 KGS = 2.84 KGS
TOTAL WEIGHT OF BOTTOM BARS = 4.6 * 0.617 KGS = 2.84 KGS

SHAZEB NOMAN 162


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 2.0m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (2.0/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 21 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *21 M
TOTAL LENGTH OF STIRRUP BARS = 23.184 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 23.184 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 9.159 KGS

SHAZEB NOMAN 163


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS B BETWEEN 5 - 7


MAIN BARS: LENGTH OF MAIN BAR = 4.85m
1. LENGTH OF TOP BAR = 4.85 M
LENGTH OF BOTTOM BAR = 4.85 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.85 * 2 M = 9.7 M
TOTAL LENGTH OF BOTTOM BARS = 4.85 * 2 M = 9.7 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 9.7 * 0.617 KGS = 5.988 KGS
TOTAL WEIGHT OF BOTTOM BARS = 9.7 * 0.617 KGS = 5.988 KGS

SHAZEB NOMAN 164


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 4.55m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (4.55/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 47 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *47 M
TOTAL LENGTH OF STIRRUP BARS = 51.888 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 51.888 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 20.499 KGS

SHAZEB NOMAN 165


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS D BETWEEN 2 - 4


MAIN BARS: LENGTH OF MAIN BARS = 4.75m
1. LENGTH OF TOP BAR = 4.75 M
LENGTH OF BOTTOM BAR = 4.75 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.75 * 2 M = 9.5 M
TOTAL LENGTH OF BOTTOM BARS = 4.75 * 2 M = 9.5 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 9.5 * 0.617 KGS = 5.864 KGS
TOTAL WEIGHT OF BOTTOM BARS = 9.5 * 0.617 KGS = 5.864 KGS

SHAZEB NOMAN 166


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 4.45m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.34) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (4.45/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 46 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *46 M
TOTAL LENGTH OF STIRRUP BARS = 50.784 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 50.784 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 20.063 KGS

SHAZEB NOMAN 167


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS D BETWEEN 4 - 5


MAIN BARS: LENGTH OF MAIN BARS = 2.3m
1. LENGTH OF TOP BAR = 2.3 M
LENGTH OF BOTTOM BAR = 2.3

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 2.3 * 2 M = 4.6 M
TOTAL LENGTH OF BOTTOM BARS = 2.3 * 2 M = 4.6 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 4.6 * 0.617 KGS = 2.84 KGS
TOTAL WEIGHT OF BOTTOM BARS = 4.6 * 0.617 KGS = 2.84 KGS

SHAZEB NOMAN 168


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 2.0m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (2.0/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 21 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *21 M
TOTAL LENGTH OF STIRRUP BARS = 23.184 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 23.184 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 9.159 KGS

SHAZEB NOMAN 169


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS D BETWEEN 5 - 7


MAIN BARS: LENGTH OF MAIN BAR = 4.85m
1. LENGTH OF TOP BAR = 4.85 M
LENGTH OF BOTTOM BAR = 4.85 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.85 * 2 M = 9.7 M
TOTAL LENGTH OF BOTTOM BARS = 4.85 * 2 M = 9.7 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 9.7 * 0.617 KGS = 5.988 KGS
TOTAL WEIGHT OF BOTTOM BARS = 9.7 * 0.617 KGS = 5.988 KGS

SHAZEB NOMAN 170


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 4.55m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (4.55/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 47 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *47 M
TOTAL LENGTH OF STIRRUP BARS = 51.888 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 51.888 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 20.499 KGS

SHAZEB NOMAN 171


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS E BETWEEN 1 - 3


LENGTH OF MAIN BARS = 4.65m
MAIN BARS:
1. LENGTH OF TOP BAR = 4.65 M
LENGTH OF BOTTOM BAR = 4.65 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.65 * 2 M = 9.3 M
TOTAL LENGTH OF BOTTOM BARS = 4.65 * 2 M = 9.3 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 9.3 * 0.617 KGS = 5.741 KGS
TOTAL WEIGHT OF BOTTOM BARS = 9.3 * 0.617 KGS = 5.741 KGS

SHAZEB NOMAN 172


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 4.35m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.34) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (4.35/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 44.5 = 45 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *45 M
TOTAL LENGTH OF STIRRUP BARS = 49.68 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 49.68 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 19.627 KGS

SHAZEB NOMAN 173


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS E BETWEEN 3 - 6


MAIN BARS: LENGTH OF MAIN BARS = 6.35
1. LENGTH OF TOP BAR = 6.35 M
LENGTH OF BOTTOM BAR = 6.35 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 6.35 * 2 M = 12.7 M
TOTAL LENGTH OF BOTTOM BARS = 6.35 * 2 M = 12.7 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 12.7 * 0.617 KGS = 7.84 KGS
TOTAL WEIGHT OF BOTTOM BARS = 12.7 * 0.617 KGS = 7.84 KGS

SHAZEB NOMAN 174


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 6.05m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (6.05/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 62 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *62 M
TOTAL LENGTH OF STIRRUP BARS = 68.448 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 68.448 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 27.041 KGS

SHAZEB NOMAN 175


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS E BETWEEN 6 - 8


MAIN BARS: LENGTH OF MAIN BARS = 4.3
1. LENGTH OF TOP BAR = 4.3 M
LENGTH OF BOTTOM BAR = 4.3 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.3 * 2 M = 8.6 M
TOTAL LENGTH OF BOTTOM BARS = 4.3 * 2 M = 8.6 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 8.6 * 0.617 KGS = 5.309 KGS
TOTAL WEIGHT OF BOTTOM BARS = 8.6 * 0.617 KGS = 5.309 KGS

SHAZEB NOMAN 176


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTAUL LENGTH OF PLINTH BEAM = 4.0m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (4/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 41 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *41 M
TOTAL LENGTH OF STIRRUP BARS = 45.264 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 45.264 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 17.882 KGS

SHAZEB NOMAN 177


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS 1 BETWEEN A - C


MAIN BARS: LENGTH OF MAIN BARS = 3.35m

1. LENGTH OF TOP BAR = 3.35 M


LENGTH OF BOTTOM BAR = 3.35 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 3.35 * 2 M = 6.7 M
TOTAL LENGTH OF BOTTOM BARS = 3.35 * 2 M = 6.7 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 6.7 * 0.617 KGS = 4.136 KGS
TOTAL WEIGHT OF BOTTOM BARS = 6.7 * 0.617 KGS = 4.136 KGS

SHAZEB NOMAN 178


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 3.05m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.05/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 32 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *32 M
TOTAL LENGTH OF STIRRUP BARS = 35.328 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 35.328 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 13.957 KGS

SHAZEB NOMAN 179


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS 1 BETWEEN C - E


LENGTH OF MAIN BARS = 5.15m
MAIN BARS:
1. LENGTH OF TOP BAR = 5.15 M
LENGTH OF BOTTOM BAR = 5.15 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 5.15 * 2 M = 10.3 M
TOTAL LENGTH OF BOTTOM BARS = 5.15 * 2 M = 10.3 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 10.3 * 0.617 KGS = 6.358 KGS
TOTAL WEIGHT OF BOTTOM BARS = 10.4 * 0.617 KGS = 6.358 KGS

SHAZEB NOMAN 180


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 4.85m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (4.85/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 50 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *50 M
TOTAL LENGTH OF STIRRUP BARS = 55.2 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 55.2 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 21.807 KGS

SHAZEB NOMAN 181


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS 2 BETWEEN B - D


MAIN BARS: LENGTH OF MAIN BARS = 3.7m

1. LENGTH OF TOP BAR = 3.7 M


LENGTH OF BOTTOM BAR = 3.7 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 3.7 * 2 M = 7.4 M
TOTAL LENGTH OF BOTTOM BARS = 3.7 * 2 M = 7.4 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 7.4 * 0.617 KGS = 4.568 KGS
TOTAL WEIGHT OF BOTTOM BARS = 7.4 * 0.617 KGS = 4.568 KGS

SHAZEB NOMAN 182


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 3.4m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.4/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 35 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *35 M
TOTAL LENGTH OF STIRRUP BARS = 38.64 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 38.64 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 15.265 KGS

SHAZEB NOMAN 183


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS 4 BETWEEN B - D


MAIN BARS: LENGTH OF MAIN BARS = 3.7m

1. LENGTH OF TOP BAR = 3.7 M


LENGTH OF BOTTOM BAR = 3.7 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 3.7 * 2 M = 7.4 M
TOTAL LENGTH OF BOTTOM BARS = 3.7 * 2 M = 7.4 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 7.4 * 0.617 KGS = 4.568 KGS
TOTAL WEIGHT OF BOTTOM BARS = 7.4 * 0.617 KGS = 4.568 KGS

