Professional Documents
Culture Documents
Learning objectives
i. Difference between direct and indirect costs
ii. Absorption costing
iii. Comparison of traditional absorption costing and activity-based costing
iv. Description of Activity Based costing system
v. Process of implementing ABC
vi. Computation of product cost under:
• Traditional absorption costing
• Activity based costing
vii. Merits and demerits of activity-based costing
ABDUL AZEEM 1
1) Direct cost vs indirect costs
Direct costs are specific to product costs but indirect costs are common expenses of business
and needs to be allocated among the products manufactured by the entity.
2) Absorption Costing
Absorption Costing is a system to distribute common overheads cost among various products of
business. Absorption costing has two main types:
i. Traditional absorption costing
a) Single rate system
b) Departmental rate system
ii. Activity based costing
ABDUL AZEEM 2
4) Description of ABC System
ABC is an improved version of traditional absorption costing in which each type of
overhead cost is distributed using different bases.
5) Process of ABC System
ABC system can be implemented through the following steps:
a. Identify the organisation’s major activities.
b. Collect the total costs associated with each activity.
c. Identify the cost drivers and estimate their quantity
d. Calculate activity-based absorption rate or cost driver rate
Activity based rate (Cost Driver rate) = Total cost of activity
Total quantity of driver
e. Absorb the overheads cost to products on the basis of cost driver
Factory overheads cost = Activity based rate x product wise driver quantity
5.1) Cost pool and cost driver
• A cost pool is simply the total expenditure charged to each activity.
• A cost driver is a factor that determines the cost of the activity. It is something that
will cause the costs for an activity to increase as more of the activity is performed.
5.2) Examples of Cost driver
Sr. No. Activity Cost pool Possible Cost Driver
1. Material procurement/ No. of purchase orders
Purchase ordering cost
2. Customer order Time to process order (or)
processing/Order handling No. of customer orders handled
3. Packing Packing hours (or)
No. of customer orders
ABDUL AZEEM 3
4. Material handling and Number of requisitions (or)
management No. of production run
5. Machine set up/ No of batches/
Production setup No. of production runs/
No. of production setups
6. Production scheduling No. of production runs
7. Quality control and inspection Inspection hours for inspected units
(or)
No. of inspections/ No. of Tests
8. Repair and maintenance Maintenance hours/
Machine hours operated
9. Delivery and dispatch No. of deliveries made (or)
No. of orders delivered
10. Engineering cost Engineering hours/
Machine hours
11. Machine running Machine Hours
cost/Machining cost
12. Warehousing cost Number of material requisitions/
Direct material usage
13. Production control Machine hours
6) Product cost under traditional absorption costing system & ABC system
Product cost has three elements:
i. Direct material cost
ii. Direct labour cost
iii. Factory overheads cost
Under traditional absorption costing, allocation of overheads cost will be made to various
products by using either:
i. Single overheads absorption rate, or
ii. Departmental overheads absorption rate
Under activity-based costing, allocation of overheads cost will be made to various products
by using cost driver rate.
ABDUL AZEEM 4
(W1) - Single overheads absorption rate = Total budgeted overheads cost
Total activity level
6.2) Product cost per unit under departmental rate system
Product Product Product
A B C
Direct material cost per unit x x x
Add: Direct labour cost per unit x x x
Add: Factory overheads cost per unit (W2)
Department 1 FOH cost x x x
Department 2 FOH cost x x x
= Product cost per unit x x x
6.3) Product cost per unit under activity- based rate system
Product Product Product
A B C
Direct material cost per unit x x x
Add: Direct labour cost per unit x x x
Add: Factory overheads cost per unit (W3) x x x
ABDUL AZEEM 5
N1) Activity based rate (Cost Driver rate) = Total cost of activity
Total quantity of driver
N2) Factory overheads cost of each product = Activity based rate x product wise
Example 1
A company manufactures two products, C and D, for which the following information is
available:
Product C Product D Total
Budgeted production (units) 1,000 4,000 5,000
Labour hours per unit/in total 8 10 48,000
Number of production runs required 13 15 28
Number of inspections during production 5 3 8
Solution
Overheads cost per unit of each product
Cost pools Cost Driver Overhead cost
Rate Product C Product D
(Rs.) (Rs.)
Set up cost Rs. 140,000/ 28 production run
= Rs. 5,000 per run 65,000 75,000
Inspection cost Rs. 80,000 / 8 inspections
= Rs. 10,000 per inspection 50,000 30,000
Other overheads Rs. 96,000 / 48,000 labour hours
= Rs. 2 per hour 16,000 80,000
= Factory overheads cost of each product 131,000 185,000
÷ Production units ÷ 1,000 ÷ 4,000
= Factory overheads cost per unit of each product Rs. 131 Rs. 46.25
Example 2
A company manufactures two products, A and B. Monthly data relating to production and
sales are as follows.
Product A Product B
Direct material cost per unit $30 $ 40
Direct labour cost per unit @ $ 40 per hour $40 $ 80
Production and Sales 200 units 1,900 units
ABDUL AZEEM 6
Production overheads are $ 400,000 each month and are currently absorbed on a direct labour
hour basis. The management of company wants to switch to activity-based costing system.
The management accountant has gathered the following monthly information:
Required: Calculate the cost per unit for product A and product B, by using:
a) Traditional absorption costing
b) Activity based costing
Solution
a) Cost per unit under traditional absorption costing
Product A Product B
$ $
Direct Material cost per unit 30 40
Direct Labour cost per unit 40 80
70 120
Factory overheads cost per unit (W1)
(Rs. 100 per hour x labour hours per unit) 100 200
= Product cost per unit 170 320
ABDUL AZEEM 7
Material management cost per unit 300 31.58
= Product cost per unit 550 280
ABDUL AZEEM 8
EXAM STANDARD PRACTICE QUESTIONS
ABDUL AZEEM 9
Question 2 ACCA F5 – December 2010
ABDUL AZEEM 10
Question 4 ICAP Study Text – Example 2
Rajput Enterprises manufactures two products, J and K, using the same equipment and similar
processes. An extract of the production data for these products for the month of June is shown
below:
Product J Product K
Quantity produced in units 5,000 7,000
Direct labour hours per unit 1 2
Machine hours per unit 3 1
Set-ups in the period 10 40
Orders handled in period 15 60
Oveheads cost for the month of June are given below:
Rs.
Machine related costs 220,000
Production run set-ups cost 20,000
Order handling cost 45,000
Total 285,000
Required: Calculate overheads cost per unit for each product by using activity-based costing
ABDUL AZEEM 11
Overhead costs are given as under:
Rs.
Short run variable cost 30,800
Set up costs 109,200
Expediting and scheduling costs 91,000
Material handling cost 77,000
Total 308,000
Labour cost per hour is equal to Rs. 5.
Required: Calculate unit cost for each product using Activity based costing.
ABDUL AZEEM 12
SOLUTIONS
Q 1 - Solution
ABDUL AZEEM 13
Q 2 - Solution
ABDUL AZEEM 14
Q 3 - Solution
Overheads cost per unit for Product RI-11 using activity-based costing
Activity Cost Activity based Overheads absorbed per unit
pool OAR Product RI - 11
(Rs.)
Purchasing cost Rs. 750,000/15,000 Rs. 50 x 25 orders
= Rs. 50 per purchase order = Rs. 1,250
Setting cost Rs. 1,120,000/28,000 Rs. 40 x 150 batches
= Rs. 40 per batch = Rs. 6,000
Material Rs. 960,000/80,000 Rs. 12 x 6 material requisition per batch x 150
handling cost = 12 per material requisition batches
= Rs. 10,800
Inspection cost Rs. 700,000/28,000 Rs. 25 x 1 inspection per batch x 150 batches
= Rs. 25 per inspection = Rs. 3,750
Machining cost Rs. 1500,000/500,000 Rs. 3 x 0.1 machine hour per unit x 15,000 units
= Rs. 3 per machine hour = Rs. 4,500
Total overheads cost = Rs. 26,300
Overheads cost per unit for product RI-11= Rs. 26,300 ÷ 15,000 units = Rs. 1.75 per unit
(W1) Number of batches produced = 15,000 units ÷ 100 units = 150 batches
Question 4 - Solution
Overheads cost per unit by using activity-based costing
Activity Cost Activity based OAR Overheads absorbed per unit
pool Product J Product K
(Rs.) (Rs.)