SHAZEB NOMAN 184


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 3.4m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.4/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 35 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *35 M
TOTAL LENGTH OF STIRRUP BARS = 38.64 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 38.64 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 15.265 KGS

SHAZEB NOMAN 185


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS 5 BETWEEN B - D


MAIN BARS: LENGTH OF MAIN BARS = 3.7m

1. LENGTH OF TOP BAR = 3.7 M


LENGTH OF BOTTOM BAR = 3.7 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 3.7 * 2 M = 7.4 M
TOTAL LENGTH OF BOTTOM BARS = 3.7 * 2 M = 7.4 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 7.4 * 0.617 KGS = 4.568 KGS
TOTAL WEIGHT OF BOTTOM BARS = 7.4 * 0.617 KGS = 4.568 KGS

SHAZEB NOMAN 186


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 3.4m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.4/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 35 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *35 M
TOTAL LENGTH OF STIRRUP BARS = 38.64 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 38.64 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 15.265 KGS

SHAZEB NOMAN 187


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS 5 BETWEEN D - E


MAIN BARS: LENGTH OF MAIN BARS = 3.3m

1. LENGTH OF TOP BAR = 3.3 M


LENGTH OF BOTTOM BAR = 3.3 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 3.3 * 2 M = 6.6 M
TOTAL LENGTH OF BOTTOM BARS = 3.3 * 2 M = 6.6 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 6.6 * 0.617 KGS = 4.074 KGS
TOTAL WEIGHT OF BOTTOM BARS = 6.6 * 0.617 KGS = 4.074 KGS

SHAZEB NOMAN 188


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 3.0m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.0/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 31 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *31 M
TOTAL LENGTH OF STIRRUP BARS = 34.224 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 34.244 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 13.521 KGS

SHAZEB NOMAN 189


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS 7 BETWEEN B - D


MAIN BARS: LENGTH OF MAIN BARS = 3.7m

1. LENGTH OF TOP BAR = 3.7 M


LENGTH OF BOTTOM BAR = 3.7 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 3.7 * 2 M = 7.4 M
TOTAL LENGTH OF BOTTOM BARS = 3.7 * 2 M = 7.4 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 7.4 * 0.617 KGS = 4.568 KGS
TOTAL WEIGHT OF BOTTOM BARS = 7.4 * 0.617 KGS = 4.568 KGS

SHAZEB NOMAN 190


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 3.4m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.4/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 35 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *35 M
TOTAL LENGTH OF STIRRUP BARS = 38.64 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 38.64 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 15.265 KGS

SHAZEB NOMAN 191


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS 8 BETWEEN A - C


MAIN BARS: LENGTH OF MAIN BARS = 3.35m

1. LENGTH OF TOP BAR = 3.35 M


LENGTH OF BOTTOM BAR = 3.35 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 3.35 * 2 M = 6.7 M
TOTAL LENGTH OF BOTTOM BARS = 3.35 * 2 M = 6.7 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 6.7 * 0.617 KGS = 4.136 KGS
TOTAL WEIGHT OF BOTTOM BARS = 6.7 * 0.617 KGS = 4.136 KGS

SHAZEB NOMAN 192


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 3.05m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.05/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 32 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *32 M
TOTAL LENGTH OF STIRRUP BARS = 35.328 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 35.328 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 13.957 KGS

SHAZEB NOMAN 193


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT CALCULATIONS: ON AXIS 8 BETWEEN C - E


LENGTH OF MAIN BARS = 5.15m
MAIN BARS:
1. LENGTH OF TOP BAR = 5.15 M
LENGTH OF BOTTOM BAR = 5.15 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 5.15 * 2 M = 10.3 M
TOTAL LENGTH OF BOTTOM BARS = 5.15 * 2 M = 10.3 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 10.3 * 0.617 KGS = 6.358 KGS
TOTAL WEIGHT OF BOTTOM BARS = 10.4 * 0.617 KGS = 6.358 KGS

SHAZEB NOMAN 194


QUANTITY SURVEY NOTES

PLINTH BEAM STIRRUP BARS: ACTUAL LENGTH OF PLINTH BEAM = 4.85m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (4.85/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 50 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *50 M
TOTAL LENGTH OF STIRRUP BARS = 55.2 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 55.2 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 21.807 KGS

SHAZEB NOMAN 195


QUANTITY SURVEY NOTES

PLINTH BEAM REINFORCEMENT ABSTRACT:


DIA OF BAR = 10mm,
WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (102)/162 Kg/m = 0.617 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.617 = 7.407 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 10mm = 220.988 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 220.988 / 7.407
= 29.83 BARS APPROXIMATELY EQUAL TO 30 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER INCREASING BARS FROM 29.83 TO 30 NO.S
ACTUAL WEIGHT = 30 X 7.407
= 222.222 Kgs

DIA OF BAR = 8mm,


WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (82)/162 Kg/m = 0.395 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.395 = 4.741 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 8mm = 374.651 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 374.651 / 4.741
= 79.03 BARS APPROXIMATELY EQUAL TO 79 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER DECREASING BARS FROM 79.03 TO 79 NO.S
ACTUAL WEIGHT = 79 X 4.741
= 374.519 Kgs

SHAZEB NOMAN 196


QUANTITY SURVEY NOTES

36. GRADE SLAB CALCULATIONS: GRADE SLAB - 1

COVER = 50 MM

SHAZEB NOMAN 197


QUANTITY SURVEY NOTES

GRADE SLAB REINFORCEMENT CALCULATIONS: GRADE SLAB - 1


X BAR:
1. LENGTH OF X- BAR = L – 0.05 - 0.05 M
LENGTH OF X- BAR = 4.45 – 0.05 – 0.05 M
LENGTH OF X- BAR = 4.35 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (3.4 – 0.05 – 0.05 / 0.1) +1
=34 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 4.35 * 34 M
TOTAL LENGTH OF X- BAR = 147.9 M

4. DIAMETER OF X- BAR = 8 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 8*8/162 KGS/M
WEIGHT PER METER OF X- BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 147.9 * 0.395 KGS
TOTAL WEIGHT OF X- BAR = 58.43 KGS

SHAZEB NOMAN 198


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L – 0.05 - 0.05 M
LENGTH OF Y-BAR = 3.4 - 0.05 – 0.05 M
LENGTH OF Y-BAR = 3.3 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (4.45 – 0.05 – 0.05 / 0.1) +1
= 44.5 = 45 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 3.3 * 45 M
TOTAL LENGTH OF Y-BAR = 148.5 M

4. DIAMETER OF Y-BAR = 8 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 8 * 8 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 148.5 * 0.395 KGS
TOTAL WEIGHT OF Y-BAR = 58.667 KGS

SHAZEB NOMAN 199


QUANTITY SURVEY NOTES

GRADE SLAB CALCULATIONS: GRADE SLAB - 2

COVER = 50 MM

SHAZEB NOMAN 200


QUANTITY SURVEY NOTES

GRADE SLAB REINFORCEMENT CALCULATIONS: GRADE SLAB - 2


X BAR:
1. LENGTH OF X- BAR = L – 0.05 - 0.05 M
LENGTH OF X- BAR = 2.0 – 0.05 – 0.05 M
LENGTH OF X- BAR = 1.9 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (3.4– 0.05 – 0.05 / 0.1) +1
=34 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 1.9 * 34 M
TOTAL LENGTH OF X- BAR = 64.6 M

4. DIAMETER OF X- BAR = 8 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 8*8/162 KGS/M
WEIGHT PER METER OF X- BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 64.6 * 0.395 KGS
TOTAL WEIGHT OF X- BAR = 25.521 KGS

SHAZEB NOMAN 201


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L – 0.05 - 0.05 M
LENGTH OF Y-BAR = 3.4 - 0.05 – 0.05 M
LENGTH OF Y-BAR = 3.3 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (2.0 – 0.05 – 0.05 / 0.1) +1
= 20 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 3.3 * 20 M
TOTAL LENGTH OF Y-BAR = 66 M

4. DIAMETER OF Y-BAR = 8 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 8 * 8 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 66 * 0.395 KGS
TOTAL WEIGHT OF Y-BAR = 26.074 KGS

SHAZEB NOMAN 202


QUANTITY SURVEY NOTES

GRADE SLAB CALCULATIONS: GRADE SLAB - 3

COVER = 50 MM

SHAZEB NOMAN 203


QUANTITY SURVEY NOTES

GRADE SLAB REINFORCEMENT CALCULATIONS: GRADE SLAB - 3


X BAR:
1. LENGTH OF X- BAR = L – 0.05 - 0.05 M
LENGTH OF X- BAR = 4.55 – 0.05 – 0.05 M
LENGTH OF X- BAR = 4.45 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (3.4 – 0.05 – 0.05 / 0.1) +1
=34 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 4.45 * 34 M
TOTAL LENGTH OF X- BAR = 151.3 M