Machine related Rs. 220,000/22,000 Rs. 10 x 15,000 MH Rs. 10 x 7,000 MH
costs = Rs. 10 per machine hour = Rs. 150,000 =Rs. 70,000
Production run Rs. 20,000/50 Rs. 400 x 10 setups Rs. 400 x 40 setups
set-ups cost = Rs. 400 per setup = Rs. 4,000 = Rs. 16,000
ABDUL AZEEM 15
Order handling Rs. 45,000/75 Rs. 600 x 15 orders Rs. 600 x 60 orders
cost = Rs. 600 per order = Rs. 9,000 = Rs. 36,000
Total overheads cost 163,000 122,000
÷ Production units 5,000 7,000
Overheads cost per unit (Rs.) 32.60 17.43
Question 5 - Solution
Overheads cost per unit by using activity-based costing
Activity Cost Activity based OAR Overheads absorbed per unit
pool Sky Moon Sun
(Rs.) (Rs.) (Rs.)
Machining Rs. 36,000/22,500 Rs. 1.60 x 5,000 MH Rs. 1.60 x 7,500 MH Rs. 1.60 x 10,000 MH
costs = Rs. 1.60 per = Rs. 8,000 =Rs. 12,000 = Rs. 16,000
machine hour
Component Rs. 100,000/40 Rs. 2,500 x 8 Rs. 2,500 x 12 Rs. 2,500 x 20
cost = Rs. 2,500 per components components components
component = Rs. 20,000 = Rs. 30,000 = Rs. 50,000
Set-up cost Rs. 180,000/30 Rs. 6,000 x 3 setups Rs. 6,000 x 1 setup Rs. 6,000 x 26 setups
= Rs. 6,000 per setup = Rs. 18,000 = Rs. 6,000 = Rs. 120,000
Packing cost Rs. 150,000/50 Rs. 3,000 x 21 orders Rs. 3,000 x 4 orders Rs. 3,000 x 25 orders
= Rs. 3,000 per order = Rs. 63,000 = Rs. 12,000 = Rs. 75,000
Total overheads cost 115,000 90,000 261,000
÷ Production units 500,000 150,000 250,000
Overheads cost per unit (Rs.) 0.23 0.60 1.044
Question 6 - Solution
Cost per unit of each product by using activity-based costing
A B C D
(Rs.) (Rs.) (Rs.) (Rs.)
Direct material cost per unit 200 800 200 800
Add: Direct labour cost per unit 50 150 50 150
Add: Overheads cost per unit 4,030 4,170 1,060 1,200
= Cost per unit 4,280 5,120 1,310 2,150
(W1) Overheads cost per unit by using activity-based costing
Activity Cost Activity based OAR Overheads absorbed per unit
pool A B C D
(Rs.) (Rs.) (Rs.) (Rs.)
Short run variable Rs. 30,800/4,400 700 2,100 7,000 21,000
cost = Rs. 7 per machine hour
Set up costs Rs. 1009,200/14 15,600 15,600 39,000 39,000
= Rs. 7,800 per production run
Expediting and Rs. 91,000/14 13,000 13,000 32,500 32,500
scheduling costs = Rs. 6,500 per production run
Material handling Rs. 77,000/14 11,000 11,000 27,500 27,500
cost = Rs. 5,500 per production run
Total overheads cost 40,300 41,700 106,000 120,000
÷ Production units 10 10 100 100
Overheads cost per unit (Rs.) 4,030 4,170 1,060 1,200
ABDUL AZEEM 16