4. DIAMETER OF X- BAR = 8 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 8*8/162 KGS/M
WEIGHT PER METER OF X- BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 151.3 * 0.395 KGS
TOTAL WEIGHT OF X- BAR = 59.773 KGS

SHAZEB NOMAN 204


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L – 0.05 - 0.05 M
LENGTH OF Y-BAR = 3.4 - 0.05 – 0.05 M
LENGTH OF Y-BAR = 3.3 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (4.55 – 0.05 – 0.05 / 0.1) +1
= 46 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 3.3 * 46 M
TOTAL LENGTH OF Y-BAR = 151.8 M

4. DIAMETER OF Y-BAR = 8 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 8 * 8 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 151.8 * 0.395 KGS
TOTAL WEIGHT OF Y-BAR = 59.970 KGS

SHAZEB NOMAN 205


QUANTITY SURVEY NOTES

GRADE SLAB - 4

COVER = 50 MM

SHAZEB NOMAN 206


QUANTITY SURVEY NOTES

GRADE SLAB REINFORCEMENT CALCULATIONS: GRADE SLAB - 4


X BAR:
1. LENGTH OF X- BAR = L – 0.05 - 0.05 M
LENGTH OF X- BAR = 7.84 – 0.05 – 0.05 M
LENGTH OF X- BAR = 7.74 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (3.0 – 0.05 – 0.05 / 0.1) +1
= 30 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 7.74 * 30 M
TOTAL LENGTH OF X- BAR = 230.2 M

4. DIAMETER OF X- BAR = 8 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 8*8/162 KGS/M
WEIGHT PER METER OF X- BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 230.2 * 0.395 KGS
TOTAL WEIGHT OF X- BAR = 91.733 KGS

SHAZEB NOMAN 207


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L – 0.05 - 0.05 M
LENGTH OF Y-BAR = 3.0 - 0.05 – 0.05 M
LENGTH OF Y-BAR = 2.9 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (7.84 – 0.05 – 0.05 / 0.1) +1
= 78 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 2.9 * 78 M
TOTAL LENGTH OF Y-BAR = 226.2 M

4. DIAMETER OF Y-BAR = 8 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 8 * 8 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 226.2 * 0.395 KGS
TOTAL WEIGHT OF Y-BAR = 89.363 KGS

SHAZEB NOMAN 208


QUANTITY SURVEY NOTES

GRADE SLAB - 5

COVER = 50 MM

SHAZEB NOMAN 209


QUANTITY SURVEY NOTES

GRADE SLAB REINFORCEMENT CALCULATIONS: GRADE SLAB - 5


X BAR:
1. LENGTH OF X- BAR = L – 0.05 - 0.05 M
LENGTH OF X- BAR = 6.86 – 0.05 – 0.05 M
LENGTH OF X- BAR = 6.76 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (3.0 – 0.05 – 0.05 / 0.1) +1
=30 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 6.76 * 30 M
TOTAL LENGTH OF X- BAR = 202.8 M

4. DIAMETER OF X- BAR = 8 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 8*8/162 KGS/M
WEIGHT PER METER OF X- BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 202.8 * 0.395 KGS
TOTAL WEIGHT OF X- BAR = 80.119 KGS

SHAZEB NOMAN 210


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L – 0.05 - 0.05 M
LENGTH OF Y-BAR = 3.0 - 0.05 – 0.05 M
LENGTH OF Y-BAR = 2.9 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (6.86 – 0.05 – 0.05 / 0.1) +1
= 69 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 2.9 * 69 M
TOTAL LENGTH OF Y-BAR = 200.1 M

4. DIAMETER OF Y-BAR = 8 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 8 * 8 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 200.1 * 0.395 KGS
TOTAL WEIGHT OF Y-BAR = 79.052 KGS

SHAZEB NOMAN 211


QUANTITY SURVEY NOTES

GRADE SLAB - 6

COVER = 50 MM

SHAZEB NOMAN 212


QUANTITY SURVEY NOTES

GRADE SLAB REINFORCEMENT CALCULATIONS: GRADE SLAB - 6


X BAR: NOTE: ADD 50D FOR OVERLAPPING BCOZ LENGTH IS MORE THAN 12m
1. LENGTH OF X- BAR = L – 0.05 - 0.05 + 50D M
LENGTH OF X- BAR = 15 – 0.05 – 0.05 + 50 * 0.008 M
LENGTH OF X- BAR = 15.3 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (1.2 – 0.05 – 0.05 / 0.1) +1
=12 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 15.3 * 12 M
TOTAL LENGTH OF X- BAR = 183.6 M

4. DIAMETER OF X- BAR = 8 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 8*8/162 KGS/M
WEIGHT PER METER OF X- BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 183.6 * 0.395 KGS
TOTAL WEIGHT OF X- BAR = 72.533 KGS

SHAZEB NOMAN 213


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L – 0.05 - 0.05 M
LENGTH OF Y-BAR = 1.2 - 0.05 – 0.05 M
LENGTH OF Y-BAR = 1.1 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (15 – 0.05 – 0.05 / 0.1) +1
= 151 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 1.1 * 151 M
TOTAL LENGTH OF Y-BAR = 166.1 M

4. DIAMETER OF Y-BAR = 8 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 8 * 8 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 166.1 * 0.395 KGS
TOTAL WEIGHT OF Y-BAR = 65.2 KGS

SHAZEB NOMAN 214


QUANTITY SURVEY NOTES

GRADE SLAB - 7

COVER = 50 MM

SHAZEB NOMAN 215


QUANTITY SURVEY NOTES

GRADE SLAB REINFORCEMENT CALCULATIONS: GRADE SLAB - 7


X BAR:
1. LENGTH OF X- BAR = L – 0.05 - 0.05 M
LENGTH OF X- BAR = 1.4– 0.05 – 0.05 M
LENGTH OF X- BAR = 1.3 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (4 – 0.05 – 0.05 / 0.1) +1
=40 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 1.3 * 40 M
TOTAL LENGTH OF X- BAR = 52 M

4. DIAMETER OF X- BAR = 8 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 8*8/162 KGS/M
WEIGHT PER METER OF X- BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 52 * 0.395 KGS
TOTAL WEIGHT OF X- BAR = 20.543 KGS

SHAZEB NOMAN 216


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L – 0.05 - 0.05 M
LENGTH OF Y-BAR = 4.0 - 0.05 – 0.05 M
LENGTH OF Y-BAR = 3.9 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (1.4 – 0.05 – 0.05 / 0.1) +1
= 14 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 3.9 * 14 M
TOTAL LENGTH OF Y-BAR = 54.6 M

4. DIAMETER OF Y-BAR = 8 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 8 * 8 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 54.6 * 0.395 KGS
TOTAL WEIGHT OF Y-BAR = 21.570 KGS

SHAZEB NOMAN 217


QUANTITY SURVEY NOTES

GRADE SLAB - 8

COVER = 50 MM

SHAZEB NOMAN 218


QUANTITY SURVEY NOTES

GRADE SLAB REINFORCEMENT CALCULATIONS: GRADE SLAB - 8


X BAR:
1. LENGTH OF X- BAR = L – 0.05 - 0.05 M
LENGTH OF X- BAR = 1.4– 0.05 – 0.05 M
LENGTH OF X- BAR = 1.3 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (4 – 0.05 – 0.05 / 0.1) +1
=40 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 1.3 * 40 M
TOTAL LENGTH OF X- BAR = 52 M

4. DIAMETER OF X- BAR = 8 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 8*8/162 KGS/M
WEIGHT PER METER OF X- BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 52 * 0.395 KGS
TOTAL WEIGHT OF X- BAR = 20.543 KGS

SHAZEB NOMAN 219


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L – 0.05 - 0.05 M
LENGTH OF Y-BAR = 4.0 - 0.05 – 0.05 M
LENGTH OF Y-BAR = 3.9 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (1.4 – 0.05 – 0.05 / 0.1) +1
= 14 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 3.9 * 14 M
TOTAL LENGTH OF Y-BAR = 54.6 M

4. DIAMETER OF Y-BAR = 8 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 8 * 8 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 54.6 * 0.395 KGS
TOTAL WEIGHT OF Y-BAR = 21.570 KGS

SHAZEB NOMAN 220


QUANTITY SURVEY NOTES

GRADE SLAB REINFORCEMENT ABSTRACT:

DIA OF BAR = 8mm,


WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (82)/162 Kg/m = 0.395 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.395 = 4.741 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 8mm = 851.081 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 851.081 / 4.741
= 179.53 BARS APPROXIMATELY EQUAL TO 180 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER INCREASING BARS FROM 179.53 TO 180 NO.S
ACTUAL WEIGHT = 180 X 4.741
= 853.333 Kgs

SHAZEB NOMAN 221


QUANTITY SURVEY NOTES

37. RETAINING WALL CALCULATIONS: ON AXIS A BETWEEN 1 - 8

SHAZEB NOMAN 222


QUANTITY SURVEY NOTES

SHAZEB NOMAN 223


QUANTITY SURVEY NOTES

RETAINING WALL REINFORCEMENT CALCULATIONS: ON AXIS A BETWEEN 1 - 8


X BAR:
1. LENGTH OF X- BAR = L M
LENGTH OF X- BAR = 15.3 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (1.33 – 0.05 – 0.05 / 0.1) +1
= 13.3 = 13 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 15.3 * 13 M
TOTAL LENGTH OF X- BAR = 198.9 M

4. DIAMETER OF X- BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 10*10/162 KGS/M
WEIGHT PER METER OF X- BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 198.9 * 0.617 KGS
TOTAL WEIGHT OF X- BAR = 122.778 KGS

SHAZEB NOMAN 224


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L – 0.05 + 0.26 + 50D + 10D M
LENGTH OF Y-BAR = 1.33 – 0.05 + 0.26 + 50 * 0.01 + 10 * 0.01 M
LENGTH OF Y-BAR = 2.14 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (L1 + L2 + L3 / 0.1) +1
= (4.35 + 6.05 + 4 / 0.1) +1
= (14.4 / 0.1) +1
= 145 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 2.14 * 145 M
TOTAL LENGTH OF Y-BAR = 310.3 M

4. DIAMETER OF Y-BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 10 * 10 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 310.3 * 0.617 KGS
TOTAL WEIGHT OF Y-BAR = 191.543 KGS

SHAZEB NOMAN 225


QUANTITY SURVEY NOTES

ON AXIS 1 BETWEEN A - E

SHAZEB NOMAN 226


QUANTITY SURVEY NOTES

SHAZEB NOMAN 227


QUANTITY SURVEY NOTES

RETAINING WALL REINFORCEMENT CALCULATIONS: ON AXIS 1 BETWEEN A - E


X BAR:
1. LENGTH OF X- BAR = L M
LENGTH OF X- BAR = 8.5 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (1.33 – 0.05 – 0.05 / 0.1) +1
= 13.3 = 13 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 8.5 * 13 M
TOTAL LENGTH OF X- BAR = 110.5 M

4. DIAMETER OF X- BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 10*10/162 KGS/M
WEIGHT PER METER OF X- BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 110.5 * 0.617 KGS
TOTAL WEIGHT OF X- BAR = 68.21 KGS

SHAZEB NOMAN 228


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L – 0.05 + 0.26 + 50D + 10D M
LENGTH OF Y-BAR = 1.33 – 0.05 + 0.26 + 50 * 0.01 + 10 * 0.01 M
LENGTH OF Y-BAR = 2.14 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (L1 + L2 / 0.1) +1
= (3.05 + 4.85 / 0.1) +1
= (7.9 / 0.1) +1
= 80 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 2.14 * 80 M
TOTAL LENGTH OF Y-BAR = 171.2 M

4. DIAMETER OF Y-BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 10 * 10 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 171.2 * 0.617 KGS
TOTAL WEIGHT OF Y-BAR = 105.679 KGS

SHAZEB NOMAN 229


QUANTITY SURVEY NOTES

ON AXIS E BETWEEN 1 - 8

SHAZEB NOMAN 230


QUANTITY SURVEY NOTES

SHAZEB NOMAN 231


QUANTITY SURVEY NOTES

RETAINING WALL REINFORCEMENT CALCULATIONS: ON AXIS E BETWEEN 1 - 8


X BAR:
1. LENGTH OF X- BAR = L M
LENGTH OF X- BAR = 15.3 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (1.33 – 0.05 – 0.05 / 0.1) +1
= 13.3 = 13 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 15.3 * 13 M
TOTAL LENGTH OF X- BAR = 198.9 M

4. DIAMETER OF X- BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 10*10/162 KGS/M
WEIGHT PER METER OF X- BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 198.9 * 0.617 KGS
TOTAL WEIGHT OF X- BAR = 122.778 KGS

SHAZEB NOMAN 232


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L – 0.05 + 0.26 + 50D + 10D M
LENGTH OF Y-BAR = 1.33 – 0.05 + 0.26 + 50 * 0.01 + 10 * 0.01 M
LENGTH OF Y-BAR = 2.14 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (L1 + L2 + L3 / 0.1) +1
= (4.35 + 6.05 + 4 / 0.1) +1
= (14.4 / 0.1) +1
= 145 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 2.14 * 145 M
TOTAL LENGTH OF Y-BAR = 310.3 M

4. DIAMETER OF Y-BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 10 * 10 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 310.3 * 0.617 KGS
TOTAL WEIGHT OF Y-BAR = 191.543 KGS

SHAZEB NOMAN 233


QUANTITY SURVEY NOTES

ON AXIS 8 BETWEEN A - E

SHAZEB NOMAN 234


QUANTITY SURVEY NOTES

SHAZEB NOMAN 235


QUANTITY SURVEY NOTES

RETAINING WALL REINFORCEMENT CALCULATIONS: ON AXIS 8 BETWEEN A - E


X BAR:
1. LENGTH OF X- BAR = L M
LENGTH OF X- BAR = 8.5 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (1.33 – 0.05 – 0.05 / 0.1) +1
= 13.3 = 13 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 8.5 * 13 M
TOTAL LENGTH OF X- BAR = 110.5 M

4. DIAMETER OF X- BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 10*10/162 KGS/M
WEIGHT PER METER OF X- BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 110.5 * 0.617 KGS
TOTAL WEIGHT OF X- BAR = 68.21 KGS

SHAZEB NOMAN 236


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L – 0.05 + 0.26 + 50D + 10D M
LENGTH OF Y-BAR = 1.33 – 0.05 + 0.26 + 50 * 0.01 + 10 * 0.01 M
LENGTH OF Y-BAR = 2.14 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (L1 + L2 / 0.1) +1
= (3.05 + 4.85 / 0.1) +1
= (7.9 / 0.1) +1
= 80 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 2.14 * 80 M
TOTAL LENGTH OF Y-BAR = 171.2 M

4. DIAMETER OF Y-BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 10 * 10 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 171.2 * 0.617 KGS
TOTAL WEIGHT OF Y-BAR = 105.679 KGS

SHAZEB NOMAN 237


QUANTITY SURVEY NOTES

RETAINING WALL REINFORCEMENT ABSTRACT:


DIA OF BAR = 10mm,
WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (102)/162 Kg/m = 0.617 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.617 = 7.407 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 10mm = 976.420 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 976.420 / 7.407
= 131.82 BARS APPROXIMATELY EQUAL TO 132 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER INCREASING BARS FROM 131.82 TO 132 NO.S
ACTUAL WEIGHT = 132 X 7.407
= 977.778 Kgs

SHAZEB NOMAN 238


QUANTITY SURVEY NOTES

38. RECTANGULAR SUMP CALCULATIONS: BOTTOM SLAB

SHAZEB NOMAN 239


QUANTITY SURVEY NOTES

BOTTOM SLAB REINFORCEMENT CALCULATIONS:


X BAR:
1. LENGTH OF X- BAR = L – 0.1 - 0.1 M
LENGTH OF X- BAR = 4 – 0.1 – 0.1 M
LENGTH OF X- BAR = 3.8 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (3 – 0.1 – 0.1 / 0.1) +1
= 29 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 3.8 * 29 M
TOTAL LENGTH OF X- BAR = 110.2 M

4. DIAMETER OF X- BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 10*10/162 KGS/M
WEIGHT PER METER OF X- BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 110.2 * 0.617 KGS
TOTAL WEIGHT OF X- BAR = 68.025 KGS

SHAZEB NOMAN 240


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L – 0.1 - 0.1 M
LENGTH OF Y-BAR = 3.0 - 0.1 – 0.1 M
LENGTH OF Y-BAR = 2.8 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (4 – 0.1 – 0.1 / 0.1) +1
= 39 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 2.8 * 39 M
TOTAL LENGTH OF Y-BAR = 109.2 M

4. DIAMETER OF Y-BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 10 * 10 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 109.2 * 0.617 KGS
TOTAL WEIGHT OF Y-BAR = 67.407 KGS

SHAZEB NOMAN 241


QUANTITY SURVEY NOTES

TOP SLAB:

SHAZEB NOMAN 242


QUANTITY SURVEY NOTES

TOP SLAB REINFORCEMENT CALCULATIONS:


X BAR:
1. LENGTH OF X- BAR = L – 0.1 - 0.1 M
LENGTH OF X- BAR = 4– 0.1 – 0.1 M
LENGTH OF X- BAR = 3.8 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (3 – 0.1 – 0.1 / 0.1) +1
= 29 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 3.8 * 29 M
TOTAL LENGTH OF X- BAR = 110.2 M

4. DIAMETER OF X- BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 10*10/162 KGS/M
WEIGHT PER METER OF X- BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 110.2 * 0.617 KGS
TOTAL WEIGHT OF X- BAR = 68.025 KGS

SHAZEB NOMAN 243


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L – 0.1 - 0.1 M
LENGTH OF Y-BAR = 3.0 - 0.1 – 0.1 M
LENGTH OF Y-BAR = 2.8 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (4 – 0.1 – 0.1 / 0.1) +1
= 39 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 2.8 * 39 M
TOTAL LENGTH OF Y-BAR = 109.2 M

4. DIAMETER OF Y-BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 10 * 10 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 109.2 * 0.617 KGS
TOTAL WEIGHT OF Y-BAR = 67.407 KGS

SHAZEB NOMAN 244


QUANTITY SURVEY NOTES

DEDUCTION OF COVER REINFORCEMENT FROM TOP SLAB:

SHAZEB NOMAN 245


QUANTITY SURVEY NOTES

DEDUCTION OF COVER REINFORCEMENT FROM TOP SLAB CALCULATIONS:


X BAR:
1. LENGTH OF X- BAR = L M
LENGTH OF X- BAR = 0.5 M

2. NUMBER OF X- BAR = 4 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 0.5 * 4 M
TOTAL LENGTH OF X- BAR = 2 M

4. DIAMETER OF X- BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 10*10/162 KGS/M
WEIGHT PER METER OF X- BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 2 * 0.617 KGS
TOTAL WEIGHT OF X- BAR = - 1.234 KGS

SHAZEB NOMAN 246


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L M
LENGTH OF Y-BAR = 0.5 M

2. NUMBER OF Y-BAR = 4 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 0.5 * 4 M
TOTAL LENGTH OF Y-BAR = 2 M

4. DIAMETER OF Y-BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 10 * 10 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 2 * 0.617 KGS
TOTAL WEIGHT OF Y-BAR = - 1.234 KGS

SHAZEB NOMAN 247


QUANTITY SURVEY NOTES

HORIZONTAL WALL REINFORCEMENT CLACULATION:

SHAZEB NOMAN 248


QUANTITY SURVEY NOTES

SHAZEB NOMAN 249


QUANTITY SURVEY NOTES

SHAZEB NOMAN 250


QUANTITY SURVEY NOTES

HORIZONTAL WALL REINFORCEMENT CLACULATION: NO.S = 2


X BAR:
1. LENGTH OF X- BAR = L – 0.1 - 0.1 + 50D + 50D M
LENGTH OF X- BAR = 4 – 0.1 – 0.1 + 50 * 0.01 + 50 * 0.01 M
LENGTH OF X- BAR = 4.8 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (2 / 0.1) +1
= 21 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 4.8 * 21 M
TOTAL LENGTH OF X- BAR = 100.8 M

4. DIAMETER OF X- BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 10*10/162 KGS/M
WEIGHT PER METER OF X- BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER * NO.S KGS
TOTAL WEIGHT OF X- BAR = 100.8 * 0.617 * 2 KGS
TOTAL WEIGHT OF X- BAR = 124.44 KGS

SHAZEB NOMAN 251


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L + 0.1 + 0.1 + 16D + 16D M
LENGTH OF Y-BAR = 2.0 + 0.1 + 0.1 + 16 * 0.01 + 16 * 0.01 M
LENGTH OF Y-BAR = 3.96 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (4 – 0.1 – 0.1 / 0.1) +1
= 39 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 3.96 * 39 M
TOTAL LENGTH OF Y-BAR = 154.4 M

4. DIAMETER OF Y-BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 10 * 10 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER * NO.S KGS
TOTAL WEIGHT OF Y-BAR = 154.4 * 0.617 * 2 KGS
TOTAL WEIGHT OF Y-BAR = 190.67 KGS

SHAZEB NOMAN 252


QUANTITY SURVEY NOTES

VERTICAL WALL REINFORCEMENT CLACULATION: NO.S = 2


X BAR:
1. LENGTH OF X- BAR = L M
LENGTH OF X- BAR = 2.8 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (2 / 0.1) +1
= 21 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 2.8 * 21 M
TOTAL LENGTH OF X- BAR = 58.8 M

4. DIAMETER OF X- BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 10*10/162 KGS/M
WEIGHT PER METER OF X- BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER * NO.S KGS
TOTAL WEIGHT OF X- BAR = 58.8 * 0.617 * 2 KGS
TOTAL WEIGHT OF X- BAR = 72.593 KGS

SHAZEB NOMAN 253


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L + 0.1 + 0.1 + 16D + 16D M
LENGTH OF Y-BAR = 2.0 + 0.1 + 0.1 + 16 * 0.01 + 16 * 0.01 M
LENGTH OF Y-BAR = 3.96 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (3 – 0.1 – 0.1 / 0.1) +1
= 29 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 3.96 * 29 M
TOTAL LENGTH OF Y-BAR = 114.8 M

4. DIAMETER OF Y-BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 10 * 10 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER * NO.S KGS
TOTAL WEIGHT OF Y-BAR = 114.8 * 0.617 * 2 KGS
TOTAL WEIGHT OF Y-BAR = 141.78 KGS

SHAZEB NOMAN 254


QUANTITY SURVEY NOTES

RECTANGULAR SUMP REINFORCEMENT ABSTRACT:


DIA OF BAR = 10mm,
WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (102)/162 Kg/m = 0.617 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.617 = 7.407 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 10mm = 797.877 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 797.877 / 7.407
= 107.71 BARS APPROXIMATELY EQUAL TO 108 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER INCREASING BARS FROM 107.71 TO 108 NO.S
ACTUAL WEIGHT = 108 X 7.407
= 800.00 Kgs

SHAZEB NOMAN 255


QUANTITY SURVEY NOTES

39. SUB STRUCTURE REINFORCEMENT ABSTRACT: PLZ CHECK EXCEL FILE

SHAZEB NOMAN 256


QUANTITY SURVEY NOTES

40. BOQ OF SUB STRUCTURE REINFORCEMENT: PLZ CHECK EXCEL FILE

SHAZEB NOMAN 257


QUANTITY SURVEY NOTES

SUPER STRUCTURE REINFORCEMENT CALCULATION 41. FLOOR COLUMN AT BOUNDARY:

SHAZEB NOMAN 258


QUANTITY SURVEY NOTES

MAIN BARS:
1. LENGTH OF MAIN BAR = L – 0.05 M
LENGTH OF MAIN BAR = 1.8 – 0.05 M
LENGTH OF MAIN BAR = 1.75 M

2. NUMBER OF MAIN BARS = 4 (GIVEN)

3. TOTAL LENGTH OF MAIN BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF MAIN BARS = 1.75 * 4 M
TOTAL LENGTH OF MAIN BARS = 7 M

4. DIAMETER OF MAIN BAR = 12 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF MAIN BAR = D2/162 KGS/M


WEIGHT PER METER OF MAIN BAR = 12*12/162 KGS/M
WEIGHT PER METER OF MAINBAR = 0.889 KGS/M

6. TOTAL WEIGHT OF MAIN BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF MAIN BARS = 7 * 0.889 KGS
TOTAL WEIGHT OF MAIN BARS = 19 KGS

SHAZEB NOMAN 259


QUANTITY SURVEY NOTES

FLOOR COLUMN STIRRUP BARS:


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH FLOOR COLUMN / SPACING) + 1


NUMBER OF STIRRUPS BAR = (1.8 - 0.05/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 19 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *19 M
TOTAL LENGTH OF STIRRUP BARS = 20.976 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 20.976 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 8.287 KGS

SHAZEB NOMAN 260


QUANTITY SURVEY NOTES

FLOOR COLUMN AT ROOMS:

SHAZEB NOMAN 261


QUANTITY SURVEY NOTES

MAIN BARS:
1. LENGTH OF MAIN BAR = L – 0.05 M
LENGTH OF MAIN BAR = 3.15 – 0.05 M
LENGTH OF MAIN BAR = 3.1 M

2. NUMBER OF MAIN BARS = 4 (GIVEN)

3. TOTAL LENGTH OF MAIN BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF MAIN BARS = 3.1 * 4 M
TOTAL LENGTH OF MAIN BARS = 12.4 M

4. DIAMETER OF MAIN BAR = 12 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF MAIN BAR = D2/162 KGS/M


WEIGHT PER METER OF MAIN BAR = 12*12/162 KGS/M
WEIGHT PER METER OF MAINBAR = 0.889 KGS/M

6. TOTAL WEIGHT OF MAIN BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF MAIN BARS = 12.4 * 0.889 KGS
TOTAL WEIGHT OF MAIN BARS = 11.022 KGS

SHAZEB NOMAN 262


QUANTITY SURVEY NOTES

FLOOR COLUMN STIRRUP BARS:


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH FLOOR COLUMN / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.15 - 0.05/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 32 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *32 M
TOTAL LENGTH OF STIRRUP BARS = 35.328 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 35.238 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 13.957 KGS

SHAZEB NOMAN 263


QUANTITY SURVEY NOTES

FLOOR COLUMN REINFORCEMENT ABSTRACT:


DIA OF BAR = 12mm,
WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (122)/162 Kg/m = 0.889 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.889 = 10.667 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 10mm = 150.4 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 150.4 / 10.667
= 14.1 BARS APPROXIMATELY EQUAL TO 14 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER DECREASING BARS FROM 14.1 TO 14 NO.S
ACTUAL WEIGHT = 14 X 10.667
= 149.333 Kgs

DIA OF BAR = 8mm,


WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (82)/162 Kg/m = 0.395 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.395 = 4.741 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 8mm = 194.522 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 194.522 / 4.741
= 41.03 BARS APPROXIMATELY EQUAL TO 41 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER INCREASING BARS FROM 41.03 TO 41 NO.S
ACTUAL WEIGHT = 41 X 4.741
= 194.37 Kgs

SHAZEB NOMAN 264


QUANTITY SURVEY NOTES

SHAZEB NOMAN 265


QUANTITY SURVEY NOTES

42. FLOOR BEAM CALCULATIONS : ON AXIS B BETWEEN 2 - 4

SHAZEB NOMAN 266


QUANTITY SURVEY NOTES

FLOOR BEAM REINFORCEMENT CALCULATIONS: ON AXIS B BETWEEN 2 - 4


MAIN BARS: LENGTH OF MAIN BARS = 4.75m
1. LENGTH OF TOP BAR = 4.75 M
LENGTH OF BOTTOM BAR = 4.75 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.75 * 2 M = 9.5 M
TOTAL LENGTH OF BOTTOM BARS = 4.75 * 2 M = 9.5 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 9.5 * 0.617 KGS = 5.864 KGS
TOTAL WEIGHT OF BOTTOM BARS = 9.5 * 0.617 KGS = 5.864 KGS

SHAZEB NOMAN 267


QUANTITY SURVEY NOTES

FLOOR BEAM STIRRUP BARS: ACTUAL LENGTH OF FLOOR BEAM = 4.45m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH FLOOR BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (4.45/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 46 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *46 M
TOTAL LENGTH OF STIRRUP BARS = 50.784 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 50.784 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 20.063 KGS

SHAZEB NOMAN 268


QUANTITY SURVEY NOTES

FLOOR BEAM REINFORCEMENT CALCULATIONS: ON AXIS B BETWEEN 4 - 5


MAIN BARS: LENGTH OF MAIN BARS = 2.3m
1. LENGTH OF TOP BAR = 2.3 M
LENGTH OF BOTTOM BAR = 2.3

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 2.3 * 2 M = 4.6 M
TOTAL LENGTH OF BOTTOM BARS = 2.3 * 2 M = 4.6 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 4.6 * 0.617 KGS = 2.84 KGS
TOTAL WEIGHT OF BOTTOM BARS = 4.6 * 0.617 KGS = 2.84 KGS

SHAZEB NOMAN 269


QUANTITY SURVEY NOTES

FLOOR BEAM STIRRUP BARS: ACTUAL LENGTH OF FLOOR BEAM = 2.0m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (2.0/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 21 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *21 M
TOTAL LENGTH OF STIRRUP BARS = 23.184 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 23.184 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 9.159 KGS

SHAZEB NOMAN 270


QUANTITY SURVEY NOTES

FLOOR BEAM REINFORCEMENT CALCULATIONS: ON AXIS B BETWEEN 5 - 7


MAIN BARS: LENGTH OF MAIN BAR = 4.85m
1. LENGTH OF TOP BAR = 4.85 M
LENGTH OF BOTTOM BAR = 4.85 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.85 * 2 M = 9.7 M
TOTAL LENGTH OF BOTTOM BARS = 4.85 * 2 M = 9.7 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 9.7 * 0.617 KGS = 5.988 KGS
TOTAL WEIGHT OF BOTTOM BARS = 9.7 * 0.617 KGS = 5.988 KGS

SHAZEB NOMAN 271


QUANTITY SURVEY NOTES

FLOOR BEAM STIRRUP BARS: ACTUAL LENGTH OF FLOOR BEAM = 4.55m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (4.55/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 47 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *47 M
TOTAL LENGTH OF STIRRUP BARS = 51.888 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 51.888 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 20.499 KGS

SHAZEB NOMAN 272


QUANTITY SURVEY NOTES

FLOOR BEAM REINFORCEMENT CALCULATIONS: ON AXIS D BETWEEN 2 - 4


MAIN BARS: LENGTH OF MAIN BARS = 4.75m
1. LENGTH OF TOP BAR = 4.75 M
LENGTH OF BOTTOM BAR = 4.75 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.75 * 2 M = 9.5 M
TOTAL LENGTH OF BOTTOM BARS = 4.75 * 2 M = 9.5 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 9.5 * 0.617 KGS = 5.864 KGS
TOTAL WEIGHT OF BOTTOM BARS = 9.5 * 0.617 KGS = 5.864 KGS

SHAZEB NOMAN 273


QUANTITY SURVEY NOTES

FLOOR BEAM STIRRUP BARS: ACTUAL LENGTH OF FLOOR BEAM = 4.45m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.34) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (4.45/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 46 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *46 M
TOTAL LENGTH OF STIRRUP BARS = 50.784 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 50.784 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 20.063 KGS

SHAZEB NOMAN 274


QUANTITY SURVEY NOTES

FLOOR BEAM REINFORCEMENT CALCULATIONS: ON AXIS D BETWEEN 4 - 5


MAIN BARS: LENGTH OF MAIN BARS = 2.3m
1. LENGTH OF TOP BAR = 2.3 M
LENGTH OF BOTTOM BAR = 2.3

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 2.3 * 2 M = 4.6 M
TOTAL LENGTH OF BOTTOM BARS = 2.3 * 2 M = 4.6 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 4.6 * 0.617 KGS = 2.84 KGS
TOTAL WEIGHT OF BOTTOM BARS = 4.6 * 0.617 KGS = 2.84 KGS

SHAZEB NOMAN 275


QUANTITY SURVEY NOTES

FLOOR BEAM STIRRUP BARS: ACTUAL LENGTH OF FLOOR BEAM = 2.0m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (2.0/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 21 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *21 M
TOTAL LENGTH OF STIRRUP BARS = 23.184 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 23.184 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 9.159 KGS

SHAZEB NOMAN 276


QUANTITY SURVEY NOTES

FLOOR BEAM REINFORCEMENT CALCULATIONS: ON AXIS D BETWEEN 5 - 7


MAIN BARS: LENGTH OF MAIN BAR = 4.85m
1. LENGTH OF TOP BAR = 4.85 M
LENGTH OF BOTTOM BAR = 4.85 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 4.85 * 2 M = 9.7 M
TOTAL LENGTH OF BOTTOM BARS = 4.85 * 2 M = 9.7 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 9.7 * 0.617 KGS = 5.988 KGS
TOTAL WEIGHT OF BOTTOM BARS = 9.7 * 0.617 KGS = 5.988 KGS

SHAZEB NOMAN 277


QUANTITY SURVEY NOTES

FLOOR BEAM STIRRUP BARS: ACTUAL LENGTH OF FLOOR BEAM = 4.55m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (4.55/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 47 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *47 M
TOTAL LENGTH OF STIRRUP BARS = 51.888 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 51.888 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 20.499 KGS

SHAZEB NOMAN 278


QUANTITY SURVEY NOTES

FLOOR BEAM REINFORCEMENT CALCULATIONS: ON AXIS 2 BETWEEN B - D


MAIN BARS: LENGTH OF MAIN BARS = 3.7m

1. LENGTH OF TOP BAR = 3.7 M


LENGTH OF BOTTOM BAR = 3.7 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 3.7 * 2 M = 7.4 M
TOTAL LENGTH OF BOTTOM BARS = 3.7 * 2 M = 7.4 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 7.4 * 0.617 KGS = 4.568 KGS
TOTAL WEIGHT OF BOTTOM BARS = 7.4 * 0.617 KGS = 4.568 KGS

SHAZEB NOMAN 279


QUANTITY SURVEY NOTES

FLOOR BEAM STIRRUP BARS: ACTUAL LENGTH OF FLOOR BEAM = 3.4m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.4/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 35 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *35 M
TOTAL LENGTH OF STIRRUP BARS = 38.64 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 38.64 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 15.265 KGS

SHAZEB NOMAN 280


QUANTITY SURVEY NOTES

FLOOR BEAM REINFORCEMENT CALCULATIONS: ON AXIS 4 BETWEEN B - D


MAIN BARS: LENGTH OF MAIN BARS = 3.7m

1. LENGTH OF TOP BAR = 3.7 M


LENGTH OF BOTTOM BAR = 3.7 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 3.7 * 2 M = 7.4 M
TOTAL LENGTH OF BOTTOM BARS = 3.7 * 2 M = 7.4 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 7.4 * 0.617 KGS = 4.568 KGS
TOTAL WEIGHT OF BOTTOM BARS = 7.4 * 0.617 KGS = 4.568 KGS

SHAZEB NOMAN 281


QUANTITY SURVEY NOTES

FLOOR BEAM STIRRUP BARS: ACTUAL LENGTH OF FLOOR BEAM = 3.4m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.4/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 35 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *35 M
TOTAL LENGTH OF STIRRUP BARS = 38.64 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 38.64 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 15.265 KGS

SHAZEB NOMAN 282


QUANTITY SURVEY NOTES

FLOOR BEAM REINFORCEMENT CALCULATIONS: ON AXIS 5 BETWEEN B - D


MAIN BARS: LENGTH OF MAIN BARS = 3.7m

1. LENGTH OF TOP BAR = 3.7 M


LENGTH OF BOTTOM BAR = 3.7 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 3.7 * 2 M = 7.4 M
TOTAL LENGTH OF BOTTOM BARS = 3.7 * 2 M = 7.4 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 7.4 * 0.617 KGS = 4.568 KGS
TOTAL WEIGHT OF BOTTOM BARS = 7.4 * 0.617 KGS = 4.568 KGS

SHAZEB NOMAN 283


QUANTITY SURVEY NOTES

FLOOR BEAM STIRRUP BARS: ACTUAL LENGTH OF FLOOR BEAM = 3.4m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.4/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 35 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *35 M
TOTAL LENGTH OF STIRRUP BARS = 38.64 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 38.64 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 15.265 KGS

SHAZEB NOMAN 284


QUANTITY SURVEY NOTES

FLOOR BEAM REINFORCEMENT CALCULATIONS: ON AXIS 7 BETWEEN B - D


MAIN BARS: LENGTH OF MAIN BARS = 3.7m

1. LENGTH OF TOP BAR = 3.7 M


LENGTH OF BOTTOM BAR = 3.7 M

2. NUMBER OF TOP BARS = 2


NUMBER OF BOTTOM BARS = 2

3. TOTAL LENGTH OF BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF TOP BARS = 3.7 * 2 M = 7.4 M
TOTAL LENGTH OF BOTTOM BARS = 3.7 * 2 M = 7.4 M

4. DIAMETER OF TOP BAR = 10 MM (GIVEN IN DRAWING)


DIAMETER OF BOTTOM BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF BAR = D2/162 KGS/M


WEIGHT PER METER OF TOP BAR = 10*10/162 KGS/M = 0.617 KGS/M
WEIGHT PER METER OF BOTTOM BAR = 10*10/162 KGS/M = 0.617 KGS/M

6. TOTAL WEIGHT OF BARS = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF TOP BARS = 7.4 * 0.617 KGS = 4.568 KGS
TOTAL WEIGHT OF BOTTOM BARS = 7.4 * 0.617 KGS = 4.568 KGS

SHAZEB NOMAN 285


QUANTITY SURVEY NOTES

FLOOR BEAM STIRRUP BARS: ACTUAL LENGTH OF FLOOR BEAM = 3.4m


1. LENGTH OF STIRRUP BAR = (L + B) * 2 + 9D + 9D M
LENGTH OF STIRRUP BAR = (0.24 + 0.24) * 2 + 9 * 0.008 + 9 * 0.008 M
LENGTH OF STIRRUP BAR = 1.104 M

2. NUMBER OF STIRRUPS BAR = (ACTUAL LENGTH PLINTH BEAM / SPACING) + 1


NUMBER OF STIRRUPS BAR = (3.4/ 0.1) + 1
NUMBER OF STIRRUPS BAR = 35 BARS

3. TOTAL LENGTH OF STIRRUP BARS = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF STIRRUP BARS = 1.104 *35 M
TOTAL LENGTH OF STIRRUP BARS = 38.64 M

4. DIAMETER OF STIRRUP BAR = 8 MM (GIVEN IN DRAWING).

5. WEIGHT PER METER OF STIRRUP BAR = D2/162 KGS/M


WEIGHT PER METER OF STIRRUP BAR = 8*8/162 KGS/M
WEIGHT PER METER OF STIRRUP BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF STIRRUP BARS = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF STIRRUP BARS = 38.64 * 0.395 KGS
TOTAL WEIGHT OF STIRRUP BARS = 15.265 KGS

SHAZEB NOMAN 286


QUANTITY SURVEY NOTES

FLOOR BEAM REINFORCEMENT ABSTRACT:


DIA OF BAR = 10mm,
WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (102)/162 Kg/m = 0.617 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.617 = 7.407 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 10mm = 95.309 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 95.309 / 7.407
= 12.87 BARS APPROXIMATELY EQUAL TO 13 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER INCREASING BARS FROM 12.87 TO 13 NO.S
ACTUAL WEIGHT = 13 X 7.407
= 96.296 Kgs

DIA OF BAR = 8mm,


WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (82)/162 Kg/m = 0.395 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.395 = 4.741 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 8mm = 160.503 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 160.503 / 4.741
= 33.86 BARS APPROXIMATELY EQUAL TO 34 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER INCREASING BARS FROM 33.86 TO 34 NO.S
ACTUAL WEIGHT = 34 X 4.741
= 161.185 Kgs

SHAZEB NOMAN 287


QUANTITY SURVEY NOTES

43. SLAB REINFORCEMENT CALCULATIONS:

SHAZEB NOMAN 288


QUANTITY SURVEY NOTES

COVER = 25 MM, SLAB THICKNESS = 0.15 M, EXTRA BAR DIA = 8mm,

SHAZEB NOMAN 289


QUANTITY SURVEY NOTES

SLAB REINFORCEMENT CALCULATIONS:


X BAR:
1. LENGTH OF X- BAR = L + 0.15 + 0.15 – 0.025 - 0.025 + 0.42D * 6 M
LENGTH OF X- BAR = 11.9 + 0.15 + 0.15 – 0.025 – 0.025 + 0.42 (0.15-0.025-0.025) * 6 M
LENGTH OF X- BAR = 12.4 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (4 – 0.1 – 0.1 / 0.1) +1
= 39 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 12.4 * 39 M
TOTAL LENGTH OF X- BAR = 483.7 M

4. DIAMETER OF X- BAR = 12 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 12*12 /162 KGS/M
WEIGHT PER METER OF X- BAR = 0.889 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 483.7 * 0.889 KGS
TOTAL WEIGHT OF X- BAR = 429.94 KGS

SHAZEB NOMAN 290


QUANTITY SURVEY NOTES

EXTRA BAR:

1. LENGTH OF EXTRA- BAR = L/4= (11.9 + 0.15 + 0.15 – 0.025 - 0.025)/4 M

= 12.15 /4 M = 3.038 M

2. NUMBER OF EXTRA- BAR = NO. OF X-BAR * 2 = 39 * 2 = 78 BARS

3. TOTAL LENGTH OF EXTRA BAR = LENGTH OF BAR * NUMBER OF BARS M


= 3.038 * 78 M = 236.9 M

4. DIAMETER OF EXTRA- BAR = 8 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF EXTRA- BAR = D2/162 KGS/M


WEIGHT PER METER OF EXTRA- BAR = 8*8/162 KGS/M
WEIGHT PER METER OF EXTRA- BAR = 0.395 KGS/M

6. TOTAL WEIGHT OF EXTRA- BAR = TOTAL LENGTH * WEIGHT PER METER KGS
TOTAL WEIGHT OF EXTRA- BAR = 236.9 * 0.395 KGS
TOTAL WEIGHT OF EXTRA- BAR = 93.6 KGS

SHAZEB NOMAN 291


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L + 0.15 + 0.15 – 0.025 - 0.025 M
LENGTH OF Y-BAR = 3.7 + 0.15 + 0.15 – 0.025 – 0.025 M
LENGTH OF Y-BAR = 3.95 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (12.2 – 0.1 – 0.1 / 0.1) +1
= 121 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 3.95 * 121 M
TOTAL LENGTH OF Y-BAR = 478 M

4. DIAMETER OF Y-BAR = 12 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 12 * 12 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.889 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 478 * 0.889 KGS
TOTAL WEIGHT OF Y-BAR = 424.844 KGS

SHAZEB NOMAN 292


QUANTITY SURVEY NOTES

SLAB REINFORCEMENT ABSTRACT:


DIA OF BAR = 12mm,
WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (122)/162 Kg/m = 0.889 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.889 = 10.667 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 12mm = 854.78 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 854.78 / 10.667
= 80.14 BARS APPROXIMATELY EQUAL TO 81 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER INCREASING BARS FROM 80.14 TO 81 NO.S
ACTUAL WEIGHT = 81 X 10.667
= 864.00 Kgs

DIA OF BAR = 8mm,


WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (82)/162 Kg/m = 0.395 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.395 = 4.741 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 8mm = 93.6 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 93.6 / 4.741
= 19.74 BARS APPROXIMATELY EQUAL TO 20 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER INCREASING BARS FROM 19.74 TO 20 NO.S
ACTUAL WEIGHT = 20 X 4.741
= 94.815 Kgs

SHAZEB NOMAN 293


QUANTITY SURVEY NOTES

44. STAIRCASE REINFORCEMENT CALCULATIONS:

COVER = 50 MM, SLAB THICKNESS = 0.15 M

SHAZEB NOMAN 294


QUANTITY SURVEY NOTES

WAIST SLAB - 1 REINFORCEMENT CALCULATIONS:

SHAZEB NOMAN 295


QUANTITY SURVEY NOTES

WAIST SLAB - 1 REINFORCEMENT CALCULATIONS:


X BAR:
1. LENGTH OF X- BAR = L + 1 + 0.01 + 9D M
LENGTH OF X- BAR = 4.082 + 1 + 0.01 + 9 * 0.01 M
LENGTH OF X- BAR = 5.182 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (1 – 0.05 – 0.05 / 0.1) +1
= 10 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 5.182 * 10 M
TOTAL LENGTH OF X- BAR = 51.82 M

4. DIAMETER OF X- BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 10*10 /162 KGS/M
WEIGHT PER METER OF X- BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 51.82 * 0.617 KGS
TOTAL WEIGHT OF X- BAR = 31.988 KGS

SHAZEB NOMAN 296


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L + 50D + 50D M
LENGTH OF Y-BAR = 1 + 50 * 0.01 + 50 * 0.01 M
LENGTH OF Y-BAR = 2 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (4.082 – 0.05 – 0.05 / 0.1) +1
= 40.82 = 40 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 2 * 40 M
TOTAL LENGTH OF Y-BAR = 80 M

4. DIAMETER OF Y-BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 10 * 10 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 80 * 0.617 KGS
TOTAL WEIGHT OF Y-BAR = 49.383 KGS

SHAZEB NOMAN 297


QUANTITY SURVEY NOTES

WAIST SLAB - 2 REINFORCEMENT CALCULATIONS:

SHAZEB NOMAN 298


QUANTITY SURVEY NOTES

WAIST SLAB - 2 REINFORCEMENT CALCULATIONS:


X BAR:
1. LENGTH OF X- BAR = L + 1 - 0.05 M
LENGTH OF X- BAR = 2.33 + 1 - 0.05 M
LENGTH OF X- BAR = 3.28 M

2. NUMBER OF X- BAR = (OPP LENGTH / SPACING) + 1


= (1 – 0.05 – 0.05 / 0.1) +1
= 10 BARS

3. TOTAL LENGTH OF X- BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF X- BAR = 3.28 * 10 M
TOTAL LENGTH OF X- BAR = 32.8 M

4. DIAMETER OF X- BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 10*10 /162 KGS/M
WEIGHT PER METER OF X- BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF X- BAR = 32.8 * 0.617 KGS
TOTAL WEIGHT OF X- BAR = 20.247 KGS

SHAZEB NOMAN 299


QUANTITY SURVEY NOTES

Y-BAR BARS:
1. LENGTH OF Y-BAR = L + 50D + 50D M
LENGTH OF Y-BAR = 1 + 50 * 0.01 + 50 * 0.01 M
LENGTH OF Y-BAR = 2 M

2. NUMBER OF Y-BAR = (OPP LENGTH / SPACING) + 1


= (2.33 – 0.05 – 0.05 / 0.1) +1
= 23.3 = 23 BARS

3. TOTAL LENGTH OF Y-BAR = LENGTH OF BAR * NUMBER OF BARS M


TOTAL LENGTH OF Y-BAR = 2 * 23 M
TOTAL LENGTH OF Y-BAR = 46 M

4. DIAMETER OF Y-BAR = 10 MM (GIVEN IN DRAWING)

5. WEIGHT PER METER OF Y-BAR = D2/162 KGS/M


WEIGHT PER METER OF Y-BAR = 10 * 10 /162 KGS/M
WEIGHT PER METER OF Y-BAR = 0.617 KGS/M

6. TOTAL WEIGHT OF Y-BAR = TOTAL LENGTH * WEIGHT PER METER KGS


TOTAL WEIGHT OF Y-BAR = 46 * 0.617 KGS
TOTAL WEIGHT OF Y-BAR = 28.395 KGS

SHAZEB NOMAN 300


QUANTITY SURVEY NOTES

L SHAPE BAR IN STEPS REINFORCEMENT CALCULATIONS:

SHAZEB NOMAN 301


QUANTITY SURVEY NOTES

L SHAPE BAR IN STEPS REINFORCEMENT CALCULATIONS:

1. TOTAL LENGTH OF X- BAR = (0.2 + 0.4 + 9D + 9D) * 2 + 1 M


TOTAL LENGTH OF X- BAR = (0.2 + 0.4 + 9 * 0.008 + 9 * 0.008) * 2 + 1 M
TOTAL LENGTH OF X- BAR = 2.488 M

2. DIAMETER OF X- BAR = 8 MM (GIVEN IN DRAWING)

3. WEIGHT PER METER OF X- BAR = D2/162 KGS/M


WEIGHT PER METER OF X- BAR = 8*8 /162 KGS/M
WEIGHT PER METER OF X- BAR = 0.395 KGS/M

4. TOTAL WEIGHT OF X- BAR = TOTAL LENGTH * WEIGHT PER METER * NO. OF STEPS KGS
TOTAL WEIGHT OF X- BAR = 2.488 * 0.395 * 20 KGS
TOTAL WEIGHT OF X- BAR = 19.655 KGS

SHAZEB NOMAN 302


QUANTITY SURVEY NOTES

STAIRCASE REINFORCEMENT ABSTRACT:


DIA OF BAR = 10mm,
WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (102)/162 Kg/m = 0.617 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.617 = 7.407 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 10mm = 60.383 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 60.383 / 7.407
= 8.15 BARS APPROXIMATELY EQUAL TO 8 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER DECREASING BARS FROM 8.15 TO 8 NO.S
ACTUAL WEIGHT = 8 X 7.407
= 59.259 Kgs

DIA OF BAR = 8mm,


WEIGHT OF STEEL BAR IN Kg/m = D2/162 Kg/m
WEIGHT OF STEEL BAR IN Kg/m = (82)/162 Kg/m = 0.395 Kg/m
LENGTH OF EACH BAR = 12.0 m
WEIGHT OF STEEL IN Kgs/Bar = 12.0 X 0.395 = 4.741 Kgs/Bar
STEEL WEIGHT REQUIRED FOR 8mm = 19.655 Kgs
NO. OF Bars OF 12.0m LENGTH EACH REQUIRED = TOTAL WEIGHT OF STEEL REQUIRED /
WEIGHT OF EACH STEEL BAR OF 12.0m LENGTH
NO. OF BARS REQUIRED = 19.655 / 4.741
= 4.15 BARS APPROXIMATELY EQUAL TO 4 BARS
ACTUAL WEIGHT OF STEEL REQUIRED AFTER DECREASING BARS FROM 4.15 TO 4 NO.S
ACTUAL WEIGHT = 4 X 4.741
= 18.963 Kgs

SHAZEB NOMAN 303


QUANTITY SURVEY NOTES

45. SUPER – STRUCTURE REINFORCEMENT ABSTRACT: IN EXCEL

46. SUPER – STRUCTURE REINFORCEMENT BILL OF QUANTITY: IN EXCEL.

47.BILL OF QUANTITY OF SAMPLE QUANTITY SURVEY PROJECT: IN EXCEL

SHAZEB NOMAN 304

You might also like